value of megaprojectsthe value of megaprojects introduction infrastructure projects in china...
TRANSCRIPT
1
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
EuroProjexEuroProjex
The Value of MegaprojectsThe Value of Megaprojects
Megaproject: Learning from CasesMegaproject: Learning from CasesLeeds University, 30Leeds University, 30thth November 2012November 2012
Prof Rodney TurnerProf Rodney TurnerAdjunct ProfessorAdjunct Professor
University of Technology SydneyUniversity of Technology Sydney
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
2
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
PS: I am sorry the letter is so long. I didnPS: I am sorry the letter is so long. I didn’’t t have time to write a shorter one.have time to write a shorter one.
Oscar WildeOscar Wilde
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
The Value of MegaprojectsThe Value of Megaprojects
IntroductionIntroductionInfrastructure projects in ChinaInfrastructure projects in China
Megaprojects in the oil and gas industryMegaprojects in the oil and gas industryLeading performance indicators on complex projectsLeading performance indicators on complex projects
3
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
A project is A project is …………
A temporary organizationA temporary organizationto which resources are assignedto which resources are assignedto do workto do workto deliver beneficial changeto deliver beneficial change
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Beneficial change Beneficial change –– project resultsproject resultsExploitationExploitation
ImplementationImplementation
ResourcesResources ProjectProject OutputsOutputs
OutcomesOutcomes
GoalsGoals
BenefitBenefit
ImprovedImprovedperformanceperformance
OperationOperation Do the right Do the right projectproject
Do the projects rightDo the projects right
4
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
The Value of MegaprojectsThe Value of Megaprojects
IntroductionIntroductionInfrastructure projects in ChinaInfrastructure projects in China
Megaprojects in the oil and gas industryMegaprojects in the oil and gas industryLeading performance indicators on complex projectsLeading performance indicators on complex projects
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Chinese economic systemChinese economic system-- 19491949--19771977
Planned economyPlanned economyBrought China from semiBrought China from semi--feudal, semi feudal, semi colonial, war ravaged country to colonial, war ravaged country to industrialized nationindustrialized nationPublic money mainly invested for political or Public money mainly invested for political or military purposesmilitary purposes
not public goodnot public good
5
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Chinese economic systemChinese economic system-- 1978 to present day1978 to present day
Significant progressSignificant progressMore delegated to provincial and municipal More delegated to provincial and municipal governmentgovernmentGDP growth 10% per yearGDP growth 10% per year
fuelled by substantial investment in infrastructurefuelled by substantial investment in infrastructureGDPGDP
45% investment45% investment45% consumption45% consumption10% exports10% exports
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Poor project performancePoor project performance
Project outputs cannot deliver desired Project outputs cannot deliver desired outcomesoutcomesOperating costs not consideredOperating costs not consideredFeasibility study unrealisticFeasibility study unrealisticPoor quality of outputsPoor quality of outputs
6
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Aims and objectivesAims and objectives
How can the public and government in China How can the public and government in China get the best results from key infrastructure get the best results from key infrastructure projects by increasing results orientation?projects by increasing results orientation?
China can realize the maximum benefit from key China can realize the maximum benefit from key projects in the public sector by increasing results projects in the public sector by increasing results orientation and performanceorientation and performancea clear definition of the project organization, with a clear definition of the project organization, with the assignment of responsibility to project the assignment of responsibility to project sponsors and owners, can improve the benefits sponsors and owners, can improve the benefits from key projectsfrom key projects
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
MW Kellogg Logic modelMW Kellogg Logic model
Resources/Inputs Activities Outputs Outcomes Impacts
Planned Work Intended Results
1 42 3 5
Traditional M & E
Results-oriented M & E
7
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults--based M&E on Projectsbased M&E on ProjectsExploitationExploitation
ImplementationImplementation
ResourcesResources ProjectProject OutputsOutputs
OutcomesOutcomes
GoalsGoals
BenefitBenefit
ImprovedImprovedperformanceperformance
OperationOperation Do the right Do the right projectproject
Do the projects rightDo the projects right
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
The project lifeThe project life--cyclecycle
ConceptConcept
FeasibilityFeasibility
DesignDesign
CloseClose--outout
ExploitationExploitation
ExecutionExecution
ResourcesResources ProjectProject OutputsOutputs
OutcomesOutcomes
GoalsGoals
BenefitBenefit
ImprovedImprovedperformanceperformance
OperationOperation
8
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Principles of good governance in the Principles of good governance in the public sectorpublic sector
IntegrityIntegrityact impartially, ethically and in the best interests act impartially, ethically and in the best interests of the publicof the publicdo not misuse informationdo not misuse information
StewardshipStewardshipenhance value of public assetsenhance value of public assets
LeadershipLeadershipgood governance through leadershipgood governance through leadership
