wild presentation -311210
TRANSCRIPT
-
8/12/2019 Wild Presentation -311210
1/46
WHEEL IMPACT LOAD DETECTOR
BY
S.VASUDEVAIAH, IRSMEAMIE,M TECH., MS., MBA
-
8/12/2019 Wild Presentation -311210
2/46
FLAT FACE ON WHEEL
-
8/12/2019 Wild Presentation -311210
3/46
ROLLING IN EXAMINATION
Wheel flats are being identified manually by
listening to the sound produced by running wheels
at the entrance to major yards
This method is based on experience and not very
accurate.
-
8/12/2019 Wild Presentation -311210
4/46
WILD CONCEPT
When the wheel is perfectly round it applies a uniform
load on the rail.
When a wheel is flat, it applies a huge impact load onthe rail when ever the flat portion hits the rail.
Wheel flat Impact Load Detector is used to catch the
flatness in the early stage and thereby protecting Railinfrastructure.
-
8/12/2019 Wild Presentation -311210
5/46
WILD CONCEPT
Automation of this system of detection is possible
by measuring the impact forces of the wheels on
the rails
Wheel flats exert large dynamic loads on the track
which can be detected through strain gauges fixed
on the instrumented rail
-
8/12/2019 Wild Presentation -311210
6/46
WILD Development
Jointly developed by RDSO & IIT-Kanpur
and M/s Apna Technologies & Solutions
Developed and successfully tested at
Aggain station, between Kanpur and
LUCKNOW.
-
8/12/2019 Wild Presentation -311210
7/46
SANCTION OF WILD
To study the loading spectrum actually passing over
the track and bridges Rly BD has sanctioned WILD
during 2005.
Vasco- Hospet- Guntakal- Renigunta- Chennai is
one of the identified route for installing the WILD
-
8/12/2019 Wild Presentation -311210
8/46
MANUFACTURER
The offer of M/s Apna Technologies & Solutions
Private limited was accepted and order was placed
on 12.02.07.
Cost Rs 75,68,910
-
8/12/2019 Wild Presentation -311210
9/46
APPROVED LOCATIONS- IR
Asonsol, ER (KalipahartiNimach)
Waltair, Eco R(Simhachalam- North Pendurthi)
Guntakal ( Haddinagundu
Hagari)
Bhilai,SE (Rajkarswanmahalimarup)
Aditypur, Jharkhand (GDZLBO Raipur divn)
Hospet, SWR (Koppal and Ginigira)
Mugalsarai,ECR (Bhabhua road on up and middle line)
Arakkonam, SR (TiruttaniArakkonum)
-
8/12/2019 Wild Presentation -311210
10/46
SALIENT FEATURES OF WILD
Automatic identification/ detection of defective
wheels causing abnormal dynamic impact load.
Detection of overloaded wagons.
Online transfer from site to Control office.
Automatic exception report generation
-
8/12/2019 Wild Presentation -311210
11/46
Exit
Trigger Sensor
Entry
Trigger Sensor
6 Channels (R1~R6) 6 Channels (R7~R12)
6 Channels (L1~L6) 6 Channels (L7~L12)
Signal Conditioning Modules
Real Time
Controller
Control &
Switching Circuits
Backup
Device
GSM ModemEB Power/
Primary Power
Solar Power/
Secondary Power
AT SITE
AT TXR CONTROL ROOM
Instrumented Track
WILD BLOCK DIAGRAM
-
8/12/2019 Wild Presentation -311210
12/46
INSTRUMENTED TRACK
-
8/12/2019 Wild Presentation -311210
13/46
Instrumented Track Pictures
-
8/12/2019 Wild Presentation -311210
14/46
INSTRUMENTED TRACK PICTURES
-
8/12/2019 Wild Presentation -311210
15/46
SIGNAL FROM INSTRUMENTED TRACK
-
8/12/2019 Wild Presentation -311210
16/46
MAIN CONSTITUENTS OF WILD
Transducer for detecting the impact load on the track
due to wheel defect.
