wested request for proposal #4

38
720 Market St, San Francisco, CA 94108 | (415) 423-0111 REQUEST FOR BIDS December 4, 2017 Unispace is seeking Bids for the following project. Project Name: WestEd Project Address: 2470 Mariner Square Loop, 2 nd Floor, Alameda, CA 94501 Those that have already submitted bids previously for any trades listed below, please re-submit proposal for consideration as we are relisting this request for bids due to the overwhelming responses that the previous bid phase was at a difficult time during Thanksgiving Holidays: Project Description Engineering of approx. 25,000 sf of Tenant Improvements space in an existing ‘cold shell’ on the 2 nd floor in Alameda CA. Unispace is seeking bids for the following: Instructions To Bidders 1. Unispace is under contract as the Designer/Architect of Record as well as independently contracted to provide the Construction Management/General Contractor Services for the Project under which this sub/trade contract bid is sought. 2. This will be a very ‘fast-track’ schedule with a completion date of March 16, 2018. 3. Overall Construction Schedule: Construction Start date is projected to be 12/6/17 w/ a Completion date of 3/16/18. 4. Project to be performed during normal working hours. 5. Submit bids per trade of which bidder is licensed to perform. 6. Provide bid based on demolition plan and general scope sheet. 7. Project is Prevailing Wage and bidders must comply with California Prevailing Wage Rates per DIR.CA.GOV website and all other applicable public works requirements including but not limited to DIR registration. 8. Project requires a performance and payment bond in accordance with California Civil Code 9550. Provide bond rate with bid submission Job Walk Job walk to review the existing conditions is scheduled for Wednesday, 12/6/17 10:00 AM at the Project site. Please contact Jim Kornoff @ 760-239-8555 with any questions. It is recommended (but not required) to confirm attendance with Jacob Mendrin [email protected] Questions & Request for Information (RFI) Please submit any questions or RFI’s to [email protected] no later than 3:00 PM Thursday 12/7/17. All questions and answers will be posted on WestEd’s website and LinkedIn page. Acoustical Insulation Metal Framing Drywall Acoustical Ceilings Glass and Glazing Doors, Frames and Hardware Flooring Tiling Specialties and Toilet Acc. Painting and Wall Coverings Millwork Fire Alarm Fire Sprinkler Final Cleaning Mechanical Electrical Plumbing Concrete Structural Steel

Upload: others

Post on 26-Feb-2022

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WestEd Request for Proposal #4

720 Market St, San Francisco, CA 94108 | (415) 423-0111

RE

QU

ES

T

FO

R

BID

S

December 4, 2017

Unispace is seeking Bids for the following project.

Project Name: WestEd Project Address: 2470 Mariner Square Loop, 2nd Floor, Alameda, CA 94501

Those that have already submitted bids previously for any trades listed below, please re-submit proposal for consideration as we are relisting this request for bids due to the overwhelming responses that the previous bid phase was at a difficult time during Thanksgiving Holidays:

Project Description Engineering of approx. 25,000 sf of Tenant Improvements space in an existing ‘cold shell’ on the 2nd floor in Alameda CA. Unispace is seeking bids for the following:

Instructions To Bidders 1. Unispace is under contract as the Designer/Architect of Record as well as independently contracted to

provide the Construction Management/General Contractor Services for the Project under which this sub/trade contract bid is sought.

2. This will be a very ‘fast-track’ schedule with a completion date of March 16, 2018.

3. Overall Construction Schedule: Construction Start date is projected to be 12/6/17 w/ a Completion date of 3/16/18.

4. Project to be performed during normal working hours. 5. Submit bids per trade of which bidder is licensed to perform. 6. Provide bid based on demolition plan and general scope sheet. 7. Project is Prevailing Wage and bidders must comply with California Prevailing Wage Rates per

DIR.CA.GOV website and all other applicable public works requirements including but not limited to DIR registration.

8. Project requires a performance and payment bond in accordance with California Civil Code 9550. Provide bond rate with bid submission

Job Walk

Job walk to review the existing conditions is scheduled for Wednesday, 12/6/17 10:00 AM at the Project site. Please contact Jim Kornoff @ 760-239-8555 with any questions. It is recommended (but not required) to confirm attendance with Jacob Mendrin [email protected]

Questions & Request for Information (RFI) Please submit any questions or RFI’s to [email protected] no later than 3:00 PM Thursday 12/7/17. All questions and answers will be posted on WestEd’s website and LinkedIn page.

Acoustical Insulation Metal Framing

Drywall Acoustical Ceilings

Glass and Glazing Doors, Frames and Hardware

Flooring Tiling

Specialties and Toilet Acc. Painting and Wall Coverings

Millwork Fire Alarm

Fire Sprinkler Final Cleaning

Mechanical Electrical

Plumbing Concrete

Structural Steel

Page 2: WestEd Request for Proposal #4

720 Market St, San Francisco, CA 94108 | (415) 423-0111

Submission Deadline ALL bids are due to Unispace via email at [email protected] by no later than Monday 12/11/17 @ 5:00 pm. All bids received after that time will not be accepted Minimum Qualifications Criteria In order to be considered, prospective bidders must meet the following minimum qualifications criteria:

1. Experience Modification Rate (EMR) less than 1. 2. Evidence of successfully completing 5 or more projects of similar size. 3. Ability to obtain payment and performance bond. 4. Availability to meet project schedule. 5. License in good standing.

Unispace reserves the right to request additional information from bidders to verify compliance with these qualifications. Basis of Award Award of the bid shall be the lowest responsible and responsive bidder. . The lowest cost bid who meets the minimum qualifications criteria listed above will be determined to be the lowest responsible and responsive bid.

Pricing Documents The following documents are included

• Architectural, Mechanical, Plumbing & Electrical Plans via link

• General Scope Sheet

• Exhibit A: Independent Contractor/Service Provider Agreement

• Landlord Property Handbook, Building Standards and Regulations, & General Contractors

Rules for TI Construction Protest A bidder may only protest award of the the bid if such protest is submitted in writing, together with all supporting documentation to Unispace within five (5) calendar days of notification of Unispace’s award decision. Unispace shall issue a written response to any such protest, which will be reviewed by the owner, WestED as appropriate. Public Works Bidders are advised that the Owner, WestEd, is a public agency as such the Project is subject to generally applicable public works requirements by law, including, but not necessarily limited to prevailing wage laws under the California Labor Code. Proposers shall include all costs associated with such public works requirements in their bid pricing.

Proposal Confirmation Please confirm your intention to participate by emailing [email protected] . Confirming intent to propose is not necessary but appreciated.

Page 3: WestEd Request for Proposal #4

1

INVITATION TO BID – RFP#4

Project Name: WestEd

Project Location: 2470 Mariner Square Loop, 2nd Floor, Alameda, CA 94501

Scope: Approx. 25,000 SF Interior Office Refresh & Tenant Improvements

Specific Scopes of Work

A. General Requirements – ALL BIDDERS:

1. Subcontractor to comply with bid instructions and Building Rules & Regulations attachment

2. Subcontractor to comply with Prevailing Wages governed by DIR.CA.GOV website.

3. Subcontractor to bid on multiple scopes as licensed to perform.

4. Bids to be broken out per scope

5. Following scopes are general descriptions. It is the responsibility of the Subcontractor to bid on all items

per bid plans, specs and site conditions.

6. All storage, delivery, and hoisting to be included in your bid proposal.

7. Protection of adjacent and your work during your operations

8. Mobilizations as necessary to complete your work

9. Work to be performed during normal business hours.

10. Comply with Insurance & Bond Requirements in Section C Herein.

B. Specific Trade Scope of Work

Acoustical Insulation:

All insulation per plans and specifications. All new partitions to have R-11 unfaced batt insulation in cavity. No

overhead insulation required.

Metal Framing:

Includes all metal stud framing and sizing per bid set of documents. All bottom track, top track, slip track

systems as noted. All framing for hard lid ceilings. Includes all caulking and sealants for your work. All metal

framing kickers and support systems as shown on plans and supplemental bracing details below. All backing for

millwork, benches, equipment, monitors, lab equipment, marker boards, and any items attaching to a wall. All

coordination and blockouts for MEPFS contractors (laid out by others), coordination with millwork, coordination

with ACT ceilings, and doors/frames/glass/glazing contractor. Includes all hardware and anchorage for your

work. Any shimming and furring of walls as necessary. Includes provisions for all recessed equipment in walls

and ceilings (fire extinguishers, toilet accessories, etc.). Includes provisions to furnish and install plywood for

tel/data backboard as necessary. All welding of metal stud work as necessary. Figure framing of all walls at

perimeter to include bracing at each intersection as outlined in these diagrams.

Alternate #1: Pricing for standard framing and kickers to deck in lieu of 45 degree bracing.

Page 4: WestEd Request for Proposal #4

2

Metal stud bracing typical 3D view

Page 5: WestEd Request for Proposal #4

3

Drywall:

Includes all gypsum board patching, wall skimming, touch-up and repair of existing walls, penetrations, and

existing outlets. Includes all gypsum board infills in accordance with drawings and specifications. Includes

drywall at walls, ceilings, soffits and furr to columns as per drawing. Level of finishing as noted on drawings and

specifications. Coordinate and install all box outs, backing locations, wall locations, MEP and other architectural

openings prior to start of work. Drywall at all recessed finished or rough equipment on walls and ceilings, not

limited to fire extinguishers, toilet accessories, light fixtures, plumbing fixtures, etc. Furnish and install all tile

backerboard at kitchens & toilet rooms as specified in drawings and specifications. All walls shall be finished,

tape and ready for paint with finish indicated. Provide caulk and sealants in direct relationship with this scope of

work. Coordination with framing contractor, MEPFS, doors, frames, glass/glazing contractor. All screws and

anchors as necessary to complete your scope. Includes daily clean-up, broom swept condition to a GC provided

trash dumpster. Includes extension of drywall at perimeter locations to match new ceiling heights.

Acoustical Ceilings:

Includes seismic wires, anchors, and ties in accordance with plans and specifications. Includes light (2 per light),

HVAC and electrical wires as necessary. Includes all suspensions systems for acoustical ceilings (wires,

trapeze assemblies, bracing assemblies, and other supplementary support members as required). Provide all

lay-in acoustical ceiling tiles. Includes seismic compression posts and perimeter attachment clips as required by

code. Includes all required finishes, panel sizes, and STC ratings. All ceiling tile cuts to be symmetrical with area

installed (sliver cuts one side of room not acceptable). Includes all caulking and sealants for your work.

Includes all field measurements and layouts and coordination with MEPFS contractors. Provisions to cut for

MEPFS finishes.

Glass/Glazing:

Safe Removal of 4 exterior glass panels for material deliveries and trash removal. Storage of panels for 3

months and re-installation of panels. Includes feature glass GL2 at C/2.7. All aluminum frames and aluminum

doors as shown. Includes all glazing in accordance with drawings and specifications. All spandrel glass, fire

rated glass, tempered glass, insulated glass, and mirrors as indicated. Includes aluminum framing for stiles,

bottom rails, and transoms. Includes all hardware prep and installation of hardware (hardware supplied by

others or provided as add alternate). Include all door stops and door operators for your scope. Provide product

data, shop drawings, samples and rough opening sizes for coordination and approval. All fasteners, gaskets,

flashing, brackets, reinforcing and inserts for your work. Aluminum finishes and coatings are in accordance with

drawings and specifications. Provisions for protection of your work and providing tape across glazing during

construction. Provisions for touch up of existing exterior aluminum. Removal of tape and protection and

cleaning of windows prior to completing your work. Coordination with framing contractor, doors/frames/hardware

contractor, and drywall contractor.

Alternate #1: Provide all hardware for your scope

Alternate #2: Provide 4’ Vinyl Film throughout for your glass.

Page 6: WestEd Request for Proposal #4

4

Doors/Frames/Hardware:

Provide all doors, frames and hardware for complete scope of work per bid set of documents. All glass and glazing is by others. Removal, storage and handling of existing doors and frames that are noted to be saved and re-installed. This subcontractor responsible for all glass vision lights & sidelights and framing of vision lights & sidelights. Includes all supply and installation of doors, hardware, and keying. Provide glass door hardware to be installed by glass/glazing subcontractor. Provide doors of sizes, thickness, and designs as indicated. Includes provisions to adjust door frames as required prior to installation of doors. All metal frame fabrication per specifications. Rated assemblies as shown on drawings. All required labeling of rated doors as required. All required frame anchors and their fasteners. Protection of others ongoing / completed work during your operations. Provide any and all protection for prevention of any galvanic action between dissimilar metals. Required shims as necessary. Provide material lists, cut sheets, rough opening dimensions, and delivery sheets for all your work. Any and all louvers as necessary. Coordination with framing contractor, drywall contractor, millwork contractor, and acoustical ceiling subcontractor.

Add alternate #1: Frosted film at glass doors and sidelights as per drawing.

Flooring: Existing floor conditions to be left a broom clean finish for your install. All floor leveling, floor preparation, and floor cleaning prior to installation of finished flooring. Protection of adjacent work during your operations. Supply and install all new carpet tiles, Resilient flooring, and wall base as shown. Includes field measure and layout prior to installation. Installation and sequence to be per plans. Submit shop drawings, samples and product literature for approval prior to ordering materials. All seaming, bonding, reducers, thresholds and transitions for your work. Includes cleaning and protection upon completion of your tasks. All stripping and waxing necessary upon completion of your work. Add alternate # 1 – Removal of excessive glue throughout entire floor space Add alternate # 2 – Excessive floor leveling…approximately 5,000 SF allowance Add alternate # 3 – Removal of existing “high level” uneven light weight concrete and new fill..allow 2,000 SF

Ceramic Tile:

Includes all wall tile, backsplash tile, misc. tile and grout where shown. Includes color groups and patterns with

installation and methods as indicated. Trim units shall match characteristics of adjoining flat tile. All setting and

grouting materials as indicated on drawings and specifications. All temporary protection of your work during and

after installation until tile and grout is set. All trims, caps, base, corners, caulking for a complete system.

System as noted including membranes, primers, resins, aggregate, grout and sealers with required thickness as

indicated. All required accessories and spare materials. Start of your work means acceptance of substrates left

by others. All thresholds adjacent to your work.

Specialties & Accessories:

All supply and install of new toilet accessories to include grab bars, toilet paper holders, sanitary napkin

dispenser(s), wall mirrors, drying racks, soap dispensers, towel rails, coat hooks, toilet seat covers, janitor rack,

shower/garment curtains and all toilet partitions. Includes all field layout, backing layout and coordination with

framing contractor during wall framing operations. Provisions for recessed and semi-recessed accessories.

Includes finish and grades per plans and specifications. Includes all hardware, trim, and caps to make a

complete installation. Includes all fire extinguisher cabinets and fire extinguishers. All wall mounted exit route

Page 7: WestEd Request for Proposal #4

5

signage required per code.

Painting & Wall Coverings:

Includes all required painting and wall coverings as indicated on the drawings inclusive of interior wall painting,

ceiling painting, specialty wall finishes, exposed ceilings, plywood backboards and painting of doors and frames.

Includes all caulking for items of painting. All surface preparation and field painting or wall coverings of all items

indicated. Includes all masking and protection of existing components prior and during your operations.

Includes primer and paint of coats necessary and as indicated. Includes provisions for touch up (one) trip for all

locations prior to job completion. All clean-up relating to your work is included.

Millwork:

All supply and installation of plywood backing as necessary for your work. All custom casework, countertops,

lockers and benches in accordance with drawings and specifications. Includes plywood backing for solid

surfaces including cutouts for sinks (furnish & install of solid surfaces to be priced as alternate). Includes all

storage shelving, pre-finishes cabinet interiors, and cabinet exteriors. Includes all cushions and fabric as it

relates to your scope. All finishes per plans and includes all glazing furnish and installation for your work. All

hardware, locks and keys. Includes all toe kicks and wood base. Comply with ADA requirements where noted.

Includes all miscellaneous casework material to include grommets, drawer guides, trims, fasteners, fillers,

sealants/caulking and door closures. All millwork to be delivered and acclimated prior to installation. Includes all

preparation for utilities and preparation for finished plumbing fixtures (fixtures supplied and installed by others)

as required. Layout of all backing requirements during framing activities. Coordination with MEPFS contractors,

flooring contractor, metal framing contractor, drywall contractor and ceiling contractor. Protection of existing

components and your finished product. Verification of all dimensions prior to casework fabrication.

Deduct Alternate #1: Provide laminate tops in lieu of any stone tops shown

Deduct Alternate #2: Provide regular closures and pulls in lieu of “soft close”

Fire Alarm System

Supply and installation of new fire life safety system and panel per plans and specifications. Includes clean up of

existing redundant wiring for code compliancy. Installation of new wiring for your work, all conduit to be installed

by others. Coordination with electrical contractor on conduit locations and terminations. Submittal of shop

drawings, product data and as-builts. Provide owner training, as builts and warranty documentation upon

completion of work. All testing and inspections for your work. Fire Life Safety wiring must be in red conduit.

Includes fire exit signage and occupancy.

Fire Sprinkler:

All fire sprinkler safe off prior to start of work. Includes all permits processing and permit payment. All

modifications to existing fire sprinkler system to include new bracing, seismic bracing, anchorage, straps,

hangers, extensions, reductions, and new heads as necessary to meet plans and specifications. Submit

sprinkler line drawings, bracing material sheets, bracing details and any calculations from a licensed fire

Page 8: WestEd Request for Proposal #4

6

protection engineer for city approval prior to installation. All final connections to existing stand pipe and any

modifications necessary to existing stand pipe. Includes all required coring, sleeving and fire caulking necessary

for your work. Required overhead main and branch piping to accommodate new head spacing and layout. All

testing and flushing per specifications. Provisions for as built drawings, required maintenance manuals,

closeouts and required parts to complete project. All temporary protection of existing components during your

operations and cleanup daily and upon final. Include supply and installation of all fire extinguisher cabinets and

extinguishers. Setup and perform inspections with all required agencies. Fire sprinkler heads to be semi-

recessed chrome heads.

HVAC:

All HVAC safe off prior to start of work. All new supply and installation of condensate piping (primary &

secondary), VAV’s, safety switches, disconnects, air distribution, dampers, ductwork, diffusers, registers, grilles,

louvers, boots, transfers, detectors, refrigerant lines, duct cleaning (as necessary), pipe and equipment

identification, and access panels/doors. Includes all cutting patching necessary, all mounting hardware, braces,

anchors, straps, duct insulation, angles, clips, unistrut, and vibration isolation. Includes coordination with all

MEPFS trades, drywall contractor, field layout, and submittals prior to start of work. Includes all duct testing,

leakage reports and independent air balancing reports upon completion. All flashing and caulking for your work.

Provide factory trained technician for start up and owners instruction. All temporary protection of your work

during operations to include register covers, duct covers, and protection of existing components. All startup,

testing and inspections for your work. Provide as built drawings, warranties, extra materials and closeout

documents upon completed operations. All duct board plenum is to be replaced with sheet metal plenums. New

ducted plenum to be located just above acoustical ceiling.

Plumbing:

All plumbing safe off prior to start of work. Includes all new plumbing rough in and tie in to existing plumbing

facilities, new water distribution, new drainage, undersink hot water heaters (as required), new garbage

disposals, and new plumbing sinks with fixtures. Includes all hardware, mounting brackets, straps, anchors,

rods, sleeves, caulking/sealants/fire stopping, penetrations, ADA drain covers, escuscions, valves, manifolds,

water hammers, access panels (walls & ceilings), labeling and final connections to existing facilities. Includes

locating main waste lines and their depths. Includes condensate drain piping & pump for HVAC unts.

Coordination with framing contractor, millwork contractor, HVAC contractor, and ceiling contractor. Includes all

layout and backing coordination during framing operations. Provide as built drawings, warranties, extra

materials and closeout documents upon completed operations.

Electrical:

Includes clean up of existing redundant wiring for code compliancy. Includes all electrical fixtures in accordance with plans and specifications. Includes all illuminated exit signs. Includes rework of existing conduit/wire, new installation of conduit and wire for power, new installation of conduit with pull string for low voltage, fire alarm and security card access system, all power and breakers for AC units and disconnects, all testing of existing breakers, all wire attachments for light fixtures (wires by others), power & connection for insta-hot water heaters, new subpanel upgrades, receptacles, and cover plates. Includes all misc. material for complete installation: anchors, sleeving, caulking, hardware, straps, bracing, clips, and GFCI’s. All coordination and layout with MEPFS contractors prior to installation. All submittals to include product data, shop drawings and lead times

Page 9: WestEd Request for Proposal #4

7

prior to installation. Long lead items need to be submitted on within 1st week of contract NTP. All final terminations to equipment, sub panels, and existing components. All lighting control wiring to be yellow for easy identification.

Structural Steel:

Figure supplying and installing a W8 beam 45 feet long attaching the existing structure above and to the

supplied and installed HSS 4x4 columns at each end. Formal structural drawings to be provided.

Concrete:

It is preferred each trade be responsible for their own concrete cutting and patching as necessary, however,

Unispace is accepting proposals for sawcutting and patch back of all new concrete patching where new

underground plumbing occurs. In addition, provide proposal for gypcrete saw cutting and patch back at all

drywall partitions. Provide proposal for patching and filling 30 4” concrete sleeves through the floor.

C. Scopes By Client:

• Furniture

• IT & Data

• Access control

• Audio Visual

• Move Management

• Signage (exterior)

D. Insurance and Bond Requirements

All bidders and subcontractors to Unispace must be prepared to comply with the contractual requirements

applicable to Unispace under its contract with WestEd for insurance and bonding. This means ensuring that

the bidder provides insurance that meets all of the minimum requirements set forth below and names

WestEd and WestEd parties as additional insureds. Payment and Peformance Bonds must be provided in

the full amount of the subcontract price. Bidders are to include the cost of compliance with all of these pass

through insurance and bonding requirements within their bid.

1 CONTRACTOR'S INSURANCE

1.1.1 CM/Contractor shall, at its expense, purchase and maintain in full force and effect such insurance as will protect itself

and WestEd from claims, such as for bodily injury, wrongful death, and property damage, which may arise out of or result from

the Work required by the Contract Documents, whether such Work is done by CM/Contractor, by any Subcontractor, by anyone

Page 10: WestEd Request for Proposal #4

8

directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable. See Exibit A: Independent

Contractor/Service Provider Agreement Insurance Requirements for information on the requested insurance policies and

coverages.

1.1.2 The following policies and coverages shall be furnished by CM/Contractor:

.1 COMMERCIAL FORM GENERAL LIABILITY INSURANCE covering all Work done by or on behalf of

CM/Contractor and providing insurance for bodily injury, wrongful death, personal injury, property damage, and

contractual liability. Except with respect to bodily injury and property damage included within the products and

completed operations hazards, the aggregate limit shall apply separately to Work required of CM/Contractor by

these Contract Documents. If the insurance under this Article 11.1.2.1 is written on a claims-made form,

coverage shall continue for a period of not less than 3 years following termination of this Contract. Coverage

shall provide for a retroactive date of placement prior to or coinciding with the effective date of this Contract.

.2 BUSINESS AUTOMOBILE LIABILITY INSURANCE on an “Occurrence” form covering owned, hired, leased, and

non-owned automobiles used by or on behalf of CM/Contractor and providing insurance for bodily injury and

property damage.

.3 WORKERS' COMPENSATION AND EMPLOYER'S LIABILITY INSURANCE as required by Federal and State of

California law. CM/Contractor shall also require all of its Subcontractors to maintain this insurance coverage.

.4 PROFESSIONAL LIABILITY INSURANCE. If the insurance under this Article 11.1.2.4 is written on a claims-

made form, coverage shall continue for a period of not less than 3 years following termination of this Contract.

Coverage shall provide for a retroactive date of placement prior to or coinciding with the effective date of this

Contract.

1.1.3 The coverages required under this Article 11 shall not in any way limit the liability of CM/Contractor.

1.1.4 Certificates of Insurance, as evidence of the insurance required by these Contract Documents and on the form contained in the Exhibits, shall be submitted by CM/Contractor to WestEd. The Certificates of Insurance shall provide for no cancellation or modification of coverage without prior written notice to WestEd, in accordance with policy provisions.

1.1.5 In the event CM/Contractor does not comply with these insurance requirements, WestEd may, at its option, provide

insurance coverage to protect WestEd; and the cost of such insurance shall be paid by CM/Contractor and may be deducted

from the Contract Sum.

1.1.6 CM/Contractor's insurance as required by Article 11.1.2, shall, by endorsement to the policies, include the following:

Page 11: WestEd Request for Proposal #4

9

.1 WestEd, and its representatives, consultants, officers, agents, employees, and each of their Representative's

consultants, regardless of whether or not identified in the Contract Documents or to the CM/Contractor in writing,

will be included as additional insureds on the CM/Contractor’s General Liability insurance for and relating to the

Work to be performed by the CM/Contractor and Subcontractors. Additional Insured provision or endorsement

shall be at least as broad as the CG 20 10 04 13 in combination with the CG 20 37 04 13 (or earlier versions of

CG 20 10 and CG 20 37 or Form B - CG 20 10 11 85 by itself), as published by Insurance Services Offices (ISO)

and shall be included with Certificates of Insurance. The additional insured requirement shall not apply to

Worker’s Compensation and Employer’s Liability insurance.

Further, the amount of insurance available to WestEd shall be for the full amount of the loss up to the available

policy limits and shall not be limited to any minimum requirements stated in the Contract Documents.

.2 A Severability of Interest Clause that shall be primary insurance as respects WestEd, its officers, agents and

employees. Any insurance or self-insurance maintained by WestEd shall be excess of and non-contributory with

this insurance. The provision shall state that, “The term 'insured' is hereby used severally and not collectively,

but the inclusion herein of more than one insured shall not operate to increase the limits of the insurers' liability.”

.3 A Cross Liability Clause stating that, “In the event of claims being made under any of the coverages of the

policies referred to herein by one or more insureds hereunder for which another insured hereunder may be liable,

then the policies shall cover such insureds against whom a claim is made or may be made in the same manner

as if separate policies had been issued to each insured hereunder. Nothing contained herein, however, shall

operate to increase the insurers' limits of liability as set forth in the insuring agreements.”

.4 WestEd, WestEd's consultants, WestEd's Representative, and WestEd's Representative's consultants will not

by reason of their inclusion as insureds incur liability to the insurance carriers for payment of premiums for such

insurance.

.5 Coverage provided is primary and is not in excess of or contributing with any insurance or self-insurance

maintained by WestEd, WestEd's consultants, WestEd's Representative, and WestEd's Representative's

consultants. This provision, however, shall only apply as per the stipulations of Article 11.1.6.1.

.6 The Professional Liability insurance policy shall include Contractual Liability Coverage or endorsements to the

insurance policies for Contractual Liability Coverage for liability that would exist in the absence of the contract.

1.1.7 The form and substance of all insurance policies required to be obtained by CM/Contractor shall be subject to approval by WestEd. All policies required by Articles 11.1.2.1, 11.1.2.2, and 11.1.2.3 above shall be issued by companies with ratings and financial classifications as specified in the Supplementary Conditions.

1.1.8 CM/Contractor shall, by mutual agreement with WestEd, furnish any additional insurance as may be required by WestEd. CM/Contractor shall provide Certificates of Insurance evidencing such additional insurance.

1.1.9 The Certificate of Insurance Exhibit shall show (1) all companies affording coverage and (2) the name of the insured exactly in the manner as shown on the Bid Form. The name of the insured must be the name under which the entity is licensed by the Contractors State License Board.

1.1.10 If insurance company refuses to use the Certificate of Insurance Exhibit, it must attach a Certificate of Insurance evidencing compliance with this Article 11 and Special Provisions 1 and 2 on Certificate of Insurance Exhibit.

Page 12: WestEd Request for Proposal #4

10

1.1.11 At the request of WestEd, CM/Contractor shall submit to WestEd copies of the policies obtained by CM/Contractor.

1.3 PERFORMANCE BOND AND PAYMENT BOND

1.3.1 CM/Contractor shall furnish bonds covering the faithful performance of the Contract (Performance Bond) and payment

of obligations arising thereunder (Payment Bond) on the forms contained in the Exhibits.

1.3.2 The Payment Bond and Performance Bond shall each be in the amount of the Anticipated Contract Value less the

Phase 1 Contract Sum. If thereafter the Contract Sum exceeds the Anticipated Contract Value less the Phase 1 Contract Sum,

CM/Contractor shall furnish supplemental Payment and Performance Bonds in an amount equal to any increase in the Contract

Sum above the Anticipated Contract Value.

1.3.3 The Payment Bond and Performance Bond shall be in effect prior to the date the Contract Amendment for Phase 2 is

signed by WestEd. The CM/Contractor shall provide Payment Bond and Performance Bond within ten (10) days of Notice of

Intent.

1.3.4 CM/Contractor shall promptly furnish such additional security as may be required by WestEd to protect its interests

and those interests of persons or firms supplying labor or materials to the Construction Work.

1.3.5 Surety companies used by CM/Contractor shall be, on the date the Contract is signed by WestEd, an admitted surety insurer (as defined in the California Code of Civil Procedure Section 995.120).

1.3.6 The premiums for the Payment Bond and Performance Bond shall be paid by CM/Contractor.

Page 13: WestEd Request for Proposal #4

PROJECT: WEST ED ALAMEDA

ADDRESS: 2470 MARINER SQUARE LOOPFLOOR 2, ALAMEDA, CA 94501

BUILDING HEIGHT: 40'

NO. OF FLOORS: 2

BUILDING FULLY SPRINKLERED: YES

OCCUPANCY GROUP: BUSINESS (E)

CONSTRUCTION CLASSIFICATION: V-B

CHANGE IN USE OCCUPANCY: NO

SINGLE TENANT FLOOR: YES

FLOOR OF WORK: LEVEL 2

TOTAL PROJECT AREA: 11,888 SF

PROJECT DESCRIPTION: INTERIOR RENOVATION TO EXISTING TENANTFLOOR 4 IN BUILDING. NO CHANGE IN OCCUPANCY, USE OR EGRESS. NORENOVATION TO EXTERIOR ENVELOPE.

DEFERRED SUBMITTALFIRE PROTECTION DRAWING TO BE SUBMITTED SEPARATELY UNDERSEPARATE SUBMITTAL

2016 CALIFORNIA BUILDING CODE2016 CALIFORNIA ELECTRICAL CODE2016 CALIFORNIA MECHANICAL CODE2016 CALIFORNIA PLUMBING CODE2016 GREEN BUILDING CODE2016 CALIFORNIA ENERGY CODE2016 NFPA 72 (FIRE ALARMS)2016 NFPA 13 (SPRINKLERS)

SMOKE CONTROL SYSTEM NON-INFRINGEMENT STATEMENT

"It is the design professional's judgement, whose signature appears on this drawing, thatthe design described in this set of drawings and specifications does not adverselyinfringe upon the existing life safety systems of the building"

AREA OF WORK

1. CODE COMPLIANCE:

ALL WORK TO BE PERFORMED IN ACCORDANCE WITH THE CALIFORNIABUILDING CODE AND REGULATIONS OF ALL OTHER AGENCIES HAVINGJURISDICTION.

