8/10/2019 WRENCH Working Steps-Consolidated
1/47
Contents
--WRENCH Working Steps
--How to Add Drawings Documents to Tasks in WRENCH
--How To Add TQ Technical Query in Wrench
--How To Reassign a Task from WBS or Users Workspace
--2 STEPS IN ACCESSING SPECTER OR NATIVE FILE FROM YOUR WORKSPACE AND IN W
---While adding a file message comes as Document Number and Sheet Number already ex
---Bulk Replace of files from Workspace
---How To Add RTCC _Reply To Client Comments_ in Wrench
-
8/10/2019 WRENCH Working Steps-Consolidated
2/47
-
8/10/2019 WRENCH Working Steps-Consolidated
3/47
WRENCH Working Steps / Rules of Credit
1st CYCLE
DISC ORIGINATE DRAW STAGE / STAGE
As soon as the originator starts work on a document, the native files are to beuploaded into the relevant task in WRENCH. By this action (uploading of docs.),5% progress is captured / reflected in WRENCH;
Originator can work on the W-drive and do multiple check-ins and check-outsensuring that the latest / updated documents are always uploaded in WRENCHtasks daily;
Originator completes the check list; checking the status boxes for the requiredcheck points and ensuring that these check points are complied;
Once the documents are ready for check, it is to be routed to DISC check stage.The originator may also provide the hard copy for checking.
Documents
attached
5 %Progress
Captured
-
8/10/2019 WRENCH Working Steps-Consolidated
4/47
DISC CHECK STAGE
The checker, checks the documents, scans the check prints and adds the PDF file to thetask. Use Comment File (s) tab to add the IDC comments;
It is then routed back (rejected) to the Disc Originate/Draw Stage).
Once Originator has incorporated the IDC comments and Routed to the Checker,
The checker converts the native file to PDF, adds the same in Squad CheckComment.
IDC Comments
-
8/10/2019 WRENCH Working Steps-Consolidated
5/47
Checker then assigns the sequence for the disciplines required to do the squad check
And routes the document to the MULTI-DISC SQUAD CHECK Stage and with thisaction, 30% progress is captured/reflected in WRENCH.
-
8/10/2019 WRENCH Working Steps-Consolidated
6/47
MULTI DISC SQUAD CHECK
All disciplines involved in squad check get automated e-mails at the start of squadcheck process. Subsequent e-mails will be sent as the routing progresses.
The First discipline checks out the squad Check Comments; Prints the Squad
Check Comments & does the mark ups on the hard copy.
The marked up copy is then scanned and checked in the Squad CheckComments in the WRENCH task.
-
8/10/2019 WRENCH Working Steps-Consolidated
7/47
While Checking In the user should, browse / Selects the required PDF file (Scanned /Marked up) and close route.
The second discipline checks out the squad Check Comments made by the first discipline;Prints the Squad Check Comments & does the mark ups on the hard copy and repeats therest of the steps in the 1
ststage The other disciplines in sequence follow the same steps
and close route one by one;
The final discipline in the SC stage also follows the same steps and routes to DISCREVIEW stage and with this action, 60% progress is captured / reflected inWRENCH.
-
8/10/2019 WRENCH Working Steps-Consolidated
8/47
Following up on squad check is the responsibility of originating discipline. Theoriginator is to follow up closely the progress of the documents through squadcheck team.
PL. NOTE THAT THE SQUAD CHECK COMMENT FILE MADE BY THE 1ST
DISCIPLINE ISUSED BY ALL SUCCEDDING DISCIPINES TO MARK UP THEIR COMMENTS. BY THISCONSOLIDATED COMMENT IS ENSURED / REFLECTED IN ONE SINGLE DOCUMENT.
DISC REVIEW
The checker reviews the SC comments and routes back (rejects) to the DISCORIGINATE / DRAW stage with instructions to incorporate the comments;
The originator incorporates the SC comments and routes to DISC check Stage. Thechecker then bypasses the document directly to DISC APPROVE stage.
DISC APPROVE
Before sending to approval stage, the originating discipline shall provide a hardcopy to approver. Once approver reviews and accepts the documents , this can berouted in wrench to approver stage.
After the approver reviews the document it could be rejected to DISC REVIEW incase of comments or if approved can be routed forward to PE REVIEW stage.
60% Progress
Captured
-
8/10/2019 WRENCH Working Steps-Consolidated
9/47
PE APPROVE
Before sending to approval stage, the originating discipline shall provide a hardcopy to approver. Once approver reviews and accepts the documents, this can berouted in wrench to approver stage.
