urban tunnelling: constraints and challenges 2011-2012... · urban tunnelling: constraints and...

43
Urban Tunnelling: Urban Tunnelling: Constraints and Challenges Constraints and Challenges (Inaugural Lecture of the Master Course on Tunnels and Underground Space) ITA/AITES ITA/AITES Prof. Andre Assis, PhD Prof. Andre Assis, PhD (University of Brasilia / ITA) (University of Brasilia / ITA) AFTES International Congress Lyon 2011 AFTES International Congress Lyon 2011 Underground Space for Tomorrow Underground Space for Tomorrow Lyon (France) 17 Lyon (France) 17 - - 19 October 2011 19 October 2011

Upload: dodang

Post on 11-Mar-2018

246 views

Category:

Documents


11 download

TRANSCRIPT

Page 1: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Urban Tunnelling:Urban Tunnelling:Constraints and ChallengesConstraints and Challenges

(Inaugural Lecture of the Master Course on Tunnels and Underground Space)

ITA/AITESITA/AITES

Prof. Andre Assis, PhD Prof. Andre Assis, PhD (University of Brasilia / ITA)(University of Brasilia / ITA)

AFTES International Congress Lyon 2011AFTES International Congress Lyon 2011““Underground Space for TomorrowUnderground Space for Tomorrow””

Lyon (France) 17Lyon (France) 17--19 October 201119 October 2011

Page 2: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

5ConclusionsConclusions

Urban Environment for TunnellingUrban Environment for Tunnelling

Design and Construction AspectsDesign and Construction Aspects

IntroductionIntroduction

Lessons Learnt from AccidentsLessons Learnt from Accidents

Contents

2

3

4

1

Page 3: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Introduction

22

33

44

55

11

•Increase of the urban population

•Environmental Era

•Tunnelling technology

Page 4: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

4/404/40

• Mass Transit Systems and Motorways

• Public Utilities

• Flood Control

• Revitalisation of City Centres

• Public Buildings

Demand of Urban Tunnelling

Page 5: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Madrid Road Ring M-30

Page 6: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

6/406/40

• Safety– During Construction– During Operation

• Costs (GC = CC + SB)– Expropriation– Indemnification– Devaluation

Difficulties in Deciding forUnderground Structures

Page 7: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Urban Urban TunnellingTunnelling��

ConstraintsConstraints

Public DecisionPublic Decision

Alignment defined by Alignment defined by demanddemand

Geology imposedGeology imposed

Page 8: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Urban Tunnelling in Soft Ground• Most cases of soft ground tunnelling are

in urban environment• Main concern during excavation is the

stability of the opening• Tunnelling-induced displacement field

may reach surface and affect existing nearby structures

• Design may be dominated by admissible-displacement criteria

Page 9: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

General Trends in the Tunnelling Industry� High risk type construction methods� Trend towards design + build contracts� One-sided contract conditions� Tight construction schedules� Low financial budgets� Fierce competition in construction

industries

Page 10: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Decade 1990Decade 1990

Page 11: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages
Page 12: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

25.11.2011

““No construction project is risk free.No construction project is risk free.

Risk can be managed, minimised,Risk can be managed, minimised,

shared, transferred or accepted.shared, transferred or accepted.

It cannot be ignored.It cannot be ignored.””

Sir Michael Latham, 1994Sir Michael Latham, 1994

Page 13: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Urban Environment for Tunnelling

13/4013/40

22

33

44

55

11Major concerns of urban tunnelling in soft ground and are related to (Kovari & Ramoni, 2004):

• Urban Environment

• Ground Conditions

• Risk Scenarios

Page 14: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

UrbanEnvironment

• Constraints for alignment• Shallow overburden• Existence of nearby structures• Foreign objects inside the ground• Restrictions for auxiliary works• Complex geometry

Page 15: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Constraintsfor Alignment

• Usually dominated by the tunnel demand• Influenced by urban constraints (p.ex.

location of ventilation towers) • Preferable under public ground• Unavoidable to underpass existing structures• Cope with existing ground conditions

Page 16: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Shallow Overburden

• Access ways as shallow as possible• Larger and larger tunnel diameters

• Concept of Shallow Tunnel– Type of Failure– Displacement field up to surface or

existing structures

Page 17: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

ShallowOverburden �Failure Mode

Page 18: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Existence of Nearby Structures

• Types of structures (transport ways, public utilities, buildings, historical sites etc.)

