Open House Purpose & Objectives
1. Present possible options for meeting the current and future needs of Highway 97 using both alternate and existing routes
2. Obtain your input on issues, opportunities, and concerns to be considered for the alternate and existing route options
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Study Overview & Outcomes
The Highway 97 – Peachland Transportation Study is examining: • Current conditions for the Highway 97 corridor through Peachland• Future needs for transportation through Peachland• Solutions that can be implemented to help meet future needs
The study will result in the identification of preliminary options within two scenarios:• One preferred option using the
existing route• One preferred option using an
alternate route
The study will not choose between these scenarios; that choice will be made by the Ministry in the future.
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Where We Are in the Process
Winter 2015-16
Spring 2016
Summer 2016
Fall 2016
Winter 2016-17 2017
Project Initiation
Current Conditions Assessment
Future Conditions Assessment
Options Generation & Assessment
Option Recommendations
Public Engagement
OPEN HOUSE #1
OPEN HOUSE #2
OPEN HOUSE #3
The study team has assessed the current and future performance of the existing highway. They have also identified possible options to improve movement along the highway using both the existing route and an alternate route. The next step is to examine the different options and gather input on the issues, concerns, and opportunities associated with each.
WE ARE HERE
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Total Collisions on Hwy 97 Between Greata Ranch Rd. and Hwy 97C 2004 - 2014
Recap of Current and Future Conditions Assessment (2016)
Peachland’s Unique Travel Patterns
A large of portion of Peachland’s population is retired, creating unique travel patterns compared to other areas in the Central Okanagan.
• Highway 97 in Peachland is vital for long-distance and local connections• Peachland hosts high volumes of visiting traffic• One-third of the traffic that starts in Peachland stays in Peachland• Risk-taking may increase at intersections as wait times grow
FromHwy 97 South of Peachland7,500 vehicles/day
To H
wy
97C
810
veh/
day
(11%
)
FromHwy 97 North of Hwy 97C10,710 vehicles/day
August 2014 (24 hrs/day, two weeks) – Daily Traffic Entering Peachland on Highway 97
Trips from Peachland - AM Peak Hour
Remain in Peachland29%
South on Hwy 972%
West on Hwy 97C< 1%
North on Hwy 9769%
Trips from Peachland - PM Peak Hour
Remain in Peachland37%
South on Hwy 972%
West on Hwy 97C< 1%
North on Hwy 9761%
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Key areas of growth in Peachland*:A: Ponderosa/Pincushion +2,100 B: New Monaco: +2,800 (proposed)C: Upper/Lower Princeton Ave:
+700 (proposed)D: Tabletop Mountain Resort:
58 unit hotel, 20 cottagesE: Downtown: +800
(new and infill)
Looking to the Future - Population
Peachland’s population growth has not kept pace with the Regional District of Central Okanagan or BC. With a current population of approximately 5,200, Peachland has a theoretical build-out potential of 27,000 or more. However, past trends suggest a population of 7,700 by 2040. For the purposes of this study, the options to be developed will be based on a 2040 population of 7,700 with sensitivity analysis considering a range of up to 13,000.
