updated schedule(if buiilding permit on 09mar'14)

17
7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14) http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 1/17 02.03.14 UPDATED  SCHEDULE  &  DELAYS If the recepit of Building Permit is on 09 Mar'14,the project completion date will be 24 July'14 Showing a delay of 126 days This Delay due to Non receipt of Building Permit which affected the following activities:- 1. Substation works 2. Chiller yard works 3. Pump room works 4. Lift Works 5. Start of Fire fighting/Fire Alarm Works 6. Application for Permanent Power connectionwill be delayed due non reciept of Building permit Description Planned as per Baseline Schedule Forecasted/ Revised Date Delays Recepit of Building Permit 28-Oct-13 9-Mar-14 Completion of Project 20-Mar-14 24-Jul-14 126

Upload: jacob-chakola

Post on 17-Feb-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 1/17

02.03.14

UPDATED 

SCHEDULE 

DELAYS

If the recepit of Building Permit is on 09 Mar'14,the project completion date will be 24 July'14

Showing a delay of 126 days

This Delay due to Non receipt of Building Permit which affected the following activities:-

1. Substation works

2. Chiller yard works

3. Pump room works

4. Lift Works

5. Start of Fire fighting/Fire Alarm Works

6. Application for Permanent Power connectionwill be delayed due non reciept of Building permit

Description

Planned asper

Baseline

Schedule

Forecasted/

Revised DateDelays

Recepit of Building Permit 28-Oct-13 9-Mar-14

Completion of Project 20-Mar-14 24-Jul-14 126

Page 2: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 2/17

Page 3: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 3/17

Page 4: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 4/17

Page 5: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 5/17

Page 6: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 6/17

Page 7: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 7/17

Page 8: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 8/17

Page 9: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 9/17

Page 10: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 10/17

Page 11: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 11/17

Page 12: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 12/17

Page 13: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 13/17

Page 14: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 14/17

Page 15: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 15/17

Page 16: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 16/17

Page 17: Updated Schedule(if Buiilding Permit on 09Mar'14)

7/23/2019 Updated Schedule(if Buiilding Permit on 09Mar'14)

http://slidepdf.com/reader/full/updated-scheduleif-buiilding-permit-on-09mar14 17/17

 Activity ID Activity Name Org.Dur Baseline EarlyStart

BaslineEarly Finish

 Actual/ForecastStart

 Actual/ForecastFinish

Schedule % Complete

 ActualPhysical %

Complete

PlannedEarned

Value%

 Actual Earned Value %

CompletePWA061 Floor/Wall finishes 8 05-Feb-14 13-Feb-14 26-Apr-14 05-May-14 100% 0% 0.22 0.00

PWA071 Doors & Windows 5 11-Feb-14 16-Feb-14 01-May-14 07-May-14 100% 0% 0.04 0.00

PWA081 Aluminium Works 5 12-Feb-14 17-Feb-14 03-May-14 08-May-14 100% 0% 0.04 0.00

PWA091 Final Fixes & Fittings 5 15-Feb-14 19-Feb-14 05-May-14 11-May-14 100% 0% 0.04 0.00

PWA101 Final coat Painting 3 17-Feb-14 19-Feb-14 07-May-14 11-May-14 100% 0% 0.03 0.00

COMMICOMMISSIONING & CLOSE OUT   54 06-Feb-14 19-Mar-14 20-May-14 23-Jul-14 49.72% 2.46 0.00

TESTINTESTING & COMMISSIONING   35 06-Feb-14 05-Mar-14 20-May-14 01-Jul-14 54.33% 2.29 0.00

OverallOverall   35 06-Feb-14 05-Mar-14 20-May-14 01-Jul-14 54.33% 2.29 0.00

HW015 Testing & commissioning of all Electr ical systems & 24 06-Feb-14 05-Mar -14 20-May-14 18-Jun-14 54.17% 0% 0.35 0.00

HW012 Testing & commissioning of all F ire fighting system 21 06-Feb-14 02-Mar-14 20-May-14 15-Jun-14 61.9% 0% 0.23 0.00

HW 010 Testing & commissioning of all HVAC systems 21 09-Feb-14 04-Mar-14 08-Jun-14 01-Jul-14 52.38% 0% 0.30 0.00

HW013 Testing & commissioning of all Drainage & Plumbin 21 09-Feb-14 04-Mar-14 08-Jun-14 01-Jul-14 52.38% 0% 0.20 0.00

HW016 Testing & commissioning of all F ire Alarm, Acces co 18 10-Feb-14 02-Mar-14 24-May-14 15-Jun-14 55.56% 0% 0.13 0.00

HW017 Testing & commissioning of all Telephone,Data,PA 18 10-Feb-14 02-Mar -14 24-May-14 15-Jun-14 55.56% 0% 1.08 0.00

CLOSECLOSE OUT   44 06-Feb-14 19-Mar-14 03-Jun-14 23-Jul-14 44.21% 0.18 0.00

OverallOverall   44 06-Feb-14 19-Mar-14 03-Jun-14 23-Jul-14 44.21% 0.18 0.00

HW 020 Submission of O&M Manuals & AS Built drawings 28 06-Feb-14 10-Mar-14 03-Jun-14 05-Jul-14 46.43% 0% 0.18 0.00

HW025 Snagging & Handingover works 21 24-Feb-14 19-Mar-14 30-Jun-14 23-Jul-14 0% 0% 0.00 0.00

O N D J F M A M J Jul A S t

2014

23-Jul-1

01-Jul-14

01-Jul-14

23-Jul-1

23-Jul-1

Empolyer : Musanada

Consultant: UPA

Contractor: Ranya Contracting

SHAMMA BINT MOHAMMAD SCHOOL Updated Schedule