EfficiencyEfficiencyoptimal use of resourcesoptimal use of resources
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Principles of good governance in the Principles of good governance in the public sectorpublic sector
AccountabilityAccountabilityanswerable for decisionsanswerable for decisionsadhere to standardsadhere to standards
Transparency, opennessTransparency, opennessclear roles and responsibilitiesclear roles and responsibilitiesclear procedures for exercising powerclear procedures for exercising power
Rule of lawRule of lawabide by the rules of societyabide by the rules of societycontracts, propertycontracts, propertypolice and courtspolice and courts
9
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults--based M&E in the public sectorbased M&E in the public sector
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
OGC project organization structureOGC project organization structure
10
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
PropositionsPropositions
P1: Strategy and objectivesP1: Strategy and objectivesalign project strategy to government strategyalign project strategy to government strategyclear definition of needs and project objectivesclear definition of needs and project objectiveseffective starteffective start--upupportfolio and program managementportfolio and program management
P2: Conceptual planning and designP2: Conceptual planning and designquality of conceptual planningquality of conceptual planningdefinition of project resultsdefinition of project resultsrelationship between results helps align outputs to userelationship between results helps align outputs to usehelps define O&M requirementshelps define O&M requirements
P3: ImplementationP3: Implementationaim for the best resultsaim for the best resultspoor output guarantees poor resultspoor output guarantees poor results
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Propositions (cont)Propositions (cont)
P4: Project transfer, operation and maintenanceP4: Project transfer, operation and maintenancetransfer output and adapt outcome based on transfer output and adapt outcome based on experience of O&Mexperience of O&M
P5: Project organization and ownershipP5: Project organization and ownershipclear ownership of results (at all levels) improves clear ownership of results (at all levels) improves performanceperformancefacilitate coordination between government facilitate coordination between government departmentsdepartments
P6: Transparency and participationP6: Transparency and participationinterest and involvement of owners and managers interest and involvement of owners and managers responsible for O&M during delivery improves responsible for O&M during delivery improves performanceperformance
11
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Water treatment plants in ChinaWater treatment plants in China
Project
Ministry ofHealth
Owner
Sponsor
Manager
LocalGovernment Operator
Finance
Ministry ofFinance
Ministry ofWorks
Ministry ofWater
FormalCommunication
RequiredCommunication
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Propositions (cont)Propositions (cont)
P7: Monitoring and evaluationP7: Monitoring and evaluationresultsresults--based M&E improves successbased M&E improves successdistribute critical reports to responsible partiesdistribute critical reports to responsible parties
P8: Law, regulation and processP8: Law, regulation and processpolitical consensus improves public projectspolitical consensus improves public projectsprofessional project management helpsprofessional project management helps
P9: China contextP9: China contextcoordinate results with contextcoordinate results with contextapply good governanceapply good governance
12
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Nine case study projectsNine case study projects
In designIn designEnergyEnergyGuanxiGuanxi LongtanLongtanHydroelectric Power StationHydroelectric Power Station
In constructionIn constructionTransportationTransportationJiangsuJiangsu SutongSutong Yangtze Yangtze River Highway BridgeRiver Highway Bridge
In constructionIn constructionSocial welfareSocial welfareDisabled Occupation and Disabled Occupation and Skill Sports Training CentreSkill Sports Training Centre
In constructionIn constructionPublic HealthPublic HealthBeijing Beijing YouanYouan HospitalHospital
Operation 1 yearsOperation 1 yearsWater ManagementWater ManagementSichuan Sichuan ZipingpuZipingpu Water Water ConservationConservation
Operation 1 yearsOperation 1 yearsCity infrastructureCity infrastructureLuanhuachiLuanhuachi XiluXilu RoadsRoads
Operation 1 yearsOperation 1 yearsCultureCultureCapital MuseumCapital Museum
Operation 3 yearsOperation 3 yearsUrban environmentUrban environmentYuannanYuannan EnvironmentEnvironment
Operation 3 yearsOperation 3 yearsTransportationTransportationHebeiHebei RoadsRoads
StageStageSectorSectorProjectProject
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Data collectionData collection
Access to project documents and project archival Access to project documents and project archival recordrecordInterviews with the project owner, implementation Interviews with the project owner, implementation agency and operators and usersagency and operators and usersSite visitsSite visitsParticipation in and observation of project meetings, Participation in and observation of project meetings, including progress meetings and post project reviewincluding progress meetings and post project reviewWorkshopsWorkshopsWork groups with the KPIOWork groups with the KPIOOther sources such as World Bank and Asian Other sources such as World Bank and Asian Development Bank specialistsDevelopment Bank specialists
13
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults
Good fit brings valueGood fit brings valueStrongStrongChina contextChina contextP9P9
Safety importantSafety importantMediumMediumLaw, regulation and processLaw, regulation and processP8P8
Reduce postReduce post--implementation justificationimplementation justification
