wrench working steps-consolidated

Upload: anonymous-iwqk1nl

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 WRENCH Working Steps-Consolidated

    1/47

    Contents

    --WRENCH Working Steps

    --How to Add Drawings Documents to Tasks in WRENCH

    --How To Add TQ Technical Query in Wrench

    --How To Reassign a Task from WBS or Users Workspace

    --2 STEPS IN ACCESSING SPECTER OR NATIVE FILE FROM YOUR WORKSPACE AND IN W

    ---While adding a file message comes as Document Number and Sheet Number already ex

    ---Bulk Replace of files from Workspace

    ---How To Add RTCC _Reply To Client Comments_ in Wrench

  • 8/10/2019 WRENCH Working Steps-Consolidated

    2/47

  • 8/10/2019 WRENCH Working Steps-Consolidated

    3/47

    WRENCH Working Steps / Rules of Credit

    1st CYCLE

    DISC ORIGINATE DRAW STAGE / STAGE

    As soon as the originator starts work on a document, the native files are to beuploaded into the relevant task in WRENCH. By this action (uploading of docs.),5% progress is captured / reflected in WRENCH;

    Originator can work on the W-drive and do multiple check-ins and check-outsensuring that the latest / updated documents are always uploaded in WRENCHtasks daily;

    Originator completes the check list; checking the status boxes for the requiredcheck points and ensuring that these check points are complied;

    Once the documents are ready for check, it is to be routed to DISC check stage.The originator may also provide the hard copy for checking.

    Documents

    attached

    5 %Progress

    Captured

  • 8/10/2019 WRENCH Working Steps-Consolidated

    4/47

    DISC CHECK STAGE

    The checker, checks the documents, scans the check prints and adds the PDF file to thetask. Use Comment File (s) tab to add the IDC comments;

    It is then routed back (rejected) to the Disc Originate/Draw Stage).

    Once Originator has incorporated the IDC comments and Routed to the Checker,

    The checker converts the native file to PDF, adds the same in Squad CheckComment.

    IDC Comments

  • 8/10/2019 WRENCH Working Steps-Consolidated

    5/47

    Checker then assigns the sequence for the disciplines required to do the squad check

    And routes the document to the MULTI-DISC SQUAD CHECK Stage and with thisaction, 30% progress is captured/reflected in WRENCH.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    6/47

    MULTI DISC SQUAD CHECK

    All disciplines involved in squad check get automated e-mails at the start of squadcheck process. Subsequent e-mails will be sent as the routing progresses.

    The First discipline checks out the squad Check Comments; Prints the Squad

    Check Comments & does the mark ups on the hard copy.

    The marked up copy is then scanned and checked in the Squad CheckComments in the WRENCH task.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    7/47

    While Checking In the user should, browse / Selects the required PDF file (Scanned /Marked up) and close route.

    The second discipline checks out the squad Check Comments made by the first discipline;Prints the Squad Check Comments & does the mark ups on the hard copy and repeats therest of the steps in the 1

    ststage The other disciplines in sequence follow the same steps

    and close route one by one;

    The final discipline in the SC stage also follows the same steps and routes to DISCREVIEW stage and with this action, 60% progress is captured / reflected inWRENCH.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    8/47

    Following up on squad check is the responsibility of originating discipline. Theoriginator is to follow up closely the progress of the documents through squadcheck team.

    PL. NOTE THAT THE SQUAD CHECK COMMENT FILE MADE BY THE 1ST

    DISCIPLINE ISUSED BY ALL SUCCEDDING DISCIPINES TO MARK UP THEIR COMMENTS. BY THISCONSOLIDATED COMMENT IS ENSURED / REFLECTED IN ONE SINGLE DOCUMENT.

    DISC REVIEW

    The checker reviews the SC comments and routes back (rejects) to the DISCORIGINATE / DRAW stage with instructions to incorporate the comments;

    The originator incorporates the SC comments and routes to DISC check Stage. Thechecker then bypasses the document directly to DISC APPROVE stage.

