wilton waste audit public v9 - centre for process … · consultants wilton site waste audit...
TRANSCRIPT
Consultants
WILTON SITE WASTE AUDIT
Client:
RENEW at CPI
Centre for Process Innovation Ltd, Wilton Centre, Wilton,
Redcar TS10 4RF
February, 2010
DRD Consultants Process Engineers & HSE Consultants
Design Research & Development Co. Ltd.
H235, Wilton Centre
Wilton, Redcar TS10 4RF UK
Tel: +44 (0)1642 430090 Fax: 08456 800 791
E-mail: [email protected]
Contents
Executive Summary 1
1 Introduction 2
2 Project Brief 3
3 Companies Surveyed 3
4 Wilton Site Major Waste Streams 3
5 Possible Future Opportunities 4
6 Other Projects 6
7 Conclusions 8
8 Dissemination Event 9
9 References 10
Executive Summary
Legislation and financial penalties have meant that many companies have
implemented their own waste reduction and resource efficiency
programmes. This is highlighted by the most recent major investment of a
plant at Wilton which has no declared waste streams. The other companies on Wilton site either deal with their waste streams directly or through third
party waste disposal companies. There may be opportunities for some
Wilton site operators to co-operate in the disposal of toxic or hazardous
wastes which are currently transported significant distances to specialist
companies for disposal. Companies could benefit from the economies of
scale from a central collection point on Wilton site for the segregation of
general solid waste such as metals, plastics, paper and wood.
At the time of writing, the future of a number of plants on the Wilton site
was unclear. Whether these plants close or restart will have a significant
effect upon the quantities of waste leaving the site, and on the
opportunities for synergies. However, aqueous effluent from Wilton site has
reduced because of plant closures and Northumbrian Water currently has
spare capacity at Bran Sands.
A key objective for Wilton site is now to attract new companies and
investment that require land, electrical and thermal energy and preferably
other services such as effluent treatment. The audit has identified a
number of potential opportunities for both conventional operations and for
renewable technologies. In general, the investment costs are high, but the
technical risks of the projects would be low, although timescales tend to be
long. However, any investment in waste treatment technology would
almost certainly require the import of waste feedstock because there would
be insufficient wastes available from Wilton site alone for these projects to
be economically viable.
It is apparent that significant commitment and investment will be required,
together with strategic planning, in order for some of the opportunities to
be realised.
Authors’ Notes
1. This is an abridged version of the full report from which confidential company information has been removed. The full report was submitted to
RENEW, which has confidentiality agreements with the companies surveyed.
2. On 27th January 2010, after this report had been completed, it was announced that the assets of Artenius UK would be taken over by KP
Chemical Corporation, a UK-based subsidiary of the Korean company Lotte.
2
1 Introduction
RENEW @ CPI was established in 2008 via Regional Development Agency funding
to maximise the economic opportunities being created by the emerging
environmental industries, specifically the renewable energy and environmental
sectors. RENEW’s remit is to identify business opportunities, initiate projects and support both local businesses and inward investors. RENEW provides advice to
businesses, instigates feasibility and viability studies, brokers partnerships and
champions projects.
RENEW has funded this feasibility study, the Wilton Waste Audit (WWA), to assess
the types and quantities of waste (liquid, solid and gaseous) leaving the Wilton
International site. This will support businesses at Wilton.
NEPIC were also keen to support this study, and discussions took place with them
in respect of the scope and purpose of this project. Also relevant to this project is
the North and South Tees Industrial Development Framework(1), which is a
strategic planning investment study for the Tees Valley area and which has been a
source of information for this report.
