ts105 test standard uground cable networks

Upload: sumer-land

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    1/17

    Use of this document is subject to the disclaimer on SA Power Networks website:

    www.sapowernetworks.com.au

    SA Power Networks.

    TECHNICAL STANDARD

    TS-105

    www.sapowernetworks.com.au

    FOR TESTING UNDERGROUND & OVERHEADNETWORKS

    Published: 3 September 2012

    WARNING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    2/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 2 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    Refer to TS-105 Appendix A for all the standard forms that are relevant to

    testing and are a pre-requisite to SA Power Networks acceptance of the

    Certificate ofSA Power Networks Electrical Compliance

    REVISION NOTICE:

    DATE EXPLANATIONOctober 2009

    Restructured the document to current standard Added new clause 6.8 Minor amendment to clause 6.3.4 & 7.1

    3 September 2012

    Company name change only. No other content of this Technical

    Standard has been altered. Any revision markings are from the October

    2009 edition.

    SA Power NetworksSA Power Networks means Distribution Lessor Corporation subject to atwo hundred year lease to the partnership of companies trading as SA Power Networks or SA PowerNetworks in its own right.

    SA Power Networks, ABN 13 332 330 749, a partnership of:Spark Infrastructure SA (No.1) Pty Ltd, ABN 54 091 142 380Spark Infrastructure SA (No.2) Pty Ltd, ABN 19 091 143 038Spark Infrastructure SA (No.3) Pty Ltd, ABN 50 091 142 362each incorporated in AustraliaCKI Utilities Development Limited, ABN 65 090 718 880PAI Utilities Development Limited, ABN 82 090 718 951

    each incorporated in The Bahamas1 Anzac Highway, Keswick, South Australia, 5035.

    SA Power Networks Disclaimer:

    1. The use of the information contained in this Technical Standard is at your sole risk.2. The information in this Technical Standard is subject to change without notice.3. SA Power Networks, its agents, instrumentalities, officers and employees:

    a. Make no representations, express or implied, as to the accuracy of the information containedin this Technical Standard;

    b. Accept no liability for any use of the said information or reliance placed on it; andc. Make no representations, either expressed or implied, as to the suitability of the said

    information for any particular purpose.4. SA Power Networks and its agencies and instrumentalities do not endorse or in any respect

    warrant any third party products or services by virtue of any information, material or content

    referred to or included on, or linked from or to this Technical Standard.

    SA Power Networks Copyright @ 2012:

    This publication is copyright. SA Power Networks reserves to itself all rights in such material. Youmust not reproduce any content of this Technical Standard by any process without first obtaining SA

    Power Networks permission, except as permitted under the Copyright Act 1968.

    All rights reserved.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    3/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS-105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 3 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    CONTENTS

    1. PURPOSE ........................................................................................................................ 5

    2. SCOPE ............................................................................................................................. 5

    3. REFERENCES ................................................................................................................ 6

    4. DEFINITIONS ................................................................................................................ 7

    5. GENERAL ....................................................................................................................... 8

    6. UNDERGROUND TESTING ........................................................................................ 9

    6.1 Low Voltage XLPE Distribution Cables.............................................................. 9

    6.1.1 Insulation Resistance ...................................................................................... 9

    6.1.2 Phasing Test ................................................................................................... 9

    6.1.3 Continuity Test (Resistance of Bolted Connections) ..................................... 9

    6.1.4 Earth Resistance Test ................................................................................... 10

    6.2 Public Lighting Cable Circuits ........................................................................... 10

    6.2.1 Insulation Resistance Testing ....................................................................... 10

    6.2.2 Polarity Checking ......................................................................................... 10

    6.2.3 Electrical Testing ......................................................................................... 10

    6.3 11 kV and 33 kV XLPE Cables Including CBD Cables ................................... 11

    6.3.1 Phasing Test ................................................................................................. 11

    6.3.2 Outer Sheath Insulation Resistance (Screen Wire Test) .............................. 11

    6.3.3 HV Test on XLPE Cables already in Service or Previously Energised ....... 126.3.4 HV Test on New XLPE Cable ..................................................................... 12

    6.3.5 Alternative HV Test Requirement on Insulation for 11kV Cables .............. 13

    6.4 Paper Insulated Cables ....................................................................................... 13

    6.4.1 General ......................................................................................................... 13

    6.4.2 Tests on LV Cables ...................................................................................... 13

    6.4.3 Test on 11KV and 33kV Cables between Cores and Earth ......................... 14

    6.5 66kV Oil Filled Cables ........................................................................................ 14

