    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    1 Excavation in foundation in ordinary soil (clay or

    sand) including lift upto 1.5 meter (loam, (5 ft.)

    and lead upto 30 meter (100 ft) and including

    filling, watering and ramming of excavated earthinto the trenches or into the space between the

    building and sides of the foundation trenches or

    into the plinth and removal and disposal of

    surplus earth as directed by the E/I upto a

    distance of 30 meters (100 ft.) from the

    foundation trenches.

    (CSI No. 4.01)

    Cum 2.00 104.00

    (Rs. One Hundred

    four only)

    208.00

    2 Clearing jungle including uprooting of rank

    vegetations, grass, bush, trees and saplings of

    girth upto 30cm measured at a height of 1.0

    meter above ground level including removal of

    rubbish upto a distance of 50 meters outside the

    periphery of area cleared.

    (CSI No. 4.09)

    Sqm. 100.00 4.50

    (Rs. Four & Paisa

    fifty only)

    450.00

    3 Concrete with 4 cm gauge I class brick ballast

    (class 150) with coarse sand (F.M. 1.8 to 2.5)

    and cement in proportion of 12:6:1 in foundation

    and under floors including supply of all

    materials, labours and tools and plants etc.

    required for proper completion of the work.

    (CSI No. 5.01)

    Cum 0.50 3072.00

    (Rs. ThreeThousand

    seventy two only)

    1536.00

    4 Precast cement concrete door, sills, chaukhats

    boundary posts, shelves and similar small work

    with cement approved coarse sand (F.M. 1.8 to

    2.5) and 2 cm gauge graded approved hard

    stone ballast in the proportion 1:2:4, excluding

    supply of reinforcement and its bending butincluding its fixing and binding the same with 24

    BWG. G.I. binding wire and including the cost of

    binding wire, moulds, all other materials, labour

    and T&P etc. required for proper completion of

    the work.

    (CSI No. 5.09)

    Cum 0.10 6148.00

    (Rs. Six Thousand

    one hundred forty

    eight only)

    614.80

    5 First class brick (class-150) work in 1:6 cement

    and coarse sand (F.M. 1.8 to 2.5) mortar in

    foundation and plinth including supply of all

    materials, labour & T&P etc. required for proper

    completion of work.

    (CSI No. 6.01)

    Cum 0.50 3498.00

    (Rs. Three

    Thousand four

    Hundred ninety eight

    only)

    1749.00

    6 First class brick work in foundation and plinthold dismantled bricks (supplied by department

    free of cost) and coarse sand of F.M. 1.8 to 2.5

    mortar in 1:6 including supply of all material,

    labour and T&P etc. required for proper

    completion of the work.

    (CSI No. 6.20)

    Cum 1.00 1538.00(Rs. One Thousand

    Five Hundred Thirty

    Eight only)

    1538.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    2/14

    Page 2

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    7 Indian salwood wrought framed and fixed

    including simple moulding straight work as in

    chaukhts including supply of all material, labour

    and T&P etc. required for proper completion ofthe work. (CSI No. 8.02)

    Cum 0.02 59275.00

    Rs. Fifty Nine

    Thousand Two

    Hundred Seventyfive only)

    1185.50

    8 Supply and fixing of galvanized mosquito proof

    heavy quality iron wire gauge or expanded metal

    heavy quality (24 x 16 gauge) over door/window

    old shisham wood beading and supply and fixing

    necessary screws, nails and all materials labour

    and T&P etc. required for proper completion of

    the work. (CSI No. 8.49)

    Sqm. 1.50 739.00

    (Rs. Siven Hundred

    thirty Nine only)

    1108.50

    9 Providing and fixing of shisham wood beading of

    tappered section of (35x10x5) mm with screws,

    nails etc. including supply of all materials, labour

    and T&P etc. required for proper completion of

    work. (CSI No. 8.66)(b)

    RM 4.00 34.00

    (Rs. Thirty four only)

    136.00

    10 Renewing panes of glass including supply of

    glass panes 4 mm thick with putty and brads

    including supply of all materials, labour and T&P

    etc. required for proper completion of the work.

    [CSI No. 20.04 (b)]

    Sqm. 1.00 388.00

    (Rs. Three Hundred

    Eighty Eight only)

    388.00

    11 Supply and fixing ISI marked approved quality

    following oxidised iron fitting in old doors and

    windows, shutters with screws, nuts, bolts, etc.

    including cartage of material, labour and T&P

    etc. required for proper completion of the work.

    (a) Tower bolts 10 mm dia x 200 mm log.

    ( C.S.I No. 22.88 (b)

    No. 1.00 44.00

    (Rs. Forty four only)

    44.00

    (b) Tower bolts 10 mm dia x 150 mm log.

    ( C.S.I No. 22.88

    No. 1.00 38.00

    (Rs.Thirty Eight only)

    38.00

    (c) M.S. Hinges 100 mm size.

