transit “new starts” background and status transit task force montgomery county

40
Transit “New Starts” Background and Status Transit Task Force Montgomery County March 2011

Upload: cicero

Post on 19-Jan-2016

44 views

Category:

Documents


0 download

DESCRIPTION

Transit “New Starts” Background and Status Transit Task Force Montgomery County. March 2011. What is “New Starts”?. Federal program to fund new transit projects FTA requires project sponsors to follow a rigorous evaluation process that results in an overall project rating Primarily focused on - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Transit “New Starts”Background and Status

Transit Task ForceMontgomery County

March 2011

Page 2: Transit “New Starts” Background and Status Transit Task Force Montgomery County

What is “New Starts”?

• Federal program to fund new transit projects• FTA requires project sponsors to follow a rigorous

evaluation process that results in an overall project rating

• Primarily focused on– Project benefits– Project readiness– Ability of the project sponsor to carry out the project

• Typically matched at <50%• Funding decisions made by Congress – national

competition

2

Page 3: Transit “New Starts” Background and Status Transit Task Force Montgomery County

New Start Development Process

Final Design

Construction

Preliminary Engineering/Final EIS

Locally Preferred Alternative

Entry into PE

Entry into Final Design

Full Funding Grant Agreement

FTA Decision Point

Major Development Stage

Systems Planning

Alternatives Analysis/Draft EIS

Pro

ject

Ma

na

ge

me

nt

Ove

rsig

ht

3

Page 4: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Financial Plan

• Required by FTA

• Provides framework for project funding appropriate for phase of the project

• Draft plan addresses funding for preliminary engineering and final design

• Revised plan will be submitted with entry into final design and must include construction funding approach

4

Page 5: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Proposed Cost Share

• Federal Share – 50%

• State Share – 50%– Transportation Trust Fund

• Local government coordination to take costs out of projects, e.g., – Georgetown Branch right of way and trail

construction– Bethesda south station entrance

5

Page 6: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Financial Plan Assumptions

• Conclusion: projects are affordable• Major assumptions

– MDOT’s current revenue forecast is accurate, including a revenue increase prior to funds being programmed for construction

– MTA expansion projects before 2020 are Purple Line, CCT, Red Line, and replacement MARC vehicles

– System preservation continues at current levels– Future projects are prioritized and funding is programmed

accordingly– MTA to receive approximately 50% of MDOT’s total capital

budget during the 2015 to 2019 timeframe– FTA funds 50% of the capital cost, with unprecedented

annual commitments

6

Page 7: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Preliminary Engineering

• What is included in PE?– Project definition, cost, and schedule– Financial Plan– Completion of NEPA process (FEIS)– Project Management Plan for Final Design and

Construction• PE evaluations include:

– Three Alternatives:• Build, No Build, and Baseline

– Phasing and staging of alternatives– Land use and policy alternatives– Implementation strategies– Financial Plan alternatives

7

Page 8: Transit “New Starts” Background and Status Transit Task Force Montgomery County

New Starts Package

8

Page 9: Transit “New Starts” Background and Status Transit Task Force Montgomery County

9

Page 10: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Project Overview

• 16-mile east-west rapid transit line

• Bethesda to New Carrollton

• Parallel to and inside the Capital Beltway

• Will operate mostly at street level

10

Page 11: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Project Goals• Faster and more reliable transit for east-west travel market• Improve access to and connectivity to Metrorail, MARC,

Amtrak, and bus services • Serve transit-dependent populations• Support local, regional and state policies and adopted Master

Plans• Strengthen and revitalize communities in the corridor• Increase potential for Transit Oriented Development at

existing and proposed stations in the corridor• Improve access to existing activity centers including and

planned commercial, office, and residential development in Bethesda, Silver Spring, Takoma/Langley, University of Maryland/College Park, and New Carrollton

11

Page 12: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Transit System Access

Bethesda

Silver S

pring

College P

ark

New Carro

llton

12

Page 13: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Locally Preferred Alternative

13

Page 14: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Locally Preferred Alternative

• Light rail: mostly in dedicated or exclusive lanes

• End to end travel time is 55 minutes• Daily ridership in 2030: 60,000

– Cars off the road: 20,000 daily

• Greatest ridership is between Bethesda and Silver Spring

• 30% will use Metro for part of their trip• Capital cost: $1.563 billion (2010 dollars)

14

Page 15: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Bethesda

• Red Line connection via direct elevator up to street and down to Metrorail

15

Page 16: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Trail at Bethesda• Trail access above transitway

16

Page 17: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Georgetown Branch Trail• Through Chevy Chase, trail next to

transitway with vertical separation and landscaped buffer

17

Page 18: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Silver Spring• Transitway on south side of CSX; trail crosses to north

side east of Talbot Street bridge• Station at SSTC one level above Metro and MARC trains

18

Page 19: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Silver Spring Library• At-grade on Bonifant Street; station integrated into the

new Silver Spring Library

19

Page 20: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Locally Preferred Alternative

• Wayne Avenue: at-grade; shared lanes with new left turns

• Short tunnel between Wayne and Arliss

• Piney Branch: median operation

20

Page 21: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: Takoma-Langley Park Transit Center• Median operation on University Boulevard

with station at New Hampshire Avenue adjacent to new regional bus hub

21

Page 22: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Design Concept: UM Campus

• At-grade along Campus Drive with open pedestrian plazas

22

Page 23: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Locally Preferred Alternative

• Paint Branch Parkway: shared lanes under CSX/Metro• Integrated into the new development at the College