    6.5.1 Core to Sheath Test after Repairs ................................................................. 14

    6.5.2 Outer Sheath Integrity Test .......................................................................... 14

    6.6 66kV XLPE Cables .............................................................................................. 14

    6.6.1 Safety ............................................................................................................ 14

    6.6.2 Core to Sheath Test after Repairs ................................................................. 14

    6.6.3 Outer Sheath Integrity Test .......................................................................... 15

    6.7 Cable Identification Testing ............................................................................... 15

    6.8 Network Access Permits ...................................................................................... 16

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    4/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS-105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 4 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    7. OVERHEAD TESTING ............................................................................................... 17

    7.1 LV ABC ................................................................................................................ 17

    7.2 Buried SWER Earthing Cable Circuits ............................................................. 17

    7.3 11kV and 33kV Covered Conductor and 11kV IUC ........................................ 17

    7.3.1 General ......................................................................................................... 17

    7.3.2 Phasing Test ................................................................................................. 17

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    5/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS-105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 5 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    1. PURPOSEThis Technical Standard specifies the standard testing methodology for underground

    and overhead SA Power Networks distribution networks. The guidelines mentioned in

    this document are applicable to any existing, new extension, repair or replacement work

    carried out that will be a component of SA Power Networks. The standard testing

    techniques will assist in determining the cable performance to prove that the circuit issafe to energise or commission.

    It also provides guidelines in obtaining a network access permit and clarifies the

    responsibilities of SA Power Networks Internal staff and external contractors in

    carrying out the duties in a safe, reliable and cost effective way with the activities

    associated with SA Power Networks networks.

    2. SCOPEThis technical standard provides background information and the SA Power Networks

    distribution specification for the Engineers, certified Inspectors, customers andelectrical installation personnel who are engaged in the activities with testing,

    maintenance and inspection of SA Power Networks distribution network.

    This document should be read in conjunction with other relevant network customer

    information brochures i.e.NICC 404 Information on Contractor Access & Working in

    the vicinity of the Electricity Network, NICC 401 Information on Network Design &

    Installation by an External Contractor, TS105 Testing Standard Appendix A - Forms

    and should also consider the references supplied in clause 3 of this document.

    This technical standard is available via:

    DaNM/DES Intranet website; andSA Power Networks Internet website:www.sapowernetworks.com.auThe use of this document is subject to the disclaimer on SA Power Networks website:

    www.sapowernetworks.com.aufor further assistance and more information concerning

    this technical standard please contact the relevant SA Power Networks Manager

    described in clause 4 in this document.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

    http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/
  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    6/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS-105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 6 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    3. REFERENCESAS/NZS 1026:2004: Electric Cables - Impregnated paper insulated - For working

    voltages up to and including 19/33 (36) kV;

    AS/NZS 3008.1.1:1998: Electrical Installations - Selection of cables - Cables foralternating voltages up to and including 0.6/1 kV - Typical Australian installation

    conditions;

    AS/NZS 3000:2007: Electrical Installations (known as the Australian/NewZealand Wiring Rules);

    ESAA Guidelines for Safe Access to Electrical and Mechanical Apparatus;SA Power Networks Network Directives Manual;SA Power Networks Substation Instruction 3.1;SA Power Networks Switching Manual;SA Power Networks Standard Terms & Conditions;Information on Application for Network Access;NICC 404 - Information on Contractor Access & Working in the vicinity of the

    Electricity Network;

    NICC 401 - Information on Network Design & Installation by an ExternalContractor;

    Regulations under the Electricity Act 1996;Service & Installation Rules 2009;S.A. Occupational Health, Safety and Welfare Act 1986;S.A. Occupational Health, Safety and Welfare Regulations, 1995; andTS 105 - Testing Standard Appendix AForms.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

    http://utilities/Orgdata/Data/Network/NtwkStdsPerf/Standards/Technical%20Standards/NEW%20BRANDING%20FOR%20TS/TS-105/Details.asp%3fdocn=stds000017409http://utilities/Orgdata/Data/Network/NtwkStdsPerf/Standards/Technical%20Standards/NEW%20BRANDING%20FOR%20TS/TS-105/Details.asp%3fdocn=stds000017409
  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    7/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS-105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 7 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    4. DEFINITIONSApplicant- Person applying for access to the SA Power Networks network.

