Week Ending April 3, 2015
1. Install High Speed Wireless Access Infrastructure
2. Install Network Electronics Infrastructure
2.1 Core Level
2.2 Hub Level
2.3 Campus Level
3. Upgrade Connectivity, Power, and Air Conditioning
3.1 Upgrade Fiber Connectivity
3.2 Upgrade Cabling Connectivity
3.3 Upgrade Electrical Power and Air Conditioning
4. Upgrade the Data Center Infrastructure
4.1 Build a Virtualized Server Data Center
4.2 Install a Storage Area Network (SAN)
4.3 Co-locate the Data Center at an External Facility
4.4 Build Backup, Recovery, and Business Continuity
5. Upgrade Staff’s Technology and Phone Systems
5.1 Replace Telephone System with VoIP
5.2 Replace Administrative Staff Technology
5.3 Replace Network Printers and Print Servers
6. Install Technology Infrastructure in New Schools
iSphere Program Management
Bond 1
Bond 2
Bond 3
Bond 4
Bond 5
Bond 6
Implementation Plans
2014 Bond Recommendations
All Other 2014 Bond Information
Implementation Team
Interesting Wireless Access Point (AP) Statistics:.Total number of indoor APs order by CFISD - 7,420 model 225
Total number of outdoor APs ordered by CFISD - 380 model 275
Bleyl AP Delivery - 3,295 indoor APs, 280 outdoor APs, plus mounts
Layer3 Warehouse - 4,125 APs, 100 outdoor APs, plus mounts
Delivery of Access Points Beginning April 1st, 2015
Bond 1.1
Table of ContentsLayer3 Personnel delivering wireless APs to Bleyl
Install High Speed Wireless Access InfrastructureCFISD Project Manager: Larry Barrios
Roland Padilla Managing AP Delivery
Layer3 began the delivery of Wireless access points (APs). Due to the significant
number of APs, the challenge was to locate a facility that could house the number of
APs ordered. Pictured below is a subset of the APs ordered that will be stored at Bleyl
Data Center, with the majority of APs stored at Layer3's warehouse.
Wireless Discussion PointsDense distribution of wireless access points (APs) is scheduled to begin at the high schools this month.
Prior to the initiation of this step, a naming scheme for the APs must be finalized. Below is the naming
convention being considered:
• Unique 3-letter campus variable, AP numbered identifier, and Room Number (RM) or unique location
identifier (i.e. HW…..abbreviation for Hallway).
Example #1 - CYR-AP005-RM3122 (AP #5 located in room 3122)
Example #2 - CYR-AP110-RM3122HW (AP #110 located in the Hallway outside of RM3122)
• Also under review is the Cable Identification for each AP.
Bond 1.1
Table of Contents
Install High Speed Wireless Access InfrastructureCFISD Project Manager: Larry Barrios
Cable indentification
required for APAP Label
Table of Contents
The core network infrastructure
for the network firewalls at the
ISC Data Center and
CyrusOne Data Center were
delivered on Monday, April 6,
2015. A total of eleven
firewalls are included as an
optimum design strategy for
securing the district’s network.
Plans for the final design and
implementation are underway.
Bond 2.1
INFRASTRUCTURE
CORE Install Network Electronics Infrastructure
Core LevelCFISD Project Manager: Oscar Villar
Roland Padilla and Oscar Villar
Jay Johnson, Kim Bowlin and MCAMCA unloading Fortinet Hardware
The core network infrastructure hardware for the IP
addressing of the network at the ISC Data Center
and CyrusOne Data Center was delivered on
Monday, April 6, 2015. Plans for the final design
and implementation of the new IP addressing
scheme are underway.
Bond 2.1
INFRASTRUCTURE
CORE Install Network Electronics Infrastructure
Core LevelCFISD Project Manager: Oscar Villar
Roland Padilla amd MCA
COmmunications
Roland Padilla and MCA
CommunicationsTable of Contents
Table of Contents
Presidio, M&S Technology, and CFISD discuss initial steps required :
1. Install second firewall at ISC
2. Upgrade firmware on existing Firewall
3. Install CyrusOne data Center Switches
Install Network Electronics Infrastructure
Core LevelCFISD Project Manager: Oscar VillarBond 2.1
INFRASTRUCTURE
CORE
Stuart Loftis and Oscar Villar Tim Ramsey, Stuart Loftis and Oscar Villar
Pictured above is the combined effort between CFISD, Presidio, and M&S Technology
defining the initial steps required. The first step outlined is to eliminate our current
production single point of failure by installing a second Fortinet firewall at ISC. The
production firewall will be updated with the most current release of firmware and the new
firewall will then be installed.