MediumMediumMonitoring and evaluationMonitoring and evaluationP7P7
Problems with people in Problems with people in different departmentsdifferent departments
StrongStrongTransparency and participationTransparency and participationP6P6
Ownership importantOwnership importantStrongStrongProject organization and ownershipProject organization and ownershipP5P5
Due to lack of experienceDue to lack of experienceWeakWeakProject transfer, O&MProject transfer, O&MP4P4
Late changes difficultLate changes difficultMediumMediumImplementationImplementationP3P3
HebeiHebei roads design changedroads design changedStrongStrongConceptual planning and designConceptual planning and designP2P2
Fit multiFit multi--year strategyyear strategyStrongStrongStrategy and objectivesStrategy and objectivesP1P1
CommentCommentSupportSupportPropositionPropositionNoNo
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults--based M&E important through based M&E important through the whole lifethe whole life--cyclecycle
FeasibilityFeasibilityalign project with strategyalign project with strategyset clear objectivesset clear objectives
DesignDesignimproved by good conceptual planningimproved by good conceptual planningset logical relationship of resultsset logical relationship of results
ExecutionExecutiona good output is a necessary condition for successa good output is a necessary condition for success
OperationOperationadapt outcomes based on experienceadapt outcomes based on experiencegood maintenance and changes ensure fitness for purposegood maintenance and changes ensure fitness for purpose
14
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Responsibility and ownershipResponsibility and ownership
Project organization and individual responsibilityProject organization and individual responsibilityclear ownership improves results orientationclear ownership improves results orientationthrough the governance structurethrough the governance structure
Transparency and participationTransparency and participationinterest of the owner in O&Minterest of the owner in O&Mclear information enables parties to accept ownershipclear information enables parties to accept ownership
Monitoring and evaluationMonitoring and evaluationresultsresults--based M&E improves performancebased M&E improves performancecritical reports distributed to key partiescritical reports distributed to key parties
Law, regulation and processLaw, regulation and processenforcement of law and political consensus necessaryenforcement of law and political consensus necessaryuseful that professional project management applieduseful that professional project management applied
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
The Value of MegaprojectsThe Value of Megaprojects
IntroductionIntroductionInfrastructure projects in ChinaInfrastructure projects in China
Megaprojects in the oil and gas industryMegaprojects in the oil and gas industryLeading performance indicators on complex projectsLeading performance indicators on complex projects
15
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Influence managers of megaInfluence managers of mega--projectsprojects
The ability of managers to influence strategy is a The ability of managers to influence strategy is a function of the amount of resource they control not function of the amount of resource they control not their senioritytheir seniorityThe managers of megaThe managers of mega--projects control between $0.5projects control between $0.5--$20 billion.$20 billion.Decisions underpin the allocation of resources and Decisions underpin the allocation of resources and the cost of poor decisions is high.the cost of poor decisions is high.Information is a key input to decision processes.Information is a key input to decision processes.A challenge of megaprojects is inadequate, unreliable A challenge of megaprojects is inadequate, unreliable or misleading information; and conflicts between or misleading information; and conflicts between decision making, policy and planning.decision making, policy and planning.
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Research questionsResearch questions
Which aspects of informationWhich aspects of information--feed factors feed factors supporting project managerssupporting project managers’’ decision impact decision impact strategic objectives the most?strategic objectives the most?How can the decision framework of the How can the decision framework of the managers of megaprojects be enhanced?managers of megaprojects be enhanced?
16
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
IDENTIFYIDENTIFY
InitiationInitiation
ASSESSASSESS
EvaluationEvaluation
OPERATIONOPERATION
Operation &Operation &MaintenanceMaintenance
EXECUTIONEXECUTION
Detail designDetail designconstructconstruct
commissioncommission
DEFINEDEFINE
TechnicalTechnicalSpecifcationSpecifcation
SELECTSELECT
GenerateGenerate& Select& SelectConceptConcept
11 22 33 44
11 Decision gate go/no go/go backDecision gate go/no go/go back
FramedFramedopportunityopportunity
FeasibilityFeasibilityreportreport
ConceptConceptselectionselection
basis forbasis fordesigndesign New assetNew asset
StageStagedeliverabledeliverable
FrontFront--end Engineeringend Engineering ExecutionExecution
Influence of project managersInfluence of project managers
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Focus of megaFocus of mega--project managersproject managers
Megaprojects are complex:Megaprojects are complex:long project and product lifelong project and product life--cyclescyclesunpredictable in terms of time and scopeunpredictable in terms of time and scopesubstantial irreversible commitmentssubstantial irreversible commitmentshigh probabilities of failurehigh probabilities of failureskewed reward structure skewed reward structure
The focus of managers of megaprojects The focus of managers of megaprojects should be on strategic objectives and business should be on strategic objectives and business benefit not project efficiency.benefit not project efficiency.