After the PE review the document, it could be rejected to DISC APPROVE stageand if OK, it will routed forward to DCC Issue stage.
DCC ISSUE
Prepare DCPI and ensure that the Document is routed to DCC workspace for issue.
Once the DCC receives the document through WRENCH and the signed hard copy,the transmittal is prepared;
The PDF of the signed hard copy is added as Specter File(s) to the task;
The transmittal is issued for Review and the document routed to DCC CLIENTCOMMENT stage and with this action 70% progress is captured / reflected inWRENCH.
70% Progress
Captured
-
8/10/2019 WRENCH Working Steps-Consolidated
10/47
DCC CLIENT COMMENT
When the client comments (with approved codes) are received, the same arescanned and added to task as client comments;
DCC routes this to the DISC ORGINATE / DRAW stage.
2nd
/ NEXT CYCLE
DISC STAGE ORIGINATE / DRAW
Based on the approval code/document class, the originator updates the documentto be, re-issued for review or issued for approval or final issue
DCC ISSUE
The cycle is repeated and the document may be :
1. Re-issued for review. With this action the progress stays at 70% inWRENCH.
2. Issued for approval. With this action 80% progress / captured reflected inWRENCH.
DCC FINAL ISSUE
1. Final Issue. With this action 100% progress / captured reflected in WRENCH.
-
8/10/2019 WRENCH Working Steps-Consolidated
11/47
WRENCH Tip Of The Week 2
How to Add Drawings & Documents to Tasks in WRENCH
Step 1.Login to WRENCH, in the main window under My Wrench click on Workspace
Step 2.Under Workspace click on Task.
Workspace
Task
-
8/10/2019 WRENCH Working Steps-Consolidated
12/47
Step 3. . Once clicked on Task it will show the list of Tasks available in your Workspace.
Select the Task in which you want to add the Drawing / Document. (You can group it forease of search E.g. By Project Number)
Step 4.Double click on the Task in which you want to add the Drawing / Document.
Grouping: Drag & Drop Here
Task
List of Task in your Workspace
-
8/10/2019 WRENCH Working Steps-Consolidated
13/47
Step 5.And it will open up the Task Properties Window. In the below half window, there arevarious tabs, Click on Related Itemtab, and inside this window do a Right click, and select Add.
Step 6. In the Related Items to TaskWindow
a) Object Type : Select Document(irrespective of you adding a drawing / document)b) Relation : Select Link, if the drawing or document is the one to be issued to Client
OR Select Refer, if the drawing / document is to be added only for In-housereference purposes, and not to be sent to Client.
c) Mode : Select New, if the drawing / document is not existing in Wrench Or SelectExisting From Wrench.
d) Objects : Select Single, if it is 1 number drawing /document OR Select Multiple, if many
drawings / documents are to be added.e) Click Select.
Add
Related Item
Right Click Here
-
8/10/2019 WRENCH Working Steps-Consolidated
14/47
Step 7. For SingleDrawing / Document, it will open up the below Add DocumentWindow,Click on Browse & Select the document from the path where it is located andclick Open.
Object Type
Browse
Relation
Objects
Mode
Select
Open
-
8/10/2019 WRENCH Working Steps-Consolidated
15/47
Step 8.Give the required details & click ok.a) Document Description as it appears on the Title Block
b) Client Document Number in the same client format as mentioned in the Title lockc) Current Revision Number of the Drawing / Document
d) Sheet Number, e) Sheet Size, f) Number of Sheets
Step 9.Again Click OK
Client Document Number
Revision Number
Sheet Number
Number of SheetsSheet Size
OK
Document Descri tion
OK
-
8/10/2019 WRENCH Working Steps-Consolidated
16/47
Step 10.For Adding Multiple Drawings / Documents to Tasks in WRENCH (Follow the sameStep 1 to Step 6 & at step 6 in Objects select Multipleas shown below)
Step 11. And it will Pop up the Add Multiple Documentswindow, click on Select files
Multiple
Select Files
-
8/10/2019 WRENCH Working Steps-Consolidated
17/47
Step 12. Onceclicked on select files Open window will appear, Click on Look in drop
down arrow & select the files from the path where it is located & click open
Step 12. After selecting the files give the required details (E.g Client, Document Number,
Document description,Current Revision Number, Sheet Number, Number of Sheets,Sheet Sizeetc Use the slider at the bottom of the window to access this information) Click
on Add to Wrench, if no errors, it will show Document Added Successfully, Click OK
Slider
Look in
Sheet NumNumber of
Sheet S
OK
Comments
Document Description
Client Document Number,User Revision Number
Add To Wrench
-
8/10/2019 WRENCH Working Steps-Consolidated
18/47
Step 13.Then click Close.