2. STRUCTURAL SAFETY:

A. CONTRACTOR TO PROVIDE ADEQUATE TEMPORARY BRACING AND SHORINGWHENEVER ANY STRUCTURAL WORK IS INVOLVED.

B. NO CHOPPING OR CUTTING OF EXISTING STRUCTURAL SLABS OR ANYOTHER BUILDING STRUCTURAL ELEMENTS IS ALLOWED EXCEPT ASSPECIFICALLY SHOWN ON THE STRUCTURAL DOCUMENTS.

3. MEANS OF EGRESS:

SHALL BE MAINTAINED CLEAR AND FREE OF OBSTRUCTION INCLUDINGBUT NOT LIMITED TO BUILDING MATERIALS, TOOLS AND EQUIPMENT.

4. FIRE SAFETY:

A. ALL BUILDING MATERIALS STORED AT THE SITE SHALL BE SECURED INLOCKED AREAS TO BE IDENTIFIED AND CONTROLLED BY THE GENERALCONTRACTOR.

B. ALL MATERIALS SHALL BE STORED IN A NEAT AND ORDERLY FASHION.C. ALL FLAMMABLE MATERIALS SHALL BE KEPT TIGHTLY SEALED IN THEIR

RESPECTIVE ORIGINAL CONTAINERS AND KEPT AWAY FROM SOURCES OFHEAT AND OPEN FLAME.

D. FLAMMABLE MATERIALS SHALL BE USED AND STORED IN ADEQUATELYVENTED AND VENTILLATED AREAS.

E. ALL ELECTRICAL POWER EQUIPMENT TO BE SHUT-OFF WHENEVER EXPOSEDWIRE IS DETECTED.

F. ALL ELECTRICAL POWER EQUIPMENT SHALL BE SHUT-OFF DURING NON-WORKING HOURS OTHER THAN AS REQUIRED FOR SECURITY LIGHTING.

G. THE CONTRACTOR SHALL VERIFY AND REPAIR ANY LEAKAGE OF NATURALGAS FROM EXISTING AND PROPOSED NEW PIPING.

H. THE CONTRACTOR TO PROVIDE AND MAINTAIN (1) FIRE EXTINGUISHER FOREACH 5,000 SF OF EACH FLOOR OF THE WORK AREA THROUGHOUT THECONSTRUCTION PERIOD.

5. CONSTRUCTION OPERATIONS:

A. WILL BE AS SHOWN AND SHALL NOT CREATE DUST, DIRT, OR OTHER SUCHINCONVENIENCE TO THE OTHER TENANTS IN THE BUILDING.

B. BUILDING MATERIALS, TOOLS AND EQUIPMENT SHALL BE KEPT AWAY FROMALL PUBLIC AREAS INCLUDING BUT NOT LIMITED TO HALLWAYS AND LOBBY.

C. CONSTRUCTION OPERATIONS MUST NOT INTERRUPT THE NORMALOPERATION OF HEAT, WATER, OR ELECATRICAL SERVICE TO OTHERTENANTS OF THE BUILDING EXCEPT WITH THE CONSENT OF THEMANAGEMENT AND / OR SUPERINTENDENT OF THE BUILDING, FOR SHORTINTERVALS, AND ONLY AFTER ADEQUATE ADVANCE NOTICE TO ALLAFFECTED TENANTS.

D. CONSTRUCTION OPERATIONS WILL BE RESTRICTED TO NORMAL WORKINGHOURS, EXCEPT FOR LEGAL HOLIDAYS AND ANY SUCH OTHER DAYSREQUIRED BY THE BUILDING MANAGEMENT AND THE BUILDINGDEPARTMENT.

E. NO ONE SHALL OCCUPY THESE SPACES DURING THE CONSTRUCTIONPERIOD.

1. GENERAL CONTRACTOR TO OBTAIN COPY OF BUILDING RULES ANDREGULATIONS AND FOLLOW BUILDING STANDARDS DURING ENTIRE PROJECTCONSTRUCTION, U.O.N.

2. GENERAL CONTRACTOR SHALL COMPLY WITH BUILDING NOISE RESTRICTIONSAND PERFORM ALL DRILLING, SHOOTING, CUTTING ETC. BEFORE 8AM FROMMONDAY THRU FRIDAY

3. REFER TO SPECIFICATION MANUAL FOR ADDITIONAL INFORMATION.

11.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

43.9

L.9North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

32 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

G0-000

COVER SHEET

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

PROJECT INFORMATION

CODE COMPLIANCE

VACINITY MAPSHT.NO. REV. SHEET DESCRIPTION

IA-700 MILLWORK DETAILSIA-801 CEILING DETAILS

01-GENERALG0-000 COVER SHEETG0-100 GENERAL NOTES, SYMBOLS & ABBREVIATIONSG0-200 ACCESIBILITY NOTES & DIAGRAMSG0-201 TYPICAL MOUNTING HEIGHTS AND SIGNAGE STANDARDSG1-000 SITE PLANLS-002 LIFE SAFETY PLAN - LEVEL 02

02-ARCHITECTUREA1-002 DEMOLITION PLAN - LEVEL02A1-102 PARTITION PLAN - LEVEL 2A1-202 REFLECTED CEILING PLAN - LEVEL 02A1-301 POWER & DATA PLAN - LEVEL 02A1-401 FLOOR FINISH PLAN - LEVEL 02A1-402 WALL FINISH PLAN - LEVEL 02A1-403 FINISH SCHEDULEA1-501 FURNITURE & EQUIPMENT PLAN - LEVEL 02A1-601 SIGNAGE PLAN - LEVEL 01A4-100 ENLARGED PLANSA4-101 ENLARGED PLANSA4-102 ENLARGED PLANS AND DETAILSA4-200 INTERIOR ELEVATIONSA4-300 WALL SECTIONSA5-200 MILLWORK DETAILSA6-001 PARTITION TYPES AND TYPICAL WALL DETAILSA6-100 DOOR AND WINDOW SCHEDULESA6-200 EQUIP. SCHEDULES, TYP. TRANSITION DETAILS

DRAWING INDEXTENANT PROTECTION NOTES

BUILDING RULES AND REGULATIONS

2470 MARINER SQ LOOPALAMEDA, CA 94501

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

SCALE: 1/16" = 1'-0"SCOPE OF WORK - LEVEL 2 1

Page 14: WestEd Request for Proposal #4

ALIGN

ALIGN ALIGN TO INDICATEDSURFACES

A6-2221 SIM

DETAIL REFERENCE NUMBERDETAIL REFERENCE SHEET

REF. TYPE (IF APPLICABLE)

EXTERIOR ELEVATION NUMBERSHEET NUMBER

101RM.NAME

150 SFROOM NAMEROOM/AREA NUMBERAREA

SECTION NUMBERSHEET NUMBER

AREA OF DETAIL

1 REVISION NUMBER

ELEVATION NUMBER TYP.SHEET NUMBER

1A6-222

SIM

DETAIL SECTION NUMBERSHEET NUMBER

A2-222

1

1 1

1

1A6-222

SIM

A1-101

1 SIM REF. TYPE (IF APPLICABLE)

ALIGN TO INDICATEDOPPOSITE SURFACES

22 GRID LINE NUMBER

LEVEL 0112'-6"

LEVEL ELEVATION

LEVEL NAME

TRUE NORTHPROJECT NORTH

X'-X"HEIGHT ABOVESEA LEVEL U.O.N.

X'-X"HEIGHT ABOVESLAB, U.O.N.

AREA NOT IN CONTRACTN.I.C.

SHEET- KEYNOTES

CL

?

CENTER LINE

REF. TYPE (IF APPLICABLE)

REF. TYPE (IF APPLICABLE)

PERF - PERFORATEDPERP - PERPENDICULARPL - PLATEPLBG - PLUMBINGPR - PAIRPREFAB - PREFABRICATEDPT - PRESSURE TREATEDPTD - PAINTEDPVC - POLYVINYL CHLORIDE

QTY - QUANTITY

R - RADIUS OR (STAIR) RISERSRAD - RADIATORRCP - REFLECTED CEILING PLANRD - ROOF DRAINREF - REFERENCEREFR - REFRIGERATORREINF - REINFORCED OR REINFORCINGREQD - REQUIREDRH - RIGHT HANDRHR - RIGHT HAND REVERSERM - ROOMRO - ROUGH OPENINGRWL - RAIN WATER LEADER

SAFB - SOUND ATTENUATION FIBER BLANKETSF - SQUARE FOOT OR FEETSIM - SIMILARSK - SINKSPEC - SPECIFICATIONSSQ - SQUAREST - STREETSTC - SOUND TRANSMISSION CLASSSTD - STANDARDSTG - STORAGESTL - STEELSTN - STONESTR - STRUCTURAL

T - TREADS (STAIRS)T&G - TONGUE AND GROOVETBD - TO BE DETERMINEDTEL - TELEPHONETEMP - TEMPORARYTOFF - TOP OF FINISHED FLOORT.O. - TOP OFTPO - THERMOPLASTIC-POLYOLEFIN ROOFINGTV - TELEVISION OR MONITORTYP - TYPICAL

UL - UNDERWRITERS LABORATORYUON - UNLESS OTHERWISE NOTEDUPS - UNINTERRUPTIBLE POWER SUPPLYUV - ULTRAVIOLET

VAC - VACUUMVCT - VINYL COMPOSITION TILEVERT - VERTICALVEST - VESTIBULEVIF - CONTRACTOR TO VERIFY IN FIELD

W - WESTW/ - WITHW/O - WITHOUTWC - WATER CLOSETWP - WORKING POINT

& - AND@ - AT

- CENTER LINE# - POUND± - TOLERANCE DIMENSION

A/E - ARCHITECT / ENGINEERACT - ACOUSTIC CEILING TILEADA - THE AMERICANS WITH DISABILITIES ACTADJ - ADJACENTAFF - ABOVE FINISHED FLOORAH - AIR HANDLERALT - ALTERNATEAPPROX - APPROXIMATELYARCH - ARCHITECT

BD - BOARDBLDG - BUILDINGBM - BEAM

CAB - CABINETCG - CORNER GUARDCLG - CEILINGCLR - CLEARCMU - CONCRETE MASONRY UNITCOL - COLUMNCONC - CONCRETECONT - CONTINUOUSCYL - CYLINDER

DEMO - DEMOLITIONDEPT - DEPARTMENTDIA - DIAMETERDIM - DIMENSIONDISP - DISPENSERDIV - DIVISIONDN - DOWNDWG - DRAWING

EA - EACHEIFS - EXTERIOR INSULATION FINISH SYSTEMEJ - EXPANSION JOINTEL - ELEVATIONELEC - ELECTRICALELEV - ELEVATOREMER - EMERGENCYENGR - ENGINEEREP - ELECTRICAL PANELEPDM - ETHYLENE PROPYLENE DIENE MONOMEREQ - EQUALEQUIP - EQUIPMENTEX / EXIST - EXISTINGEXH - EXHAUST

FA - FIRE ALARMFACP - FIRE ALARM CONTROL PANELFD - FLOOR DRAINFDC - FIRE DEPARTMENT CONNECTIONFE - FIRE EXTINGUISHERFEC - FIRE EXTINGUISHER CABINETFHC - FIRE HOSE CABINET

FIN - FINISHFLR - FLOORFT - FOOT OR FEETFTG - FOOTINGFTR - FIN TUBE RADIATIONFURN - FURNITURE

GA - GAUGEGALV - GALVANIZEDGB - GRAB BARGC - GENERAL CONTRACTORGEN - GENERATORGFRC - GLASS FIBER REINFORCED CONCRETEGFRG - GLASS FIBER REINFORCED GYPSUMGL - GLASSGWB - GYPSUM WALL BOARD

HB - HOSE BIBBHC - HOLLOW COREHT - HEIGHTHM - HOLLOW METALHO - HOLD OPENHORIZ - HORIZONTALHP - HIGH POINTHVAC - HEAT, VENTILATION & AIR CONDITIONING

ID - INSIDE DIAMETERIN - INCH OR INCHESINSUL - INSULATIONINT - INTERIOR

JAN - JANITOR

KD - KNOCKED DOWNKO - KNOCKOUT

L - LENGTH OR LEFTLAB - LABORATORYLAM - LAMINATELAV - LAVATORYLB - POUNDLF - LINEAR FOOT OR FEETLH - LEFT HANDLHR - LEFT HAND REVERSELIN - LINEARLP - LOW POINTLTG - LIGHTING

MACH - MACHINEMAX - MAXIMUMMDF - MEDIUM DENSITY FIBERBOARDMECH - MECHANICALMFR - MANUFACTURERMIN - MINIMUMMIR - MIRRORMISC - MISCELLANEOUSMO - MASONRY OPENINGMTD - MOUNTEDMTL - METAL

N/A - NOT APPLICABLENIC - NOT IN CONTRACTNOM - NOMINALNTS - NOT TO SCALE

OA - OVERALLO.C. - ON CENTEROD - OUTSIDE DIAMETEROFCI - OWNER FURNISHED/CONTRACTOR INSTALLEDOFOI - OWNER FURNISHED/OWNER INSTALLEDOPP - OPPOSITE

CL

1.1 SCOPE OF WORKA. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING THE EXTENT,

NATURE, AND SCOPE OF WORK DESCRIBED IN THE CONTRACT DOCUMENTS.THE GENERAL CONTRACTOR SHALL PROVIDE ALL LABOR, MATERIALS, ANDEQUIPMENT NECESSARY TO EXECUTE ALL WORK SHOWN ON THESEDRAWINGS EXCEPT WHERE NOTED AS NOT IN CONTRACT (NIC). HE SHALLBE RESPONSIBLE FOR COORDINATING HIS WORK WITH THAT OF ALL OTHERTRADES INCLUDING THOSE OPERATING UNDER SEPARATE CONTRACTSWITH THE LANDLORD AND/OR TENANT. ALL WORK SHALL BE PERFORMED BYSKILLED AND QUALIFIED WORKMEN IN ACCORDANCE WITH THE BESTPRACTICES OF THE TRADES INVOLVED.

B. THE DRAWINGS SHALL BE RECOGNIZED AS DIAGRAMMATIC IN NATURE ANDNOT COMPLETELY DESCRIPTIVE OF ALL REQUIREMENTS FORCONSTRUCTION. WHATEVER WORK THAT MAY BE SPECIFIED AND NOTDRAWN OR DRAWN AND NOT SPECIFIED SHALL BE EXECUTED AS FULLY ASIF DESCRIBED IN BOTH THESE WAYS. SHOULD ANY WORKMANSHIP ORMATERIAL BE NECESSARY THAT IS NOT EITHER DIRECTLY OR INDIRECTLYNOTED IN THESE SPECIFICATIONS OR SHOWN ON THE DRAWINGS BUT ISNEVERTHELESS NECESSARY FOR PROPERLY CARRYING OUT THE OBVIOUSINTENTION THEREOF; CONTRACTOR SHALL UNDERSTAND IT TO BE IMPLIEDAND SHALL PROVIDE FOR THE SAME AS FULLY AS IF IT WERE PARTICULARLYDESCRIBED OR DELINEATED.

C. THE GENERAL CONTRACTOR SHALL REVIEW ALL CONSTRUCTIONDOCUMENTS AND VERIFY ALL GOVERNING DIMENSIONS AT THE BUILDING.HE SHALL EXAMINE ALL ADJOINING WORK OR AREAS UPON WHICH THEPERFORMANCE OF HIS WORK IS IN ANY WAY DEPENDENT. ANY VARIATIONSOR DISCREPANCIES SHALL BE REPORTED, WITH ALL DUE EXPEDIENCY, TOARCHITECT PRIOR TO THE FABRICATION OR ERECTION OF THE WORK INQUESTION.

D. ALL WORK IS TO BE PERFORMED IN STRICT ACCORDANCE WITH RULES ANDREGULATIONS OF GOVERNMENTAL AGENCIES AND SHALL CONFORM TO ALLCITY, COUNTY, STATE AND FEDERAL CODES AND ORDINANCES. ALL FEES,TAXES, AND PERMIT APPLICATIONS WITH THE APPROPRIATEGOVERNMENTAL AGENCIES SHALL BE THE RESPONSIBILITY OF THEGENERAL CONTRACTOR UNLESS OTHERWISE NOTED.

1.2 THESE GENERAL CONDITIONS SHALL APPLY TO ALL WORK SHOWNHEREIN, AND SHALL EXTEND TO ANY CHANGES, EXTRAS, OR ADDITIONSAGREED TO DURING THE COURSE OF WORK.

1.3 THE AIA STANDARD DOCUMENT A201 ENTITLED "GENERAL CONDITIONSOF THE CONTRACT FOR CONSTRUCTION" IS MADE PART OF THE GENERALCONDITIONS.

1.4 USE OF DRAWINGS:DO NOT SCALE DRAWINGS, DIMENSIONS SHALL GOVERN. LARGE SCALEDETAILS SHALL GOVERN OVER PLANS AND ELEVATIONS. DIMENSIONS AREFROM FACE OF FINISH TO FACE OF FINISH UNLESS OTHERWISE NOTED.

1.5 CONSTRUCTION SCHEDULE:WITHIN ONE WEEK OF THE AWARD OF THE CONTRACT THE GENERALCONTRACTOR SHALL SUBMIT A DETAILED CONSTRUCTION SCHEDULE TOTHE ARCHITECT FOR REVIEW. SCHEDULE SHALL INCLUDE THE ORDER ANDANTICIPATED DELIVERY DATES OF ALL LONG LEAD TIME MATERIALS.CONTRACTOR SHALL UPDATE THE SCHEDULE NO LESS THAN WEEKLYTHROUGHOUT THE COURSE OF CONSTRUCTION.

1.6 CONSTRUCTION MEETINGS:CONTRACTORS SHALL BE RESPONSIBLE FOR KEEPING DETAILED WEEKLYMINUTES OF CONSTRUCTION MEETINGS.

1.7 SITE VISITS:BIDDERS ARE INSTRUCTED TO VISIT AND INSPECT THE PREMISES PRIOR TOSUBMITTING THEIR PROPOSALS AND TO FAMILIARIZE THEMSELVES WITHTHE CONDITIONS UNDER WHICH THE WORK WILL BE PERFORMED. NOSUBSEQUENT EXTRAS OR ADDITIONS WILL BE ALLOWED ON ANY CLAIMFOR LACK OF KNOWLEDGE OF CONDITIONS OR CIRCUMSTANCES ABOUTWHICH THE BIDDER COULD HAVE INFORMED HIM/HERSELF.

1.8 LIMITATIONS AND EXCLUSIONS:BIDDER SHALL MAKE KNOWN TO ARCHITECT ANY LIMITATIONS,EXCLUSIONS, OR MODIFICATIONS TO THE PROJECT DURING THE BIDPERIOD OF THE PROJECT. ALL LIMITATIONS, EXCLUSIONS, ORMODIFICATIONS SHALL BE ITEMIZED IN THE BID PROPOSAL, OR THEY WILLBE PRESUMED INCLUDED; IN WHICH CASE NO ADDITIONAL MONIES WILL BEALLOCATED.

1.9 INSURANCE:ALL CONTRACTORS INVOLVED IN THIS PROJECT SHALL CARRY PROPERTYDAMAGE AND PUBLIC LIABILITY INSURANCE AS REQUIRED BYGOVERNMENTAL AGENCIES HAVING JURISDICTION OVER THE PROJECT ANDSHALL COMPLY WITH STATUTORY REQUIREMENTS FOR DISABILITY ANDWORKER'S COMPENSATION. CONTRACTORS SHALL COMPLY WITH ALLRULES AND REGULATIONS DICTATED BY THE LANDLORD. INSURANCE SHALLPROTECT LANDLORD, TENANT, ARCHITECT AND ANY OTHERENTITIES REQUESTED TO BE FREE FROM LIABILITY DUE TO CONTRACTOR'SNEGLIGENCE. A PROPERLY EXECUTED CERTIFICATE OF INSURANCE, AIADOCUMENT #G705, SHALL BE SUBMITTED TO THE ARCHITECT PRIOR TO THECOMMENCEMENT OF ANY WORK.

1.10 SUBMITTALS AND SHOP DRAWINGS:A. THE GENERAL CONTRACTOR SHALL SUBMIT THREE (3) SAMPLES AND / OR

SCHEDULES OF EACH OF THE VARIOUS MATERIALS, HARDWARE,EQUIPMENT, AND FINISHES TO ARCHITECT FOR REVIEW AND COMMENT.SUBMITTALS INCLUDE, BUT ARE NOT LIMITED TO, DOORS, HARDWARE,LIGHTING, PLUMBING, ELECTRICAL, MECHANICAL, FINISHES, AND SPECIALTYEQUIPMENT.

B. THE GENERAL CONTRACTOR SHALL SUBMIT TO ARCHITECT FOR REVIEWAND COMMENT THREE (3) PRINTS OF ALL FABRICATION, ERECTION, ORINSTALLATION SHOP DRAWINGS. SHOP DRAWINGS INCLUDE, BUT ARE NOTLIMITED TO, MILLWORK, STRUCTURAL, LIFE SAFETY, AND HVAC.

C. CONTRACTORS SHALL NOT COMMENCE ANY PORTION OF THE WORKREQUIRING SUBMISSION OF A SHOP DRAWINGS, PRODUCT DATUM, ORSAMPLE UNTIL THE SUBMITTAL HAS BEEN REVIEWED BY THE ARCHITECTAND / OR THE APPROPRIATE CONSULTANT. ARCHITECT SHALL HAVE FIVE (5)BUSINESS DAYS PER REVIEW. INCOMPLETE SUBMITTALS WILL DELAYREVIEW. DOORS, HARDWARE, AND FRAMES ARE CONSIDERED A SINGLEREVIEW PACKAGE.

1.11 SUBSTITUTIONS:THERE SHALL BE NO SUBSTITUTION OF MATERIALS SPECIFIED BY THEARCHITECT. WHERE THE TERM "OR EQUAL" IS USED THE ARCHITECT ALONESHALL DETERMINE EQUALITY BASED UPON INFORMATIONSUBMITTED BY THE CONTRACTOR.

1.12 MANUFACTURER’S INSTRUCTIONS:A. A. UNLESS OTHERWISE SPECIFIED, INSTALLATION OF WORK SHALL COMPLY

WITH MANUFACTURER’S PRINTED INSTRUCTIONS AND RECOMMENDATIONS.CONTRACTOR SHALL OBTAIN AND DISTRIBUTE COPIES OF SUCHINSTRUMENTS TO PARTIES INVOLVED IN INSTALLATION; AND MAINTAIN ONESET OF COMPLETE INSTRUCTIONS AT THE JOBSITE DURING INSTALLATIONAND UNTIL COMPLETION.

B. CONTRACTOR SHALL HANDLE, INSTALL, CONNECT, CLEAN, CONDITION, ANDADJUST PRODUCTS IN STRICT ACCORDANCE WITH MANUFACTURER’SINSTRUCTIONS.

C. CONTRACTOR SHALL PERFORM WORK IN STRICT ACCORDANCE WITHMANUFACTURER’S INSTRUCTIONS. DO NO OMIT ANY PREPARATORY SET ORINSTALLATION PROCEDURE, UNLESS SPECIFICALLY MODIFIED OREXEMPTED BY THE CONTRACT DOCUMENTS.

1.13 OVER – STOCK:GENERAL CONTRACTOR TO CONSULT TENANT AND LANDLORD REGARDINGOVER�STOCK MATERIALS FOR FUTURE MAINTENANCE. SUCH ITEMS MAYINCLUDE: CARPET, CARPET ACCESSORIES, DOOR HARDWARE, CEILING TILE,AND PAINT. UNLESS OTHERWISE NOTED, PROVIDE OVER–STOCK ASFOLLOWS: CEILING TILE – ONE (1) CASE, CARPET TILE – TWO (2) CASES PEREACH TYPE SPECIFIED, BROADLOOM CARPET – TO BE DETERMINED.

1.14 BUILDING REGULATIONS:THE GENERAL CONTRACTOR SHALL COMPLY WITH THE RULES ANDREGULATIONS OF THE BUILDING LANDLORD, AND SHALL COORDINATE THEUSE OF ELEVATORS AND LOADING DOCKS PRIOR TO COMMENCEMENT OFWORK WITH SAME.

1.15 BUILDING PROTECTION:GREAT CARE SHALL BE EXERCISED TO ASSURE THAT THE BUILDING ANDTENANT AREAS SHALL BE PROTECTED FROM DAMAGE THAT COULD OCCURBECAUSE OF THIS WORK. CONTRACTORS SHALL PROVIDE PROTECTION FOREXISTING AREAS AND NEW WORK AREAS. ANY DAMAGE DUE TO THECONTRACTOR’S WORK SHALL BE REPAIRED OR REPLACED AT THECONTRACTOR'S SOLE EXPENSE. CONTRACTOR SHALL PROVIDE DUSTPROOF BARRICADES AROUND ALL AREAS OF NEW WORK AS NECESSARY TOPROTECT ADJACENT TENANT AREAS FROM DAMAGE.

DIVISION 1 - GENERAL CONDITIONS

2.1 DESCRIPTION OF WORKPERFORM ALL WORK OF A DEMOLITION NATURE THAT MAY BE REQUIRED ORNECESSARY TO A FULL AND COMPLETE EXECUTION OF THE WORK, WHETHEROR NOT SHOWN OR SPECIFIED. EXACT EXTENT OF DEMOLITION MAY NOT BEFULLY INDICATED BY THE DRAWINGS.

2.2 SALVAGED COMPONENTS:A. WHERE SHOWN ON DRAWINGS, SALVAGE CONSTRUCTION MATERIALS AND

EQUIPMENT (E.G., LIGHT FIXTURES, DOORS, FRAMES, HARDWARE, ETC.)SUITABLE FOR REUSE. SALVAGED COMPONENTS SHALL BE CLEANED ANDREPAIRED BEFORE REUSING.

B. COORDINATE SALVAGE AND STORAGE OF BUILDING STANDARDCONSTRUCTION MATERIALS AND EQUIPMENT NOT NECESSARY FOR NEWTENANT CONSTRUCTION WITH LANDLORD.

2.3 PATCH AND REPAIR:A. EXISTING CONSTRUCTION WHERE AFFECTED BY DEMOLITION WORK SHALL BE

PROPERLY REMEMBERED, ALIGNED, AND REPAIRED TO LEAVE NO EVIDENCEOF REMODELING WORK. AREAS AFFECTED OUTSIDE OF TENANT SPACE BYDEMOLITION AND NEW CONSTRUCTION TO BE REPAIRED SO AS TO LEAVE NOEVIDENCE OF DAMAGE. INTEGRITY OF NON-TENANT SPACE TO BE MAINTAINED.

B. GENERAL CONTRACTOR SHALL REPAIR ANY FIRE PROOFING DAMAGED DURINGTHE COURSE OF DEMOLITION OR CONSTRUCTION SO AS TO MAINTAIN THEORIGINAL FIRE RATING.

DIVISION 2 - DEMOLITION

A. GENERAL CONTRACTOR TO FURNISH AND INSTALL ALL CONCRETE WORK INACCORDANCE WITH THE “AMERICAN CONCRETE INSTITUTE” (ACI) BUILDINGCODE REQUIREMENTS FOR REINFORCED CONCRETE STANDARD 318-83.

B. CONTRACTOR TO CHECK AND LEVEL CONCRETE FLOOR SURFACE TO ATOLERANCE NOT EXCEEDING ¼” IN A 10’-0” DIAMETER WHEN MEASURED WITH A10’-0” STRAIGHT EDGE. CONTRACTOR SHALL PATCH AND REPAIRIMPERFECTIONS IN EXISTING CONCRETE SLAB AT ARCHITECT’S DISCRETION ORAS REQUIRED PRIOR TO INSTALLING FLOOR FINISH PER MANUFACTURER’SRECOMMENDATIONS. FLOOR SHALL BE LEVEL TO ¼” IN 10’-0” DIAMETER ON ANON-CUMULATIVE BASIS ON ALL AREAS TO RECEIVE STONE OR TILE FLOORING.

DIVISION 3 - CONCRETE

6.1 CARPENTRY:A. GENERAL CONTRACTOR TO FURNISH AND INSTALL ALL WOOD BLOCKING AND

OTHER REINFORCING WHERE INDICATED ON THE DRAWINGS OR WHEREREQUIRED FOR ADEQUATE SUPPORT OF NEW WORK.

B. ALL WOOD BLOCKING SHALL BE FIRE-RETARDANT TREATED IN ACCORDANCEWITH GOVERNING ORDINANCES AND BUILDING CODES.

6.2 ARCHITECTURAL WOODWORK AND CABINETRY:

A. THIS CONTRACTOR TO FURNISH AND INSTALL ALL CUSTOM ARCHITECTURALWOODWORK INCLUDING, BUT NOT LIMITED TO:

1. STANDING OR RUNNING TRIM2. WOOD CABINETS AND HARDWARE3. DOORS AND HARDWARE4. WOOD FRAMES5. SHELVING AND HARDWARE

B. QUALITY AND WORKMANSHIP:ALL MATERIALS AND WORKMANSHIP SHALL BE IN STRICT ACCORDANCE WITHTHE “ARCHITECTURAL WOODWORK INSTITUTE” (AWI) "PREMIUM GRADESTANDARDS". REFER TO 9.6 FOR FINISH STANDARDS FOR SHOP PAINTEDDOORS.

C. MATERIALS AND FINISHES:1. MATERIALS AND FINISHES SHALL BE SPECIFIED ON THE DRAWINGS. SAMPLES

SHALL BE SUBMITTED TO ARCHITECT FOR REVIEW AS SPECIFIED IN DIVISION 1OF THESE SPECIFICATIONS.

2. WOOD VENEERS TO RECEIVE TRANSPARENT FINISH TO BE PLAIN SLICED ANDBOOK AND END MATCHED, UNLESS OTHERWISE NOTED.

3. MELAMINE COLOR, WHERE SPECIFIED, SHALL BE WHITE AT PLASTIC LAMINATEMILLWORK AND BLACK AT WOOD VENEER MILLWORK, UNLESS OTHERWISENOTED.

4. PROVIDE GROMMETS IN COUNTERTOPS ABOVE EACH WALL MOUNTEDOUTLET. GROMMETS TO BE MOCKETT & COMPANY SG SERIES, 1 3/4" HOLE,COLOR BLACK.