• Nearby structures are affected by the induced displacement field, but they also affect the displacement field � Interaction

• Sensitivity to potential damages

Page 19: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Existence of Nearby Structures

Page 20: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Foreign Objects inside the Ground

• Direct conflict with tunnel alignment–Structural elements (foundation,

anchors, sheet piles)–Public utilities–Wells–Tree trunks and roots

Page 21: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Foreign Objects inside the Ground

Page 22: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Restrictions forAuxiliary Works• Exploitation• Shaft of attack• Ventilation towers• Muck transport and disposal• Dewatering• Ground improvement• Monitoring

Page 23: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Ground Conditions

• Existing ground conditions– Recent geological formations– Fills– Frequent changing conditions (weathering)– Groundwater

• Complex Local Geology � requires �� Ground Improvement and Reinforcement

Page 24: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Face reinforcement Face reinforcement by fiberglass by fiberglass

elements FGEelements FGE

Steel pipes Steel pipes umbrellaumbrella

Page 25: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Purpose of Ground Improvement(Grasso, 2009)

Note:Note:CONVCONV: Conventional Tunnelling : Conventional Tunnelling

TBMTBM: Mechanised Tunnelling: Mechanised Tunnelling

Needs for Ground Improvement CONV TBM

Geo-problems (thrust zone, shear zone, fault zone especially when water-bearing, zone of very poor quality ground, Kartstic voids …) � �

Insufficient self-supporting time �

Unacceptable ground surface settlement � �

Very low overburden underpasses in urban area � �

Keeping natural water table � �

Global face stability �

Face stability during machine maintenance �

Modify Ground Reaction Curve (GRC) (radial and longitudinal directions) � �

Water inflow with high pressure � �

Interaction of newly designed underground structures with those excavated earlier � �

Flowing ground � �

TunnellingTunnelling

ConventionalConventional

Mechanised Mechanised ““TBMTBM””

Difficult ground conditionDifficult ground condition

Limit work conditionLimit work condition

Page 26: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Risk Scenarios

• Collapses up to surface• Damages due to tunnelling-induced

displacements

Design Criteria in terms of:Design Criteria in terms of:-- FailureFailure-- Admissible DisplacementsAdmissible Displacements

(damages)(damages)

Page 27: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

High Visibility of Damages

• Sensitivity of potential damages

• Loss of public confidence is very jeopardising to tunnelling industry

Page 28: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Design and Construction Aspects

22

33

44

55

11

Principles of Tunnelling

• Ground excavation

• Support installation

• Monitoring

Ground-SupportInteraction �

Bearing Ring of Reinforced Ground

ObservationalMethod

Page 29: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Geology

Lab and In-Situ Tests

Designer Experience

Investigation

Geotechnical Properties

Excavation Method and Support System

Structural Model and Design Predictions

Ok?

Construction

Yes

NoElements of

Tunnel Design

Page 30: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Tunnelling-Induced Displacements

Page 31: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Vs = VpVs = Vp

Loss of Ground Vp (mLoss of Ground Vp (m33/m)/m)00 22 4433 5511

1122

33445566

77

Vs (m

Vs (m

33 /m)

/m)

A'A"

BB'

q

p

eei

A

before collapse

collapse

after collapse

colla

pse

crite

rion

Page 32: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Checking for Tunnelling-Induced Damages

• Calculate the green field settlement trough• For structures inside the settlement trough,

check potential damages due to green field settlements and distortions

• For those in critical state, run a more accurate analysis taking into account the structure stiffness

• Perform reinforcement when required

• Mair, R. (2011). ITA Muir Wood Lecture.

Page 33: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Contractor Experience Construction

Ok?

Yes

NoElements of

Construction

Monitoring

Ok?

