BP.080 - Purchasing Process
Document Control
Change Record
4
Date Author Version Change Reference
12-Jan-2013 Ajay Singh 0.1 Base Document
22-Mar-2013 Ajay Singh 1.0 Final Version
Reviewers
Name Position
Prithwish Chatterjee Wipro Project Manager
Swarup Ghosal Chaudhary Wipro Program Manager
Approver
Name Position Signature
Sh. Kamal Kant Kaushaik Manager - Projects
Sh. Kumar Bachchan Sr. Manager - DNM
Sh. A K Sablania GGM DNM
Sh. Ashutosh Vasant GM - Projects
Sh. Puran Singh GGM - Infrastructure
Sh. Suresh Kumar GGM NTP
Distribution
Copy No. Name Location
1 RailTel Project Parivartan Steering Committee Gurgaon2 RailTel Project Parivartan Core Working Group Gurgaon3 RailTel Project Parivartan Regional CWG New Delhi/Mumbai/Secunderabad/Kolkata4 Wipro Onsite Team Gurgaon5 Wipro Technical Team Gurgaon
Note to Holders:
If you receive an electronic copy of this document and print it out, please write your name on the equivalent of the cover
page, for document control purposes.
If you receive a hard copy of this document, please write your name on the front cover, for document control purposes.
-
7/27/2019 Wipro BP080 Purchasing V1 0
3/125
BP.080 - Purchasing Process
Contents
Document Control ..................................................................................................................... ii
Introduction ...................................................................................................................... ......... 1
About this Document.......................................................................................................... 1How this document is organized ............................................. ........................................... 2Generic Assumptions .......................................................................................................... 3
Overall Project & Procurement Flow ......................................................... ................................ 4
PO 01 - On Line Purchase Indent Process .................................................................................. 6PO 02 - Purchase Indent Process ............................................................................................... 9
PO 03 - Indent Preparation & Approval ................................................................................... 11
PO 04 - Overall Procurement Tender Process (Supply Item) ................................................... 13
PO 05 - Overall Project Tender Process (Works/Service/Item) ............................................... 17
PO 06 - Open/Global Tender Process Single Packet ............................... .............................. 21
PO 07 - Open/Global Tender Process Two Packet ......................................................... ....... 24
PO 08 - Limited Tender Process ............................................................................................... 27
PO 09 - Single Tender Process ................................................................................................. 30
PO 10 - Dispensation of Tender Process for Material .............................................................. 33
PO 11 - Dispensation of Tender Process for Works Contract & Execution .............................. 35
PO 12 - Procurement Process for Material (Supply Item) ....................................................... 38
PO 13 - Procurement Process for Works Contract (Supply, Installation & Commissioning) ... 41
PO 14 - Procurement Process for Execution .......................................................... .................. 44
PO 15 - Procurement Process for AMC (Equipments, Sections, Miscellaneous) ..................... 47
PO 16 - Procurement Process for Inspection (Material, Works Contract & Execution) .......... 49
PO 17 - Imprest/Advance Procurement Process .............................................................. ....... 52
PO 18 - Bank Guarantee Process ............................................................................................. 54
PO 19 - Site Readiness Process-For Material and Service ........................................................ 56
PO 20 - Inspection Process....................................................................................................... 59
PO 21 - Standard Purchase Order Process ............................................................. .................. 62
PO 22- Rate Contract for Material (Supply Item) .............................................................. ....... 65
PO 23 - Rate Contract Releases of Material (Sub PO) .............................................................. 68
PO 24 - Rate Contract for Service & Works Contract ........................................................ ....... 71
PO 25 - Rate Contract Releases of Service & Works Contract (Sub PO) ................ .................. 75
PO 26 - Advance Purchase Order ............................................................... .............................. 78
PO 27 - Advance Purchase Order Release (Sub PO) ................................................................ 80
-
7/27/2019 Wipro BP080 Purchasing V1 0
4/125
BP.080 - Purchasing Process
PO 28 - Global Purchase Agreement........................................................................................ 83
PO 29 - Maintain Purchase Order Process (Variation/Enhancement in Quantities) ............... 86
PO 30 - RFI- Request for Information (Tender Process) ........................................................... 89
PO 31 - Request for Quotation and Quotations (Tender Process)........................................... 92
PO 32 - Supplier Registration (iSupplier Module) .................................................................... 96
PO 33 PO/LOA Acknowledgement (iSupplier Module) ......................................................... 98
PO 34 - ASN Creation and Online Submission (iSupplier Module) ......................................... 101
PO 35 - Contracting Process (Procurement Contract) ........................................... ................ 104
PO 36 - Contracting Amendment Process (Procurement Contract) ...................................... 107
PO 37 - Approved Supplier List (ASL) ..................................................................................... 110
PO 38 Spot Purchase Process .................................................................. ............................ 113
PO 39 Inspection Waiver Process ........................... ............................................................ 116
PO 40 Delivery Period/Date of Completion - Extension ................................................ ..... 119
Open and Closed Issues for this Deliverable .......................................................... ................ 121
Open Issues..................................................................................................................... 121Closed Issues ................................................................................................................... 121
-
7/27/2019 Wipro BP080 Purchasing V1 0
5/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Introduction
About this Document
RAILTEL has appointed Wipro Limited to implement Oracle E-Business Suite. The implementation spans
Financials and Supply Chain Management processes. This document describes the ProcurementProcess for RAILTEL.
The project is divided into Five Stages viz. Plan, Analyse, Design, Develop and Go-Live. The Analyse
Stage covers identifying the gaps in the As-Is processes and re-designing them in order to adopt
leading processes as also to harness the capability of the chosen technology.
This document contains the RAILTEL Procurement process flow that would be configured onto
the Oracle E-Business Suite.
-
7/27/2019 Wipro BP080 Purchasing V1 0
6/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
How this document is organized
This document forms deliverable of the operation analysis phase of the ERP
implementation project for RailTel. The purpose of this document is to compile a
comprehensive list of requirements against which to map Application features. The
scenarios listed in the subsequent sections are reusable templates and are created once
for each business process.
Each of the following sections consists of the following sub sections:
Assumptions
Any assumptions that are specific to the process being detailed are recorded in this
sub section.
Process Scenario
The Event initiates the corresponding process.
Process Solution:
1. Complete process flow2. Process Id #: Unique number for the sub-processes within the main
process.
Description
1. Process Title & Description: The bold letters gives the process titlefollowed by the detailed description of the process in normal font.
2. Key Requirements from the above process
Requirement Fulfillment using ERP Approach
1. Solution Type & Description: Used to designate type of solution. Thetypes mentioned here are Screen, Manual and System. The Screen refers
to the type where the data is to be entered in the screen or can be viewed
in the screen. Manual type is the manual way of doing the process whetherthe user would be performing the process in the system or otherwise. The
System type of solution is referred to when the system performs the step
through automation or sub-automation. The following keys can be used for
the process in the system.
i.S Standardii.W - Workaroundiii.C Extension/Customization
2. Navigation Path: The path to navigate to the relevant functionality inApplications. The following acronyms have been used for navigation type:
i.(T) Tabii.(B) Buttoniii.(CB) Check Boxiv.(F) Field
3. Impact analysisProcess Improvements
Quality & Customer Service
-
7/27/2019 Wipro BP080 Purchasing V1 0
7/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Leading Practices
Note: The texts in grey shade are optional activities.
Generic Assumptions
Any additional information captured in ERP through external systems will be highly dependent
on the external systems. Wipro will not be responsible for the functioning or the
implementation of the external systems.
Customizations identified in the requirement definition document will be developed subject
to the scope defined in the approved project charter.