HWY 97
HWY 97C
District ofPeachland
DB
EA
C 0.0
0.5
1.0
1.5
2.0
Annual Population Growth2001 - 2013 (%)
Perc
enta
ge
BC RDCO Peachland
0.98
1.51
0.78
* Estimated residential unit growth
Recap of Current and Future Conditions Assessment (2016)
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Travel times and congestion are expected to increase gradually but noticeably in the future.• Traffic growth has been slow, but trips through Peachland in 25 years may
increase up to 3 minutes• Crossing and turning onto the highway will become more challenging
Looking to the Future - Traffic
Okanagan Lake
Peachland
HWY 97C
HW
Y 97
Hardy Street
Renfrew Road
Princeton Avenue
Ponderosa Drive/13th StreetClements Crescent
Chidley Road/Todd Road
Trepanier Bench Road
Buchanan Road (East)/Huston RoadBuchanan Road (West)
Drought Road
Seclusion Bay Road
2014 2040 Greater than 50 seconds 35 - 50 seconds Less than 35 seconds
Estimated Travel Time Changes 2014 - 2040
Okanagan Lake
Peac
hlan
d
HWY 97C
HWY 97
North of Hwy 97C to South of Peachland AM PM2014 8.5 min 9.5 min 2040 10 min 12.5 minChange +1.5 min +3 min
South of Peachland to North of Hwy 97C AM PM2014 9 min 9.5 min 2040 10 min 11.5 minChange +1 min +2 min
+1 min (AM peak)
+2 min (PM peak)
+1.5 min (AM peak)
+3 min (PM peak)
2015 Actual and 2040 Forecast Peak Hour Volumes, Highway 97 through Peachland
AM and PM Peak Hour Volumes
201499 (99)
AMPM
204099 (99)
AMPM
481 (
715)
630 (1052)
545 (1026)
517
(756
)
721 (964)
815 (996)
735 (
1095
)
972 (1489)
895 (1468)
750
(108
0)
937 (1410)
1067 (1491)
Recap of Current and Future Conditions Assessment (2016)
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Public Input
Public input has been gathered through a public open house in June 2016, feedback forms, emails and letters from the public. The study team also meets with:• The District of Peachland • Local First Nations• Peachland Council• Technical Advisory Group • Community Liaison Committee
The Importance of Public and Stakeholder Input
Public and stakeholder input is critical to understanding the opportunities, issues, and concerns of the Peachland community. The study team has benefited from meetings with Peachland Council, a Community Liaison Committee reflecting a cross section of interests, and a Technical Advisory Group. This input will help the Ministry make informed decisions about how to best meet transportation needs now and in the future.
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Public Input – Considerations
The public has identified several considerations for the project team to keep in mind. These include:
Safety Concerns:• Reducing the speed of
vehicles travelling through the community
• Mitigating the risk of accidents at intersections
• Providing space for pedestrians and cyclists
• Providing options that allow people of all ages and abilities to travel safely
• Considering the need for emergency routes
Community Impacts:• The community’s small
town atmosphere • Property values • Private property ownership
(e.g. land acquisition)• The vibrancy of local
business and tourism• The quality of life in the
community (e.g. additional noise and pollution, additional traffic etc.)
Traffic Congestion: • The way vehicles get on
and off the highway • Traffic flow at key
intersections• Access to neighbourhoods
and community destinations
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Alternate Route Options
Option One Characteristics:• Takes advantage of the valley west of McCall Lakes• Furthest from populated areas and generally not visible• Maximum 6% grade for most of the route• Intersects Highway 97C approximately 8.5 km west of the Highway 97/97C junction
Option Two Characteristics:• Follows a route over Pincushion Mountain, to the west of the peak• Longest and highest of the options, with significant cuts at the top required• At maximum 6% grade for approximately the same distance as Option 1; remainder is relatively flat• Intersects Highway 97C at the same point as Option 1
Option Three Characteristics:• Follows approximately the same route as developed by the Highway 97 Task Force• Stays well above most populated areas along the west and north sides of Pincushion Mountain• At maximum 6% grade for approximately half the length• Intersects Highway 97C at approximately Trepanier Road, 6 km west of the Highway 97/97C junction
Option 4 Characteristics:• Follows the base of Pincushion Mountain• Comes within 100m of existing development at the top of Ponderosa Drive• Northern portion is generally flat, with a maximum 6% grade at the south end• Intersects Highway 97C at approximately Trepanier Road
Option 5 Characteristics:• Most of the alignment is the same as Option 4, except the southern 4 km, which follows a shorter, more direct route• The southern portion passes through areas of existing development, particularly as it crosses Princeton Avenue below
Vernon Avenue• Flattest and shortest of all options, with least amount of rock cut required
Distance: 13.4 kmMax. elevation: 858 m
Distance: 15 kmMax. elevation: 863 m
Distance: 13.4 kmMax. elevation: 746 m
Distance: 12.6 kmMax. elevation: 690 m
Distance: 10.3 kmMax. elevation: 605 m
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Alternate Route Options – Potential Considerations for Future Investigation
The alternate route options have been reviewed with the Technical Advisory Group and the Community Liaison Committee and these groups have brought to our attention a number of potential considerations for further investigation, as marked verbatim on this map.