The purpose of collecting the data is:
• To identify the gaps and the opportunities for a potential waste treatment facility at the Wilton site
• To support all the Wilton companies by identifying any problems in their waste management regimes
• To identify synergies for future developments
The anticipated benefits to companies on the Wilton site are:
• Potential creation of synergies between Wilton companies in relation to waste storage, treatment and collection • Promotion of cost effective waste management treatment and disposal regimes • Raising awareness of opportunities to save money and implement best practice • Promotion of best practice • Identification of potential cost savings through economies of scale
The project team consisted of:
• Anastasios Bereketidis MSc MCIWM AIEMA RENEW Project Manager
• Roger Mallinson CEng FIChemE DRD Senior Consultant
• Clive Whitbourn CEng FIChemE DRD Senior Consultant
• Barry Boden CEng FIChemE DRD Senior Consultant
Since the commissioning of this project there have been announcements of
various plant closures, mothballing, or assets being placed into
administration. Consequently, it has been more difficult to predict with any
great accuracy the future quantities of wastes which will be produced from
Wilton site.
3
2 Project Brief
• To assess the quantities and, where possible, compositions of all waste streams (liquid, solid and gaseous) leaving Wilton site.
• To assess the current arrangements for disposal or storage of all waste streams.
• To assess future opportunities and their economics. • To identify opportunities for a waste treatment option that has a sustainable future.
• To identify possible synergies for future development. • To quantify any energy or heat that might be generated from, or required by, a new waste treatment plant at Wilton.
3 Companies Surveyed
The following companies were surveyed and asked for details of all their waste
streams leaving the Wilton site:
• Air Products
• Artenius
• Croda
• Dow
• Ensus
• GDF Suez UK
• Huntsman
• Invista
• Sabic
• Sembcorp
• UK Wood Recycling Ltd
• Waste Exchange Services
• Wilton Centre
• Site Canteens
In addition, DRD contacted the Environment Agency for IPPC applications in the
public domain, and Northumbrian Water PLC.
Almost all the above companies responded positively. However, during the period
in which this report was prepared plant closures or mothballing were announced at
Croda, Dow, Invista and Artenius and this has had a significant effect upon the quantities of waste being produced.
4 Wilton Site Major Waste Streams
4.1 Liquid Waste
The majority of liquid waste consists of either hazardous chemical waste or aqueous
effluent. Liquid chemical waste from Wilton site totals ~4400tpa. Companies
either try to recover useful product from liquid waste streams or send the material
for incineration. Quantities of liquid waste are summarised in Table 1, which shows
the quantities prior to the plant closures in 2009 and also after the plant closures.
Table 1
Type of Liquid Waste (tpa) Pre Closures Post Closures
Non-hazardous Chemical 90 50
Hazardous Chemical 4684 4374
Sludge 750 750
Oil 46 46
Cooking Oil 1 1
4
4.2 Aqueous Effluent
Aqueous effluent from Invista Nylon and Artenius T8 plants (both currently shut
down and mothballed respectively) and some aqueous effluent from other
plants is pumped to Northumbrian Water’s Bran Sands effluent treatment plant.
Aqueous effluent from other plants, amounting to about 600 tonnes/hour, is
discharged to the Wilton Site Drainage Sewer and then, after consent levels have been checked, into Dabholm Gut and the River Tees.
4.3 Solid Waste
Most companies recycle those components of their solid waste that can readily be
recycled, such as metals, plastics, paper and wood, in order to minimise the
quantity going to landfill. Solid waste to recycle from the plants still operating at
Wilton amounts to ~2600tpa. Solid waste to landfill (non-hazardous chemical
waste, ash and general waste) amounts to ~10ktpa. Quantities of solid waste are
summarised in Table 2.
Table 2
Type of Solid Waste (tpa) Pre Closures Post Closures
Non hazardous Chemical 2694 1794
Hazardous Chemical 435 24
Ash 4552 4552
Mixed Metal 395 215
Ferrous Metal 1351 1238
Non-ferrous Metal 68 60
Plastics 77 77
Wood 940 902
General 3696 3438
Food 5 5
4.4 Gaseous Effluent
Quantitative data on gaseous effluents was more difficult to obtain, but such
effluents consist of three broad types:
• Flue gases from fired heaters • LP steam • Plant vents containing mostly nitrogen It is more appropriate to recover energy from such streams rather than material
and, because of the low pressure of these streams, the energy is best recovered in
situ by the individual companies.