-
7/27/2019 Wipro BP080 Purchasing V1 0
8/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Overall Project & Procurement Flow
-
7/27/2019 Wipro BP080 Purchasing V1 0
9/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Railtel End to End Project Flow and Integration with other Modules
General Ledger Payables Fixed Assets Receivables
Finance
Projects
Procurement
Marketing&
Sales
Business
Business Plan
General Ledger
Budget Definition as per theBusiness Plan
Transaction posted form other
Modules
Sources of the Projects
Railways Pink Book
Railtel Law BookOthers Marketing
START
ProjectCreation &
Approval
Project Budget
Creation,Revision &
Approval
Workplan Creation,
Versioning andProgress
Management
Project StatusInquiry
Project AssetCreation &
Transfer to FA
Transfer toInventory/
ProjectVice Versa
Inspection &Recieving
PurchaseOrders/APO/Rate Contracts
Commercial &TechnicalAnalysis
TenderCreation &
Floating
PurchaseIndent/
Creation &Approval
Invoicing relatedto Project in
Payables
Asset Posting inFixed Assets
Invoice to theCustomer inRecievables
Note:The Business plan is conceptualized by the RailtelDirectorsBusiness Plan prepared by Railtel Team / ConsultantsProjects are created as per the Business plan decided.
Project Closure
END
Demand NoteCreation & Customer
Acceptance
Sales OrderBooking
Contract Creation Billing
Note :The Approval related to the projects is further elaborated in the next flow.The Project Planning team will do the estimation and enter the budget in thesystem.The details estimate will be done and Indent / Requisitions will be raised withreference to the project.Detail processes related to the project are further elaborated in the document.
ManualERP
-
7/27/2019 Wipro BP080 Purchasing V1 0
10/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 01 - On Line Purchase Indent Process
-
7/27/2019 Wipro BP080 Purchasing V1 0
11/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
On Line Purchase Indent Process
AllDepartments
Log in to I ProcurementEnter indent online usingweb forms and catalogs
Find Items Add Items & Quantity
Edit Shopping Cart
Add Items , Quantityand delivery location
detail
Review/ModifyIndent
Submit Indent
Proceed to Check Out
Proceed to Check Out
Check OutWorkflow basedpurchase indent
approval
ProcurementProcessPO12
Suppliernotified anddeliver the
goods
Record receiptin to the web
End
ERP Manual Email
Start
No
Yes
Finance
FinanceVetting
O & Mactivities
Projects(Railway/
RailTel/LMCetc)
Others(General
Admin etc.)
RAILTEL Process: On Line Purchase Indent Process Business Function: RAILTEL Project Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
12/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 01 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 01 Description: This step explains the On Line Purchase Indent Process.
Event Description: This process is triggered to raise the online purchase indent.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # DescriptionMode
RequirementFulfillment using ERP
Approach (Y/N)
Procurement POM_PO_PI_1 PO 01.01 On line Indent will be created using web forms and catalogs. System Y
Procurement POM_PO_PI_1 PO 01.02 Find Items online and add quantity and delivery details. System Y
Procurement POM_PO_PI_1 PO 01.03 Edit, modify and review indent online. System Y
Procurement POM_PO_PI_1 PO 01.04 Online Indent will be submitted. System Y
Procurement POM_PO_PI_1 PO 01.05 Purchase Indent will be approved as per defined approval hierarchy. System Y
Procurement POM_PO_PI_1 PO 01.06 After approval of Online Indent, Procurement process is initiated. System Y
Procurement POM_PO_PI_1 PO 01.07 Supplier notified and delivers the goods as required. Receipt detail will be recorded. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
13/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 02 - Purchase Indent Process
Purchase Indent Process
AllDepartments
ERP Manual Email
Start
User to enter the
IndentHeader details
Enter the Linedetails Item code,
Qty, Need by date,Etc
Select theOrganization,
Location andSupplier(Optional)
Save the
Document andsubmit for
Approval
Purchase
IndentApproved
Automaticnotification to
Requestor
Yes
Approved Purchase
Indent becomes theinput for Purchase
Order to be created bythe Purchasing
department
ProcurementProcess
PO12
End
Capture the ChargeAccount, If any
consumablesitems(without Item Code)
No
Finance
Finance
Vetting
O & M
activities
Projects(Railway/RailTel/LMC
etc)
Others
(GeneralAdmin etc.)
-
7/27/2019 Wipro BP080 Purchasing V1 0
14/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Purchase Indent Process Business Function: RAILTEL Project Date: 12-01-2013
Control Number: PO 02 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 02 Description: This step explains the Purchase Indent Process.
Event Description: This process is triggered to raise the purchase indent.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Procurement POM_PO_PI_1 PO 02.01 User will create the Indent by mentioning the PR headers details like the PR type ,
Description
System Y
Procurement POM_PO_PI_1 PO 02.02 Create Purchase Indent with information like item or description, quantity and
(Approx) purchase price. When item not available the user should choose
purchasing category and write a description.
System Y
Procurement POM_PO_PI_1 PO 02.03 Indent preparers should select the inventory organization name, location and
Supplier details (options).
System Y
Procurement POM_PO_PI_1 PO 02.04 Select the Charge Account Number in case of Expense or Consumables items. System Y
Procurement POM_PO_PI_1 PO 02.05 Generate a Purchase Indent with automatic document number. System Y
Procurement POM_PO_PI_1 PO 02.06 Submit the purchase Indent for approval through the delegation of authority. System Y
Procurement POM_PO_PI_1 PO 02.07 Requester will not be able to approve Indent. Indent approval will be a workflow
based process based on approval limits. Approved Purchase Indent is the input for
Purchase Order Creation.
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
15/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 03 - Indent Preparation & Approval
Indent Preparation & Approval
Project&Proc
urement
ERP Manual
Start
Indent/
Estimates
raised at
territory level
Submit for
approval &
Finance
Concurrence
Finance
Approval as
per SOP
Approval from
TM as per
SOP
Yes
More Info
MoreInfo
No
RO collates all Indent/
Estimates of territory level
and prepares consolidated
proposal
Or Indent/Estimate raised
at regional level
Yes
Finance
concurrence
as per SOP
Submit for
approval &
Finance
Concurrence
Approval from
RGM as per
SOP
Yes
More Info
No
More Info
CO collates all Indent/
Estimates of regional level
and prepares consolidated
proposal
Or Indent/Estimate raised
at corporate level
Yes
Submit for
approval &
Finance
Concurrence
Corporate
finance
concurrence
as per SOP
Approval from
MD/Director as
per SOP
End
Yes
More Info
oN
More Info
Tender
Process at
Territory Level
If applicable
PO04-PO05
Tender
Process at
Regional Level
PO04-PO05
Territory Level Regional Level Corporate Level
Tender Process
at Corporate
Level
PO04-PO05
-
7/27/2019 Wipro BP080 Purchasing V1 0
16/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Indent Preparation & Approval Business Function: RAILTEL Project Date: 12-01-2013
Control Number: PO 03 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 03 Description: This step explains the Indent preparation and approval.