    ( C.S.I No. 22.88 (d)

    No. 2.00 31.00

    (Rs. Thirty One only)

    62.00

    (d) Handles, 100 to 150 mm size long.

    ( C.S.I No. 22.88 (f)

    No. 1.00 33.00

    (Rs Thirty Three

    only)

    33.00

    (e) L-drop 16 mm dia x 250 mm long. (

    C.S.I No. 22.88 (g)

    No. 1.00 75.00

    (Rs. Seventy five

    only)

    75.00

    12(a) Easing door and windows (CSI No. 20.05) Each 1.00 36.50

    (Rs. Thirty Six &

    Paisa Fifty only)

    36.50

    (b) Labour for fixing door bolts or hinges or tower

    bolts or hasp and staples or handles etc. to door

    and windows. (CSI No. 20.10)

    Each 4.00 13.30

    (Rs. Thirteen &

    Paisa Thirty only)

    53.20

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    3/14

    Page 3

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    13 Mild Steel or Iron in plain work such as

    reinforced concrete or reinforced brick work

    (when not included in an over all rates) wrought

    to required shape as necessary includingbending for proper completion of the work and

    including supply of steel its wastage, bend,

    hooks and authorised overlapping shall be

    measured. (steel shall be arranged by the

    contractor). (CSI No. 9.05)

    MT 0.01 69500.00

    (Rs. Sixty Nine

    Thousand Five

    Hundred only)

    695.00

    14(a) Providing barbed iron wire fencing including

    fixing in to post after straightening it including

    labour and T&P etc. required for proper

    completion of the work but excluding supply of

    posts and wire. (labour rates only)

    (CSI NO. 9.12)

    RM 50.00 2.20

    (Rs. Two & Paisa

    Twenty only)

    110.00

    (b) Same as item No. 15(a) above but alsoincluding stretching, fixing into the post including

    all labour, materials and T&P required for proper

    completion of work the weight of hot dipped GI

    barbed wire having 12 SWG- 2 ply wires and 4

    point ordinary barbs @ 150 mm (approx) C/C

    should be 100 gm per Meter. (CSI No. 9.13)

    Kg 2.00 95.40(Rs. Ninty Five and

    Paisa Fourty only)

    190.80

    15 Supply and fixing welded wire mesh size 75mm

    x 25mm and rectangular made out of 10 SWG

    over M.S. angle frame with M.S. flat with nut and

    bolts welded as required including cost of drilling

    holes, bolts, nuts, washer wilding etc. as

    required including cost of all labour, materials,

    T&P require for proper completion of the workexcept cost of angle iron and flat. (CSI No. 933).

    Sqm. 1.00 575.00

    (Rs. Five Hundred

    Seventy Five only)

    575.00

    16 Supply & fixing hold fasts 300x40x6 mm flat iron

    with 10 mm dia bolts with nut including grouting

    in CC 1:2:4 size of block 230x115x75 mm (CC

    shall be measured separately) (CSI No. 9.28)

    Each 1.00 66.10

    (Rs.Sixty six & Paisa

    Ten only)

    66.10

    17 Spreading over leaky roofs with bitumen paints

    at 10 Lbs. per 100 sq.ft. or 1 LB (0.45 Kg.) per

    sq.m. including sweeping, cleaning the roof with

    brushes, heating of the paints up to the required

    temperature, pouring it on the surface,

    spreading of necessary quantity of approvedcoarse sand 1 cft. per 100 sft. and including

    supply of all materials, labour and T&P etc.

    required for proper completion of the work. (CSI

    No. 10.08)

    Sqm. 1.00 42.90

    (Rs. Forty Two &

    Paisa Ninety only)

    42.90

    18 12 mm thick plaster in 1:6 with cement and

    coarse sand mortar. (CSI No. 11.10)

    Sqm. 5.00 125.00

    (Rs. One hundred

    Twenty Five only)

    625.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    4/14

    Page 4

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    19 Same as Item No. 18 above but in patches (CSI

    No. 11.10+20.02)

    Sqm. 10.00 156.25

    (Rs. One Hundred

    fifty six & Paisa

    Twanety five only)

    1562.50

    20 Supply and mixing approved water proofing

    compound in cement mortar in plaster or

    concrete work in the proposition as

    recommended by the manufacturer. (CSI No.

    11.18)

    Kg 1.00 54.70

    (Rs. Fifty Four &

    Paisa Seventy only)

    54.70

    21 2.5 cm thick 1:2:4 plain cement concrete floor

    with cement approved coarse sand, and 2 cm

    (3/4") graded approved stone ballast laid in

    panels finished with 3 mm (1/8") floating coat of

    neat cement or cement and marble dust in ratio

    of 5:1 as specified without base concrete

    including supply of all materials, labour and T&P

    etc. required for proper completion of the work.

    (CSI No. 12.02)

    Sqm. 3.00 202.00

    (Rs. Two Hundred

    Two only)

    606.00

    22 Repair to 2.5 cm thick 1:2:4 plain CC floor in

    patches/panels with cement, approved coarse

    sand and 2 cm gauge approved stone ballast in

    panels f inished with 3 mm floating coat of neat

    cement including dismantling and removal of old

    damaged floor and also including supply of all

    material, labour and T&P etc. (CSI No.