17
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults--based viewbased viewExploitationExploitation
ImplementationImplementation
ResourcesResources ProjectProject OutputsOutputs
OutcomesOutcomes
GoalsGoals
BenefitBenefit
ImprovedImprovedperformanceperformance
OperationOperation
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Shenhar and Dvir (2007)Shenhar and Dvir (2007)
EfficiencyEfficiency(end)(end)TimeTimeCostCostYieldYield
functionalityfunctionalityperformanceperformance
OthersOthers
TeamTeam(end)(end)SatisfactionSatisfactionMoraleMoraleLearningLearningGrowthGrowthRetentionRetentionWellWell--beingbeing
CustomerCustomer(+months)(+months)RequirementsRequirementsSpecificationSpecificationBenefitBenefitUseUseARMARMSatisfactionSatisfactionLoyaltyLoyaltyBrandBrand
BusinessBusiness(+years)(+years)SalesSalesProfitsProfitsMarket shareMarket shareROIROICashCashCycle timeCycle timeOrganizationOrganizationRegulatory Regulatory acceptanceacceptance
FutureFuture (Learning)(Learning)(+years)(+years)NewNew
technologytechnologymarketmarketproduct lineproduct linecompetencecompetencecapabilitycapability
18
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Challenges of megaprojectsChallenges of megaprojects
Numerous stakeholdersNumerous stakeholdershigh sociohigh socio--economic and political interesteconomic and political interest
High time and cost pressureHigh time and cost pressurecan impair decisionscan impair decisionsproject efficiency versus business effectivenessproject efficiency versus business effectiveness
Decisions influenceDecisions influenceteam performanceteam performancesenior management perceptionsenior management perception
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Strategic value in the Oil and Gas Strategic value in the Oil and Gas IndustryIndustry
Admiration of key stakeholdersAdmiration of key stakeholdersHealth, safety, security and environmental Health, safety, security and environmental responsibility (HSSE)responsibility (HSSE)Significant socioSignificant socio--economic contribution to the economic contribution to the societysocietyProfitability of the businessProfitability of the business
19
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Normative decision approachNormative decision approach
People make decisions to maximize utility People make decisions to maximize utility based on selfbased on self--interest and rationalityinterest and rationality
restricts ability to respond to uncertaintyrestricts ability to respond to uncertaintyoil and gas industry dominated by technical oil and gas industry dominated by technical people who adopt a normative approachpeople who adopt a normative approach
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Descriptive decision approachDescriptive decision approach
People make decisions to satisfy their People make decisions to satisfy their important needs important needs
even if they do not have all the required even if they do not have all the required informationinformationtheir choice is not optimal their choice is not optimal
Faced with uncertainty people simplifyFaced with uncertainty people simplifyrules of thumb/heuristicsrules of thumb/heuristicsbounded rationality/satisfyingbounded rationality/satisfyingprospect theoryprospect theory
20
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Prospect theoryProspect theory
Decision making under riskDecision making under riskFramingFraming
analysis of prospectsanalysis of prospectssimplification of riskssimplification of risks
ValuationValuationassess value of prospectsassess value of prospectsopportunityopportunity--threat/gainthreat/gain--lossloss
During framing information feed has a big impactDuring framing information feed has a big impactuntimely information is degradeduntimely information is degraded
DecisionDecision--makers who use more informationmakers who use more informationare more comfortable with ambiguity and uncertaintyare more comfortable with ambiguity and uncertaintyare more positive with labelling their challengesare more positive with labelling their challenges
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
InformationInformation--feedfeed LongLong--termtermstrategic valuestrategic value
PMPM’’s perceptions perceptionof controllabilityof controllability
H2H2
H1H1
••PMPM’’s perceptions perceptionof needs of seniorof needs of senior
managementmanagement••PMPM’’s professionals professional
experienceexperience
H3H3
Research modelResearch model
21
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
VariablesVariables
Information feedInformation feedinformation on stakeholdersinformation on stakeholdersproject performanceproject performancecorporate performancecorporate performanceinformation timelinessinformation timeliness
Strategic valueStrategic valuevalue to partnersvalue to partnersHSSE complianceHSSE complianceprofitabilityprofitabilityvalue to host communityvalue to host community
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Variables Variables -- ControllabilityControllability
10 areas of challenge on megaprojects10 areas of challenge on megaprojects1.1. Contracting and procurement management; Contracting and procurement management; 2.2. Government relations Government relations 3.3. Host community relation Host community relation 4.4. Joint venture interfaces Joint venture interfaces 5.5. Health, safety, security, and environmental (HSSE)Health, safety, security, and environmental (HSSE)6.6. MultiMulti--location of fabrication and facilities location of fabrication and facilities
integrationintegration7.7. Implementation of local content policiesImplementation of local content policies8.8. Project governance;Project governance;9.9. Aspirations of the core project team Aspirations of the core project team 10.10. MultiMulti--cultural leadershipcultural leadership
22
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Variables Variables -- contextcontext
PMsPMs perception of senior management perception of senior management driversdrivers
costcostscheduleschedulestakeholdersstakeholderssafetysafetyeconomicseconomics…………
PMsPMs experience (tenure)experience (tenure)
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
SurveySurvey
107 total responses107 total responses8 not from the Oil and Gas Industry8 not from the Oil and Gas Industry30 did not complete the questionnaire30 did not complete the questionnaire
69 useable responses69 useable responses11 responses per variable11 responses per variable
5 pilot responses also not used5 pilot responses also not used
23
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Information feed and strategyInformation feed and strategy
1 = p<0.11 = p<0.12 = p<0.052 = p<0.05
3 = p<0.013 = p<0.014 = p<0.0014 = p<0.001
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Hypothesis 1Hypothesis 1
Hypothesis 1 is supported with respect to Hypothesis 1 is supported with respect to stakeholder pulsestakeholder pulseproject performance project performance
Hypothesis 1 is not supported with respect toHypothesis 1 is not supported with respect tocorporate performancecorporate performancetimeliness timeliness
Strong interaction of megaStrong interaction of mega--projects on societyprojects on societycontext analysis is very important to successful context analysis is very important to successful strategic management in business organizationsstrategic management in business organizations
24
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Controllability and information feedControllability and information feed
1 = p<0.11 = p<0.12 = p<0.052 = p<0.05
3 = p<0.013 = p<0.014 = p<0.0014 = p<0.001
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Scores for controllabilityScores for controllability
25
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Hypothesis 2Hypothesis 2
Hypothesis 2 supportedHypothesis 2 supportedAll means (except team cohesion) less than 3All means (except team cohesion) less than 3
PMsPMs of megaof mega--projects feel exposed to risksprojects feel exposed to risks3 risk factors are external to the project team3 risk factors are external to the project team
quality of relationships with context is a major quality of relationships with context is a major success factor on large projectssuccess factor on large projects
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Influence of contextInfluence of context
P = Pure moderatorP = Pure moderatorQ = Quasi moderatorQ = Quasi moderator
PO = Profitable operationsPO = Profitable operationsSS = Stakeholder supportSS = Stakeholder supportPS = Project schedulePS = Project schedule
26
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Hypothesis 3Hypothesis 3
Hypothesis 3 Hypothesis 3 isis supported for some senior supported for some senior management driversmanagement driversHypothesis 3 is not supported for PM tenureHypothesis 3 is not supported for PM tenure
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ConclusionConclusion
Poor knowledge of the external environment has a Poor knowledge of the external environment has a significant impact on poor performance of megasignificant impact on poor performance of mega--projectsprojectsRisk mitigation on megaRisk mitigation on mega--projects significantly projects significantly influences information feedinfluences information feed
a superior risk management system enhances the a superior risk management system enhances the PMsPMs sense sense of controlof control
The significance project managers attach to HSSE as a The significance project managers attach to HSSE as a core value is indicative of a fear of losscore value is indicative of a fear of loss
they have greater fear of defaulting on cost and schedule they have greater fear of defaulting on cost and schedule than on HSSE. than on HSSE.
