water management plan
TRANSCRIPT
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 1 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
WATER MANAGEMENT PLAN
1. COMMITMENT AND POLICY
1.1 Introduction
Ravensworth Underground Mine (RUM) is located in the upper Hunter Valley of New South Wales,
approximately 25 kilometres [km] north-west of Singleton (refer to Figure 1). Xstrata Coal NSW are
the site operators. Mining currently occurs via longwall methods in the Pikes Gully and Liddell coal
seams however RUM has approval to mine additional seams (Lemington and Barrett) and consideration
is being given to modify the mine plan and access these seams.
Development consent was granted to Nardell Coal Corporation Pty Limited for the mining operations on
20 November 1996 (DA 104/96). The Development Consent is provided in full in Appendix A. This
Water Management Plan (WMP) is specifically required by and has been prepared in accordance with
Condition 8, Schedule 2 of the Development Consent, which states that:
The Applicant shall prepare and implement a Site Water Management Plan for the development
to the satisfaction of the Director-General. This plan must:
(a) be prepared in consultation with NOW, DECCW and I&I NSW;
(b) be submitted to the Director-General for approval by the end of December 2009;and
(c) include:
- a Site Water Balance;
- an Erosion and Sediment Control Plan;
- a Surface Water Monitoring Plan;
- a Groundwater Monitoring Program;
- a Surface and Groundwater Response Plan.
Under the three-yearly review requirement, this WMP is to be submitted to the Director-General for
approval by the end of December 2012. This WMP updates and supersedes the 2009 WMP for the
Ravensworth Underground Mine (RUM, 2009).
The predicted Site Water Balance (SWB) is discussed in Section 2.0, the Erosion and Sediment Control
Plan (ESCP) is provided in Section 3.0, the Surface Water Monitoring Program (SWMP) in Section 4.0,
the Ground Water Monitoring Program (GMP) in Section 5.0, and the Surface and Ground Water
Response Plan (SWGRP) in Section 6.0.
The primary objective of the WMP is to describe management measures that will be used to minimise
potential mine-related impacts on water resources.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 2 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 1 Site Locality
After Umwelt (2009)
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 3 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
1.2 Surface Water Management Description
Figure 2a shows the mine layout in relation to surface features including watercourses, while Figure 2b
shows the layout of the surface facilities (pit top). RUM surface facilities are located adjacent to
Bayswater Creek. Existing and future underground operations extend southwards and are located
between Bayswater Creek (to the west) and Bowmans Creek (to the east). Bayswater Creek is a
heavily modified stream being dammed by Lake Liddell upstream and diverted further downstream
around neighbouring mining operations. Bayswater Creek drains southwards joining the Hunter River
approximately 40 km upstream of Singleton. Bowmans Creek has a largely unmodified catchment and
also flows southwards joining the Hunter River 3 km downstream of the confluence with Bayswater
Creek. RUM No.2 Ventilation Shaft and RUM No.3 Ventilation Shaft are located near Bowmans Creek
but are separated from the creek by the main northern rail line. Drainage above the RUM longwall
panels are dominated by highly modified post-mining landscapes associated with other mining
operations.
RUM currently holds licences under the Water Act 1912 for the operation of groundwater extraction
from mining operations and monitoring bores, and Water Access Licences (WAL) under the Water
Management Act 2000 for water extraction under the Water Sharing Plan for the Hunter River
Regulated Water Source. A summary of water licences held by RUM is given in Table 1.
Table 1
Summary of Water Licences
Licence Number Category Limit
WAL1046 High Security (Zone 1B) 3 units
WAL8964 General Security (Zone 1B) 1590 units
WAL1325 Supplementary (Zone 1B) 13 units
20BL168023 Groundwater Extraction 400 ML/year
20BL171422 Groundwater Monitoring n/a
RUM holds 1,590 ML/annum of Hunter River General Security Entitlements (GSE), 3 ML/annum of High
Security Entitlements (HSE) and 13 ML/annum of Supplementary Entitlement. RUM does not have any
pumping infrastructure to allow direct extraction from the Hunter River. Instead RUM have entered
into an agreement with Macquarie Generation (MacGen) to source water from Lake Liddell (MacGen
power station cooling water reservoir), with MacGen pumping water into Lake Liddell using their
pumping infrastructure (debiting RUM’s Hunter Licence), and RUM pumping water from Lake Liddell to
the surface facilities.
RUM also hold 400 ML/year groundwater extraction licence associated with dewatering the
underground mining operations. Groundwater is extracted from the underground operations via the
mine access portal and no dewatering bores exist.
The Ravensworth North Project (RNP) has recently been approved and is inherently linked to the RUM
water management system. The RUM CHPP will process coal from the RNP, while the RUM Highway
Dam (the CHPP water supply storage) will receive tailings return water from a number of RNP tailings
storage facilities. Pumps at the Highway Dam will facilitate transfer of water to and from the RNP via
the RNP Booster Dam (refer Figure 2a).
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 4 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
The key components of the water management system at RUM are shown in schematic fashion in
Figure 3. The catchment area and capacity of each water storage is given in Table 2.
Table 2
Ravensworth Underground Mine Water Storages
Storage Catchment
Area (ha)
Surface
Area (ha)
Capacity
(ML)
Eastern Dam 6.1 0.23 4.0
Highway Dam 6.6 5.43 264.1
Office Dam 20.0 0.34 9.8
Pit Top Dam 12.2 0.26 6.3
ROM Dam 3.2 0.19 3.9
Product Coal Collection Dam 38.5 0.82 17.8
Product Coal Stockpile Dams 6.9 0.46 8.0
Product Coal Construction Dam 6.3 0.16 1.0
The Highway Dam is the main water storage on site and is the main source of make-up water for the
Coal Handling and Preparation Plant (CHPP) and supply to the underground operations.
The CHPP is by far the largest consumer of water on site, using an average of 62.1 ML/month, while
dust suppression usage (i.e. of haul roads and stockpiles) is estimated to average around
0.5 ML/month. The majority of CHPP demand is supplied by recycled tailings water from the
Ravensworth South Tailings Dam. Additional make-up is provided from water held in other storages on
site, including surface facilities dams, which collect runoff from the approximately 132 ha catchment
area of the site and groundwater from underground mine dewatering as well as water recycled from
underground mining operations. Underground mining operations currently require approximately
17.5 ML/month. Supply of water to the underground is required for various uses such as operation of
underground mining equipment and dust suppression. It is anticipated that the underground water use
and water make will increase as the mine progresses (refer Section 2.0).