    12.02+20.03)

    Sqm. 5.00 252.50

    (Rs. Two Hundred

    Fifty Two & Paisa

    Fifty only)

    1262.50

    23 First class brick on edge floor laid dry, joints

    sand filled, including preparation of base to

    proper slope and its ramming including supply of

    all material labour & T&P etc. required for proper

    completion of the work. (CSI No. 12.08)

    Sqm. 1.00 338.00

    (Rs. Three Hundred

    Thirty Eight only)

    338.00

    24 Same as Item No. 23 above but bricks laid flat

    (CSI No. 12.11)

    Sqm. 1.00 297.00

    (Rs. Two Hundred

    ninety seven only)

    297.00

    25 1st class brick on edge floor laid dry joints sand

    filled but resoling work with existing bricks,

    including preparation base to proper slope and

    its ramming including supply of labour T&P etc.

    (labour only) (CSI No. 20.24)

    Sqm. 5.00 113.00

    (Rs.One hundred

    Thirteen only)

    565.00

    26 Providing and fixing glass strips of 3.15 mm

    thickness in joints of floor and skirting at the

    time of laying, floors flush with floor level

    including labour, Tools and plants etc. complete.(CSI No. 12.18)

    (a) of 25 mm depth.

    RM 8.00 18.80

    (Rs. Eighteen &

    Paisa Eighty only)

    150.40

    27 Painting or varnishing one coat synthetic enamel

    paint (Berger/Luxol) or varnish on previously

    painted surface on wood work or iron work

    including its sand papering, rubbing and

    cleaning as required, for proper completion of

    work. (CSI No. 13.03)

    Sqm. 20.00 36.60

    (Rs. Sixty six &

    Paisa sixty only)

    732.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    5/14

    Page 5

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    28 Same as item No. (27) above but for every coat

    after first coat.

    (CSI No. 13.02)

    Sqm. 20.00 26.80

    (Rs. Twenty six &

    Paisa Eighty only)

    536.00

    29 Finishing walls with one coat of water proof cement paint of approved quality like "Super

    Snowcem" or equivalent on previously old

    treated surface with this paint to give an even

    shade including supply of all materials, labour

    and Tools & plants etc. required for proper

    completion of work. (CSI No. 13.09)

    Sqm. 50.00 25.50(Rs. Twenty five &

    Paisa fifty only)

    1275.00

    30 Same as item No. (29) above but for each coat

    of water proof cement paint after the first coat.

    (CSI No. 13.08)

    Sqm. 50.00 16.70

    (Rs. Sixteen & Paisa

    seventy only)

    835.00

    31 White washing two coats including cost of all

    materials, labour and T&P etc. required for

    proper completion of the work. (CSI No. 14.02)

    Sqm. 160.00 6.60

    (Rs. Six & Paisa

    sixty only)

    1056.00

    32 Colour washing two coats, using approved

    colouring materials, of buff, blue gray or brown

    shade including supply of all materials, labour

    and T&P etc. for proper completion of the work.

    (CSI No. 14.05)

    Sqm. 80.00 11.80

    (Rs. Eleven & Paisa

    Eighty only)

    944.00

    33 One coat of dry distemper on previously treated

    old surface including supply of all materials,

    labour and T&P etc. for proper completion of the

    work. (CSI No. 14.08)

    Sqm. 80.00 13.50

    (Rs. Thirteen &

    Paisa fifty only)

    1080.00

    34 Scrapping old white or colour wash or distemper

    including disposal refuse as directed by the

    Engineer-Incharge within a distance of 60 M.

    (CSI No. 15.10)

    Sqm. 100.00 7.80

    (Rs. Seven & Paisa

    Eitghty only)

    780.00

    35 Dismantling of existing plaster including disposal

    of refuse as directed by the Engineer-Incharge

    within a distance of 60 M. (CSI No. 15.09)

    Sqm. 10.00 25.30

    (Rs.Twenty five &

    Paisa Thirty only)

    253.00

    36 Providing and fixing stop/bib cock (brass) 15

    mm dia 200 gm weight of approved superior

    quality. (CSI No. 26.52)

    Each 5.00 303.00

    (Rs. Three Hundred

    Three only)

    1515.00

    37 Providing and fixing 15 mm dia C.P. pillar cock

    of approved make including cost of all materials,

    cartage, labour, T&P etc. required for proper

    completion of work. (CSI No. 26.66)

    Each 2.00 624.00

    (Rs. Six Hundred

    Twenty four only)

    1248.00

    38 Supply and fixing C.P. Brass stop cock heavyquality 15 mm dia ISI mark including cutting and

    threading the pipe if required including supply of

    all materials, labour, T&P etc. required for

    proper completion of work. (CSI No. 26.59)

    Each 2.00 519.00(Rs. Five Hundred

    Nineteen only)

    1038.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    6/14

    Page 6

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    39(a) Providing and fixing 15 mm dia B-class Jindal,

    JTC, ISI marked G.I. pipes complete with

    special such as bend, tee, socket, cross, clamp

    etc. earth work including filling the trenches etc.required for proper completion of the work, the

    rate also includes concealed GI f itting where

    required, cutting and making good the walls etc

    and all materials, labour and T&P complete.