Step 14.Click OK
OK
Close
-
8/10/2019 WRENCH Working Steps-Consolidated
19/47
WRENCH Tip of The Week
How To Add Vendor TQ (Technical Query) in Wrench
For Adding (uploading) Vendor TQ in wrench please follow the below Steps.
Step1. In Wrench main Window, Under Folders, Maximize Documents Tab.
Click to Maximize Documents 2
Folders 1
-
8/10/2019 WRENCH Working Steps-Consolidated
20/47
Step2. Select respective Discipline, Maximizeand Click on TQ (Technical Query).
Step3. After Clicking on TQ, Right Click on Wrench Desktop, Select Newand Click on Single Document.
Right Click 5Here (Wrench Desktop
Single Documen
Click to Maximize 3
TQ 4
New 6
-
8/10/2019 WRENCH Working Steps-Consolidated
21/47
Step4. On Clicking Single Documentthe below Add Documentwindow will be opened, Click on the Browse,under project ID (as shown below), Enter project No. in Look Forunder Project SearchWindow and select
the respective project by Double Clickingon project No.
Step5. Then TQ Noto be generated.
For generating TQ No, Click on Browse tab (In Document No), on clicking Browse DocumentNumber Generatorwindow will open, Select Vendor Technical Query& Click Ok.
Browse 11
Enter Project No 9
Tab to select the Project 8
Select Project 10
Document Number Generator
VTQ 12
OK 13
-
8/10/2019 WRENCH Working Steps-Consolidated
22/47
Step6. On Clicking OKthe below Generate Numberwindow will open, Select the Sender Codeby Clickingon Sender Code Taband Select the Receiver Codeby Clicking on Receiver Code Tab, then Click on MR
NO.
Step7. On Clicking on MR Numberthe below Manual Entrywindow will open, type the corresponding MR
No for this TQ (You need to type in the Document Genealogy (e.g. ECMR) and No (e.g.005) as shown belowand Click Ok
Note:
*For all Veco Generated MRs the corresponding MR No which will be mentioned in between the TQ no
shall be Vecos MR No.
*For all CPE Generated MRs the corresponding MR No which will be mentioned in between the TQ no
shall be Client MR No.
E.g. For Veco Generated MRs
Generator Number window
MR Number 16
Sender Code 14
Receiver Code 15
MR Number 16
MR Number 17MR Number 17
Ok 18
MR Number 17
-
8/10/2019 WRENCH Working Steps-Consolidated
23/47
Step8. Then Click on Correspondence Typeand select Technical Query (Q) (Double Click).
Step9. Then Click on Auto Numberand copy the No generatedfrom Preview of generated numberand
Click Ok.
Doc Genealogy & NO
Correspondence Type 19
Auto Number 21
Preview of generated No. 22
Technical Query 20
Ok 23
-
8/10/2019 WRENCH Working Steps-Consolidated
24/47
Step10. Then open the TQnative file and Paste the copied TQ Nounder Query No / & type in the Date thensave and close the file.
Eg.For CPE Generated MR
CPE Generated MRs the corresponding MR No which will be mentioned in between the TQ no shall be Client
MR No as shown below
TQ No & Date 24
-
8/10/2019 WRENCH Working Steps-Consolidated
25/47
Step11. Then Enter TQ Description. After entering TQ Description, Click on Browse, Select TQ Native file
andClick Open. After selecting the file tick on Add as released document(TQ are added as a releaseddocument as it not going through any Workflow) and click Ok.
You can also send Notification to your Team from Wrench that the following TQ has been added in Wrench.
Open 28
Q Description 25
Browse 26
Native file 27
Ok 29
Client MR No.
-
8/10/2019 WRENCH Working Steps-Consolidated
26/47
Step12. For sending Notification from Wrench after Add as released documentis ticked, click on
Notification.
Step13. On clicking Notificationthe below Notificationswindow will open, click on Browseto select User.
Notification 31
Browse 32
Add as Released 30
-
8/10/2019 WRENCH Working Steps-Consolidated
27/47
Step14. On clicking Browse, the below User Listwindow will appear. You can select either by grouporprovide aUser Name/ Login Nameto initiate a Search and then List of users satisfying the specified search
criteria will be returned. Then Select the User from the Available Users list and click on the right arrow.
Same way you can also remove Users from the Selected User list by selecting the users and clicking on the LeftArrow. Then click on Ok.