Supply of potable water to offices, workshops, bathhouses and underground workings is trucked to
site. Sewage treatment at the pit-top facilities is provided by a dedicated Sewage Treatment Plant
(STP). The STP has primary and secondary treatment systems. Effluent from the STP is irrigated on
dedicated land located within the mine water management system adjacent to the Highway Dam.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 5 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 2a Site Layout General
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 6 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 2b Site Layout Surface Facilities
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 7 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 3 Ravensworth Underground Mine Water Management System Schematic
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 8 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
The surface water management system of RUM involves a number of interlinked dams, their
catchments, the tailings storage, the underground mining operation, the CHPP and water pumping
systems. The main storages/features are as follows:
The ROM Dam captures runoff from the run of mine (ROM) coal stockpile area and drains under
gravity via a pipeline into the Pit Top Dam.
The Pit Top Dam captures runoff from a portion of the pit top and rail loop facilities and, in addition
to receiving gravity inflow from the ROM Dam, also receives water pumped from the underground
workings. RUM is currently investigating alternative arrangements for underground dewatering to
other surface storage dams. Water in the Pit Top Dam is pumped out to the Office Dam. Currently
RUM is in the process of designing an upgrade to this system following an offsite discharge event.
These works are focused on increasing the capacity of the dam, improving the reliability and
capacity of pumping infrastructure and also optimising water management. Preliminary designs
(refer Figure 4) suggest a total capacity of approximately 12 ML can be obtained by these works
while a rock-lined spillway will provide safe access for de-silting purposes. It is anticipated that the
enlargement project will be completed by the end of quarter 1 2013.
The Office Dam captures the majority of runoff from surface infrastructure facilities (including the
CHPP and the rail loop). Water in the Office Dam is pumped out to the Highway Dam.
The Eastern Dam captures runoff from a laydown/storage area and is pumped to the Highway Dam.
The Product Coal Construction Dam captures runoff from a small catchment area and is pumped
out to the Product Coal Stockpile Dam.
The Product Coal Stockpile Dams capture runoff from the product coal stockpile and accumulated
water is pumped to the RCT Dam. These dams comprise a sediment dam and a storage dam (the
former draining into the latter).
The Product Coal Collection Dam captures runoff from the product stockpile. Water from the
Product Coal Collection Dam is pumped out to the Highway Dam.
CHPP tailings thickener underflow is pumped to a secondary flocculation facility located adjacent to
the discharge point at the Ravensworth South Tailings Dam. Water from settling tailings and runoff
reporting to the storage is reclaimed via staged settling dams and returned by pumping to the
Highway Dam.
The Highway Dam is a turkeys nest structure which receives or will receive pumped inflow from the
Office Dam, Product Coal Collection Dam, Eastern Dam, Ravensworth South Tailings Dam,
Ravensworth North Tailings Storages, Ravensworth North Booster Dam and Lake Liddell (Hunter
River WALs). Water is pumped out of the Highway Dam to the underground and CHPP.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 9 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 4 Preliminary Design Layout of Pit Top Dam Upgrade
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 10 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
RUM currently holds 6 credits under the Hunter River Salinity Trading Scheme (HRSTS). However,
RUM do not have discharge infrastructure and there are no licensed discharge points. Therefore these
credits are available to transfer to other Xstrata Coal New South Wales (XCN) operations in the event
of a discharge opportunity. Current approval allows transfer of water between RUM and Ravensworth
Operations (which is being incorporated into the RNP) however this infrastructure is currently being
upgraded and transfer is not possible at present.
In compliance with Condition L1.1 of Environmental Protection Licence 10337 under Section 120 of the
Protection of the Environment Operations Act (1997), saline mine water cannot be discharged from
RUM.
2. SITE WATER BALANCE
A life-of-mine water balance model of the RUM complex has been developed by Gilbert & Associates Pty Limited. The structure of the model is generally per the schematic in Figure 3.
The model operates on a sub-daily time-step and can be setup to simulate any period up to the projected end of RUM operations. The simulations reported below correspond to the planned 12 ¼ year mine life - from 1st May 2012 to 31st July 2024. Surface catchment areas of the mine were simulated using supplied plans and were constant over the life of the mine. Total catchment area reporting to the RUM water management system is 91.3 ha.
Annually varying ROM coal tonnages (which affect CHPP water demand) are expected to be between 1.5-5.7 Mtpa and are detailed on an annual basis in Table 3. Underground mine groundwater inflow
rates were taken from groundwater modelling by Mackie Environmental Research (MER, 2011) and vary up to 1.6 ML/d for the Liddell seam and 1.2 ML/d for the Pikes Gully seam.
Table 3
ROM Coal Tonnages
Year ROM Coal (Mt)
2012 1.5
2013 4.7
2014 4.2
2015 5.0
2016 3.9
2017 4.9
2018 4.2
2019 5.7
2020 4.6
2021 5.3
2022 3.4
The AWBM (Boughton, 2004) was used to simulate runoff from rainfall on the various catchments and landforms across the mine area. Model rainfall-runoff parameters have been taken from studies conducted at similar mining operations, along with calibration against local streamflow records and experience with similar projects. Different sub-catchment types were used.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 11 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
The model simulates 119, 12 ¼ year mine life “sequences”, derived using the climatic record from 1892 to 20101. The first sequence uses climatic data from 1892-1905, the second 1893-1906 the third 1894-1907 and so on. The Hunter River IQQM2 was first run to estimate allocation levels for the next 12 ¼ years (these estimates are affected by current allocation levels, regulating storage levels and the historical rainfall/streamflow data set used). The model used output from the Hunter River IQQM in order to simulate variations in available Hunter River water in parallel with climatic variations.
Based on data provided by RUM, approximately 503 ML of water was calculated held in storages on site as at 1st May 2012.
The average predicted water balance (averaged over the simulation period) for median, wet (90th
percentile) and dry (10th percentile) rainfall sequences is summarised in Table 4.