    (CSI No. 26.01)

    RM 8.00 167.00

    (Rs. One Hundred

    sixty seven only)

    1336.00

    (b) Same as Item No. 39(a) above but for 20 mm

    dia. (CSI No. 26.02)

    RM 20.00 203.00

    (Rs. Two Hundred

    Three only)

    406.00

    (c) Same as Item No. 39(a) above but for 25 mm

    dia. (CSI No. 26.03)

    RM 3.00 279.00

    (Rs. Two Hundred

    Seventy Nine only)

    837.00

    (d) Same as Item No. 39(a) above but for 32 mm

    dia. (CSI No. 26.04)

    RM 1.00 344.00

    (Rs. Three Hundred

    Forty four only)

    344.00

    40 S/F P.V.C. float for float valve 15 mm with brass

    rod and union. (CSI No. 26.28)

    Each 1.00 223.00

    (Rs. Two Hundred

    Twanety Three only)

    223.00

    41 Supply and fixing P.V.C./C.I. Bibcock 15 mm dia

    of approved quality (old cock shall be the

    property of contractor).[CSI No. 26.52(d)]

    Each 10.00 42.90

    (Rs. Forty two &

    Paisa Ninety only)

    429.00

    42 Providing and replacing of the following

    galvanized iron fittings in existing pipe line

    including cutting, threading in pipe if required.

    (Chapter 24.00)

    (a) GI Elbows 15 mm dia

    ((CSI No. 26.78)(a)

    No. 10.00 35.20

    (Rs. Thirty five &Paisa Twenty only)

    352.00

    (b) GI Socket 15 mm dia

    (CSI No. 26.75)(a)

    No. 10.00 30.80

    (Rs. Thirty & Paisa

    Eighty only)

    308.00

    (c) GI Elbow 20 mm dia

    (CSI No. 26.78)(B)

    No. 5.00 49.50

    (Rs. Forty Nine &

    Paisa fifty only)

    247.50

    (d) GI Socket 20 mm dia.

    (CSI No. 26.75)(B)

    No. 5.00 46.20

    (Rs. Forty six &

    Paisa Twenty only)

    231.00

    (e) G.I. Tee 15 mm dia

    (CSI No. 26.76) (a)

    No. 3.00 73.70

    (Rs. Seventy Three

    & Paisa seventy

    only)

    221.10

    (f) G.I. Tee 20 mm dia

    (CSI No. 26.76)(B)

    No. 3.00 95.70

    (Rs. Ninety five &

    Paisa seventy only)

    287.10

    (g) G.I. Union 15 mm dia

    (CSI No. 26.79)(A)

    No. 2.00 81.40

    (Rs. Eighty One &

    Paisa forty only)

    162.80

    (h) G.I. Union 20 mm dia

    (CSI No. 26.79)(B)

    No. 2.00 129.00

    (Rs. One Hundred

    Twenty Nine only)

    258.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    7/14

    Page 7

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    43 Repair of sluice valve 80mm size including

    repair of valve seat & spindle etc. NSI.

    Job 1.00 359.80

    (Rs. Three Hundred

    Fifty Nine & Paisa

    Eighty only)

    359.80

    44 Dismantling reinforced cement concrete or

    reinforced brick work. Including stacking of

    dismantled materials as directed by the

    Engineer I/C within a distance of 60 meters.

    (CSI No. 15.03).

    Cum 0.50 667.00

    (Rs. Six Hundred

    sixty seven only)

    333.50

    45 One Coat of ready mixed primer of 'Burger' or

    equivalent brand on new iron/wood surface

    including supply of all material, labour & T&P

    etc. required for proper completion of the work.

    (CSI No. 13.01-13.02)

    Sqm. 10.00 26.70

    (Rs. Twenty six &

    Paisa seventy only)

    267.00

    46 Cleaning of existing water pipe line having dia

    upto 50 mm including digging trenches openingand cleaning of pipes, cutting threading if

    required and refilling of earth and including

    making good the road and wall etc.as directed

    by the Engineer-I/C. [CSI No. 20.45(b)]

    RM 50.00 52.20

    (Rs. Fifty two &Paisa twenty only)

    2610.00

    47 Providing and fixing first quality Indian type white

    glazed earthen wire ISI mark W.C. Pan size 580

    mm (Hindustan, Cera make) including supply of

    all materials, labour and T&P etc. required for

    proper completion of the work.

