wild presentation -311210

Upload: vasu-dev

Post on 03-Jun-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Wild Presentation -311210

    1/46

    WHEEL IMPACT LOAD DETECTOR

    BY

    S.VASUDEVAIAH, IRSMEAMIE,M TECH., MS., MBA

  • 8/12/2019 Wild Presentation -311210

    2/46

    FLAT FACE ON WHEEL

  • 8/12/2019 Wild Presentation -311210

    3/46

    ROLLING IN EXAMINATION

    Wheel flats are being identified manually by

    listening to the sound produced by running wheels

    at the entrance to major yards

    This method is based on experience and not very

    accurate.

  • 8/12/2019 Wild Presentation -311210

    4/46

    WILD CONCEPT

    When the wheel is perfectly round it applies a uniform

    load on the rail.

    When a wheel is flat, it applies a huge impact load onthe rail when ever the flat portion hits the rail.

    Wheel flat Impact Load Detector is used to catch the

    flatness in the early stage and thereby protecting Railinfrastructure.

  • 8/12/2019 Wild Presentation -311210

    5/46

    WILD CONCEPT

    Automation of this system of detection is possible

    by measuring the impact forces of the wheels on

    the rails

    Wheel flats exert large dynamic loads on the track

    which can be detected through strain gauges fixed

    on the instrumented rail

  • 8/12/2019 Wild Presentation -311210

    6/46

    WILD Development

    Jointly developed by RDSO & IIT-Kanpur

    and M/s Apna Technologies & Solutions

    Developed and successfully tested at

    Aggain station, between Kanpur and

    LUCKNOW.

  • 8/12/2019 Wild Presentation -311210

    7/46

    SANCTION OF WILD

    To study the loading spectrum actually passing over

    the track and bridges Rly BD has sanctioned WILD

    during 2005.

    Vasco- Hospet- Guntakal- Renigunta- Chennai is

    one of the identified route for installing the WILD

  • 8/12/2019 Wild Presentation -311210

    8/46

    MANUFACTURER

    The offer of M/s Apna Technologies & Solutions

    Private limited was accepted and order was placed

    on 12.02.07.

    Cost Rs 75,68,910

  • 8/12/2019 Wild Presentation -311210

    9/46

    APPROVED LOCATIONS- IR

    Asonsol, ER (KalipahartiNimach)

    Waltair, Eco R(Simhachalam- North Pendurthi)

    Guntakal ( Haddinagundu

    Hagari)

    Bhilai,SE (Rajkarswanmahalimarup)

    Aditypur, Jharkhand (GDZLBO Raipur divn)

    Hospet, SWR (Koppal and Ginigira)

    Mugalsarai,ECR (Bhabhua road on up and middle line)

    Arakkonam, SR (TiruttaniArakkonum)

  • 8/12/2019 Wild Presentation -311210

    10/46

    SALIENT FEATURES OF WILD

    Automatic identification/ detection of defective

    wheels causing abnormal dynamic impact load.

    Detection of overloaded wagons.

    Online transfer from site to Control office.

    Automatic exception report generation

  • 8/12/2019 Wild Presentation -311210

    11/46

    Exit

    Trigger Sensor

    Entry

    Trigger Sensor

    6 Channels (R1~R6) 6 Channels (R7~R12)

    6 Channels (L1~L6) 6 Channels (L7~L12)

    Signal Conditioning Modules

    Real Time

    Controller

    Control &

    Switching Circuits

    Backup

    Device

    GSM ModemEB Power/

    Primary Power

    Solar Power/

    Secondary Power

    AT SITE

    AT TXR CONTROL ROOM

    Instrumented Track

    WILD BLOCK DIAGRAM

  • 8/12/2019 Wild Presentation -311210

    12/46

    INSTRUMENTED TRACK

  • 8/12/2019 Wild Presentation -311210

    13/46

    Instrumented Track Pictures

  • 8/12/2019 Wild Presentation -311210

    14/46

    INSTRUMENTED TRACK PICTURES

  • 8/12/2019 Wild Presentation -311210

    15/46

    SIGNAL FROM INSTRUMENTED TRACK

  • 8/12/2019 Wild Presentation -311210

    16/46

    MAIN CONSTITUENTS OF WILD

    Transducer for detecting the impact load on the track

    due to wheel defect.