Event Description: This process is triggered whenever an Indent is prepared and approved.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Procurement POM_RP_EP_2 PO 03.01 Indent/Estimates are raised at territory level System Y
Procurement POM_RP_EP_2 PO 03.02 Indent is submitted for approval System Y
Procurement POM_RP_EP_2 PO 03.03 Approval is done as per SOP System Y
Procurement POM_RP_EP_2 PO 03.04 Final approval is done from TM as per SOP System Y
Procurement POM_RP_EP_2 PO 03.05 RO collates all indent/estimates of territory level and prepares consolidated
proposal then it is put up for approval
System Y
Procurement POM_RP_EP_2 PO 03.06 Approval from finance for concurrence is done as per SOP System Y
Procurement POM_RP_EP_2 PO 03.07 Final approval is done from RGM as per SOP System Y
Procurement POM_RP_EP_2 PO 03.08 CO collates all indent/estimates of regional level and prepares consolidated proposal
then it is put up for approval
System Y
Procurement POM_RP_EP_2 PO 03.09 Approval from finance for concurrence is done as per SOP System Y
Procurement POM_RP_EP_2 PO 03.10 Final approval is done from CMD/Director as per SOP System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
17/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 04 - Overall Procurement Tender Process (Supply Item)
-
7/27/2019 Wipro BP080 Purchasing V1 0
18/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Start
Procurement
Finance
Business Plan
Railways OFCSection Works
Other Railways
Project
Other CustomerProject
O&M Activities
Govt. Projects
Global Tender
Open Tender
Limited Tender
Special LimitedTender
Single Tender
Quotation
Tender DocumentFloated
Receive
response frombidder
Tender document
is opened bynominated TOC
Comparative sheet
and Briefing noteare prepared by
executive
B
C
Vetted
comparative sheetand Briefing note
put up to TC
TC prepares final
observation
Comparative sheet & final
minutes sent to TAA forapproval
Successful bidderdeposit various
documents like PBG,Security Deposit
EMD handed over
to finance
Comparative sheet &
Briefing note vettedby financeB C
Purchase Indent/Estimates raised at
Territory Level.(Project
budget will be revised if
indent estimate increases
more than project budget)
Purchase Indent/Estimates raised
at regional Level
RO collates all
requisitions fromterritories & Prepares
consolidatedproposal
CO collates allrequisitions from
regions & Preparesconsolidated
proposal
EMD Return tounsuccessful
bidder & EMD
returns tosuccessful bidder
or adjusted withInvoice
Purchase Order
Issued tosuccessful bidder.
Tender estimate
will be revised ifPO estimate
increases morethan tender
estimate.
Tender processing
officer isnominated
ProjectBudgeting
ProcessPRJ05
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting & approval as per
SOP along with PACissued by Region/
Corporate and approvedby Director
A
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting
A
Prebid meeting and
change/modificationTender document
accordingly
Acceptance from
Supplier
Supplier
RegistrationProcess
PO32
TC nomination asper SOP
Purchase Indent
raised at corporatelevel
Overall Procurement Tender Process ERP Manual Email
Discharge
Counter offer/LOI
Acceptance
NIT Published in
News Paper(Online)
Negotiation maydone with
supplier
Approved Supplier
List or Freshapproved supplier
list via approvalPO37
End
Non-Acceptance
NIT and Tender
Document
uploaded on
website
PR Process
RAILTEL Process: Overall Procurement Tender Process Business Function: RAILTEL Tender Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
19/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 04 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 04 Description: This step explains the Overall Procurement Tender process for material.
Event Description: This process is triggered Whenever a Tender is created for material.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERPApproach (Y/N)
Requirement
Generation
POM_TP_
RG_1
PO 04.1 Requirement for floating the tender is triggered from the various sources.
Business Plan (Long Term & Short Term)
Railway Project OFC section works
Other Railway Projects
Other Customer projects
O&M activities
Customer Lead
Government Project
Manual Y
Indent/Estimates POM_RP_
EP_2
PO 04.2 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting.
System Y
Tender Document POM_TP_
TD_2
PO 04.3 Tender Processing officer is nominated.
Tender are of various types, open tender, limited tender, special limited tender,
Global tender, single tender and quotation. Respective tender document is created.
System Y
Tender Document
Execution
POM_TP_
TE_3
PO 04.4 As per SOP and schedule of work, Tender process is followed and floated;
Simultaneously It is published in news paper and on RailTel website also.
As required tender is floated to selected supplier from approved supplier
list.
Prebid meeting is done and tender document is changed accordingly
Response is received from various vendors.
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
20/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Tender document is opened by nominated TOC
Comparative sheet and Briefing note are prepared by executive
EMD is hand over to finance and Comparative sheet and briefing note are
vetted by finance.
TC nomination is done.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
Purchase Order is issued to successful bidder and acknowledgment is
received.
Successful bidder deposit various document like PBG, Security deposit.
Simultaneously EMD is returned to unsuccessful bidder.
-
7/27/2019 Wipro BP080 Purchasing V1 0
21/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 05 - Overall Project Tender Process (Works/Service/Item)
-
7/27/2019 Wipro BP080 Purchasing V1 0
22/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Start
Project
Finance
Business Plan
Railways OFC
Section Works
Other Railways
Project
Other CustomerProject
O&M Activities
Govt. Projects
Global Tender
Open Tender
Limited Tender
Special LimitedTender
Single Tender
Quotation
Tender DocumentFloated
Receive
response frombidder
Tender document
is opened bynominated TOC
Comparative sheet
and Briefing noteare prepared by
executive
B
C
Vettedcomparative sheet
and Briefing note
put up to TC
TC prepares finalobservation
Comparative sheet & final
minutes sent to TAA for
approval
Successful bidder
deposit variousdocuments like PBG,
Security Deposit
EMD handed over
to finance
Comparative sheet &Briefing note vetted
by financeB C
Purchase Indent/Estimates raised at
Territory Level.(Project
budget will be revised ifindent estimate
increases more thanproject budget)
Purchase Indent/
Estimates raised
at regional Level
RO collates all
requisitions from
territories & Preparesconsolidated
proposal
CO collates all
requisitions fromregions & Prepares
consolidated
proposal
EMD Return to
unsuccessfulbidder & EMD
returns to
successful bidderor adjusted with
Invoice
LOA Issued tosuccessful bidder.
Tender estimate
will be revised ifLOA estimate
increases more
than tenderestimate.
Tender processing
officer is
nominated
Project
BudgetingProcess
PRJ05
Tender cost Estimation
prepared and Put up to
Finance for FinanceVetting & approval as per
SOP along with PAC
issued by Region/Corporate and approved
by Director
A
Tender cost Estimation
prepared and Put up to
Finance for FinanceVetting
A
Prebid meeting andchange/modification
Tender document
accordingly
Acceptance fromSupplier
Supplier
RegistrationProcess
PO32
TC nomination as
per SOP
Purchase Indentraised at corporate
level
Overall Project Tender Process ERP Manual Email
Discharge
Counter offer/LOI
Acceptance
NIT Published in
News Paper
(Online)
Negotiation may
done with
supplier
Approved Supplier
List or Freshapproved supplier
list via approval
PO37
End
Non-Acceptance
NIT and Tender
Document
uploaded on
website
PR Process
RAILTEL Process: Overall Project Tender Process Business Function: RAILTEL Tender Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
23/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 05 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 05 Description: This step explains the Overall Project Tender process for Service and Work Contract.
Event Description: This process is triggered Whenever a Tender is created for service and works contract.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERPApproach (Y/N)
Requirement
Generation
POM_TP_
RG_1
PO 05.1 Requirement for floating the tender is triggered from the various sources.
Business Plan (Long Term & Short Term)
Railway Project OFC section works
Other Railway Projects
Other Customer projects
O&M activities
Customer Lead
Government Project
Manual Y
Indent/Estimates POM_RP_
EP_2
PO 05.2 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting.
System Y
Tender Document POM_TP_
TD_2
PO 05.3 Tender Processing officer is nominated.
Tender are of various types, open tender, limited tender, special limited tender,
Global tender, single tender and quotation. Respective tender document is created.
