Stormwater Program Update

New Rule and General Permit

VT DEC Stormwater Program

Page 2: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• 13 staff

• Several permit programs

• > 4,000 regulated sites

Stormwater Program

Page 3: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Authorities

Federal Clean Water Act. Vermont Statute

Page 4: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Operational Permitting

Impervious Surface > 1 acre

Page 5: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• 60,000 acres, statewide –roughly

• < 10% are currently regulated

Impervious Surfaces

Page 6: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Lake Champlain Phosphorus TMDLs

Page 7: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Sources of phosphorus in the Vermont portion of the Lake Champlain Basin (Preliminary estimates from Tetra Tech, 2013)

Page 8: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Sources of phosphorus in the Vermont portion of the Lake Champlain Basin (Preliminary estimates from Tetra Tech, 2013)

Page 9: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Stormwater Pollutant Loading

• Champlain TMDLs require a 21% reduction from “Developed Lands”

• How achieved?

Page 10: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Act 64 and Champlain TMDLs Requirements

• Municipal Roads General Permit

• MS4 General Permit

• TS4 General Permit

• New Stormwater Permitting Rule

• “3-Acre General Permit”

Page 11: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Adopted

• Went into effect on 3/15/2019

Stormwater Rule

Page 12: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Covers all stormwater permit programs

• Includes requirements for “3-acre sites”

Stormwater Rule

Page 13: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

3-Acre General Permit

Page 14: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Single tract with >3 acres of impervious surface with no permit, or a pre-2002 permit; or,

• A multi-lot project with a pre-2002 stormwater permit for >3 acres of impervious surface;

• And, adjacent impervious surfaces where part of a related operation, e.g. a campus

3-Acre Site

Page 15: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Roughly 1,000 sites statewide

• Half are previously permitted

3-Acre General Permit

Page 16: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• General Permit - due 4 months after Rule

• Permit Coverage No Later Than:

• Champlain and Memphremagog -2023

• Rest of the State – 2033

3-Acre General Permit

Page 17: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Requirements

• Retrofit Stormwater System

• Maximize treatment on site

• Vermont Stormwater Management Manual

3-Acre General Permit

Page 18: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• For example, don’t need to:

• Purchase additional land

• Pump stormwater

• Construct in flood plains or wetlands

Engineering Feasibility Analysis(EFA)

Page 19: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Stormwater rule and 3-Acre GP

• “shall allow use of”

• Offsets

• Impact fees

• Trading

Stormwater Impact Fees

Page 20: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Incentives - pay if you can’t treat

• Equity – everyone contributes

Impact Fees

Page 21: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Channel Protection Volume

• $25,000 per acre of impervious Surface

• Redevelopment Standard (50% of Water Quality Volume)

• $25,000/acre * (required volume – actual volume)

• $25,000/acre * (50% - 0%) = $12,500/acre

Impact Fees

Page 22: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Standard not

met --> $

Fund $

--> $ Project exceeding standards

Impact

Fees

Page 23: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Stormwater Only

• Permit obtained

Impact FeesEligible Projects

Page 24: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Rule

• Effective March 15, 2019

• General Permit

• Due July 2019

• Draft for public comment – soon

Rule and General PermitTiming

Page 25: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

• Schedule for 3-Acre Sites

• BMPs for “isolated impervious surfaces”

• <400 ft2

• BMPs for isolated roads

• Same as municipal roads

Key General Permit Decisions

Page 26: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit

Rule Information

• http://dec.vermont.gov/watershed/stormwater/stormwater-rule-2017-update

• E-mail Distribution List

Page 27: VT DEC Stormwater Program...3-Acre Site •Roughly 1,000 sites statewide •Half are previously permitted 3-Acre General Permit •General Permit - due 4 months after Rule •Permit