27
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
The Value of MegaprojectsThe Value of Megaprojects
IntroductionIntroductionInfrastructure projects in ChinaInfrastructure projects in China
Megaprojects in the oil and gas industryMegaprojects in the oil and gas industryLeading performance indicators on complex projectsLeading performance indicators on complex projects
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Early Warning System for Success Early Warning System for Success and Failure in Complex Projectsand Failure in Complex Projects
Associate Professor Roxanne ZolinQueensland University of TechnologyProfessor Rodney Turner, SKEMA Business SchoolDr. Kaye Remington, Research Fellow, University of Technology SydneyDr. Artemis Chang, Senior Lecturer,Queensland University of Technology
28
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Increasing complexity of projectsIncreasing complexity of projects
Projects finished late and overspent are later Projects finished late and overspent are later perceived to be a successperceived to be a success
Sydney Opera House, Thames BarrierSydney Opera House, Thames BarrierOthers finished on time and on budget are Others finished on time and on budget are later perceived to have failedlater perceived to have failed
Sydney Cross City TunnelSydney Cross City TunnelPPP project where the private sector investors lost their PPP project where the private sector investors lost their moneymoneybecause motorists were not willing to pay the toll and because motorists were not willing to pay the toll and use the tunneluse the tunnel
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Our research projectOur research project
The aim was to identify leading performance The aim was to identify leading performance indicators as early warning systemsindicators as early warning systems
modelling successmodelling successassessing complexityassessing complexity
dimensionsdimensionsseverity of the dimensionsseverity of the dimensions
impact of dimensions of complexity of complexity impact of dimensions of complexity of complexity on successon success
In this paper we describe the modelling of In this paper we describe the modelling of successsuccess
29
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Leading performance indicators may Leading performance indicators may be be …………
Measures of success criteria that show the Measures of success criteria that show the projects is heading to a successful conclusionprojects is heading to a successful conclusionMeasures of success (or failure factors) that Measures of success (or failure factors) that show the project is going off the railsshow the project is going off the rails
may interact with each othermay interact with each othermay interact with dimensions of complexitymay interact with dimensions of complexity
Be perceived differently by differently Be perceived differently by differently stakeholdersstakeholdersBe perceived differently over different Be perceived differently over different timescalestimescales
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Research questionsResearch questions
How can we assess the success of large complex How can we assess the success of large complex projectsprojects
multiple stakeholdersmultiple stakeholdersmultiple time framesmultiple time framesduring the life of the projectduring the life of the projectto predict the performance of the product it producesto predict the performance of the product it produces
What leading performance indicatorsWhat leading performance indicatorsmeasured during project deliverymeasured during project deliveryprovide a valid and reliable forecast of the assessment of all provide a valid and reliable forecast of the assessment of all the stakeholders during the productthe stakeholders during the product’’s lifes life
Can the leading performance indicators be used as Can the leading performance indicators be used as early warning systemsearly warning systems
30
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Stages of the researchStages of the research
1.1. Develop a model of project success reflecting the assessment Develop a model of project success reflecting the assessment of the projectof the project’’s output,. outcome and impact by different s output,. outcome and impact by different stakeholders over different timescalesstakeholders over different timescales
2.2. Evaluate the ability of success and failure factors as perceivedEvaluate the ability of success and failure factors as perceivedby the project team to act as leading performance indicators by the project team to act as leading performance indicators during project deliveryduring project delivery
3.3. Evaluate the ability of those leading performance indictors to Evaluate the ability of those leading performance indictors to predict the achievement of the projects output, outcome and predict the achievement of the projects output, outcome and impact as perceived by different stakeholders over different impact as perceived by different stakeholders over different timescalestimescales
4.4. Identify combinations of the leading performance indicators in Identify combinations of the leading performance indicators in the context of different combinations of complexity that are the context of different combinations of complexity that are more likely to be precursors of project failuremore likely to be precursors of project failure
1.1. Develop a model of project success reflecting the assessment Develop a model of project success reflecting the assessment of the projectof the project’’s output,. outcome and impact by different s output,. outcome and impact by different stakeholders over different timescalesstakeholders over different timescales