System Y
Tender Document
Execution
POM_TP_
TE_3
PO 05.4 As per SOP and schedule of work, Tender process is followed and floated;
Simultaneously It is published in news paper and on RailTel website also.
As required tender is floated to selected supplier from approved supplier
list.
Prebid meeting is done and tender document is changed accordingly
Response is received from various vendors.
Tender document is opened by nominated TOC
Comparative sheet and Briefing note are prepared by executive
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
24/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
EMD is hand over to finance and Comparative sheet and briefing note are
vetted by finance.
TC nomination is done.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
LOA is issued to successful bidder and acknowledgment is received.
Successful bidder deposit various document like PBG, Security deposit.
Simultaneously EMD is returned to unsuccessful bidder.
-
7/27/2019 Wipro BP080 Purchasing V1 0
25/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 06 - Open/Global Tender Process Single Packet
Start
Project&Procurement
Finance
Open/Global
Tender documentfloated
Receiveresponse from
bidder
Tender document
is opened bynominated TOC
Comparative sheetand Briefing note
are prepared byexecutive
B
C
Vettedcomparative sheetand Briefing note
put up to TC
TC prepares finalobservation
Comparative sheet & final
minutes sent to TAA forapproval
Successful bidder
deposit variousdocuments like PBG,
Security Deposit
EMD handed over
to finance
Comparative sheet &
Briefing note vettedby financeB C
Purchase Indent/Estimates raised at
Territory Level.(Projectbudget will be revised if
indent estimate increasesmore than project
budget)
Purchase Indent/Estimates raised
at regional Level
RO collates allrequisitions from
territories & Prepares
consolidated
proposal
CO collates allrequisitions from
regions & Preparesconsolidated
proposal
EMD Return tounsuccessfulbidder & EMD
returns tosuccessful bidder
or adjusted withInvoice
Purchase Order/LOAIssued to successful
bidder.
Tender estimate will berevised if LOA/PO
estimate increases morethan tender estimate.
Tender processingofficer is
nominated
ProjectBudgeting
ProcessPRJ05
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting & approval as per
SOP
A
Tender cost Estimationprepared and Put up to
Finance for Finance
Vetting
A
Acceptance fromSupplier
SupplierRegistration
ProcessPO32
End
TC nomination asper SOP
Purchase Indent
raised at corporatelevel
Open/Global Tender Process Single Packet ERP Manual Email
Discharge
Counter offer/LOI
NIT Published inNews Paper
(Online)
Negotiation maydone withsupplier
AcceptanceNon-Acceptance
NIT and Tender
Document
uploaded on
website
PR Process
-
7/27/2019 Wipro BP080 Purchasing V1 0
26/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Open/Global Tender Process
Single Packet
Business Function: RAILTEL Tender Date: 12-01-2013
Control Number: PO 06 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 06 Description: This step explains the Open/Global Tender process for Single Packet.
Event Description: This process is triggered Whenever an Open Tender is created.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Indent/Estimates POM_RP_
EP_2
PO 06.1 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting.
Tender Document POM_TP_
TD_2
PO 06.2 Tender Processing officer is nominated for Open/Global Tender Single Packet. System Y
Tender Document
Execution
POM_TP_
TE_3
PO 06.3 As per SOP and schedule of work, Tender process is followed and floated;
Simultaneously It is published in news paper and on RailTel website also.
Response is received from various vendors.
Tender document is opened by nominated TOC
Comparative sheet and Briefing note are prepared by executive
EMD is hand over to finance and Comparative sheet and briefing note arevetted by finance.
TC nomination is done.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
PO/LOA is issued to successful bidder and acknowledgment is received.
Successful bidder deposit various document like PBG, Security deposit.
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
27/125
-
7/27/2019 Wipro BP080 Purchasing V1 0
28/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 07 - Open/Global Tender Process Two Packet
Start
Project&Procurement
Finance
Open/Global
Tender documentfloated
Receiveresponse from
bidder
Tenderdocument(Technical)
is opened bynominated TOC
Briefing note are
prepared byexecutive
B
C
Vetted Briefingnote put up to TC
TC prepares final
observation
Final minutes sent to TAA for
approval
EMD handed over
to finance
Comparative sheet &
Briefing note vettedby financeB C
Purchase Indent/Estimates raised at
Territory Level.(Projectbudget will be revised if
indent estimateincreases more than
project budget)
Purchase Indent/Estimates raised
at regional Level
RO collates allrequisitions from
territories & Prepares
consolidated
proposal
CO collates allrequisitions from
regions & Preparesconsolidated
proposal
Tender processingofficer is
nominated
ProjectBudgeting
ProcessPRJ05
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting and approval as
per SOP
A
Tender cost Estimationprepared and Put up to
Finance for Finance
Vetting
A
TC nomination asper SOP
Purchase Indent
raised at corporatelevel
Open/Global Tender Process Two Packet ERP Manual Email
NIT Published inNews Paper
(Online)
Prebid Meeting &Change/Modify
Tender document
Prebid queriesPublish on
Website
Price bid kept in
seal packet withexecutive along
with seal of RCIL
and sign. of TOCand all bidders
EMD and
Unopened Pricebid returns to
unsuccessfulbidders
Price TC openedby nominated
TOC
Notification to allsuccessful bidder
of Price bid
Comparative sheet
are prepared byexecutive
C
B
Vettedcomparative sheet
put up to TC
TC prepares finalobservation
Comparative sheet & final
minutes sent to TAA forapproval
Successful bidder
deposit variousdocuments like PBG,
Security Deposit
EMD Return to
unsuccessfulbidder & EMD
returns tosuccessful bidder
or adjusted withInvoice
Purchase Order/LOA
Issued to successfulbidder.
Tender estimate will berevised if LOA/PO
estimate increases morethan tender estimate.
Acceptance fromSupplier
SupplierRegistration
ProcessPO32
Discharge
Counter Offer/LOI
Negotiation may
done withsupplier
End
AcceptanceNon-Acceptance
NIT and Tender
Documentuploaded on
website
PR Process
-
7/27/2019 Wipro BP080 Purchasing V1 0
29/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Open/Global Tender Process Two
Packet
Business Function: RAILTEL Tender Date: 12-01-2013
Control Number: PO 07 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 07 Description: This step explains the Open/Global Tender process for Two Packet.
Event Description: This process is triggered Whenever an Open Tender is created.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Indent/Estimates POM_RP_
EP_2
PO 07.1 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting.
Manual N
Tender Document POM_TP_
TD_2
PO 07.2 Tender Processing officer is nominated for Open/Global Tender Two Packet. System Y
Tender Document
Execution
POM_TP_
TE_3
PO 07.4 As per SOP and schedule of work, Tender process is followed and floated;
Simultaneously It is published in news paper and on RailTel website also.
Prebid meeting is done and tender document is changed /modified
accordingly. Prebid queries are published on website also.
Response is received from various vendors.
Tender document (Technical) is opened by nominated TOCPrice bid kept in seal packet with executive along with seal of RCIL and sign.
of TOC and all bidders
Briefing note is prepared by executive.
EMD is hand over to finance and briefing note is vetted by finance.
TC nomination is done.
Vetted Briefing note put up to TC and TC prepares the technical
observation.
Technical minutes sent to competent authority for approval.
EMD and unopened price bid returned to unsuccessful bidder
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
30/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Price TC opened by nominated TOC
Notification is sent to all successful bidders of price bid for opening.
Comparative sheet and Briefing note are prepared by executive
Comparative sheet and briefing note are vetted by finance.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
PO/LOA is issued to successful bidder and acknowledgment is received.
Successful bidder deposit various document like PBG, Security deposit.
Simultaneously EMD is returned to unsuccessful bidders.
