MagicPlus

Takuya Iwanaga

u3017798 Project Manager

MamdouhQahl

u3029656 Quality Manager

Yasir Ali u3055632 Communication Manager

Javad Nicou u3055845 Risk Manager

[email protected]

Project Idea

Online Lecture

Recorded

Online Classes

Not Interactive

Note Taking

Not Integrated

University Systems

Not Easily Accessible

Online Education Limitations

Interactive Online Education Framework

Framework

Online Lecture

Online Classes

Referencing System

Online Note

Simulation System

3D Modelling for Graphics

Live Coding

IT

Sciences

Art

Project PrototypeIOE Web App Course Page

Takuya

IOE Web App Resource page

IOE Guest Lecture Page

IOE Web App student view

IOE Web App lecturers view

IOE Web App class view

Project Outputs and Outcomes

o To create an integrated front-end for participating

Educational Institutions/Corporate Training Firms

o Has a number of functionalities

o Our application will use several combinations of

current technology.

o Market the Educational services globally by using

the internet.

o Enables users and scholars to develop their own

solutions based on the application framework

provided

Outputs Outcomes

o Increase the level of interaction in an online

education environment.

o Increase the number of prospective students

(both undergraduate and postgraduate)

o Increase the number of prospective lecturers

and educators.

o Increase the flexibility and accessibility of

education:

Disabled Community.

Specialist Knowledge.

o Increase the quality of online education.

o Decrease Education cost.

Project Scope

Plan to create application

• Include ability to incorporate 3rd party modules and

systems such as simulation systems, stereoscopic camera

functionality etc

• Interaction system for large number of participants

• Private communication system

• Incorporate emailing/messaging system

• Ability to incorporate institution's student system (ie.

Moodle)

• Provide functionality to include modular extensions

Create

Implementation plan

Within Scope Out of Scope

Developing Payment System

Developing and providing Technical Support

System

Providing maintenance and updates

Developing and providing Training

Converting existing course material into online

equivalents

Creating new courses and their relevant

materials

Within Time

Measuring Success

Within Specifications

Quality of ProjectManagement process

Project Stakeholdersatisfaction

Within Budget

SystemQuality

InformationQuality

ServiceQuality

Intention to Use

Net Benefits

User Satisfaction

Project Management Success Project Product Success Project Success+ =

IncreaseThe number of prospective

students (both undergraduate

and postgraduate)

The level of interaction in an

online education environment

The number of prospective

lecturers and educators

Within SpecificationsThe World Wide Web Consortium

(W3C) standards

Quality of ProjectManagement process

Quality Assurance

Project Stakeholdersatisfaction

Clients satisfied that project outputs meet their needs and expectations.

Within Budget$ 201.146.67

Within Time41 work weeks

SystemQuality

The project will increase the uptake of NBN

Project Stakeholdersatisfaction

Clients satisfied that project outputs meet their needs and

expectations.

Project Risks

Major risks that are likely to

impede the success delivery of

the outputs and achievement of

the desired outcome

Risk Rating Mitigation Strategy

Loss of line funding from clients

or stakeholder High• Maintenance of financial controls and budgets

Information lost due to IT

failure Medium

• Data/records lost. Cannot refer to project files to process service requests

Service providers and/or Magic

plus team do not provide service

in an appropriate wayLow

• Service providers (Outsource Company )under agreement and performance

regularly monitored

Clients lodge grievances and

complaints Medium• Clear description of services to be provided to a client (program descriptions)

Board governance member

responsibilities not understoodHigh

• All Team member sign governance protocols

Strategic plan formulation and

approval High• Agreed approval process of all material and strategies before used publically

Technical

Risks(hardware/software/break

down of equipment)

High• Ensure adequate hardware facilities are provided and updated software has been

installed

IT system security breachesMedium

• Firewalls and virus software

Project Time & WBS

Cost

Resources Cost

Development $183,946.67

Hardware $16,000

Software $1,200

Total $201,146.67

Buffer (+75%) $352,006.67

Thank you for your attention

Any Questions?