5 Possible Future Opportunities
5.1 Liquid Chemical Waste
Companies either try to recover useful product from liquid waste streams or
send the material for incineration. Currently, short loads of chemical waste
are sent to Ince Marshes at Ellesmere Port for incineration, but some simple
co-ordination would enable companies to contribute to a full load and thus
reduce transport costs and CO2 footprint for their chemical waste.
5
A Waste Incineration Directive (WID)-compliant incinerator at or near the
Wilton site might be used to incinerate the various residue streams and
save transport costs. A WID compliant thermal oxidiser capable of handling
~4,000 tpa of liquid chemical waste and operating on a continuous basis
would cost approximately £2M (Source: Process Combustion Ltd).
A typical plant comprises:-
• thermal oxidiser with waste gas and waste liquid capability • waste heat boiler (fire tube type) • ceramic filter plant to remove particulates and acid gases (uses bicarbonate powder injection)
• 160 kW id fan and motor with variable speed drive • SCR catalytic unit to control NOx • 12 m chimney • structural steelwork, access ladders, platforms, handrails etc. • control system
The client would provide:-
• foundations and building • storage of waste liquid • emissions monitoring equipment and SCADA • planning and permitting applications
There are limitations on the quantities of halogenated compounds and
sodium or potassium salts that can be treated. Assuming a calorific value
for the chemical waste of 40MJ/kg and 8,000 hours operation per year, the
residual heat would produce approximately 6 tph of 10 Barg steam. Based
on a steam value of £16/t this would provide a revenue of £768k/annum.
Additional savings of road transport and incineration costs would provide
additional savings and give a project payback period of 2 – 3 years.
The North and South Tees Industrial Development Framework Report(1) identified
the waste market in the UK as developing quickly as a result of legislative
drivers such as the Waste Incineration Directive. Allied to this is the
concept of industrial symbiosis, where the waste streams from other
processes can be used beneficially by others, in this case for the generation
of steam and potentially power.
5.2 Aqueous Effluent
Access to an aqueous effluent treatment plant could make Wilton more
attractive for new investment. However, process drains and storm water
drains would need to be segregated. Northumbrian Water has potential
spare capacity at Bran Sands for appropriate biologically treatable liquids.
If there was a redundant pipeline under the Tees it might be used as far as
Bran Sands to pipe aqueous effluent for treatment. If T8 does not restart,
could another company make use of the 14” SS pipeline from T8 to Bran
Sands? Invista Nylon has a 14” 304L Class 150 line that took waste water
from Adipic Acid and KA to Bran Sands, and which is now redundant. Each
line could handle ~500m3/hr.
6
5.3 Solid Waste
Currently, most companies on Wilton site undertake limited segregation of
waste in terms of batteries, paper, cardboard etc from their general waste.
Although most companies use Veolia for disposal of solid waste, one
company stated that it could see value in having one contractor to collect all
waste of a particular type from all Wilton site locations, provided that the waste remains segregated. That company’s past experience indicated that
certain contractors re-mixed the segregated waste.
Going one step further, there could be value in having an agent to act on
behalf of all the companies at Wilton with, perhaps, the establishment of a
Waste Segregation Station for the site.
5.4 Waste Heat
Shoreline Polychaete Farms at Ashington, Lynemouth, use low grade waste
heat (30C – 40C) from the Rio Tinto Alcan smelter for ragworm production.
The primary requirements for Shoreline’s aquaculture facility are:
• 2 – 15 hectares land
• 1800 – 2500m3/hour sea water at 20C.
Design Research & Development Company has visited Shoreline who have
expressed an interest in using waste heat for a new aquaculture installation
at Wilton.