-
7/27/2019 Wipro BP080 Purchasing V1 0
31/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 08 - Limited Tender Process
Start
Project&Procurement
Finance
Limited Tenderfloated to selected
vendor
Receiveresponse from
bidder
Tender documentis opened by
nominated TOC
Comparative sheetand Briefing noteare prepared by
executive
B
C
Vetted
comparative sheetand Briefing note
put up to TC
TC prepares finalobservation
Comparative sheet & finalminutes sent to TAA for
approval
Successful bidderdeposit various
documents like PBG,Security Deposit
EMD handed over
to finance
Comparative sheet &
Briefing note vettedby financeB C
Purchase Indent/
Estimates raised at
Territory Level.(Projectbudget will be revised if
indent estimateincreases more than
project budget)
Purchase Indent/
Estimates raisedat regional Level
RO collates allrequisitions from
territories & Preparesconsolidated
proposal
CO collates all
requisitions fromregions & Prepares
consolidated
proposal
EMD Return tounsuccessful
bidder & EMDreturns to
successful bidder
or adjusted withInvoice
Purchase Order/LOA Issued to
successful bidder.Tender estimate willbe revised if LOA/
PO estimate
increases more thantender estimate.
Tender processingofficer is
nominated
ProjectBudgeting
ProcessPRJ05
Tender cost Estimation
prepared and Put up toFinance for Finance
Vetting & approval as per
SOP
A
Tender cost Estimationprepared and Put up to
Finance for Finance
Vetting
A
Acceptance fromSupplier
Supplier
RegistrationProcessPO32
End
TC nomination asper SOP
Purchase Indentraised at corporate
level
Limited Tender ERP Manual Email
Discharge
Counter offer/LOI
Negotiation maydone with
supplier
ApprovedSupplier List
PO37
Fresh approvedsupplier list via
approval
Prebid Meeting &
Change/Modify
Tender document
Non-AcceptanceAcceptance
NIT and Tender
Documentuploaded on
website
PR Process
-
7/27/2019 Wipro BP080 Purchasing V1 0
32/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Limited Tender Process Business Function: RAILTEL Tender Date: 12-01-2013
Control Number: PO 08 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 08 Description: This step explains the Limited Tender process.
Event Description: This process is triggered Whenever a Limited Tender is created.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # DescriptionMode
RequirementFulfillment using ERP
Approach (Y/N)
Indent/Estimates POM_RP_
EP_2
PO 08.1 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting.
System Y
Tender Document POM_TP_
TD_2
PO 08.2 Tender Processing officer is nominated and Limited tender is floated to selected
vendors.
System Y
Tender Document
Execution
POM_TP_
TE_3
PO 08.3 As per SOP and schedule of work, Tender process is followed and floated;
Simultaneously It is published on RailTel website also.
As required tender is floated to selected supplier from approved supplier
list or fresh approved supplier list can be created before floating the tender
document.
Prebid meeting may be done and tender document is changed accordinglyif required.
Response is received from various vendors.
Tender document is opened by nominated TOC
Comparative sheet and Briefing note are prepared by executive
EMD is hand over to finance and Comparative sheet and briefing note are
vetted by finance.
TC nomination is done.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
33/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
LOA is issued to successful bidder and acknowledgment is received.
Successful bidder deposit various document like PBG, Security deposit.
Simultaneously EMD is returned to unsuccessful bidder.
-
7/27/2019 Wipro BP080 Purchasing V1 0
34/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 09 - Single Tender Process
Start
Project&Procurement
Finance
Single Tenderfloated to single
vendor
Receiveresponse from
bidder
Tender documentis opened by
nominated TOC
Comparative sheetand Briefing noteare prepared by
executive
B
C
Vetted
comparative sheetand Briefing note
put up to TC
TC prepares finalobservation
Comparative sheet & finalminutes sent to TAA for
approval
Successful bidderdeposit various
documents like PBG,Security Deposit
EMD handed overto finance
Comparative sheet &Briefing note vetted
by financeB C
Purchase Indent/Estimates raised at
Territory Level.(Projectbudget will be revised if
indent estimate increasesmore than project
budget)
Purchase Indent/Estimates raisedat regional Level
RO collates all
requisitions fromterritories & Prepares
consolidated
proposal
CO collates allrequisitions from
regions & Preparesconsolidated
proposal
EMD returns oradjusted with
Invoice
Purchase Order/LOA Issuedto successful bidder.
Tender estimate will berevised if LOA/PO estimateincreases more than tender
estimate.
Tender processingofficer is
nominated
ProjectBudgetingProcessPRJ05
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting & approval as per
SOP. Along with PACissued by region/
Corporate (with vetting)and approval by director/
Corporate
A
Tender cost Estimationprepared and Put up to
Finance for FinanceVetting
A
Acceptance fromSupplier
SupplierRegistration
Process
PO32
End
TC nomination asper SOP
Purchase Indentraised at corporate
level
Single Tender ERP Manual Email
Discharge
Counter offer/LOI
Negotiation maydone with
supplier
ApprovedSupplier List
PO37
Fresh approvedsupplier list via
approval
Non AcceptanceAcceptance
-
7/27/2019 Wipro BP080 Purchasing V1 0
35/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Single Tender Process Business Function: RAILTEL Tender Date: 12-01-2013
Control Number: PO 09 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 09 Description: This step explains the Single Tender process.
Event Description: This process is triggered Whenever Single Tender is created.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # DescriptionMode
RequirementFulfillment using ERP
Approach (Y/N)
Indent/Estimates POM_RP_
EP_2
PO 09.1 Purchase Indent/Estimates raised at territory and regional level
RO & CO collates all the indent and prepares consolidated proposal
Estimates and Tender document prepared and put up to finance for finance
vetting, along and with PAC issued by region (with vetting) and approval by
director/corporate.
System Y
Tender Document POM_TP_
TD_2
PO 09.2 Tender Processing officer is nominated and Singe tender is floated to vendor. System Y
Tender Document
Execution
POM_TP_
TE_3
PO 09.3 As per SOP and schedule of work, Tender process is followed and floated.
As required tender is floated to selected supplier from approved supplier
list or fresh approved supplier list can be created before floating the tender
document.
Tender document is opened by nominated TOC
Comparative sheet and Briefing note are prepared by executiveEMD is hand over to finance and Comparative sheet and briefing note are
vetted by finance.
TC nomination is done.
Vetted comparative sheet put up to TC and TC prepares the final
observation.
Comparative sheet and final minutes sent to competent authority approval.
Negotiation is done if required and Discharge can also be happen
Counter offer process is done for final price.
LOA is issued to successful bidder and acknowledgment is received.
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
36/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Successful bidder deposit various document like PBG, Security deposit.
Simultaneously EMD is returned to unsuccessful bidder.
-
7/27/2019 Wipro BP080 Purchasing V1 0
37/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 10 - Dispensation of Tender Process for Material
Dispensation of Tender for Material
Territory/Region/
Corporate
Finance
Project&Procurement
Start
Executive
processes thedispensation of
Tender
RFQ will becreated for
quotation
Quotation are
called fromvarious vendors
(Minimum 3)PO31
Comparative
statement isprepared by the
executive andsent to finance
for vetting
Comparativesheet sent to
competentauthority
approval
Purchase
Order is issuedto successful
bidder
End
RFQProcess
PO31
Executive sends the
proposal PurchaseRequisition/Indent to
Manager (HQ/RO/CO)PO01-PO02
Purchase
Indent Process
PO01-PO02
ProcurementProcess
PO12
Successful bidder
deposit variousdocuments like PBG,
Security Deposit(Optional)
A
AFinance
Vetting
ERP Manual Email
-
7/27/2019 Wipro BP080 Purchasing V1 0
38/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Dispensation of Tender Process for
Material
Business Function: RAILTEL Tender Date: 12-01-2013
Control Number: PO 10 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 10 Description: This step explains the Dispensation of Tender process for Material.
