March 28, 2017 VIA INTERNET POSTING
3 Pages + 1 Attachment
ADDENDUM NO. 2
Request for Quotation No. 9115-17-5025
Re: Material Testing for Six-Points Interchange Project
REVISED CLOSING DATE: April 3, 2017, 12:00 O'CLOCK NOON (LOCAL TIME)
Please refer to the above Request for Quotation in your possession and be advised of the
following revisions.
I. REVISIONS
The pricing pages have been revised. Bidders must use the revised pricing pages dated March
28, 2017, failure to use the revised pricing form pages will result in your quotation being
declared non-compliant.
II. ATTACHMENTS
i. Revised Pricing Form – Addendum 2 (March 28, 2017)
III. QUESTIONS AND ANSWERS
Q1. Price Form Item 19: What is the test procedure or reference?
A1. Refer to the attached revised Price Form (Appendix C).
Q2. Price Form Item 22: What is the required hole diameter?
A2. The core hole diameter shall be greater or equal to 37.5 mm. Refer to the revised Price
Form (Appendix C).
Q3. Price Form Item 42: What are the test parameters?
A3. Refer to the revised Price Form (Appendix C).
Q4. Price Form Item 66: Is the contingency supposed to be $70,000.00 or $75,000.00?
A4. The contingency amount is $75,000.00. Refer to the revised Price Form (Appendix C).
Q5. Can the City please clarify if the Bidders can utilize sub-consultants in order to comply
with the following required qualifications listed in Section 6.7 Bidder Qualifications:
1 of 10
o Visual Inspectors must have a minimum Level II, CSA Standard W178.2
o Ultrasonic testing personnel must be certified under CAN/CGSB 48.9712-
2000, Qualification and Certification of Non-Destructive Testing Personnel,
Level II, Option A.
o Certified by the Canadian Welding Bureau to the requirements of CSA
Standard W178.1 (Certification of Welding Inspection Organizations) by the
specified Test Method.
A5. Yes, the Bidder may utilize sub-consultants to meet the required qualifications.
Q6. Will the City allow for an annual increase in the unit prices within the 5 year term?
A6. The unit price shall be fixed for the duration of the assignment up to the completion
date of the project. The City will consider requests for unit price adjustment, should the
duration of the project extend beyond the proposed schedule due to delays beyond the
Consultant’s control. The unit price adjustment shall not exceed the average consumer
price index for Toronto, Ontario for the year previous to the start of the extension. Unit
price adjustment will not be considered for delays caused by the Consultant or its sub-
consultant.
Q7. As the Ontario Association of Certified Engineering Technicians and Technologists
(OACETT) does not govern/implement any of the required certification programs, will
the City consider waiving its requirement for OACETT certifications for the testing
technicians?
A7. Yes, the requirement for OACETT is waived.
Q8. We would like to verify if Items 5 and 6 of Appendix “C” Price Form - cover site visit,
sampling, testing and mix design review. These are the descriptions provided in the Price
Form;
“5 – Visit plant, retrieve batch sample test and review the asphalt mix design
prior to commencement of contract work. Refer to Note 1.”
“6 – Visit concrete batching plant, check concrete mix design, test proportion and
materials, including casting and testing of concrete cylinders. Refer to Note 1. “
A8. Refer to the attached revised Price Form (Appendix C).
NOTE: Bidders are reminded that the following statement appears on the Request for
Quotation Form:
“I/WE ACKNOWLEDGE THE RECEIPT OF ADDENDUM
NO____TO____DATED____TO____.
THIS FORM MUST BE COMPLETED, SIGNED AND RECEIVED ON OR BEFORE
THE DATE AND TIME SPECIFIED, OR YOUR QUOTATION WILL NOT BE
CONSIDERED”.
2 of 10
As such, bidders are required to acknowledge all addenda in the space(s) provided on the
Request for Quotation Form or your quotation will not be considered.
Should you have any questions regarding this addendum, contact Marianne Gonzalez Angulo at
Yours truly
Joanne Kehoe
Manager, Construction Services
3 of 10
March 28, 2017 Addendum 2
APPENDIX “C” REVISED PRICE FORM – ADDENDUM 1 (MARCH 28, 2017)
UNIT PRICES QUOTED SHALL INCLUDE Supply of labour, equipment and materials necessary for Material Specification Compliance Tests and Project Quality Assurance services for the Six Points Interchange Reconfiguration Project. EXCLUDING HARMONIZED SALES TAX (HST)
IN THE EVENT OF MATHEMATICAL ERRORS FOUND IN THE PRICING PAGES, THE UNIT PRICES
QUOTED SHALL PREVAIL. EXTENSIONS AND TOTALS WILL BE CORRECTED ACCORDINGLY AND
ADJUSTMENTS RESULTING FROM THE CORRECTION WILL BE APPLIED TO THE TOTAL PRICE
QUOTED.
