Project Flow Sales Order Memo: indicates that Order has been
approved and we may move on. Sp. Segm & Regulatory commences activities: Procuring satellite capacity Assist Customer to Obtain License
[email protected] 408.656.2498 2
![Page 3: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/3.jpg)
Space Segment If capacity offered is within our present holdings, all
we need to do is an internal assignment & notification to operator.
If we need to purchase new capacity we contact Panamsat or Satmex, and sometimes Intelsat
If we need to contract teleport services, we place order with vendor
[email protected] 408.656.2498 3
![Page 4: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/4.jpg)
Space Segment Issues System Engineering to define, if not already done at
time of quote: modulation scheme (QPSK vs 8PSK) FEC rate (1/2, 3/4, 2/3, R/S) Choice done based on space segment resource
optimization : bandwidth & power Convenient to have a flexible modem for future
upgrades & possible changes
[email protected] 408.656.2498 4
![Page 5: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/5.jpg)
Space Segment Issues #2 Make sure NOC is involved with circuit start up
process. Need to notify satellite operator of new circuit May need to run antenna patterns (which may take
hours or days!) Coordinate power & frequency use with Operator
[email protected] 408.656.2498 5
![Page 6: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/6.jpg)
Space Segment Questions: If in doubt, please check with NOC first They will usually get assistance from Operator
(satellite signatures, beacon frequencies, “center of the box” times etc
Problems? Please report to Sytems Eng; we will escalate to Operator’s bosses
[email protected] 408.656.2498 6
![Page 7: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/7.jpg)
Regulatory Aspects Except for Mexico (and Venezuela in the future), all we
are doing is ASSISTING customer obtaining its private station license.
Be aware that the process typically takes 3months or so; thus it needs to be triggered at day 0. And followed up by PMs.
[email protected] 408.656.2498 7
![Page 8: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/8.jpg)
Regulatory Comparison Mexico, private station: 30 days Ecuador, private station: 90-120days: process goes
through Two regulatory agencies plus the Armed Forces!
Paraguay: approx 30 days from first submission To submit application….. Stay tuned
[email protected] 408.656.2498 8
![Page 9: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/9.jpg)
To Submit the application The customer needs to provide name of company,
address, point of contact etc. The customer needs to provide documents of
incorporation the enterprise (ie proof of legal existence)
Various administrative and techincal forms need to be filled out.
Provide link budgets, description of the system, equipment specs etc.
[email protected] 408.656.2498 9
![Page 10: V-Sat Project Flow](https://reader038.vdocuments.net/reader038/viewer/2022100600/5565b15ad8b42a083a8b5499/html5/thumbnails/10.jpg)
People Involved New Ops Agreements, correspondent deals,
teleport contracts, Space. Segm. contracts etc: F.N. Permits, interaction with Satmex for new
frequencies, etc: Monica Salazar (Vitamex) Transmission Plans: MS(Solidaridad), G.Duay
(PAS), F.N (overall) Link analysis support: Aaron (Vitamex) Other support: apps engineers
[email protected] 408.656.2498 10