    (CSI No. 27.03)

    Each 1.00 790.00

    (Rs. Seven Hundred

    Ninety only)

    790.00

    48 Providing and fixing a pair of white glazed foots

    rests of standard pattern for Indian Type W.C.pan including supply of all materials, labour and

    T&P etc. reqruied for proper completion of the

    work. (CSI No. 27.14)

    Pair 1.00 158.00

    (Rs. One HundredFifty Eight only)

    158.00

    49 Supply and fixing white glazed earthen-ware

    W.C. "Orissa" Pan Hindustan make of size

    (58x44 cm) including supply of all materials

    labour and T&P etc. complete. [CSI No. 27.02

    (b)]

    Each 1.00 1457.00

    (Rs. One Thousand

    Four Hundred fifty

    Seven only)

    1457.00

    50 supply and fixing wash hand basin (56x41) cm

    of white glazed earthen ware of hindware /perry

    or eqyivalent make excluding fittings. (C.S.I.

    No.27.09)(b)

    Each 1.00 1257.00 Rs. One

    Thousand two

    hundred fifty seven

    only)

    1257.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    8/14

    Page 8

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    51 Providing and fixing 600 mm x 450 mm plain,

    edge mirror of Atul, Kiran make glass with Indian

    polish 6.50 mm thick complete with back of 600

    mm x 450 mm x 6 mm hard board sheet fixed towooden cleats with C.P. brass screws and

    washers including supply of all materials, labour

    and T&P etc. required for proper completion of

    the work.

    [CSI No.27.23 (a)]

    Each 1.00 616.00

    Rs.(Six hundred

    eighteen only)

    616.00

    52 Supply and replacing of 40 mm dia P.V.C. waste

    pipe for wash basin/ sink including cost of all

    labour, materials, and T&P etc. required for

    proper completion of the work. (CSI No. 20.14)

    Each 5.00 66.00

    (Rs. Sixty six only)

    330.00

    53 Providing and replacing P.V.C. connection pipe

    15 mm with two no. brass union.

    (CSI No. 26.40)

    Each 4.00 57.00

    (Rs. Fifty seven only)

    228.00

    54 Supply and fixing P.V.C. cistern Hindustan or

    equivalent make 10 litres. Capacity complete

    with all accessories (Low level) including all

    materials, labour and T&P etc. complete.

    [CSI No. 27.16(b)]

    Each 1.00 1093.00

    (Rs. One thousand

    Ninety three only)

    1093.00

    55 Providing and fixing fully way G.M. gate valve 25

    mm dia with wheel, ISI mark heavy quality

    including supply of all materials, labour and T&P

    required for proper completion of work.

    (CSI No. 26.24)

    Each 1.00 1012.00

    (Rs. One thousand

    Twelve only)

    1012.00

    56 Disposal of rubbish / Debris out side the UPPCL

    area as per direction of Engineer -in-charge

    including cartage, labour and materials, T&P

    etc. required for proper completion of the work.

    No deduction for voids shall be made. (CSI No.

    20.19)

    Cum 10.00 107.00

    (Rs.One hundred

    seven only)

    1017.00

    57(A) Cleaning of septic tank including disposal of

    waste out side the UPPCL area as per direction

    of the Engineer-in-charge including cost of all

    labour, T&P etc. required for proper completion

    of the work. (CSI No. 20.15)

    Job 2.00 1295.00

    (Rs. One thousand

    two hundred Ninety

    five only)

    2590.00

    (B) Same as Item No. 59(a) above but for

    inspection chamber. (CSI No. 20.16)

    No. 5.00 92.80

    (Rs. Ninety two &

    Paisa eighty only)

    464.00

    58 Cleaning of R.C.C. over head tank upto capacity

    of one lac litres and chlorinating with bleachingpowder mixed to water as per direction of

    Engineer-in-charge complete.

    (CSI No. 20.48)

    Job 1.00 1301.00

    (Rs. One Thousandthree hundred one

    only)

    1301.00

    59 Cutting out cracks of roof terrace to V-selection

    cleaning out, wetting, grouting with cement and

    sand slurry 1:3 (1 cement and 3 sand) including

    cost of all materials, labours, T&P etc. required

    for proper completion of the work. (Cement

    consumption .004 Bags/RM) (CSI No. 22.55)

    RM 5.00 38.60

    (Rs. Thirty eight &

    Paisa Sixty only)

    193.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    9/14

    Page 9

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    60 Opening, cleaning, overhauling, oiling and

    greasing of defective roll ing shutter and also

    resetting of its springs for its smooth functioning

    including cost of all materials, labour and T&Petc. (CSI No. 20.27)

    Job 1.00 285.00

    (Rs. Two Hundred

    eighty five only)

    285.00

    61 Painting and printing house No. or residence in

    circle of size 8" including preparation of base

    with enameled paint complete as directed by the

    engineer-in-charge.

    (CSI No. 20.81)

    Job 10.00 31.90

    (Rs. Thirty one &

    Paisa Ninety only)

    319.00

    62 Attending maintenance petty problems with in

    the reach of one suitable and experienced

    beldar/mali along with required T&P & sundries.