    ASO- Authorised Switching OfficerA person authorised to issue NAPs.

    SA Power Networks- SA Power Networks means Distribution Lessor Corporation

    subject to a two hundred year lease to the partnership of companies trading as SA Power

    Networks or SA Power Networks in its own right.

    SA Power Networks, ABN 13 332 330 749, a partnership of -Spark Infrastructure SA (No.1) Pty Ltd, ABN 54 091 142 380Spark Infrastructure SA (No.2) Pty Ltd, ABN 19 091 143 038

    Spark Infrastructure SA (No.3) Pty Ltd, ABN 50 091 142 362each incorporated in AustraliaCKI Utilities Development Limited, ABN 65 090 718 880

    PAI Utilities Development Limited, ABN 82 090 718 951each incorporated in The Bahamas

    1 Anzac Highway, Keswick, South Australia, 5035.

    SA Power Networks' Manager- The SA Power Networks' Manager or the authorised

    Officer serving that area of the customers installation. For specific Asset Manager

    Areas and their contact details please refer to SA Power Networks internet website

    www.sapowernetworks.com.auand then either under Residential Services or Business

    & Government tabs, browse for Service & Installation Rules and check in Section 3,

    clause 3.0 & 3.1.

    Must- is to be understood as mandatory.

    NAO- Network Access Officer.

    NAP- Network Access Permit.

    NAR- Network Access Request.

    Power line means -

    a set of cables for the transmission or distribution of electricity and theirsupporting structures and equipment; and

    associated equipment for the transmission or distribution of electricity

    Responsible Off icer- means the officer appointed by the relevant SA Power Networks

    Manager to be responsible for the application of this document. There may be multiple

    Responsible Officers with specific responsibilities, e.g. negotiation for supply, provision

    of transformers, specification of points of supply, types of supply, servicing and

    metering.

    Shall- is to be understood as mandatory.

    Should- is to be understood as nonmandatory, i.e. advisory or recommended.

    Sui table (or suitably)- means to the satisfaction of the relevant SA Power NetworksManager.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

    http://www.etsautilities.com.au/http://www.etsautilities.com.au/http://www.etsautilities.com.au/
  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    8/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 8 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    5. GENERALThis Instruction is applicable to any new extension or repair and replacement work.

    The purpose of performing cable tests is to prove that the circuit is safe to energise or

    commission. Cable testing does not necessarily indicate the condition or remaining life

    of a circuit.

    Isolating and earthing requirements for cables connected to transformers and switching

    devices are contained in the Switching Operators Handbook.

    During single phase switching, Ferro resonance conditions can be avoided in loaded

    cable circuits by switching at the transformer location.

    The test work area shall be defined with a red tape barrier and warning signs.

    High Voltage commissioning tests on new URD cables shall be performed without

    connection to other equipment.

    All tests shall be performed on individual sections of HV cable. Separate sections of HV

    cable shall not be connected in series and tested as a whole.

    All test results shall be recorded in accordance with TS-105 - Testing Standard

    Appendix-A - Forms.

    All low and high voltage cables must have the point of destination clearly labelled at

    both ends. As an example:

    Low voltage isolator: Destination is the lot number and streetname for the first service pillar.

    High voltage switch: LB1 to transformere.g. LB1 to LB1 - TC xxxxxx

    Refer to E-1943 Sheet 7.11 for cable naming and labelling details.

    The basis for any numbering sequence for any electrical equipment is to look at the

    equipment from the kerb and circuit one is on the left side of the equipment and any

    identification sequence is undertaken in a clockwise direction.

    For example for a three way pillar the incoming low voltage circuit as shown on the

    plan on the left side is circuit one the centre circuit is two and the right side circuit is

    three.

    The cable destination needs to also reflect the FINAL destination.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    9/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 9 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6. UNDERGROUND TESTING6.1 Low Voltage XLPE Distribution Cables

    The low voltage cables must be tested in the following sequence:

    6.1.1Insulation ResistanceCables shall be tested for insulation resistance with an insulation tester(i.e. Megger) at 1000 Volts for 1 minute.

    The minimum insulation resistance to earth or between phases shall be

    100 meg-ohms.

    The instrument used for this measurement shall have a minimum

    resolution of 10 meg-ohms on the 0 to 500 meg-ohm range.

    At the conclusion of LV insulation resistance testing, the neutrals must

    be connected to the earth stakes.

    6.1.2Phasing TestThe correct phasing of all LV circuits shall be checked at all positions

    where the LV cables are terminated into fuse bases and where any LV

    cable is run from point to point.