2.2. Evaluate the ability of success and failure factors as perceivedEvaluate the ability of success and failure factors as perceivedby the project team to act as leading performance indicators by the project team to act as leading performance indicators during project deliveryduring project delivery
3.3. Evaluate the ability of those leading performance indictors to Evaluate the ability of those leading performance indictors to predict the achievement of the projects output, outcome and predict the achievement of the projects output, outcome and impact as perceived by different stakeholders over different impact as perceived by different stakeholders over different timescalestimescales
4.4. Identify combinations of the leading performance indicators in Identify combinations of the leading performance indicators in the context of different combinations of complexity that are the context of different combinations of complexity that are more likely to be precursors of project failuremore likely to be precursors of project failure
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Turner (2009, 1Turner (2009, 1stst ed 1993) ed 1993)
MeasureMeasure StakeholderStakeholder TimescaleTimescaleShareholder valueShareholder value ShareholdersShareholders End+yearsEnd+yearsProfitableProfitable BoardBoard End+yearsEnd+yearsHappy sponsorHappy sponsor BoardBoard End+yearsEnd+yearsHappy consumersHappy consumers ConsumersConsumers End+monthsEnd+monthsEasy to operateEasy to operate UsersUsers End+monthsEnd+monthsEasy to sellEasy to sell MarketingMarketing End+monthsEnd+monthsTime, cost, qualityTime, cost, quality AllAll EndEndHappy project teamHappy project team Project teamProject team EndEndProfitable for contractorProfitable for contractor Project teamProject team EndEnd
31
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Shenhar and DvirShenhar and Dvir
EfficiencyEfficiency(end)(end)TimeTimeCostCostYieldYield
functionalityfunctionalityperformanceperformance
OthersOthers
TeamTeam(end)(end)SatisfactionSatisfactionMoraleMoraleLearningLearningGrowthGrowthRetentionRetentionWellWell--beingbeing
CustomerCustomer(+months)(+months)RequirementsRequirementsSpecificationSpecificationBenefitBenefitUseUseARMARMSatisfactionSatisfactionLoyaltyLoyaltyBrandBrand
BusinessBusiness(+years)(+years)SalesSalesProfitsProfitsMarket shareMarket shareROIROICashCashCycle timeCycle timeOrganizationOrganizationRegulatory Regulatory acceptanceacceptance
FutureFuture (Learning)(Learning)(+years)(+years)NewNew
technologytechnologymarketmarketproduct lineproduct linecompetencecompetencecapabilitycapability
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
XueXue YanYan (2010) (2010) ––sponsored by the Asian Development Banksponsored by the Asian Development Bank
ExploitationExploitation
ImplementationImplementation
ResourcesResources ProjectProject OutputsOutputs
OutcomesOutcomes
GoalsGoals
BenefitBenefit
ImprovedImprovedperformanceperformance
OperationOperation
32
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Multiple views, multiple stakeholders, Multiple views, multiple stakeholders, multiple timemultiple time--framesframes
StakeholdersStakeholdersInvestorInvestor
ConsumerConsumer
OperatorsOperators
SponsorSponsor
Manager/teamManager/team
Senior supplierSenior supplier
SuppliersSuppliers
PublicPublic
OutputOutput -- endendEfficiencyEfficiency
Price, timePrice, timeFeaturesFeaturesDocumentationDocumentationTrainingTrainingEfficiencyEfficiencyRisk, safetyRisk, safetyEfficiencyEfficiencyExperienceExperienceEfficiencyEfficiencyProfitProfitProfitProfitClient satisfactionClient satisfactionEnvironmentEnvironment
OutcomeOutcome -- +months+monthsProfitProfitReputationReputationPricePriceBenefitBenefitOperabilityOperabilityARMARMRelationshipsRelationshipsInvestor loyaltyInvestor loyaltyReputationReputationRepeat businessRepeat businessReputationReputationRepeat businessRepeat businessReputationReputationRepeat businessRepeat businessEnvironmentEnvironmentSocial cost/benefitSocial cost/benefit
ImpactImpact -- +years+yearsWhole life valueWhole life valueLearningLearningAdvantageAdvantageDevelopmentDevelopmentOperability, ARMOperability, ARMLearningLearningNew projectsNew projectsLearningLearningNew projectsNew projectsLearningLearningNew projectsNew projectsLearningLearningNew projectsNew projectsLearningLearningEnvironmentEnvironmentSocial cost/benefitSocial cost/benefit
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Evaluating and predicting successEvaluating and predicting success
Success can only be evaluated in the days months Success can only be evaluated in the days months and years following the projectand years following the project
different stakeholdersdifferent stakeholdersdifferent timescalesdifferent timescales
The aim is to develop leading performance indicators The aim is to develop leading performance indicators that predict the likelihood of achieving later that predict the likelihood of achieving later assessments of successassessments of success
monitor and adjust the performance of the project team, monitor and adjust the performance of the project team, contractors and subcontractors and sub--contractorscontractorsidentify as soon as possible that the project cannot be identify as soon as possible that the project cannot be achieved within the resources the stakeholders are willing to achieved within the resources the stakeholders are willing to commitcommitand cancel the project if necessaryand cancel the project if necessary
33
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Possible success factors and leading Possible success factors and leading performance indicators (LPI)performance indicators (LPI)
StakeholdersStakeholdersInvestorInvestor
ConsumerConsumer
OperatorsOperators
SponsorSponsor
Manager/teamManager/team
Senior supplierSenior supplier