    DISC APPROVE

    Before sending to approval stage, the originating discipline shall provide a hardcopy to approver. Once approver reviews and accepts the documents , this can berouted in wrench to approver stage.

    After the approver reviews the document it could be rejected to DISC REVIEW incase of comments or if approved can be routed forward to PE REVIEW stage.

    60% Progress

    Captured

  • 8/10/2019 WRENCH Working Steps-Consolidated

    9/47

    PE APPROVE

    Before sending to approval stage, the originating discipline shall provide a hardcopy to approver. Once approver reviews and accepts the documents, this can berouted in wrench to approver stage.

    After the PE review the document, it could be rejected to DISC APPROVE stageand if OK, it will routed forward to DCC Issue stage.

    DCC ISSUE

    Prepare DCPI and ensure that the Document is routed to DCC workspace for issue.

    Once the DCC receives the document through WRENCH and the signed hard copy,the transmittal is prepared;

    The PDF of the signed hard copy is added as Specter File(s) to the task;

    The transmittal is issued for Review and the document routed to DCC CLIENTCOMMENT stage and with this action 70% progress is captured / reflected inWRENCH.

    70% Progress

    Captured

  • 8/10/2019 WRENCH Working Steps-Consolidated

    10/47

    DCC CLIENT COMMENT

    When the client comments (with approved codes) are received, the same arescanned and added to task as client comments;

    DCC routes this to the DISC ORGINATE / DRAW stage.

    2nd

    / NEXT CYCLE

    DISC STAGE ORIGINATE / DRAW

    Based on the approval code/document class, the originator updates the documentto be, re-issued for review or issued for approval or final issue

    DCC ISSUE

    The cycle is repeated and the document may be :

    1. Re-issued for review. With this action the progress stays at 70% inWRENCH.

    2. Issued for approval. With this action 80% progress / captured reflected inWRENCH.

    DCC FINAL ISSUE

    1. Final Issue. With this action 100% progress / captured reflected in WRENCH.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    11/47

    WRENCH Tip Of The Week 2

    How to Add Drawings & Documents to Tasks in WRENCH

    Step 1.Login to WRENCH, in the main window under My Wrench click on Workspace

    Step 2.Under Workspace click on Task.

    Workspace

    Task

  • 8/10/2019 WRENCH Working Steps-Consolidated

    12/47

    Step 3. . Once clicked on Task it will show the list of Tasks available in your Workspace.

    Select the Task in which you want to add the Drawing / Document. (You can group it forease of search E.g. By Project Number)

    Step 4.Double click on the Task in which you want to add the Drawing / Document.

    Grouping: Drag & Drop Here

    Task

    List of Task in your Workspace

  • 8/10/2019 WRENCH Working Steps-Consolidated

    13/47

    Step 5.And it will open up the Task Properties Window. In the below half window, there arevarious tabs, Click on Related Itemtab, and inside this window do a Right click, and select Add.

    Step 6. In the Related Items to TaskWindow

    a) Object Type : Select Document(irrespective of you adding a drawing / document)b) Relation : Select Link, if the drawing or document is the one to be issued to Client

    OR Select Refer, if the drawing / document is to be added only for In-housereference purposes, and not to be sent to Client.

    c) Mode : Select New, if the drawing / document is not existing in Wrench Or SelectExisting From Wrench.

    d) Objects : Select Single, if it is 1 number drawing /document OR Select Multiple, if many

    drawings / documents are to be added.e) Click Select.

    Add

    Related Item

    Right Click Here

  • 8/10/2019 WRENCH Working Steps-Consolidated

    14/47

    Step 7. For SingleDrawing / Document, it will open up the below Add DocumentWindow,Click on Browse & Select the document from the path where it is located andclick Open.