Item
No.
Description Estimated
Quantity
Unit Price Extended Price
(Estimated Quantity x
Unit Price)
Site Visits and Travel (A)
1
Standby time for field technician at the
request of City.
1000 hours
$ _______/hour
$ ___________
2
Hourly rates for field technician over 12
hours per day Monday – Friday. Refer to
Note 2.
800 hours
$ _______/hour
$ ___________
3
Hourly rates for field technician on
weekends or statutory holidays. Refer to
Note 2.
1200 hours
$ _______/hour
$ ___________
4
Mileage paid at 0.52 cents per kilometer for
sampling at plants or locations outside of the
project locations. Provisional Sum
9600 Km
0.52 / Km
$ 4992.00
Batch Testing and Mix Design Review (B)
5
Visit asphalt plant, retrieve batch sample,
test and compare with the reviewed asphalt
mix design prior to commencement of
contract work. Refer to Note 1.
12 each
$ _______/each
$ ___________
6
Visit concrete batching plant, test proportion
and material, including casting and testing
of concrete cylinders, and compare with the
reviewed concrete mix design.
Refer to Note 1.
12 each
$ _______/each
$ ___________
7
Visit granular material supplier, recover
material sample, and deliver to laboratory,
perform gradation analysis and modified
proctor test. Refer to Note 1.
24 each
$ _______/each
$ ___________
8
Review Asphalt Mix design prepared by
others to verify compliance with City
specifications and procedures outlined in
City Specification TS 1101, TS 1150 and
provide comments. Includes all engineering
and administrative costs, report writing and
report submission.
12 each
$ _______/each
$ ___________
4 of 10
March 28, 2017 Addendum 2
9
Review Concrete Mix design prepared by
others to verify compliance with City
specifications and procedures outlined in
City Specification TS 1350, TS 13.10 and
provide comments. Includes all engineering
and administrative costs, report writing and
report submission.
12 each
$ _______/each
$ ___________
Asphalt Sampling / Testing (C)
10
Retrieve asphalt sample from Project site
during paving operation, (plate samples or
MTO specified sampling methods). Refer to
Note 2.
108 each
$ _______/each
$ ___________
11
Full Marshall compliance check (stability,
flow, Air voids and voids mineral
aggregate) with 3 briquettes. Includes cost
of emailing and faxing preliminary report
and writing/submission of written report.
40 each
$ _______/each
$ ___________
12
Extraction and gradation compliance check
of asphalt sample (washed and unwashed).
Includes cost of performing testing and
sending preliminary results by telephone
and email and fax for unwashed sample
within two (2) hours of sampling and for
washed sample within five (5) hours of
sampling.
26 each
$ _______/each
$ ___________
13
Recovered penetration test (Abson recovery,
penetration and viscosity). Includes cost of
faxing and emailing preliminary results and
writing/submission of report.
9 each
$ _______/each
$ ___________
14
PGAC binder grade verification
9 each
$ _______/each
$ ___________
15
Determination of the ash content of asphalt
cement and asphalt emulsions as per MTO
Laboratory Testing Manual LS-227.
3 each
$ _______/each
$ ___________
16
Determination of asphalt cement’s
resistance to ductile failure using double
edge notched tension test (dent) as per MTO
Laboratory Testing Manual LS-299.
3 each
$ _______/each
$ ___________
17
Determination of performance grade of
physically aged asphalt cement using
extended bending beam rheometer (BBR)
method as per MTO Laboratory Testing
Manual LS-308.
2 each
$ _______/each
$ ___________
18
Multiple Stress Creep Recovery (MSCR)
Test Of Asphalt Binder Using A Dynamic
Shear Rheometer (DSR) as per AASHTO T
350.
6 each
$ _______/each
$ ___________
5 of 10
March 28, 2017 Addendum 2
19 Tack coat testing (TS 3.20), including
sampling, pick up, travel expenses and
laboratory testing and reporting.
9 each $ _______/each $ ___________
Field Sampling (D)
20
Field air entrainment and slump tests on
fresh concrete. Includes cost of leaving copy
of results on-site and mailing of report with
invoice. Refer to Note 2.