Table 4
Summary of Simulated Annual Inflows and Outflows (ML/annum)
Flows 10th Percentile Rainfall
Sequence (Dry)
Median Rainfall Sequence
90th Percentile Rainfall
Sequence (Wet)
Inflows
Catchment Runoff 169 229 277
Groundwater 496 496 496
Hunter River Licensed Extraction 953 623 277
Tailings Water 1,399 1,400 1,410
From Ravensworth North Booster Dam (mine runoff)
1,474 1,735 1,878
Outflows
CHPP Supply 3,828 3,936 3,936
Evaporation 77 83 84
Underground Supply 259 259 259
To Ravensworth North Booster Dam
209 133 74
Table 4 shows that the main source of supply to site is water reclaimed from the tailings storages and water imported to RUM from the RNP via the Booster Dam. Water supplied to the CHPP dominates the outflows from the RUM water balance.
Water supply security can be described in terms of water supply reliability. The average predicted water supply reliability to the CHPP was 97.7 % (that is 97.7 % of the total CHPP demand could be supplied), while the lowest reliability in any 12¼ year sequence was 81.7 %. The average predicted water supply reliability to the underground was greater than 99.9 % (that is more than 99.9 % of the total underground demand could be supplied), and did not drop below this level in any 12 year sequence.
An annual retrospective site water balance for the reporting period will be documented in the Annual Environmental Monitoring Report (AEMR). A monthly internal water accounting system summarises water use and volume of water stored on site for XCN.
1 Additional climate data after 2010 was generated by “wrapping” data from the beginning of the climate record to after 2010. In
this way, the drought period of 2005/06 and the wet period of 2007 could be simulated as occurring at varying times through the mine life.
2 The integrated quantity-quality model is the model used by the NSW Office of Water to simulate the hydrology of the Hunter River Regulated Water Source.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 12 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Measures to minimise water use include:
Tailings thickening and flocculation and the use of water reclaimed from the tailings storage(s) in preference to using Hunter River WALs
Future sourcing of excess water from the RNP in preference to using Hunter River WALs
Storage and use of runoff from disturbed areas in preference to using Hunter River WALs
Use of water reclaimed from underground operations in preference to using Hunter River WALs
Inspections and maintenance of water management infrastructure.
3. EROSION AND SEDIMENT CONTROL PLAN
The objective of this ESCP is to set out strategies to control soil erosion and sediment generation close to the source and thereby minimise the potential for mine activities to adversely affect downstream water quality.
The following principles, which have been taken from the Landcom (2004) guidelines, underpin the approach to erosion and sediment control for the mine site:
Minimising surface disturbance and restricting access to undisturbed areas.
Progressive rehabilitation/stabilisation of mine infrastructure areas.
Separation of runoff from disturbed and undisturbed areas where practicable.
Construction of surface drains to control and manage surface runoff.
Construction of sediment dams or use of existing/modified water storages to contain runoff up to a specified design criterion.
These measures are used to minimise soil erosion and the potential for transport of sediment downstream.
Development activities will generally occur in the following order:
1. Construction of diversion drains (typically upslope of disturbance areas) – these will only be constructed where they will significantly reduce the catchment reporting to disturbance areas.
2. Construction of sediment dams/sumps where required to provide for temporary retention of runoff from disturbance areas.
3. Construction of collection drains (downslope of or within disturbance areas) where required to convey runoff to sediment dams or other storages.
4. Construction of sediment fences and straw bale filters (downslope of disturbance and stockpile areas) where appropriate.
5. Construction works only taking place once erosion and sediment control measures are in place.
The design criteria for sediment control structures are summarised in Table 5
Table 5 Design Criteria for Sediment Control Structures
Sediment Control Structure
Function Design Capacity
Upslope diversion drains Reduce runoff from undisturbed areas onto
disturbed areas
Peak flow calculated for 1 in 20 year* critical duration rainfall event (DECCW,
(2008), Table 6.1)
Downslope collection drains
Intercept and convey disturbed area runoff water to
sediment dams/sumps
Peak flow calculated for 1 in 20 year* critical duration rainfall event (DECCW,
(2008), Table 6.1)
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 13 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Sediment dams Containment of sediment-laden runoff from disturbed
areas with more than 150 m3/yr estimated soil loss
(Landcom (2004), Section 6.3.2(d))
Settling Zone: Capacity to store the runoff produced from the 90th
percentile*, 5-day rainfall event (DECCW (2008), Table 6.1)
Sediment Zone: Two months calculated soil loss estimated using RUSLE**
(Landcom (2004), Section 6.3.4 (i))
Sediment fences and/or
straw bale filters
Retention/filtration of
suspended sediments
Peak flow limited to less than 50 L/s in
the design 1 in 10 year critical duration rainfall event (Landcom (2004), Section
6.3.7(e))†
* Assuming a duration of disturbance greater than 3 years with a standard, not sensitive, receiving environment.
** Revised Universal Soil Loss Equation (RUSLE) † Assuming a duration of disturbance between 1 and 3 years with a standard sensitivity receiving environment.
To prevent offsite discharge of dirty water from sediment dams, following a rainfall event, water in sediment dams will be pumped back to the mine water system. Sediment dams will be maintained with a minimum practicable volume of water in between rainfall events to ensure sufficient capacity is available when a rainfall event does occur.
The 90th percentile 5-day rainfall event, used in determining the sediment dam settling zone capacity, was calculated to be 39.4 mm from the average of values for Scone and Cessnock3 as given in Table 6.3a in Landcom (2004).
Based on the methodology and parameters contained in Landcom (2004) and DECCW (2008), the settling zone capacity and sediment storage zone capacity and hence required dam capacity are calculated using Equations 1, 2 and 3 below respectively:
Settling Zone Capacity (m3) = Vsettling = 251.8 x A (1)
Sediment Zone Capacity (m3) = Vsediment = 0.5 x Vsettling (2)
Required Dam Capacity (m3) = Vtotal = Vsettling + Vsediment (3)
Where; Vsettling = settling volume
Vsediment = sediment volume
Vtotal = total volume
A = catchment area of the sediment dam (ha)
Water storages at RUM serve both as water management structures and sediment dams. The locations of the sediment control dams employed at RUM are shown in Figure 2b.
Table 6 summarises the minimum sediment dam capacity requirements in comparison to existing surveyed capacities. Additional dedicated sediment dams will be constructed as required.