Upgrade Fiber ConnectivityCFISD Project Manager: Paula Ross
Bond 3.1
Fiber
Fiber Optic Cable Routes:CFISD plans for fiber optic cable routes between the
Instructional Support Center and CyrusOne. These routes will
follow diverse physical routes.
The following contract addendums are begin finalized:
1. Master Networking Service
2. Fiber Optic Network Lease
Additional Options Under Consideration:1. Additional dark fiber pair available on a month-to-month cost
until wavelength service is available.
2. Fiber pair available for Pope Elementary School
Table of Contents
Completed This Week:Comprehensive Walkthroughs at ALC East and Cook Middle School
Follow up Site Visits at Jersey Village High School
A preliminary walk-through schedule for the remaining middle
schools was created by iSphere and is being reviewed by the CFISD
Technology Team.
Planned Next Week:
Comprehensive Walkthroughs: Campbell Middle School, Arnold
Middle School, Aragon Middle School, Labay Middle School, Hopper
Middle School, and Thornton Middle School
Table of Contents
Upgrade Cabling ConnectivityCFISD Project Manager: Larry Barrios
Bond 3.2
Cabling
Table of Contents
VLK Architects delivered a proposed schedule for bidding the electrical and power
upgrades needed for the hub and secondary campuses. Frankie Jackson is
scheduled to discuss the details of this plan with Dillon Brady, Assistant
Superintendent of Facilities and Planning, on April 7, 2015.
Table of Contents
Anthony MS*
Goodson MS
Hamilton MS
Smith MS
Spillane MS
Aragon MS
Arnold MS
Truitt MS
Hopper MS
Kahla MS
Thornton MS
Watkins MS
Cy-Ridge HS
Cy-Falls HS
Bleyl MS
Campbell MS
Jersey Village HS
4. Cy-Ridge Router1. Cy-Woods Router 2. Berry Center Router 3. Cy-Lakes Router 5. Bleyl Router 6. Dean Router
1
2
3
Cy-Woods HS
Cy-Ranch HS
Cy-Fair HS
Langham Creek HS
Cy-Lakes HS
Cy-Springs HS
Labay MS
Cy-Creek HS
Windfern HS
Dean MS
Cook MS
Upgrade Electrical Power and Air ConditioningCFISD Project Manager: Frankie Jackson and Daniel Grosz
Bond 3.2
Site Investigation 12/22/14 - 2/6/15
District approval of
Phase 1 Scope of Work 4/3/2015
90% CD Print Date 4/10/2015
CD Review with Owner 4/14/2015
BIDDING
1st Advertisement 4/19/2015
Issue documents for
Bidding 4/20/2015
2nd Advertisement 4/26/2015
Pre-Proposal 5/5/2015
Bid Date 5/19/2015
Back-Up Due for Board Packet 5/29/2015
Committee of the Whole Meeting 6/4/2015
Board Meeting 6/8/2015
CONSTRUCTION
Notice to Proceed 5/12/2015
Table of Contents
Anna Senties
Information
GatheringPlanning &
Design
RFP Submission
& Procurement
Implementation
& MigrationProject
Completion
- Vendor/Product Interviews & Research
- Current Environment Assessment Tools
- Product Matrix of Pros/Cons
- Applications Inventory & Priority
The Network Management and Operations (NMO) virtualization team
will soon finish the “Information Gathering” phase. The main focus is
now on completing the Application Inventory & Priority workbook where
Nelda Hanzi is making great progress. The virtualized design, product
selection, and possible RFP process are anticipated to start in April.