    Data logging and processing equipment.

    Report generation and communication equipment

  • 8/12/2019 Wild Presentation -311210

    17/46

    TRANSDUCER

    Transducers for the system are strain gauges fixed on the

    two rails for measurement of vertical wheel loads.

    Rosette strain gauges are fixed on neutral axis on the web ofrails between sleeper cribs with Wheatstone bridge.

    The impact load of a flat wheel will indicate a signature with a

    sudden drop followed by and instantaneous increase with inmilliseconds.

  • 8/12/2019 Wild Presentation -311210

    18/46

    TRANSDUCER

    An algorithm based on this principle is used to isolatethe defective wheel from normal wheel.

    Based on this algorithm, LabVIEW platform is usedfor data acquisition.

    Analysis of data is done by MATLAB software which

    is interfaced with LabVIEW.

  • 8/12/2019 Wild Presentation -311210

    19/46

    CONCEPT OF MEASUREMENT

    On each instrumented rails there are 12 channels which

    record dynamic wheel load

    During the length each wheel makes two revolutions

    With 12 values of dynamic load max value is picked up

    With the average of 10 lower values is treated as normaldynamic wheel load.

  • 8/12/2019 Wild Presentation -311210

    20/46

    FUNCTIONAL CAPABILITY

    Can detect defective wheels by measuring impactload on rails

    Can generate hard copy of reports Wheel identification

    Axle identification

    Impact load Speed

    Direction, date, time etc.,

  • 8/12/2019 Wild Presentation -311210

    21/46

    Work efficiently in the speed range of 30 kmph to 160kmph

    System can work in ambient temp range of 0 to 500C andrelative humidity up to 95% or more.

    System operates on 230 V AC.

    System can measure impact load up to 60 tonnes or evenmore.

    System can cater for all wheels with 770 mm to 1100 mm.

    FUNCTIONAL CAPABILITY

  • 8/12/2019 Wild Presentation -311210

    22/46

    It is capable of detecting 95% or more defects in

    wheel on first pass.

    It is capable of functioning with trains consisting upto 100 vehicles (400 axles) of all categories.

    Locos ; Coaches ; wagons

    FUNCTIONAL CAPABILITY

  • 8/12/2019 Wild Presentation -311210

    23/46

    Data storage capacity for at least 20,000 trainsat a time.

    System test is performed after every run, anddiagnostic report is sent to computer system incontrol office.

    Transducers are protected by suitable coveringto avoid damage by track machines

    FUNCTIONAL CAPABILITY

  • 8/12/2019 Wild Presentation -311210

    24/46

    To be installed on straight and level track of 250 m lengthincluding approaches to the site.

    Preferably there should not be any fish plated joint with in13 m on either side of the instrumented portion of thetrack.

    No weld joint in the instrumented portion of the track is

    permitted. Track condition should be as close as new condition as

    possible.

    SITE REQUIREMENT

  • 8/12/2019 Wild Presentation -311210

    25/46

    Rail used for instrumentation should be ultrasonically

    tested and to be defect free.

    Rail section should be 52 kg/m or 60 kg/m with PSCsleeper spacing of 60-65 cm.

    The site should not be very close to any station or at the

    approach of signal to avoid acceleration or braking over the

    instrumented rails

    SITE REQUIREMENT

  • 8/12/2019 Wild Presentation -311210

    26/46

    Hut for installing the system.

    The section should have good GSM connectivity so

    that the data can be transferred via GSM to thecontrol room.

    Electrical supply connection.

    Drinking and security arrangements

    INFRASTRUCTURE AT SITE

  • 8/12/2019 Wild Presentation -311210

    27/46

    HARDWARE

    Two full length 50kg/60 kg rails.

    Signal conditioners and amplifiers.

    32 channel high speed data acquisition system.

    One PC at the site and other at control.

    Dedicated communication link of handling datatransfer up to 64 kbps.

    100 nos of rosette type strain gauges

  • 8/12/2019 Wild Presentation -311210

    28/46

    SOFTWARE

    Window based software on LabVIEW and MATLAB

    platform.

    Compatible with VB.