5. MILLWORK CABINETS CONSTRUCTION TO BE FLUSH OVERLAY TYPE WITHEUROPEAN (INVISIBLE) SELF-CLOSING , 170 DEGREE OPENING, HEAVY-DUTYHINGES AND 100 POUND RATED, FULL EXTENSION SIDE MOUNTED DRAWERSLIDES, UNLESS OTHERWISE NOTED. JOINTS BETWEEN DOORS AND DRAWERSTO BE 3/32" MAXIMUM WIDTH AND CONSISTENT THROUGHOUT.

6. SCRIBE COUNTERTOPS AN D SPLASHES TO ADJACENT SURFACES.7. PROVIDE 1/2" X 1/2" REVEAL WHERE CABINETS MEET ANOTHER SURFACE.

REVEAL COLOR TO MATCH CABINET, UON.8. MAXIMUM UNSUPPORTED CABINET SHELF WIDTH TO BE 3'-0".

D. SHOP DRAWINGS: CONTRACTOR SHALL SUBMIT SHOP DRAWINGS FORARCHITECT’S REVIEW AS SPECIFIED IN DIVISION 1 OF THESE SPECIFICATIONS.

DIVISION 6 - WOODWORK AND CABINETRY

8.1 DOORSA. A. THE GENERAL CONTRACTOR SHALL FURNISH AND INSTALL DOORS, FRAMES

AND HARDWARE WHERE SPECIFIED AND DETAILED ON THE DRAWINGS. NEWMATERIALS AND INSTALLATION OF SAME SHALL MATCH EXISTING WORKEXCEPT WHERE OTHERWISE NOTED.

B. HARDWARE SHALL MATCH EXISTING EXCEPT WHERE SPECIFIED OTHERWISE ONDRAWINGS. CONTRACTOR TO SUBMIT A FINISH HARDWARE SCHEDULE FORARCHITECT'S REVIEW AND APPROVAL PRIOR TO ORDERING MATERIALS.

C. PROVIDE ¼” MAXIMUM UNDERCUT AT ALL NEW DOORS.

8.2 GLASS AND BORROWED LIGHT PARTITIONS:A. THE GENERAL CONTRACTOR SHALL FURNISH AND INSTALL ALL GLASS WORK

WITH FRAMES AND HARDWARE AS SPECIFIED AND DETAILED ON THEDRAWINGS. GLASS WORK EXCEPT WHERE DETAILED OR NOTED OTHERWISESHALL MATCH EXISTING WORK.

B. ALL GLASS WITHIN 12” OF A DOOR, IN A DOOR, OR WITHIN 18” OF THE FINISHEDFLOOR SHALL BE TEMPERED OR LAMINATED SAFETY GLASS.

C. SUBMIT SHOP DRAWINGS OF ALL GLASS FRAMING AND GLAZING WORK ALONGWITH MATERIAL SAMPLES TO ARCHITECT FOR REVIEW PRIOR TO PROCEEDINGWITH FABRICATION WORK.

D. INSTALL TEMPERED GLASS WITH MANUFACTURER’S SEAL LOCATED AT THELOWER CORNER OF THE LITE. CONCEAL TONG MARKS, IF ANY.

E. ALL FIRE RATED SAFETY GLAZING SHALL BE “FIRE LITE” FIRE RATED CERAMICGLASS AS MANUFACTURED BY TECHNICAL GLASS PRODUCTS, UNLESSOTHERWISE NOTED. REFER TO DRAWINGS FOR GLASS LITE FIRE RATING.

DIVISION 8 - DOORS, WINDOWS AND GLASS

9.1 DRYWALL PARTITIONS:A. THE GENERAL CONTRACTOR SHALL FURNISH AND INSTALL ALL NEW PARTITION,

SOFFIT, AND CEILING CONSTRUCTION WHERE INDICATED ON THE DRAWINGS.NEW CONSTRUCTION SHALL MATCH THAT OF EXISTING ADJACENT CONDITIONS, IFAPPLICABLE, EXCEPT WHERE NOTED OTHERWISE ON THE DRAWINGS.

B. ALL NEW PARTITION CONSTRUCTION SHALL BE IN STRICT ACCORDANCE WITH THEMANUFACTURER'S RECOMMENDATIONS AND SPECIFICATIONS, AND SHALLCONFORM TO BUILDING STANDARD SPECIFICATIONS WHERE APPLICABLE.

C. THE GENERAL CONTRACTOR SHALL LOCATE AND DESIGNATE ALL NEW ANDREMAINING PARTITIONS AS NOTED ON THE DRAWINGS FOR REVIEW BYARCHITECT ON SITE PRIOR TO COMMENCEMENT OF DEMOLITION OR NEW WORK.

D. PARTITIONS SHALL BE PLUMB AND DIMENSIONS SHALL BE WITHIN 1/8” IN 20’-0”ALONG LENGTH OF PARTITIONS. CONTRACTOR SHALL NOT ADJUST DIMENSIONSMARKED “CLEAR” OR “HOLD” WITHOUT REVIEW BY ARCHITECT.

E. PROVIDE WATER RESISTANT GYPSUM WALL BOARD AT TOILET ROOMPARTITIONS AND OTHER WET AREAS. PROVIDE TYPE “X” GYPSUM BOARD ATFIRE-RATED ASSEMBLIES.

F. INSTALL GYPSUM WALL BOARD WITH LONG DIMENSIONS PERPENDICULAR TOFRAMING.

G. NEW AND EXISTING GYPSUM WALL BOARD SHALL BE TAPED AND SANDED WITHNO VISIBLE JOINTS. SURFACES ARE TO BE FREE OF IMPERFECTIONS AND SHALLHAVE SMOOTH LEVEL 4 SURFACE READY TO RECEIVE SCHEDULED FINISH.WHERE DEEP TONE PAINT IS SCHEDULED, SKIM COAT FULL SURFACE OFSUBSTRATE TO LEVEL 5 FINISH. REFERENCE USG STANDARDS.

H. ALL PENETRATIONS THROUGH FIRE RATED PARTITIONS TO BE PROPERLY FIRESTOPPED PER CODE.

9.2 CEILINGS SYSTEMS:A. PATCH AND REPAIR: GENERAL CONTRACTOR TO PATCH AND REPAIR EXISTING

CEILING SYSTEM WHERE AFFECTED BY DEMOLITION OR NEW CONSTRUCTION SOAS TO LEAVE NO EVIDENCE OF REMODELING WORK.

B. GYPSUM CEILINGS:1. CEILING SUPPORT SYSTEM SHALL LIMIT DEFLECTION OF FINISHEDCEILING TO LESS THAN 1/260 OF SPAN.2. ATTACHMENT DEVICES SHALL BE AN APPROVED TYPE, CAPABLE OFCARRYING FIVE TIMES THE CEILING LOAD OR 100 POUNDS, WHICHEVER ISGREATER.3. HANGERS SHALL BE PLUMB OR COUNTERSPLAYED AND SHALL NOTPRESS AGAINST PIPE OR DUCT INSULATION.4. CARRYING CHANNELS AND MAIN RUNNERS SHALL BE LEVEL TO WITHIN 1/8INCHES IN 10'-0".5. SUSPENSION SYSTEM SHALL NOT BE VISIBLE FROM EYE LEVEL OF APERSON STANDING ON THE FLOOR.

C. LAY IN PANEL CEILINGS:1. SPACE MAIN RUNNERS 4'-0" ON CENTER. LEVEL AND SQUARE TOADJACENT WALLS2. SPACE CROSS RUNNERS AT 2'-0" ON CENTER3. PROVIDE COMPRESSION STRUTS AT SEISMIC WIRE LOCATIONS.COMPRESSION STRUTS SHALL NOT REPLACE HANGER WIRES.

9.3 RESILIENT BASE:A. RESILIENT BASE TO BE STRAIGHT AT CARPETING AND COVE AT HARDSURFACE FLOORING.B. RESILIENT BASE TO BE INSTALLED IN CONTINUOUS RUNS

9.4 CARPET TILE:A. STORE CARPET TILE AT LEAST 3 DAYS PRIOR TO INSTALLATION IN AREA

OF INSTALLATION TO ACHIEVE TEMPERATURE STABILITY.1. FOLLOW CRI 104 STANDARD FOR ROOM TEMPERATURE AND HUMIDITY CONDITIONS.2. MAINTAIN RECOMMENDED CONDITIONS AT LEAST 72 HOURS PRIOR TO INSTALLATION AND AFTER COMPLETION.3. DO NOT STACK CARPET TILE BOXES MORE THAN 6 CARTONS HIGH TO AVOID POTENTIAL CRUSHING.

B. SEQUENCE CARPET TILE INSTALLATION WITH OTHER WORK TO MINIMIZEPOSSIBILITY OF DAMAGE AND SOILING DURING REMAINDER OFCONSTRUCTION PERIOD.

C. CONSISTENCY OF COLOR SHALL BE SUCH THAT ANY TILE SHALL BEINTERCHANGEABLE WITH ANY OTHER TILE, WITHIN A DYE LOT, WITH NOVISUAL DIFFERENCE.

D. ADHESIVES, IF REQUIRED, TO BE PER MANUFACTURER'S GUIDELINES.E. SUBFLOOR MUST BE CLEANED, FREE OF DUST, DIRT, GREASE, WAX, PAINT,

CURING OR PARTING AGENTS, OR ANY OTHER SUBSTANCE THAT MAYAFFECT THE BOND. CONCRETE FLOORS MUST BE LEVEL, FULLY CURED,FREE OF EXCESSIVE MOISTURE EMISSIONS AND ALKALI. CONCRETEFLOORS WITH A MOISTURE EMISSION RATE EXCEEDING 3.0 lbs / 1,000 SQ. FT.IN A 24 HOUR PERIOD REQUIRE CORRECTIVE MEASURES.

9.5 BROADLOOM CARPET:A. FACE YARNS SHALL BE OF SAME DYE BATCH, AND FINISH MATERIAL SHALL BE

OF ONE MILL RUN.B. WHERE SPECIFIED PROVIDE STANDARD CUSHION: NOVA “CONTRACT” BY

LEGGETT & PLATT, OR EQUAL. WEIGHT: 6.5 POUNDS PER CUBIC FOOT.THICKNESS: 5/16”.

C. TACKLESS CARPET STRIPPING SHALL BE WATER RESISTANT PLYWOOD STRIPS,3/8” OR 9/32” THICK, AS REQUIRED TO MATCH CUSHION/CARPET THICKNESS, WITHANGULAR PINS PROTRUDING FROM TOP FOR GRIPPING AND HOLDINGSTRETCHED CARPET.

D. SUBFLOOR MUST BE CLEANED, FREE OF DUST, DIRT, GREASE, WAX, PAINT,CURING OR PARTING AGENTS, OR ANY OTHER SUBSTANCE THAT MAY AFFECTTHE BOND. CONCRETE FLOORS MUST BE LEVEL, FULLY CURED, FREE OFEXCESSIVE MOISTURE EMISSIONS AND ALKALI. CONCRETE FLOORS WITH AMOISTURE EMISSION RATE EXCEEDING 3.0 lbs / 1,000 SQ. FT. IN A 24 HOURPERIOD REQUIRE CORRECTIVE MEASURES.

DIVISION 9 - FINISHES

9.6 PAINTING AND DECORATINGA. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING ALLMATERIALS AND LABOR AS NECESSARY TO PROVIDE PAINTING ANDDECORATING WORK AS SPECIFIED AND INDICATED ON THE DRAWINGS.

B. ALL WALLS, DRYWALL CEILINGS, DOORS, FRAMES AND WOODWORK SHALLBE FREE FROM DEFECTS AND BE FILLED AND SANDED SMOOTH PRIOR TORECEIVING PAINTED AND/OR NATURAL FINISHES. NEW WORK SHALL BE PRIMEDAND PAINTED WITH NOT LESS THAN ONE PRIME AND TWO FINISH COATS.PREVIOUSLY FINISHED WORK SHALL RECEIVE NOT LESS THAN TWO FINISHCOATS.

C. PAINTING SYSTEM NEW CONSTRUCTION:1. DRYWALL - 1ST COAT - BENJAMIN MOORE (BM) LATEX QUICK DRY PRIMESEALER II (201).a. DRYWALL CEILINGS 2ND & 3RD COAT - "BM" REGAL WALL SATIN LATEX FLAT

(215). REFER TO FINISH PLAN FOR PAINT COLORS.b. DRYWALL WALLS - 2ND & 3RD COAT - "BM" REGAL AQUAPEARL LATEX (310) OR

EGGSHELL. REFER TO FINISH PLAN FOR PAINT COLORS.c. DRYWALL WALLS 2ND & 3RD COAT IN BATHROOMS, KITCHENS, JANITOR

CLOSETS, ETC. SEMI GLOSS FINISH. REFETRO FINISH PLAN FOR PAINTCOLORS.

d. OTHER FINISH COATS AS NOTED ON PLAN.e. EXISTING CONSTRUCTION ONLY, 2ND & 3RD COAT AS REQUIRED, OR NOTED.

2. MISCELLANEOUS WOOD TRIM - 1ST COAT - BENJAMIN MOORE ALKYD ENAMELUNDERBODY (217).a. 2ND & 3RD COAT � AS NOTED.b. EXISTING CONSTRUCTION

3. MISCELLANEOUS METAL TRIM - 1ST COAT - BENJAMIN MOORE IRONCLADRETARDO RUST INHIBITIVE PAINT (163).a. 2ND & 3RD COAT - "BM" SATIN IMPERVO (235) OR ALKYD DULAMEL (207) FORSEMI-GLOSS FINISH.b. OTHER FINISH COATS AS NOTED ON PLAN.c. EXISTING CONSTRUCTION ONLY, 2ND & 3RD COAT AS REQUIRED.

4. UNLESS OTHERWISE NOTED, PREPARE AND PAINT ALL EXPOSED ITEMSINCLUDING COLUMNS, PANEL BOXES, CONDUIT, SURFACE RACEWAYS,DRAPERY POCKETS, ETC. NOT PRE�FINISHED TO MATCH ADJACENT PARTITIONOR CEILING COLOR.

5. FINISH VERTICAL EDGES OF PAINT GRADE DOORS TO MATCH FACES. SEALTOP AND BOTTOM EDGES.

6. PAINT ASTRAGALS AT FIRE RATED DOORS TO MATCH DOOR.

7. ALL SHOP PAINTED WOOD DOORS TO BE PAINTED TO AWI-OP4SPECIFICATION FOR SOLID COLORS AND AWI TO VIF-4 FOR CLEAR FINISHES.

8. WALL COVERING:INSTALL WALL COVERING USING MANUFACTURER’S RECOMMENDED ADHESIVE.WALL COVERING SHALL BE CONTINUOUS BEHIND COUNTERTOPS, CHAIR RAILS,ETC. SEAMS SHALL BE TIGHT, NEAT, AND NOT LESS THAN 12” FROM CORNERS.DO NOT END WALL COVERING AT AN OUTSIDE CORNER.

9.RESILIENT FLOORING:THE CONTRACTOR SHALL WAX ALL NEW AND, WHERE OCCURS, EXISTINGRESILIENT FLOORS, U.O.N.

PROVIDE ELECTRICAL AND WATER SYSTEMS REQUIRED FOR A COMPLETE ANDOPERATIONAL INSTALLATION OF ALL APPLIANCES AS SHOWN OR SPECIFIED ONTHE DRAWINGS.

A. FURNITURE IS BY TENANT UNLESS OTHERWISE NOTED. REFER TO POWER ANDSIGNAL PLAN FOR ELECTRICAL REQUIREMENTS.

B. CONTRACTOR SHALL COORDINATE HIS WORK WITH THAT OF THE TENANT’SFURNITURE VENDOR TO INCLUDE FLOOR CORE LOCATIONS, BASE POWER, ANDDATA IN FEED LOCATIONS

DIVISION 10 - SPECIALTIES

[NOT USED]

DIVISION 13 - SPECIAL CONSTRUCTION

[NOT USED]

DIVISION 14 - CONVEYING SYSTEM

15.1 SCOPE OF WORKCONTRACTOR SHALL PROVIDE ALL MATERIALS, LABOR AND ENGINEERINGDESIGN SERVICES REQUIRED TO PROVIDE A COMPLETE AND OPERATIONALHEATING, AIR CONDITIONING, VENTILATION, PLUMBING, FIRE PROTECTION, ANDLIFE SAFETY SYSTEM. CONTRACTOR SHALL VISIT THE PROJECT SITE TODETERMINE THE EXACT LOCATIONS AND ELEVATIONS OF EXISTINGDUCTWORK, PIPING AND FIRE PROTECTION EQUIPMENT. CONTRACTOR SHALLBE RESPONSIBLE FOR THE REMOVAL OF EXISTING WORK AS NECESSARY TOACCOMMODATE NEW WORK.

15.2 ENGINEERING DESIGN DOCUMENTSCONTRACTOR SHALL PREPARE OR CAUSE TO HAVE PREPARED A COMPLETESET OF MECHANICAL AND PLUMBING ENGINEERING DRAWINGS ANDSPECIFICATIONS. CONTRACTORS SHALL SUBMIT DRAWINGS ANDSPECIFICATIONS TO ARCHITECT FOR REVIEW AND APPROVAL PRIOR TOCOMMENCING WITH NEW WORK. CONTRACTOR SHALL PROVIDE WET STAMPEDAND SIGNED DRAWINGS FOR BUILDING DEPARTMENT PERMIT SUBMISSION.

15.3 ORDINANCES, REGULATIONS AND BUILDING CODES ALL WORK SHALL BE INSTRICT ACCORDANCE WITH APPLICABLE ORDINANCES, REGULATIONS ANDBUILDING CODES. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING ALLPERMITS TO PERFORM THIS WORK.

DIVISION 15 - MECHANICAL

16.1 SCOPE OF WORKCONTRACTOR SHALL PROVIDE ALL MATERIALS, LABOR AND ENGINEERINGDESIGN SERVICES REQUIRED TO PROVIDE A COMPLETE OPERATIONALELECTRICAL SYSTEM. CONTRACTOR SHALL VISIT THE PROJECT SITE ANDVERIFY ALL ELECTRICAL CONDITIONS TO DETERMINE THE EXTENT OF NEWWORK AND DEMOLITION INVOLVED. CONTRACTOR SHALL REMOVE ANDTERMINATE ALL EXISTING ELECTRICAL, TELEPHONE AND OTHER DEVISESNOT OTHERWISE INDICATED TO REMAIN. (REFER TO ENGINEER'SDOCUMENTS.)

16.2 ENGINEERING DESIGN DOCUMENTSCONTRACTOR SHALL PREPARE OR CAUSE TO HAVE PREPARED A COMPLETESET OF ELECTRICAL ENGINEERING DRAWINGS AND SPECIFICATIONS.CONTRACTORS SHALL SUBMIT DRAWINGS ANDSPECIFICATIONS TO ARCHITECT FOR REVIEW AND APPROVAL PRIOR TOCOMMENCING WITH NEW WORK. CONTRACTOR SHALL PROVIDE WETSTAMPED AND SIGNED DRAWINGS FOR BUILDING DEPARTMENT PERMITSUBMISSION.

16.3 ORDINANCE, REGULATIONS & BUILDING CODESALL WORK SHALL BE IN STRICT ACCORDANCE WITH APPLICABLEORDINANCES, REGULATIONS AND BUILDING CODES. CONTRACTOR SHALL BERESPONSIBLE FOR OBTAINING ALL PERMITS TO PERFORM THIS WORK.

16.5 TELEPHONE/DATA SYSTEMS COORDINATIONCONTRACTOR SHALL COORDINATE HIS WORK WITH THE TENANT'STELEPHONE AND COMMUNICATIONS VENDOR PRIOR TO COMMENCING WITHNEW WORK.

DIVISION 16 - ELECTRICAL

1.16 CUTTING AND DRILLING:CUTTING, CHASING, DRILLING OR DEMOLITION OF WALLS, SLABS, ETC.REQUIRING THE USE OF JACK HAMMERS OR OTHER HEAVY HAND OR POWERTOOLS SHALL BE PERFORMED OUTSIDE REGULAR BUSINESS HOURS ON ANOVERTIME BASIS UNLESS THE LANDLORD AND ANY AFFECTED TENANTEXPRESSLY PERMIT IT.

1.17 HAZARDOUS MATERIALSREPORT ANY HAZARDOUS MATERIALS TO THE LANDLORD AND ARCHITECTIMMEDIATELY.

1.18 CLEAN-UPTHE GENERAL CONTRACTOR SHALL AT ALL TIMES KEEP THE PREMISES FREEOF ACCUMULATION OF WASTE MATERIALS OR RUBBISH CAUSED BY HIS/HEROPERATIONS OR BY THOSE OF OTHER CONTRACTORS UNDER SEPARATECONTRACT. CONTRACTOR SHALL CONFINE HIS/HER OPERATIONS FORREMOVAL TO SUCH METHODS AS MAY BE AGREEABLE WITH THE LANDLORD.PREMISES TO BE SWEPT CLEAN ON A DAILY BASIS.

1.19 PUNCH-LIST:UPON COMPLETION OF THE WORK THE GENERAL CONTRACTOR SHALL NOTIFYARCHITECT TO PREPARE A "PUNCH-LIST" OF CORRECTIONS ANDUNSATISFACTORY AND/OR INCOMPLETE WORK. RELEASE OF FINAL PAYMENTWILL BE CONTINGENT ON THE COMPLETION OF THESE ITEMS UNDER THETERMS OF THE OWNER�CONTRACTOR AGREEMENT.

1.20 GUARANTEE:ALL WORK AND MATERIALS SHALL BE GUARANTEED AGAINST DEFECTS INDESIGN, WORKMANSHIP AND MATERIALS FOR A PERIOD OF AT LEAST (1) ONEYEAR FROM DATE OF FINAL ACCEPTANCE AND PAYMENT. ALL DEFECTSOCCURRING IN THE GUARANTEE PERIOD SHALL BE CORRECTED AT NO COSTTO THE TENANT.

1.21 AS BUILT DRAWINGS:DURING THE COURSE OF CONSTRUCTION, ACTUAL LOCATIONS OF ALL RUNS OFMECHANICAL AND ELECTRICAL WORK SHALL BE INDICATED TO SCALE IN REDINK ON THE DRAWINGS, INCLUDING CONCEALED DEVIATIONS FROM THEDRAWINGS. UPON COMPLETION OF THE PROJECT, INCLUDING THE PUNCH-LIST,THIS DRAWING SET SHALL BE TRANSFERRED TO ELECTRONIC CAD DRAWINGS.THE CAD DRAWINGS SHALL BE MARKED "AS-BUILT SET" AND RETURNED TOARCHITECT AND TENANT ON COMPACT DISK. THE ARCHITECT SHALL, WITHINFIVE WORKING DAYS OF THE RECEIPT OF THIS SET, GRANT APPROVAL FORFINAL PAYMENT TO THE CONTRACTOR OR SHOW REASONABLE CAUSE WHYSUCH APPROVAL IS DENIED.

1.22 SUBSTANTIAL COMPLETIONTHE FOLLOWING ARE REQUIRED FOR SUBSTANTIAL COMPLETION:A. FINAL CLEANING BY A PROFESSIONAL SERVICEB. AS-BUILT DRAWINGS ON COMPACT DISKC. A BINDER WITH OPERATION, MAINTENANCE DATA, AND WARRANTIES FOR ALL

INSTALLED SYSTEMS.D. SPECIFIED QUANTITIES OF MAINTENANCE AND OVER STOCK MATERIALSE. HVAC BALANCE REPORT

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

36 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

12" = 1'-0"

G0-100

GENERAL NOTES,SYMBOLS &

ABBREVIATIONS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

GENERAL SYMBOLS

STANDARD ABBREVIATIONS

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 15: WestEd Request for Proposal #4

1/2" M

AX.

CARPET PILE HEIGHT

-

1/2" MAX

DOMINANT DIRECTIONOF TRAVEL

LONG DIMENSIONPERPENDICULAR TODOMINANT DIRECTION OFTRAVEL

ELONGATED OPENINGIN FLOOR SURFACES

1/4" M

AX

VERTICAL CHANGE IN LEVEL BEVELED CHANGE IN LEVEL

21

1/2" M

AX1/4" M

AX1/4

" MAX

CIRCULAR SPACE

60" MIN.

60" MIN

36" M

IN24

" MIN

12" MIN

36" MIN

12" MIN

60" M

IN

T-SHAPED SPACE

30" M

IN

48" M

IN

30" MIN

30" M

IN

48" MIN

CLEAR FLOOR ORGROUND SPACE

(A) FORWARD (B) PARALLEL

POSITION OF CLEARFLOOR OR GROUND SPACE

MANUEVERING CLEARNACEIN AN ALCOVE, FORWARDAPPROACH

MANUEVERING CLEARANCE IN ANALCOVE, PARALLEL APPROACH

X>24

"

36" MIN 60" MIN

X>15

"

4" MAX

X>27

"

X≥80

"

LIMITS OF PROTRUDING OBJECTS

POST-MOUNTED PROTRUDING OBJECTS

27"-8

0" 12" MAX 12" MAX

27" M

AX X>30"

X>12"

80" M

IN

(B)(A)

VERTICAL CLEARANCE

27" M

AX

X>80

"CLEAR WIDTH OF AN ACECSSIBLE ROUTE

36" M

IN

32" M

IN

24" MAX 48" MAX 24" MAX

32" M

IN

36" M

IN

48" M

IN

42" MIN

X<48"

42" MIN

60" M

IN

36" MIN

X<48"

36" MIN

CLEAR WIDTH AT TURN

(A) 180 DEGREE TURN (B) 180 DEGREE TURN(EXCEPTION)

90.000

°

32" MIN 32" MIN 32" MIN

(A)HINGED DOOR

(B)SLIDING DOOR

(C)FOLDING DOOR

CLEAR WIDTH OF DOORWAYS

60" M

IN

18" MIN

48" M

IN

12" MIN

(A)FRONT APPROACH,

PULL SIDE

(B)FRONT APPROACH,

PUSH SIDE

(C)FRONT APPROACH, PUSH

SIDE, DOOR PROVIDED WITHBOTH CLOSER AND LATCH

(D)HINGE APPROACH, PULL SIDE

(E)HINGE APPROACH, PULL SIDE

36" MIN 60" M

IN

42" MIN

54" M

IN

(F)HINGE APPROACH, PUSH SIDE

(E)HINGE APPROACH, PUSH SIDE,DOOR PROVIDED WITH BOTH

CLOSER AND LATCH

22" MIN42" M

IN

12" MIN 22" MIN48" M

IN

(H)LATCH APPROACH, PULL SIDE

(I)LATCH APPROACH, PULL SIDE, DOOR

PROVIDED WITH CLOSER

48" M

IN

24" MIN

24" MIN 42" M

IN

24" MIN 48" M

IN

(J)LATCH APPROACH, PUSH SIDE

(K)LATCH APPROACH, PUSH SIDE, DOOR

PROVIDED WITH CLOSER

24" MIN54" M

IN

48" M

IN

42" M

IN

22" MIN 42" M

IN

42" M

IN

24" MIN

(A)FRONT APPROACH

(B)SIDE APPROACH

(C)POCKET OR HINGE APPROACH

(D)STOP OR LATCH APPROACH

(A)PULL SIDE

(B)PUSH SIDE

(C)PUSH SIDE, DOOTR

PROVIDED WITH BOTHCLOSER AND LATCH

60" M

IN

18" MIN

> 8"

12" MIN

> 8" 48

" MIN

> 8"

48" M

IN

48" MIN 48" MIN 48" MIN

(A) (B) (C)

60" MIN 60" MINBETWEEN HANDRAILS

60" MIN CLEAR

BETW

EEN

HAND

RAILS

60" M

IN C

LEAR

LANDING LANDING LANDINGRAMP RUN RAMP RUN

RAMP

RUN

(A)STRAIGHT

(B)CHANGE IN DIRECTION

MAX RISE 30"

MAX SLOPE1:12

AT LE

ST A

S W

IDE

AS R

AMP

RUN

36" M

IN C

LEAR

BET

WEE

N HA

NDRA

ILS

12" MIN 12" MIN

(A)EXTENDED SURFACE

(B)CURB OR BARRIER

X<4"

RADIUS1/2" MAX

30 MAX1 1/2" MAX

(A)RADIUS OF TREAD EDGE

(TYPICAL FOR ALL PROFILES)

(B)ANGLED RISER

(C)NOSING

34"-3

8"

34"-3

8"

34"-3

8"

(A)STAIRS

(B)RAMPS

(C)WALKING SURFACES

1 1/2" MIN

1 1/2"

MIN

12" MIN

NOTE: X = TREAD DEPTH

HANDRAILCLEARANCE

HORIZONTALPROJECTIONS BELOWGRIPPING SURFACE

TOP HANDRAILEXTENSION AT STAIRS

BOTTOM HANDRAILEXTENSION AT STAIRS

TOP AND BOTTOM HANDRAILEXTENSION AT RAMPS

12" MIN

12" MIN

X

ELEVATOR CAR DIMENSIONS

(C)ANY DOOR LOCATION

(D)ANY DOOR LOCATION

(E)EXCEPTION

EXISTING ELEVATORCAR CONFIGURATION

54" MIN

80" M

IN

36" MIN

60" M

IN

36" MIN

60" MIN

54" M

IN

36" MIN

16 SF MIN

LIMITED-USE/ LIMITED-APPLICATION (LULA) ELEVATOR CAR DIMENSION

(A)NEW CONSTRUCTION

(B)NEW CONSTRUCTION

EXCEPTION 1

(C)EXISTING BUILDING

EXCEPTION 2

42" MIN

54" M

IN

32" MIN 36" MIN

51" M

IN

51" MIN36" MIN

54" M

IN15 SF MIN

LOCATION OF PRIVATERESIDENCE ELEVATOR

CONTROL PANEL

PLATFORM LIFTDOORS AND GATES

12" M

IN

LIFT

MECH

ANIS

M

PLATFORM

32" MIN

42" M

IN

51" M

IN

54" M

IN

42" MIN

80" MIN 68" MIN

54" M

IN

51" M

IN

36" MIN

(A)CENTERED DOOR

(B)SIDE (OFF-CENTERED) DOOR

46" M

AX

34" M

AX

10"- 24"

34" M

AX 48" M

AX

MAX10"

48" M

AX

MAX10"

EXCEPTION: EXISTING ELEMENTS THAT ARENOT ALTERED SHALL BE PERMITTED AT 54" MAXABOVE THE FLOOR

20"-25"

46" M

AX

48" M

AXMI

N15

"

(A) FORWARD (B) SIDE

(A) (B)

EXCEPTION: AT WASHING MACHINES AND CLOTHES DRYERS, THEHEIGHT OF THE OBSTRUCTION SHALL BE PERMITTED TO 36 INCHES- MAXIMUM ABOVE THE FLOOR

48" M

AX

(A) (B)

UNOBSTRUCTED REACH

OBSTRUCTED HIGH SIDE REACH

OBSTRUCTED HIGH FORWARD REACH

20" MAX

CHILDREN'S REACH RANGE

MIN

15"

FORWARD OR SIDE REACH HIGH (MAX) LOW (MIN)AGES 3 AND 4 36 IN. 20 IN.AGES 5 THRU 8 40 IN. 18 IN.AGES 9 THRU 12 44 IN. 16 IN.