Lance Melancon
Mike Diaz
Jody Clark of VMware presented a
deep dive on NSX (virtual networking)
April 2nd to ECN. Virtual networking
will be an important consideration in
the overall design.Thomas Hollister
Jody Clark
Bond 4.1
Build a Virtualized Data CenterCFISD Project Manager: Greg Rhodes
Oscar Villar
Mike Hanson and his team from
Brocade presented their data center
and fibre channel switch solutions
March 30th.
Table of Contents
Information
GatheringPlanning &
Design
RFP Submission
& Procurement
Implementation
& MigrationProject
Completion
- Vendor/Product Interviews & Research
- Current Environment Assessment Tools
- Product Matrix of Pros/Cons
The Network Management Operations (NMO) team will soon move
to the next phase of the storage area network (SAN) project.
Vendor discussions have included topics about replication and
backup. The effort is now concentrated on determining space
requirements for applications and data shares currently and for
future growth. Further assessment tools are scheduled to be run
this week. The storage design, product selection, and possible
RFP process are anticipated to start in April.
Install a Storage Area NetworkCFISD Project Manager: Greg Rhodes
Bond 4.2
Mark Csepke of EMC presented strategies for backup
and replication between sites April 1st. There were also
discussions about active/active SAN with Vplex.
NetApp is being scheduled this
next week to run their assessment
tool.
Lance Melancon
Mark Csepke
Steve Wheeler
Timothy Hamilton
Table of Contents
Polly Gifford with Education Partners Solution, has been working on power budgets and rack elevations for CyrusOne. A sample rack elevation may be viewed here.
Contract execution is still pending.
John Sblendorio with CyrusOne sent their implementation process which may be viewed here.
The official kickoff meeting for CyrusOne will be scheduled once the contract is signed.
CoLocate the Data Center at an External FacilityCFISD Project Manager: Greg Rhodes
Bond 4.3
Coming Soon!
Table of Contents
The ISC data center is close to being ready for the upcoming
construction to a Tier 3 facility. One entire side of the data center
has been cleared to start the floor replacement. The project
budget is being reviewed by Evolve for possible funds to
purchase new network/server cabinets.
Mike Raspet
Tyndall Overby
Build Backup, Recovery, and Business ContinuityCFISD Project Manager: Greg Rhodes
Bond 4.4
Paula Ross
Richard Hoffman
Oscar Villar
Thomas Hollister
Tyndall Overby, the Evolve project manager, led the "Drawing Review" meeting April 2nd. Progress drawings
and equipment cutsheets have been sent to Facilities for review. After the review approval, an order will be
sent to CenterPoint for the new dedicated service entrance. Submitted drawings may be viewed through the
following links: power, electrical, and HVAC. The next data center construction meeting is
scheduled for April 8th.
A final design meeting with AT&T was held on Wednesday,
April 1, 2015. Attendees from AT&T, Education Partners
Solution (EPS), Cisco, iSphere, along with the Technology
Services team met to review the network design and cost
proposal. AT&T is finalizing contracts and a Total Cost of
Ownership (TCO) presentation. The contracts will be
submitted to CFISD the week of April 6, 2015, in time to file
for 2015-2015 e-rate reimbursements.
Bond 5.1
Co-Locate the Data Center at an External FacilityCFISD Project Manager: Paula Ross
Table of Contents
Cisco, CFISD staff, EPS, eSphere, and AT&T
The proposal includes:
• Total Quantity of users 6380
• Cisco Call Center Express with 10 Agents
• Licenses - Essential, Basic and Enhanced
• SRST Routers for 101 locations for E911
and DR/Survivability
• WAN Bandwidth – 2 locations with 30Mbps
and Police Dept. 1.5Mbps
• IPFlex SIP trunk 20Mbps with 310
Concurrent Calls.
• 36 Month term with all equipment being
purchase and owned by CFISD
Cost savings:
• With this solution, 94% (estimate) of the current cost on
local voice services would be replaced. (327 Alarm and
45 Elevator lines are currently in place from total of 6380
Plexar lines)
• 100% of the long distance service as well as voicemail
services cost will be eliminated. AT&T SIP Trunking offer
provides 300 Min. of free long distance per concurrent call
per month.
• The solution is based on 310 Concurrent calls for the
district, which would give CFISD a total of 93,000 min in
free domestic long calling.
