WEST PALM BEACH FIELD STATION SLOPE MOWING SERVICES. RFB 6000000550. MANDATORY PRE-BID CONFERENCE. * The material contained herein is for informational purposes only. INTRODUCTION. Approximately 406 acres of canal Right-of-Ways 3 Storm Water Treatment Areas (STAs) - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

RFB 6000000550RFB 6000000550

MANDATORY PRE-BID CONFERENCEMANDATORY PRE-BID CONFERENCE

* The material contained herein is for informational purposes only

1

Page 2: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Approximately 406 acres of canal Right-of-Ways‐ 3 Storm Water Treatment Areas (STAs)

• Approximately 45 access gates• Access roads of various widths, signs, telephone poles

and water control structures

2

Page 3: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

3

Page 4: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

4

Page 5: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Work consists of side slope mowing of grassed and/or vegetated embankment areas with conventional high production style mowing equipment. Additionally, the use of small machine mowing and/or hand held equipment (string trimmers) shall be necessary.

• Mowing surface greater than a 3:1 ratio• Equipment: To include all tools or devices utilized by

the Contractor to complete services under the RFB

5

Page 6: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

6

Page 7: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

7

Rattlers!

7

Page 8: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

8

• Obey all speed limit signs• Do not hunt, fish, approach, attack, harm, harass,

handle, or remove any animal or plant species

8

Page 9: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• 4 to 6 cycles per year• District can modify as needed• Monday thru Saturday excluding District holidays• Dawn to dusk• Changes to the work schedule must be approved in writing

9

Page 10: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Areas, boundaries and limits have been pre-established• Area quantities have been inventoried and calculated

- Width of area calculated using a Westward Distance Wheel- Distance in feet calculated using JAMAR RAC Plus 1

10

Page 11: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

•Contractor must obtain keys from the District to access work site(s). District Key Permitting current key deposit rates apply for each key requested •All gates and entry barriers must be IMMEDIATELY secured when entering or exiting a ROW

Change to OPEN

11

Page 12: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Notice to Proceed Issued- Contractor receives NTP prior to each cycle- Contractor reviews start and end dates and acreage- Contractor starts work within 7 working days of receiving NTP

• Pre-Work Meeting- Contractor attendance mandatory- Contractor provides anticipated work schedule - Questions are resolved with the District Project Manager prior work

• Mowing Schedule- Contractor provides detailed schedule to be completed by the NTP end date- Mutual agreement dates for inspections- Revised mowing schedule: How and when to recover from slippage

12

Page 13: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• District Project Manager Inspects ROW- Contractor anticipates completion of each ROW and

provides advanced notification to the District Project Manager

- The District Project Manager will inspect the ROW within 2 business days

13

• Contractor Pre-Inspects ROW- Contractor mows ROWs- Contractor inspects completed ROW prior to requesting inspection

Page 14: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Two way communication is vital for the success of the project

- Weekly status reports are due by 12:00 PM every Thursday during a mowing cycle

- Immediately telephone the District Project Manager when absent from the work site or delayed in mowing on a scheduled work day. Email follow up by 7:00 AM prior to the scheduled start of work.

- Respond to all phone calls and/or pages within 2 hours, followed by email and/or fax within the same business day

14

Page 15: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Minimal equipment maintenance allowed on ROWs• Mowing blades must be maintained and kept sharp for optimal

results and to prevent scalping

15

Page 16: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• All Contractor employees, vehicles and mowing equipment must be clearly and visibly identified

• Each vehicle must contain a copy of the NTP under which work is being performed

16

Page 17: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Tractor Safety- Seat Belt- Mirrors- Reflectors

• Personal Protection Equipment (PPE)- Protective Eyewear- Gloves- Proper Footwear- Hearing Protection- Reflective Safety Vests- Hard Hat- Seat Belt

17

Page 18: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Contractor Removes Debris- Contractor pre-inspects ROWs and removes all debris- Debris over 150 lbs or 4’ in dimension will be removed by

the District

18

Page 19: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Dense vegetation may require more than 1 pass• 6” height “+” or “-” 1”• Within 1’ of all structures

5-10 ft tall

6” cut

19

Page 20: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

• Canal Bank Conditions

DO NOT MOW WHEN:- Soggy due to excessive wet conditions- Sandy due to excessive dry conditions

- Will cause rutting: Contractor responsible for repairs- Contact District Project Manager

20

Page 21: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

Any damage to property that is caused by the Contractor shall be repaired within five (5) working days. In the case of scalping, rutting, gouging, or similar damage, there are two (2) methods of which the repairs shall be made.

Sod or Seeding: The Contractor is responsible for establishing a growing, healthy stand of turf over the area that was damaged.

The SOW contains the Districts standards for both applications.

21

Page 22: WEST PALM BEACH FIELD STATION  SLOPE MOWING SERVICES

22