Step15. Again ClickOk.
OK 39
Available Users35
Users to be removed
Login / User name 34
User Group 33
Left Arrow 38
Right Arrow 36
Ok 40
-
8/10/2019 WRENCH Working Steps-Consolidated
28/47
Step16. Then again click Okto save the documents and sent Notification.
Step17. On Clicking Okthe below Document successfully added as a released document window will
open, Click Ok.
OK 41OK 41
OK 42
-
8/10/2019 WRENCH Working Steps-Consolidated
29/47
WRENCH-Tip of The Week
How To Reassign a Task / Deliverable from WBS / Workspace
Reassigning a Task / Deliverable from WBS / Users Workspace is much easier andtime saving as compared to the Reassign Utility. Please follow the below steps toreassign from WBS / Workspace.
Step 1. UnderWBS / Workspace, select the Task you want toReassign and Doubleclickon it.
.
Select the Task & Double Click
-
8/10/2019 WRENCH Working Steps-Consolidated
30/47
Step 2.On Double Clicking the below Task Propertieswindow will popup. Click onReassign Resource.
Step 3.On clicking Reassign Resource, the below Reassign Resourcewindow willappear. Click on the current stage(From where you want to reassign resource)
Current Stage
Reassign Resource
-
8/10/2019 WRENCH Working Steps-Consolidated
31/47
Step 4.On clicking current stage, resources for current stage will be available. Click onBrowseto assign New Resource.
Step 5.On Clicking Browsethe below User listwindow will appear with list of current
users of the stage. Remove the users by clicking on the (
-
8/10/2019 WRENCH Working Steps-Consolidated
32/47
Step 6.Provide a User Nameor Login Nameto initiate a Search, List of users satisfyingthe specified search criteria will be returned. Select the Userthen click on Right arrowand click OK.
Note:If the user is not available in the Available users list then untick on Filterresources based on project. Aswhen Filter is ticked then it will filter with the list ofresource available in the Project Resource. If the user is not a resource of that projectthen the user name will not be available. On removing the tick the resource will be taken
from the Masters.
Project Resources
Login name to Search
OK
Ri ht arrow
Selected User
Available Users
Filter
-
8/10/2019 WRENCH Working Steps-Consolidated
33/47
Step 7.On Clicking OK, the selected user will be in the New Resourceslist. Givecommentson Reaasign and click on Reassign.
Step 8.On clicking Reassign Resources are reassigned successfully message willpopup. Click Ok.
OK
Reassign
Comments on Reassign
New Resources
-
8/10/2019 WRENCH Working Steps-Consolidated
34/47
I. ACCESSING FROM WBS.
Step 1.1.Open WBS, e.g. [WBS-401910], and select a task which you want to view the specter or the nativefile, as shown below.
Step 1.2. Click VIEWoption to view the native application of the file and click VIEW SPECTER to View thlatest available Specter Copy (PDF File). The document will be automatically displayed, upon clickinthese options.
WRENCH TIP OF THE WEEK
2 STEPS IN ACCESSING SPECTER/NATIVE FILE FROM YOUR WORKSPACE AND IN WBS
WBS-401910
Selected task which you want to view the
specter or native file
View
View Specter
-
8/10/2019 WRENCH Working Steps-Consolidated
35/47
II. ACCESSING FROM YOUR WORKSPACE.
Step 2.1.Open your workspace, and select a task which you want to view the specter or the native file, ashown below.
Step 2.2.Click VIEW ATTACHED DOCUMENToption to view the latest native application of the file anclick VIEW SPECTER to View the latest available Specter Copy (PDF File). The document will b
automatically displayed, upon clicking these options.
WORKSPACE
Selected task which you want to view thespecter or native file
View
View Spec
-
8/10/2019 WRENCH Working Steps-Consolidated
36/47
WRENCH Tip Of The Week 3
While adding a file message comes as Document Number and Sheet
Number already exists
Step 1.When a message popup Document Number and Sheet Number already
exists, Click OK.
Ok
Document Number and Sheet Number already exists
-
8/10/2019 WRENCH Working Steps-Consolidated
37/47
Step 2.After clicking Ok, it will go back to Add DocumentWindow. Click Cancel.
Step 3. Once clicked on Cancel,Related Items To Taskwindow will appear. Select
Existing from Wrench, and then click on Select.
Existing from Wrench
Select
Cancel
-
8/10/2019 WRENCH Working Steps-Consolidated
38/47
Step 4.After clicking Select, the below shown Document Searchwindow will appear,
click Search, it will show the search result in the below half window Double click ondocument from the search result.