    This test shall be performed with an instrument designed for the purpose.

    Mains frequency voltage of 240 Volts is not acceptable for this test.

    The neutral conductor shall be connected to the earth stake for this test.

    6.1.3Continuity Test (Resistance of Bolted Connections)For loop LV UD systems, a continuity test shall be carried out on each

    LV circuit to ensure that all bolted connections are complete and

    adequate. The test shall be carried out as follows:

    At the transformer firmly bond all 4 conductors together; andUndertake a continuity test at every point where there is a service

    provision or open point. In a fused service pillar the bottom row of

    fuses bases must be the point at which the test is undertaken as thatis the furthest extent of the SA Power Networks network.

    The difference between the readings of each phase conductor and the

    neutral for each individual test shall not be greater than 10% of each

    other. Any difference in reading greater than this may indicate a loose or

    dirty connection and will require further investigation.

    The instrument used for this measurement should have a resolution to the

    second decimal point in the 0 to 5 ohm range. A typical instrument would

    be the earth Megger type and taking into account the resistance values

    of the test leads.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    10/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 10 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.1.4Earth Resistance TestMEN AreasIn any overhead or underground network the earth resistance at any point

    along the length of a LV feeder is to have a maximum resistance of 10

    ohms prior to connection to the existing network.

    In difficult earthing locations, alternative configurations may be utilisedwith agreement from the relevant SA Power Networks Manager, as

    detailed in TS-109 (currently in DRAFT format and to be issued shortly).

    CMEN AreasIn any overhead or underground network the overall resistance to earth

    shall be less than 1 ohm prior to connection to the existing network.

    6.2 Public Lighting Cable Circuits6.2.1Insulation Resistance Testing

    The insulation resistance of public lighting circuits, including columnswired on site, shall be tested in accordance with clause 6.1.1 above.

    6.2.2Polarity CheckingA visual check at each end of public lighting circuits shall be carried

    prior to commissioning.

    6.2.3Electrical TestingThe earth and neutral are to be left disconnected at the point of supply.

    The earth and neutral are to be individually meggered at 250 Volts.

    The neutral and earth can be bolted up if testing is satisfactory.

    Check the active by meggering the active back to the point of supply.

    Check the P/L column and assembly. Apply 250 Volts to the load side of

    the fuses at the column. Different types and sizes of luminaries have

    different characteristics.

    Any variation from the normal consistent readings for the same type ofluminarie indicates a problem in the connection or PL fitting.

    Any reading that is greater then this may indicate an open circuit

    problem.

    Any reading that is lower then this may indicate a fault on the load side

    of the fuse.

    On completion the active conductor should be well clear of any metal

    components in the column.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    11/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 11 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.3 11 kV and 33 kV XLPE Cables Including CBD CablesNew cables shall be tested individually, i.e. one phase at a time and one section

    at a time.

    6.3.1Phasing TestThe correct phasing of all HV circuits shall be checked at all positionswhere the HV cables have been terminated.

    This test shall be performed with an instrument designed for the purpose.

    240 Volt mains frequency is not acceptable for the performance of this

    test. The test may be conducted on either the wire screens or the

    aluminium conductors.

    Where the test is performed on the wire screens, they shall be

    disconnected from earth.

    6.3.2Outer Sheath Insulation Resistance (Screen Wire Test)The purpose of the test is to determine soundness of the outer

    polyethylene sheath against water ingress, mechanical damage and

    termite attack.

    Values below 0.5 meg-ohms (500 k) can indicate sheath damage.

    Values between 1.0 and 10 meg-ohms may not indicate damage in a

    single location. Fault finding can often be very difficult. In new cables, a

    value of greater than 100 meg-ohms is required.

    The integrity of the outer sheath shall be checked after cables have beenburied by an insulation tester (Megger) at 1000 Volts. The test shall be

    conducted for 1 minute between each wire screen and earth after the

    cable has been jointed and terminations installed.

    For cables after repairs, the resistance must not be less than 10 meg-

    ohms.

    Where HV cable circuits are cut and joined to new circuits, sheath testing

    must be carried out on the existing old circuit prior to jointing to the new

    cable.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    12/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 12 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.3.3HV Test on XLPE Cables already in Service or Previously EnergisedExcept for new cables, testing at voltages greater than 5.0 kV is not

    permitted;

    DC testing above 5kV of field aged XLPE cables generallyincreases water tree growth and reduces service life; and

    5kV is not considered a High Voltage DC Test.The test voltages for conducting tests on XLPE cables is now limited to

    5kV after in service repairs and 10kV for new installations. A 5kV

    Megger is suitable for a 5kV test on cables after repairs.