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Segments
The existing route of approximately 12 kilometres is broken down into five segments. This division is based on the way the highway and intersections interact with each other, and how local traffic accesses Highway 97.
Existing route options can be developed progressively as new needs emerge over time, and include: • Short-term improvements
to address problems that currently exist.
• Long- term improvements to address problems that will emerge over the next 25 years or so, and beyond.
South of Princeton Avenue
Princeton Avenue/Beach Avenue
Ponderosa Drive to Todd Road
Trepanier Bench Road to Huston Road
Drought Hilll
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Options - Drought Hill
Drought Hill Option 2a: Drought Road Overpass
New connection between Robinson Place and Drought Road
New connection between Seclusion Bay Road and Drought Road
Right in/right out turn only at Drought Road
Four lanes across entire segment, including median barrier
Close Seclusion Bay Road access to Highway 97
Create Drought Road overpass
Connect to local road network
Drought Hill Option 2b: Seclusion Bay Road & Drought Road Overpasses
New connection between Robinson Place and Drought Road
Right in/right out turn only at Drought Road
Four lanes across entire segment, including median barrier
Close Seclusion Bay Road access to Highway 97
Connect Drought Road underneath Highway 97 to new Seclusion Bay Road extension
Provide new right in/right out turn only at new Seclusion Bay Road extension
Connect to local road network
Connect Seclusion Bay Road to local road network underneath Highway 97
Drought Hill Option 1: Parallel Local Road
New connection between Robinson Place and Drought Road
New connection between Seclusion Bay Road and Drought Road
Right in/right out turn only at Drought Road
Four lanes across entire segment, including median barrier
Right in/right out turn only at Seclusion Bay Road
KEY CONSIDERATIONS
By 2040, this area will need to address:
• Delays getting onto the highway
• Delays on the highway due to higher traffic volumes
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Options - Trepanier Bench Road to Huston Road
Trepanier Bench Road to Huston Road Option 1a: Signals at Trepanier Bench Road
KEY CONSIDERATIONS
By 2040, this area will need to address:
• Two-lane highway will be at capacity; four-laning is required by 2040
• Delays getting onto the highway
• Delays on the highway due to higher traffic volumes
Traffic signals at either Trepanier Bench Road or Huston/Buchanan are currently under consideration as part of a separate study
Close Buchanan Road (West) access to Highway 97
New traffic signal at Trepanier Bench Road
Right-in/right-out turns only at Huston Road and Buchanan Road
Four lanes across entire segment
Trepanier Bench Road to Huston Road Option 1b: Signals at Huston Road / Buchanan Road
Close Buchanan Road (West) access to Highway 97
Right-in/right-out turns only at Trepanier Bench Road
New traffic signal at Huston Road/ Buchanan Road
Four lanes across entire segment
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Right in/right out turns only at Huston Road and Buchanan Road
Trepanier Bench Road to Huston Road Option 2a: Lang Road Connection
Close Buchanan Road (West) access to Highway 97
Close Trepanier Bench Road access to Highway 97
New connection between Lang Road and Eyre Road
Lang Road crosses over Highway 97
For Options 2a, b and c, the right-in/right-out can be provided at Huston Road and/or Trepanier Bench Road. The illustrations have shown this right-in/right-out at Huston Road.