Data logging and processing equipment.
Report generation and communication equipment
-
8/12/2019 Wild Presentation -311210
17/46
TRANSDUCER
Transducers for the system are strain gauges fixed on the
two rails for measurement of vertical wheel loads.
Rosette strain gauges are fixed on neutral axis on the web ofrails between sleeper cribs with Wheatstone bridge.
The impact load of a flat wheel will indicate a signature with a
sudden drop followed by and instantaneous increase with inmilliseconds.
-
8/12/2019 Wild Presentation -311210
18/46
TRANSDUCER
An algorithm based on this principle is used to isolatethe defective wheel from normal wheel.
Based on this algorithm, LabVIEW platform is usedfor data acquisition.
Analysis of data is done by MATLAB software which
is interfaced with LabVIEW.
-
8/12/2019 Wild Presentation -311210
19/46
CONCEPT OF MEASUREMENT
On each instrumented rails there are 12 channels which
record dynamic wheel load
During the length each wheel makes two revolutions
With 12 values of dynamic load max value is picked up
With the average of 10 lower values is treated as normaldynamic wheel load.
-
8/12/2019 Wild Presentation -311210
20/46
FUNCTIONAL CAPABILITY
Can detect defective wheels by measuring impactload on rails
Can generate hard copy of reports Wheel identification
Axle identification
Impact load Speed
Direction, date, time etc.,
-
8/12/2019 Wild Presentation -311210
21/46
Work efficiently in the speed range of 30 kmph to 160kmph
System can work in ambient temp range of 0 to 500C andrelative humidity up to 95% or more.
System operates on 230 V AC.
System can measure impact load up to 60 tonnes or evenmore.
System can cater for all wheels with 770 mm to 1100 mm.
FUNCTIONAL CAPABILITY
-
8/12/2019 Wild Presentation -311210
22/46
It is capable of detecting 95% or more defects in
wheel on first pass.
It is capable of functioning with trains consisting upto 100 vehicles (400 axles) of all categories.
Locos ; Coaches ; wagons
FUNCTIONAL CAPABILITY
-
8/12/2019 Wild Presentation -311210
23/46
Data storage capacity for at least 20,000 trainsat a time.
System test is performed after every run, anddiagnostic report is sent to computer system incontrol office.
Transducers are protected by suitable coveringto avoid damage by track machines
FUNCTIONAL CAPABILITY
-
8/12/2019 Wild Presentation -311210
24/46
To be installed on straight and level track of 250 m lengthincluding approaches to the site.
Preferably there should not be any fish plated joint with in13 m on either side of the instrumented portion of thetrack.
No weld joint in the instrumented portion of the track is
permitted. Track condition should be as close as new condition as
possible.
SITE REQUIREMENT
-
8/12/2019 Wild Presentation -311210
25/46
Rail used for instrumentation should be ultrasonically
tested and to be defect free.
Rail section should be 52 kg/m or 60 kg/m with PSCsleeper spacing of 60-65 cm.
The site should not be very close to any station or at the
approach of signal to avoid acceleration or braking over the
instrumented rails
SITE REQUIREMENT
-
8/12/2019 Wild Presentation -311210
26/46
Hut for installing the system.
The section should have good GSM connectivity so
that the data can be transferred via GSM to thecontrol room.
Electrical supply connection.
Drinking and security arrangements
INFRASTRUCTURE AT SITE
-
8/12/2019 Wild Presentation -311210
27/46
HARDWARE
Two full length 50kg/60 kg rails.
Signal conditioners and amplifiers.
32 channel high speed data acquisition system.
One PC at the site and other at control.
Dedicated communication link of handling datatransfer up to 64 kbps.
100 nos of rosette type strain gauges
-
8/12/2019 Wild Presentation -311210
28/46
SOFTWARE
Window based software on LabVIEW and MATLAB
platform.
Compatible with VB.