    6.3.4HV Test on New XLPE CablePrior to the performance of this test, the screen wires must be connected

    to the permanent earth position.

    The cable shall be tested at the test voltage and the pass criteria shall be

    in accordance with the following table:

    Note: A new cable installation is one not previously connected and

    energised to any existing network asset.

    If further repair works are undertaken, and they require additional joints

    to be installed, the complete HV testing procedure shall be repeated.

    Application Test Voltage Criteria

    After repairsSheath 1kV Megger 1 minute 10 meg-ohms min.

    After repairs -Insulation

    5kV Megger 1 minute

    or5kV DC 1 minute

    1000 meg-ohms min.

    5.0 A (micro-amps)max.

    Application Test Voltage Criteria

    New cables - Sheath 1kV Megger 1 minute 100 meg-ohms

    New cables - Insulation 10kV DC 15 minute; or

    10kV Megger 1 minute

    1.0 A (micro-amps)

    Max. 1000 meg-ohms min.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    13/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 13 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.3.5Alternative HV Test Requirement on Insulation for 11kV CablesWhere it is not practical to conduct a high voltage test, the test

    requirements for insulation (core to screen wire) may be limited to testing

    for the condition of safe to energise.

    The following list of circumstances and conditions must be met as a

    minimum requirement:

    The work conditions shall be emergency or as determined by SAPower Networks Project Manager;

    The cable circuit voltage shall be 11kV;The circuit outage duration shall be not more than 48 hours;The work shall involve extending or repairs to existing circuits;The insulation test shall be applied for 1 minute between each

    phase core and screen with a 1000 Volt minimum insulation tester

    (Megger); and

    Typically the test result should be in the order of 1000 meg-ohms.6.4 Paper Insulated Cables

    6.4.1GeneralTests on paper insulated cable systems shall be performed after new

    installations, extensions or repairs.

    Many CBD high voltage cable circuits are connected to older style

    equipment and therefore test voltages are purposely reduced from those

    in Australian Standard AS1026.

    6.4.2Tests on LV CablesAn insulation resistance test shall be conducted with a 1000 Volt megger.

    Test results as low as 10 meg-ohms on old cable circuits are common andtherefore considered safe to energise.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    14/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 14 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.4.3Test on 11KV and 33kV Cables between Cores and EarthFor three core belted cables, the test on any core shall be conducted

    between the core and lead sheath with the remaining two cores connected

    to earth. The test voltages and pass criteria shall be in accordance with

    the table below.

    Application Test Voltage Criteria

    11kV new cables 5kV Megger 1 minute 1000 meg-ohms

    11kV after repairs 5kV Megger 1 minute 100 meg-ohms

    33kV - no TFs connected 5kV Megger 1 minute 1000 meg-ohms

    33kV - with TFs connected 5kV Megger 1 minute 15 meg-ohms

    6.5 66kV Oil Filled Cables6.5.1Core to Sheath Test after Repairs

    After repairs have been carried out on 66kV single core oil filled cables,

    a DC test shall be applied between the conductor core and metallic sheath

    (earthed). The test voltage shall be 60kV DC for 15 minutes.

    The cable shall be considered safe to energise if the test voltage is

    maintained without failure for the duration of the test. The leakage

    current at the end of the test shall be recorded.

    6.5.2Outer Sheath Integrity TestAn insulation resistance test between the aluminium sheath and earth

    shall be conducted. Where the cable construction includes an anti-termite

    metallic barrier, that barrier shall be connected to the aluminium sheath

    and the insulation test performed to earth.

    The test voltage applied for 1 minute shall be 5kV DC applied with either

    a high voltage test set or insulation resistance tester (Megger).

    6.6 66kV XLPE Cables6.6.1Safety

    Careful attention to safety procedures must be carried out. Rope barriers

    and warning signs are particularly important when testing 66kV cable

    circuits.

    6.6.2Core to Sheath Test after RepairsAfter repairs have been carried out, the 66kV XLPE cable shall be

    energised at power frequency for 24 hours without load.

    DC testing is not permitted.