18"

4"

2" M

IN12

" 2"

(A) (B)

NOTE:L-SHAPED GRAB BAR ATTRANSFER TYPE SHOWER

NOTE: RECESSED DISPENSERSPROJECTING 1/4" FROM THE WALLSHALL BE PERMITTED IN THE 1'-0"SPACE INDICATED IN DIAGRAM (A)

(A) BACK WALL

CLEARANCE FOR WATER CLOSET WHEELCHAIR ACCESSIBLE TOILET COMPARTMENTS

WATER CLOSET SEAT HEIGHT BACK WALL AND SIDE WALL GRAB BAR FOR WATER CLOSET

DISPENSER OUTLET LOCATION

HEIGHT OF LAVATORIES / SINKS AND MIRRORS

12" MIN

36" MIN24" MIN

CL12" MAX

42" MIN

3' - 4"

54" MIN

18" M

IN

CL

60" MIN

56" M

IN

Other fixtures notallowed within this area

(B) SIDE WALL

2' - 1

0"

18"

18" M

IN

18" M

IN

24" MIN 1 1/2"

MIN

42" MAX 24" MIN36" MAX

12" M

IN

48" M

AX

24" MIN

48" M

AX

42" MAX

(a) Protruding Dispenser Below Grab Bar (b) Protruding Dispenser Above Grab Bar

(c) Recessed Dispenser

59" M

IN F

LOOR

MOU

NTED

W.C

. AND

CHI

LDRE

N 56

" MIN

WAL

L MOU

NTED

W.C

.

60" MIN

WHEELCHAIR ACCESSIBLE COMPARTMENT TOE CLEARANCES

6" MIN

MIN9"

6" MIN

MIN

12"

(A) ELEVATION ADULT (B) ELEVATION CHILDREN (c) Plan

DRINKING FOUNTAIN SPOUT LOCATION

36"

(A) PARALLEL APPROACH

3 1/2" MAX

(C) FORWARD APPROACH SIDE ELEVATION

5" MAX1'-3" MIN

(B) FORWARD APPROACH PLAN ELEVATION

5" MAX

1'-3" MIN

NOTE: SPOUT SHALL PROVIDE AFLOW OF WATER 4" MIN - HTANGLE OF WATER STREAMTO FRONT OF FOUNTAINSHALL BE 30 DEGREES - COORDINATEWITH PLUMBING

WATER CLOSET LOCATION

CL CL

16" - 18" 17" - 19"

(a) Accessible WaterClosets (b) Ambulatory

Accessible WaterClosets

42" M

IN

CL

60" M

IN

TYPICAL ACCESSIBLE URINAL

CL1' - 5" 1' - 5"

1' - 0

"3'

- 6"

TOP

OF R

IM17

" ADA

2'-0"

TYP

ICAL

URI

NAL

NOTE: WALL HUNG URINALS SHALL BE 13 1/2"MINIMUM DEPTH MEASURED FROM THE OUTER FACEOF THE URINAL RIM TO THE WALL

NOTE: MIRRORS ABOVE ACCESSIBLE LAVATORIES SHALL HAVE THE BOTTOM EDGEOF THE REFLECTING SURFACE 40" MAX ABOVE THE FLOOR. CENTERLINE OFMIRROR SHALL ALIGN WITH CENTERLINE OF LAV, UNLESS NOTED OTHERWISE. WHENMIRRORS ARE LOCATED ABOVE COUNTERS THAT DO NOT HAVE LAVATORIES, THEBOTTOM EDGE OF THE MIRROR SHALL BE 40" MAXIMUM ABOVE THE FLOOR

(a) Front View (b) Side View

18" DEEP URINALSCREEN

8" 6"

9"2'

- 3"

MIN MAX MIN

MIN

CLR

1' - 5"MIN

2' - 1

0"MA

X3'-

4" M

AXBO

TTOM

OF

MIRR

OR

2' - 3

"MI

N CL

R

BOTT

OM O

F MI

RROR

3'-4"

MAX

CL

CL

(SIDE VIEW)(FRONT VIEW)

2' - 6"

4' - 0

"

2' - 6

"

4' - 0"

6" MIN

6" M

IN42

" MIN

55" M

IN F

LOO R

MOU

NTED

W.C

.

52" M

IN W

ALL M

OUNT

ED W

.C.

4" M

AX

4" MAX

56"

60" M

IN

59" MIN FOR CHILDREN

C L

DOOR SHALL NOTSWING INTO THEREQD MIN AREAOF COMPARTMENT

WHEELCHAIR ACCESSIBLE COMPARTMENT ALTERNATE DOOR OPENING

59" MIN FLOOR MOUNTED W.C.56" MIN WALL HUNG W.C.

15" C

HILD

REN

18" A

DULT

3"

1 1/4" MIN1 1/2" MAX

33" -

36" A

FF

1 1/2" 1 1/2"

3"

LINE DENOTES WALL

18 GA SHEET METAL,TYP STL STUD FRAMING

(C)

(A)HANDRAIL NON-

CLEARANCECROSS SECTION

(C)HANDRAIL CIRCULAR

CROSS SECTION

(B)

PERIMETER= 4"-6 1/4"

1 1/4"- ø 2"MAX2 1/2"

MAX2 1/2"

FLOOR SURFACES

CHANGE OF LEVEL

TURNING SPACE CLEAR FLOOR OR GROUND SPACE

PROTRUDING OBJECTS

WALKING SURFACESCLEAR WIDTH OF DOORS

CLEARNACES AT MANUAL SWING DR.

CLEARNACES AT SLIDING DOORS

CLEARANCES AT RECESSED DOORS

DOORS & GATES IN A SERIES

RAMP LANDINGS RAMP EDGE PROTECTION

STAIR NOSINGS

HANDRAIL HEIGHT & CLEARANCES

ELEVATOR CLEARANCES

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

41 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

G0-200

ACCESIBILITY NOTES& DIAGRAMS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

ADA REACHES

GRAB BAR SPACING

ADA PLUMBING FIXTURES

ADA-HANDRAIL DIMENSIONS

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 16: WestEd Request for Proposal #4

2 1/2"

MIN

2 1/2"

MIN

2" M

IN 2" M

IN

HEIGHT OF ELEVATOR CALLBUTTONS AND SIGNALS

CALL

BUT

TONS

42"

DIRE

CTIO

N SI

GNAL

S72

" MIN

FLOOR DESIGNATIONS ONJAMBS OF ELEVATORHOISTWAY ENTRANCES

CAR DESIGNATIONS ONJAMBS OF DESTINATION-ORIENTED ELEVATOR

HEIGHT OF RAISEDCHARACTERS

POSITION OF BRAILLEHEIGHT OF TACTILE CHARACTERS ABOVEFINISHED FLOOR OR GROUND

LOCATION OF TACTILESIGNS AT DOORS

PICTOGRAM FIELDINTERNATIONAL SYMBOLOF ACCESSIBILITY

LIBRARY

5/8" -

2"

AREA OFREFUGE

3/8" M

IN3/8

" MIN

CL

45.00

18" M

IN

CENTERED ONTACTILECHARACTERS

18" MINMEN

NOT IN PICTOGRAMFIELD

6" M

IN

48" M

IN

60" M

AX

AREA OFREFUGE

MIRROR

36"42

"

COAT HOOK POSITION OFOPEN DOOR

ACCESSIBLE URINAL STANDARD URINAL

WALL MOUNTED ACCESSORIES

ACCESSIBLE W.C. TYPICAL TOILET STALL

LAVATORY

AT WOMEN'S

17" 26

"

6" M

AX

42" 18"

33" -

36"

12"MIN42"

33" -

36"

42"MAX

6"

23"

44"

4"34

" MAX

48"

36"

27"

TO C

ONTR

OLS,

TYP

42"

42"

42"

DRINKING FOUNTAINS

DISPOSAL TO CLEAREND OF TOILET AT

WOMEN'S

26"

27"

4' - 0

" MAX

31"

31"

30"

54"

36"

COATHOOK

48"

FIRE EXTINGUISHER CABINETAND FIRE HOSE CABINET

18"

84"

AECCISBLE SHOWER

SHOWERROD

FOLDINGSHOWERSEAT

3' - 0" MAX

MIN.15"

MIRROR

BOTT

OM O

F M I

RROR

40"

TO N

OZZL

E44

" MA

X

TO O

PERA

TION

48"

MAX

TOP

OF O

PEN

SHEL

F34

"

DISPENSERPAPER

TOWELS

PAPER TOWELS &WASTE RECEPTACLE

WASTE RECEPTACLE

WALL MTDSOAP

BABY CHANGINGSTATION

TO O

PERA

TION

48"

SHELFCOAT RACK

48"

MAX

TOWEL &ROBE HOOK

BOTT

OM O

F MI

RROR

40"

C L

17"

MIN8"

MIRROR

TYPICAL ACCESSIBLE CASEWORK

34" M

AX

BOTT

OM O

F MI

RROR

40"

27" C

LEAR

MIN

9" M

IN

17" MIN

MIN8"

17" MIN

9" M

IN

27" C

LEAR

MIN

6" M

AX

3"

1' - 6"

1'-6"

3'-10"

4'-6"

6'-8"

FIRE ALARM ANNUNCIATION DEVICE

WALL PHONE

LIGHTING SWITCHES

FIRE ALARM PULL STATION

RECEPTACLESTELE/DATA OUTLET / FLUSHCOMPUTER INTERFACE

FINISHED FLOOR

NOTES:1.DEVICES INSTALLED AS SHOWN U.O.N.2.MOUNTING HEIGHTS MEASURED FROM CENTERLINE OF

DEVICE, OR GROUP OF DEVICES, TO FINISHED FLOOR.3.DEVICES, OR GROUP OF DEVICES, INSTALLED ON

COMMON VERTICAL CENTERLINE.

3'-0"

THERMOSTAT

CARD READER

FROM CORNER

6"

MINIMIZE, TYP

EXAMPLE OF GROUPING & ALIGNING DEVICES ON COMMONVERTICAL CENTERLINE. INCLUDE FE CABS & OTHER WALL-MOUNTED OBJECTS IN COMMON VERTICAL CENTERLINE

EQ EQ

CENTER ALL DEVICES ATWALL/COLUMN U.O.N.

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

43 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

G0-201

TYPICAL MOUNTINGHEIGHTS AND

SIGNAGE STANDARDS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

COMMUNICATION ELEMENTS COMMUNICATION ELEMENTS

MOUNTING HEIGHTS - PLUMBINGMOUNTING HEIGHTS - POWER & DATA

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 17: WestEd Request for Proposal #4

UP

UP

1. COMPLY WITH APPLICABLE LOCAL, STATE AND FEDERAL CODES ANDREGULATIONS PERTAINING TO SAFETY OF PERSONS, PROPERTY ANDENVIRONMENTAL PROTECTION.

2. PROVIDE AND MAINTAIN BARRICADES, LIGHTING AND GUARDRAILS ASREQUIRED BY APPLICABLE CODES AND REGULATIONS TO PROTECTBUILDING OPPUPANTS.

3. ERECT AND MAINTAIN DUST PROOF PARTITIONS AS REQUIRED, TO PREVENTSPREAD OF DUST, FUMES AND SMOKE, ETC TO OTHER PART OF THEBUILDING. ON COMPLETION, REMOVE PARTITIONS AND REPAIR DAMAGEDSURFACES TO MATCH ADJACENT SURFACES.

4. PERMIT BUSINESS ACTIVITIES TO CONTINUE THROUGH ENTIRETY OFPROJECT.

5. IF DEMOLITION IS PERFORMED IN EXCESS OF THAT REQUIRED, RESTOREEFFECTED AREAS AT NO COST TO OWNER.

6. REMOVE FROM SITE DAILY AND LEGALLY DISPOSE OF REFUSE, DEBRIS,RUBBISH, AND OTHER MATERIALS RESULTING FROM DEMOLITIONOPERATIONS

7. FIRE SPRINKLERS AND LIFE SAFETY SYSTEMS TO REMAIN OPERATIONALDURING AND AFTER DEMOLITION.

8. CUT AND CAP ALL EXISTING, ABANDONED MEP PIPING AND CONDUITROUTING TO/FROM THE CEILING. CUT PIPING AND CONDUIT TO UNDERSIDEOF SLAB. VERIFY ALL EXISTING SERVICES TO BE ABANDONED PRIOR TOPERFORMING WORK

9. MAINTAIN ACOUSTIC AND/OR FIRE RATINGS AROUND RECESSED FIXTURES,PIPING, DUCTWORK, PENETRATIONS AND ALL OBSTRUCTIONS.

10. REMOVE EXISTING FLOOR FINISHES PER FINISH PLAN LOCATIONS. . CLEANAND PREP FLOOR AS REQUIRED.

11. REMOVE ALL EXISTING CEILING GRID, TILES, LIGHT FIXTURES & CEILINGEQUIPMENT. CLEAN, REFURBISH AND REBALLAST EXISTING LIGHTFIXTURES TO BE REUSED PER AOR DIRECTION.

12. DEMOLISH ALL EXISTING MILLWORK ON FLOOR IN SCOPED AREAS U.O.N.13. SALVAGE AND REUSE DOOR FRAMES & HARDWARE AS APPLICABLE14. ALL SAFE-OFF MECHANICAL, ELECTRICAL & PLUMBING MUST BE

PERFORMED PRIOR TO ANY DEMOLITION.15. ELECTRICAL CONTRACTOR TO "LOCK-OUT & TAG-OUT" ALL ELECTRICAL

SERVICES PRIOR TO ANY DEMOLITION.16. CONTRACTOR TO PROTECT AND MAINTAIN ALL PATHWAYS, EXISTING

CONDITIONS, STAIRWELLS & LOBBY AREAS PRIOR AND DURING DEMOLITIONACTIVITIES.

17. DEMOLITION CONTRACTOR TO COORDINATE WITH MECHANICAL,ELECTRICAL, PLUMBING, AND IT CONTRACTORS. ALL ITEMS TO BE REMOVEDSHALL BE TAGGED WITH RIBBON.

18. DEMO CONTRACTOR TO COMPLY WITH CITY AND STATE RECYCLINGREQUIREMENTS AND PROVIDE PERIODIC AND FINAL EVIDENCE OFRECYCLABLE CONTENT.

EXISTING PARTITIONTO BE REMOVED.

EXISTING DOOR,FRAME & HARDWARETO BE REMOVED.

SYMBOL DESCRIPTION

NOT IN CONTRACTN.I.C.

DEMOLISH EXISTINGCEILING GRID ANDTILES.

1

1.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

43.9

L.9

D201TYP

D202

D203TYP

TYP

D102 D102

OPEN TOBELOW

D101

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:25:

10 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-002

DEMOLITION PLAN -LEVEL02

SFC-00018A

ISSUE FOR PERMIT

10/17/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

PMAP

4' 8' 16'0

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

DEMOLITION NOTESDEMOLITION LEGENDNO. NOTES

D101 BOOKSHELF TO REMAIN IN PLACE, PROTECT DURNING DEMOLITION.D102 REMOVE (E) TOILET PARTITIONS, CLEAN, PROTECT & STORE ON SITE TO

BE REINSTALLED AT DIMENSIONS SPECIFIED ON SHEET A1.102D201 DEMO (E) LIGHT FIXTURE.D202 FIRE SPRINKLERS & FIRE LIFE SAFETY EQUIPMENT TO REMAIN

OPERATIONAL THROUGH CONSTRUCTION.D203 MECHANICAL & ELECTRICAL EQUIPMENT TO REMAIN IN PLACE UNLESS

INDICATED BY MEP ENGINEERS PRIOR TO DEMOLITIONCOMMENCEMENT.

KEY NOTES

SCALE: 1/8" = 1'-0"DEMOLITION PLAN - LEVEL 02 1

TYP. EXISTING REFLECTED CEILING PLAN

REV DESCRIPTION DATE BY CHKISSUE FOR DEMOLITION PERMIT 10/09/2017ISSUE FOR PERMIT 11/20/2017

Page 18: WestEd Request for Proposal #4

ALIG

N

ALIGNALIGN

ALIGN

ALIG

N

ALIGN

ALIGN

ALIGN

ALIGNALIGN

ALIGN

ALIGN ALIGN

ALIG

N

ALIG

N

A4-200

STAIR#1 STAIR

#2

OPEN TOBELOW

2049CONFERENCE 2050

PRIVATEOFFICE

2051

PRIVATEOFFICE

2053

PRIVATEOFFICE

2055

PRIVATEOFFICE

2057

PRIVATEOFFICE

2059

PRIVATEOFFICE

2061

PRIVATEOFFICE

2063HOTEL

2048

PRIVATEOFFICE

2052

PRIVATEOFFICE

2054

PRIVATEOFFICE

2058

PRIVATEOFFICE

2060

PRIVATEOFFICE

2062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2036

PRIVATEOFFICE

2041CONFERENCE

2040HOTEL

2039

PRIVATEOFFICE

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2034

PRIVATEOFFICE2038

PRIVATEOFFICE

2028HOTEL 2026

CONFERENCE

2074CONFERENCE

2080BREAK ROOM

2082TRAINING

2101

PRIVATEOFFICE

2103

PRIVATEOFFICE

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE

2000CONFERENCE

2102

PRIVATEOFFICE

2100

PRIVATEOFFICE

2002

PRIVATEOFFICE

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2010

PRIVATEOFFICE

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

2087CLOSET

2007

PRIVATEOFFICE

2008CONFERENCE

2009HOTEL

2011

PRIVATEOFFICE

2013

PRIVATEOFFICE

2015

PRIVATEOFFICE

2017

PRIVATEOFFICE

2019

PRIVATEOFFICE

2021

PRIVATEOFFICE

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM

2065WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2064

HALL

WAY

2089

FURNITURESTORAGE

A4-200

2085GN RR

2086WELLNESS

2079LOBBY

2004OPEN OFFICE

1

1.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

4

3.9

L.9

A4-1001

2023

PRIVATEOFFICE

2001

PRIVATEOFFICE

1' - 8" 8' - 11" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 9' - 2"8' - 2 1/2" 10' - 6" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 8' - 9" 1' - 8"

20' - 6" 9' - 6" 10 1/2" 1' - 0" 10' - 5"

20' -

10"

1' - 6"

6' - 4

"10

' - 5"

2068PRINT

2071HOTEL

4' - 5

1/2"

26' -

10"

10' - 5" 10' - 5" 10' - 5"

2' - 1"

10' - 2" 10' - 5" 8' - 7"

5' - 0"

10' - 5" 10' - 5" 10' - 5"

7' - 4

"

2' - 4

1/2"

2077CONFERENCE

10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5" 9' - 4"

8' - 6"

2078MAIL ROOM

2069FOCUS

2070SUPPLIES

2083TRAINING

2027OPEN OFFICE

2025OPEN OFFICE

2092FOCUS

2047OPEN OFFICE

2075WORK ROOM

2081

TRAININGBREAKOUT

2073CLOSET

10' - 7" 10' - 5" 10' - 5"

10' -

2"

8' - 10"

1' - 3

"9'

- 0"

10' -

6"

3' - 0"

10' - 5" 10' - 5" 10' - 5" 10' - 5" 10' - 5"

3' - 4

"10

' - 5"

8' - 7"

5' - 9" 7' - 0" 7' - 0"

10' -

6 1/2"

10' -

5"10

' - 5"

3' - 4

"

6' - 6

"7'

- 2"

3' - 0"

4' - 6

"

2 1/2" 10' - 5 1/2" 10' - 5"

A1-1022

TYP

2044

2014

2104

2002

2005

2010

2050

2105

2009

2001

2040

2052

2059

2061

2057

2055

2053

2051

2048

2058

2060

2062

2031

2033

2035

2037

2039

2034

2036

2019

2017

2015

2013

2011

2023

2030

2007

2006

2003

2103

2018

2045

2046

2043

2012

2022

2095

2089

2028

2054

2016

2087

2080

2101

2093

2092

2094

2065

2038

2073

2071

2069

A4-10010

2096FOCUS

2102

2100

2021

2067HALLWAY

2056HALLWAY

2032HALLWAY

2072HALLWAY

2076HALLWAY

2020HALLWAY

2084HALLWAY

2099HALLWAY

2097HALLWAY

2090HALLWAY

2042PRINT

2098PRINT

2075

2070

2096B32

0

32' -

4"

A4-1007

A101

A101

A101

A101

A101

A101

A101

A101

2063

4' - 0

"

1

C310C31

0B320

C310

B320

B320

B320

B320

B320

B320

B320

B320

B320

B320

A1-1025

A1-1023

A4-1011

2077

2049

20412026

2074

2024

2008

2000

2029

A4-1021

3

A4-2004

A4-200 5

A4-2005

A4-200

6

A4-200

7

A4-200 2

2082

B

2082

A

2083

A

2083

B

A4-200 8

A4-200

9

A4-200

11

10

A4-200

13

12

14

A4-200

15

16

A4-200 17

A4-200

18

A4-200

19

A4-200

20

2079

21

A4-102

4A4-102

5A4-102 7 A4-1026

1. ALL WALLS ARE TO BE TYPE "A" U.O.N.2. ALL "A" TYPE WALLS ARE TO BE BRACED TO THE CLOSEST FULL HEIGHT

PARTITION. SEE WALL DETAILS FOR MORE INFORMATION.3. ALL GYPSUM BOARD IS 5/8" TYPE C THICK U.O.N.4. ALL METAL STUDS ARE 16" O.C. U.ON.5. ALL METAL STUDS ARE 20 GA U.O.N.6. ALL FIRE RATED PARTITIONS MUST CONFORM TO MINIMUM REQUIREMENTS

OF THE LISTED TESTED ASSEMBLY UNLESS MORE STRINGENTREQUIREMENTS ARE DESIGNATED BY DETAIL.

7. ALL ACOUSTICAL STC RATED PARTITION CONSTRUCTION EXTENDING TOTHE BOTTOM OF STRUCTURE SHALL HAVE ALL PENETRATIONS ANDINTERSECTIONS SEALED AIR TIGHT WITH ACOUSTICAL SEALANT.

8. FIRE RATED SEALANT SHALL BE USED AT FIRE RATED PARTITIONS. ALLRECESSED BOXES SHALL BE SEALED AND RUNNERS SHALL BE SET IN 2BEADS OF SEALANT.

9. ALL ROOMS WITH PLUMBING FIXTURES SHALL BE CONSTRUCTED WITHWATER RESISTANT GYPSUM BOARD U.O.N.

10. COORDINATE PARTITION CONSTRUCTION WITH FINISH PLANS.11. PROVIDE 18 GA. METAL REINFORCING PLATES FOR ALL WALL MOUNTED

CONSTRUCTION.12. PROVIDE 1/2" CEMENT BOARD AT ALL LOCATIONS TO RECEIVE TILE FINISH.13. EXTEND GYPSUM BOARD CONSTRUCTION TO BOTTOM OF STRUCTURE IN

ALL ROOM WITHOUT FINISH SUSPENDED CEILING. FINISH GYP. BD. EDGEWITH J BEAD AND SEALANT.

14. ALL GYPSUM BOARD PARTITIONS SUPPORTING WALL HUNG CABINETS,SHELVING, OVERHEAD BINS AND FURNITURE SHALL HAVE 20 GAUGE STUDSSPACED AT 16" O.C. WITH FLAT GAUGE BLOCKING.

15. BRACE ALL METAL STUD PARTITIONS AT ALL LOCK SIDES OF DOORS, WHEREDUCTS INTERFERE WITH METAL STUDS GOING TO UNDERSIDE OF SLABABOVE AND WHERE CALLED FOR ON DRAWINGS.

16. PROVIDE CONTROL JOINTS IN GYPSUM BOARD PARTITION RUNS EXCEEDING30' OR MORE AND AT ALL INTERSECTIONS WITH BUILDING CORE, EXTERIORWALLS, COLUMNS AND WHERE RECOMMENDED BY MANUFACTURERS'WRITTEN INSTRUCTIONS.

17. TAPE AND SPACKLE ALL JOINTS IN DRYWALL, INCLUDING JOINTS ABOVE THECEILING.

18. PROVIDE WOOD BLOCKING OR STEEL STRAPPING AT ALL PARTITIONSSUPPORTING WALL HUNG CABINETS, SHELVING, OVERHEAD BINS ANDFURNITURE AS PER THE ARCHITECTURAL WOODWORK INSTITUTEINSTALLATION STANDARDS SECTION 1700. REFER TO CONSTRUCTIONPLANS.

19. PROVIDE DOUBLE STUDS AT BOTH JAMBS AND HEADER OF ALL DOORFRAMES.

20. ALL (N) WALLS TYPE A30 U.O.N.21. ALL (N) RESTROOM EQUIPMENT, GRAB BARS & TOILET TO COMPLY WITH

DIAGRAMS ON SHEET G0-201

FIRE RATING(BLANK = NON-RATED)

STUD/CMU SIZECOMMENT

WALL TYPE

0 — 7/8"1 — 1 5/8"2 — 2 1/2"3 — 3 5/8"4 — 4" 6 — 6"8 — 8"

A322X

4 — 3 5/8" 6 — 5 5/8" 8 — 7 5/8"10 — 9 5/8"12 — 11 5/8"

A STUDS: EXTEND FULL HEIGHT TO DECKGWB: EXTEND FULL HEIGHT TO DECK

B STUDS: EXTEND FULL HEIGHT TO DECKGWB: EXTEND 6" ABOVE CEILING

C STUDS: EXTEND 6" ABOVE CEILING - TIEDBACK TO STRUCTUREGWB: EXTEND TO UNDERSIDE OF CEILING

E STUDS: EXTEND FULL HEIGHT TO DECKGWB: SIDE 1 EXTEND 6" ABOVE CEILING,

SIDE 2 EXTEND TO DECKF FURRING

GWB: EXTEND FULL HEIGHT TO DECKG GLASS SIDELITEH PARTIAL HEIGHT, SEE ELEVATIONS

NUMBER OF BOARDS(BLANK=NO BOARD)

X SOUND ATTENUATION BATTS, AS SCHEDULEDQ SOUNDPROOF BOARD, AS SCHEDULED

STUD SIZE CMU SIZEWALL TAG LEGEND

WALL TYPES

1.1

D

C320

G-1

C320

2021

PRIVATEOFFICE

4"DOOR SCHED

REF 4' - 0"

SEE PLAN

A1022

F

60" MIN6' - 11 1/2"

EQRE

LOCA

TE (E

) PAR

TITI

ONS

EQEQ

ø 5' - 0

"

RELO

CATE

(E) P

ARTI

T ION

5' - 0

"

2

H

ø 5' - 0"

RELO

CATE

(E) P

ARTI

T ION

5' - 0

"

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:25:

13 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-102

PARTITION PLAN -LEVEL 2

SFC-00018A

ISSUE FOR PERMIT

09/11/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

SCALE: 1/8" = 1'-0"PARTITION PLAN - LEVEL 02 1

NO. NOTES

A101 PROVIDE BACKING IN WALL FOR LCD PANEL.A102 PROVIDE 4'X8' WHITE BOARD CENTERERED ON WALL AT 5'AFF O.C.

PARTITION NOTESPARTITION LEGEND

SCALE: 1/4" = 1'-0" A1-102TYPICAL OFFICE - PARTITION PLAN 2

REV DESCRIPTION DATE BY CHKDD TESTFIT 09/25/2017ISSUE FOR PERMIT 11/20/2017

SCALE: 1/4" = 1'-0" A1-102ENLARGED PLAN - EXISTING WOMENS RESTROOM 3

SCALE: 1/4" = 1'-0" A1-102ENLARGE PLAN - EXISTING MENS RESTROOM 5

KEY NOTES

Page 19: WestEd Request for Proposal #4

ALIGN

ALIG

N

1. ALL CEILING HEIGHTS ARE SHOWN A.F.F. U.O.N.2. CEILING HEIGHTS TO BE 9'-0" AFF UNLESS OTHERWISE NOTED.3. CENTER ALL CEILING MOUNTED DEVICES IN TILE U.O.N. INCLUDING ALL

DEVICES REFERENCED IN ELECTRICAL DRAWINGS.4. ALL GWB CEILINGS, SOFFITS, AND FACIA SHALL BE PAINTED P-2, REFER TO

FINISH SCHEDULE. U.O.N.5. ALL EXPOSED DECK AND DUCTWORK TO MATCH EXISTING SOFFIT PAINT.6. SWITCHES/DEVICES SHOWN ADJACENT TO DOORS SHALL BE INSTALLED 6"

FROM THE EDGE OF THE ADJACENT DOOR OPENING TO THE CENTERLINEOF THE SWITCH OR DEVICE U.O.N.

7. ALL NEW SWITCHES TO BE MOUNTED 4'-0" A.F.F. (U.O.N.) TO CENTER LINEOF SWITCH. MULTIPLE SWITCHES/DIMMERS TO BE GANGED & PROVIDEDWITH SINGLE GANG PLATE.

8. CEILING MOUNTED LIGHT FIXTURES, SMOKE DETECTORS, AND DIFFUSERSIN HALLWAYS SHALL BE CENTERED TO THE HALLWAY. FLAG ARCHITECT IFSPACING CAN'T BE EQUAL. U.O.N.

9. REFER TO FINISH SCHEDULE FOR CEILING MATERIAL.10. DIMENSIONS ARE TO THE CENTERLINE OF FIXTURE U.O.N.11. THE CONTRACTOR SHALL CHECK AND VERIFY ALL CEILING HEIGHTS AND

CONDITIONS FOR CLEARANCE OF MECHANICAL UNITS, DUCTWORK, PIPING,LIGHT FIXTURES, ETC. CONTRACTOR SHALL NOTIFY UNISPACE OF ANYCOMPLICATIONS WITH HEIGHT PRIOR TO START OF CONSTRUCTION.

12. SEE ENGINEERING DRAWINGS FOR ALL LIGHT FIXTURE CIRCUITING,SWITCHING AND RELATED WORK AND FOR QUANTITIES OF ALL CEILINGDIFFUSERS, DUCTWORK LAYOUTS.

