standard contract forum 3 november 2005 13.30 customer suite, bt centre, london
TRANSCRIPT
www.btwholesale.com
.
Standard Contract Forum 3 November 2005
13.30Customer Suite, BT Centre, London
www.btwholesale.com
Standard Contract Forum Thursday 3 November 2005
AGENDA
1 Introduction and Notes of Previous Meeting
2 Consult 21
3 Lead Times
4 Review of New and Amended Schedules
5 Geographic VOIP Ranges
6 TMP Update
7 Any Other Business
www.btwholesale.com
Consult21New Working Groups
The Groups
The People
The Objectives
28th October 2005
Nigel ScottConsult21 4
Update Commentary
The scope and interactions of the WGs have been modified based on feedback and internal Buddy “war gaming”, in particular:
•The work of the Legacy Working Group is subsumed into the appropriate Product Working Group
•A new “WG Management” group is formed
•The WG scopes have been fleshed out
Consult21 Working Group Structure
WG
Man
ag
em
en
et
& C
o-C
hair
Co-
ord
inati
on
Steering Board
To be a co-ordination and
escalation point
Implementation & Migration
To make tomorrow happen
• Operational Planning
• Implementation
Communications
To keep end users informed
Architecture & Framework
GroupsProviding the underpinning
Systems & ProcessesNetwork Structure, Network Hooks
Product GroupsBroadbandLine AccessInterconnect & PortfolioPoint to Point
Contract GroupCommercial Group
Top Level Themes
Architecture &Framework
Capability timelines
LegacyWhat do we do with whatwe've got
21CN NewWhat (new) do we want and when
Contract &Commercial
How we do business
Implementation& Migration
Final say on delivering products/services
Product Groups
The Product WGs address both legacy transition and 21CN products
Consult21 Themes & Contacts
Industry Co-Chair Consult21 ‘Buddy’
Key Player/s
Commercial Group tba Chris Evans tba
Contract tba n/a Keith Mitchinson
Communications Claire Wallace (Energis)
Andy Rudman Joe Kelly
Implementation & Migration Chris Danzelman (C&W)
Liz Walsh Mike Cook
Broadband Gavin Young (Bulldog)
Tom Saville
- LLU Paul Barratt (O)
- Datastream / FAS Bill Jones
- IPStream Andy Jugg
Line Access Justin Orde (Spitfire)
Tom Saville
- WLR (legacy migration) "Colin Reith" (O)
- MSAN Voice Access product(s) Mike Ward
Interconnect & Portfolio Paul Griffin (Energis)
Chris Evans Mike Ward
Point to Point John Lee (Energis) Tom Saville
- PCs & PPCs Rob Thomas
- Ethernet (WES) Peter Newton (O)
- Backhaul (BES) tba
Systems & Processes Nancy Saunders (Kingston)
Tim Short Graham CraneMark Gray
Network Structure Paul Rosbotham (C&W)
Chris Evans Tim Wright
Network Hooks Antony Millington (Energis)
Tim Short Andy Fielden
WG Management Bill Du Cann Guy Bradshaw
tba (O)
Key Players & C0-Chairs to be re-confirmed 8
www.btwholesale.com
Consult 21
Working Groups
Proposed Scopes
(Updated)
9
WG Management Group: Scope
Objective / Purpose
To own and manage the obligatory products transformation plan (with clear understandings of what constitutes no change, transfer engineering and equivalent 21CN products and where these will apply and impact migration plans)
To manage the cross-WG Issues and Requirements register(s) to facilitate the WGs to achieve their objectives
To monitor and report on the critical delivery path for the Plan, instigating appropriate actions to resolve any problems.
To monitor the Consult21 process, proposing improvements where necessary
Product Working Group ScopesBroadband, Point to Point, Interconnect & Portfolio and Line Access
Objective / Purpose
To provide the detailed trajectory and critical path plans for those products contained within the obligatory products transformation plan, in particular addressing withdrawal and transformation issues.
To agree the:
outline requirements / product descriptions for:
new products/services
transformation products e.g. VIECs
commercial and service wrap for the above products
introduction timeframes for the new products
Scope
Obligatory products during the transformation phase to BTs 21CN
Architecture & Framework Scope Systems & Processes, Network Hooks and Network Structure (e.g. MSAN) Working Groups
Objective / Purpose
To adopt interface standards, rules, functionality, principles, frameworks etc that govern the development and implementation of networks and systems.
To ensure that as far as is practicable individual product needs are catered for in a consistent way with a minimum of re-invention
Application of standards, inherent resilience, impairment standards, planning rules, firewalls etc
Scope
Builds on UK standards from NICC etc.
Implementation & Migration Scope
Objective / Purpose
To create an assured environment that enables the migration of voice and non-voice products off affected BT switches and platforms
To minimise any potential negative impact of migration on end users
To capture learning from the migration processes for application to BAU.