Currently Cypress-Fairbanks ISD utilizes on average
1500 Domestic Long Distance Minutes/month
Bond 5.1
Co-Locate the Data Center at an External FacilityCFISD Project Manager: Paula Ross
uuuuuATT
VPN MPLS
Site 1
10300 Jones Rd
Houston, TX
CyFair Site 2
5150 Westway Park Blvd.
Houston, TX 77041
IDC
900 Venture Dr
Allen, TX. 75013
CyFair ISDRFP 3936
Hosted UC
uuuuuIP FR SIP
310 CC’s
uuuuuCustomer
Private
Fiber
96 sites
Site 3
11200 A Telge
Cypress, TX
Cisco, CFISD staff, EPS, eSphere, and AT&T
Table of Contents
Summary
o AT&T has developed a Unified Communication (UC)
solution based on Cisco's network electronics.
o Fully Managed/Monitored 7x24x365 Solution with helpdesk
support with truck role for SRST router failure.
o Hosted UC robust and redundant design for Disaster
Recovery with 999.99% uptime.
o Session Initiated Protocol (SIP) trunk located in the Data
Center - 310 Concurrent Calls and includes 93,000
minutes of Domestic Long Distance per Month
o (2) MPLS connections to (2) CFISD locations for
redundancy.
o All IOS and Patch updates are tested before being
deployed into the network to insure systems keep working
and up to date.
o CFISD staff will be trained on the Support Portal to allow
them to enter Move, Add, Change and Delete (MACD)
requests as well as obtain engineering support via web or
phone.
o Cost proposal leverages new e-rate modernization
changes.
Table of Contents
Leonard Chance, CFISD Technology
Assets Manager, compiled and verified the
“replacement data” for the instructional
campuses. Leonard has started this week
to make site visits to help the campus
technicians validated the inventories to
ensure accuracy, so an order can be
placed. This week he went to Cy Fair high
school, Cy Ranch high school, Hamiltion
middle school, and Hopper middle school.
For the administrative campuses, the
technology service technicians have
surveyed those sites to verify inventories.
The data will be reviewed and added to
the items that have been compiled from
the Instructional campuses.Service tech Chris Roberts
surveying equipment at the
Food Service facility.Leonard working with the
service techs Karen Davis and
Bradley Mulligan at Cy Ranch
HS to validated their inventory.
Replace Administrative Staff TechnologyCFISD Project Manager: Jay Johnson
Bond 5.2
Table of Contents
Leonard Chance, the
Technology Assets manager,
has gathered a list of printers
by school of equipment that
is currently in need of
replacement or that will need
to be replaced within the next
five years. An analysis is
currently underway to
determine when the best time
to replace this equipment.
Leonard will visit campuses
to help determine their needs
and to prioritize the
deliveries.
Leonard met with the service
techs Andrew Lopez and
Donisha Fontenet at Cy Fair HS
to verify network printers location
Replace Network Printers and Print ServersCFISD Project Manager: Jay Johnson
Bond 5.3
Table of Contents
Install Technology Infrastructure in New SchoolsCFISD Project Manager: Thomas Hollister
Bond 6.1
On Wednesday, April 1, 2015, Thomas Hollister, Roland
Padilla, and Frankie Jackson met with Becky Cook, Director
of Instructional Technology, and the Facilities Planning
department to review high school #12 at the 75% review.
High School #12
75% Review
Table of Contents
Weekly Summary:
Frankie Jackson worked with the iSphere project management team to make improvements in the weekly status reporting and the monitoring of Bond projects. Improvements are currently being implemented.