6 Other Projects
This assessment of the quantities of waste from Wilton site has indicated
that the total quantities are small, especially after the announcements of the
closure of the Croda, Dow and Invista plants and the mothballing of the Artenius plants. It is therefore worth considering other projects that might
take place at Wilton, and the effect that these might have on the quantities
of waste.
6.1 Anaerobic Digestion with Power Generation
Anaerobic digestion was identified as an opportunity for development in the
North and South Tees Industrial Development Framework(1) Report.
For the immediate future it appears that Northumbrian Water has sufficient
capacity to handle most likely new investments and so an AD plant at Wilton
would seem unnecessary. Any additional AD investment at Wilton would
require the import of suitable waste feedstocks. However, it is understood
that Newcastle University is planning a large AD facility for R&D (Source:
Professor Dermot Roddy at the Third ICIS Bioresources Summit in
Gateshead, 26th November, 2009). Wilton site could be a suitable location
for such a unit.
The authors were asked to consider the viability of an anaerobic digestion
plant at Wilton and a brief overview of anaerobic digestion is as follows:
Almost any organic material can be processed by anaerobic digestion. This
includes biomass materials such as waste paper, food waste, sewage and
7
animal waste. After sorting or screening, the material to be processed is
often shredded to increase the surface area available to microbes in the
digesters and hence increase the speed of digestion. The material is then
fed into an airtight digester, often with extra water added depending on the
digestion process and feedstock.
Advanced waste treatment technologies can produce biogas with ca. 60 mole % CH4 and 40 mole % CO2 with 1-5 % H2. Operating efficiency is such
that 60 – 80 % of volatile matter is transformed into biogas. Unfortunately,
the process requires a residence time of 15 – 30 days, which leads to rather
large plants. The cost of producing anaerobic biogas is £0.12 - £0.18/kWh
cf purchase price of natural gas, ca. £0.02/kWh.
An anaerobic digestion plant using 45ktpa feed and generating 2MW
electricity would cost ~£12m (Source: Confidential). At a standard
electricity price of £60/MWh, this will generate £60 x 2 x 8000 = £960kpa.
If we assume double ROCs for generation from a renewable source then it
will give £130 x 2 x 8000 = £2mpa, which is still a 6 year pay back!
However, if the feedstock is supermarket food waste and the supermarkets
pay for the waste to be treated then a fee of £44/tes would generate a
further £2mpa and halve the pay back to 3 years.
Digesting 1 tonne of food waste can generate about 300 kWh of energy.
(Source: NNFCC) So, 45kt food waste generates 13500MWh of energy, or
1.7MW over 8000 hours, which is in line with 2MW quoted above.
6.2 Tyre Pyrolysis
The possibility of locating a tyre pyrolysis plant at Wilton has been
rumoured in the past with the interested party being METSO Minerals
PYReco Limited. See Ref.1.
A typical tyre pyrolysis plant would handle ~170 tes/day shredded tyres and
produce 55 tes/day off-gas. The off-gas composition is very rich in
hydrocarbons and also contains sulphur compounds. It is not suitable for
discharge to atmosphere, but could be used as a fuel elsewhere on Wilton
site.
Off-gas from tyre pyrolysis contains little carbon monoxide (CO) or
hydrogen, but could be put through a high temperature partial oxidation to
convert the hydrocarbons to hydrogen and CO. After removal of the sulphur
compounds it could then be suitable for the Fischer Tropsch process, which
is a catalysed chemical reaction in which CO and hydrogen are converted
into liquid hydrocarbons, producing a synthetic petroleum substitute for use
as synthetic lubrication oil or as synthetic fuel.
