Second Public PresentationMay 31, 2017

TREMONT NAIL FACTORY

Page 2: TREMONT NAIL FACTORY - Cloudinary

Agenda

• Project Team• Project Process• Recap of First Presentation• Feasibility Analysis• Preliminary Concepts• Proposed Vision Plan• Discussion

Page 3: TREMONT NAIL FACTORY - Cloudinary

Project Team

Page 4: TREMONT NAIL FACTORY - Cloudinary

Project Team

Town of Wareham Kenneth Buckland, AICP, Director of Planning &Community Development

Derek Sullivan, Town AdministratorPeter W. Teitelbaum, Esq., Chair, Wareham Board of

Selectmen

MassDevelopment Edward Starzec, Director, Land Entitlements &Master Planning

Laura Barrett, Project Manager, Real Estate

Union Studio Jeremy R. Lake, AIA, Senior AssociateJoel VanderWeele, Architectural Designer

Peregrine Group Eric J. Busch, Principal

Horsley Witten Joseph E. Longo, Principal, Senior Engineer

Page 5: TREMONT NAIL FACTORY - Cloudinary
Page 6: TREMONT NAIL FACTORY - Cloudinary

Project Process

Page 7: TREMONT NAIL FACTORY - Cloudinary

Project ProcessPre-Design December 2016 -

Visit Site and Review Overall Objectives, Opportunities and January 2017Constraints with Project Team

Stakeholder InputMeet w/ Local Business Owners, Board Members and Town Officials February 2017Online comments and questions on coUrbanize website Ongoing

First Public Presentation March 9, 2017

Feasibility Analysis/Preliminary Concepts March/April 2017Study a range of options based on stakeholder and public input,

review market, regulatory and physical feasibility

Draft Vision Plan/Recommendations April/May 2017Generate vision plan for the site based on preferred concept

including steps towards implementation

Second Public Presentation May 31, 2017

Final Vision Plan/Recommendations Report TBD

Page 8: TREMONT NAIL FACTORY - Cloudinary

Recap of First Presentation

Page 9: TREMONT NAIL FACTORY - Cloudinary

Project Location

Project Site

Page 10: TREMONT NAIL FACTORY - Cloudinary

Project Site

Besse Park

Center Park

Project Location

Page 11: TREMONT NAIL FACTORY - Cloudinary

Project Location

DayCare

ProposedCranberry Museum

HistoricalSociety

Buildings

WCTV(Old Town

Hall)

Churches

Church

FearingTavern

ProposedSenior

Housing

Page 12: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Page 13: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Page 14: TREMONT NAIL FACTORY - Cloudinary
Page 15: TREMONT NAIL FACTORY - Cloudinary
Page 16: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Page 17: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Wetlands

Page 18: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Wetlands

Page 19: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Wetlands

New ConstructionNot Allowed,Renovation

Possible

New ConstructionAllowed if Raised Above Flood Plain

New ConstructionAllowed at

Current Elevation

Page 20: TREMONT NAIL FACTORY - Cloudinary
Page 21: TREMONT NAIL FACTORY - Cloudinary

Existing Conditions

Wetlands

New ConstructionNot Allowed,Renovation

Possible

New ConstructionAllowed if Raised Above Flood Plain

New ConstructionAllowed at

Current Elevation

Page 22: TREMONT NAIL FACTORY - Cloudinary

Preliminary Thoughts

Open Space

Connection toMerchant’s Way

KayakLaunch

PicnicArea

Parking/Access

New Construction (Residential?)

Factory Building:Main Space – Preserved, Event Space/

Music VenueElls – Education/Museum or Retail Use

Pickling Building:Retail or Gallery Space

Packaging Building:Retail or Gallery Space

Freight Building:Main Space – Preserved, Event SpaceNorth Ell – Retail Use

Freight Shed:Storage

Office Building:Education/Museum, Retail,

Office or Residential Use

Restroom Building:Restrooms for Events

Page 23: TREMONT NAIL FACTORY - Cloudinary

Stakeholder Input – Round TwoSuggestions made at First Public Presentation:• Generally supportive of ideas proposed (preservation, mixed use, etc.)• Support for museum idea, could have more regional focus (Iron Trail of SE Mass)• Preserve blacksmith and tool shops – possible demonstrations, relation with Tremont Nail Co.• Utilize Metal Building for affordable artist studios, or larger events in inclement weather• Kayak Launch should include a dock, when tide is low current launch is inaccessible• Need to repair Dam• Relation to Merchant’s Way – distinct approach here so as to compliment, not compete

Suggestions made via coUrbanize website: (87 comments and counting!)• Generally supportive of ideas proposed• Include a mix of uses accessible to all residents of Wareham:

• Waterfront restaurant(s)• Microbrewery• Museum(s) – factory, region, children• Artist/Maker/Shared Office spaces• Exhibit Space

• Be sure to preserve the historic character of the site• Launch point for boat tours about history of river• Take advantage of rail access, trolley to downtown• Need to repair Dam• Need to remediate contamination• Consider relocating the Metal Building

• Farmers’ Markets / Arts & Crafts Shows• Paddlesports/Fishing Rentals• Recreation Center• Indoor Dog Park• Community Gardens/Farming