Event Description: This process is triggered Whenever Dispensation of Tender Process is done.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 10.1 Dispensation of tender is requested on urgent basis for extension of maintenance
activity or last mile. Executive processes the dispensation of tender process.
System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 10.2 RFQ document is created and sent to approve suppliers or Fresh Suppliers.
Quotations are called from various suppliers.
System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 10.3 Comparative statement is prepared and sends to finance for vetting then it is sent to
competent authority for approval.
System Y
Dispensation of
Tender/QuotationProcess
POM_TP
_DT_4
PO 10.4 Purchase Order is issued to successful bidder System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 10.5 Successful bidder deposits various documents like PBG, Security deposit. System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 10.6 Procurement process is initiated for further activity. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
39/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 11 - Dispensation of Tender Process for Works Contract & Execution
-
7/27/2019 Wipro BP080 Purchasing V1 0
40/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Dispensation of Tender for Works Contract & Execution
Territory/Region/
Corporate
Finance
Pro
curement
Start
Executive
processes the
dispensation ofTender
RFQ will becreated for
quotation
Quotation are
called fromvarious vendors
(Minimum 3)
PO31
Comparative
statement is
prepared by theexecutive and sent to
finance for vetting
Comparative
sheet sent to
competentauthority
approval
LOA is issued
to successfulbidder
End
RFQProcess
PO31
Executive sends the
proposal Purchase
Requisition/Indent toManager (HQ/RO/CO)
PO01-PO02
PurchaseIndent Process
PO01-PO02
Procurement
ProcessPO13
Successful bidder
deposit various
documents like PBG,Security Deposit
(Optional)
A
AFinance
Vetting
ERP Manual Email
RAILTEL Process: Dispensation of Tender Process for Business Function: RAILTEL Tender Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
41/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Service & Works Contract
Control Number: PO 11 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 11 Description: This step explains the Dispensation of Tender process for Service & Works Contract.
Event Description: This process is triggered Whenever Dispensation of Tender Process is done.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID # Description
Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.1 Dispensation of tender is requested on urgent basis for extension of maintenance
activity or last mile. Executive processes the dispensation of tender process.
System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.2 RFQ document is created and sent to approve suppliers or Fresh Suppliers
Quotations are called from various suppliers.
System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.3 Comparative statement is prepared and sent to finance for vetting then it is sent to
competent authority for approval.
System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.4 LOA is issued to successful bidder System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.5 Successful bidder deposits various documents like PBG, Security deposit. System Y
Dispensation of
Tender/Quotation
Process
POM_TP
_DT_4
PO 11.6 Procurement process is initiated for further activity. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
42/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 12 - Procurement Process for Material (Supply Item)
Standard
PurchaseOrder
APO/RC/SPO/SubAPO/Sub RC Sent
for Finance Vetting
Purchase
Order Issuedto Successful
bidder
Sub PO arereleased
against RC
Procurement
Finance
Supplier offer
RailTel forcarrying
inspection
Inspection from
nominated agencyeither from ASL orby RailTel officials
Confirmation of
Change ofconsignee if
any
Item delivered
at store
Warranty asper PO
conditions
Invoice Bills &
PaymentsAP02-AP04
RailTel Usesthe item to the
site or RailTeldeliver the item
to the site
Start
End
PurchaseOrder
DocumentCreated
Sub PO are
releasedagainst APO
Region wiseDistribution
Procurement Process for Supply Item
Standing Bank
GuaranteeSubmission
from Supplier
AdvancePurchase
Order
Rate Contract
PO will be amended
to change theconsignee detail withexecutive approval
Nomination ofinspection
authorizedagency
ApprovedSupplier List or
New SupplierPO37
Payment to
OutsideInspection
authority
ERP Manual Email
End
Receiving
ProcessINV02
Inspectionreport is
entered in tothe system
Acceptance &
BG submissionfrom Supplier
PO18
Inspection Outside
RailTel
-
7/27/2019 Wipro BP080 Purchasing V1 0
43/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Procurement Process for Material Business Function: RAILTEL-Project Date: 12-01-2013
Control Number: PO 12 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 12 Description: This step explains the procurement process of Material.
Event Description: This process is triggered Whenever a purchase order is raised for material procurement.
Source: RAILTEL Project Team/AS-IS Document
AS ISProcess
AS IS ID # Process ID #Description Mode
RequirementFulfillment using ERP
Approach (Y/N)
Purchase
Order
Creation
POM_PO_PC_3 PO 12.1 Purchase Order is created as per the requirement in the tender with the
successful bidder.
System Y
Purchase
Order
POM_PP_PO_4 PO12.2 Purchase Order can be of multiple types like Standard PO, APO and
RC.
Purchase Order is issued to successful bidder after finance vetting.
Standing BG is submitted from supplier against APO and RC.
BG is submitted and accepted from supplier against Standard PO and
Sub-Pos against APO & RC.
System Y
Inspection POM_PO_IP_4 PO 12.3 Supplier offer RailTel for carrying Inspection.
Inspection can be from nominated agency either from ASL or by
RailTel officials.
If Inspection is from outside, nomination of inspection authorizedagency is done from ASL and Payment to inspection authority is made.
Inspection report is entered in to the system.
System Y
None None PO 12.4 PO will be amended to change the consignee detail with the executive
approval.
System Y
Receiving/D
elivery
POM_PO_RD_5 PO 12.5 Item is delivered at store
RailTel uses the item to the site or RailTel deliver the item to the site.
System Y
Inspection/F POM_RP_TS_4/P PO 12.6 Warranty will be applicable after delivery of Item as per PO condition. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
44/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS
Process
AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
AT OM_PP_FT_5
-
7/27/2019 Wipro BP080 Purchasing V1 0
45/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 13 - Procurement Process for Works Contract (Supply, Installation & Commissioning)
LOA Sent for
FinanceVetting
LOA Issued toSuccessful
bidder
Project
Finance
Contract agreement
is prepared with
successful bidder
Contractoroffer RailTel
for carrying
inspection
Inspection fromnominated agency
either from ASL or
by RailTel officials
Confirmation ofchange in
consignee if
any
Service/Itemdelivered &
recorded
Item deliveredat site
Vendor doesI&C after site
readiness
SI Conducts
AT in co-
ordination with
RailTel
Executive
PAC released
after AT
FAC as per
LOA T&C EndWarranty as
per LOA T&C
Invoice Bills &
Payments
AP02-AP04
Start
LOADocument
Created
Region wise
Distribution
Contract
agreement is
sent for legal
vetting
Procurement Process for Works Contract
Nomination of
inspection
authorized
agency
Approved
Supplier
List
PO37
Payment to
Inspection
authority
End
LOA will be amendedto change the
consignee detail with
executive approval
Part PAC can
also be released
as per LOA T&C
Acceptance &
BGSubmission
from Supplier
PO18
ERP Manual Email
Inspection Outside
RailTel
-
7/27/2019 Wipro BP080 Purchasing V1 0
46/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Procurement Process for Service &
Works Contract
Business Function: RAILTEL-Project Date: 12-01-2013
Control Number: PO 13 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 13 Description: This step explains the procurement process for service & Works Contract.
Event Description: This process is triggered Whenever a LOA is created for service and Works Contract.