  • 8/12/2019 Wild Presentation -311210

    29/46

    SUMMERY REPORT

    Axle no from front

    Average dynamic wheel load for each axle

    Max dynamic load for each axle Speed of each axle

    Overloaded wheels

    Serial no of the defective wheel from engine

  • 8/12/2019 Wild Presentation -311210

    30/46

    CABLING

    The location should be with in the vicinity of 3 kms

    of the first stop signal in the direction of movement

    as cabling up to 3 kms is covered in the scope ofwork

  • 8/12/2019 Wild Presentation -311210

    31/46

    MONITORING OF WILD

    S. No Alarm ILF Load (T)

    1 Maintenance 2.0-4.5 25-35

    2 Critical >4.5 >35

    Information should be given to next TXR point afterreceiving the alarm.

    Wagon/Coach should be thoroughly examined forrunning gear defects.

    Based on the defects noticed decision should betaken to allow or detach the wagon/coach.

    WILD Sample Report

    http://localhost/var/www/apps/conversion/tmp/scratch_7/irwild_net.htm
  • 8/12/2019 Wild Presentation -311210

    32/46

    DATA OF WILD ALARMS

    Alarm Stock DetachedMinor

    defect

    No

    defect

    Feedback

    not received Total

    Critical

    Freight 44 5 19 - 68

    Coaching 17 6 68 3 94

    Engine 5 - 4 - 9

    Total 66 11 91 3 171

    Percentage 38.8 6.5 53.2 1.8

    Maintenance

    Freight 27 44 458 - 529

    Coaching 109 108 1349 65 1631

    Engine 3 1 12 2 18

    Total 139 153 1819 67 2178

    Percentage 6.4 7.0 83.5 2.4

    Data is from 16.10.08 to 31.01.11

  • 8/12/2019 Wild Presentation -311210

    33/46

    Train passing over instrumented rail

  • 8/12/2019 Wild Presentation -311210

    34/46

    Trigger sensor

  • 8/12/2019 Wild Presentation -311210

    35/46

    Control Panel room

  • 8/12/2019 Wild Presentation -311210

    36/46

    Channel fixing arrangement to rail

    Control panel

  • 8/12/2019 Wild Presentation -311210

    37/46

    Control panel

    System showing critical alarm

  • 8/12/2019 Wild Presentation -311210

    38/46

    System showing critical alarm

  • 8/12/2019 Wild Presentation -311210

    39/46

    THANKYOU

  • 8/12/2019 Wild Presentation -311210

    40/46

    TESTS TO BE CONDUCTED FOR PTC

    Consistency test

    Calibration test

    Accuracy test

    Repeatability test

    Speed test

    No. of Engines/wagons test

  • 8/12/2019 Wild Presentation -311210

    41/46

    CONSISTENCY TEST

    The train has to run 6 times over theinstrument.

    The reports has to be verified for number of

    working channels. The number of working channels should be 21

    or higher.

  • 8/12/2019 Wild Presentation -311210

    42/46

    CALIBRATION TEST

    A vertical known impact load should be appliedon any of four channels.

    The load recorded in the system should be

    within +/- 2%. The test has to be repeated on the same

    channels after 15 days

  • 8/12/2019 Wild Presentation -311210

    43/46

    ACCURACY TEST

    The Loco/Wagon of known weight should berun through the system at crawling speed.

    Sum of all the wheel loads of the Loco/Wagonhas to be calculated.

    The sum should be within +/- 4% of originalweight of the Loco/Wagon

  • 8/12/2019 Wild Presentation -311210

    44/46

    REPEATABILITY TEST

    The test train has to run at three different speeds and

    three runs at each speed.

    The avg. axle load has to be calculated.

    The individual axle load should be within +/- 5% of the

    avg. axle load.

  • 8/12/2019 Wild Presentation -311210

    45/46

    SPEEDTEST

    The test formation has to be run at different speeds.

    The speed in the Locomotive speedometer should be

    recorded.

    The speed recorded in the report should be within +/- 5 Kmph

  • 8/12/2019 Wild Presentation -311210

    46/46

    NO. OF ENGINES/WAGONS TEST

    The test formation has to be moved for 9 runs.

    The number of axles recorded in the report should

    be recorded.

    It has to be compared with actual number of axlespassed through.

    No variation should be permitted.