2000 each
$ _______/each
$ ___________
21
Casting of concrete cylinder for
compressive tests, including mailing and
reporting with invoice. Price per cylinder
cast. Refer to Note 2.
5000 each
$ _______/each
$ ___________
22
Core drilling 37.5mm(or greater) diameter
core for in-situ testing of the depth of
concrete / asphalt. Refer to Note 2.
100 each
$ _______/each
$ ___________
23
Core drilling 100mm diameter core for in-
situ testing of concrete road base. Refer to
Note 2.
100 each
$ _______/each
$ ___________
24
Asbestos content determination from asphalt
cores including full depth coring, cutting
cores to the desired thickness, laboratory
testing and reporting of test results. Refer to
Note 2.
6 each
$ _______/each
$ ___________
Concrete Sample Testing (E)
25
Compressive strength test (CSA A23.2) of
150mm x 300mm or 150mm x 200mm
cylinder. Price per cylinder tested. Includes
cost of all labour and faxing and emailing
preliminary report and writing/submission
of written report.
5000 each
$ _______/each
$ ___________
26
Pick-up, cure, grind, perform compression
test, report per Special Requirements for
High-Strength Concrete (Def’n. A23.1).
Prices per cylinder to include travel to site
expenses.
250 each
$ _______/each
$ ___________
27
Pick-up, cure, test, report per Special
Requirements for Standard Test Method for
preconstruction and construction evaluation
of Mortars for plain and reinforced unit
masonry (ASTM C 780).
Prices per cylinder to include travel to site
expenses.
50 each
$ _______/each
$ ___________
6 of 10
March 28, 2017 Addendum 2
Aggregate and Soil Sample Laboratory Testing (F)
28
Retrieve soil or aggregate sample from
Project site. Refer to Note 2.
100 each
$ _______/each
$ ___________
29
Shrinking Test, 7th day and 28th day
10 each
$ _______/each
$ ___________
30
On site concrete hammer test for onsite
strength test. Refer to Note 2.
10 each $_______/each $ ___________
31
Perform test on sample to determine
percentage volume of asphalt coated
particles. Includes cost of faxing and
emailing preliminary results and
writing/submission of report.
20 each
$ _______/each
$ ___________
32
Perform gradation analysis with wash in
accordance with MTO procedure, including
cost of all labour and reporting, faxing and
emailing preliminary results and
writing/submission of report.
50 each
$ _______/each
$ ___________
33
Perform 5-point Modified Proctor test on
sample, including cost of all labour.
Includes cost of faxing and emailing
preliminary results and writing/submission
of report.
50 each
$ _______/each
$ ___________
34
X-ray diffraction (XRD) testing by an
accredited environmental analytical
laboratory to identify gypsum, ettringite and
thaumasite.
15 each
$ _______/each
$ ___________
35
Sieve analysis on granular fill, bedding
material, base courses and aggregates in
accordance with ASTM C136 or MTO Lab
Test No. LS602report.
30 each
$ _______/each
$ ___________
36
Standard Proctor test. ASTM D698.
30 each
$ _______/each
$ ___________
Field Nuclear Density (G)
37
All-inclusive on-site rate for nuclear testing.
Refer to Note 2.
5600 hours
$ _______/hour
$ ___________
38
All-inclusive on-site rate for nuclear testing
over 12 hours per day Mon-Fri. Refer to
Note 2.
400 hours
$ _______/hour
$ ___________
39
All-inclusive on-site rate for nuclear testing
during weekends or statutory holidays,
Refer to Note 2.
400 hours
$ _______/hour
$ ___________
7 of 10
March 28, 2017 Addendum 2
Sampling, testing and written report in accordance with MOEE guidelines (H)
40
Sulphate, chloride ion, electrical
conductivity, PH, and redox potential
analysis. Refer to Note 2.
65 samples
$ _____/sample
$ ___________
41
Reg. 558 Leachate chemistry with VOCs,
SVOCs, inorganics and PCBs.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
42A
Inorganic and General Chemistry for Soil
under MOECC Soil, Groundwater and
Sediment Standards for Use Under Part
XV.1 of the Environmental Protection Act,
2011.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
42B
PHCs and BTEX for soil under MOECC
Soil, Groundwater and Sediment Standards
for Use Under Part XV.1 of the
Environmental Protection Act, 2011.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
42C
VOCs for soil under MOECC Soil,
Groundwater and Sediment Standards for
Use Under Part XV.1 of the Environmental
Protection Act, 2011.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
42D
PAHs for soil under MOECC Soil,
Groundwater and Sediment Standards for
Use Under Part XV.1 of the Environmental
Protection Act, 2011.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
42E
PCBs for Soil under MOECC Soil,
Groundwater and Sediment Standards for
Use Under Part XV.1 of the Environmental
Protection Act, 2011.