SuppliersSuppliers
PublicPublic
Success factorsSuccess factorsClear accepted purposeClear accepted purposeEndorsement, interestEndorsement, interestClear specificationClear specificationCommunication, acceptanceCommunication, acceptanceClear specificationClear specificationCommitment, communicationCommitment, communicationOpen communicationOpen communicationPolitical supportPolitical supportClear accepted purpose Clear accepted purpose Respect, trust, risk awarenessRespect, trust, risk awarenessRisk awareness, communicationRisk awareness, communicationRespect, trustRespect, trustCommitment, communicationCommitment, communicationRespect, trust, collaborationRespect, trust, collaborationTransparency, accountabilityTransparency, accountabilityCommunity outreachCommunity outreach
LPILPISatisfaction with specificationSatisfaction with specificationRelationship with contractorRelationship with contractorSatisfaction with specificationSatisfaction with specificationRelationship with sponsorRelationship with sponsorSatisfaction with specificationSatisfaction with specificationPrototype performancePrototype performanceStakeholder satisfactionStakeholder satisfactionClear strategic goalsClear strategic goalsPride, satisfaction, growthPride, satisfaction, growthTop management supportTop management supportRisk, HSE, stakeholdersRisk, HSE, stakeholdersContract, strategic goals, learningContract, strategic goals, learningContract complianceContract complianceBusiness goalsBusiness goalsSocial impactsSocial impactsEnvironmental impactsEnvironmental impacts
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Based on the work of Based on the work of …………
Jacobson and Jacobson and ChoiChoi, 2008, 2008Andersen et al, 2006Andersen et al, 2006Kang and Moe, 2008Kang and Moe, 2008MMüüller, 2003ller, 2003Pinto and Pinto and SlevinSlevin, 1988, 1988MMüüller & Turner, 2007ller & Turner, 2007
Turner, 2009Turner, 2009Yu et al, 2005Yu et al, 2005Atkinson, 1999Atkinson, 1999BrydeBryde, 2005, 2005Turner et al, 2008Turner et al, 2008
34
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Scale development processScale development process
DeVellisDeVellis (2003) eight step guidelines for scale (2003) eight step guidelines for scale developmentdevelopment
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Pilot StudyPilot Study
Ascertain reliability and appropriateness of Ascertain reliability and appropriateness of survey questionssurvey questions8 DMO project managers or program 8 DMO project managers or program directorsdirectors
by telephoneby telephoneRevised questionnaireRevised questionnaire
final check by senior DMO stafffinal check by senior DMO staff
35
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Main studyMain study
ZoomerangZoomerangProject managers and program directors Project managers and program directors from DMOfrom DMO
237 invited to participate237 invited to participate152 responses152 responses64% response rate64% response rate50 air projects50 air projects31 land projects31 land projects31 sea projects31 sea projects40 joint responses40 joint responses
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Factor analysisFactor analysis
Ascertain construct validity and reliabilityAscertain construct validity and reliabilitydrop from scale questions whichdrop from scale questions which
detract from detract from ChronbackChronback’’ss alphaalphado not load optimally on scaledo not load optimally on scale’’s s factorfactor
Rotated Rotated VarimaxVarimaxeigeneigen values greater than 1values greater than 1converged in 11 iterationsconverged in 11 iterationsrepeated repeated ChronbachChronbach’’ss alpha testalpha test
36
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ResultsResults
Two project success factor scalesTwo project success factor scales1.1. success in planningsuccess in planning2.2. stakeholder engagementstakeholder engagement
Seven stakeholder satisfaction scalesSeven stakeholder satisfaction scales1.1. stakeholder satisfactionstakeholder satisfaction2.2. supplier profitabilitysupplier profitability3.3. contractor satisfactioncontractor satisfaction4.4. product efficiencyproduct efficiency5.5. project executive satisfactionproject executive satisfaction6.6. satisfaction with specificationssatisfaction with specifications7.7. public stakeholder satisfactionpublic stakeholder satisfaction
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
P1: Success in planningP1: Success in planning
Well established information and Well established information and communication routinescommunication routinesKey information gathered and distributed Key information gathered and distributed efficientlyefficientlyProject control follows good managerial and Project control follows good managerial and technical methodstechnical methodsProject tools used in an effective wayProject tools used in an effective wayProject is well described and well coordinated Project is well described and well coordinated with other projects and programswith other projects and programs
37
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
P2: Stakeholder engagementP2: Stakeholder engagement
Key participants engaged in producing the Key participants engaged in producing the business plan and could influence itbusiness plan and could influence itKey participants given the opportunity to air Key participants given the opportunity to air their views on the projecttheir views on the project’’s goal and missions goal and missionKey participants know who has decided the Key participants know who has decided the project's terms of referenceproject's terms of reference
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S1: Stakeholder satisfactionS1: Stakeholder satisfaction