Table 6
Comparison of Sediment Dam Requirements to Existing Dam Capacities
Sediment Dam Name
Capacity
(m3)
Required Settling Zone Volume (m3)
Required Sediment
Zone Volume (m3)
Minimum Required
Total Volume (m3)
Eastern Dam
4000 1526 763 2289
3 Table 6.3a of Landcom (2004) gives 90
th percentile 5-day rainfall depths for Cessnock and Scone of 42.8 mm and 35.9 mm
respectively
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 14 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Office Dam
(inc. Product Coal
Construction Dam)
10800 6621 3310 9931
Pit Top Dam
6300 3072 1536 4609
ROM Dam
3900 806 403 1209
Product Coal Collection Dam
17800 9696 4848 14544
Product Coal Stockpile Dams
8000 1743 871 2614
Dam batters are typically covered with topsoil following construction and/or seeded to promote revegetation and assist with minimising the potential for erosion of the dam batters.
Activities that have the potential to cause or increase erosion, and subsequently increase the generation of sediment at the site, include exposure of soils during construction of mine infrastructure (i.e. during vegetation clearance, soil stripping and earthworks activities) and stockpiling mine materials. The following components have the potential to generate sediment:
coal handling and preparation plant (CHPP);
earthen bunds and temporary topsoil stockpiles;
coal stockpiles;
access and haul roads;
water management infrastructure (pumps, pipelines, dams, sumps and drains);
exploration sites; and
general construction works on site.
Routine inspections of sediment control structures as well as inspections following rainfall events of 25 mm or more in a 24 hour period are conducted by RUM personnel. During these inspections, sediment control structures are inspected for capacity, structural integrity and effectiveness. Inspections are documented using a check sheet developed by RUM.
Where inspections indicate substantial accumulation of sediment in a sediment dam, clean-out is undertaken so as to reinstate the minimum required volumes given in Table 6. Silt fences and straw bale filters are inspected and trapped sediment removed or straw bales replaced as necessary. Removed sediment is placed in areas upslope of existing sediment control structures, mine water
storages or tailings storages.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 15 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
4. SURFACE WATER MONITORING PROGRAM
The objective of the surface water monitoring program (SWMP) is to provide details of the monitoring
program used to monitor the effects of RUM on existing surface water bodies, in order to assist in
detecting if any significant off-site impacts occur as a result of mining and to trigger response plans to
adverse impacts.
4.1 Baseline Data
Bayswater Creek is a highly modified stream due to the construction of Lake Liddell and the creek
diversion located between Lake Liddell and its confluence with the Hunter River. Bowmans Creek is a
moderately modified stream in its lower reaches with Ashton Coal Operations currently constructing
two diversions on this creek. Historical data relating to water quality and flows in Bayswater Creek and
Bowmans Creek is summarised below. This data is used as a baseline for on-going monitoring of the
impacts of mining activities on surface water in the Bayswater Creek and Bowmans Creek catchment
areas. The baseline data end date has been assumed at 14th of January 2007 as this is the date at
which mining of LW1 at RUM began.
4.11 Water Quality
Water quality in the downstream watercourses has been monitored since 1993 at GS210130. Water
samples have been monitored for pH and total suspended solids (excluding NOW gauging stations) and
electrical conductivity (EC). Sampling points include locations along Bayswater Creek and Bowmans
Creek. The sampling locations are indicated on Figure 5 and water quality data summarised in Table 7.
Table 7
Summary of Baseline Surface Water Quality Monitoring Data
Creek Site Data
Collection
Period
pH EC (μS/cm) TSS (mg/L
Min Max Min Max Min Max
Baysw
ate
r
Cre
ek
GS210110* 19/1/1994 –
14/1/2007
- - 658 4712 - -
Bayswater
Midstream
1/7/2004 –
4/1/2007
7.1 8.4 1250 7000 3 52
Bayswater
Downstream
1/7/2003 –
3/1/2006
7.2 8.6 680 7110 1 235
Bow
mans
Cre
ek
BCK6 1/6/2002 –
1/11/2006
7.2 9.3 719 5440 1 116
GS210130* 28/10/1993 –
14/1/2007
- - 10 2790 - -
* Data source: NOW, 2012
4.12 Streamflow
Streamflow gauging stations on both Bayswater Creek and Bowmans Creek are maintained by the NSW
Office of Water (NOW). The locations of these stations are shown on Figure 5 and available streamflow
data is summarised in Table 8. As illustrated in Figure 5, the gauging station on Bayswater Creek is
immediately downstream of the spillway from Lake Liddell.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 16 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Table 8
Summary of Recorded Baseline Streamflow Monitoring Data
Station: Bayswater Creek
GS210110*
Bowmans Creek
GS210130*
Period of Record: 19/01/1994 to 14/01/2007 28/10/1993 to 14/01/2007
No. Missing Days: 572 547
No. Zero Flow Days: 134 19
Max. Daily Flow (ML/d): 1385 12036
Mean Annual Flow (ML/d): 2529 11097
* Data source: NOW, 2012
Figure 5 Surface Water Monitoring Locations
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 17 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
4.2 Surface Water Impact Assessment Criteria
Impact assessment criteria can be described as trigger levels, which, if triggered, would lead to a
response in terms of more intensive monitoring, investigation and ultimately, if required, remedial
action. The SGWRP contains details of all responses relating to each impact assessment criterion.
Surface water impact assessment criteria focus on particular areas and each area may contain more
than one criterion. Table 9 shows a summary of each focus area and the associated impact
assessment criteria.
Table 9
Surface Water Impact Assessment Criteria
Focus Area Parameter Trigger Value
Surface water
quality (local creeks)
pH If recorded value at a monitoring site is
greater than the 80th percentile of baseline
data for 2 consecutive readings or, for pH,
less than the 20th percentile of baseline data
for 2 consecutive readings
EC
TSS
Riparian and in-
stream vegetation
Density of vegetation –
photographic log
If photographs suggest a visual degradation
in vegetation cover for 4 consecutive
monitoring periods
Channel stability Erosion/deposition
features –
photographic log
If it is obvious that erosional and/or
depositional features are changing with time
4.3 Monitoring Program
The SWMP for RUM involves the monitoring of all surface water impact assessment criteria (refer Table
9). A summary of the monitoring locations and parameters monitored is provided in Table 10. In
accordance with Schedule 2 Condition 11 (d) of the Development Consent, the impacts of the operation
on private water users will be monitored, assessed and responded to in accordance with the SWGRP.
There are no private water users on Bayswater Creek (NSW Trade and Investment, 2012). There are
10 private water users on Bowmans Creek with 13 extraction licenses (NSW Trade and Investment,
2012). The existing water monitoring points shown in Figure 5 will be used to monitor and assess any
impacts on these users. A summary of the surface water monitoring program is provided in Table 10.