Refer to Note 2.
65 samples
$ _____/sample
$ ___________
Brick Testing (I)
43
Sample, pick up and test bricks as per
A.S.T.M. Spec. C-902, C.S.A. A82.2 and
City standards, including travel to site
expense.
20 each
$ _______/each
$ ___________
Visual & Dye Penetrant Welding Inspection (J)
44 All-inclusive on-site rate for visual and
welding inspection. Refer to Note 2. 900 hrs
$ _______/hour $ ___________
8 of 10
March 28, 2017 Addendum 2
45 All-inclusive on-site rate for visual and
welding inspection over 12 hours per day
Mon-Fri. Refer to Note 2.
180 hrs
$ _______/hour
$ ___________
46 All-inclusive on-site rate for visual and
welding inspection during weekends or
statutory holidays, Refer to Note 2.
90 each
$ _______/hour
$ ___________
Inspect Steel Structures as per OPSS 906 and CAN/CSA-S16.1 (K)
47 All-inclusive on-site rate for steel structure
inspection. Refer to Note 2. 100 hrs $ _______/hour
$ ___________
48 All-inclusive on-site rate for steel structure
inspection over 12 hours per day Mon-Fri.
Refer to Note 2.
20 hrs
$ _______/hour
$ ___________
49 All-inclusive on-site rate for steel structure
inspection during weekends or statutory
holidays, Refer to Note 2.
10 hrs
$ _______/hour
$ ___________
Radiographic Testing (L)
50 Radiographer team (Radiographer &
Helper) all-inclusive on-site rate. Refer to
Note 2.
100 hrs
$ _______/hour $ ___________
51 Radiographer team (Radiographer &
Helper) all-inclusive on-site rate over 12
hours per day Mon-Fri. Refer to Note 2.
20 hrs
$ _______/hour
$ ___________
52 Radiographer team (Radiographer &
Helper) all-inclusive on-site rate during
weekends or statutory holidays, Refer to
Note 2.
20 hrs
$ _______/hour
$ ___________
53 Radiographic film – 114mm x 216mm 20 $ _______/each $ ___________
54 Radiographic film – 114mm x 432mm 30 $ _______/each $ ___________
Ultrasonic Testing (M)
55 All-inclusive on-site rate for ultrasound
testing. Refer to Note 2.
20 hrs $ _______/hour $ ___________
56 All-inclusive on-site rate for ultrasound
testing over 12 hours per day Mon-Fri.
Refer to Note 2.
8 hrs
$ _______/hour
$ ___________
57 All-inclusive on-site rate for ultrasound
testing during weekends or statutory
holidays. Refer to Note 2.
4 hrs
$ _______/hour
$ ___________
Quality Assurance Report (N)
58
Compile test results for the Project,
comment and provide remedial
recommendations where necessary, and
submit monthly QA report.
48 each
$ _______/each
$ ___________
9 of 10
March 28, 2017 Addendum 2
59
Compile test results, provide summary
charts and final QA reports during
Construction and Post-Construction phases.
2 each
$ _______/each
$ ___________
Provisional Items (O)
60
Review soil analysis reports for the
suitability of sub grade material
30 each
$ _______/each
$ ___________
61
Senior Professional Engineer
100 hours
$ _______/hour
$ ___________
62
Professional Engineer
500 hours
$ _______/hour
$ ___________
63
Field Technician/Certified Engineering
Technician
600 hours
$ _______/hour
$ ___________
64
Clerical/secretarial
200 hours
$ _______/hour
$ ___________
65 Hardened Air-Void analysis (ASTM C457
Test Procedures). The item to include,
coring for samples, polishing, testing and
reporting.
50 each
$ _______/each
$ ___________
Contingency (P)
66
Contingency Allowance (Provisional Sum)
P.S.
$75,000.00
$75,000.00
(A+B+C+D+E+F+G+H+I+J+K+L+M+N+O+P) Subtotal
$ ___________
HST @ 13%
$ ___________
TOTAL BASE BID PRICE (This amount to be transcribed to page 1)
$ ___________
Notes:
1) Traveling expense is paid under Item No. 4
2) Traveling expense is included in the unit price.
10 of 10