    Object Type

    Browse

    Relation

    Objects

    Mode

    Select

    Open

  • 8/10/2019 WRENCH Working Steps-Consolidated

    15/47

    Step 8.Give the required details & click ok.a) Document Description as it appears on the Title Block

    b) Client Document Number in the same client format as mentioned in the Title lockc) Current Revision Number of the Drawing / Document

    d) Sheet Number, e) Sheet Size, f) Number of Sheets

    Step 9.Again Click OK

    Client Document Number

    Revision Number

    Sheet Number

    Number of SheetsSheet Size

    OK

    Document Descri tion

    OK

  • 8/10/2019 WRENCH Working Steps-Consolidated

    16/47

    Step 10.For Adding Multiple Drawings / Documents to Tasks in WRENCH (Follow the sameStep 1 to Step 6 & at step 6 in Objects select Multipleas shown below)

    Step 11. And it will Pop up the Add Multiple Documentswindow, click on Select files

    Multiple

    Select Files

  • 8/10/2019 WRENCH Working Steps-Consolidated

    17/47

    Step 12. Onceclicked on select files Open window will appear, Click on Look in drop

    down arrow & select the files from the path where it is located & click open

    Step 12. After selecting the files give the required details (E.g Client, Document Number,

    Document description,Current Revision Number, Sheet Number, Number of Sheets,Sheet Sizeetc Use the slider at the bottom of the window to access this information) Click

    on Add to Wrench, if no errors, it will show Document Added Successfully, Click OK

    Slider

    Look in

    Sheet NumNumber of

    Sheet S

    OK

    Comments

    Document Description

    Client Document Number,User Revision Number

    Add To Wrench

  • 8/10/2019 WRENCH Working Steps-Consolidated

    18/47

    Step 13.Then click Close.

    Step 14.Click OK

    OK

    Close

  • 8/10/2019 WRENCH Working Steps-Consolidated

    19/47

    WRENCH Tip of The Week

    How To Add Vendor TQ (Technical Query) in Wrench

    For Adding (uploading) Vendor TQ in wrench please follow the below Steps.

    Step1. In Wrench main Window, Under Folders, Maximize Documents Tab.

    Click to Maximize Documents 2

    Folders 1

  • 8/10/2019 WRENCH Working Steps-Consolidated

    20/47

    Step2. Select respective Discipline, Maximizeand Click on TQ (Technical Query).

    Step3. After Clicking on TQ, Right Click on Wrench Desktop, Select Newand Click on Single Document.

    Right Click 5Here (Wrench Desktop

    Single Documen

    Click to Maximize 3

    TQ 4

    New 6

  • 8/10/2019 WRENCH Working Steps-Consolidated

    21/47

    Step4. On Clicking Single Documentthe below Add Documentwindow will be opened, Click on the Browse,under project ID (as shown below), Enter project No. in Look Forunder Project SearchWindow and select

    the respective project by Double Clickingon project No.

    Step5. Then TQ Noto be generated.

    For generating TQ No, Click on Browse tab (In Document No), on clicking Browse DocumentNumber Generatorwindow will open, Select Vendor Technical Query& Click Ok.

    Browse 11

    Enter Project No 9

    Tab to select the Project 8

    Select Project 10

    Document Number Generator

    VTQ 12

    OK 13

  • 8/10/2019 WRENCH Working Steps-Consolidated

    22/47

    Step6. On Clicking OKthe below Generate Numberwindow will open, Select the Sender Codeby Clickingon Sender Code Taband Select the Receiver Codeby Clicking on Receiver Code Tab, then Click on MR

    NO.

    Step7. On Clicking on MR Numberthe below Manual Entrywindow will open, type the corresponding MR

    No for this TQ (You need to type in the Document Genealogy (e.g. ECMR) and No (e.g.005) as shown belowand Click Ok

    Note:

    *For all Veco Generated MRs the corresponding MR No which will be mentioned in between the TQ no

    shall be Vecos MR No.

    *For all CPE Generated MRs the corresponding MR No which will be mentioned in between the TQ no

    shall be Client MR No.

