tropic shores rehabilitation project€¦ · where the balcony was fully replaced and with a total...
TRANSCRIPT
![Page 1: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/1.jpg)
Page 1
TROPIC SHORES
REHABILITATION PROJECT
The fourteen assigned workers continued gaining ground for this rehabilitation project,
with the fall temperatures reaching record highs the employees stayed hydrated
withstanding the heat with minimal time lost this reporting period.
Gulfstream Glass, which is the glazing sub-contractor, mobilized on October 24, 2019 and
the three workers began installation at the 01-stack completing five sliding glass doors this
period. Keystone verified the materials being used as Dymonic 100 polyurethane sealant
applied under the threshold, including the surface of the 1x6-inch PVC sill extender, with
3-1/4 inch stainless tapcon style anchors that were encapsulated with the sealant.
The stairwell shearwalls and elevator tower painting was finished, and the contractor plans
to apply the primer on November 4, 2019 at the Porte-cochere.
The east elevation 01-stack is currently forming the edge repairs and once completed the
post tension sub-contractor is scheduled to complete the necessary hardware for the pre-
pour evaluation by the engineer.
Both the north and south elevations have the post tension hardware installed and with
Keystones’ approval to cast, the crew pumped the 6000psi redi-mix concrete at Unit 308
where the balcony was fully replaced and with a total of 4-yards the employees also cst the
kneewalls at Unit 208 and some other approved locations.
Project Summary #6 Prime Contractor: SPEC Contractor Services
Reporting Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes
Daytona Beach Shores Permit # 20190844
PROJECT LOCATION
3111 South Atlantic Avenue, Daytona Beach Shores, Florida 32118
![Page 2: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/2.jpg)
Page 2
Photo during the
stucco application
View at the west
elevation with
SuperPaint
in-progress
![Page 3: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/3.jpg)
Page 3
Photo at the 08-
stack kneewall
formwork
View at the northeast
elevation
![Page 4: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/4.jpg)
Page 4
Photo of the door sub-
contractor assembling the
sliding glass door frame
Photo of Gulfstream
removing the SGD
frame at Unit 401
![Page 5: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/5.jpg)
Page 5
Unit 308 formwork
installation
Photo at the 01-
stack east elevation
![Page 6: TROPIC SHORES REHABILITATION PROJECT€¦ · where the balcony was fully replaced and with a total of 4-yards the ... Period: 10.21.2019 thru 11.1.2019 Superintendent: Beto Fuentes](https://reader035.vdocuments.net/reader035/viewer/2022070917/5fb766317ece8648037a3d46/html5/thumbnails/6.jpg)
Page 6
View of the workers
installing steel at Unit
901-south
Picture of the
contractor at the 08-
stack during
inspection