Good relationship with prime contractorGood relationship with prime contractorGood performanceGood performanceAppropriate earned valueAppropriate earned valueProject executive or sponsor profitsProject executive or sponsor profitsAchieved stakeholder satisfactionAchieved stakeholder satisfactionSenior supplier achieves appropriate business goalsSenior supplier achieves appropriate business goalsOther supplier achieves appropriate business goalsOther supplier achieves appropriate business goalsGood safety recordGood safety record
38
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S2: Product satisfactionS2: Product satisfaction
Useful prototypeUseful prototypeGood performanceGood performance
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S3: Contractor satisfactionS3: Contractor satisfaction
Achieved stakeholder satisfactionAchieved stakeholder satisfactionAchieved performance effectivenessAchieved performance effectivenessReduced wasteReduced wasteDemonstrated contract complianceDemonstrated contract compliance
39
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S4: Product efficiencyS4: Product efficiency
Useful prototypeUseful prototypeAchieved performance efficiencyAchieved performance efficiencyManaged risk appropriatelyManaged risk appropriatelyGood performanceGood performance
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S5: Project executive satisfaction S5: Project executive satisfaction
Achieved stakeholder satisfactionAchieved stakeholder satisfactionAchieved performance efficiencyAchieved performance efficiencyAchieved performance effectivenessAchieved performance effectivenessHelps executive achieve their goalsHelps executive achieve their goalsHas stakeholder satisfactionHas stakeholder satisfaction
40
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S6: Satisfaction with specificationsS6: Satisfaction with specifications
Appropriate specificationsAppropriate specificationsGood relationship with the project ownerGood relationship with the project owner
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S7: Public stakeholder satisfactionS7: Public stakeholder satisfaction
Balanced social costs and benefitsBalanced social costs and benefitsAcceptable environmental impactsAcceptable environmental impacts
41
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S8: Supplier profitabilityS8: Supplier profitability
Achieved performance efficiencyAchieved performance efficiencyAllowed supplier to profitAllowed supplier to profit
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
S9: Project manager satisfactionS9: Project manager satisfaction
Pride in workPride in workJob satisfactionJob satisfactionRecognitionRecognitionSkilSkil growthgrowthContactsContactsHigh moraleHigh moraleAttracts top management supportAttracts top management support
42
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Performance indictorsPerformance indictors
1.1. Clear specificationClear specification2.2. Clear purposeClear purpose3.3. Accepted purposeAccepted purpose4.4. Appropriate L1 planAppropriate L1 plan5.5. Appropriate planAppropriate plan6.6. Open communicationOpen communication7.7. Stakeholder endorsementStakeholder endorsement8.8. Interested ownersInterested owners9.9. Appropriate specificationAppropriate specification10.10. Effective communicationEffective communication
11.11. Efficient decision makingEfficient decision making12.12. Contractor relationshipContractor relationship13.13. Useful prototypeUseful prototype14.14. Good performanceGood performance15.15. Met earned value targetsMet earned value targets16.16. Right execution costsRight execution costs17.17. Environmental standardsEnvironmental standards18.18. Met safety standardsMet safety standards19.19. Relationship with ownerRelationship with owner20.20. Consistent safety recordConsistent safety record
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
KippendorffKippendorff’’ss alphaalpha
0.7000.700--0.7990.7990.8000.800--0.8990.8990.9000.900--1.0001.000
Appropriate for exploratory studiesAppropriate for exploratory studiesMostly acceptableMostly acceptableNearly always acceptableNearly always acceptable
43
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Alignment of the project managers Alignment of the project managers views with views with …………
The ownerThe ownergood performance (good performance (αα=.7367 =.7367 -- low)low)environmental standards (environmental standards (αα=.8255 =.8255 –– medium)medium)safety standards (safety standards (αα=.7301 =.7301 -- low)low)
The consumerThe consumerconsumersconsumers’’ acceptance (acceptance (αα=.7258 =.7258 –– low))low))
The project executivesThe project executivesgood risk awareness (good risk awareness (αα=.7070 =.7070 -- low)low)managed risk (managed risk (αα=.8648 =.8648 -- medium)medium)consistent safety record (consistent safety record (αα=.7576 =.7576 -- low) low)
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
Alignment of the project managers Alignment of the project managers views with views with …………
The lead/prime contractorThe lead/prime contractorlead contractor made a profit (lead contractor made a profit (αα=.8355 =.8355 -- medium)medium)
Other contractorsOther contractorsgood relationship with prime contractor (good relationship with prime contractor (αα=.8673 =.8673 --medium)medium)clear specification (clear specification (αα=.8157 =.8157 -- medium)medium)trusted (trusted (αα=.7282 =.7282 -- low)low)
Operators/usersOperators/usersnothingnothing
PublicPublicnothingnothing
44
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
What a sorry tale!!!What a sorry tale!!!
Interest is in more what is missing than what Interest is in more what is missing than what is thereis there
EuroProjexEuroProjex [email protected]© jrt/gpbo/jul08
ThatThat’’s All Folkss All Folks
[email protected]@[email protected]@skema.edu