    E.g. For Veco Generated MRs

    Generator Number window

    MR Number 16

    Sender Code 14

    Receiver Code 15

    MR Number 16

    MR Number 17MR Number 17

    Ok 18

    MR Number 17

  • 8/10/2019 WRENCH Working Steps-Consolidated

    23/47

    Step8. Then Click on Correspondence Typeand select Technical Query (Q) (Double Click).

    Step9. Then Click on Auto Numberand copy the No generatedfrom Preview of generated numberand

    Click Ok.

    Doc Genealogy & NO

    Correspondence Type 19

    Auto Number 21

    Preview of generated No. 22

    Technical Query 20

    Ok 23

  • 8/10/2019 WRENCH Working Steps-Consolidated

    24/47

    Step10. Then open the TQnative file and Paste the copied TQ Nounder Query No / & type in the Date thensave and close the file.

    Eg.For CPE Generated MR

    CPE Generated MRs the corresponding MR No which will be mentioned in between the TQ no shall be Client

    MR No as shown below

    TQ No & Date 24

  • 8/10/2019 WRENCH Working Steps-Consolidated

    25/47

    Step11. Then Enter TQ Description. After entering TQ Description, Click on Browse, Select TQ Native file

    andClick Open. After selecting the file tick on Add as released document(TQ are added as a releaseddocument as it not going through any Workflow) and click Ok.

    You can also send Notification to your Team from Wrench that the following TQ has been added in Wrench.

    Open 28

    Q Description 25

    Browse 26

    Native file 27

    Ok 29

    Client MR No.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    26/47

    Step12. For sending Notification from Wrench after Add as released documentis ticked, click on

    Notification.

    Step13. On clicking Notificationthe below Notificationswindow will open, click on Browseto select User.

    Notification 31

    Browse 32

    Add as Released 30

  • 8/10/2019 WRENCH Working Steps-Consolidated

    27/47

    Step14. On clicking Browse, the below User Listwindow will appear. You can select either by grouporprovide aUser Name/ Login Nameto initiate a Search and then List of users satisfying the specified search

    criteria will be returned. Then Select the User from the Available Users list and click on the right arrow.

    Same way you can also remove Users from the Selected User list by selecting the users and clicking on the LeftArrow. Then click on Ok.

    Step15. Again ClickOk.

    OK 39

    Available Users35

    Users to be removed

    Login / User name 34

    User Group 33

    Left Arrow 38

    Right Arrow 36

    Ok 40

  • 8/10/2019 WRENCH Working Steps-Consolidated

    28/47

    Step16. Then again click Okto save the documents and sent Notification.

    Step17. On Clicking Okthe below Document successfully added as a released document window will

    open, Click Ok.

    OK 41OK 41

    OK 42

  • 8/10/2019 WRENCH Working Steps-Consolidated

    29/47

    WRENCH-Tip of The Week

    How To Reassign a Task / Deliverable from WBS / Workspace

    Reassigning a Task / Deliverable from WBS / Users Workspace is much easier andtime saving as compared to the Reassign Utility. Please follow the below steps toreassign from WBS / Workspace.

    Step 1. UnderWBS / Workspace, select the Task you want toReassign and Doubleclickon it.

    .

    Select the Task & Double Click

  • 8/10/2019 WRENCH Working Steps-Consolidated

    30/47

    Step 2.On Double Clicking the below Task Propertieswindow will popup. Click onReassign Resource.

    Step 3.On clicking Reassign Resource, the below Reassign Resourcewindow willappear. Click on the current stage(From where you want to reassign resource)

    Current Stage

    Reassign Resource

  • 8/10/2019 WRENCH Working Steps-Consolidated

    31/47

    Step 4.On clicking current stage, resources for current stage will be available. Click onBrowseto assign New Resource.