    (Chapter 2 Item 9+10%)

    Per Day 5.00 220.00

    (Rs. Two Hundred

    twenty only)

    1100.00

    63 Attending to petty maintenance service like

    plumbing service , welder sevice ,and carpenter

    service required as below. (C.S.I. No.22.71)

    A Job attending by one no. plumber / welder /

    mason/ carpenter with one no. helper per hour

    or part of an hour ,

    hour 10.00 67.40 (Rs.

    Sixty seven & paisa

    forty only)

    674.00

    B Job attending by one no. plumber / welder /

    mason/ carpenter with two no. helper per hour

    or part of an hour ,

    hour 10.00 95 .00

    (Rs. Ninety five only)

    950.00

    65(a) Cleaning of main drain width less than 300 mm

    including disposal of waste refuses sludge out

    side the board's area including washing and

    cleaning by clean water completely (Rate for

    cleaning the drain per R.M. per month for

    cleaning the drains once a week). (CSI No.

    20.17)

    RM 800.00 14.10

    (Rs. Forteen &

    Paisa ten only)

    11280.00

    (b) Same as above in item No. 65(a) but for drain of

    width less than 300 mm. (CSI No. 20.18)

    RM 300.00 7.30

    (Rs. Seven & Paisa

    thirty only)

    2190.00

    66 Cement washing two coat with slack lime in ratio

    1:2 (Cement : lime) including supply of all

    materials, labour and T&P etc. required for

    proper completion of the work. (CSI No. 14.09)

    Sqm. 100.00 7.20

    (Rs.Seven & Paisa

    twenty only)

    720.00

    67 Same as in Item No. 66 but for subsequent coat.

    (CSI No. 14.10)

    Sqm. 100.00 6.20

    (Rs. Six & Paisa

    twenty only)

    620.00

    68 Supply and fixing of Syntex or equivalent make

    water storage tank including all materials,labours, T&P etc required for proper completion

    of work. (CSI No. 26.50)

    Litre 200.00 9.20

    (Rs. Nine & PaisaTwenty only)

    1840.00

    69 Oil bound distemper (Berger or equivalent) on

    old previously distempered surface including

    supply of material, labour and T&P etc. required

    for proper completion of work. (CSI No. 13.13)

    Sqm. 50.00 22.30

    (Rs. Twenty two &

    Paisa thirty only)

    1115.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    10/14

    Page 10

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    70 Same as Item No. 70 above but for each coat

    after first coat or subsequent coat. (CSI No.

    13.14)

    Sqm. 50.00 19.40

    (Rs. Nineteen &

    Paisa forty only)

    970.00

    71 Supply and planting Ashoka, Pendula, Mango,Neem or other Shadow trees including digging

    hole of proper size, manure anti termite with

    proper chemical etc., including cost of all

    materials, labour and T&P etc. complete in all

    respects. (CSI No.23.13)

    Nos. 50.00 44.00(Rs. Forty four only) 2200.00

    72 (a) Supply and fixing of double action floor spring

    including cutting in floors and RCC slabs and

    grouting the same with C.C. & finishing the

    surface properly as and where required under

    Al. doors as per direction of Engineer-in-

    charge. The rate includes all labour material and

    T&P required for completion of work. (CSI No.

    8.70)

    No. 1.00 2471.00

    (Rs. Two Thousand

    four hundred

    seventy one only)

    2471.00

    73 P/F Neosprine Gasket for fixing glass panes ofdoor and window shutters including cost of all

    materials, labour and T&P etc. required for

    proper completion of the work. (CSI No. 22.52)

    RM 1.00 84.70(Rs. Eighty four

    &paisa Seventy

    only)

    84.70

    74 Cleaning of grass and removal of rubbish up to

    a distrance of 50 M outside the UPPCL area

    cleared. (CSI No. 4.10)

    Sqm. 1000.00 1.70

    (Rs. One & Paisa

    seventy only)

    1700.00

    75(a) Cement concrete with 2 cm gauge approved

    hard stone ballast, coarse sand (F.M. 1.8 to 2.5)

    and cement in proportion of 4:2:1 including

    supply of all materials, labour, side shuttering if

    required and T&P etc. required for proper

    completion of work. (CSI No. 5.06)

    Cum 0.30 5257.00

    (Rs. Five Thousand

    Two Hundred Fifty

    Seven only)

    1577.10

    (b) RCC work with cement approved coarse sand

    (F.M. 1.8 to 2.5) and 2 cm gauge graded

    approved hard stone ballast in proportion 1:2:4

    in slabs excluding supply of reinforcement and

    its bending but including its f ixing and binding

    the same with 24 B.W.G. binding wire and

    including necessary centering and shuttering

    etc. and also including cost of all materials,

    binding wire, labour and T&P etc. required for

    proper completion of the work (binding wire to

    be supplied by the contractor free of cost. (CSI

    No. 5.11)

    Cum 0.10 6613.00

    (Rs. Six Thousand

    Six Hundred

    Thriteen only)

