Page 1: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Use of GIS in Determination of the Probable Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant SitesMaximum Flood at Nuclear Plant Sites

Presented by:

Monica Anderson, GISP Tennessee Valley Authority

Carrie Stokes, PE, CHMMBarge Waggoner Sumner & Cannon, Inc.

Page 2: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Presentation OverviewPresentation Overview

• Requirements for Probable Maximum Flood (PMF) Determination

• Definition of PMF• TVA River System Overview• Modeling Needs• GIS data processing• GIS-based inputs for model• Lessons Learned• Questions

Page 3: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Requirements for PMF DeterminationRequirements for PMF Determination

Nuclear Regulatory Commission (NRC) regulations require that nuclear plants be designed for the Probable Maximum Flood (PMF) as described in Regulatory Guide 1.59, “Design Basis Floods for Nuclear Power Plants”.

Page 4: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Probable Maximum Flood (PMF)Probable Maximum Flood (PMF)

The Probable Maximum Flood (PMF) is the flood that may be expected from the most severe combination of critical meteorological and hydrologic conditions that are reasonably possible in a particular drainage area.

Page 5: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Tennessee River System OverviewTennessee River System Overview

The Tennessee River is the fifth largest in the United States in terms of discharge and seventh largest in North America.

The drainage area covers 40,910 square miles and lies mostly in the state of Tennessee with parts in six other states- Kentucky, Virginia, North Carolina, Georgia, Alabama, and Mississippi.

There are over 49 dams on the Tennessee River watershed. The river system is operated as a multi-purpose system.

Page 6: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Tennessee River System OverviewTennessee River System Overview

Page 7: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Tennessee River System OverviewTennessee River System Overview

813

741

682.5

634.5

595556

507.7414

359

Summer Pool Elevations

Page 8: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Modeling NeedsModeling Needs

Inputs to the PMF model simulations included:•calibrated reservoir models (geometry files and Manning’s n values),•operating guides and initial reservoir levels,•reservoir storage,•initial dam rating curves, and •storm-specific inflow hydrographs developed based on rainfall, rain/runoff relationship, and basin runoff response.

Page 9: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

GIS Data UsedGIS Data Used• USGS Digital Elevation Model (DEM) 10M & 30M & hard copy 1:24,000

Topographic Maps • US Army Corps of Engineers – 500’ Underwater Elevation Points• Rain/Stream Gage Data from TVA River Operations Hydro Engineers• Watershed Boundaries were derived from the Hydrologic Units based

on the 12-digit Hydrologic Unit Codes downloaded January 2008. Watershed boundaries for AL, GA, and VA were downloaded from NRCS (http://datagateway.nrcs.usda.gov); for NC, from USDA (ftp://ftp-fc.sc.egov.usda.gov/NC); for TN, from Tennessee Spatial Data Server (http://www.tngis.org/frequently_accessed_data.html). Additional boundaries were delineated at selected stream gages from 1:24,000 scale USGS topographic maps.

• State of Tennessee Digital Terrain Model (DTM) data

Page 10: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Data Processing ApproachData Processing Approach• Convert DEM data to Contour Polygons• Digitize data from hard copy 1:24,000 Topographic Maps from

USGS• Converted the USACE 500’ underwater elevation points to TIN

– Perfected this process through a number of trial and error attempts.

• HUC delineation in areas of concern with existing sub-basin data• Antecedent Precipitation Index (API) regions were geo-referenced

and plotted with the watershed basins.• Reservoir Storage – calculate total surface area of each contour

polygon.• Probable Maximum Precipitation Isohyets used to calculate the

weighted average rainfall for each sub-basin.

Page 11: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input - Watershed DelineationModel Input - Watershed Delineation

Page 12: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input – API RegionsModel Input – API Regions

Page 13: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input – Channel GeometryModel Input – Channel Geometry

Page 14: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input - Channel GeometryModel Input - Channel Geometry

Page 15: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input – Reservoir StorageModel Input – Reservoir Storage

Page 16: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Model Input – Critical Storm SelectionModel Input – Critical Storm Selection

Page 17: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Lessons LearnedLessons Learned

• DEM Conversion Inaccuracies – details matter!– 32-bit floating point option instead of 16-bit integer option– This change allows ArcGIS Spatial Analyst Contour Tool to create

smoother (interpolated) contour linework.– US Survey Feet conversion factor 3.28083333333(repeating) should

have been used instead of international feet (3.28084).

Page 18: Use of GIS in Determination of the Probable Maximum Flood at Nuclear Plant Sites Presented by: Monica Anderson, GISP Tennessee Valley Authority Carrie

Questions?Questions?