Trepanier Bench Road to Huston Road Option 2b: Shaw Road Overpass
Close Buchanan Road (West) access to Highway 97
Close Trepanier Bench Road access to Highway 97
Highway 97 crosses over new Shaw Road connection to Buchanan Road
Right in/right out turn only at Huston Road and Buchanan Road
Shaw Road Extension
Close Buchanan Road (West) access to Highway 97
Right in/right out turn only at Huston Road and Buchanan Road
Trepanier Bench Road to Huston Road Option 2c: Trepanier Bench Road Overpass
Close Trepanier Bench Road access to Highway 97
Trepanier Bench Road crosses over Highway 97 to connect to Buchanan Road
Existing Route Options - Trepanier Bench Road to Huston Road
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Options - Ponderosa Drive to Todd Road
Ponderosa Drive to Todd Road Option 1: Retain Signals at Ponderosa Drive and Clements Crescent
KEY CONSIDERATIONS
By 2040, this area will need to address:
• Safety, particularly at the intersections of Ponderosa Drive/13 Street, and Clements Crescent
• Delays getting onto the highway
• Delays on the highway due to high traffic volumes
Connect Chidley Road to Clements Crescent
Right in/right out turn only at Todd Road
Four lanes across entire segment
Maintain existing traffic signal at Ponderosa Drive/ 13th Street
Maintain existing traffic signal at Clements Crescent
Close Chidley Road access to Highway 97
Ponderosa Drive to Todd Road Option 2: Overpass at Ponderosa Drive
Right in/right out turn only to Highway 97 at Clements Crescent
New connection between Ponderosa Drive and Clements Crescent
New northbound on-ramp to Highway 97 from Todd Road
Connect Chidley Road and Todd Road underneath Highway 97
Connect Ponderosa Drive to 13 Street over Highway 97
Close 13 Street /San Clemente Avenue access to Highway 97
Four lanes across entire segment
New northbound off-ramp to 13 Street
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Options - Princeton Avenue/Beach Avenue
Four lanes across entire segment
Signal maintained at Princeton Avenue and Beach Avenue
Princeton Avenue/Beach Avenue Option 1: Signalized Intersection
KEY CONSIDERATIONS
By 2040, this area will need to address:
• Delays getting onto the highway
• Delays on the highway due to higher traffic volumes
New northbound off-ramp to Princeton Avenue and Beach Avenue
New northbound on-ramp to Highway 97
Princeton Avenue/Beach Avenue Option 2: Interchange
Right-in/right-out turn only at new connection between Princeton Avenue and Highway 97
Connect Princeton Avenue and Beach Avenue underneath Highway 97
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
LEGEND HIGHWAY CONNECTION HIGHWAY REALIGNMENT LOCAL ROAD NEW HIGHWAY RAMP
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Existing Route Options - South of Princeton Avenue
South of Princeton Avenue Option 1: Small Realignment at Antlers Beach
Right-in/right-out turn only at Renfrew Road
Right-in/right-out turn only at Hardy Street
Right-in/right-out turn only onto Highway 97
Princess Street connection to Lipsett Avenue
KEY CONSIDERATIONS
By 2040, this area will need to address:
• Delays getting onto the highway
Hardy Avenue connection/crossing to be determined based on future development needs
Four lanes across entire segment
Upgrade Renfrew Road
Highway 97 realignment
South of Princeton Avenue Option 2: Short Bypass
Lipsett Avenue crosses over or under Highway 97
Highway 97 realignment
Four lanes across entire segment
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Multiple Account Evaluation (MAE) Process
The Ministry of Transportation and Infrastructure uses standard accounts and project-specific metrics when evaluating different options. Local governments, First Nations, stakeholders and the public help identify key impacts and trade-offs that are incorporated into the MAE process.
Financial- Capital costs- Periodic rehabilitation costs- Operation and maintenance costs
Social & Community- Noise and visual impacts- Pollution impacts- Land acquisition needs- Community connectivity- Consistency with community plans
Customer Service- Travel time- Collisions- Travel demand- Vehicle operating costs
Environmental- Land requirements- Energy consumption- Emissions- Wildlife / habitat- Water pollution
Economic Development- Employment- Investment and trade- Revenue- Productivity
ACCOUNTS METRICS
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
Next Steps
The options for the Highway 97 corridor in Peachland will now be evaluated from a number of perspectives to better understand how the options within each scenario compare to each other. When complete, the evaluation is meant to provide a balanced assessment of the options that takes into account all of the important variables, including public input.
Once the evaluation is complete, the study team will present a preferred existing route option and a preferred alternate route option to the public for input and discussion.
ScreeningRemove
redundant options & show‑stoppers
RefinementRefine remaining
options & address issues raised
during screening
EvaluationApply evaluation
framework to alternate route
options & existing route options
Preferred Options
Identify preferred alternate route & preferred existing
route options
Ministry of Transportation and Infrastructure
Highway 97 – Peachland Transportation Study
We Want to Hear from You!
Provide your input by: • Sharing with a member of the project team• Filling out a comment form in person or online by visiting the project website
Stay tuned to the project website at: www.gov.bc.ca/peachlandtransportationstudy
To sign up for project updates, or to contact a member of the project team, please email:[email protected]