To introduce new products as defined by the Product WGs.
Scope
All obligatory products and those non-obligatory products within the remit of Consult21 to achieve the above objectives
Legacy vs New Products
Interconnect & Portfolio
Broadband
Line Access
Point to Point
Legacy 21CN New
Point to Point includes all TDM and Ethernet type services
All Product Working Groups have both legacy & new product opportunities.
Many of the same people will be involved in Legacy & New discussionsLegacy work will conclude before New concludes, but they will overlap
Working Group
Thank you
This is an evolving Consultation
Your feedback on the structure and operation is very much
appreciated
www.btwholesale.com
MIGRATION PROPOSAL:CONSULTATION FRAMEWORK
Nigel ScottThis presentation provides an overview of the National Migration
Proposal and its associated Consultation
PRE- CONSULTATION FEEDBACK:SUMMARY
8 responses were received
Feedback fell into 3 categories:
The data set
Additional information relating to DLE closure or clarifications has been incorporated into the revised proposal
Clear methodology around document control included
Consultation Framework
Feedback received is consistent with Consultation Framework
Adjudication process defined for Consultation Phase only
Additional Information required to enable planning:
Voice Migration Methodology “Strawman” confirmed to facilitate Bi-lateral discussion
Development of a Roadmap identifying when additional information will be available
MIGRATION PROPOSAL & DATASET:ISSUE 2
Audience:
Communications Providers with whom BT has direct interconnect or LLU relationship
Objectives:
Provides details of the 21CN locations and high-level site-based details of how the existing infrastructure will be mapped on to the 21CN infrastructure enabling these Communications Providers to understand the implications for their existing network infrastructure
To be viewed as a statement of BT’s current likely sequencing of migration activity, subject to successful resolution of a series of complex commercial and technical issues
Reflects regional workforce constraints in scheduling work
Smoother ramp up of migration activities to reflect training and realistic productivity performance improvements
Outlines the consultation process which will operate from issue to 16 Dec 2005
Dataset disclosure:
Through NIPP or other appropriate closed user portal
Subset of locational information available through NISCC only
MIGRATION PROPOSAL:CONSULTATION SCOPE
Aim is:
Production of a Plan of Record for business planning purposes (Jan 06)
BT seeks views on the most appropriate and timely approach to:
reach acceptable solution to all parties – recognising the schedule will be fine tuned to reflect operational needs as migration proceeds
effective change control management
minimising & anticipating the impact on customers
MIGRATION PROPOSAL:CONSULTATION FRAMEWORK & TIMETABLE
(21/10 – 02/11)•CP Impact Analysis
CONSULTATION (22/10 – 16/12)
02/11-02/12•Bi-laterals
•Interconnect CP’s
•Service Provider CP’s
•Multi-lateral consultation through IMWG & expert groups
05/12 – 16/12• BT/Industry Board
reviews/agrees Migration Proposal Change Requests
• Expert Groups on Migration methodology
• Communicate outcome of Change Requests to CP’s
• IMWG – 16/12/05
MIGRATION PROPOSAL:BI-LATERAL TOPICS
Technical & Operations focus on three broad areas:
Implementation Considerations and Impacts
sequencing, timing, freeze periods, sensitive customer impacts
asset and operational optimisation, NGN business plan considerations
Migration Plan Change Requests
recording of Changes Required
recording of impacts & rationale
Migration Methodology
transfer engineering methodologies to be used to support Migration
minimising end user negative impact and operational resource optimisation
CONSULTATION PHASE:CHANGE CONTROL & ADJUDICATION
Change Requests documented at Bi-laterals
Change Requests circulated to industry:
anonymous basis & excluding rationale
other CP’s identify impacts if such a change were to be accepted by BT
enables the acceptance or rejection to be done in light of impacts across industry
BT Impact Analysis undertaken
W/C 12/12/05, BT and Industry convene a pre agreed Adjudication Board:
Accepts or rejects each Change Request
Membership is 3 from BT and 3 Industry nominees, under BT chairmanship
Chair has casting vote
www.btwholesale.com
STANDARD CONTRACTS FORUM
3 November 2005
Geoff Wills
Interconnect Links Lead Times
Standard Contract Forum Thursday 3rd November 2005
Order Original timescale
New or proposed timescale
Comments
Traffic route through new point of connection
6 months 6 months No Change
New traffic route through an existing POC
65 days 45 days New orders from date to be briefed
New traffic route through an existing POC with IEC
75 days 65 days Agreed at General Contact Review
Route augmentation 25 days 25 days No change
Route augmentation with IEC
35 days 25 days Agreed at General Contract Review
Standard Lead Time Reduction from 65 to 45 working days
Annex ‘A’
11.1.3 “New Traffic Routes between Switch Connections through an established Point of Connection using the same technology, including the provision of new Traffic Routes by way of additional Customer Sited Interconnect from a particular Operator site:”
11.1.5 “New Traffic Routes over IECs at a Switch Connection using the same technology:”
11.1.7 “Capacity Re-arrangements involving the provision of new Traffic Routes using the same technology or a new technology already in service at the relevant Switch Connection:”
11.1.9 “Capacity Re-arrangements involving the provision of new Traffic Routes requiring IECs using the same technology or a new technology already in service at the relevant Switch Connection:”
.