    Step 5.On Clicking Browsethe below User listwindow will appear with list of current

    users of the stage. Remove the users by clicking on the (

  • 8/10/2019 WRENCH Working Steps-Consolidated

    32/47

    Step 6.Provide a User Nameor Login Nameto initiate a Search, List of users satisfyingthe specified search criteria will be returned. Select the Userthen click on Right arrowand click OK.

    Note:If the user is not available in the Available users list then untick on Filterresources based on project. Aswhen Filter is ticked then it will filter with the list ofresource available in the Project Resource. If the user is not a resource of that projectthen the user name will not be available. On removing the tick the resource will be taken

    from the Masters.

    Project Resources

    Login name to Search

    OK

    Ri ht arrow

    Selected User

    Available Users

    Filter

  • 8/10/2019 WRENCH Working Steps-Consolidated

    33/47

    Step 7.On Clicking OK, the selected user will be in the New Resourceslist. Givecommentson Reaasign and click on Reassign.

    Step 8.On clicking Reassign Resources are reassigned successfully message willpopup. Click Ok.

    OK

    Reassign

    Comments on Reassign

    New Resources

  • 8/10/2019 WRENCH Working Steps-Consolidated

    34/47

    I. ACCESSING FROM WBS.

    Step 1.1.Open WBS, e.g. [WBS-401910], and select a task which you want to view the specter or the nativefile, as shown below.

    Step 1.2. Click VIEWoption to view the native application of the file and click VIEW SPECTER to View thlatest available Specter Copy (PDF File). The document will be automatically displayed, upon clickinthese options.

    WRENCH TIP OF THE WEEK

    2 STEPS IN ACCESSING SPECTER/NATIVE FILE FROM YOUR WORKSPACE AND IN WBS

    WBS-401910

    Selected task which you want to view the

    specter or native file

    View

    View Specter

  • 8/10/2019 WRENCH Working Steps-Consolidated

    35/47

    II. ACCESSING FROM YOUR WORKSPACE.

    Step 2.1.Open your workspace, and select a task which you want to view the specter or the native file, ashown below.

    Step 2.2.Click VIEW ATTACHED DOCUMENToption to view the latest native application of the file anclick VIEW SPECTER to View the latest available Specter Copy (PDF File). The document will b

    automatically displayed, upon clicking these options.

    WORKSPACE

    Selected task which you want to view thespecter or native file

    View

    View Spec

  • 8/10/2019 WRENCH Working Steps-Consolidated

    36/47

    WRENCH Tip Of The Week 3

    While adding a file message comes as Document Number and Sheet

    Number already exists

    Step 1.When a message popup Document Number and Sheet Number already

    exists, Click OK.

    Ok

    Document Number and Sheet Number already exists

  • 8/10/2019 WRENCH Working Steps-Consolidated

    37/47

    Step 2.After clicking Ok, it will go back to Add DocumentWindow. Click Cancel.

    Step 3. Once clicked on Cancel,Related Items To Taskwindow will appear. Select

    Existing from Wrench, and then click on Select.

    Existing from Wrench

    Select

    Cancel

  • 8/10/2019 WRENCH Working Steps-Consolidated

    38/47

    Step 4.After clicking Select, the below shown Document Searchwindow will appear,

    click Search, it will show the search result in the below half window Double click ondocument from the search result.

    Step 5. OnceDouble Clicked, the Document will added as shown below, clickOK

    Search

    Document Added

    Double Click

  • 8/10/2019 WRENCH Working Steps-Consolidated

    39/47

    Many cases users have to replace multiple documents from Workspace, particularly documents like P&IDs &Isometrics which are created & issued in bulk.

    WRENCH provides a convenient method of replacing documents in bulk, irrespective of how many files to bereplaced.

    Step 1:

    Select the tasks from Workspace whose file needs to be replaced. Right click select Replace.

    WRENCH TIP OF THE WEEK

    BULK REPLACE OF FILES FROM WORKSPACE

  • 8/10/2019 WRENCH Working Steps-Consolidated

    40/47

    Step 2:

    On selecting Replace an intermediate interface opens as below.