13. APPROVAL FOR THE SPRINKLER SYSTEM SHALL BE FILED AND OBTAINED BYTHE SPRINKLER CONTRACTOR USING HIS OWN SHOP DRAWINGS, SIGNEDAND SEALED BY A LICENSED PROFESSIONAL ENGINEER IN THE STATECALIFORNIA. SPRINKLER CONTRACTOR SHALL SUBMIT SHOP DRAWING TOTHE ARCHITECT/ENGINEER FOR REVIEW PRIOR TO FILING WITH THEBUILDING DEPARTMENT.

14. PROVIDE AND INSTALL APPROPRIATE LAMPS AS REQ'D BY SPECIFIED LIGHTFIXTURES.

15. SPRINKLER HEADS IN DRYWALL CEILINGS AND SOFFITS SHALL BE FULLYRECESSED CONCEALED TYPE WITH WHITE FINISH AND SHALL BE CENTEREDON CEILING OR SOFFIT U.O.N.

16. SPRINKLER HEADS IN EXPOSED AREAS SHALL BE BRASS UPRIGHT HEADS.PIPING IN EXPOSED AREAS SHALL RUN PARALLEL OR PERPENDICULAR TOWALLS/BUILDING STRUCTURE.

17. THE ARCHITECTURAL REFLECTED CEILING PLANS INDICATE THE PROPERLOCATIONS OF LIGHTING FIXTURES. DO NOT SCALE ELECTRICAL DRAWINGSFOR LOCATION OF THE LIGHTING FIXTURES. VERIFY DIMENSIONS IN FIELD.

18. INSTALL EACH FIXTURE PROPERLY, PLUMB, TRUE, IN ALIGNMENT AND FREEOF DISTORTION. G.C. TO PROVIDE HANGERS, RODS, MOUNTING BRACKETS,MISCELLANEOUS FRAMING, SUPPORTING OR ATTACHING DEVICES, FRAMESAND OTHER COMPONENTS OR EQUIPMENT AS REQUIRED FOR ACOMPLETE INSTALLATION, AND AS REQUIRED TO PROPERLY SUPPORTIMPOSED LOADS INCLUDING FIXTURE WEIGHT. SECURE LIGHTING FIXTURESTO SUPPORTS. SUPPORT ALL LIGHTING FIXTURES INDEPENDENTLY OFDUCT WORK, PIPING, CEILING SUPPORTS OR OTHER ITEMS OCCURRINGWITHIN THE CEILING.

19. G.C. TO COORDINATE WITH A/V AND SECURITY DRAWINGS FOR ALLRELATED WORK.

20. ALL EXPOSED NEW AND EXISTING CONDUIT, DUCTWORK, VALVES, ETC TOBE PAINTED TO MATCH CEILING, U.O.N.

21. ALL CEILING DEVICES TO BE WHITE U.O.N.22. PAINT TO MATCH ALL DIFFUSERS, GRILLES, ACCESS PANELS, AND OTHER

EQUIPMENT TO THE SURFACE THEY ARE HOSTED ON.23. ALL LIGHT FIXTURES & CEILING EQUIPMENT TO BE MOUNTED EITHER AT THE

CENTER POINT OF THE TILE, OR ALONG THE CEILING GRID U.O.N.

ACT1 - 2' x 2' SUSPENDEDCEILING GRID SYSTEM, SEE FINISHSCHEDULE

GWB1, GWB2 AND GWB3 - GYPSUMBOARD CEILING/SOFFIT, SEE FINISHSCHEDULE

S SPEAKER

SUPPLY AIR DIFFUSER-LINEAR

SUPPLY AIR DIFFUSER

RETURN AIR GRILLE

SPECIALTY SPRINKLER HEAD

PROJECTION SCREEN

WINDOW TREATMENTCEILING MOUNTED

PS

EXIT SIGN CEILING MOUNTED

ACCESS PANEL

DIRECTION

8'-0" AFFACT-01

CEILING HEIGHT

CEILING MATERIAL

EXIT SIGN WALL MOUNTED

L1, INDIRECT 4' LINEAR PENDANT

L5, 4" x 4" SQUARE DOWNLIGHT.A=ACT APPLICATION,B=DRYWALL APPLICATION

L6, 4" x 4" SQUARE WALLWASHERA=ACT APPLICATION,B=DRYWALL APPLICATION

ACT2 - 2' x 5' SUSPENDEDCEILING GRID SYSTEM, SEE FINISHSCHEDULE

L10, ACCENT PIN LIGHT

L8, LED TAPELIGHT

L9, LED TAPELIGHT WITH EXTRUSION AND ACRYLIC LENS

L11, DECORATIVE PENDANT

L12, DECORATIVE PENDANT

L7, 2' X 2' RECESSED LED FIXTURE

L4, RECESSED 4' DIAMETER LED FIXTURE

L3A, RECESSED 8' LED LINEAR AT ACT

L2, INDIRECT 4' LINEAR PENDANT

L3B, RECESSED 6' LED LINEAR AT ACT

L3C, RECESSED 4' LED LINEAR AT ACT ACT3 - 1' X 6' SUSPENDEDCEILING GRID SYSTEM, SEE FINISHSCHEDULE

L3C

L1

L1

L1

L1

L1

L1

L1

L1L1

L1 L1L1L1L1L1

L1 L1 L1 L1

L1L1L1L1L1

L1L1

L1 L1 L1 L1 L1L1 L1L1L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L2 L2

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3A

L3A

L3C

L3C

L3C

L3C L3CL1

L1L1 L1

L3B

L3A

L4

L3C

L3A L3A

L3A

L3A

L3A

L3A

L4

L11 L11 L11L11 L11

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L1

L7

L7

L7

L7

L7

L7

11.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

43.9

L.9

L8

L8

L8, IN RECEPTIONDESK

L9L9L9

L8

L8

L9 L9

L9

L9

L7 L7

L7

L7

L7

L7

L7

L7L7

L7L7

L7

L7

L7

L7

L7

L7

L7

L7L1

L3C

L3C

L3C

? ?

L1

L3C L3CL3C

L3A

L7

L7

L1

L1

L4

L4

L4

L3C

?

L6B

L6B

L6B

L6B

L6B

L6B

L6B

L6B

L10

L6B

L6B

L6B

L5B

L4

L4

L4

L5AL5A

L5B

L5B

L5B L5B L5B

L5B

L12

L6A L6AL6A

L5B

L5B

L5B

L5B

L5AL5A L5A L5AL5A

L5A

L6A

L6A

L6A

L6A

L6A

L6A

L5A

L5A

L6A

L5A

L5A

L6A

L6A

L7

L7

L7

L7

L7

L7

L7

L5A L5A L5A L5A L6AL5AL5AL5A

L6A

L6A

L5A

L7L7

L6A

L6A

L6A

L6A L6A

L6A

L5A L5A

L6A

L6A

L5A L5AL5AL5A

L5AL5A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L6A

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L3C

L1

L1L1

L1 L1

L1

L1

L1

L1

L1

L-24 L-24

L1

L1

L1

L1

?

?

L3C

L3C

L3C

L3C

L5AL5A L5A L5AL5A

L3AL3A

L6AL3A

L9

L9L3B L3B L3B L3B L3B L3B L3B L3BL12

L12L12

L12

2' - 9

"

3' - 9"

4' - 4"

EQ EQ

3' - 9"

2' - 9

"

1' - 0" TYP

5' - 2

"

9' - 0"

9' - 4"

9' - 4"

9' - 0

"

9' - 0"TYP

9' - 0"

9' - 4"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0"

9' - 0" 9' - 0"

9' - 0"

9' - 0"

9' - 0"

1' - 1

1/2"

1' - 8

1/2"

2' - 10 1/2"2' - 9 1/2"

8' - 4" 8' - 4"TYP

TYP

8' - 4"

L9 L9

L2 L2

L2 L2

L2 L2

L2 L2

L2 L2

EQEQ

EQEQ

10' -

3 1/2"

10' -

0"10

' - 2"

10' -

0"10

' - 3 1

/2"EQ

.EQ

.

2' - 0"

2' - 0"

L2 L2

L2 L2

L2 L2

L2 L2

EQ.

10' -

3 1/2"

10' -

0"10

' - 3 1

/2"EQ

.

2' - 6

"

2062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2036

PRIVATEOFFICE

2028HOTEL 2026

CONFERENCE

2074CONFERENCE

2102

PRIVATEOFFICE2100

PRIVATEOFFICE

2002

PRIVATEOFFICE

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2010

PRIVATEOFFICE

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

2087CLOSET

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM 2065

WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2071HOTEL

2068PRINT

2079LOBBY

2064HALLWAY

2089

FURNITURESTORAGE

2077CONFERENCE

2085GN RR

2086WELLNESS

2049CONFERENCE

2000CONFERENCE

2001

PRIVATEOFFICE

2004OPEN OFFICE

2007

PRIVATEOFFICE

2008CONFERENCE

2047OPEN OFFICE

2041CONFERENCE

2039

PRIVATEOFFICE

2040HOTEL

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2027OPEN OFFICE

2025OPEN OFFICE

2023

PRIVATEOFFICE

2021

PRIVATEOFFICE

2019

PRIVATEOFFICE

2017

PRIVATEOFFICE

2015

PRIVATEOFFICE

2013

PRIVATEOFFICE

2011

PRIVATEOFFICE

2009HOTEL

2069FOCUS

2070SUPPLIES

2092FOCUS

2078MAIL ROOM

2060

PRIVATEOFFICE

2058

PRIVATEOFFICE2054

PRIVATEOFFICE

2052

PRIVATEOFFICE

2048

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2072HALLWAY

2032HALLWAY

2056HALLWAY

2067HALLWAY 2097

HALLWAY

2099HALLWAY

2020HALLWAY

2084HALLWAY

2038

PRIVATEOFFICE

2034

PRIVATEOFFICE

2075WORK ROOM

2042PRINT

2098PRINT

2096FOCUS

L7

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE

2103

PRIVATEOFFICE

2101

PRIVATEOFFICE

2083TRAINING

2082TRAINING

2080BREAK ROOM

2063HOTEL

2061

PRIVATEOFFICE

2059

PRIVATEOFFICE

2057

PRIVATEOFFICE

2055

PRIVATEOFFICE

2053

PRIVATEOFFICE

2051

PRIVATEOFFICE

2050

PRIVATEOFFICE

2076HALLWAY

2090HALLWAY

2081

TRAININGBREAKOUT

2073CLOSET

L7

L7

L7

L7

L7

L7

L7L7L7

ACT2

GWB2 GWB2

GWB3

GWB3

L5B

L5B

L5B

L5B

L5B

L5B

L5B

L5B

GWB3

GWB3

ACT2 ACT2

ACT3

9' - 0"A4-101

2

L3AL5A L3A L3A L3A L3A

L3A L5A

L3A

L3AL3AL3AL3A L3A

L3A

L5A

L5A

L3A L3A L3C L3A L3A

L3A

L5A

L3A

1.1

D

EQEQ

EQ EQ

L1

FULL TILE2' - 0

"

2' - 0"

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:25:

25 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-202

REFLECTED CEILINGPLAN - LEVEL 02

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REFLECTED CEILING NOTESREFLECTED CEILING LEGEND

NO. NOTES

KEY NOTES

SCALE: 1/8" = 1'-0"REFLECTED CEILING PLAN - LEVEL 02 1

REV DESCRIPTION DATE BY CHKDD TESTFIT 09/25/2017ISSUE FOR PERMIT 11/20/2017

SCALE: 1/4" = 1'-0"TYPICAL OFFICE - REFLECTED CEILING PLAN 2

Page 20: WestEd Request for Proposal #4

PS

P

1. POWER AND DATA LOCATIONS TO MAINTAIN ACOUSTIC SEPARATIONWITHIN A PARTITION. PLACE AT LEAST 12" SEPARATION & IN SEPARATESTUD BAYS WHERE LOCATED ON BOTH SIDES OF PARTITION.

2. PROVIDE DEDICATED POWER TO REFRIGERATORS. VERIFYELECTRICAL SIZE AND REQUIREMENTS WITH EQUIPMENT SPEC.

3. SEE GENERAL NOTES AT G0-100 AND ON FLOOR PLANS FORADDITIONAL INFORMATION.

4. DATA AND COMMUNICATIONS SCOPE IS BY CLIENT VENDOR.5. SWITCHING SHOWN FOR REFERENCE ONLY. SEE SHEET G0-202 FOR

MOUNTING HEIGHT DETAILS.6. COORDINATE ALL DEVICE LOCATIONS (INCLUDING FIRE ALARM

DEVICES) WITH DEVICE LOCATION DIAGRAM ON SHEET G0-201 OFARCHITECTURAL DRAWINGS PRIOR TO INSTALLATION.

7. G.C. TO LOCATE ALL OUTLETS AS PER POWER/ COMMUNICATION PLANAND MARK OUT OUTLETS FOR APPROVAL ON SITE PRIOR TOINSTALLATION. ENGINEERING DRAWINGS TO BE USED FOR CIRCUITINGAND POWER REQUIREMENTS ONLY. FOR LOCATIONS REFER TOARCHITECTURAL DRAWINGS.

8. FURNITURE DEALER TO LAYOUT FURNITURE FOR ARCHITECTAPPROVAL ON SITE. G.C. TO COORDINATE.

9. G.C. TO CONFIRM IF EXISTING TO BE RE-USED POWER OUTLETS HAVEBEEN TERMINATED. ALL ABANDONED POWER, DATA AND PHONE LINESTO BE COMPLETELY REMOVED.

10. REFER TO MEP DOCUMENT PACKAGE FOR ALL CIRCUITREQUIREMENTS AND ADDITIONAL CRITERIA. ELECTRICAL 'J' BOXES,SWITCHES, DEVICES, DATA DEVICES, ETC, TO MATCH OWNERSPECIFICATIONS, REFER TO MEP DOCUMENTS FOR ALL EQUIPMENTSPECIFICATIONS AND INSTALLATION CRITERIA.

11. REFER TO MEP DOCUMENT PACKAGE FOR LOCATIONS OF HVACTHERMOSTATS, SPECIFICATIONS AND INSTALLATION REQUIREMENTS.MOUNTING HEIGHTS PER ARCHITECTURAL DRAWINGS.

12. REFER TO AV DRAWINGS FOR ALL AUDIO VISUAL AND CONFERENCINGEQUIPMENT LOCATIONS AND CIRCUITING.

13. SEE DRAWINGS G0-100, G0-101, G0-201 AND G0-401 FOR ADDITIONALNOTES, LEGENDS AND SYMBOLS.

14. ALL OUTLETS AND CONDUIT BEING INSTALLED IN FIRE RATEDPARTITIONS ARE TO BE FIRESTOPPED AS REQUIRED BY CODE AND TOMAINTAIN FIRE RATING, TYP.

15. WHITE COLORED WALL OUTLETS AND DATA DEVICES/ PLATES TO BEINSTALLED, TYP. U.O.N. DEDICATED AND COMPUTER OUTLETS TO BELIGHT GRAY WITH WHITE PLATES.

16. SEE AV DRAWINGS FOR ADDITIONAL CONDUIT AND JUNCTION BOXREQUIREMENTS. ALL LOCATIONS TO BE MARKED OUT ON SITE FORARCHITECT APPROVAL.

17. ALL CEILING DEVICES TO BE WHITE U.O.N.18. DEVICE LOCATIONS IN OFFICES AND CONFERENCE ROOMS AS WELL AS

WORKSTATIONS TO HAVE LOCATIONS VERIFIED ON SITE BY FURNITUREVENDOR TO AVOID HITS AND CONFLICTS.

19. POWER/ DATA/ AV FEEDS AT TABLE LOCATIONS NEED TO BEHARDWIRED TO FURNITURE VIA STUB-UP IN TABLE BASE U.O.N.

20. ELECTRICAL VOICE/ DATA AND AV FEED IN LOCATIONS TO BECOORDINATED WITH ARCHITECT AND FURNITURE VENDOR ON SITE.

21. SEE EQUIPMENT SCHEDULE FOR APPLIANCE SPECIFICATION.22. GENERAL CONTRACTOR TO CONFIRM THAT ALL (E) ELECTRICAL/DATA

OUTLETS TO REMAIN ARE IN ACCORDANCE WITH BUILDINGSTANDARDS, (TYP, THROUGHOUT).

23. ALL FURNITURE SHOWN IS FOR REFERENCE ONLY.24. WIRELESS ACCESS POINTS LOCATIONS TO BE CONFIRMED BY CLIENT

IT/AV TEAM.

DUPLEX LOCATION

VIDEO INTERCOM DEVICEVI

CARD READER

OCCUPANCY SENOR, WALL MOUNTED

OCCUPANCY SENOR, CEILING MOUNTEDOS

S SECURITY CAMERA W/ AUDIO

PROJECTOR LOCATION

DATA LOCATION (SEE IT DWGS FOR MORE INFO)

USB / SIMPLEX COMBO LOCATION

CABLE TV FEED (SEE AV DWGS)

AV CONTROL PANEL LOCATIONAV

SPECIALTY RECEPTACLE LOCATION (SEE AV / IT /ELEC FOR MORE INFO)

CR

OS

TV

DEDICATED DUPLEX LOCATION

PROJECTION SCREEN

QUAD LOCATION

POWER/ DATA & AV LOCATION AT RECESSED FLOOR BOX

POWER LOCATION AT RECESSED FLOOR BOX

A/V IN-WALL BOX (SEE IT DRAWINGS FOR MORE INFO)WB

WIRELESS ACCESS POINT AT CEILING (SEE IT DRAWINGS FOR REQ'S)WA

1

1.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

4

3.9

L.9

2049CONFERENCE

2050

PRIVATEOFFICE

2051

PRIVATEOFFICE

2053

PRIVATEOFFICE

2055

PRIVATEOFFICE

2057

PRIVATEOFFICE

2059

PRIVATEOFFICE

2061

PRIVATEOFFICE

2063HOTEL

2048

PRIVATEOFFICE

2052

PRIVATEOFFICE

2054

PRIVATEOFFICE

2058

PRIVATEOFFICE

2060

PRIVATEOFFICE

2062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2036

PRIVATEOFFICE

2041CONFERENCE

2040HOTEL

2039

PRIVATEOFFICE

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2034

PRIVATEOFFICE2038

PRIVATEOFFICE

2028HOTEL

2026CONFERENCE

2074CONFERENCE

2080BREAK ROOM

2082TRAINING

2101

PRIVATEOFFICE

2103

PRIVATEOFFICE

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE 2000

CONFERENCE

2102

PRIVATEOFFICE

2100

PRIVATEOFFICE

2002

PRIVATEOFFICE

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2010

PRIVATEOFFICE

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

2087CLOSET

2007

PRIVATEOFFICE

2008CONFERENCE

2009HOTEL

2011

PRIVATEOFFICE

2013

PRIVATEOFFICE

2015

PRIVATEOFFICE

2017

PRIVATEOFFICE

2019

PRIVATEOFFICE

2021

PRIVATEOFFICE

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM

2065WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2004OPEN OFFICE

2071HOTEL

2068PRINT

2079LOBBY

2064HALLWAY

2089

FURNITURESTORAGE

2077CONFERENCE

2085GN RR

2086WELLNESS

2083TRAINING

2081

TRAININGBREAKOUT

2047OPEN OFFICE

2092FOCUS

2023

PRIVATEOFFICE

2075WORK ROOM

2001

PRIVATEOFFICE

2070SUPPLIES

2069FOCUS

2073CLOSET

2078MAIL ROOM

2027OPEN OFFICE 2025

OPEN OFFICE

2098PRINT

2096FOCUS

A301

A301A301

A301

A302

A302

A302

A302

A302A302

A302

A302A302 A302

A302

+54"+54"

+54"+54"+54"+54"

+54"+54"

+34"

+38" +38"

+38"+38"

+22"

+22"

+38"

+38"

+29"

+34" +34" +34" +34"

+34"

+34"

+38"

+38"+3

8"

+38"

+38"

+38"

+38"

+38"

A303

A304

A304

A303

A303

A303

A303

+38" +38"

+34"

+38"+38"+38"

+38" +38" +38"

+29"+29"

+38"

+38"

+38"

A301 A301

+54"+54"+54"+54"

+54"+54"

A305

A305

CRJ

CRJ

CRJ

CRJ

CRJ

2' - 2

"

5' - 3

"

4' - 7"

WBWB

WB

WB

WB

WB

WB WB WB

+54"

+54"

WA WA WA WA

WAWAWAWA

WA WA WAWA

WA

WA

WA

WA

A306

A306

A306

A306

A306

A306

A306

A306

A306

A306

A306

A306

A306

A306

1.1

D

2021

PRIVATEOFFICE

4' - 0

" 6"6"

1' - 2

"

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

05 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-301

POWER & DATA PLAN -LEVEL 02

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

POWER AND DATA NOTESPOWER AND DATA LEGENDNO. NOTES

A301 PROVIDE POWER IN J BOX IN CEILING ABOVE FOR TENANT PROVIDEDIPAD ROOM IDENTIFICATION SYSTEM

A302 TENANT PROVIDED LED MONITORA303 PROVIDE POWER & DATA FROM WALL FOR 1 QUAD, 1 DUPLEX & DATA

PER WORKSTATIONA304 REUSE EXISTING FLOOR AND WALL CONDUIT TO PROVIDE POWER &

DATA TO WORKSTATIONS. PROVIDE 1 QUAD, 1 DUPLEX & DATA PERWORKSTATION

A305 PROVIDE POWER & DATA FOR FLUSH MOUNTED CAMERA ABOVE ONCENTER ABOVE DISPLAY

A306 PROVIDE RECESSED FLOOR BOX AS PER CLIENT REQUIREMENTS.COORDINATE HOMERUN TRENCH SIZE TO CLIENT REQUIREMENTS. SEEIT DRAWINGS FOR MORE INFO

KEY NOTES

SCALE: 1/8" = 1'-0"POWER & COMM - LEVEL 02 1

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

SCALE: 1/4" = 1'-0"TYPICAL OFFICE/HOTELING OFFICE - POWER PLAN 2

Page 21: WestEd Request for Proposal #4

OPEN

TO

BELOW

UP

UP UP

1. ALL WALLS WITHIN PROJECT SCOPE TO RECIEVE P-1 PAINT WITH B-1BASE U.O.N.

2. SCHEDULED FINISHES REFER TO SHEET A6-103. SEE SPECIFICATIONSFOR ADDITIONAL INSTRUCTION.

3. ALL NEW SURFACES RECEIVING PAINT SHALL RECEIVE (1) COAT OFPRIMER AND (2) COATS OF FINISH PAINT.

4. ALL FINISHES ARE TO BE INSTALLED AS PER MANUFACTURERGUIDELINES.

5. CARPET INSTALLER TO MAINTAIN PATTERN ALIGNMENT FROM WIDTHTO WIDTH.

6. ARCHITECT TO VERIFY CARPET PATTERN LAYOUT MOCK-UP ON SITEPRIOR TO INSTALL. REFER TO SHEET A6-103.

7. FLOORING CONTRACTOR TO INSTALL ALL CARPET PER SPECIFIEDDIRECTION.

8. PAINTING CONTRACTOR SHALL PAINT ALL GYPSUM BOARDCEILINGS, FASCIAS, AND SOFFITS TO MATCH EXISTING. UON.

9. CONTRACTOR SHALL INSURE THAT ALL SURFACE TO RECEIVEFINISHES ARE CLEAN, TRUE AND FREE OF IRREGULARITIES. PATCHAND REPAIR AS NEEDED.

10. FLOORING CONTRACTOR SHALL SEE SHEET 1/A5-100 FORTRASITION STRIP.

11. COORDINATE ALL INTERIOR FINISHES/TRANSITION WITH (E) BASEBUILDING FINISHES. VERIFY SCOPE PRIOR TO INSTALLATION.

12. CONTRACTOR SHALL PROPERLY PREPARE (SPACKLE/PLASTER,SANDING, ETC.) ALL NEW SURFACES FOR PAINTING OR WALLCOVERING AS PER MANUFACTURER'S RECOMMENDATION.

13. CONTRACTOR SHALL PREPARE SUB-FLOOR AND/OR MORTAR FILL INACCORDANCE WITH MANUFACTURER'S SPECIFICATION TO RECEIVENEW FINISHES. PREP SUB FLOOR TO MAINTAIN LEVEL TRANSITIONSFROM ONE FLOOR MATERIAL TO ANOTHER.

14. G.C. TO VERIFY ALL TILE START POINTS WITH ARCHITECT PRIOR TOINSTALLATION.

15. ALL RECESSED/FLUSH BASE TO HAVE 20GA FLAT STOCK BLOCKINGSECURED TO STUDS FOR BASE SUPPORT

16. CONTRACTOR SHALL PROVIDE MANUFACTURE REQUIRED SUBSTRATEUNDER ALL FINISHED SURFACE. CONTRACTOR SHALL PROPERLYPREPARE SURFACES PER FINISH MANUFACTURES SPECIFICATIONS.

17. ALL WORK BY OTHERS SHALL BE ADEQUATELY PROTECTED BY SUB-CONTRACTOR AGAINST DAMAGE.

18. BASE CORNER SECTIONS SHALL BE PROVIDED IN LENGTHS NOT LESSTHAN 6'-0" AS MEASURED FROM THE CORNER PROPER.

19. FLOOR FINISH TRANSITION TO OCCUR AT CENTERLINE OF DOOR ORCASED OPENING UON.

20. PROVIDE STRAIGHT TYPE BASE AT CARPETED AREAS, AND COVE BASEAT

21. FLOORING SUB-CONTRACTOR IS RESPONSIBLE FOR FLOORPREPARATION AND CONCRETE FLOOR RESTORATION. REFER TOSPECIFICATIONS AND MANDATORY WALK-THROUGH FOR FURTHERINFORMATION.

22. ALL CLOSETS SHALL RECEIVE SAME FINISHES AS ADJACENT AREA,UON.

23. APPLY ALL PRIMERS AND SEALERS PER MANUFACTURERRECOMMENDATION. REFER TO SPECIFICATIONS FOR ADDITIONALINFORMATION.

24. ALL PROJECT FINISHES SHALL BE SUBMITTED TO ARCHITECT FORAPPROVAL PRIOR TO COMMENCEMENT.

25. ALL FINISHED MATERIALS SHALL MEET AND COMPLY WITH LOCALAND FEDERAL FLAME SPREAD AND TOXICITY REGULATIONS.

26. FOR ADDITIONAL FINISH INFORMATION SEE FINISH SCHEDULE ONSHEET A6-103.

27. GC TO VERIFY ALL EXISTING WALL, FLOOR, & LEVEL CONDITIONS.IF ADDITONAL FEATHERING OR LEVELING IS REQUIRED,COORDINATE APPROVAL WITH ARCHITECT PRIOR TO INSTALL.

/- ---

BASE FINISHWALL FINISH

CPT1 FLOOR FINISH TAG

WALL / BASE FINISH TAG

PATTERN DIRECTION

FINISH TRANSITION TAG

PT1XX

CPT1

CPT1

CPT12062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2036

PRIVATEOFFICE

2028HOTEL 2026

CONFERENCE

2074CONFERENCE

2102

PRIVATEOFFICE

2100

PRIVATEOFFICE

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2010

PRIVATEOFFICE

2087CLOSET

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM 2065

WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2071HOTEL

2068PRINT

2079LOBBY

2064HALLWAY

2089

FURNITURESTORAGE

2077CONFERENCE

2085GN RR

2086WELLNESS

2049CONFERENCE

2000CONFERENCE

2001

PRIVATEOFFICE

2004OPEN OFFICE

2007

PRIVATEOFFICE

2008CONFERENCE

2047OPEN OFFICE

2041CONFERENCE

2039

PRIVATEOFFICE

2040HOTEL

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2027OPEN OFFICE

2025OPEN OFFICE

2023

PRIVATEOFFICE

2021

PRIVATEOFFICE

2019

PRIVATEOFFICE

2017

PRIVATEOFFICE

2015

PRIVATEOFFICE

2013

PRIVATEOFFICE

2011

PRIVATEOFFICE

2009HOTEL

2069FOCUS

2070SUPPLIES 2092

FOCUS

2078MAIL ROOM

2060

PRIVATEOFFICE

2054

PRIVATEOFFICE

2052

PRIVATEOFFICE

2048

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2072HALLWAY

2032HALLWAY

2056HALLWAY

2067HALLWAY

2097HALLWAY

2099HALLWAY

2020HALLWAY

2084HALLWAY

2038

PRIVATEOFFICE

2034

PRIVATEOFFICE

2075WORK ROOM

2042PRINT

2098PRINT

2096FOCUS

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE

2103

PRIVATEOFFICE

2101

PRIVATEOFFICE

2083TRAINING

2082TRAINING

2080BREAK ROOM

2063HOTEL

2061

PRIVATEOFFICE

2059

PRIVATEOFFICE

2057

PRIVATEOFFICE

2055

PRIVATEOFFICE

2053

PRIVATEOFFICE

2051

PRIVATEOFFICE

2050

PRIVATEOFFICE

2076HALLWAY

2090HALLWAY

2081

TRAININGBREAKOUT

2073CLOSET

CPT1

CPT1

CPT1

CPT1

CPT1

CPT1

CPT1

CPT1

CPT4CPT4

CPT4

CPT4

CPT2CPT2CPT2CPT2

CPT2 CPT2

CPT2

CPT2

CPT2

CPT2

CPT2

CPT2CPT2CPT2CPT2CPT2

CPT2 CPT2 CPT2 CPT2 CPT2 CPT2 CPT2 CPT2

CPT2CPT2

CPT2CPT2CPT2CPT2CPT2CPT2CPT2CPT2

CPT2CPT2CPT2

CPT2

CPT2

CPT2

CPT2

CPT2 CPT2 CPT2 CPT2 CPT2 CPT2

CPT2CPT2CPT2CPT2CPT2CPT2CPT2CPT2

2058

PRIVATEOFFICE

CPT2

CPT2

CPT2

CPT3

CPT3

CPT3 CPT3

CPT3

CPT2

CPT2

CPT2 CPT2

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

2002

PRIVATEOFFICE

CPT2

TL1

TL2

CPT5

TL2

TL2TL2

TL2

TL4

TL3

TL3

TL3

TL4

TL3

2' - 0"

2' - 0

"

1' - 0

"

1' - 0"

1' - 0"

1' - 0"

TL1

TL1

EQ.

EQ.