Park Metrorail Station• River Road: dedicated lanes on south side• Kenilworth Avenue: elevated aerial structure, crossing

over the MD 410 intersection• Aerial station in Riverdale Park• MD 410: returns to grade, dedicated right of way on

south side• Veterans Parkway: dedicated right of way on south

side • South side of Ellin Road into New Carrollton Station

23

Page 24: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Public Involvement

• Open houses• Community Focus Groups• Small Group Workshops• Community and civic association meetings• Community outreach events

– Libraries, grocery stores, shopping centers

• www.purplelinemd.com• Newsletters

24

Page 25: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Upcoming Coordination

• Resource agencies• CSX and utilities• Review of development proposals• Montgomery County (Bethesda Station,

Capital Crescent Trail, Takoma/Langley Sector Plan, Takoma/Langley Transit Center)

• Prince George’s County (MD 410, East Campus, River Road, Takoma/Langley Sector Plan)

25

Page 26: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Schedule

• Request Permission to Enter Summer 2011 Preliminary Engineering

• PE and Final Environmental Summer 2013 Impact Statement Completed

• Begin Final Design Summer 2013

• Begin Construction Summer 2015

• Open to Revenue Service 202026

Page 27: Transit “New Starts” Background and Status Transit Task Force Montgomery County

27

Page 28: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Project Overview

• Part of the I-270/US 15 Multi-Modal Corridor Study• Planning studies ongoing since 1990s• Completed Environmental Documents and held Public

Hearings– 2002 Draft Environmental Impact Statement– 2009 Alternatives Analysis/Environmental Assessment– 2010 Supplemental Environmental Analysis (SEA)

• Highway Improvements - 30 miles• Transit Improvements - 13-15 miles• Light Rail Transit (LRT) or Bus Rapid Transit (BRT)

28

Page 29: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Alternatives Evaluation

• Alternative 1: No-Build • Alternative 2: TSM • Alternatives 3A/B, 4A/B, 5A/B/C, 6A/B and 7A/B

– Various highway lanes configurations, including general purpose lanes and managed lanes (HOV or ETL)

– Transit options• “A” – light rail transit on original Master Plan alignment• “B” – bus rapid transit on Original Master Plan alignment• “C” – premium bus service on managed lanes

• Additional Transit Alternatives were evaluated as part of the 2010 SEA– Crown Farm– Life Sciences Center– Kentlands

29

Page 30: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Key Features

• 15 stations+3 as needed for development

• Exclusive running way

• End to end travel time is 44-48 minutes

• Transit transfers to MARC (Metro. Grove) and Red Line (Shady Grove)

• Access from local streets, I-270 interchanges, and direct access ramps

30

Page 31: Transit “New Starts” Background and Status Transit Task Force Montgomery County

One Transitway; Two Options

LIGHT RAIL TRANSITLIGHT RAIL TRANSIT

BUS RAPID TRANSITBUS RAPID TRANSIT

31

Page 32: Transit “New Starts” Background and Status Transit Task Force Montgomery County

• Leaving Shady Grove station, cross MD 355 at or below

grade

• Median of King Farm Boulevard

• Over I-270/Shady Grove Rd. interchange

• Under intersection of Key West Avenue and Decoverly Dr

• Right onto Medical Center Drive; cross Great Seneca

Highway at-grade

• Under Key West Ave again, cross Belward Farm to

Muddy Branch Rd

• Muddy Branch: median or south side

• Great Seneca: west side to Kentlands; over to south side

of Quince Orchard Rd

• Cross over Quince Orchard and Clopper Rd; under CSX

tracks

32

Page 33: Transit “New Starts” Background and Status Transit Task Force Montgomery County

• Adjacent to I-270 through Seneca Creek State Park to Middlebrook Rd

• Under Germantown Rd to proposed transit center

• Century Boulevard: median to under Father Hurley Boulevard to proposed extension of Dorsey Mill Road across I-270

• Observation Drive: median of existing and proposed extension to COMSAT

33

Page 34: Transit “New Starts” Background and Status Transit Task Force Montgomery County

2010 Alignment Study Results

• Changes beneficial to project

40%

15%14%

42%Ridership

Cost

BRTLRT

34

Page 35: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Cost & Ridership

35

Page 36: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Right-of-Way Status

• Approximately 35% lies within publicly controlled land

• Additional 25% has right-of-way protection through reservation or easement

• Remaining 40% has no protections at this time

36

Page 37: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Next Step –Transit Only

• Full proposed highway improvements by 2030 not feasible

• Highway and transit on separate schedules– Highway: Additional studies, Tiered FEIS

approach, break-out projects

– Transit: Select Locally Preferred Alternative (LPA); proceed with FTA New Starts process

• Close coordination between highway and transit studies to continue

37

Page 38: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Locally Preferred Alternative

• Mode Selection – Bus Rapid Transit or Light Rail Transit

• Alternative alignments and environmental impacts• Public Hearing review – evaluate concerns:

– Citizen/community groups– Montgomery County Government– FTA/FHWA– Environmental agencies

• Funding/Affordability• Phasing options

38

Page 39: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Public Outreach

• Ongoing meetings with area community associations, business groups, and local officials

• Enhanced coordination with the City of Rockville and King Farm residents

• www.mta.maryland.gov/cct

• Newsletters

39

Page 40: Transit “New Starts” Background and Status Transit Task Force Montgomery County

Schedule

• Select Preferred Alternative Spring 2011• Request Permission to Enter Fall 2011

Preliminary Engineering

• PE and Final Environmental Fall 2013 Impact Statement Completed

• Begin Final Design Winter 2013/14

• Begin Construction 2014/15

40