    661.30

    76 Same as above in item No. 75(b) but for R.C.C.

    raft foundation (CSI No. 5.15)

    Cum 0.10 5539.00

    (Rs. Five Thousand

    five Hundred thirty

    nine only)

    553.90

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    11/14

    Page 11

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    77 Concrete work with 40 mm gauge brick ballast

    obtained from breaking brick bats (brick bats

    supplied by the department free of cost) in

    proportion of 12:6:1 as in item 5.01 aboveincluding cost of al l labour, material, T&P etc.

    required for proper completion of work. (CSI

    No. 5.22)

    Cum 0.20 2356.00

    (Rs.Two Thousand

    three Hundred fifty

    six only)

    471.20

    78 Mild Steel or Iron work of small size and

    sections such as holding down bolts, Holdfast

    tie rods, gratings etc. (when not included in an

    over all rates) wrought etc. and their fixing,

    required for proper completion of the work

    including cost of steel which shall be arranged

    by the contractor. (CSI No. 9.01)

    MT 0.020 68757.00

    (Rs. Sixty Eight

    Thousand seven

    Hundred Fifty seven

    only)

    1375.14

    79 Fixing panes of glass with and including putty

    brads and including supply of all materials,

    labour and T&P etc. required for proper

    completion of the work but excluding cost of glass. (CSI No. 20.07)

    Sqm. 2.00 124.00

    (Rs. One Hundred

    Twenty four only)

    248.00

    80 As in Item No. 79 above but with wooden

    beading. (CSI No. 20.08)

    Sqm. 2.00 223.00

    (Rs. Two Hundred

    Twenty three only)

    446.00

    81 First class brick work in 1:6 with old dismantled

    bricks with cement coarse sand mortar in 9"

    (230 mm) thick wall in super structure including

    all materials, labour T&P etc. except brick which

    will be issued free of cost. (CSI No.6.20)

    Cum 0.50 1538.00

    (Rs. One Thousand

    Five Hundred thirty

    eight only)

    769.00

    82 Supply and sprinkling of lime in all drains of

    colony and water logged area including cost of

    all labour, materials and T&P etc. as required for

    proper completion of the work. (CSI No. 22.72)

    Kg. 10.00 11.00

    (Rs. Eleven only)

    110.00

    83 RCC work with cement approved coarse sand

    (F.M. 1.8 to 2.5) and 2 cm gauge graded

    approved hard stone ballast in proportion 1:2:4

    in T-beam-slab and RCC Columns excluding

    supply of reinforcement and its fixing and

    binding the same with 24 B.W.G. G.I. binding

    wire and including necessary centering and

    shuttering etc. and also including cost of all

    materials, binding wire, labour and T&P etc.

    required for proper completion of the work. (CSI

    No. 5.16)

    Cum 0.10 6380.00

    (Rs. Six Thousand

    three Hundred

    eighty only)

    638.00

    84 Providing and fixing 15 mm dia PVC ball float

    valve with brass rod and union complete ISI

    mark including supply of all materials, labour

    and T&P etc. required for proper completion of

    work. CSI No. 26.28

    No. 3.00 223.00

    (Rs. Two Hundred

    twenty three only)

    669.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    12/14

    Page 12

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    85 Providing and fixing of PVC pipe 6 Kg/Sq.cm for

    water supply mains and rain water pipe of

    Tirupati or equivalent make with special such as

    Tee, bend, socket, elbow etc. including cuttingof pipe where necessary and including

    excavation of trenches for laying the pipe line of

    approved size (600 x 900 mm) and including its

    back filling after testing the pipe line, watering,

    ramming etc. complete including disposal of

    surplus earth from the sides upto 100 Meter as

    per direction of Engineer Incharge as required

    for ro er com letion of work.(a) 110 mm dia PVC Pipe (CSI No. 26.64 a) RM 5.00 224.00

    (Rs. Two Hundred

    twenty Four only)

    1120.00

    (b) 75 mm dia PVC Pipe (CSI No. 26.64 c) RM 5.00 116.00

    (Rs. One Hundred

    sixteen only)

    580.00

    (c) 50 mm dia PVC Pipe (CSI No. 26.64 e) RM 5.00 73.00

    (Rs. Seventy three

    only)

    365.00

    (d) 25 mm dia PVC Pipe (CSI No. 26.64 h) RM 5.00 30.80

    (Rs. Thity & paisa

    eighty only)

    154.00

    86 Fixing and grouting of 25 mm dia Anchor bolts

    in proper alignment level and setout with the

    help of a template including supply of all labour

    T&P etc. required for proper completion of the

    work. (CSI No. 9.21)

    No. 4.00 58.20

    (Rs. Fifty eight &

    Paisa Twenty only)

    232.80

    87 Providing and fixing full way G.M. gate valve 15

    mm dia with wheel, ISI mark heavy qualityincluding supply of all materials, labour and T&P

    required for proper completion of work. (CSI No.