6.3 Gasification of Municipal Waste or Biomass
Gasification processes such as the MME Technology use rapeseed pressings,
palm pressing, foodwaste, sewage sludge (human or animal), flourmill
wastes, brewery wastes and AD residues as their feed stock. The products
from the reaction are gas, biodiesel, carbon black and water. Approximate
yields that are claimed are as follows:-
Synthetic Diesel ~30 to 42%
8
Gas ~ 25%
Carbon black ~ 13%
Water ~22%
Any investment in gasification plant at Wilton would require the import of
suitable waste feedstocks. However, it is understood that a plant using
MME technology will be built in the North East in the near future (Source: David Atkinson, MD, MME-UK Ltd, at the Third ICIS Bioresources Summit in
Gateshead, 26th November, 2009).
The North and South Tees Industrial Development Framework(1) Report indicated
that sites with good infrastructure connections would be particularly
attractive
for companies looking to build merchant gasification or autoclave facilities.
6.4 Paper Mill
The possibility of locating a paper mill at Wilton has been rumoured in the
past. The interested party is Ecco News Print Limited. See Ref.1. A typical
paper mill producing 200tpd air-dried pulp (ADP) would generate 160 –
2000 m3/hr waste water. The waste water is high in BOD, COD, suspended
solids, and chlorinated organic compounds, and is a suitable feed for an
anaerobic digestion plant such as Bran Sands.
6.5 Sonhoe - Heavy Crude Upgrader Project
This proposed new facility was referred to in the North and South Tees
Industrial Development Framework(1) report and would process 200,000 barrels
a day of heavy crude oil into high quality, low sulphur diesel, petrochemical
feedstock naphtha and kerosene for use in the UK or for export. The plant
also incorporates the production of hydrogen and would be one of the largest hydrogen producing plants in Europe. At the time of the proposal
this was estimated to be a £2bn investment for Wilton site and would have
a significant impact on the site effluent and waste streams. However, the
current status of the project is no longer clear.
7 Conclusions
At the time of writing, the future of the Artenius T8 and Melinar plants, and
the Dow ethylene oxide and Croda EOD plants was unclear. Whether these
plants close or restart will have a significant effect upon the quantities of
waste leaving the site, and on the opportunities for synergies. However,
aqueous effluent from Wilton site has reduced because of plant closures and
Northumbrian Water currently has spare capacity at Bran Sands.
Possible opportunities for investment on Wilton site that have been
identified are summarised in Table 3. In general, the investment costs are
high, but the technical risks of the projects would be low, although
timescales tend to be long. Any investment in waste treatment technology
at Wilton would almost certainly require the import of waste feedstock. A
central system for the disposal of solid waste could provide synergies that
would benefit the companies on Wilton site.
9
Table 3
Potential Projects for Wilton Site
Project
Investment Technical
Risk
Required
Timescale
Comments
Thermal
Oxidiser
High Low/Medium Medium Payback 2–3
years.
Aqueous Effluent
Treatment
High Low Medium/Long Spare capacity
available at
NWL Bran
Sands.
Solid Waste
Central
Collection
Low/Medium Low Short
Aquaculture Medium/High Low Medium/Long Requires land,
sea water and
waste heat.
Anaerobic
Digestion with
Power
Generation
High Low/Medium Long R&D facility
planned by
Newcastle
University.
Tyre Pyrolysis High Low Long Import of
tyres
required.
Gasification of
Municipal
Waste/Biomas
s
Medium/High Low/Medium Long Gas can be
used for
chemicals
manufacture,
biodiesel
and/or power generation.
Paper Mill High Low Medium/Long
Heavy Crude
Upgrader
High Medium Long Import of
heavy crude
required.
8 Dissemination Event
The results of the project were disseminated to all companies that had
contributed to the project at a meeting held in the Wilton Centre on 25th
February 2010. At that meeting the following possible future projects were
identified:
• Use of waste heat at ~40C for drying. • Opportunities for pre-treatment of waste streams going to Bran Sands.
• Cultivation of algae and incineration as a biofuel. • Treatment of waste oils and solvents.
10
9 References
(1) North & South Tees Industrial Development Framework Report - Tees
Valley Joint Strategy Unit; FSE97402A.2170; November 2009.