Source: RAILTEL Project Team/AS-IS Document
AS IS Process AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
LOA Creation POM_PO_P
C_3
PO 13.1 LOA document is created and region wise distribution can also be happen. System Y
LOA Creation POM_PP_P
O_4
PO 13.2 LOA is issued to successful bidder after finance vetting. System Y
None None PO 13.3 LOA is accepted and Bank Guarantee is submitted from supplier.
None POM_RP_TP
_5
PO 13.4 Contract agreement is prepared with successful bidder and it is sent for legal
vetting.
System Y
Inspection POM_PO_IP
_4
PO 13.5 Contractor offer RailTel for carrying Inspection
Inspection can be from nominated agency either from ASL or RailTel
officials. Fresh nomination of agency can also be done.
If inspection is from outside, nomination of inspection authorized agency isdone from ASL and Payment to inspection authority is made.
System Y
None None PO 13.6 Consignee detail can be changed by amending the consignee detail in LOA. LOA will
go for executive approval.
System Y
Receiving/Delivery POM_PO_R
D_5
PO 13.7 Service/Item is delivered to site/Store.
Vendor does I&C at site after site readiness.
System Y
Inspection/FAT POM_PP_FT PO 13.8 SI conducts AT in coordination with RailTel executive
-
7/27/2019 Wipro BP080 Purchasing V1 0
47/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
AS IS Process AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
_5/POM_RP
_TS_4
PAC is released after AT, Part PAC can also be released as per LOA terms &
condition
FAC will be issued after PAC release as per LOA terms & condition
Warranty will be applicable after delivery as per LOA terms & condition
-
7/27/2019 Wipro BP080 Purchasing V1 0
48/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 14 - Procurement Process for Execution
-
7/27/2019 Wipro BP080 Purchasing V1 0
49/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
LOA Sent for
FinanceVetting
LOA Issued toSuccessful
bidder
Project
Finance
Contract agreement
is prepared withsuccessful bidder
Work
Confirmation of
Service
delivered
Invoice Bills &
PaymentsAP02-AP04
Start
LOA
Document
Created
Region wiseDistribution
Contract agreement issent for legal vetting
Optional for Execution
works at RO
Procurement Process for Execution ERP Manual Email
PAC released
after AT
FAC as per
LOA condition End
Part PAC canalso be released
as per LOAcondition
Acceptance &
BG, SDSubmission
from Supplier
PO18
SI Conducts AT
in co-ordination
with RailTel
Executive
SI Conducts AT
in co-ordination
with RailTel
Executive
Stock
Transfer
from Store toProject Site
INV04
On-hand
quantity will
get updated
End
Indent for
Material
requirement atsites
PO01-PO02
Materialrequired at site
for other
activity
RAILTEL Process: Procurement Process for Execution Business Function: RAILTEL-Project Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
50/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 14 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 14 Description: This step explains the procurement process for Execution.
Event Description: This process is triggered Whenever LOA is raised for execution activity.
Source: RAILTEL Project Team/AS-IS Document
AS IS
Process
AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERPApproach (Y/N)
LOA
Creation
POM_PO_
PC_3
PO 13.1 LOA document is created and region wise distribution can also be happen. System Y
LOA
Creation
POM_PP_
PO_4
PO 13.2 LOA is issued to successful bidder after finance vetting. System Y
None None PO 13.3 LOA is accepted and Bank Guarantee, Security Deposit is submitted from supplier.
None POM_RP_
TP_5
PO 13.4 Contract agreement is prepared with successful bidder and it is sent for legal
vetting.
System Y
Receiving/D
elivery
POM_PO_
RD_5
PO 13.5 Work Confirmation of Service is entered for service receiving. System Y
None None PO 13.6 In case of Material requirement like Duct, Cable at site an Indent will be
raised to issue the material from store to site.
Stock is transferred from store to site.
System Y
Inspection/F
AT
POM_PP_
FT_5/POM_RP_TS
_4
PO 13.7 SI conducts AT in coordination with RailTel executive
PAC is released after AT, Part PAC can also be released as per LOA terms &condition
FAC will be issued after PAC release as per LOA terms & condition
System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
51/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 15 - Procurement Process for AMC (Equipments, Sections, Miscellaneous)
LOA Sent forFinanceVetting
LOA Issued toSuccessful
bidder for AMCWork
Project
Finance
Contract agreementis prepared with
successful bidder
Servicedelivered &recorded
Invoice Bills& PaymentsAP02-AP04
Start
LOADocumentCreated
Region wiseDistribution
Contractagreement issent for legal
vetting
Procurement Process for AMC Work (Equipment, Section)
WorkConfirmation of
Service
End
EmailManualERP
Acceptance &BG
Submissionfrom Supplier
PO18
WorkOrder
MNT04
-
7/27/2019 Wipro BP080 Purchasing V1 0
52/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Procurement Process for AMC Business Function: RAILTEL-Project Date: 12-01-2013
Control Number: PO 15 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 15 Description: This step explains the procurement process for AMC work.
Event Description: This process is triggered Whenever LOA is raised for AMC work against Work Order and Purchase Indent.
Source: RAILTEL Project Team/AS-IS Document
AS IS
Process
AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
LOA
Creation
POM_PO_
PC_3
PO 13.1 LOA document is created and region wise distribution can also be happen for AMC
work.
System Y
LOA
Creation
POM_PP_
PO_4
PO 13.2 LOA is issued to successful bidder after finance vetting. System Y
None None PO 13.3 LOA is accepted and Bank Guarantee is submitted from supplier.
None POM_RP_
TP_5
PO 13.4 Contract agreement is prepared with successful bidder and it is sent for legal
vetting.
System Y
Receiving/D
elivery
POM_PO_
RD_5
PO 13.5 Work Confirmation of Service is entered for service receiving. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
53/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 16 - Procurement Process for Inspection (Material, Works Contract & Execution)
-
7/27/2019 Wipro BP080 Purchasing V1 0
54/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Procurement Process for Inspection Charges
Procurement
Procurement
Fin
ance
Start
Service PO is created for
Inspection Charges with
Supplier Ship to and Bill to
details
Shipment
detail is
entered
Distribution detail is
entered for service
delivery/Inspection
work/Inspection
charges
Service details,
amount, need by
date and
promised date is
entered
Give Distribution
detail location wise
and delivery
schedule for item
delivery
Approve POPO
approved
No
Automaticnotification to
buyer
Yes
PO sent for
finance vetting
ServiceDelivered/Inspection
completed
Inspection reportis submitted to
Project Executive
End
Invoice Bill &
Payments to
supplier for
Inspection Work
AP02-AP04
ERP Manual Email
WorkConfirmationof Service
INV03
RAILTEL Process: Procurement Process for Inspection Business Function: RAILTEL-Project Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
55/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 16 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 16 Description: This step explains the procurement process for Inspection Charges.
Event Description: This process is triggered Whenever Payment for Inspection Charges is done.
