updates on cenf sb wg cenf project meeting 19 th september 2013

28
Updates on CENF SB WG CENF Project Meeting 19 th September 2013 M. Calviani for the CENF SB WG team

Upload: alain

Post on 23-Feb-2016

41 views

Category:

Documents


0 download

DESCRIPTION

Updates on CENF SB WG CENF Project Meeting 19 th September 2013 . M. Calviani for the CENF SB WG team. Civil Engineering updates. L. Faisandel, N. Baddams, S. Girod. Civil Engineering updates. Space added to fix backwards shielding leakage w/ Fe blocks. L. Faisandel, N. Baddams, S. Girod. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

Updates on CENF SB WGCENF Project Meeting 19th

September 2013

M. Calviani for the CENF SB WG team

Page 2: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

2 M. Calviani - CENF PTM 19th September 2013

Civil Engineering updates

19th September 2013

L. Faisandel, N. Baddams, S. Girod

Page 3: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

3 M. Calviani - CENF PTM 19th September 2013

Civil Engineering updates

19th September 2013

L. Faisandel, N. Baddams, S. GirodSpace added to fix backwards shielding leakage w/ Fe blocks

Page 4: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

4 M. Calviani - CENF PTM 19th September 2013

Civil Engineering design updates

19th September 2013

L. Faisandel, N. Baddams, S. Girod

Space reserved for Fe collar at the beginning of DP (thermal analysis pending)

Page 5: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

5 M. Calviani - CENF PTM 19th September 2013

Secondary Beam integration

19th September 2013L. F

aisa

ndel

, N. B

adda

ms,

S. G

irod

Page 6: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

6 M. Calviani - CENF PTM 19th September 2013

Secondary Beam integration

19th September 2013

S. Girod

Page 7: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

7 M. Calviani - CENF PTM 19th September 2013

Secondary Beam integration

19th September 2013

S. Girod

Inconsistencies between integration and CE will be removed at the next iteration

Page 8: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

8 M. Calviani - CENF PTM 19th September 2013

Transport and manipulation input

Updated layout and modifications of previous design Bigger overall height due to a larger span Festoon parallel to the railways containing all cables

19th September 2013

R. Rinaldesi, K. Kershaw

Main hoist Capacity: 40 ton Lifting height: 24 m Lifting speed: 5 m/min FEM classification: M4/A4 Reeving system: 4/2 (true vertical lift)

Auxiliary hoist: Capacity: 5 ton Lifting height: 26,1 m Lifting speeds: 1.6 m/min FEM classification: M4/A4 Reeving system: 4/2 (true vertical lift)

Page 9: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

9 M. Calviani - CENF PTM 19th September 2013

Transport and manipulation input

19th September 2013

R. Rinaldesi, K. Kershaw

40 ton 5 ton

Page 10: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

10 M. Calviani - CENF PTM 19th September 2013

Transport and manipulation input

19th September 2013

Fault analysis (link) Mechanical faults (hoist + cross and long travel)

Most risky is gearbox assembly – additional mitigation with heavy duty gearbox

Electrical faults Cubicles (power and control) outside radiation areas

Page 11: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

11 M. Calviani - CENF PTM 19th September 2013

Initial discussion on access system configuration

19th September 2013

F. Valentini

Material Door:Controlled

Page 12: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

12 M. Calviani - CENF PTM 19th September 2013 19th September 2013

F. Valentini

Page 13: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

13 M. Calviani - CENF PTM 19th September 2013 19th September 2013

F. Valentini

TO BE MODIFIED WITH NEW LAYOUT OF HS BUILDING

Page 14: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

14 M. Calviani - CENF PTM 19th September 2013

Next items for discussions: Confirmation of the role of the CV systems Confirmation of radiological classification of the different areas (RP) List of all CENF areas accessible by personnel Confirmation of the CENF sectorization

19th September 2013

F. Valentini

Page 15: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

15 M. Calviani - CENF PTM 19th September 2013

Update on He-vessel calculations

Preliminary evaluation on the He-vessel structural issues Assuming vacuum needed before refilling with He

Case studied: 100 mm thick – 250 ton 50 mm thick – 125 ton 50 mm thick – lateral stiffeners 50 mm clamped

Max total deformation 36 mm Max reaction force 1.2 MN Stress ~175 MPa, good safety factors with S235/S355 SSS

Other solutions under investigation (i.e. screw pushing the blocks)!

