trns • port modification reports process

11
Trnsport Modification Reports Process sented at the Trns•port User Group Conference lington VT Shirley Daugherty NE DOR ir, Trns•port Task Force tember 8, 2003

Upload: raymond-rice

Post on 31-Dec-2015

23 views

Category:

Documents


1 download

DESCRIPTION

Trns • port Modification Reports Process. Presented at the Trns•port User Group Conference Burlington VT by Shirley Daugherty NE DOR Chair, Trns•port Task Force September 8, 2003. Trns•port TMRs. Trns•port Modification Requests Errors Enhancements. Trns•port Enhancements. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Trns • port Modification  Reports Process

Trns•port Modification Reports Process

Presented at the Trns•port User Group ConferenceBurlington VTby Shirley Daugherty NE DOR Chair, Trns•port Task Force

September 8, 2003

Page 2: Trns • port Modification  Reports Process

Trns•port TMRs

• Trns•port Modification Requests– Errors– Enhancements

Page 3: Trns • port Modification  Reports Process

Trns•port Enhancements

An Enhancement TMR requests a change to software programs or documentation to extend or improve functionality or performance. All enhancements to the generic Trns•port system must have the

approval of the Trns•port Task Force prior

to being implemented.

Page 4: Trns • port Modification  Reports Process

Trns•port Errors

• In general, a Maintenance TMR requests correction of an error that causes product materials (programs or documentation) to perform contrary to their requirements, design, or other documented specifications.

• Maintenance TMRs may also refer to activity involved in changing program code in response to the discovery of unacceptable performance issues or to address changes in software operating environment that cause the program to work incorrectly.

Page 5: Trns • port Modification  Reports Process

Trns•port Errors

• Report to Info Tech Help Desk by phone or Cloverleaf on-line report– What is the problem?– Document what you were trying to do

• Provide as much detail as you can

– What result was expected?– Provide priority ranking

Page 6: Trns • port Modification  Reports Process

Trns•port Errors

• Info Tech staff will – Assign Call Number– Evaluate report for completeness– Request additional information if needed– Will verify error– Assign a Error Report Number

Page 7: Trns • port Modification  Reports Process

Trns•port Errors

Five priorities:

Urgent – Very important, stops ability to perform a critical business function

Critical – Problem presents licensee from completing implementation (should include a date needed by)

High – Important, a major inconvenience but does not stop a critical business process

Page 8: Trns • port Modification  Reports Process

Trns•port Errors

Five priorities (continued):

Medium – A definite issue but does not stop business process; can work around

Low – A Nuisance to business procedures; can work around

Page 9: Trns • port Modification  Reports Process

Trns•port Errors

SiteManager Errors

CIRT – Construction Issues Review Team

MIRT – Materials Issues Review Team

Page 10: Trns • port Modification  Reports Process

Trns•port Errors

What affects the scheduling of delivery of the Error Resolution?

1) Priority Rating

2) Level of complexity to resolve

3) Resource Availability

Funds and Time

4) Bundling for Efficiency

Page 11: Trns • port Modification  Reports Process