Table 10
Summary of Surface Water Monitoring Program
Creek Site Monitored By Parameters Frequency
Baysw
ate
r Cre
ek
GS210110 NOW Flow, EC Continuous
Bayswater Midstream Liddell Coal
Operations**
pH, EC, TSS,
photo point*
Monthly
Bayswater
Downstream
Liddell Coal
Operations**
pH, EC, TSS,
photo point*
Monthly
W114 Ravensworth
Operations**
pH, EC, TSS Monthly
W115 Ravensworth pH, EC, TSS Monthly
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 18 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Operations** Bow
mans C
reek
BCK6 Liddell Coal
Operations**
pH, EC, TSS Monthly
BMC4 Xstrata Coal Mt
Owen**
pH, EC, TSS Monthly
GS210130 NOW Flow, EC Continuous
EPL3 Ravensworth
Operations**
pH, EC, TSS Monthly
EPL4 Ravensworth
Operations**
pH, EC, TSS Monthly
* Monitoring performed by RUM on a quarterly basis
** Xstrata Coal NSW Managed Operation
4.31 Water
RUM undertake routine monitoring of water usage, water imported to the mine & volumes of water
stored onsite, as part of a program of monitoring & reporting undertaken by XCN. The data is used to:
monitor trends in water use and efficiency;
check stored water inventory; and
assist in future mine water supply and management planning.
Table 11 provides a summary of monitoring undertaken for the water balance.
Table 11
Summary of Water Balance Monitoring
Monitoring of Description Location Frequency
Site Water Supply Water imported to site using
Hunter River WALs via
agreement with Macquarie
Generation (Lake Liddell)
Flow meter west
of the Highway
Dam
Continuous
CHPP Water
Usage
Water supplied to the CHPP
from the Highway Dam
Flow meter at
the CHPP
Continuous
Underground Mine
Extraction
Water volume pumped from
underground operation into
surface water management
facilities
Flow meter at
the portal
Continuous
Underground Mine
Supply
Water volume pumped from
Highway Dam to underground
operations
Flow meter at
the Highway
Dam
Continuous
Storage Volume Water level Individual
storages
Continuous
and/or monthly
4.311 Streamflow
RUM will continue to make use of the streamflow monitoring data collected by NOW.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 19 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
4.312 Water Quality
Table 10 summarises surface water quality monitoring undertaken at sites within and surrounding
RUM. Site locations are also shown on Figure 5.
The results of water quality monitoring are reported in the AEMR. The AEMR includes an assessment of
results in terms of off-site impacts as a result of mining.
Surface water quality monitoring and sample collection, storage and transportation will be undertaken
in accordance with the procedures outlined in the relevant sections of the Australian Standard for
Water Quality Sampling AS/NZS5667.1-1998. Laboratory analysis will be undertaken by a laboratory
which has relevant accreditation by the National Association of Testing Authorities (NATA), Australia.
4.313 Stream Health and Channel Stability
The stream condition and stream health of Bayswater Creek is heavily influenced by the releases from
Lake Liddell. RUM do not undertake licensed discharges. Accordingly, the impact of RUM on
Bayswater Creek stream health is considered to be low. Notwithstanding, RUM will undertake photo
point monitoring along Bayswater Creek at the two stations nearest RUM surface facilities: Bayswater
Midstream and Bayswater Downstream (refer Figure 5).
Monitoring of riparian vegetation and channel stability is to be undertaken quarterly by taking four
photographs at each surface water monitoring site on Bayswater Creek; looking upstream, looking
downstream, looking at the left bank4 and looking at the right bank5. These photographs are to be
documented with the location, direction and date.
5. GROUNDWATER MONITORING PROGRAM
The aim of the GMP is to provide details of the monitoring program used to monitor the effects of RUM
on surrounding groundwater aquifers. The GMP also exists in order to assist in detecting if any
significant off-site impacts occur as a result of mining and to trigger response plans to adverse
impacts.
5.1 Baseline Data
Groundwater levels and basic groundwater quality parameters (pH and EC) have been measured
routinely at a number of piezometers across and external to the site. Historical groundwater level and
quality data collected at the piezometers shown in Figure 6 are summarised in Table 12.
Table 12
Historical Water Quality Results (Ravensworth Operations)
Seam Monitoring Bore pH EC (μS/cm)
Min Max Mean Min Max Mean
Bayswater
NPZ3 Mid 6.8 7.1 7.0 7,780 12,990 11,570
NPZ4 Mid 6.1 7.2 6.5 5,470 6,440 6,113
Lemington NPZ1 Tall 6.9 7.4 7.2 6,740 10,400 9,310
4 Left bank refers to the bank to the left when looking in a downstream direction.
5 Right bank refers to the bank to the right when looking in a downstream direction.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 20 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
NPZ2 Tall 8.1 8.4 8.3 9,460 9,830 9,613
NPZ3 Tall 7.3 8.4 7.6 7,410 9,830 9,041
NPZ4 Tall 6.8 7.4 7.1 6,800 8,330 7,803
Pikes Gully
CS4641C Pumps 11.2 12.2 11.7 6,170 7,700 6,969
CS4539A (S2) Hill 6.9 8.2 7.3 4,850 7,560 6,983
Liddell
CS4536 (HF7) 6.9 7.4 7.1 9,170 14,900 13,261
CS4545 (S4) 8.7 12.5 10.5 5,990 10,700 8,427
CS4547C (EE4) 6.8 8.1 7.1 8,180 13,700 12,552
Borehole P / SDH17 /
SDH18
7.1 9.6 8.3 6,590 8,900 7,573
Barrett Site 11 Conveyor 6.9 7.1 7.0 10,200 10,630 10,343
Site 3 Inside Gate 6.7 7.0 6.9 10,060 10,600 10,270
Note: Data in the table above is after Umwelt (2009)
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 21 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Figure 6 Groundwater Monitoring Locations
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 22 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
5.2 Groundwater Assessment Criteria
Impact assessment criteria can be described as trigger levels, which, if triggered, would lead to a
response in terms of further, more intensive monitoring, investigation and ultimately, if required,
remedial action. The SGWRP contains details of all responses relating to each impact assessment
criterion. Groundwater impact assessment criteria focus on particular areas and each area may
contain more than one criterion. Table 13 provides a summary of each focus area and the associated
nominated impact assessment criteria.