-
8/12/2019 Wild Presentation -311210
29/46
SUMMERY REPORT
Axle no from front
Average dynamic wheel load for each axle
Max dynamic load for each axle Speed of each axle
Overloaded wheels
Serial no of the defective wheel from engine
-
8/12/2019 Wild Presentation -311210
30/46
CABLING
The location should be with in the vicinity of 3 kms
of the first stop signal in the direction of movement
as cabling up to 3 kms is covered in the scope ofwork
-
8/12/2019 Wild Presentation -311210
31/46
MONITORING OF WILD
S. No Alarm ILF Load (T)
1 Maintenance 2.0-4.5 25-35
2 Critical >4.5 >35
Information should be given to next TXR point afterreceiving the alarm.
Wagon/Coach should be thoroughly examined forrunning gear defects.
Based on the defects noticed decision should betaken to allow or detach the wagon/coach.
WILD Sample Report
http://localhost/var/www/apps/conversion/tmp/scratch_7/irwild_net.htm -
8/12/2019 Wild Presentation -311210
32/46
DATA OF WILD ALARMS
Alarm Stock DetachedMinor
defect
No
defect
Feedback
not received Total
Critical
Freight 44 5 19 - 68
Coaching 17 6 68 3 94
Engine 5 - 4 - 9
Total 66 11 91 3 171
Percentage 38.8 6.5 53.2 1.8
Maintenance
Freight 27 44 458 - 529
Coaching 109 108 1349 65 1631
Engine 3 1 12 2 18
Total 139 153 1819 67 2178
Percentage 6.4 7.0 83.5 2.4
Data is from 16.10.08 to 31.01.11
-
8/12/2019 Wild Presentation -311210
33/46
Train passing over instrumented rail
-
8/12/2019 Wild Presentation -311210
34/46
Trigger sensor
-
8/12/2019 Wild Presentation -311210
35/46
Control Panel room
-
8/12/2019 Wild Presentation -311210
36/46
Channel fixing arrangement to rail
Control panel
-
8/12/2019 Wild Presentation -311210
37/46
Control panel
System showing critical alarm
-
8/12/2019 Wild Presentation -311210
38/46
System showing critical alarm
-
8/12/2019 Wild Presentation -311210
39/46
THANKYOU
-
8/12/2019 Wild Presentation -311210
40/46
TESTS TO BE CONDUCTED FOR PTC
Consistency test
Calibration test
Accuracy test
Repeatability test
Speed test
No. of Engines/wagons test
-
8/12/2019 Wild Presentation -311210
41/46
CONSISTENCY TEST
The train has to run 6 times over theinstrument.
The reports has to be verified for number of
working channels. The number of working channels should be 21
or higher.
-
8/12/2019 Wild Presentation -311210
42/46
CALIBRATION TEST
A vertical known impact load should be appliedon any of four channels.
The load recorded in the system should be
within +/- 2%. The test has to be repeated on the same
channels after 15 days
-
8/12/2019 Wild Presentation -311210
43/46
ACCURACY TEST
The Loco/Wagon of known weight should berun through the system at crawling speed.
Sum of all the wheel loads of the Loco/Wagonhas to be calculated.
The sum should be within +/- 4% of originalweight of the Loco/Wagon
-
8/12/2019 Wild Presentation -311210
44/46
REPEATABILITY TEST
The test train has to run at three different speeds and
three runs at each speed.
The avg. axle load has to be calculated.
The individual axle load should be within +/- 5% of the
avg. axle load.
-
8/12/2019 Wild Presentation -311210
45/46
SPEEDTEST
The test formation has to be run at different speeds.
The speed in the Locomotive speedometer should be
recorded.
The speed recorded in the report should be within +/- 5 Kmph
-
8/12/2019 Wild Presentation -311210
46/46
NO. OF ENGINES/WAGONS TEST
The test formation has to be moved for 9 runs.
The number of axles recorded in the report should
be recorded.
It has to be compared with actual number of axlespassed through.
No variation should be permitted.