    The cable sheath link box/cross bonding system shall be put into its

    normal condition.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    15/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 15 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    6.6.3Outer Sheath Integrity TestAn insulation resistance test between the metallic sheath and earth shall

    be conducted. The anti-termite barrier must be connected to the metallic

    sheath and the insulation test performed to earth.

    The test voltage applied for 1 minute shall be 5kV DC applied with either

    a high voltage test set or insulation resistance tester (Megger).

    6.7 Cable Identification TestingWhenever any work is performed on cables that are installed in an SA Power

    Networks transformer or switching cubicle the relevant personnel will

    undertake the following in accordance with the current Network Access

    Procedure:

    Locate the labelling at each end of each cable and note what is recordedon the label;

    If the labels match and identify each cable as being the same phase,proceed to step 2;

    If the labels do not match, all cables MUST be traced and the correctidentification confirmed;

    All cables are to be proved dead and earthed before continuing with thetesting;

    Perform a phase identity test;Perform a screen to earth and screen to core test for high voltage cables

    and a Megger test for low voltage cables in accordance with clause 6.0 of

    this standard;

    The test results will be written up on the relevant forms in TS-105Appendix A, F-34 (HV) / F-31 (LV) in duplicate; and

    If cable test results on the existing cable/s are unsatisfactory, then thedamage to the cable/s is to be identified & repaired. The Contractors

    NAP will be withheld until the damaged cable/s is rectified, then re-

    issued when satisfactory cable test results are available.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    16/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 16 of 17

    The use of this Technical Standard is subject to the conditions stated in SA Power Networks Disclaimer.

    In the event that the cable identification tests are performed as a Request for

    Network Access (NAR) then:

    The original of the test results will be supplied to the contractor alongwith the NAP at the site handover; and

    The cables to be worked on for the period of the contractors access willbe earthed. It will be the contractors responsibility to arrange for earthsto be removed and cables disconnected at both ends for the purpose of

    cable testing.

    The contractor MUST be present for the site handover of any SA Power

    Networks assets.

    6.8 Network Access PermitsTo assist in the delivery of work associated with Network Access Permits

    (NAP) for contestable work it is in the contractors interests to submit the

    request at the earliest opportunity. If the date is tentative only, state that.

    If the date needs to be changed the Network Access Officer (NAO) has the

    opportunity to log and process the request and it is in the system for scoping

    and costing.

    With the preliminary work completed it should improve on-site delivery of the

    request at the time it is needed.

    The following must be undertaken by the SA Power Networks Switching

    Officer (ASO) at the time of the asset handover:

    Install all the required tags and earths on isolated equipment;Clearly record all the Isolation & Earthing points on the Network Access

    Permit;

    Fully explain the extent of the switching and isolation that has takenplace to the Contractor receiving the access, i.e. where the nearest live /

    open points are located; and

    Hand over a copy of the Work Party Responsibilities and one pagesummary sheets when issuing the Network Access Permit.The Contractor accepts the Network Access Permit on the understanding that

    full knowledge of the asset condition has been relayed. The Contractor should

    only accept the Network Access Permit with a full understanding of the on-site

    SA Power Networks network status.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.

  • 7/30/2019 Ts105 Test Standard Uground Cable Networks

    17/17

    TS-105Technical Standard for Testing Underground & Overhead Networks

    TS - 105 Issue: 03/09/12 Authorised: Jehad Ali Date: 03/09/12 Page 17 of 17

    7. OVERHEAD TESTING7.1 LV ABC

    New LV ABC circuits shall be tested (Meggered) for insulation resistance

    between cores and earth prior to commissioning to prove safe to energise.

    Confirm that all working earths have been removed.

    Any cores not being tested are to be earthed including the neutral.

    Ensure neutral bond is still re-connected at the completion of testing.

    7.2 Buried SWER Earthing Cable CircuitsA visual check of cable connections is only required prior to the reinstatement

    of trenching. Refer to E1451 and E1453 for construction details.

    7.3 11kV and 33kV Covered Conductor and 11kV IUC7.3.1

    GeneralA conductor covering insulation test is not required.

    7.3.2Phasing TestHV covered conductors shall be tested for correct phasing in accordance

    with existing procedures for bare conductor systems.

    New and repaired HV ABC circuits shall be tested (Meggered) for

    insulation resistance prior to commissioning to prove safe to energise and

    confirm that all earths have been removed.

    WARN

    ING:Printedcopiesofthisdocu

    mentAREDEEMEDUNCONTROLLED.Themostup-to-dateversionislocatedontheinternet/intranet.