Table 13
Groundwater Impact Assessment Criteria
Focus Area Parameter Trigger Value
Groundwater
Level and
Baseflow in
Watercourses
Drawdown The larger of:
a) 10% greater than model prediction*; or
b) 1 m greater than model prediction.
If:
i) Three or more alluvial bores exceed the above
in one round of monitoring
OR
Any alluvial bore exceeds the above for three
consecutive readings
ii) Average drawdowns for the fractured rock bore
network exceed the above for two consecutive
readings
Groundwater
Inflow to the
Underground
Inflow Sustained exceedence 10% greater than model
prediction* for a period greater than 6 months.
Riparian
Vegetation
Density of
vegetation –
photographic log
If photographs suggest a visual degradation in vegetation
cover for 4 consecutive monitoring periods
* Groundwater model documented in MER (2011)
There are no known Groundwater Dependant Ecosystems (GDEs) within the RUM complex (Umwelt,
2011) and therefore no impact assessment criteria have been set for groundwater ecology
Groundwater level impact assessment criteria have been designed to ensure that measured
depressurisation due to mining of the coal measures and associated impacts on the alluvial aquifer
systems do not significantly vary from modelled predictions (MER, 2011).
5.3 Monitoring Program
5.31 Monitoring Bores
Monitoring of water levels and water quality parameters is undertaken at a number of
bores/piezometers as summarised in Table 14. Chemical speciation is also undertaken in selected
bores as indicated in Table 14 twice yearly. Bore locations are shown in Figure 6. RUM is pursuing a
data sharing agreement with the Ashton Coal Project in order to access information collected from
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 23 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
seven known bores: WML115, WML175, RSGM1, RM3, RM4, RM5, and RM6.
Table 14
Summary of Groundwater Monitoring Program
Monitored by Piezometer
No.
Target Seam Parameters Frequency
Ravensw
ort
h O
pera
tions
Coffey Dam
Borehole Liddell Level, pH, EC
Monthly (Level),
Quarterly (Quality)
CS4545 (S4) Liddell Level, pH, EC Monthly (Level),
Quarterly (Quality)
CS4641C Lower Pikes Gully Level, pH, EC Monthly (Level),
Quarterly (Quality)
CS4655
Bayswater, Lemington
LMH, Lemington LMA,
Upper Pikes Gully,
Upper Arties, Upper
Liddell, Lower Liddell,
Barrett
Level 12 hourly
Note: Data in the table above is after Umwelt (2009)
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 24 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Table 14 continued
Summary of Groundwater Monitoring Program
Monitored
by
Piezometer
No. Target Seam Parameters Frequency
NPZ1 Alluvium, Bayswater,
Lemington Level, pH, EC
Monthly (Level), Quarterly
(Quality)
NPZ2 Alluvium, Bayswater,
Lemington Level, pH, EC
Monthly (Level), Quarterly
(Quality)
Ravensw
ort
h O
pera
tions
NPZ5 Alluvium, Broonies Level, pH, EC Monthly (Level), Quarterly
(Quality)
NPZ6 Alluvium, Broonies Level, pH, EC Monthly (Level), Quarterly
(Quality)
NPZ7 (SP1) Alluvium, Broonies,
Bayswater Level, pH, EC
Monthly (Level), Quarterly
(Quality)
RNVW1
Bayswater, Lemington
LMH, Lemington LMA,
Upper Pikes Gully,
Upper Arties, Upper
Liddell, Lower Liddell,
Barrett
Level 12 hourly
RNVW2
Bayswater, Lemington
LMH, Lemington LMA,
Upper Pikes Gully,
Upper Arties, Upper
Liddell, Lower Liddell,
Barrett
Level 12 hourly
Note: Data in the table above is after Umwelt (2009)
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 25 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Table 14 continued
Summary of Groundwater Monitoring Program
Monitored
by
Piezometer
No. Target Seam Parameters Frequency
RNVW4
Bayswater, Lemington LMH,
Lemington LMA, Upper Pikes
Gully, Upper Arties, Upper Liddell,
Lower Liddell, Barrett
Level 12 hourly
RNVW5
Alluvium, Unnamed, Bayswater,
Lemington H, Lemington A, Upper
Liddell, Barrett
Level 12 hourly
RNVW6
Alluvium, Unnamed, Bayswater,
Lemington H, Lemington A, Upper
Liddell, Barrett
Level 12 hourly
Mt
Ow
en
NPZ13 Swamp Creek Alluvium, Lower
Pikes Gully, Lower Liddell Level, pH, EC
Quarterly
(Level), Six
Monthly
(Quality)
NPZ16 Swamp Creek Alluvium,
Lemington, Upper Liddell Level, pH, EC
Quarterly
(Level), Six
Monthly
(Quality)
GA1 Swamp Creek Alluvium Level, pH, EC
Quarterly
(Level), Six
Monthly
(Quality)
GA2 Swamp Creek Alluvium Level, pH, EC
Quarterly
(Level), Six
Monthly
(Quality)
BC-SP19 Bayswater Creek Alluvium Level, pH, EC 12 hourly
BC-SP22 Bayswater Creek Alluvium Level, pH, EC 12 hourly
Note: Data in the table above is after Umwelt (2009)
5.32 Underground Inflow
Groundwater model predictions (MER, 2011) provide an estimate of the expected rate of groundwater
seepage to mining operations. This seepage may be increased by dewatering of local storage in joints
and fractures which typically occurs over a period of 1 to 3 months after mining. The summation of
both contributions represents the maximum predicted groundwater seepage to the underground
operations. Monitoring of seepage and comparison between measured and predicted rates may
therefore provide early indication of leakage from a remote source such as alluvium.
Volumes of water pumped from the underground operations may be calculated monthly from flow
meter readings at the dewatering point (refer Table 11) and flow meter readings at the underground
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 26 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
supply point at the Pit Top. An estimate of net groundwater inflow to the mine can then be calculated
by subtracting the supply to the underground from the dewatering volumes, with an allowance for
ventilation rise losses. Water quality monitoring is undertaken at the dewatering point on a monthly
basis.
Table 15 provides predicted groundwater inflow rates to the underground and rates including provision
for dewatering of localised storage without contributions from rainfall seepage to the underground
mine via the subsidence zone.