Yes

No

Safe

4 m6 m

H - 2 m

(H - 2 m) / 2

H

M1

E1

E2P1

M2M4 M3 M5

P2

P4

P6

P3

P7

P5

Page 34: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

Per

cent

Pas

sing

[%]

Particle Size [mm]

0

10

20

30

60 10020620,60,20,060,020,0060,002

40

50

60

70

80

90

100

EPB

1Water for consistency, foam for stickiness

2Foam

3Foam + Polymers, water pressure < 2 bar

4Foam + Polymers + fines, no water pressure

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

Per

cent

Pas

sing

[%]

Particle Size [mm]

0

10

20

30

60 10020620,60,20,060,020,0060,002

40

50

60

70

80

90

100

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

Per

cent

Pas

sing

[%]

Particle Size [mm]

0

10

20

30

60 10020620,60,20,060,020,0060,002

40

50

60

70

80

90

100

EPB

1Water for consistency, foam for stickiness

1Water for consistency, foam for stickiness

2Foam

2Foam

3Foam + Polymers, water pressure < 2 bar

3Foam + Polymers, water pressure < 2 bar

4Foam + Polymers + fines, no water pressure

4Foam + Polymers + fines, no water pressure

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

Per

cent

Pas

sing

[%]

Particle Size [mm]

0

10

20

30

60 10020620,60,20,060,020,0060,002

40

50

60

70

80

90

100

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

GRAVELSANDSILTCLAY

coarsemediumfinecoarsemediumfinecoarsemediumfine

Per

cent

Pas

sing

[%]

Particle Size [mm]

0

10

20

30

60 10020620,60,20,060,020,0060,002

40

50

60

70

80

90

100

Fluid-Supported

ASt

anda

rdap

plica

tion

+se

para

tion

ASt

anda

rdap

plica

tion

+se

para

tion

CFa

cesu

ppor

t diffi

cult:

susp

ensio

n+fill

ers

CFa

cesu

ppor

t diffi

cult:

susp

ensio

n+fill

ers

BAn

ti-clo

ggin

g-m

easu

res,

high

sepa

ratio

nef

fort

BAn

ti-clo

ggin

g-m

easu

res,

high

sepa

ratio

nef

fort

Page 35: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Monitoring andTBM Active Control

Control system• Controlling of Boring

Process: guide parameters from interdisciplinary processing of geotechnical, geodetic and machine data

Page 36: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

22

33

44

55

11

Statistics on Causes of AccidentsLessons Learnt

Page 37: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Pre-Bidding Documents• Geological investigation and geotechnical

data as much as possible

• Full disclosure of all GG data– Geological model– GG Data Report– Geotechnical Base Report

• Different Ground Conditions � Owner

Page 38: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Design Documents

• Geomechanical model• Structural model of the tunnel• Assumptions, completeness and type of

calculations and simulations– Continuum media?– Type of model and parameters– 2D or 3D analysis?

• Monitoring � threshold values• Design Reviewer

Page 39: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Design during Construction

• Complementary investigation and mapping of all GG conditions

• Monitoring interpretation

• Design back-analysis

• Design Validation

-25

-20

-15

-10

-5

0

5

23/1

1/06

03/1

2/06

13/1

2/06

23/1

2/06

02/0

1/07

12/0

1/07

Data

Rec

alqu

e (m

m) 7.0+86 - P1

7.0+86 - P2

7.0+86 - P3

7.0+96 - P1

7.0+96 - P2

7.0+96 - P3

7.1+06 - P1

7.1+06 - P2

7.1+06 - P3

7.1+15 - P1

7.1+15 - P2

7.1+15 - P3

Page 40: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Construction

• Faithful to the design � changes in agreement

• Quality control (materials and services)

• Integrated risk and construction management � contingency and emergency actions

Page 41: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Role of Contracts

• Keep fair balance– quality, schedule and costs

• Mix of technical and performance specifications � quality control

• Independent auditing and full disclosure of control parameters

• Incorporate risk management and risk sharing

Page 42: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages

Conclusions

22

33

44

55

11• Urban tunnelling is a great and

increasing demand worldwide

• Urban tunnelling is challenging due to urban environment and its constraints

• Urban tunnelling is likely dominated by limit admissible damage criteria

• Risk management has to be incorporated in all project phases

Page 43: Urban Tunnelling: Constraints and Challenges 2011-2012... · Urban Tunnelling: Constraints and Challenges ... (Kovari & Ramoni, 2004): ... Checking for Tunnelling-Induced Damages