Table of Contents
Project ManagementProject Managers: Larry Short and Charity Farve
Bond PM
Weekly Status
Report Ending
April 3, 2015(click here)
Summary Level Project Schedules
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2016 2017 2018 2019 2020
2.1 Install Network Electronics Infrastructure
3.1 Upgrade Fiber and Cabling Connectivity
4.1 Build Virtualized Server Data Center
4.2 Install a Storage Area Network (SAN)
4.3 Co-locate Data Center at CyrusOne
4.4 Build Backup, Recovery, and Business Continuity
5.1 Replace Telephone System with VoIP Communications
5.2 Replace Administrative Staff Technology
5.3 Replace Network Printers and Print Servers
1.1 Install High Speed Wireless Assess Infrastructure
3.2 Upgrade Electrical Power and Air Conditioning
6.1 Install Technology in New Schools
Table of Contents
Goodson MS 6/15/2015
Hamilton MS 6/15/2015
Smith MS 6/15/2015
Spillane MS 6/15/2015
Anthony MS*
Aragon MS 7/6/2015
Arnold MS 7/6/2015
Truitt MS 7/6/2015
Hopper MS 7/20/2015
Kahla MS 7/20/2015
Thornton MS 7/20/2015
Watkins MS 7/20/2015
Cy-Ridge HS 7/27/2015
Cy-Falls HS 7/27/2015
Bleyl MS 8/10/2015
Campbell MS 8/10/2015
Jersey Village HS
8/17/2015
4. Cy-Ridge HUB
July 13, 2015
1. Cy-Woods HUB
April – May 2015
2. Berry Center HUB
June 29, 2015
3. Cy-Lakes HUB
July 6, 2015
5. Bleyl HUB
July 20, 2015
6. Dean HUB
July 27, 2015
1
2
3 Cy-Woods HS 6/8/2015
Cy-Ranch HS 6/8/2015
Cy-Fair HS 6/29/2015
Langham HS 6/29/2015
Cy-Lakes HS 7/13/2015
Cy-Springs HS 7/13/2015
Labay MS 7/27/2015
Cy-Creek HS 8/10/2015
Windfern HS 8/10/2015
Dean MS 8/17/2015
Cook MS 8/17/2015
CyrusOne ( CoLocation)
June 1, 2015ISC (Data Center)
February 1, 2015
4
Summary Level Campus Deployment Schedule
Cy-Ridge Hub
CyrusOne – Core 2
(data center)
Cy-Woods HubBerry Center Hub
Cy-Lakes Hub Bleyl Hub
(data center)
ISC – Core 1
(data center)
Dean Hub
1. Cy-Woods Router
Cy-Woods HS
Carlton Center
Cy-Ranch HS
Spillane MS
Smith MS
Goodson MS
Hamilton MS
Salyards MS
Black ES
Warner ES
Keith ES
Farney ES
Robison ES
Hamilton ES
Sampson ES
Ault ES
Moore ES
Swenke ES
Chiller Plant
Carlton Center
2. Berry Ctr Router
Cy-Fair HS
Langham Creek HS
Anthony MS
Aragon MS
Arnold MS
Truitt MS
Postma ES
Birkes ES
Copeland ES
Lamkin ES
Holmsley ES
Horne ES
Millsap ES
Rennell ES
Police Station
Telge Transp.
Science Resource Ctr
Berry Center
Cy-Fair Annex
Barker Transp
Exhibit Center
3. Cy-Lakes Router
Cy-Lakes HS
Cy-Springs HS
Hopper MS
Kahla MS
ALC West
Thornton MS
Watkins MS
Andre ES
Duryea ES
McFee ES
Robinson ES
Metcalf ES
Emery ES
Hemmenway ES
Jowell ES
Lieder ES
Sheridan ES
Tipps ES
Walker ES
Wilson ES
4. Cy-Ridge Router
Cy-Ridge HS
Cy-Falls HS
Labay MS
Danish ES
Adam ES
Willbern ES
Emmott ES
Fiest ES
Hairgrove ES
Lowery ES
Owens ES
Telge Ag Barn
Eldridge Transp.
Eldridge Ag
ELC Smokey Trail
5. Bleyl Router
Bleyl MS
Cy-Creek HS
Windfern HS
ALC East
Campbell MS
Francone ES
Hancock ES
Matzke ES
Yeager ES
Pridgeon Stadium
Falcon Annex
Falcon Transp
Windfern Annex
Maintenance Ctr
6. Dean Router
Dean MS
Jersey Village HS
Cook MS
Lee ES
Bane ES
Kirk ES
Bang ES
Frazier ES
Gleason ES
Holbrook ES
Pope ES
Post ES
Reed ES
Food Ser Warehouse
Food Production Ctr
* Denotes priority campuses
Detail Level Campus Deployment