Table 15
Predicted Groundwater Inflow to Underground (MER, 2011)
Year Estimated Strata Seepage
(ML/d)
2012 1.8
2014 2.2
2016 2.9
2018 3
2020 3.1
2022 2.5
To determine the impact RUM may have on regional and surrounding aquifers, groundwater levels are
monitored as per the groundwater monitoring schedule in Table 14.
MER (2011) state “…there are no identified private boreholes within or near the approved or proposed
modified operations that are likely to be affected”.
There are no known Groundwater Dependant Ecosystems (GDEs) within the RUM complex (Umwelt,
2011).
Future revisions of this Water Management Plan will include copies of future bore construction logs as
required.
The results of groundwater monitoring are reported in the AEMR. The AEMR includes an assessment of
results in terms of off-site impacts as a result of mining.
6. SURFACE AND GROUNDWATER RESPONSE PLAN
6.1 Objective
The objective of this SGWRP is to present a set of protocols to be followed and actions for
implementation should the surface or groundwater assessment criteria be exceeded. These protocols
will be followed in addition to the RUM Incident Management Procedure (2012) which states:
Should the incident be deemed a notifiable incident to the Environmental Protection Authority
(EPA), (that is, pollution incidents threatening material harm to the environment) this must be
done immediately. Upon becoming aware of the incident notification of the necessary
stakeholders must be completed immediately. Five different authorities must be notified in
the following order:
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 27 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
Information that must be reported at the time of notification includes:
The type of pollution;
Its concentration;
The circumstances in which the pollution incident occurred
The names, positions and 24 hour contact details for those personnel who are involved
in managing the incident; and
The action taken to deal with the incident.
Any required information that is not known at the time of notification must be communicated
to each of the relevant authorities immediately after it becomes known. These authorities
must continue to be notified each time new information becomes available.
6.2 Protocol for Exceedence of Surface Water & Groundwater Trigger Values
In the event of a surface water or groundwater assessment criterion being exceeded, the following
protocol will be followed:
1. Check and validate the data which indicates an exceedence of the criterion.
2. A preliminary investigation will be undertaken to establish the cause(s) and determine whether changes to the water management system are required. This will involve the consideration of the
monitoring results in conjunction with:
a) site activities being undertaken at the time;
b) baseline monitoring results;
c) surface water/groundwater results at nearby locations;
d) the prevailing and preceding meteorological conditions;
e) available data indicating releases from Lake Liddell;
f) changes to the land use/activities being undertaken in the contributing catchment area; and
g) hydrological conditions.
3. If the preliminary investigation shows that the impact is linked to activities undertaken by RUM, a report will be emailed to the Department of Planning & Infrastructure (DPI) and any other relevant department. Causal factors will be addressed and rectified if possible. Contingency measures will
be developed in consultation with the DPI and any other relevant department and implemented in response to the outcomes of the investigation.
4. Remedial/compensatory measures will be developed in consultation with DPI and any other relevant department and implemented in response to the outcomes of the investigations.
5. Monitoring would be implemented as required to confirm the effectiveness of remedial measures.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 28 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
6.3 Protocol for Exceedence of Stream Health and Channel Stability Triggers
In the event of a stream health assessment criterion being exceeded, the following protocol will be
followed:
6. The area will be inspected to confirm the condition of vegetation in the photograph and the condition of vegetation in other similar areas of the site.
7. An preliminary investigation will then be undertaken and will involve the consideration of the visual inspection documented above in conjunction with:
a) site activities being undertaken at the time;
b) baseline surface water and groundwater monitoring results;
c) surface water and groundwater results in nearby locations;
d) the prevailing and preceding meteorological conditions;
e) available data indicating releases from Lake Liddell;
f) hydrological conditions; and
g) changes to the land use/activities being undertaken in the contributing catchment or
hydrogeological regime.
8. If the investigation shows that the vegetation impact is linked to activities undertaken by RUM, a report will be emailed to the DPI and any other relevant department. Causal factors will be
addressed and rectified if possible. Contingency measures will be developed in consultation with DPI and any other relevant department and implemented in response to the outcomes of the investigation. Such contingency measures could involve direct revegetation or vegetation offsets.
9. Monitoring would be implemented as required to measure the effectiveness of contingency measures if appropriate.
In the event of a channel stability assessment criterion being exceeded, the following protocol will be
followed:
1. Undertake a ground inspection to validate the photograph and confirm the magnitude of the change (increase in erosion/deposition) evident in the photograph.
2. If this observation confirms that significant additional erosion or deposition has occurred and is likely to have been caused by RUM, DPI and any other relevant department will be notified via email.
3. An investigation will then be conducted in consultation with DPI and any other relevant department and will involve the consideration of one above in conjunction with:
a) site activities being undertaken at the time;
b) the prevailing and preceding meteorological conditions;
c) available data indicating releases from Lake Liddell;
d) hydrological conditions; and in particular any high runoff events which may have
preceded the change; and
e) changes to the land use/activities being undertaken in the contributing catchment area.
4. If the investigation shows that the creek channel impact is linked to activities undertaken by RUM, a report will be emailed to the DPI and any other relevant department. Causal factors will be addressed and rectified if possible. Contingency measures will be developed in consultation with DPI and any other relevant department and implemented in response to the outcomes of the investigation. Such contingency measures could involve bank and channel stabilisation methods (i.e. promotion of riparian vegetation, use of rip-rap or removal of sediment accretion).
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 29 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
5. Additional monitoring will be implemented as required to measure the effectiveness of contingency measures.
6.4 Protocol for Impacts on the Water Supply of Private Landowners
No privately owned groundwater bores exist “within or near the approved or proposed modified
operations that are likely to be affected” (MER, 2011); hence an impact on the groundwater supply of
private landowners is not expected. There are no privately owned surface water storages within the
RUM colliery holding boundary and hence impacts of the surface water supply of private landowners is
not expected. In the event that a complaint is received, this would be handled in accordance with RUM
procedures, which includes recording the details of the complaint, providing feedback to the
complainant (including corrective actions) and reporting of investigation outcomes and corrective
actions. Compensation would be developed in consultation with the private landowner where it can be
demonstrated that RUM has adversely affected the water supply. To date, no complaints have been
received in relation to groundwater or surface water supply of private landowners.
6.5 Roles and Responsibilities
The roles and responsibilities assigned to water management on site under this WMP are outlined in
Table 16.