19th September 2013

A. Perillo-Marcone, M. Hora

Page 16: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

16 M. Calviani - CENF PTM 19th September 2013

T2K He-vessel clamping

19th September 2013

Page 17: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

17 M. Calviani - CENF PTM 19th September 2013

Updates on EL infrastructure

Preliminary layout of the EL infrastructure

19th September 2013

J. Devine

Page 18: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

18 M. Calviani - CENF PTM 19th September 2013 19th September 2013

J. D

evin

e

Page 19: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

19 M. Calviani - CENF PTM 19th September 2013 19th September 2013

18 kV stable loop

18 kV pulsed loop

3.3 kV secure loop

J. Devine, M. Dujardin

Redundant 18kV/400V transformers

UPS network

Safety 400V loadsNormal loads 400 V

UPS

Horn/reflector

Page 20: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

20 M. Calviani - CENF PTM 19th September 2013

Discussion on cooling and ventilation matters

19th September 2013

Design air-tightness parameter (until CE parameters will be available) 0.6 vol/h @50Pa

Morgue will be at a lower pressure with respect to target hall

In the next days a proposition on the pressure cascade will be discussed Flow estimation !

M. Battistin

Page 21: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

21 M. Calviani - CENF PTM 19th September 2013

Avoid recirculation in the underground areas (dry air) Recirculation in the target hall Dedicated extraction for the service pit will be foreseen Foresee a delay line in the underground extraction HTO condensation at the extraction or at stack?

19th September 2013

M. Battistin

Delay line/buffer tank

PRELIMINARY

Page 22: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

22 M. Calviani - CENF PTM 19th September 2013 19th September 2013

No recirculation

M. Battistin

PRELIMINARY

Page 23: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

23 M. Calviani - CENF PTM 19th September 2013

Discussion on cooling and ventilation matters

19th September 2013

M. Battistin

b. 893

Flow estimation will be clarified with an improved thermal load distribution ongoing

PRELIMINARY

Page 24: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

24 M. Calviani - CENF PTM 19th September 2013

Radioprotection updates

19th September 2013

C. Strabel, H. Vincke

Page 25: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

25 M. Calviani - CENF PTM 19th September 2013

Cumulated dose in reflector area

19th September 2013

C. Strabel, H. Vincke

~10 Gy/y at motors location (~1010 HEH/cm2/y) ~Gy/y in the service pit Expected <O(10) mGy/y in target hall

Page 26: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

26 M. Calviani - CENF PTM 19th September 2013

Cumulated dose in 1st pit area

~1-50 kGy/y at 1st muon pit

19th September 2013

C. Strabel, H. Vincke

Page 27: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

27 M. Calviani - CENF PTM 19th September 2013

Radioprotection and radionuclide emission

According to present calculations, 44 TBq/y would be released if extraction would be immediate; 30 TBq/y are due to 15O, with a t1/2 of 2 min;

If air could be released with a delay of 5 to 10 minutes, the effective dose to public will be minimal

Next: When ventilation flow will be know, the effect of

continuous release will be evaluated by HSE

19th September 2013

P. Vojtyla

Page 28: Updates on CENF SB WG CENF Project Meeting 19 th  September 2013

28 M. Calviani - CENF PTM 19th September 2013

Next steps

Next meeting to be organized during next week

URGENT and being followed-up: clarify ventilation flows, propose pressure cascade and sectorization Small document to be prepared?

Thermal loads evaluation in the installation