TL5

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

11 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-401

FLOOR FINISH PLAN -LEVEL 02

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

FINISH NOTESFINISH LEGEND

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

SCALE: 1/8" = 1'-0"FLOOR FINISH PLAN - LEVEL 02 1

Page 22: WestEd Request for Proposal #4

OPEN

TO

BELOW

UP

UP UP

2062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2036

PRIVATEOFFICE

2028HOTEL

2026CONFERENCE

2074CONFERENCE

2102

PRIVATEOFFICE

2100

PRIVATEOFFICE

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2010

PRIVATEOFFICE

2087CLOSET

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM 2065

WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2071HOTEL

2068PRINT

2079LOBBY

2064HALLWAY

2089

FURNITURESTORAGE

2077CONFERENCE

2085GN RR

2086WELLNESS

2049CONFERENCE

2000CONFERENCE

2001

PRIVATEOFFICE

2004OPEN OFFICE

2007

PRIVATEOFFICE

2008CONFERENCE

2047OPEN OFFICE

2041CONFERENCE

2039

PRIVATEOFFICE

2040HOTEL

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2027OPEN OFFICE

2025OPEN OFFICE

2023

PRIVATEOFFICE

2021

PRIVATEOFFICE

2019

PRIVATEOFFICE

2017

PRIVATEOFFICE

2015

PRIVATEOFFICE

2013

PRIVATEOFFICE

2011

PRIVATEOFFICE

2009HOTEL

2069FOCUS

2070SUPPLIES 2092

FOCUS

2078MAIL ROOM

2060

PRIVATEOFFICE

2054

PRIVATEOFFICE

2052

PRIVATEOFFICE

2048

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2072HALLWAY

2032HALLWAY

2056HALLWAY

2067HALLWAY

2097HALLWAY

2099HALLWAY

2020HALLWAY

2084HALLWAY

2038

PRIVATEOFFICE

2034

PRIVATEOFFICE

2075WORK ROOM

2042PRINT

2098PRINT

2096FOCUS

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE

2103

PRIVATEOFFICE

2101

PRIVATEOFFICE

2083TRAINING

2082TRAINING

2080BREAK ROOM

2063HOTEL

2061

PRIVATEOFFICE

2059

PRIVATEOFFICE

2057

PRIVATEOFFICE

2055

PRIVATEOFFICE

2053

PRIVATEOFFICE

2051

PRIVATEOFFICE

2050

PRIVATEOFFICE

2076HALLWAY

2090HALLWAY

2081

TRAININGBREAKOUT

2073CLOSET

2058

PRIVATEOFFICE

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

2002

PRIVATEOFFICE

PT4RB4

PT8RB4

WC1 WC1

WC2

WC2

WC2

WC2

WC2

WC2

WC2

WC2

WC2 WC2

WC2

A4-1013

A4-10011

WT1

PT5RB5

PT5RB5

PT5RB5

PT5RB5

PT3RB3

PT3RB3

PT3RB3

PT3RB3

PT6RB6

PT6RB6

PT6RB6

TYP.

TYP.

TYP.

PT6RB6

TYP.

1. ALL WALLS WITHIN PROJECT SCOPE TO RECIEVE P-1 PAINT WITH B-1BASE U.O.N.

2. SCHEDULED FINISHES REFER TO SHEET A6-103. SEE SPECIFICATIONSFOR ADDITIONAL INSTRUCTION.

3. ALL NEW SURFACES RECEIVING PAINT SHALL RECEIVE (1) COAT OFPRIMER AND (2) COATS OF FINISH PAINT.

4. ALL FINISHES ARE TO BE INSTALLED AS PER MANUFACTURERGUIDELINES.

5. CARPET INSTALLER TO MAINTAIN PATTERN ALIGNMENT FROM WIDTHTO WIDTH.

6. ARCHITECT TO VERIFY CARPET PATTERN LAYOUT MOCK-UP ON SITEPRIOR TO INSTALL. REFER TO SHEET A6-103.

7. FLOORING CONTRACTOR TO INSTALL ALL CARPET PER SPECIFIEDDIRECTION.

8. PAINTING CONTRACTOR SHALL PAINT ALL GYPSUM BOARDCEILINGS, FASCIAS, AND SOFFITS TO MATCH EXISTING. UON.

9. CONTRACTOR SHALL INSURE THAT ALL SURFACE TO RECEIVEFINISHES ARE CLEAN, TRUE AND FREE OF IRREGULARITIES. PATCHAND REPAIR AS NEEDED.

10. FLOORING CONTRACTOR SHALL SEE SHEET 1/A5-100 FORTRASITION STRIP.

11. COORDINATE ALL INTERIOR FINISHES/TRANSITION WITH (E) BASEBUILDING FINISHES. VERIFY SCOPE PRIOR TO INSTALLATION.

12. CONTRACTOR SHALL PROPERLY PREPARE (SPACKLE/PLASTER,SANDING, ETC.) ALL NEW SURFACES FOR PAINTING OR WALLCOVERING AS PER MANUFACTURER'S RECOMMENDATION.

13. CONTRACTOR SHALL PREPARE SUB-FLOOR AND/OR MORTAR FILL INACCORDANCE WITH MANUFACTURER'S SPECIFICATION TO RECEIVENEW FINISHES. PREP SUB FLOOR TO MAINTAIN LEVEL TRANSITIONSFROM ONE FLOOR MATERIAL TO ANOTHER.

14. G.C. TO VERIFY ALL TILE START POINTS WITH ARCHITECT PRIOR TOINSTALLATION.

15. ALL RECESSED/FLUSH BASE TO HAVE 20GA FLAT STOCK BLOCKINGSECURED TO STUDS FOR BASE SUPPORT

16. CONTRACTOR SHALL PROVIDE MANUFACTURE REQUIRED SUBSTRATEUNDER ALL FINISHED SURFACE. CONTRACTOR SHALL PROPERLYPREPARE SURFACES PER FINISH MANUFACTURES SPECIFICATIONS.

17. ALL WORK BY OTHERS SHALL BE ADEQUATELY PROTECTED BY SUB-CONTRACTOR AGAINST DAMAGE.

18. BASE CORNER SECTIONS SHALL BE PROVIDED IN LENGTHS NOT LESSTHAN 6'-0" AS MEASURED FROM THE CORNER PROPER.

19. FLOOR FINISH TRANSITION TO OCCUR AT CENTERLINE OF DOOR ORCASED OPENING UON.

20. PROVIDE STRAIGHT TYPE BASE AT CARPETED AREAS, AND COVE BASEAT

21. FLOORING SUB-CONTRACTOR IS RESPONSIBLE FOR FLOORPREPARATION AND CONCRETE FLOOR RESTORATION. REFER TOSPECIFICATIONS AND MANDATORY WALK-THROUGH FOR FURTHERINFORMATION.

22. ALL CLOSETS SHALL RECEIVE SAME FINISHES AS ADJACENT AREA,UON.

23. APPLY ALL PRIMERS AND SEALERS PER MANUFACTURERRECOMMENDATION. REFER TO SPECIFICATIONS FOR ADDITIONALINFORMATION.

24. ALL PROJECT FINISHES SHALL BE SUBMITTED TO ARCHITECT FORAPPROVAL PRIOR TO COMMENCEMENT.

25. ALL FINISHED MATERIALS SHALL MEET AND COMPLY WITH LOCALAND FEDERAL FLAME SPREAD AND TOXICITY REGULATIONS.

26. FOR ADDITIONAL FINISH INFORMATION SEE FINISH SCHEDULE ONSHEET A6-103.

27. GC TO VERIFY ALL EXISTING WALL, FLOOR, & LEVEL CONDITIONS.IF ADDITONAL FEATHERING OR LEVELING IS REQUIRED,COORDINATE APPROVAL WITH ARCHITECT PRIOR TO INSTALL.

/- ---

BASE FINISHWALL FINISH

CPT1 FLOOR FINISH TAG

WALL / BASE FINISH TAG

PATTERN DIRECTION

FINISH TRANSITION TAG

PT1XX

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

16 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-402

WALL FINISH PLAN -LEVEL 02

SFC-00018A

ISSUE FOR PERMIT

11/09/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

SCALE: 1/8" = 1'-0"WALL FINISH PLAN - LEVEL 02 1

FINISH NOTESFINISH LEGEND

Page 23: WestEd Request for Proposal #4

SYMBOL MANUFACTURER/DESCRIPTIONSYMBOL MANUFACTURER/DESCRIPTIONSYMBOL MANUFACTURER/DESCRIPTIONSYMBOL MANUFACTURER/DESCRIPTIONGYPSUM BOARD CEILING

CARPET TILE

COLOR: PT1FINISH: FLATDESCRIPTION: 5/8" SUSPENDED GYPSUM BOARD CEILING, TYPICAL GYPSUM BOARDCEILING UNLESS OTHERWISE NOTED

GWB1

MANUFACTURER: INTERFACESTYLE/SERIES: GROUND WAVES VERSE 163130AK00COLOR: 104901 ICEBERG/COLORSSIZE: 25CM X 1MDESCRIPTION: PLANK CARPET, HERRINGBONE INSTALLATIONDESCRIPTION (CONT): GLASBAC RE BACKINGDIRECTION: REFER TO FINISH PLAN FOR DIRECTIONLOCATION: TYPICAL CARPET UNLESS NOTED OTHERWISEVENDOR CONTACT: JOE FOLEY, 312-961-7046, [email protected]

CPT1

MANUFACTURER: ARMSTRONGSTYLE/SERIES: MIGRATIONS BBTCOLOR: T3500 BASALT BLACKSIZE: 12" X 12"DESCRIPTION: BIO BASED TILEDIRECTION: REFER TO FINISH PLAN FOR LAYOUT, MONOLITHIC INSTALLATIONLOCATION: CLOSETS AS NOTED ON FINISH PLAN

TL3

RESILIENT FLOORING

SYMBOL MANUFACTURER/DESCRIPTION

FINISH: STAINED TO MATCH ARCHITECT'S SAMPLE, CLEAR COAT PRE-CATALYZEDLACQUER, APPROXIMATELY 40 SHEEN, APPLIED WITH SPRAY GUNFLITCH: VENEER TO BE FROM SINGLE LOG. PROVIDE FLITCH SAMPLES FOR REVIEW |FLITCH # SAMPLE: 5184-24-13PATTERN NAME: BOOKMATCHSPECIES: RIFT CUT EUROPEAN OAK FSCLOCATION: TRAINING BREAKOUT AS NOTED ON PLANVENDOR CONTACT: ROB GIBSON, 616-871-3345, [email protected]: GRAIN DIRECTION TO BE VERTICAL, SEE ELEVATIONSSUBSTRATE: 3/4" MDFSUPPLIER: DOOGE VENEERS

WD1

FINISH: CLEAR COAT PRE-CATALYZED LACQUER, APPROXIMATELY 40 SHEEN,APPLIED WITH SPRAY GUNSIZE: 4" HIGH WITH 1/2" REVEALDESCRIPTION: FLUSH SOLID WOOD BASE WITH WD01 VENEERNOTE: VENEER GRAIN DIRECTION TO MATCH VENEER PANELS

WD2

INTERIOR WOODWORK

PAINT

PAINT

PAINT

MANUFACTURER: BENJAMIN MOORECOLOR: CHANTILLY LACEFINISH: EGGSHELL AT WALLS AND FLAT AT CEILINGS/SOFFITSNUMBER: OC-65LOCATION: WALL + GWB CEILINGS PAINT THROUGHOUT U.N.O.

PT1

MANUFACTURER: BENJAMIN MOORECOLOR: KENDALL CHARCOALFINISH: EGGSHELLNUMBER: HC-166LOCATION: REFER TO FINISH PLAN

PT2

PAINT

RESILIENT FLOORING

MANUFACTURER: SHAW CONTRACTCOLOR: BONE 65515FINISH: 0503V PIGMENT DIRECT GLUESIZE: 7"X48"DESCRIPTION: DIRECT GLUE LUXURY VINYL TILEDESCRIPTION (CONT): MONOLITHIC INSTALLATIONTHICKNESS: 20 MILLOCATION: REFER TO FINISH PLANS FOR DIRECTION AND LAYOUTVENDOR CONTACT: PAIGE SIVERTSEN, 312-391-0792,[email protected]

TL1

ACOUSTICAL PANEL CEILING

INTERIOR WOODWORK

PAINT

BASE - RUBBER BASEMANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 08 ICICLESIZE: 4" HIGH 1/8" THICKDESCRIPTION: ROLLED GOODSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: TYPICAL BASE U.N.O.

RB1

BASE - RUBBER BASE

MANUFACTURER: NEVAMARCOLOR: JETT BLACK S6053TFINISH: ARMORED PROTECTION, TEXTUREDDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: TYPICAL BASE CABINETS AND COUNTERTOPS UNLESS NOTEDOTHERWISEVENDOR CONTACT: DEBBIE COPOT, 630-470-2554, [email protected]

PL1

PAINT

FABRIC WRAPPED PANELSMANUFACTURER: CARNEGIESTYLE/SERIES: ABACUS EMBROIDERCOLOR: 6185 4SIZE: WRAPPED ON 1" THICK ACOUSTICAL PANELS, WHISPERWALLS OR EQUALDESCRIPTION: FABRIC WRAPPED PANELSWIDTH: FABRIC WIDTH 56"LOCATION: TRAINING BREAKOUT AS SHOWN ON FINISH PLANVENDOR CONTACT: KATHLEEN NEARY, 312-593-6069,[email protected]: REFER TO ELEVATIONS FOR SEAMING LOCATIONSBACKING: UNBACKED

FWP1

MANUFACTURER: ARMSTRONGSTYLE/SERIES: ULTIMACOLOR: WHITESIZE: 24"X60"EDGE CONDITION: TEGULARLOCATION: ACCENT CEILING TILE AS NOTED ON REFLECTED CEILING PLANGRID STYLE: SILHOUETTE 9/16" BOLT SLOT SYSTEMS

ACT2ACOUSTICAL PANEL CEILING

INTERIOR WOODWORK

PAINT

PAINT

BASE - RUBBER BASE

INTERIOR WOODWORK

MANUFACTURER: NEVAMARCOLOR: NEUTRAL GRAY, S6012-GFINISH: GLOSSDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: BREAKROOM UPPER CABINETSVENDOR CONTACT: DEBBIE COPOT, 630-470-2554, [email protected]

PL2

INTERIOR WOODWORK

INTERIOR WOODWORK

RESIN PANELMANUFACTURER: 3-FORMCOLOR: NEBULOUS N47 + POWDER D03FINISH: FRONT: VELLUM FO4/VELLUM FO4DESCRIPTION: RESIN LIGHTBOXDESCRIPTION (CONT): CHROMATHICKNESS: 1/2" THICKLOCATION: RECEPTION DESK, REFER TO RECEPTION DESK DETAILSVENDOR CONTACT: CHRIS JANSON, 773-368-6770, [email protected]

RP01

ENGINEERED STONE COUNTERMANUFACTURER: OKITECOLOR: 1911 GRIGIO NORDICOFINISH: POLISHEDDESCRIPTION: RESTROOM COUNTERTOPTHICKNESS: 3/4" THICK, MITER EDGEVENDOR CONTACT: TIM COYNE, 312-259-1070, [email protected]

ST2

ENGINEERED STONE COUNTERMANUFACTURER: OKITECOLOR: 1665 BIANCO ASSOLUTOFINISH: POLISHEDDESCRIPTION: COUNTERTOPS AS NOTED IN THE ELEVATIONSTHICKNESS: 3/4" THICK, MITER EDGEVENDOR CONTACT: TIM COYNE, 312-259-1070, [email protected]

ST1

WALL TILEMANUFACTURER: AKDOCOLOR: BIRCH WHITEFINISH: ORIGINSIZE: 2.5" X 10.5" SUBWAY TILEGROUT: MAPEI UNSANDED GROUT. COLOR TBDLOCATION: BACKSPLASH AT BREAK ROOMVENDOR CONTACT: BURAK ARAL, 646-856-0795, [email protected]

WT1

MANUFACTURER: BENJAMIN MOORECOLOR: SERENATAFINISH: EGGSHELLNUMBER: AF-535LOCATION: REFER TO FINISH PLAN

PT8

MANUFACTURER: BENJAMIN MOORECOLOR: MYSTERIOUSFINISH: EGGSHELLNUMBER: AF-565LOCATION: REFER TO FINISH PLAN

PT4

MANUFACTURER: BENJAMIN MOORECOLOR: GRAPPAFINISH: EGGSHELLNUMBER: 1393LOCATION: REFER TO FINISH PLAN

PT5

MANUFACTURER: BENJAMIN MOORECOLOR: CAPE BLUEFINISH: EGGSHELLNUMBER: 1642LOCATION: REFER TO FINISH PLAN

PT7

MANUFACTURER: BENJAMIN MOORECOLOR: BLACKFINISH: EGGSHELLNUMBER: 2132-10LOCATION: AT ALL PERIMETER WALLS EXCEPT WITHIN PRIVATE OFFICES. TERMINATEPAINT AT INSIDE CORNERS WHERE TRANSITIONING TO NEW PARTITIONSPERPENDICULAR TO WINDOWS

PT6

MANUFACTURER: BENJAMIN MOORECOLOR: RED TBDFINISH: EGGSHELLLOCATION: REFER TO FINISH PLAN

PT3

WALL TILE

DESCRIPTION: CLEAR TEMPERED GLASS, POLISHED AND EASED EDGESTHICKNESS: 1/2" THICKLOCATION: TYPICAL GLAZING UNLESS NOTED OTHERWISEGL1GLAZING

GLAZINGMANUFACTURER: MCGRORY GLASS OR EQUALCOLOR: UNCH-080DESCRIPTION: LAMINATED GLASS WITH COLORED FILM INTERLAYERTHICKNESS: 5/16" THICKLOCATION: ACCENT GLAZING AT TRAINING BREAKOUTVENDOR CONTACT: JOHN CLARK, 856-579-3211, [email protected]

GL2

MANUFACTURER: NEVAMARCOLOR: DEEP BLUE S3022GFINISH: GLOSSDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: BREAKROOM BASE CABINETS AND MILLWORK AS NOTEDVENDOR CONTACT: DEBBIE COPOT, 630-470-2554, [email protected]

PL4

MANUFACTURER: FORMICACOLOR: GRENADINE 6902-58FINISH: MATTE FINISHDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: BREAKROOM FLOATING SHELVING, BASE CABINETS AT PRINT ROOMS ASNOTED ON ELEVATIONS

PL5

INTERIOR WOODWORKMANUFACTURER: NEVAMARCOLOR: DRY CREEK PLUM, WZ6001TFINISH: ARMORED PROTECTION, TEXTUREDDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: FOCUS ROOM COUNTERTOPSVENDOR CONTACT: DEBBIE COPOT, 630-470-2554, [email protected]

PL6

MANUFACTURER: ARMSTRONGSTYLE/SERIES: ULTIMACOLOR: WHITESIZE: 12"X72"EDGE CONDITION: TEGULARLOCATION: ACCENT CEILING TILE AS NOTED ON REFLECTED CEILING PLANGRID STYLE: SILHOUETTE 9/16" BOLT SLOT SYSTEMS

ACT3ACOUSTICAL PANEL CEILING

MANUFACTURER: USGSTYLE/SERIES: MILLENIA CLIMA PLUSCOLOR: WHITE MATTE WITH WHITE REVEAL SUSPENSION SYSTEMSIZE: 24"X24"EDGE CONDITION: TEGULARLOCATION: TYPICAL CEILING TILE UNLESS OTHERWISE NOTEDGRID STYLE: DONN FINELINE DXFF NARROW 9/16" FACE WITH 1/8" REVEAL

ACT1

GYPSUM BOARD CEILINGCOLOR: PT2FINISH: FLATDESCRIPTION: 5/8" SUSPENDED GYPSUM BOARD CEILINGGWB2

GYPSUM BOARD CEILINGCOLOR: PT8FINISH: FLATDESCRIPTION: 5/8" SUSPENDED GYPSUM BOARD CEILINGGWB3

MANUFACTURER: INTERFACESTYLE/SERIES: HARMONIZE 138720AK00COLOR: 104044 PEWTERSIZE: 25CM X 1MDESCRIPTION: PLANK CARPET, ASHLAR INSTALLATIONDESCRIPTION (CONT): GLASBAC RE BACKINGDIRECTION: REFER TO FINISH PLAN FOR DIRECTIONLOCATION: REFER TO FINISH PLANVENDOR CONTACT: JOE FOLEY, 312-961-7046, [email protected]

CPT2CARPET TILE

CARPET TILEMANUFACTURER: INTERFACESTYLE/SERIES: GROUND WAVES 138730AK00COLOR: 104053 ICEBERG/COLORSSIZE: 25CM X 1MDESCRIPTION: PLANK CARPET, HERRINGBONE INSTALLATIONDESCRIPTION (CONT): GLASBAC RE BACKINGDIRECTION: REFER TO FINISH PLAN FOR DIRECTIONLOCATION: ACCENT CARPET, REFER TO FINISH PLANVENDOR CONTACT: JOE FOLEY, 312-961-7046, [email protected]

CPT3

CARPET TILEMANUFACTURER: BENTLEYSTYLE/SERIES: TROUBADOUR 4TOT5COLOR: NOMAD 400341SIZE: 24"x24"DESCRIPTION: PLANK CARPET, MONOLITHIC INSTALLATIONDESCRIPTION (CONT): NEXSTEP CUSHION TILEDIRECTION: REFER TO FINISH PLAN FOR DIRECTIONLOCATION: MEETING ROOM CARPET AS NOTED ON FINISH PLANVENDOR CONTACT: PAULA HAGERTY, 312-802-6991,[email protected]

CPT4

CARPET TILEMANUFACTURER: BENTLEYSTYLE/SERIES: CIPHER 4CJ30COLOR: HIDDEN PASSAGE 400432SIZE: 12' WIDEDESCRIPTION: BROADLOOM CARPETDESCRIPTION (CONT): STANDARD HP HIGH PERFORMANCE BACKINGDIRECTION: REFER TO FINISH PLAN FOR DIRECTIONLOCATION: TRAINING BREAKOUT INSET AREA RUGVENDOR CONTACT: PAULA HAGERTY, 312-802-6991,[email protected]

CPT5

WALLCOVERINGMANUFACTURER: KOROSEAL WALLTALKERSSTYLE/SERIES: PROJECTABLE MAG-RITECOLOR: M2PRDESCRIPTION: PROJECTABLE WRITABLE MAGNETIC WALLCOVERINGDESCRIPTION (CONT): INSTALL ALUMINUM J-TRIM AT EXPOSED CORNERSWIDTH: 47/48", 24MILS THICKNESSLOCATION: ACCENT WALLS, REFER TO PLAN AND ELEVATIONSVENDOR CONTACT: CELINE EHLERS, 312-420-1242, [email protected]: REFER TO ELEVATIONS FOR SEAMING LOCATIONS

WC1

MANUFACTURER: SHAW CONTRACTCOLOR: BUFF 64140FINISH: 0502V GRAIN DIRECT GLUESIZE: 7"X48"DESCRIPTION: DIRECT GLUE LUXURY VINYL TILEDESCRIPTION (CONT): STAGGERED STRIP INSTALLATIONTHICKNESS: 20 MILLOCATION: REFER TO FINISH PLANS FOR DIRECTION AND LAYOUTVENDOR CONTACT: PAIGE SIVERTSEN, 312-391-0792,[email protected]

TL2

RESILIENT FLOORING

MANUFACTURER: MOHAWKSTYLE/SERIES: ANGLED PATHCOLOR: FACTOR 828SIZE: 24"X24"DESCRIPTION: DIRECT GLUE LUXURY VINYL TILEDIRECTION: REFER TO FINISH PLAN FOR LAYOUT, MONOLITHIC INSTALLATIONLOCATION: PRINT ROOMS, REFER TO FINISH PLANVENDOR CONTACT: KATIE CALLAHAN, 312-566-6451,[email protected]

TL4RESILIENT FLOORING

MANUFACTURER: NEVAMARCOLOR: NEUTRAL GRAY, S6012-TFINISH: ARMORED PROTECTION, TEXTUREDDESCRIPTION: PLASTIC LAMINATEDESCRIPTION (CONT): PHENOLIC BACKINGLOCATION: MILLWORK AS NOTED IN ELEVATIONSVENDOR CONTACT: DEBBIE COPOT, 630-470-2554, [email protected]

PL3INTERIOR WOODWORK

MANUFACTURER: DALTILECOLOR: TBDSIZE: 3.75" X 7.75" TILEDESCRIPTION: BULLNOSE TILE WITH CORRESPONDING CORNER PIECESGROUT: MAPEI UNSANDED GROUT. COLOR TBDLOCATION: GENDER NEUTRAL RESTROOM BASE, SEE FINISH PLAN AND ELEVATIONSVENDOR CONTACT: MELISSA MORAN, 224-306-7881, [email protected]

WT2MANUFACTURER: DALTILESTYLE/SERIES: TBDCOLOR: TBDSIZE: TBDDESCRIPTION: MOSAIC PORCELAIN TILE FLOORINGDESCRIPTION (CONT): INTEGRATE SCHLUTER DILEX-AHK COVE BASEDIRECTION: REFER TO FINISH PLAN FOR LAYOUT, MONOLITHIC INSTALLATIONLOCATION: GENDER NEUTRAL RESTROOM, SEE FINISH PLANVENDOR CONTACT: MELISSA MORAN, 224-306-7881, [email protected]

TL5PORCELAIN TILE FLOORING

WALL TILEMANUFACTURER: DALTILECOLOR: QH57 MIDNIGHT BLUESIZE: 2.75" X 5.75" X 8" EL HEXDESCRIPTION: HEXAGON TILESGROUT: MAPEI UNSANDED GROUT. COLOR TBDLOCATION: GENDER NEUTRAL RESTROOM, SEE FINISH PLAN AND ELEVATIONSVENDOR CONTACT: MELISSA MORAN, 224-306-7881, [email protected]

WT3

MANUFACTURER: DALTILECOLOR: QH68 STARLIGHTSIZE: 2.75" X 5.75" X 8" EL HEXDESCRIPTION: HEXAGON TILESGROUT: MAPEI UNSANDED GROUT. COLOR TBDLOCATION: GENDER NEUTRAL RESTROOM, SEE FINISH PLAN AND ELEVATIONSVENDOR CONTACT: MELISSA MORAN, 224-306-7881, [email protected]

WT4WALL TILE

MANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 20 CHARCOAL WGSIZE: 4" HIGH 1/8" THICKDESCRIPTION: ROLLED GOODSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: AT ALL PT2 LOCATIONS

RB2

BASE - RUBBER BASE

BASE - RUBBER BASE

BASE - RUBBER BASE

MANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 148 PAPRIKASIZE: 4" HIGH 1/8" THICKDESCRIPTION: 4' STRAIGHT LENGTHSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: AT ALL PT3 LOCATIONS

RB3

MANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 92 BLUE LAGOONSIZE: 4" HIGH 1/8" THICKDESCRIPTION: ROLLED GOODSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: AT ALL PT4 AND PT8 LOCATIONS

RB4

MANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 14 TROPICAL STORMSIZE: 4" HIGH 1/8" THICKDESCRIPTION: 4' STRAIGHT LENGTHSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: AT ALL PT5 LOCATIONS

RB5

MANUFACTURER: JOHNSONITESTYLE/SERIES: RUBBER; THERMOPLASTIC (TP)COLOR: 40 BLACK BSIZE: 4" HIGH 1/8" THICKDESCRIPTION: ROLLED GOODSDESCRIPTION (CONT): STRAIGHT AT CARPET, COVE AT RESILIENT FLOORINGLOCATION: AT ALL PT6 LOCATIONS

RB6

WALLCOVERINGMANUFACTURER: KOROSEAL WALLTALKERSSTYLE/SERIES: MAG-RITECOLOR: M248DESCRIPTION: WRITABLE MAGNETIC WALLCOVERINGDESCRIPTION (CONT): INSTALL ALUMINUM J-TRIM AT EXPOSED CORNERSWIDTH: 47/48", 24MILS THICKNESSLOCATION: ACCENT WALLS, REFER TO PLAN AND ELEVATIONSVENDOR CONTACT: CELINE EHLERS, 312-420-1242, [email protected]: REFER TO ELEVATIONS FOR SEAMING LOCATIONS

WC2

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

18 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

12" = 1'-0"

A1-403

FINISH SCHEDULE

SFC-00018A

ISSUE FOR PERMIT

11/09/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 24: WestEd Request for Proposal #4

UP

UP

1. FURNITURE SHOWN ON PLAN IS FOR REFERENCE ONLY.2. FURNITURE TO BE PROVIDED AND INSTALLED BY OTHERS.3. G.C. TO COORDINATE WITH ARCHITECT AND DEALER FOR LAYOUT OF

POWERED FURNITURE ON SITE PRIOR TO CORE DRILL AND STUB UPWIRING.

4. FURNITURE DEALER TO LAYOUT ALL WORKSTATION IN FEED LOCATIONSFOR APPROVAL ON SITE BY ARCHITECT AND G.C.

5. G.C. TO PROVIDE WALL BLOCKING FOR ALL OFFICES PER CONSTRUCTIONPLAN.

6. G.C. TO INSTALL TASK LIGHTS AS INDICATED ON POWER PLAN.

11.1

1.5

2

2.5

3

3.5

AA.1BCDEFGHIKM L

43.9

L.9

WS-01WS-01WS-01WS-01

WS-02WS-02

WS-02WS-02

WS-01WS-01WS-01WS-01

WS-02WS-02

WS-01WS-01WS-01WS-01

WS-02WS-02

PO-1 PO-1 PO-1 PO-1 PO-1 PO-1

PO-1PO-1PO-1PO-1PO-1PO-1

PO-1PO-1PO-1PO-1PO-1PO-1

PO-1 PO-1 PO-1

PO-1

PO-1

PO-1

PO-1 PO-1 PO-1 PO-1 PO-1 PO-1 PO-1

PO-1PO-1PO-1PO-1PO-1

PO-1

PO-1

PO-1

PO-1

PO-1

PO-1

PO-1PO-1

PO-1PO-1PO-1

PO-1

PO-1

OPEN TOBELOW

2062

PRIVATEOFFICE

2046

PRIVATEOFFICE

2036

PRIVATEOFFICE 2028

HOTEL

2026CONFERENCE

2074CONFERENCE

2102

PRIVATEOFFICE

2100

PRIVATEOFFICE

2002

PRIVATEOFFICE

2010

PRIVATEOFFICE

2087CLOSET

2088PANTRY

2022HOTEL

2024CONFERENCE

2066WORK ROOM

2065WORK ROOM

2093FOCUS

2094CLOSET

2095CLOSET

-ELEC.

