value-based transmission investment and operations...value-based transmission investment and...
TRANSCRIPT
Value-based Transmission Investment and Operations
Marija Ilic [email protected]
Invited Panel, IEEE PES 2014
Washington DC
Outline
• The evolving role of on-line T&D management
• Basic definition of an optimal grid
• Valuing transmission value –an example [1]
• Valuing flexible transmission in systems with intermittent resources [2]
2
[1] Yoon, Y. T., "Electric Power Network Economics: Designing Principles for a For-Profit
Independent Transmission Company and Underlying Architectures for Reliability”, PhD
thesis, June 2001, EECS, MIT (thesis advisor: M. Ilic)
[2] C. Tee and M. Ilic, "Optimal Investment Decisions in Transmission Expansion," in
Proceedings of the 44th North American Power Symposium, Urbana-Champaign, 2012
.
The evolving role of on-line T&D management
• T&D as the enabler of T&D users’ (generation and demand) needs
• Time-varying needs require dynamic adjustments of T&D resources to maximize the ATC for least constraining delivery
• Examples of thermally- and voltage-limited ATC delivery (steady state; non-time critical congestion); key role of T&D grid optimization
• Examples of small signal- and transient stability-limited ATC (dynamic; time critical); key role of automation
• GROWING ROLE OF ON-LINE INFORMATION PROCESSING
Optimal grid for congestion relief
• Hard to design T&D grid ``optimally” because conditions vary; need to rely on T&D management to optimize use of existing asset capacity
• ``optimal grid”—any grid design break-even point between the incremental capital cost and annual cumulative cost of unserved/expensive power delivery
• Becoming possible to utilize T&D assets more ``optimally”; new technologies provide shorter-term solutions/lower risks than large capital investments;
• The challenge—framework to use new technologies; hardware limits (thermal) and systems limits (voltage, stability) can be co-optimized
Transmission Congestion
Bus 1
Bus 2
PL = 100 MW
Marginal Cost = 30 $/MWh Marginal Cost =
10 $/MWh
• Some Causes: • Thermal limit of the line • Voltage drop in the line
Causes of Transmission Congestion: Thermal Limits of Lines
• Determined by the conductor’s material properties and the weather
• The higher the voltage, the greater the thermal limit
• If exceeded, can harm line
Voltage (kV) Rating (MW) With DLRs
230 400 420
345 1200 1270
500 2600 2550
765 5400 5800
1100 24000 24500 [1]
Short-term value of relieving congestion
• Reliability
• Economic Value
Value of New Transmission Capacity = (MC2 – MC1) * Additional Power Flow
Bus 1 Bus 2
PL = 100 MW
Marginal Cost = 30 $/MWh
Marginal Cost = 10 $/MWh
Transmission Limit After Upgrade/ON-LINE DLR
Transmission Limit Before Upgrade
Optimal Grid for Congestion Relief—Value vs Cost
Summary of Charges
In Millions In 100,000
Motivation for valuing flexible transmission in systems with intermittent resources
• Increased variability and intermittency in the power system due to: – Renewable energy integration – Distributed generation and load resources
• Greater variety of technologies that can supplement
conventional AC transmission lines: – Flexible AC Transmission System Devices (FACTS) – Controllable DC Lines
• How do we value the flexibility provided by flexible
transmission devices in making investment decisions?
15
Flexibility in Transmission
• Operational Flexibility: – Is the operational capability of the system flexible enough to
efficiently and effectively manage a variety of short-run system conditions and uncertainties?
• Investment Flexibility
– Is the long-run investment plan for the system flexible enough to efficiently adapt to changes in long-run system conditions and forecasts?
• Institutional Flexibility – Is the regulatory and market framework flexible enough to
accommodate and incentivize a wide variety of currently available and future technology?
16
Overview of Case Studies
• Two key questions answered: – What is the optimal investment in flexible transmission devices
considering the value of short-run operational flexibility? – What is the value of long-run investment flexibility that can be
brought about by flexible transmission devices?
• General framework demonstrated using simple 3-bus examples
• Technology considered: Thyristor-Controlled Series Compensator (TCSC) – Control real power flow in system by changing reactance in the line – Better utilize existing transmission capacity – Case studies demonstrates: Value of TCSC in providing short-run
operational flexibility and long-run investment flexibility
17
INVESTMENTS IN TCSC AND SHORT-RUN OPERATIONAL FLEXIBILITY What is the optimal investment in TCSC considering the value of short-run operational flexibility?
18
Optimal Investment Model (Minimize Operational and
Investment Cost)
(DC Power Flow and
Thermal Line Constraints)
(Line Investment Min)
(Power Balance in System)
(Power Injection Min/Max)
(TCSC Investment Min/Max)
(TCSC Operational Range)
Optimality Conditions for Investments in TCSC:
Marginal Cost of
Investment
Cumulative Sum of
the Additional
Congestion Rent
Brought About by
TCSC
19
Base Case Test System and Parameters
Technology Scaled and Annualized
Investment Cost
New Line Capacity $20 thousand per MW
New TCSC Capacity $20 million per p.u. flexible reactance
Load Profile:
20
Results: Optimal Investments With and Without Wind
Case Optimal Investment Decision
Investment Cost
($ thousand)
Savings in Operational Cost ($ million)
(1) No Wind 22.5 MW of New Line Capacity at Line 2
450 1.6
(2) With Wind
0.0025 pu of Flexible Reactance at Line 1
50 0.12
S
S
COSTG1=
$100/MWh
COSTG2=
$300/MWh
Xbase,1= j0.01 pu
Kbase,1=150MW
S
COSTG3=
$400/MWh
Lower Load
Xbase,2= j0.02 pu
Kbase,2=122.5MW
Xbase,2= j0.03 pu
Kbase,2=100MW
Higher Load
Line 1 Line 2
Line 3
COSTG1=
$100/MWh
S
S
COSTG2=
$300/MWh
Xbase,1= j0.01 pu
Kbase,1=150MW
S
COSTG3=
$400/MWh
Lower Load
Xbase,2= j0.02 pu
Kbase,2=100MW
Xbase,2= j0.03 pu
Kbase,2=100MW
Higher
Load
Line 1
Line 2
Line 3
No wind: With wind:
21
Results: Different Investment Scenarios with Wind Scenarios Optimal Investment
Decision Investment
Cost ($ thousand)
Operational Cost ($ million)
(a) No Investment - - 6.5
(b) New Line Capacity
4.6 MW of New Line Capacity at Line 2
92 6.4
(c) New TCSC/Line Capacity
0.0025 pu of Flexible Reactance at Line 1
50 6.3
Scenarios Percentage of Time Congested (%)
Line 1 Line 2 Line 3
(a) No Investment 1.3 24 0
(b) New Line Capacity 3.7 0 0
(c) New TCSC/Line Capacity 17 25 0
Policy question: Should we redefine what it means to “relieve
congestion”? 22
Conclusion and Future Work • Possible to have a general framework to evaluate how flexible
transmission devices add value to a system particularly in system with high renewable resources
• Future work: – What kind of tools do we need to apply proposed methods to
larger system and models with stochasticity? • Decomposition approaches, dynamic programming with
heuristics, Markov modeling etc. – How do we develop institutional flexibility?
• Market and regulatory design • Centralized vs decentralized planning approaches • Multi-time scale contracts for distributed risk management • What do we really mean when we want to “relieve congestion”?
23