Page 24: TREMONT NAIL FACTORY - Cloudinary

Feasibility Analysis

Page 25: TREMONT NAIL FACTORY - Cloudinary

Regulatory Issues

Redevelopment is possible, but there is a process, and it will take time…

• Site includes Wetlands, Riverfront Area, and Salt Marshes – required buffers, limits and review• Due to existing conditions/disturbance, there is some flexibility/exemptions possible• Both state and local requirements/review needed

• Portions of site are within FEMA flood zone – limits, flood insurance and management issues• Redevelopment of existing structures in flood zone limited to 50% of appraised value –

will likely require incremental improvements (and patience) over a stretch of time• Potential new development area is above/close to being above flood zone

• Site is not listed as a Rare Species Habitat

• Site has access to Utilities like public water and sewer, as well as electric and gas

• Redevelopment will utilize best practices for mitigation, tuned to this site, as it relates to Erosion and Sediment Control during site redevelopment…

… and integrated, low-impact Stormwater Management as part of the final design

Page 26: TREMONT NAIL FACTORY - Cloudinary

Market Feasibility

• Market feasibility - a real estate development perspective (“finance-ability”)

• Macro/regional – activity in the Cape, Plymouth County and the Southcoast

• Local data – existing studies, survey of available properties and developer input

• Stakeholder input – wants and needs

• Practical, balanced approach - goal is implementable framework to establish vision

Page 27: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

Page 28: TREMONT NAIL FACTORY - Cloudinary

Preliminary Thoughts

Open Space

Connection toMerchant’s Way

KayakLaunch

PicnicArea

Parking/Access

New Construction (Residential?)

Factory Building:Main Space – Preserved, Event Space/

Music VenueElls – Education/Museum or Retail Use

Pickling Building:Retail or Gallery Space

Packaging Building:Retail or Gallery Space

Freight Building:Main Space – Preserved, Event SpaceNorth Ell – Retail Use

Freight Shed:Storage

Office Building:Education/Museum, Retail,

Office or Residential Use

Restroom Building:Restrooms for Events

Page 29: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

“This density is too high...”

Option A: Single, Large Multifamily Building

Page 30: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

“This density is too low…”

Option B: Multiple, Small Single Family Buildings

Page 31: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

“This density is just right!”

Option C: Multiple, Small Multifamily Buildings

Page 32: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

“This option also seems reasonable as a short term means of generating income to offset needed improvements to help create long term viability…”

Option D: Keep the Metal Building

Page 33: TREMONT NAIL FACTORY - Cloudinary

Preliminary Concepts

“This option also seems reasonable as a short term means of generating income to offset needed improvements to help create long term viability…”

Option D: Keep the Metal Building

Potential to build first new building in vacant corner of site

Page 34: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision Plan

Page 35: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision Plan

1. Retain Existing Buildings

Short Term

2. Retain Central Parking

3. Utilize and Improve “The Yard”

4. Utilize and Improve River’s Edge

5. Build Dock at Launch

6. Create Pedestrian Connections

7. Utilize Bridge/Dam Pending Repairs

1

1

1

1

1

2 3

4

4

4

5

6

6

6

7

Page 36: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanShort Term

Page 37: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanShort Term

Factory Building – West Ell:Museum – Blacksmith Shop

Pickling Building:Whitebox (Retail and/or Gallery)

Packaging Building:Retail/Paddlesports

Freight Building – North Ell:Restaurant/Cafe

Freight Shed:Storage

Office Building - Historic:Museum - Welcome Center

Restroom Building:Restrooms for Events

Office Building - Addition:Offices (Property Management)

Metal Building:Artist Studios/Maker Spaces,Markets/Shows, Storage…

Factory Building – Main Space:Event Space, Music Venue, Exhibitions

Factory Building – East Ell:Artist Studios/Maker Spaces

Factory Building – South Ell:Museum – Tool ShopRestaurant/Microbrewery

Freight Building – Main Space:Event Space

Page 38: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanShort Term

Proposed Dockw/ Pavilion

Proposed Path to Merchant’s Way

Proposed Patio

Proposed Lawn / Picnic Area/ Outdoor Classroom

Proposed Lookout and Bridge

Proposed Access to East Ell

Seating and Planters Until Bridge Repaired

Primary Site Access

Welcome Center

Parking

The “Yard” – Outdoor Event Space shown with Café Tables, Retail Layout Space, Food Trucks and Market Stands

Formalized Parking Area

Proposed Sidewalk along South Side of Elm Street

Page 39: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanLong Term

1. Add Residential Units

2. Repair Bridge – Reopen to Vehicular Traffic

1

2

Page 40: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanLong Term

Page 41: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanShort Term: Keep the Metal BuildingProposed Vision PlanLong Term

New Multifamily:Series of Three 12-Unit Buildings

Page 42: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanLong Term

Residential Amenity/Gazebo

Residential Green Space

Reconfigured Parking Area

Building Oriented to Present Sympathetic

Massing to Street

Additional Connections?

Page 43: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanPerspective Views

Page 44: TREMONT NAIL FACTORY - Cloudinary

Proposed Vision PlanPerspective Views

Page 45: TREMONT NAIL FACTORY - Cloudinary

Discussion courb.co/tnf• Visit the project page at this short web

address on desktop or mobile• You can learn about the new project

information, see the timeline and stay in the loop as the project moves forward on coUrbanize

• We’ll post all the information about new plans, meetings, and milestone events here

• There are 2 ways you can participate1) add comments or questions here -all comments go right to the project team and we’ll respond directly2) Follow to subscribe get project updates from the development team by email