-WOMENS RR

-MENS RR

2091PRINT ROOM

2071HOTEL

2068PRINT

2079LOBBY

2064HALLWAY

2089

FURNITURESTORAGE

2077CONFERENCE

2085GN RR

2086WELLNESS

2049CONFERENCE

2104

PRIVATEOFFICE

2105

PRIVATEOFFICE

2000CONFERENCE

2001

PRIVATEOFFICE

2004OPEN OFFICE

2007

PRIVATEOFFICE

2008CONFERENCE

2047OPEN OFFICE

2041CONFERENCE

2039

PRIVATEOFFICE

2040HOTEL

2037

PRIVATEOFFICE

2035

PRIVATEOFFICE

2033

PRIVATEOFFICE

2031

PRIVATEOFFICE

2030

PRIVATEOFFICE

2029

PRIVATEOFFICE

2027OPEN OFFICE

2025OPEN OFFICE

2023

PRIVATEOFFICE

2021

PRIVATEOFFICE

2019

PRIVATEOFFICE

2017

PRIVATEOFFICE

2015

PRIVATEOFFICE

2013

PRIVATEOFFICE

2011

PRIVATEOFFICE

2009HOTEL

2069FOCUS

2070SUPPLIES

2092FOCUS

2078MAIL ROOM

2060

PRIVATEOFFICE

2058

PRIVATEOFFICE

2054

PRIVATEOFFICE

2052

PRIVATEOFFICE

2048

PRIVATEOFFICE

2045

PRIVATEOFFICE

2044

PRIVATEOFFICE

2043

PRIVATEOFFICE

2072HALLWAY

2032HALLWAY

2056HALLWAY

2067HALLWAY

2097HALLWAY

2099HALLWAY

2020HALLWAY

2084HALLWAY

2038

PRIVATEOFFICE

2034

PRIVATEOFFICE

2075WORK ROOM

2042PRINT

2098PRINT

2096FOCUS

2003

PRIVATEOFFICE

2005

PRIVATEOFFICE

2006

PRIVATEOFFICE

2012

PRIVATEOFFICE

2014

PRIVATEOFFICE

2016

PRIVATEOFFICE

2018

PRIVATEOFFICE

PO-1

2081

TRAININGBREAKOUT

2090HALLWAY

2103

PRIVATEOFFICE

2101

PRIVATEOFFICE

2083TRAINING

2082TRAINING

2080BREAK ROOM

2063HOTEL

2061

PRIVATEOFFICE

2059

PRIVATEOFFICE

2057

PRIVATEOFFICE

2055

PRIVATEOFFICE

2053

PRIVATEOFFICE

2051

PRIVATEOFFICE

2050

PRIVATEOFFICE

PO-1

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

40 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A1-501

FURNITURE &EQUIPMENT PLAN -

LEVEL 02

SFC-00018A

ISSUE FOR PERMIT

10/24/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerCP

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

FURNITURE & EQUIPMENT NOTES

NO. NOTES

KEY NOTES

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

SCALE: 1/8" = 1'-0"FURNITURE & EQUIPMENT PLAN - LEVEL 02 1

Page 25: WestEd Request for Proposal #4

ALIG

N

ALIG

NALIGN

A4-100

3

2

A4-1004

A4-100

6

5

2080BREAK ROOM

2078MAIL ROOM

A320

C310

C310

A4-102

5A4-102 7 A4-1026

2 EQ PANELSEQ EQ EQ

2 EQ PANELSEQ

13' - 5"

2' - 4

"2'

- 0"

2' - 1

0"

1' - 3

1/2"

3"2 EQ PANELS

2' - 10" 2' - 10" 1' - 6" 1' - 6"2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0" 3"

TRASH/REC.

TRASH/REC.

2A5-200

Sim4A5-200

Sim

11A5-200

Sim11

A5-200

Sim

PL4 BASECABINETS

ST1COUNTERTOP

PL2 OPENSHELVING ANDUPPER CABINETS

WT1 BACKSPLASH

2' - 2

"1'

- 6"

MANU

FACT

URER

'S SP

ECIF

ICAT

IONS

6' - 0

" COO

RDIN

ATE

W/

2' - 4

"

2 EQ PANELS3' - 5"

2 EQ PANELS3' - 5"

2 EQ PANELS3' - 0"

2 EQ PANELS3' - 0"

2 EQ PANELS3' - 0"

5' - 7"

FILLER PANEL ABOVE

2A5-200

Sim

11A5-200

Sim

12A5-200

Sim

3A5-200

Sim

PL4 BASE CABINETS

ST1

PL5 FLOATING SHELVESWT1 BACKSPLASH

EXISTING BOOKCASESPAINTED PT1

REMOVE EXISTING BOOKCASES IN CONFLICT WITHNEW PARTITIONS PER PARTITION PLAN. FASTENREMAINING BOOKCASES TO NEW PARTITION.

PL3 COUNTERTOPAND BASE CABINETS

6A5-200

Sim

8 EQ PANELS12' - 0"

PL3 MAILSLOTS

PL3

PL3 BASE,SHELVES ANDCABINET SHELL

PL5 BACK PANELONLY, TYP.

2' - 1

0"2'

- 0"

4 EQ.

UNI

TS2'

- 4"

6" T

YP

1' - 1 1/2" TYP

6A5-200

Sim

4 EQ UNITS12' - 0"

10 EQ 8" DEEP UNITS12' - 0"

2088PANTRY

A4-100 89

C320

2' - 1"2' - 1"

3' - 9

"1 1

/2"

SEE DOOR SCHED 2' - 3"

9' - 3"

12' -

0"

3' - 3

"

2A5-200

Sim

2' - 1

0"

3' - 0" 3' - 0" 3' - 0" 3' - 0"

ST1 COUNTERTOPWITH 2.5"BACKSPLASH

PL1

11A5-200

Sim

MANUFACTURER'S SPECIFICATIONS3' - 9" COORDINATE W/

FILLER PANELABOVE

2' - 4

"SP

ECIF

ICAT

IONS

6' - 0

" COO

RDIN

ATE

W/M

ANUF

ACTU

RER'

S

2' - 1

0"

ST1 COUNTERTOPWITH 2.5" BACKSPLASH

PL1

TRASH/REC

3' - 0" 3' - 0" 1' - 6"

C200

C200

C200

C200

C200

10' - 1"

ø 5' - 0" CLEAR

1' - 6

"1'

- 4 1/

2"

30 X

48CL

EAR

4' - 6"

5' - 1

"

2085

A

2085B

2085C

2085D

2085

E

1' - 2"

2085

E20

85A

B320

B320

B320

2086

C310

A4-10020

A4-10015

12

13

14

A4-10016

A4-10019

17

18

6' - 0

"

9' - 7 1/2"

21

2' - 2

"

10 1/2"

C310

C310

5' - 5"

PT7

PT7 WT3 WT4

PT7 WT3 WT4

PT7 WT3 WT4

PT7 WT3 WT4

PT1WT2

WT1

RE: SHEET G0-200 FOR ALLTYPICAL (N) RESTROOM

EQUIPMENT & DIMENSIONS PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT4

4' - 4

"

4' - 4

"

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT4

4' - 4

"

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT4

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT4

2' - 1

0"

7"

WT2

ST2

4' - 0

"

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT4

4' - 4

"

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3WT4

4' - 4

"

PT7

SCHLUTER SCHIENETRANSITION STRIPALONG TOP

WT3

WT44' - 4

"

5A5-200

Sim

3' - 0"MIN.1' - 6"

TRASH/REC

ST1 COUNTERTOPAND 2.5"

BACKSPLASH

PL4

PT7

ST1 COUNTERTOPAND 2.5"

BACKSPLASH

PL4 BASE ANDFILLER PANELS

PT7

BASE AS SCHEDULED

PT1

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

52 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A4-100

ENLARGED PLANS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

1/4" = 1'-0"1 ENLARGED PLAN - BREAK ROOM AND MAIL ROOM 3/8" = 1'-0"2 BREAKROOM 2080 - EAST ELEVATION

3/8" = 1'-0"3 BREAKROOM 2080 - SOUTH ELEVATION

3/8" = 1'-0"4 BREAKROOM 2080 - WEST ELEVATION 3/8" = 1'-0"5 MAILROOM 2078 - NORTH ELEVATION

3/8" = 1'-0"6 MAILROOM 2078 - SOUTH ELEVATION

1/4" = 1'-0"7 ENLARGED PLAN - CATERING 3/8" = 1'-0"8 CATERING 2088 - EAST ELEVATION

3/8" = 1'-0"9 CATERING 2088 - WEST ELEVATION

3/8" = 1'-0"10 ENLARGED PLAN - GENDER NEUTRAL RR 3/8" = 1'-0"11 WALL FINISH PLAN - ENLARGED PLAN - GENDER NEUTRAL RR

3/8" = 1'-0"12 ADA WATER CLOSET - NORTH ELEVATION 3/8" = 1'-0"13 ADA WATER CLOSET - EAST ELEVATION

3/8" = 1'-0"14 ADA WATER CLOSET - SOUTH ELEVATION 3/8" = 1'-0"15 ADA WATER CLOSET - WEST ELEVATION

3/8" = 1'-0"16 RESTROOM VANITY - WEST ELEVATION

3/8" = 1'-0"17 TYPICAL RR STALL - NORTH ELEVATION 3/8" = 1'-0"18 TYPICAL RR STALL - SOUTH ELEVATION

3/8" = 1'-0"19 TYPICAL RR STALL - WEST ELEVATION 3/8" = 1'-0"20 MOTHER'S ROOM - WEST ELEVATION

3/8" = 1'-0"21 MOTHER'S ROOM - NORTH ELEVATION

Page 26: WestEd Request for Proposal #4

ALIGN ALIGN

ALIGNALIGN ALIGN ALIGN

ALIGN

A4-101

A4-101

A4-101

7

9

A4-101 6

4

A4-101

5

A4-101

8

2081

TRAININGBREAKOUT

2083TRAINING

2082TRAINING

3' - 0

"4'

- 5"

14' - 0" EQ.EQ.

7' - 4

"2'

- 3"

B320

2082

A

2082

B

C310 4'

- 6 1/

2"

C3104'

- 2"

COORDINATE W/FURNITURE VENDOR

2' - 4

1/2" 4'-

5" M

IN. 20

83B

2083

A

B320

B320

C310

C310

A4-102

4A4-1026

L12

L6A L6AL6A L6A

L12

L12L12

L12

76"AFF80"AFF

84"AFF 80"AFF78"AFF

5' - 6

"8 1

/2"

5' - 6

"

6' - 0

"6 1

/2"

1' - 10" 1' - 9 1/2" 4' - 2"1' - 10" 1' - 6"

2' - 6

"

WD1WD2

FWP1

DOTTED LINE INDICATES EXTENT OFWOOD VENEER PANELING. SEE

ELEVATIONS FOR MORE INFORMATIONGL2

PT8 PT8

PT2RB2

2' - 1

0"

3" 3"

6' - 8

"

6' - 6

"

7' - 0

"

6' - 8

"

6' - 4

"

ST1 COUNTERTOP AND WATERFALLEDGES, MITER CORNERS, TYP.

PL1 SEAM IN PLASTIC LAMINATE

2' - 1

0"

3"3"

1' - 6"2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0"

6' - 4

"

6' - 8

"

7' - 0

"

6' - 6

"

6' - 8

"

ST1 COUNTERTOP AND WATERFALLEDGES, MITER CORNERS, TYP.

OFDRAWER

OFDRAWER

OFDRAWER

OFDRAWER

TRASH/REC.

PL1

2' - 1

0"

4 EQUAL PANELS

8' - 4

" TYP

.

WD2

WD1

FWP1

EQ.2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0"2 EQ PANELS

3' - 0" 1' - 6" 1' - 6" EQ.

2' - 1

0" TRASH/REC.

TRASH/REC.

EQ.2 EQ. PANELS

3' - 0"2 EQ. PANELS

3' - 0"2 EQ. PANELS

3' - 0"1' - 6"1' - 6"EQ.

2' - 1

0"

8' - 4

" TYP

.

ST1

PL1

ST1

PL1

OPEN TOBEYOND

GL2 WD2

BASE AS SCHEDULED

WD1

EQ EQ

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:26:

58 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A4-101

ENLARGED PLANS

SFC-00018A

ISSUE FOR PERMIT

11/09/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

1/4" = 1'-0"1 ENLARGED PLAN - TRAINING BREAKOUT 1/4" = 1'-0"2 REFLECTED CEILING PLAN - ENLARGED PLAN - TRAINING BREAKOUT

1/4" = 1'-0"3 WALL FINISH PLAN - ENLARGED PLAN - TRAINING BREAKOUT

3/8" = 1'-0"4 ELEVATION - TRAINING ROOM SERVERY NORTH 3/8" = 1'-0"5 ELEVATION - TRAINING SERVERY SOUTH

3/8" = 1'-0"6 ELEVATION - TRAINING ROOM SERV. EAST 3/8" = 1'-0"7 TRAINING BREAKOUT 2081 - NORTH ELEVATION

3/8" = 1'-0"8 ELEVATION - TRAINING ROOM CREDENZA 3/8" = 1'-0"9 HALLWAY 2097 - WEST ELEVATION

Page 27: WestEd Request for Proposal #4

A4-102

4

A4-102

5

A4-102 7A4-1026

10' - 6"

6' - 2"4"

6' - 8"

10"

2' - 1

0"

2' - 1

0"

3' - 1

0"

4"

6' - 8"

1' - 4

"

PL2

RP1

WHITE PLASTIC LAMINATEPL2

RP1

WHITE PLASTIC LAMINATE

2' - 6

"

2' - 1

0"

2' - 1

0"

4"

3' - 5

"

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

01 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

3/4" = 1'-0"

A4-102

ENLARGED PLANSAND DETAILS

SFC-00018A

ISSUE FOR PERMIT

11/10/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

3/4" = 1'-0"1 RECEPTION DESK - PLAN VIEW2 RECEPTION DESK FRONT

PL2

PL3 WORKSURFACE

GL1 WITH DUSTED CRYSTALFILM

RP1 LIGHTBOX WITH INTEGRALLED STRIPLIGHT

WHITE PLAM BASE

3/4" = 1'-0"4 RECEPTION DESK FRONT

3 RECEPTION DESK BACK

PL2

PL2

WHITE PLAM BASE

RP1 LIGHTBOX WITH INTEGRALLED STRIPLIGHT

GL1 WITH DUSTED CRYSTALFILM

PL3 WORKSURFACE

3/4" = 1'-0"5 RECEPTION DESK BACK 3/4" = 1'-0"6 RECEPTION DESK SIDE

3/4" = 1'-0"7 RECEPTION DESK - SIDE

Page 28: WestEd Request for Proposal #4

4' - 4

"

2' - 1

0"

6 EQUAL PANELS9' - 1 1/2" VERIFY IN FIELD BETWEEN EXISTING SHAFT WALLS

PT4PT4 PAINTED MDF PANELSON TOUCH-LATCH

RB4

PT1CONCEALED LED COVE FIXTURE

6A5-200

Sim

WD2

WD1

RB1

PT1

WD1 FLOATING CREDENZA

OF MILLWORKEQ. EQ.

8' - 0"

11' - 6"

1' - 6

"

2' - 1

0"1'

- 5 1/

2"1'

- 5 1/

2"

1 1/2"

1 1/2"

PL3 SHELVES

EQ.

EQ.

EQ.

12A5-200

Sim

7A5-200

WC1

BASE AS SCHEDULED

WALLCOVERING SEAMS

4' - 0

"3'

- 0"

PL6

1 1/2"

RAKKS CONCEALEDCOUNTER SUPPORTEH-1818

4' - 0" O.C. MAX2' - 1

0"

RB5

PT5

5A5-200

Sim

PT4

PT1

RB4RB1

CONCEALED LEDCOVE FIXTURE

7' - 4

"

8' - 4

"

2' - 1

0"TRASH/REC.

PL1

PL14A5-200

Sim6

A5-200

Sim

3' - 0"1' - 6"PL5 BASE CABINETS

PL3 COUNTERTOP

TRASH/REC.

3' - 0" 3' - 0" 3' - 0" 1' - 6"1' - 6"

2' - 1

0"

COOR

DINA

TE W

/AV

DRAW

INGS

5' - 7

"

OF TVS

OF TVS OF TVS

EQ.7' - 6"EQ.

WC2 4' - 0

"3'

- 0"

BASE AS SCHEDULED

WALLCOVERING SEAMS

TRASH/REC.

PL5 BASE CABINETS

PL3COUNTERTOP

1' - 6" 1' - 6" 3' - 0" 3' - 0" 3' - 0" 3' - 0" 3' - 0"

2' - 1

0"

TRASH/REC.

PL1

PL1

1' - 6" 1' - 6" 3' - 6" 3' - 6"

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

14 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

3/8" = 1'-0"

A4-200

INTERIOR ELEVATIONS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

3/8" = 1'-0"1 LOBBY 2079 - NORTH ELEVATION 3/8" = 1'-0"3 LOBBY 2079 - EAST ELEVATION

3/8" = 1'-0"4 LOBBY 2079 - WEST ELEVATION

3/8" = 1'-0"5 TRAINING ROOM - TYPICAL ELEVATION 3/8" = 1'-0"6 FOCUS ROOM - TYPICAL ELEVATION

3/8" = 1'-0"2 LOBBY 2079 - EAST ACCENT WALL ELEVATION

3/8" = 1'-0"7 PRINT 2098 - SOUTH ELEVATION 3/8" = 1'-0"8 PRINT ROOM 2091 - EAST ELEVATION

3/8" = 1'-0"9 CONFERENCE ROOM TYPICAL 3/8" = 1'-0"10 CONFERENCE 2077 - NORTH ELEVATION

3/8" = 1'-0"11 CONFERENCE 2077 - SOUTH ELEVATION 3/8" = 1'-0"12 CONFERENCE 2074 - NORTH ELEVATION

3/8" = 1'-0"13 CONFERENCE 2074 - SOUTH ELEVATION 3/8" = 1'-0"14 CONFERENCE 2074 - WEST ELEVATION

3/8" = 1'-0"15 PRINT 2068 - NORTH ELEVATION 3/8" = 1'-0"16 TYPICAL CONFERENCE FRONT

3/8" = 1'-0"17 PRINT 2042 - EAST ELEVATION 3/8" = 1'-0"18 TYPICAL OFFICE FRONT ELEVATION

3/8" = 1'-0"19 CONFERENCE ROOM 2026 - OFFICE FRONT 3/8" = 1'-0"20 OPEN OFFICE 2025 - NORTH ELEVATION

Page 29: WestEd Request for Proposal #4

3/4" x 4" STRETCHER W/FINISH ON FRONT EDGE TOMATCH EXTERIOR

DOOR FINISH ASSCHEDULED.

COUNTERTOP ASSCHEDULED WITH 1/8"EASED EDGES. SCRIBECOUNTERTOP TO WALL

TAB PULL; DOUG MOCKETT,DP3 SERIESSIZE: DP3AFINISH: SATIN CHROME

PLAM BASE ASSCHEDULED

WHITE MELAMINE ON 1/2"SUBSTRATE. PANELFASTENED TO 1/2" WOODSPACER

4"

3/4" DUST PANEL W/ FINISHON FRONT EDGE TO MATCHEXTERIOR

REFER TO PLAN

DRAWERS WITH WHITEMELAMINE INTERIOR. GLIDESTO BE ACCURIDE FULLEXTENSION.

EQ.

EQ.

EQ.

EQ.

2' ‐ 10

"

1 1/2"

3"

FASTEN CABINET BACKPANEL TO CONTINUOUSSTEEL PLATE AT WINDOWLOCATION ONLY

WHITE MELAMINEINTERIOR

ADJ. SHELF: SCHEDULEDFINISH ON 3/4" SUBSTRATE.(1) SHELF PER CABINET,U.O.N.

3/4" x 4" STRETCHER W/FINISH ON FRONT EDGE TOMATCH EXTERIOR

DOOR FINISH ASSCHEDULED.

COUNTERTOP ASSCHEDULED WITH 1/8"EASED EDGES. SCRIBECOUNTERTOP TO WALL

TAB PULL; DOUG MOCKETT,DP3 SERIESSIZE: DP3AFINISH: SATIN CHROME

PLAM BASE ASSCHEDULED

REFER TO PLAN

2' ‐ 10

"

3"

4"1/2"

1 1/2" 1 1/2"

WHITE MELAMINE ON 1/2"SUBSTRATE. PANELFASTENED TO 1/2" WOODSPACER

1 1/2"

SCHEDULED FINISH ONALL INTERIOR

SURFACES

1/2" WD SPACER

COUNTERTOP ASSCHEDULEDWTIH 1/8"

EASED EDGES

WALL AS SCHEDULED

3"

SEE PLAN

PROVIDE WOODSTRUCTURE AS

NEEDED

SCHEDULED CEILING

SCHEDULED HARDWARE

3/4" ADJUSTABLE SHELF ONSHELF CLIPS

CLEAR SILENCER, TYP.

FRENCH CLEATS

SEE ELEVATION

LINE OF SCHEDULED PARTITION

ROUTED FINGER PULL

3/4"

2"

2" OPENING FOR VENTILATION(TYP.)

VENTILATION SLOT TOPLENUM

LINE OF BULKHEAD WHEREOCCURS

LINE OF END PARTITION BEYOND

INTERMEDIATE BLOCKING ASNEEDED.

SEE PLAN

SCHEDULED EQUIPMENT

PANEL & HARDWARE WHERESCHEDULED SEE ELEVATION

FLOATING SHELVES, 3/4"SUBSTRATE FULLY CLAD INFINISH AS SCHEDULED, SEEELEVATION.

BLOCKING IN WALL

WALL FINISH AS SCHEDULED

7/8" DIAMETER STEEL TUBEWELDED TO CONCEALED STEELPLATE

1' ‐ 0"

1' ‐ 6"

STEEL PLATE FASTENED TOWOOD BLOCKING IN WALL

FLATHEAD SCREW FASTENED TOSTEEL TUBE. SCREW TO MATCHSTAINLESS STEEL FINISH COLOR.

2 1/2"

SEEELEVATIONS

SEEELEVATIONS

DOORS: 3/4" MEDDENSITY PB

BACK PANEL: 1/2" MEDDENSITY PB

COUNTERTOP: 3/4" MEDDENSITY MOISTURERESISTANT PB. SEE

ELEVATION FOR CONDITIONAT WALL

PL1

2' -

10"

4"

1/2"

2' - 1"

3"

1/2" WD SPACER

DOOR PULL AS SCHEDULED

PL1

1 1/

2"

3/4" FASCIA W/ PLAMFINISH ON FACES & EDGES

TO MATCH EXTERIOR

EQ EQ

SCHEDULED SINK ANDFAUCET

TOE KICK TO MATCHFINISH FACE

ALL DRAWERSURFACES AND

EDGES

PL1

PL1

SEE ELEV

ATION

4"

SCHEDULEDHARDWARE

TOE KICK TO MATCH FINISHFACE

1/4"

, TYP

.

3/4" MED DENSITY PB WITHFINISHED FRONT FACE, FACEFRAME EDGES AND EXPOSED

SIDES1/4" MELAMINE PANELS ON

CABINET INTERIOR &DRAWER

DOOR PULL AS SCHEDULED

3/4" PLASTIC LAMINATE SLIDEOUT TRASH CONTAINER SHELFW/ ANGLED SLIDES ATTACHEDTO FRONT W/ 24" DEEP FULLEXTENSION ACCURIDE GLIDES

BLOCKING

ALL INTERIORSURFACES TO BEWHITE MELAMINE

2' -

10"

4"

1/2"

3"

1/4"

1 1/

2"

TOE KICK TO MATCHFINISH FACE

IN WALL BLOCKING TOSECURE CABINET

DOORS: 3/4" MED DENSITYPB

BACK PANEL: 1/2" MEDDENSITY PB

ADJ. SHELF: 3/4" MEDDENSITY PB. (1) SHELF PER

CABINET, UNO

3/4" x 4" STRETCHER W/FINISH ON FRONT EDGE TO

MATCH EXTERIOR

COUNTERTOP: 3/4" MEDDENSITY PB. SEE ELEVATIONFOR CONDITION AT WALL

BASE: 3/4" MED DENSITY PB

1/2" WD SPACER

1/2" WD SPACERDOOR PULL AS SPECIFIED

SCHEDULED PARTITION

3/4" PLYWOOD

WOOD FRAMINGPROVIDED AS

NEEDED

BOOK DISPLAY

1/2" FRENCH CLEAT

SCHEDULED WALL

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

18 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

1 1/2" = 1'-0"

A5-200

MILLWORK DETAILS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHK

1 1/2" = 1'-0"1 MILLWORK DETAIL - BASE CABINET WITH (4) DRAWERS 1 1/2" = 1'-0"2 MILLWORK DETAIL - BASE CABINET WITH (1) DOOR

1 1/2" = 1'-0"5 MILLWORK DETAIL - BASE CABINET WITH APPLIANCE

1 1/2" = 1'-0"11 DETAIL SECTION - UPPER CABINET 1 1/2" = 1'-0"12 MILLWORK DETAIL - FLOATING SHELVES

1 1/2" = 1'-0"3 MILLWORK DTL AT BASE CABINET W/ SINK 1 1/2" = 1'-0"4 MILLWORK DTL AT PULL-OUT TRASH CABINET AT KITCHEN ISLAND

1 1/2" = 1'-0"6 MILLWORK DTL AT BASE CABINET W/ DOOR 1 1/2" = 1'-0"7 LOBBY BOOK DISPLAY

Page 30: WestEd Request for Proposal #4

6"

LINE OF STRUCTURAL CONCRETEFLOOR SLAB

FINISHED FLOORSCHEDULED BASE

BOTTOM RUNNER SECURED TOFLOOR

(1) LAYER 5/8" GYP. BD. BOTHSIDES TYP (OR PER CONDITION)

SCHEDULED RECESSED FIREEXTINGUISHER CABINET.

FIRE EXTINGUISHER

54" TO TOP OF CABINET (VERIFY WITHLOCAL CODE REQUIREMENTS)

UNDERSIDE OF STRUCTURALSLAB ABOVE

LINE OF FINISHED CEILING

PROVIDE CONTINUOUS ACOUSTICALSEALANT AT TOP AND BOTTOM

FIRE RATING(BLANK = NON-RATED)

STUD/CMU SIZECOMMENT

WALL TYPE

0 — 7/8"1 — 1 5/8"2 — 2 1/2"3 — 3 5/8"4 — 4" 6 — 6"8 — 8"

A322X

4 — 3 5/8" 6 — 5 5/8" 8 — 7 5/8"10 — 9 5/8"12 — 11 5/8"

A STUDS: EXTEND FULL HEIGHT TO DECKGWB: EXTEND FULL HEIGHT TO DECK

B STUDS: EXTEND FULL HEIGHT TO DECKGWB: EXTEND 6" ABOVE CEILING

C STUDS: EXTEND 6" ABOVE CEILING - TIEDBACK TO STRUCTUREGWB: EXTEND TO UNDERSIDE OF CEILING

E STUDS: EXTEND FULL HEIGHT TO DECKGWB: SIDE 1 EXTEND 6" ABOVE CEILING,

SIDE 2 EXTEND TO DECKF FURRING

GWB: EXTEND FULL HEIGHT TO DECKG GLASS SIDELITEH PARTIAL HEIGHT, SEE ELEVATIONS

NUMBER OF BOARDS(BLANK=NO BOARD)

X SOUND ATTENUATION BATTS, AS SCHEDULEDQ SOUNDPROOF BOARD, AS SCHEDULED

STUD SIZE CMU SIZEWALL TAG LEGEND

WALL TYPES

1. ALL WALLS ARE TO BE TYPE "A" U.O.N.2. ALL "A" TYPE WALLS ARE TO BE BRACED TO THE CLOSEST FULL HEIGHT

PARTITION. SEE WALL DETAILS FOR MORE INFORMATION.3. ALL GYPSUM BOARD IS 5/8" TYPE C THICK U.O.N.4. ALL METAL STUDS ARE 16" O.C. U.ON.5. ALL METAL STUDS ARE 20 GA U.O.N.6. ALL FIRE RATED PARTITIONS MUST CONFORM TO MINIMUM REQUIREMENTS

OF THE LISTED TESTED ASSEMBLY UNLESS MORE STRINGENTREQUIREMENTS ARE DESIGNATED BY DETAIL.

7. ALL ACOUSTICAL STC RATED PARTITION CONSTRUCTION EXTENDING TOTHE BOTTOM OF STRUCTURE SHALL HAVE ALL PENETRATIONS ANDINTERSECTIONS SEALED AIR TIGHT WITH ACOUSTICAL SEALANT.

8. FIRE RATED SEALANT SHALL BE USED AT FIRE RATED PARTITIONS. ALLRECESSED BOXES SHALL BE SEALED AND RUNNERS SHALL BE SET IN 2BEADS OF SEALANT.

9. ALL ROOMS WITH PLUMBING FIXTURES SHALL BE CONSTRUCTED WITHWATER RESISTANT GYPSUM BOARD U.O.N.

10. COORDINATE PARTITION CONSTRUCTION WITH FINISH PLANS.11. PROVIDE 18 GA. METAL REINFORCING PLATES FOR ALL WALL MOUNTED

CONSTRUCTION.12. PROVIDE 1/2" CEMENT BOARD AT ALL LOCATIONS TO RECEIVE TILE FINISH.13. EXTEND GYPSUM BOARD CONSTRUCTION TO BOTTOM OF STRUCTURE IN

ALL ROOM WITHOUT FINISH SUSPENDED CEILING. FINISH GYP. BD. EDGEWITH J BEAD AND SEALANT.

14. ALL GYPSUM BOARD PARTITIONS SUPPORTING WALL HUNG CABINETS,SHELVING, OVERHEAD BINS AND FURNITURE SHALL HAVE 20 GAUGE STUDSSPACED AT 16" O.C. WITH FLAT GAUGE BLOCKING.

15. BRACE ALL METAL STUD PARTITIONS AT ALL LOCK SIDES OF DOORS, WHEREDUCTS INTERFERE WITH METAL STUDS GOING TO UNDERSIDE OF SLABABOVE AND WHERE CALLED FOR ON DRAWINGS.

16. PROVIDE CONTROL JOINTS IN GYPSUM BOARD PARTITION RUNS EXCEEDING30' OR MORE AND AT ALL INTERSECTIONS WITH BUILDING CORE, EXTERIORWALLS, COLUMNS AND WHERE RECOMMENDED BY MANUFACTURERS'WRITTEN INSTRUCTIONS.

17. TAPE AND SPACKLE ALL JOINTS IN DRYWALL, INCLUDING JOINTS ABOVE THECEILING.

18. PROVIDE WOOD BLOCKING OR STEEL STRAPPING AT ALL PARTITIONSSUPPORTING WALL HUNG CABINETS, SHELVING, OVERHEAD BINS ANDFURNITURE AS PER THE ARCHITECTURAL WOODWORK INSTITUTEINSTALLATION STANDARDS SECTION 1700. REFER TO CONSTRUCTIONPLANS.

19. PROVIDE DOUBLE STUDS AT BOTH JAMBS AND HEADER OF ALL DOORFRAMES.

20. ALL (N) WALLS TYPE A30 U.O.N.21. ALL (N) RESTROOM EQUIPMENT, GRAB BARS & TOILET TO COMPLY WITH

DIAGRAMS ON SHEET G0-201

FLOOR

CEILING

STRUC.

