Second Avenue Subway Phase 2 Update to Community Board 11 Land Use Committee

April 14, 2021

Project Overview

2

SASP2 Project Overview - Second Avenue Subway Phase 2

3

4

Soil

Cut-and-Cover Construction Modification of Existing Tunnel Mined Construction

New Tunnels Constructed

using Tunnel Boring Machine

SASP2 Project Overview - Construction Approach

Existing 1970s TunnelEnd of Phase 1 Tunnel

New Storage Tunnels

Constructed using Tunnel

Boring Machine

5

SASP2 Project Overview - Stations Spacing and Arrangement

125 Entrance 2 &

Ancillary 2

125 Mezzanine & Platform

125 Entrance 1 & Ancillary 1

116 Mezzanine & Platform

116 Ancillary 1

116 Ancillary 2

116 Entrance 1

106 Ancillary 2

106 Ancillary 1

106 Mezzanine & Platform

106 Entrance 1

106 Entrance 2

Federal Funding

Funding AgreementEngineeringProject Development

• Entered Project

Development Dec. 2016

• NEPA Re-evaluation

SEA (Supplemental

Environmental Assessment)

completed and FONSI (Finding

of No Significant Impact)

issued Nov. 2018.

• Project received Medium-High

rating from FTA in February

2020

• NEPA Re-evaluation (Tech.

Memo) issued April 2020.

Approved: August 2020.

• Submit request for an FFGA

(Full Funding Grant Agreement)

Goal: TBD

• Project team is coordinating with FTA

consultant to help expedite the FFGA

after project enters Engineering

Phase.

• 2020-2024 Capital Plan includes

remainder of funding for SAS Phase 2.

• Received FTA’s Risk & Readiness

Workshop results : August 28, 2019

• Submitted revised Request to Enter

Engineering on September 5, 2019

• Need FTA approval to Enter

Engineering Phase of New Starts

Program.

Goal: TBD

7

For shallow stations

Ancillary StructuresProposed Acquisition of Property Interests

116th St. Station

Ancillary 2

125th St. Station

Ent. 1 & Anc. 1

125th St. Station

Ent. 2 & Anc. 2 125th St. Tail Track

Ancillary A

9

Contract 1 (Utility Relocation) – Overview

9

CONTRACT C-26201

Design Progress &

Other Activities

• Advanced Works (Contract 1)

• Design completed.

• Meetings with impacted property owners to start soon.

• Civil/Structural Design/Build (DB) (Contracts 2 & 3)

• Contract documents being updated to incorporate additional cost

containment and based on developer coordination at 125th Street.

• MEP, Systems, and Arch. Fit-out Design/Build (DB) (Contract 4)

• Draft documents completed: Q1 2021

• Anticipated completion of final documents by end of 2021

• Ongoing coordination with Developers at 125th Street Station

• Ongoing Geotechnical boring investigations.

11

SASP2 Contract Overview

11

• Contract 1• Advanced utility relocation at 106th Street Station

• Contract 2• TBM construction at 125th Street Station

• TBM launch shaft/bell-mouth will be in proximity to Second Avenue and 120th Street.• TBM extraction shaft will be in proximity to 125th Street and Malcolm X Boulevard.

• Station cavern excavation• Contract 3

• Heavy civil construction at 106th Street Station• Station shell and utility restoration

• Heavy civil construction at 116th Street Station• Existing station tunnel rehabilitation• Excavation for station entrance and ancillaries

• Contract 4• Station entrances and ancillaries excavation at 106th and 125th Street Station• Station, entrances and ancillaries finishes at 106th, 116th and 125th Street Station• Final street restoration

1212

Questions or Comments

Contact Information:

Joe O’DonnellMTA Construction & DevelopmentJoseph.O'[email protected]

Alex Zamudio East Harlem Community Collaborators [email protected]