update to community board 11 land use committee th st
TRANSCRIPT
Metro-North
4
5
6
125th St.
116th St.
106th St.
Second Avenue Subway Phase 2 Update to Community Board 11 Land Use Committee
April 14, 2021
4
Soil
Cut-and-Cover Construction Modification of Existing Tunnel Mined Construction
New Tunnels Constructed
using Tunnel Boring Machine
SASP2 Project Overview - Construction Approach
Existing 1970s TunnelEnd of Phase 1 Tunnel
New Storage Tunnels
Constructed using Tunnel
Boring Machine
5
SASP2 Project Overview - Stations Spacing and Arrangement
125 Entrance 2 &
Ancillary 2
125 Mezzanine & Platform
125 Entrance 1 & Ancillary 1
116 Mezzanine & Platform
116 Ancillary 1
116 Ancillary 2
116 Entrance 1
106 Ancillary 2
106 Ancillary 1
106 Mezzanine & Platform
106 Entrance 1
106 Entrance 2
Federal Funding
Funding AgreementEngineeringProject Development
• Entered Project
Development Dec. 2016
• NEPA Re-evaluation
SEA (Supplemental
Environmental Assessment)
completed and FONSI (Finding
of No Significant Impact)
issued Nov. 2018.
• Project received Medium-High
rating from FTA in February
2020
• NEPA Re-evaluation (Tech.
Memo) issued April 2020.
Approved: August 2020.
• Submit request for an FFGA
(Full Funding Grant Agreement)
Goal: TBD
• Project team is coordinating with FTA
consultant to help expedite the FFGA
after project enters Engineering
Phase.
• 2020-2024 Capital Plan includes
remainder of funding for SAS Phase 2.
• Received FTA’s Risk & Readiness
Workshop results : August 28, 2019
• Submitted revised Request to Enter
Engineering on September 5, 2019
• Need FTA approval to Enter
Engineering Phase of New Starts
Program.
Goal: TBD
For shallow stations
Ancillary StructuresProposed Acquisition of Property Interests
116th St. Station
Ancillary 2
125th St. Station
Ent. 1 & Anc. 1
125th St. Station
Ent. 2 & Anc. 2 125th St. Tail Track
Ancillary A
Design Progress &
Other Activities
• Advanced Works (Contract 1)
• Design completed.
• Meetings with impacted property owners to start soon.
• Civil/Structural Design/Build (DB) (Contracts 2 & 3)
• Contract documents being updated to incorporate additional cost
containment and based on developer coordination at 125th Street.
• MEP, Systems, and Arch. Fit-out Design/Build (DB) (Contract 4)
• Draft documents completed: Q1 2021
• Anticipated completion of final documents by end of 2021
• Ongoing coordination with Developers at 125th Street Station
• Ongoing Geotechnical boring investigations.
11
SASP2 Contract Overview
11
• Contract 1• Advanced utility relocation at 106th Street Station
• Contract 2• TBM construction at 125th Street Station
• TBM launch shaft/bell-mouth will be in proximity to Second Avenue and 120th Street.• TBM extraction shaft will be in proximity to 125th Street and Malcolm X Boulevard.
• Station cavern excavation• Contract 3
• Heavy civil construction at 106th Street Station• Station shell and utility restoration
• Heavy civil construction at 116th Street Station• Existing station tunnel rehabilitation• Excavation for station entrance and ancillaries
• Contract 4• Station entrances and ancillaries excavation at 106th and 125th Street Station• Station, entrances and ancillaries finishes at 106th, 116th and 125th Street Station• Final street restoration
1212
Questions or Comments
Contact Information:
Joe O’DonnellMTA Construction & DevelopmentJoseph.O'[email protected]
Alex Zamudio East Harlem Community Collaborators [email protected]