Source: RAILTEL Project Team/AS-IS Document
AS ISProcess
AS IS ID # Process ID #Description Mode
RequirementFulfillment using ERP
Approach (Y/N)
None None PO 16.1 Service Purchase Order is created for Inspection charges with supplier details. System Y
None None PO 16.2 Service amount/quantity, service fulfillment date is entered. System Y
None None PO 16.3 Shipment detail is entered System Y
None None PO 16.4 Distribution detail location wise is entered for service delivery information System Y
None None PO 16.5 Service Purchase Order is submitted for approval for finance vetting System Y
None None PO 16.6 Automatic notification will be sent to buyer for confirmation of LOA approval. System Y
None None PO 16.7 Inspection report is submitted to project executive. Manual N
-
7/27/2019 Wipro BP080 Purchasing V1 0
56/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 17 - Imprest/Advance Procurement Process
Imprest/Advance Procurement Process
Procurem
ent
Operation&Maintenance
Finance
Start
ServicePurchase
Order sent forfinance vetting
Invoice Bill &Payments to
supplierAP02-AP04
ERP Manual Email
Unoreredreceipt of Item/Service detail
is created
Receipt of linedetail is
recorded
Item/Service,Quantity, UOM andreceiving locationfor receipt line is
specified
Generate newreceipt or add
unordered receiptlines to an
existing receipt
Projects&Procurement
Receipt headerinformation isentered and
transaction issubmitted
SearchUnorderedreceipts to
match
Select receiptlines to match
PurchaseOrder is
created tomatch the
receipt lines
Select PurchaseOrder documentnumber & Linedetails to match
SubmitUnordered
receipt line formatching
Receiving ofItem/Service is
done in thesystem
Final deliveryof Item/Service
End
-
7/27/2019 Wipro BP080 Purchasing V1 0
57/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
RAILTEL Process: Imprest/Advance Procurement
Process
Business Function: RAILTEL-Project Date: 12-01-2013
Control Number: PO 17 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 17 Description: This step explains the Imprest/Advance Procurement Process.
Event Description: This process is triggered Whenever unordered receipt is made without valid Purchase Order.
Source: RAILTEL Project Team/AS-IS Document
AS IS
Process
AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
None None PO 17.1 Unordered receipt of Item/Service detail is created System Y
None None PO 17.2 Item/Service, Quantity, UOM and receiving location for receipt line is specified System Y
None None PO 17.3 Generate new receipt or add unordered receipt lines to an existing receipt System Y
None None PO 17.4 Receipt header information is entered and transaction is submitted System Y
None None PO 17.5 Purchase Order is created to match the receipt lines System Y
None None PO 17.6 Unordered receipt and receipt lines is searched to match with PO document number System Y
None None PO 17.7 Unordered receipt line is submitted for matching System Y
None None PO 17.8 Receiving of Item/Service is done in the system System Y
None None PO 17.9 Final delivery is created of Item/Service. System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
58/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 18 - Bank Guarantee Process
Bank Guarantee Process
Procurem
ent
Project&Procurement
Legal
PBG sent forlegal vetting
ERP Manual Email
Start
Purchase
Order
Letter of Award
Sub PO
against RateContract
Sub PO
againstAdvance
PurchaseOrder
Performance BankGuarantee will sent
to bank for
confirmation
Afterconfirmation,
sent for legal
vetting
After legalvetting
submitted to
finance forsafe custody
Standing BGwill be sent to
bank for
confirmation
Advance
PurchaseOrder
Rate Contract
Delivery/DOC period
extends
Extension of BankGuarantee date &
Performance BankGuarantee will sent to bank
for confirmation. System
alert will go to finance forbank guarantee date
extension
Yes
After Bank
Confirmation itis submitted to
finance for
safe custody
Supplier Bank Guarantee will
be released after PO/LOAfulfillment/Encashment in
case of default/termination
End
No
-
7/27/2019 Wipro BP080 Purchasing V1 0
59/125
-
7/27/2019 Wipro BP080 Purchasing V1 0
60/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 19 - Site Readiness Process-For Material and Service
-
7/27/2019 Wipro BP080 Purchasing V1 0
61/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Site Readiness Process
Procurement
Project&Procurement
ERP Manual
Start
Notification will
be sent to
concern stores
for Space
check
Space
Available for
Material
PO/LOA
issued for
Material/Works
PO12-PO13
Procurement
process for
Material/Works
Execution
Executive will
check & show
drop down menu
for readiness of
activity
Activities can be like for I&C activity:
Fiber through & Terminated from BS to
BS
Power Supply-AC
Power Supply-DC, Battery, Chargers
Rack Installation
Space
Earthing etc.
Concern authority
will put suitable
remarks for
readiness/non
readiness
LOA for
work
execution
PO14
Pre-requisite
Activity
defined
Executive will
check & show
drop down
menu for
readiness of
activity
Activities can be like:
Proposed route Plan
Approval from Railways/other
authority along with offset boundary
lines
ROW permission
Duct Availability
OFC Availability etc..
Concern authority
will put suitable
remarks for
readiness/non
readiness
Yes
No (Authority will put suitable remarks)
Yes
No (Authority will put suitable
remarks)
End
End
RAILTEL Process: Installation & Commissioning and Business Function: RAILTEL-Project Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
62/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Site Readiness Process
Control Number: PO 19 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 19 Description: This step explains the Installation & Commissioning/Site readiness activity.
Event Description: This process is triggered to fulfill pre-requisite activity before doing the Installation and Commissioning.
Source: RAILTEL Project Team/AS-IS Document
AS IS
Process
AS IS ID # Process ID #
Description Mode
Requirement
Fulfillment using ERP
Approach (Y/N)
None None PO 19.1 PO/LOA is issued for Material/Work/Execution process System Y
None None PO 19.2 Notification will be sent to concern stores for space check System Y
None None PO 19.3 Concern store checks the space availability of material System Y
None None PO 19.4 Executive will check and enter detail for readiness of activity for works System Y
None None PO 19.5 Various activities are required to check before I&C activities like:
Fiber through & Terminated from BS to BS
Power Supply AC
Power Supply DC, Battery, Chargers
Rack Installation etc..
System Y
None None PO 19.6 Concern authority will put suitable remarks for readiness/non-readiness System Y
None None PO 19.7 Pre-requisite activity will be defined for execution activity System Y
None None PO 19.8 Executive will check and enter detail for readiness of activity for execution System Y
None None PO 19.9 Various activities are required to check before execution:
Proposed Route Plan
Approval from railways authority along with offset boundary lines
Duct availability
OFC availability etc..boundary lines
Duct availability
OFC availability etc..
System Y
None None PO 19.10 Concern authority will put suitable remarks for readiness/non-readiness System Y
-
7/27/2019 Wipro BP080 Purchasing V1 0
63/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
PO 20 - Inspection Process
-
7/27/2019 Wipro BP080 Purchasing V1 0
64/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Inspection Process
Procurement
Project&Procurement
ERP Manual
Start
Supplier/Contractor offer
RailTel for carryingInspection
Inspection
Inspection byRailTel official
Inspection report
is submitted toProject
Executives
Inspection
report isentered in to
the system
End
RailTel
Nomination ofInspection
authorized agencyeither by ASL or by
RailTel officials
Outside Agency
Outside agencysubmits the
Inspection reportto Project
Executives
Inspectionreport is
entered in tothe system
End
In case of FAT/AT outside India agreement in between RailTel and Supplier is mandate, without agreement (Formal) no official of RailTel can go outside of India
RAILTEL Process: Inspection Process Business Function: RAILTEL-Project Date: 12-01-2013
-
7/27/2019 Wipro BP080 Purchasing V1 0
65/125
BP.080 - Purchasing Process
CompanyConfidential - For internal use only
Control Number: PO 20 Mapping Team: Wipro Process Owner: RAILTEL Project Team
Process Number: PO 20 Description: This step explains the Inspection Process.
Event Description: This process is triggered whenever Inspection is required.
Source: RAILTEL Project Team/AS-IS Document
AS ISProcess
AS IS ID # Process ID #Description Mode
RequirementFulfillment using ERP
Approach (Y/N)
None None PO 20.1 Supplier/Contractor offer RailTel for carrying Inspection System Y
None None PO 20.2 Inspection can be done by RailTel team or Outside agency System Y
None None PO 20.3 In case of RailTel team, Inspection is done by RailTel officials System Y
None None PO 20.4 Inspection report is submitted to Project executives System Y