    Step 3:

    WRENCH can automatically select the files that needs to be replaced against each task/deliverable, for whichuser needs to select the Matching option available in the Multiple Replace Manager window.

    From Matching Option user needsto select Advanced Option.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    41/47

    Step 4:

    From Properties option user needs to select one of the matching criteria between the existing file in WRENCH& the file to be replaced. In most cases the file available in WRENCH & the new file being replaced will havethe same File Name.

    If yes, please select the matching option as File Name from the drop down against Properties.

    Step 5:

    After Matching Option is selected, click ok. From the Multiple Replace Manager window, use Select Folderoption to select the folder in which the files which needs to be replaced are available (All the files that needs tobe replaced needs to be in one folder).

  • 8/10/2019 WRENCH Working Steps-Consolidated

    42/47

    Clicking Select Folder will open a window to select the folder in your PC.

    Step 6:

    Select the folder containing the files to be replaced. Click Ok.

    User can give his comments on replace in the option available & then click Apply to selected Files & then ClicOK to have the files replaced.

    User can also replace the files one by one, by expanding the tree to find theSelect Fileto replace file.

  • 8/10/2019 WRENCH Working Steps-Consolidated

    43/47

    WRENCH Tip Of The Week

    Addition of CRC (Client Review Comments) in Wrench

    Earlier we used to term all Response to Client Comments as RTCC. Now it is CRC (Client Review Comments)

    CRCs are basically CH2M HILLs reply to the comments given by the client on the documents submitted.

    CRC for a client comment is provided along with the subsequent revision of the document.

    CRC is originated & owned by the department engineers. CRC is added to CRC folder defined under each ofthe department folder structure in WRENCH.

    For adding CRC please follow the below steps.

    E.g. If a Civil Engineer wants to add CRC.

    Step1. In Wrench main Window, Under Folders, Maximize Documents Tab.

    Click to Maximize Documents

    Folders

  • 8/10/2019 WRENCH Working Steps-Consolidated

    44/47

    Step2. Select respective Discipline, Maximizeand Click on RTCC/CRC.

    Step3. After Clicking on CRC, Right Click on Wrench Desktop, Select New, Click on Single Document.

    Click to Maximize

    CRC

    1.Right Click Here

    (Wrench Desktop)

    2.New 3.Single Document

  • 8/10/2019 WRENCH Working Steps-Consolidated

    45/47

    Step4. On Clicking Single Documentthe below Add Documentwindow will popup, Click on Browse, under

    Project No., Enter project No in Look Forunder Project SearchWindow and select the project by Double

    Clickingon project.

    2.Enter Project No

    1. Browse to select the Pr

    3.Select P

  • 8/10/2019 WRENCH Working Steps-Consolidated

    46/47

    Step5. Then CRC Nohas to be generated.For generating CRC No, Click on Browse, on clicking Browse Document Number Generatorwindow

    will popup, Select Client Review Commentunder Document Number Generatorwindow & Click

    Ok. Select Client Review Comments from the drop down menu (2). Add the Client document No. (3),Click on the Auto Number (4) and the number will appear. Click OK to generate number.

    Step 6. Then open CRC Native file which is on your desktopand paste the copied CRC No.under Tracking

    IDand save it.

    1. Browse

    2. Select CRCDocument Number Generator

    5.OK

    Once clicking OK, CRC No. will appear here for copying to the CRC native file

    Add CRC No

    3.Add Client Doc

    4. Auto Generated No. will appear

  • 8/10/2019 WRENCH Working Steps-Consolidated

    47/47

    Step 7. Then Provide CRC Descriptionunder Document Description, Click on Browseand select the CRC

    native file (CRC to be attached).

    Step 8On Clicking Okthe below Document successfully added as a released document window will

    popup, Click Ok.

    1. Document Description

    2. Browse and add the CRnative file

    Tick add as released document

    OK