Step 5. OnceDouble Clicked, the Document will added as shown below, clickOK
Search
Document Added
Double Click
-
8/10/2019 WRENCH Working Steps-Consolidated
39/47
Many cases users have to replace multiple documents from Workspace, particularly documents like P&IDs &Isometrics which are created & issued in bulk.
WRENCH provides a convenient method of replacing documents in bulk, irrespective of how many files to bereplaced.
Step 1:
Select the tasks from Workspace whose file needs to be replaced. Right click select Replace.
WRENCH TIP OF THE WEEK
BULK REPLACE OF FILES FROM WORKSPACE
-
8/10/2019 WRENCH Working Steps-Consolidated
40/47
Step 2:
On selecting Replace an intermediate interface opens as below.
Step 3:
WRENCH can automatically select the files that needs to be replaced against each task/deliverable, for whichuser needs to select the Matching option available in the Multiple Replace Manager window.
From Matching Option user needsto select Advanced Option.
-
8/10/2019 WRENCH Working Steps-Consolidated
41/47
Step 4:
From Properties option user needs to select one of the matching criteria between the existing file in WRENCH& the file to be replaced. In most cases the file available in WRENCH & the new file being replaced will havethe same File Name.
If yes, please select the matching option as File Name from the drop down against Properties.
Step 5:
After Matching Option is selected, click ok. From the Multiple Replace Manager window, use Select Folderoption to select the folder in which the files which needs to be replaced are available (All the files that needs tobe replaced needs to be in one folder).
-
8/10/2019 WRENCH Working Steps-Consolidated
42/47
Clicking Select Folder will open a window to select the folder in your PC.
Step 6:
Select the folder containing the files to be replaced. Click Ok.
User can give his comments on replace in the option available & then click Apply to selected Files & then ClicOK to have the files replaced.
User can also replace the files one by one, by expanding the tree to find theSelect Fileto replace file.
-
8/10/2019 WRENCH Working Steps-Consolidated
43/47
WRENCH Tip Of The Week
Addition of CRC (Client Review Comments) in Wrench
Earlier we used to term all Response to Client Comments as RTCC. Now it is CRC (Client Review Comments)
CRCs are basically CH2M HILLs reply to the comments given by the client on the documents submitted.
CRC for a client comment is provided along with the subsequent revision of the document.
CRC is originated & owned by the department engineers. CRC is added to CRC folder defined under each ofthe department folder structure in WRENCH.
For adding CRC please follow the below steps.
E.g. If a Civil Engineer wants to add CRC.
Step1. In Wrench main Window, Under Folders, Maximize Documents Tab.
Click to Maximize Documents
Folders
-
8/10/2019 WRENCH Working Steps-Consolidated
44/47
Step2. Select respective Discipline, Maximizeand Click on RTCC/CRC.
Step3. After Clicking on CRC, Right Click on Wrench Desktop, Select New, Click on Single Document.
Click to Maximize
CRC
1.Right Click Here
(Wrench Desktop)
2.New 3.Single Document
-
8/10/2019 WRENCH Working Steps-Consolidated
45/47
Step4. On Clicking Single Documentthe below Add Documentwindow will popup, Click on Browse, under
Project No., Enter project No in Look Forunder Project SearchWindow and select the project by Double
Clickingon project.
2.Enter Project No
1. Browse to select the Pr
3.Select P
-
8/10/2019 WRENCH Working Steps-Consolidated
46/47
Step5. Then CRC Nohas to be generated.For generating CRC No, Click on Browse, on clicking Browse Document Number Generatorwindow
will popup, Select Client Review Commentunder Document Number Generatorwindow & Click
Ok. Select Client Review Comments from the drop down menu (2). Add the Client document No. (3),Click on the Auto Number (4) and the number will appear. Click OK to generate number.
Step 6. Then open CRC Native file which is on your desktopand paste the copied CRC No.under Tracking
IDand save it.
1. Browse
2. Select CRCDocument Number Generator
5.OK
Once clicking OK, CRC No. will appear here for copying to the CRC native file
Add CRC No
3.Add Client Doc
4. Auto Generated No. will appear
-
8/10/2019 WRENCH Working Steps-Consolidated
47/47
Step 7. Then Provide CRC Descriptionunder Document Description, Click on Browseand select the CRC
native file (CRC to be attached).
Step 8On Clicking Okthe below Document successfully added as a released document window will
popup, Click Ok.
1. Document Description
2. Browse and add the CRnative file
Tick add as released document
OK