A

PARTITION TYPES

B C G F

STEEL STUD RUNNER TO MATCHGAUGE OF STUD,SECURED TO SLAB

TOP OF SLAB

HEAD

BASE

FINISHED CEILING LEVEL,SEE RCP FOR CEILING TYPE & HEIGHT

TOP OF SLAB

HEAD

BASE

5/8" GYPSUM WALL BOARD

UNDERSIDE OF FLOOR SLAB ABOVE

FINISHED CEILING LEVEL,SEE RCP FOR CEILING TYPE & HEIGHT

Metal Stud Furring (see plan), 5/8" Gypsum Wall Board One Side

STEEL STUD RUNNER TO MATCHGAUGE OF STUD,SECURED TO SLAB

CONT. 14 GA. METAL PLATE ASREQUIRED TO SPAN DECKING FLUTESCONT. COMPRESSIVE FILLER/ CONT.FIRESTOPPING W/FIRESTOP SEALANTAT RATED PARTITION

BASE, SEE FINISH SCHEDULE

BASE, SEE FINISH SCHEDULE

F For Non-Rated

METAL STUD INTERIOR FURRING

B For Non-Rated

5/8" Gypsum Wall Board Both Sides

METAL STUD INTERIOR PARTITION

For 1 Hour-Rated | UL - 425

5/8" Type X Gypsum Wall Board Both Sides

For 3 Hour-Rated | UL - 425

3 Layers 5/8" Type X Gypsum Wall Board Both Sides

For 2 Hour-Rated | UL - 474

2 Layers 5/8" Type X Gypsum Wall Board Both Sides

STC 60

20 GAUGE STEEL STUDS@ 16" O.C

5/8" TYPE X GYPSUM WALLBOARD PER WALL TYPEBELOW

PLAN

PLAN20 GAUGE STUDCHANNELS 16" O.C.. SEEPLAN FOR STUD SIZING.

EXISTINGCONSTRUCTION

TOP OF SLAB

HEAD

BASE

UNDERSIDE OF FLOOR SLAB ABOVE

FINISHED CEILING LEVEL,SEE RCP FOR CEILING TYPE & HEIGHT

CONT. 14 GA. METAL PLATE ASREQUIRED TO SPAN DECKING FLUTESCONT. COMPRESSIVE FILLER/ CONT.FIRESTOPPING W/FIRESTOP SEALANTAT RATED PARTITION

GLAZING SHOE,SEE DETAILS

G Non-Rated

5/8" Gypsum Wall Board Both Sides at Header

GLASS INTERIOR PARTITION

20 GAUGE STEEL STUDS@ 16" O.C

GLAZING, SEE SCHEDULEAND DETAILS

PLAN

GLAZING HEADER, MOUNTEDTO CONTINUOUS BLOCKING

NOTE: SEE GLAZINGDETAILS FOR THISPARTITION TYPE

STC 60

6"

6"

6"

STEEL STUD RUNNER TO MATCHGAUGE OF STUD,SECURED TO SLAB

TOP OF SLAB

HEAD

BASE

UNDERSIDE OF FLOOR SLAB ABOVE

FINISHED CEILING LEVEL,SEE RCP FOR CEILING TYPE & HEIGHT

CONT. 14 GA. METAL PLATE ASREQUIRED TO SPAN DECKINGFLUTES

BASE, SEE FINISH SCHEDULE

A For Non-Rated

5/8" Gypsum Wall Board Both Sides

METAL STUD INTERIOR PARTITIONSTC 60

20 GAUGE STEEL STUDS@ 16" O.C

5/8" TYPE X GYPSUM WALLBOARD PER WALL TYPEBELOW

PLAN

ACOUSTIC SEALANT AS REQUIRED

20 GA. METAL BRACING STUD TONEAREST FULL HT. CORE WALL ORTYPE B WALL. SEE DETAILS FORMORE INFORMATION.

C For Non-Rated

5/8" Gypsum Wall Board One Side

METAL STUD FURRING PARTITION

STEEL STUD RUNNER TO MATCHGAUGE OF STUD,SECURED TO SLAB

TOP OF SLAB

HEAD

BASE

UNDERSIDE OF FLOOR SLAB ABOVE

FINISHED CEILING LEVEL,SEE RCP FOR CEILING TYPE & HEIGHT

CONT. 14 GA. METAL PLATE ASREQUIRED TO SPAN DECKINGFLUTES

BASE, SEE FINISH SCHEDULE

20 GAUGE STEEL STUDS@ 16" O.C.

5/8" TYPE X GYPSUM WALLBOARD

PLAN

ACOUSTIC SEALANT AS REQUIRED

SCALE: 1 1/2" = 1'-0"RECESSED FIRE EXTINGUISHER 2

PARTITION LEGEND

PARTITION NOTES

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

19 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A6-001

PARTITION TYPES ANDTYPICAL WALL

DETAILS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

PARTITION TYPES

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 31: WestEd Request for Proposal #4

1. GENERAL CONTRACTOR AND MILLWORK CONTRACTOR ARE TO VERIFYDOOR SWINGS AND CEILING HT. PRIOR TO PLACEMENT OF ORDER.

2. GENERAL CONTRACTOR TO SUPPLY A COMPLETE DOOR SCHEDULE,HARDWARE SCHEDULE & HARDWARE CUTS FOR APPROVAL PRIOR TOORDERING.

3. GENERAL CONTRACTOR TO COORDINATE DOORS, FRAMES AND HARDWAREWITH REQUIREMENTS FOR CARD ACCESS WHERE NOTED.

4. WHERE DOOR AND/ OR DOOR FRAME IS INDICATED AS PAINT, PAINT TO BESEMI-GLOSS FINISH COLOR TO MATCH ADJACENT WALL.

5. G.C. TO COORDINATE ALL MILLWORK & HARDWARE WITH MILLWORK SHOPDRAWINGS APPROVED BY ARCHITECT.

6. FRAMES TO BE EXTRUDED ALUMINUM, MATCHING EXISTING.7. DOORS TO BE PRIMED AND READY FOR FIELD FINISH PAINT APPLICATION.

FINISH PAINT TO BE APPLIED IN TWO COATS. PAINT TO BE SEMI-GLOSSFINISH.

8. FIRE RATED DOORS AND FRAMES SHALL COMPLY WITH THE REQUIREMENTSOF NFPA 80.

9. HARDWARE FINISH SHALL BE 630 U.O.N..10. FRAMES SHALL BE THE WELDED TYPE AND GROUND SMOOTH.11. DO NOT PAINT WOOL DOOR SILENCERS.12. DO NOT PAINT FIRE RATING UL TEST LABELS.13. ALL CYLINDERS SHALL BE TO MATCH BUILDING STANDARD.14. ALL HARDWARE TO MATCH BUILDING STANDARD HARDWARE.15. ALL KEYING TO BE DONE BY BUILDING APPROVED LOCKSMITH. GC TO

COORDINATE MASTER-KEYING PROCEDURE WITH CLIENT AND BUILDINGMANAGEMENT OFFICE.

D1 D3 D4D2 D5

SEE

SCHE

DULE

SEE

SCHE

DULE

SEE SCHEDULE

SINGLE - SOLID CORETYPICAL OFFICE DOOR

SEE

SCHE

DULE

SEE SCHEDULE

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

D6 D7 D8 D9 D10

SEE

SCHE

DULE

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE SEE SCHEDULE

SEE

SCHE

DULE

SEE

SCHE

DULE

SEE SCHEDULE

SINGLE - GLASS TYPICALCONFERENCE DOOR

DOUBLE - GLASS DOORS SINGLE - HOLLOW METALPAINT-GRADE DOOR

DOUBLE - HOLLOW METALPAINT-GRADE DOOR

SINGLE - GLASS SLIDINGDOOR

SINGLE - GLASS LITEDOOR WITH WOOD CORE

STILE AND RAIL

SINGLE - SOLID CORERESTROOM DOOR

SINGLE - SOLID CORETYPICAL OFFICE DOOR

SINGLE - SOLID COREWOOD SLIDING DOOR

F1ALUMINUM FRAME

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

F2DEMOUNTABLE

FRAME

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

F3HOLLOW METAL

FRAME

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

F4ALUMINUM SLIDING

DOOR FRAME

SEE SCHEDULE

SEE

SCHE

DULE

SEE SCHEDULE

GROUP 1 - OFFICE LOCKSET• (2) PAIR BUTT HINGES• (1) LEVER OFFICE LOCKSET (AS DEFINED BY SCHLAGE)• (1) FLOOR MOUNTED DOME STOP• (1) WOOL PILE SOUND SEAL

GROUP 2 - GLASS CONFERENCE BARSET• (2) GLASS DOOR HINGESETS• (2) 14" PUSH/PULL BAR (SPEC TBD)• (1) FLOOR MOUNTED DOME STOP• (1) WOOL PILE SOUND SEAL• (1) CONCEALED CLOSER

GROUP 3 - GLASS PANTRY DOOR BARSET• (4) GLASS DOOR HINGESETS• (4) 14" PUSH/PULL BAR (SPEC TBD)• (2) DOME STOPS• (1) WOOL PILE SOUND SEAL• (2) CONCEALED CLOSERS• (2) MANUAL HOLD-OPENS

GROUP 4 - GLASS ENTRY DOOR BARSET• (4) GLASS DOOR HINGESETS• (2) PANIC BARSETS (DORMA DG1000 OR EQUAL)• (2) DOME STOPS• (1) WOOL PILE SOUND SEAL• (2) CONCEALED CLOSERS• (1) ELECTRONIC CARD-KEY READER

GROUP 5 - STORAGE ROOM LOCKSET• (2) PAIR BUTT HINGES• (1) LEVER LOCKSET (AS DEFINED BY SCHLAGE)• (1) FLOOR MOUNTED DOME STOP• (1) RUBBER SOUND SEAL• (1) ELECTRONIC CARD-KEY READER• (1) KICKPLATE• (1) CLOSER• (1) MANUAL HOLD-OPEN

GROUP 6 - BARN DOOR SLIDER BARSET• (1) BARN DOOR RAIL SYSTEM• (1) 14" PUSH/PULL BAR• (1) RUBBER GLIDE STOP• (1) WOOL PILE SOUND SEAL

GROUP 7 - UNISEX RESTROOM DOOR• (2) BUTT HINGES• (1) UNISEX TOILET SIGNAGE• (1) RESTROOM LOCKSET WITH OCCUPANCY INDICATOR (SEE SCHLAGE)• (1) RUBBER SOUND SEAL• (1) DOMESTOP• (1) COATHOOK (SEE ADA MOUNTING DETAILS FOR MORE INFO)

GROUP 8 - WORKROOM LATCHSET• (2) BUTT HINGES• (1) KICKPLATE• (1) WORKROOM LATCHSET (AS DEFINED BY SCHLAGE)• (1) RUBBER SOUND SEAL• (1) DOMESTOP• (1) CLOSER• (1) MANUAL HOLD-OPEN

GROUP 9 - TRAINING ROOM BARSET• (2) BUTT HINGES• (1) SET PANIC HARDWARE• (1) WOOL PILE SOUND SEAL• (1) DOMESTOP• (1) CLOSER• (1) MANUAL HOLD-OPEN

DOOR STOP

DOOR JAMB

JAMB CASING

STRIKE FILLER

GLAZ. AS SCHEDULED

DOOR JAMB

JAMB CASING

DOOR STOP

STUD

SCHEDULED DOOR

STUD

DOORDOOR HEAD STOP

DOOR HEAD

DOOR HEAD CASING

STUD

DOOR

1 1/2" 2 1/2" 2"

2" DOUBLE RABBETHOLLOW METAL DOORFRAME

DOOR JAMB

STUD

SCHEDULED DOOR

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

23 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

As indicated

A6-100

DOOR AND WINDOWSCHEDULES

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

WESTED DOOR SCHEDULEDOOR

NUMBER LOCATION

DOOR FRAME

FIRE RATINGHARDWARE

GROUP REMARKSTYPE MAT.NOMINAL SIZE

TYPE MAT.DETAIL REFERENCE

WIDTH HEIGHT THICKNESS HEAD JAMB

2000 CONFERENCE D2 GL 3' - 0" 8' - 0" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22001 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12002 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12003 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12005 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12006 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12007 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12008 CONFERENCE D2 GL 3' - 0" 8' - 0" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22009 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12010 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12011 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12012 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12013 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12014 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12015 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12016 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12017 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12018 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12019 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12021 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12022 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12023 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12024 CONFERENCE D2 GL 3' - 0" 8' - 2" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22026 CONFERENCE D2 GL 3' - 0" 8' - 2" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22028 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12029 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12030 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12031 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12033 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12034 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12035 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12036 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12037 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12038 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12039 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12040 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12041 CONFERENCE D2 GL 3' - 0" 8' - 4" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22043 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12044 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12045 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12046 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12048 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12049 CONFERENCE D2 GL 3' - 2" 8' - 0" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22050 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12051 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12052 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12053 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12054 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12055 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12057 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12058 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12059 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12060 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12061 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12062 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12063 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12065 WORK ROOM D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 82069 FOCUS D6 GL 3' - 0" 9' - 0" 1/2" F4 AL 03/A6-100 02/A6-100 NR 62070 SUPPLIES D5 MT/PT 6' - 0" 7' - 0" 1 3/4" F3 MT 05/A6-100 04/A6-100 NR 52071 HOTEL D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12073 CLOSET D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 52074 CONFERENCE D2 GL 3' - 2" 8' - 10" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22075 WORK ROOM D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 82077 CONFERENCE D2 GL 3' - 2" 8' - 10" 1/2" F2 AL 03/A6-100 02/A6-100 NR 22079 LOBBY D3 GL 6' - 0" 9' - 0" 1/2" F2 AL 03/A6-100 02/A6-100 NR 42080 BREAK ROOM D3 GL 6' - 0" 9' - 0" 1/2" F2 AL 03/A6-100 02/A6-100 NR 32082A TRAINING D7 WD/GL 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 92082B TRAINING D7 WD/GL 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 92083A TRAINING D7 WD/GL 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 92083B TRAINING D7 WD/GL 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 92085A GN RR D8 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 82085B GN RR D8 WD 2' - 4" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 72085C GN RR D8 WD 2' - 4" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 72085D GN RR D8 WD 2' - 4" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 72085E GN RR D8 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 72086 WELLNESS D8 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 72087 CLOSET D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 52088 PANTRY D4 MT/PT 3' - 0" 7' - 0" 1 3/4" F3 MT 05/A6-100 04/A6-100 NR 82089 FURNITURE STORAGE D4 MT/PT 3' - 0" 7' - 0" 1 3/4" F3 MT 05/A6-100 04/A6-100 NR 52092 FOCUS D6 GL 3' - 0" 9' - 0" 1/2" F4 AL 03/A6-100 02/A6-100 NR 62093 FOCUS D6 GL 3' - 0" 9' - 0" 1/2" F4 AL 03/A6-100 02/A6-100 NR 62094 CLOSET D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 52095 CLOSET D9 WD/GL 3' - 0" 8' - 0" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 52096 FOCUS D6 GL 3' - 0" 9' - 0" 1/2" F4 AL 03/A6-100 02/A6-100 NR 62100 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12101 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12102 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12103 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12104 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 12105 PRIVATE OFFICE D1 WD 3' - 0" 8' - 2" 1 3/4" F1 AL 03/A6-100 02/A6-100 NR 1

DOOR SCHEDULE NOTESDOOR TYPES LEGEND

UNI_DOOR FRAME TYPES LEGEND

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

DOOR HARDWARE SCHEDULES

SCALE: 6" = 1'-0"ALUMINUM FRAME AT SIDELIGHT 1SCALE: 6" = 1'-0"

ALUMINUM FRAME AT PARTITION 2SCALE: 6" = 1'-0"ALUMINUM FRAME AT GYP. HEADER 3SCALE: 6" = 1'-0"

HOLLOW METAL FRAME HEADER 5 SCALE: 6" = 1'-0"HOLLOW METAL FRAME AT JAMB 4

Page 32: WestEd Request for Proposal #4

SCHEDULED CARPET

SCHEDULED DOOR

SCHEDULED CARPET

ALIGN

EXISTING FLOOR SLAB

VINYL REDUCING STRIP, COLOR TOBE APPROVED BY ARCHITECT

CARPET

GLUE DOWN INSTALLATION

VINYLFLOORING

SCHEDULED CARPET

SCHEDULED DOOR

EXISTING FLOOR SLAB

VINYL REDUCING STRIP, COLOR TOBE APPROVED BY ARCHITECT. GCTO SUBMIT COLOR OPTIONS.

1/4" M

AX.

STONE SADDLELEVEL AND ANCHORTO FLOOR SLAB

CARPET

CERAMIC TILE ORSTONE ON THIN SETBED AS INDICATED

1/4" M

AX.

1/4" M

AX.

STONE SADDLE LEVELAND ANCHOR TO FLOORSLAB SLOPE TO BEGRADUAL FOR ADACOMPLIANCE

CONCRETE

CERAMIC TILE ORSTONE ON THIN SETBED AS INDICATED

1/8" THK. ALUM. OR SS ANGLETRANSITION STRIP FASTENEDSECURELY TO FLOOR SLAB; VERIFYPROPER HEIGHT FOR CARPETTHICKNESS

CONCRETE FLOOR

CARPET OR CARPET TILE -INSTALL PER MANUF.RECOMMENDATIONS

5/8" .VINYL/ RUBBER TILES ORSTATIC DISSAPATIVE TILES

TOP OF FLOOR SLAB TACKLESS STRIP

CARPET

ALUMINUM REDUCING STRIP -FUTURA IND. #415003 TR 14 OREQUAL APPROVED

ALUM. OR RUBBER TRANSITIONPIECE. ARCHITECT TO SELECTCOLOR. 1/4" MAX HEIGHTDIFFERENCE ACCEPTED.

SCHEDULED FINISH

SCHEDULED FINISH

ALUM. RAMP NOSING.ARCHITECT TOSELECT COLORSCHEDULED FINISH

RAISED FLOOR RAMPEXISTING SLAB

CONTRACTOR RO SUBMIT COLOR OPTIONS FOR TRANSITION PIECES AT ALLRAMP LOCATIONS. COLORS TO MATCH ADJACENT FLOOR COVERING.

T1 THRESHOLD - CARPET TO CARPET

T2 THRESHOLD - VINYL TO CARPET or VINYL TO VINYL

T3 TRANSITION - CARPET OR VINYL TO CONRETE

T4 THRESHOLD - CARPET OR VINYL TO STONE @ BATHROOM

T5 THRESHOLD - CONCRETE TO STONE AT THE BATHROOM

T6 THRESHOLD - CARPET OR VINYL TO CONCRETE (METAL STRIP)

T7 THRESHOLD - CARPET TO RUBBER FLOORING

T8 THRESHOLD - CARPET AT RAMP

EQUIPMENT SCHEDULE

TYPE DESCRIPTION MANUFACTURER TILE/ COLOR GRID REMARKS

ACT 2'x2' DEMOACT-1 (1'x6') ACOUSTICAL CEILING

TILEARMSTRONG 24" X 24" X 1" SQUARE

TEGULAR9/16" SUPRAFINE XL GRID WHITE

ACT-1 (2'x2') ACOUSTICAL CEILINGTILE

ARMSTRONG 24" X 24" X 1" SQUARETEGULAR

9/16" SUPRAFINE XL GRID WHITE

ACT-1 (2'x5') ACOUSTICAL CEILINGTILE

ARMSTRONG 24" X 24" X 1" SQUARETEGULAR

9/16" SUPRAFINE XL GRID WHITE

CLG-1 GYP. BD. CEILING - P-1 (FLAT) ASSCHEDULED

-

CEILING TYPE SCHEDULE

FLOOR TRANSITION TYPES

North

UNISPACE ©

Drawing Title:

General Notes:

Key Plan:

Status:

Drawing Number:

Project Number:

Scale:

Client / Project Name / Address:

Revision:

Drawn By: Checked By:

Date:

Consultants:

Stamp:

All work to be carried out in accordance with the US International Building Code, LocalBuilding Codes and Safety Regulations, Water, Electricity regulations and all otherrelevant Authorities requirement concerned.All work to be carried out in a professional & workmanship like manner according to theplans & specification.Do not scale off the drawings unless otherwise stated and use figured dimensions inpreference.All dimensions are to be checked & verified on site before the commencement of anywork, all dimensions & levels are subject to final survey and set-out.This drawing & design is the property of the design group noted on this sheet andshould not be reproduced either in part or whole without the written consent of this firm.

PRIN

TED

:00 11/1

3/20

17 4

:27:

26 P

MC

:\Use

rs\L

iam

Cla

rk\D

ocum

ents

\Cen

tral_

Wes

tEd

Alam

eda_

liam

.cla

rkEL

B5B.

rvt

12" = 1'-0"

A6-200

EQUIP. SCHEDULES,TYP. TRANSITION

DETAILS

SFC-00018A

ISSUE FOR PERMIT

01/01/17

of 200

WESTED2470 MARINER SQ LOOP, ALAMEDA CA

94501

CheckerAuthor

720 Market St. 10th FloorSan Francisco CA 94108 USA

+1 415 423 0111www.unispace.com

REV DESCRIPTION DATE BY CHKISSUE FOR PERMIT 11/20/2017

Page 33: WestEd Request for Proposal #4

Exhibit A

Independent Contractor/Service Provider Agreement Insurance Requirements WestEd-Alameda Center Owner, LLC

2470 Mariner Square Loop, Suite 200, Alameda, CA

Workers' Compensation & Employer’s Liability: 1. Policy to be amended to state THIRTY (30) days prior written notice of cancellation to

be given to the Employer’s Liability for not less than $1,000,000 per Person/Accident 2. Waiver of Subrogation in favor of WestEd and its affiliates, subsidiaries, successors,

directors, officers, employees, agents and representatives; Alameda Center Owner, LLC, a Delaware limited liability company and its affiliates, subsidiaries, successors, directors, officers, employees, agents and representatives; and Steelwave L.P. and its affiliates, subsidiaries, successors, directors, officers, employees, agents.

Commercial General and Automobile Liability & Umbrella (Excess) Liability Insurance; Professional Liability & Pollution Liability, if applicable to operations:

1. General Liability with Bodily Injury and Property Damage Liability limits of not less than $1,000,000 each occurrence/$2,000,000 aggregate. Your policy must include Premises/Operations, Products & Completed Operations, Personal & Advertising Injury and Contractual Liability coverage.

2. Automobile Liability limits of not less than $1,000,000 per occurrence.

3. Umbrella (Excess Liability) with limits not less than $4,000,000 per occurrence, $8,000,000 Aggregate above General Liability, Auto and Employer’s Liability.

4. WestEd and its affiliates, subsidiaries, successors, directors, officers, employees, agents and representatives; Alameda Center Owner, LLC, a Delaware limited liability company and its affiliates, subsidiaries, successors, directors, officers, employees, agents and representatives; and Steelwave L.P. and its affiliates, subsidiaries, successors, directors, officers, employees, agents shall be named as Additional Insureds including premises/operations (CG2010 -1185 or equivalent form) and products/completed operations (CG2037-1185) with the proper endorsements attached.

5. Your policies must be endorsed as follows: The policies shall be primary and not contributing with any other insurance in effect for the Additional Insureds shown in #4 above and include a Waiver of Subrogation in favor of Additional Insureds above.

6. Contractor’s Pollution and Professional Liability required if applicable to contract for limits not less than $1,000,000 per occurrence. If policies are written on a claims–made basis, coverage needs to remain in force for at least 5 years after the completion of the project/services rendered.

7. All Policies to be endorsed to state THIRTY (30) days prior written notice of cancellation to be given to the.

All Certificates & Endorsements are to be addressed and sent to:

Jonathan Mills Director, Property & Facility Management WestEd 730 Harrison Street San Francisco, CA 94107 [email protected] 415.615.3114

Alexandra Arsenlis Regional Vice President Steelwave 400 E Third Ave, Suite 500 Foster City, CA 94404 [email protected] 650.235.2724

Page 34: WestEd Request for Proposal #4

Steelwave 4000 East Third Avenue, Suite 500 Foster City, CA 94404-1167 Phone: 650.571.2200

General Contractor Rules For Tenant Improvement Construction

1. All work shall comply with the rules and regulations of the building, city, state and federal

government agencies having jurisdiction.

2. Architect and/or contractor shall file drawings and secure all permits prior to any

construction.

3. A set of permit drawings and all required permits and licenses must be on site at all

times.

4. MS DS Sheets, (as applicable to supplies and materials furnished or used on site), must

be on-site and available for review at all times.

5. The contractor shall notify the Building Manager at least 24 hours in advance of any

interruption of building services, including electrical, mechanical, and fire/life safety

systems.

6. The contractor shall contact the Building Manager at start of construction for instructions

on how the fire/life safety system is to be handled during construction. Each day,

Contractor must make sure all site devices have been isolated or protected before

commencing with construction.

7. The contractor shall contact the Building Manager at start of construction for instructions

on building keying and hardware schedules. Hardware must meet building standards.

8. Contractor will be responsible for security of the construction site and premises.

Contractor will secure the property each day. Building Management will not be

responsible for providing access to Contractor or Contractor’s subs at any time (unless

under special prior arrangement).

9. Access to other tenant or building areas outside of tenant areas must be arranged in

advance through the Building Office.

10. Contractor must make all precautions against fire danger. All contractors on site must be

versed with emergency exits and location of fire extinguishers. At no time shall

contractor allow any stairwell or fire exit doors to be blocked or held open. Doors to

equipment and electrical rooms shall not be left open when contractor is not present. All

Page 35: WestEd Request for Proposal #4

contractors on site must be instructed to evacuate site in the event of a fire alarm. They

are to go back to the site once the Fire Department or Building Management has given

direction to do so.

11. The construction site must be supplied by Contractor with at least two fire extinguishers

per floor; if no fire extinguisher exists on the floor at time of build-out.

12. Permission and access arrangements must be obtained from the Building Office for any

after hours or weekend work. This work may be subject to supervision by Building

Engineer.

13. The contractor shall notify the Building Office at least 48 hours in advance of completion

of construction. A punch list walk through shall be performed at the end of job with

Steelwave personnel in attendance.

14. Contractor must post the attached “Construction Site Rules and Regulations” at the site

as well as provide copies to all on-site personnel (job foreman, job superintendent,

subcontractors). Contractor must enforce construction site Rules and Regulations with

all personnel and subcontractors. These Rules and Regulations comprise Steelwave

“Minding the Store” program for construction sites.

15. A construction superintendent must be available by phone or pager at all times. When

an emergency arises, the construction superintendent must go to the site immediately.

16. Post Emergency numbers at the site. See attached.

Page 36: WestEd Request for Proposal #4

ATTENTION ALL CONTRACTORS MUST READ THIS

BEFORE ENTERING SITE

“ALAMEDA CENTER”

CONSTRUCTION SITE RULES & REGULATIONS

1. Access to the site is via side entries at all times. Do not access the site via the main

lobby and passenger elevators. Passenger elevators can be used as described

below.

2. The following restrooms are to be used by contractors: (location)

3. Deliveries to the site must be done with the passenger elevator fully protected.

Should you need to deliver large items require the use of the elevator for an

extended period of time, please contact the Job Superintendent before using the

elevator. Such use must be done prior to 8:30 AM or after 6:00 PM on weekdays or

at anytime during the weekends with prior notice to the Job Superintendent.

4. No radios on the site. No smoking on the site. No trash left on site at end of day.

Disposal of food and beverages is in trash bins – do not leave around site.

5. All construction work which is particularly noisy must be done before 8:30 AM or after

6:00 PM on weekdays. Please keep this in mind at all times. Disruption or

interruption of the building’s occupants will not be tolerated.

6. All core drilling must be done before 8:30 AM and after 6:00 PM on weekdays or

anytime on weekends with prior notice to the Job Superintendent of the exact

schedule for core drilling.

7. Upon being told to stop any work by the Building Manager or a building tenant, stop

the work immediately and notify the Job Superintendent.

8. Security is critical to the building’s occupants and the construction site. The front

door to the site must remain shut at all times. The door must be secured by the Job

Superintendent at the end of each work day. DO NOT LEAVE THE SITE

UNATTENDED. Wait for or contact the Job Superintendent before leaving.

Remember: your tools and materials are at stake. Office buildings are often

targeted for construction site theft.

Page 37: WestEd Request for Proposal #4

Maintain cleanliness throughout the construction site. Take your trash or debris with you

at the end of each day. DO NOT LEAVE ANY TRASH OR DEBRIS OUTSIDE OF THE

BUILDING AT ANY TIME. USE THE DEBRIS BINS ON SITE OR DEBRIS BOXES

SUPPLIES BY THE JOB SUPERINTENDENT.

9. Debris boxes may be delivered only after permission from Building Management.

You must confirm the delivery location with Building Management.

10. Do not clutter any area of the site, exterior, stairwell, lobbies, etc. with material.

11. Do not block open any stairwell or fire exit doors.

12. Access to other tenant areas must be arranged in advance through the Job

Superintendent. The Job Superintendent must contact the Building Manager in

advance to make these arrangements.

13. All debris removal will be made as quickly as possible when using the passenger

elevator which must be fully protected. Large scale debris removal must be done

before 8:30 AM or after 6:00 PM on weekdays, or at anytime on weekends with prior

notice to the Job Superintendent.

14. Do not pour any foreign matter down sinks in janitor closets or restrooms.

15. Doors to equipment and electrical rooms shall not be left open when contractor is not

present.

16. Access to the site must be arranged with the Job Superintendent. The security officer

and Building Engineer will not provide access unless notified in advance by the

Building Manager via the Job Superintendent OR UNDER SPECIAL

ARRANGEMENT WITH AN ID CARD.

17. Locate and be familiar with all fire exists and fire extinguishers on site. Each floor has

two exits and two extinguishers. You must vacate the premises and building in the

event of a fire alarm. You can re-enter the building once instructed by the Fire

Department or Building Management.

18. You must speak with the Job Superintendent first before starting any construction

which could cause a fire alarm device to be activated. This includes sanding, drilling,

sawing, welding, soldering, carpet seam heating, disconnection or fire detection

devices, cutting of fire detection wiring, shut down of sprinkler system.

19. Contact the Building Manager immediately should any type of emergency arise at the

building.

Page 38: WestEd Request for Proposal #4

Post at Construction site

EMERGENCY NUMBERS

FIRE: 9 1 1

POLICE: 9 1 1

AMBULANCE: 9 1 1

Job Superintendent: Office: Mobile: Pager: Project Manager: Building Manager: Alexandra Arsenlis (408) 799-1365