    26.22)

    No. 1.00 509.00

    (Rs. Five HundredNine only)

    509.00

    88 Same as Item No. 87 above but for 20 mm dia

    (CSI No. 26.23)

    No. 1.00 675.00

    (Rs. Six Hundred

    seventy five only)

    675.00

    89 3 mm thick floating coat of neat cement finish

    including supply of all materials, labour and T&P

    etc. required for proper completion of the work.

    (including cost of cement), cement consumption

    0.044 bag/Sq.m. (CSI No. 20.23)

    Sqm. 5.00 21.80

    (Rs. Twenty one &

    Paisa eighty only)

    109.00

    90 Filling of 20 mm wide 80/100/115 mm deep joint

    with coarse sand and saw dust mixed with hot

    bitumen etc. complete (CSI No. 18.20)

    RM. 10.00 37.40

    (Rs. Thirty seven &

    paisa forty only)

    374.00

    91 Providing Gola 75 x 75 mm in C.C. 1:2:4 with

    coarse sand and 10 mm down grit including

    finishing with cement mortar 1:3 as per standard

    design. (CSI No. 10.17)

    RM 20.00 53.40

    (Rs. Fifty three &

    Paisa forty only)

    1068.00

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    13/14

    Page 13

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    92 S/F 6 mm white glazed tiles of size 200x300 mm

    in skirting, wall or dado laid with 1:3 cement and

    approved coarse sand mortar finished with white

    cement slurry, jointing and polishing complete,including supply of all materials, labour and

    Tools and Plants etc. required for proper

    completition of the work. (CSI No. 12.17a)

    Sqm. 0.50 1000.00

    (Rs.One thousand

    Only)

    500.00

    93 S/F 6 mm white glazed tiles of size 300x300 mm

    in flooring laid with 1:3 cement and approved

    coarse sand mortar finished with white cement

    slurry, jointing and polishing complete, including

    supply of all materials, labour and Tools and

    Plants etc. required for proper completion of the

    work. (CSI No. 12.17b)

    Sqm. 0.50 981.00

    (Rs. Nine Hundred

    eighty one only)

    490.50

    94 Dismantling doors or windows including

    chaukhats with hold fasts and including stackingof materials as directed by the Engineer-I/C

    within a distance of 60 metres. (CSI No. 15.07)

    Sqm. 10.00 44.30

    (Rs. Forty Four &Paisa Thirtty only)

    443.00

    95 Providing and mixing "Acrocrete" or any other

    approved polymer modified water proofing

    coating system in cement mortar for filling

    cracks in plaster or concrete work in proportion

    as recommended by the manufacturer including

    supply of all materials, labour and T&P etc. as

    required for proper completion of the work. (CSI

    No. 22.78)

    Kg 3.00 332.00

    (Rs. Three Hundred

    Thirty Two only)

    996.00

    96 Extraction of defective chocked hand pump

    machines with variable length of pipe andstrainer and reinsertion of complete assembly

    afters its repairing such as welding of pipe

    handle jhoola and replacing strainer bolts, nuts,

    washers Rubber seats etc. if also cleaning

    borehole by boring etc. if necxessay.(old SOR,

    CSI NO. 20.41)

    1.00 Each 450.00

    (Rs Four HundredFifty Only)

    450.00

    97 Replacing of plastic mesh with new strainer

    (fitter) including dismantl ing of old damaged

    plastic mesh cleaning of the holes etc.

    complete. (Old SOR, CSI NO, 20.39)

    1.00 Each 72.00 (Rs.

    Seventy Two Ony)

    72.00

    98 Development of hand pumps by operating

    continuously for clean water with testing and

    commissioning etc. (Old SOR, CSI NO. 20.43)

    1.00 Job 325.00 (Rs.

    Three Hundred

    Twenty Five Only)

    325.00

    99 Boring with 4" dia (100 mm) casing pipe upto 6

    meter depth (Old SOR, CSI NO. 20.37)

    1.00 Rm 133.00

    (Rs. One Hundred

    Thirty Three Only)

    133.00

    100 Boring with 4" dia (100 mm) casing pipe

    beyound 6 meter to 50 meter depth (Old SOR,

    CSI NO. 20.38)

    1.00 Rm 169.00

    (Rs One Hundred

    Sixty Nine Only)

    169.00

    TOTAL 94209.84

    Rs. Eighty Sixe Thousand Eight Hundred Twenety Two and Paisa Seventy Three Only

    TOTAL 94209.84

    J.E. S.D.O. COMPUTER / J.E. E.E.

  • 7/30/2019 Vivek Shukla Sir

    14/14

    Page 14

    BILL OF QUANTITY FOR ANNUAL MAINTENANCE AND REPAIR WORKS AT

    132. KV SUB-STATION ---------------------------

    S.No. Item of Work Unit Qty. Rate Amount

    Rs. Eighty Sixe Thousand Eight Hundred Twenety Two and Paisa Seventy Three Only

    J.E. S.D.O. COMPUTER / J.E. E.E.