Table 16
Roles and Responsibilities for Site Water Management
Water Management Component Responsible Entity
Provide resources required to implement the
WMP Operations Manager
Review and updates of WMP Environment and Community Manager
Management and maintenance of water
management infrastructure Services Superintendent and CHPP Manager
Monitoring Environment and Community Manager
Investigation of incidents Environment and Community Manager
Reporting (including AEMR and incident
reporting) Environment and Community Manager
7. REFERENCES
7.1 Legislation
Environmental Planning & Assessment Act 1979
Protection of the Environment Operations Act 1997
7.2 Australian Standards
Australian Standard for Water Quality Sampling AS/NZS5667.1-1998
7.3 Xstrata plc
Xstrata plc Sustainable Development Standard 10 – Environment, Biodiversity and Landscape Functions
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 30 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
7.4 Xstrata Coal NSW
XCN SD GDL 0010 10.0 Environment, Biodiversity & Landscape Functions
XCN SD ANN 0078 10.12 Water Management Strategy
XCN SD ANN 0040 - 10.3 Pipeline Management
XCN SD ANN 0077 – 10.11 Erosion and Sediment Control Management
7.5 Ravensworth Underground Mine
RUM SD PRO 0057 Underground Water Sample Collection
RUM SD FRM 0036 XCN Water Management / Water Supply Questionnaire
RUM SD PRO 0054 Raw Water Access (Surface Water Licences) System Procedure
RUM SD PRO 0055 Dam Water Response System Procedure - Pit Top and Office Dams
RUM SD PRO 0056 Dam Levels Operating System Procedure
RUM SD PLN 0020 Private Water Supply Management Plan
7.6 Licences
RUM SD EXT 0470 Groundwater Licences - Mine Dewatering - Bore Licence Renewal Certificate - 20BL168023
RUM SD EXT 0471 Groundwater Licences - Mine Dewatering - Bore Licence Renewal Certificate - 20BL171422
RUM SD EXT 0472 Surface Water Licence - Water Access - Certificate of Title WAL8964
RUM SD EXT 0473 Surface Water Licence - Water Access - Certificate of Title WAL8964
RUM SD EXT 0474 Surface Water Licence - Water Access - Certificate of Title WAL1046
RUM SD EXT 0475 Surface Water Licence - Water Access - Certificate of Title WAL1046
RUM SD EXT 0476 Surface Water Licence - Water Access - Certificate of Title WAL1325
RUM SD EXT 0477 Surface Water Licence - Water Access - Certificate of Title WAL1325
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 31 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
8. APPENDICES
8.1 Appendix 1—Development Consent Conditions
Extract taken from Development Application 104/96 under section 101 of the Environmental Planning and Assessment Act, 1979
Schedule 2 – Conditions of Development Consent
SITE WATER MANAGEMENT PLAN
8. The Applicant shall prepare and implement a Site Water Management Plan for the development to the satisfaction of the Director-General. This plan must:
a) be prepared in consultation with NOW, DECCW and I&I NSW;
b) be submitted to the Director-General for approval by the end of December 2009; and
c) include:
a Site Water Balance;
an Erosion and Sediment Control Plan;
a Surface Water Monitoring Plan;
a Groundwater Monitoring Program; and
a Surface and Groundwater Response Plan.
SITE WATER BALANCE
9. The Site Water Balance must:
a) include details of:
sources and security of water supply;
water use and management on site;
any off-site water transfers or discharges; and
reporting procedures; and
b) describe measures to minimise water use by the site.
EROSION AND SEDIMENT CONTROL
10. The Erosion and Sediment Control Plan must:
a) be consistent with the requirements of Landcom’s Managing Urban Stormwater: Soils and Construction manual;
b) identify activities that could cause soil erosion and generate sediment;
c) describe measures to minimise soil erosion and the potential for transport of sediment
downstream;
d) describe the location, function and capacity of erosion and sediment control structures; and
e) describe what measures would be implemented to maintain the structures over time.
SURFACE WATER MONITORING
11. The Surface Water Monitoring Program must include:
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 32 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
a) detailed baseline data on surface water flows and quality in creeks and other waterbodies that could potentially be affected by the development;
b) surface water and stream health impact assessment criteria;
c) a program to monitor;
surface water flows and quality;
stream health; and
channel stability;
d) a program to monitor any impacts on private water users and water levels in privately-owned farm dams; and
e) reporting procedures for the results of the monitoring program.
GROUNDWATER MONITORING
11A. The Groundwater Monitoring Program must include:
a) groundwater impact assessment criteria, including trigger levels for investigating any potentially adverse groundwater impacts of the development;
b) a program to monitor the volume and quality of groundwater seeping into the underground mine workings;
c) a program to monitor:
groundwater inflows to the underground mining operations;
impacts on regional aquifers and surrounding aquifers;
impacts on the groundwater supply of potentially affected private landowners; and
impacts on groundwater dependent ecosystems and riparian vegetation;
d) reporting procedures for the results of the monitoring program.
SURFACE AND GROUNDWATER RESPONSE PLAN
11B. The Surface and Groundwater Response Plan must describe the measures and/or procedures that would be implemented to:
a) respond to any exceedances of the surface water, stream health and groundwater impact assessment criteria;
b) offset the loss of any baseflow to watercourses caused by the development where the impact assessment criteria are exceeded;
c) compensate landowners of privately-owned land whose water supply is adversely affected by the development; and
d) mitigate and/or offset any adverse impacts on groundwater dependent ecosystems or riparian vegetation.
Ravensworth Underground Mine
Sustainable Development Plan
RUM SD PLN 0040
Water Management Plan
Status: Approved
Version: 3.0
Effective: 20/09/2012
Review: 20/09/2015
Page 33 of 33
THIS DOCUMENT IS UNCONTROLLED UNLESS VIEWED ON THE INTRANET
9. CONTROL AND REVISION HISTORY
9.1 Document information
Property Value
Approved by Environment & Community Manager
Document Owner Environment & Community Coordinator
Effective Date 20/09/2012
Keywords
Environment, Community, Water, Management, Plant, WMP, Groundwater, surface,
consent, monitoring
For a complete list of document properties, select View Properties from the document’s context menu on the intranet.
9.2 Revisions
Version Date reviewed
Review team
(consultation) Nature of the amendment
1 31/08/09 James Barben
Vicki McBride
Initial MP
2 06/09/12 James Barben
Chris Standing
Publication of revised Water Management Plan following approval
by Department of Planning & Infrastructure.
3 20/09/12 Amendments to document properties (version history)