www.btwholesale.com
Standard Contract Forum Thursday 3 November 2005
Keith Mitchinson
3 November 05
www.btwholesale.com
Standard Contract Forum Thursday 3 November 2005
REVISED SCHEDULE:
Schedule 143 – Carrier Pre – Selection
WITHDRAWN SCHEDULE:
Schedule 153/153A – Supply of Operator Branded Telephone Directories
www.btwholesale.com
Standard Contract Review
Briefing on:
BT and Operator Geographic NVS (New Voice Service Calls)
3rd November 2005
Les Stevens
Product Manager BT Core Network Services - Interconnect
Contents
1. Product overview BT / Operator NVS Services
2. Ofcom Description summary
3. Current position Operator & BT NVS
4. BT Service update.
5. Applicable Contact Schedules – BT Proposal
6. Customer Feedback?
7. Next Steps?
Schematic Diagram of Operator NVS Geo Call Termination
Diagram below shows a typical application (may also be VOiP Originated?)
Customer Originates a Call to Operator Geo NVS number.
BT TDM Network
TDM Interconnect
Operator PSTN
(TDM to IP conversion)
IP ‘CloudDelivery of IP Geo NVS call
Schematic Diagram of BT Geo NVS Call Termination
Diagram below shows a typical application (May also be VOiP originated).
CP Customer Originates a Call to BT Geo NVS number.
CP TDM Network
TDM Interconnect
BT PSTN(TDM to IP conversion)
IP ‘Cloud’Delivery of IP Geo NVS call
Ofcom Description - Extract from Ofcom statement of the 6/9/04 “Numbering Arrangements for New Voice Services”
Location Independent Electronic Communications Services (LIECS) Calls.
The Ofcom description of the characteristic of a Location Independent Electronic Communications Services as defined in their statement of the 6/9/04 “Numbering Arrangements for New Voice Services” can be summarised as follows:-
•The numbering plan of the Communications Provider offering the service has no geographic significance.
•The location of the customers apparatus identified by a given telephone number at the time of use is not permanently associated with a particular network termination point.
•No revenue sharing with end users is allowed.
•Number translation to a geographic number is not involved and the service is not a mobile service.
• Service does not have to offer PATS.
Current position Operator & BT NVS.
• Increase in Operator Geo code builds – believed to be NVS driven.
• BT Issued Interconnect Notification 05073 (12/08/05)
• BT Notification of opening on Geo ranges associated with NVS (19/08/05).
• Draft Geo NVS schedule offered for discussion.
• Debate unfortunately deferred to Nov Meeting.
Update on BT Launch Of Geo NVS.
• Originally notified on 19th August.
• Original service ready date 4th October 2005.
• Some 10K allocations but mainly at Ofcom request sub allocations @ 1K.
• Problems encountered building @ 1K using automated systems.
• Manual build progressing.
• Upgrade to automated required – funding now agreed.
• New target completion by end April 2006.
• BT NVS Platform connected to 10 Trunk Switches (as per notification)
• Interconnection at these POI = Single Tandem rates.
• BT to issue revised timescale notice.
Contract Schedule for Geographic NVS ?
• Are Operators trading Geo NVS with BT under existing Geo Schedules?
• If so is this a sustainable position?
• Feedback to BT Proposed Schedule?
• Next steps to regularise this anomaly?
www.btwholesale.com
www.btwholesale.com
Standard Contract Forum
Briefing on:
Technical Master Plan3rd November 2005
Kevin Young
BT Interconnect & Numbering Services
Contents
1. The Definition
2. BT’s view of the TMP content
3. TMP Information ownership & retention
The Definition
Contract (Annex D) Definition
Current:
“Technical Master Plan” a document recording details of the Points of Connection and the plans for development of further Points of Connection;
Proposed:
“Technical Master Plan” a document, retained and owned by both Parties, recording details of the Points of Connection and the plans for development of further Points of Connection;
BT’s view of the TMP content
There are three aspects of information that should be recorded within the TMP, these are:
• The details of the interconnect between the Parties’ Systems and the plans for future developments relating to interconnect. Typically, but not solely, exchanged through the Capacity Profile/ACO process.
• The physical arrangements and Number Ranges, or part thereof, for each of the Traffic Routes on an Interconnect Link. Information shall be provided in accordance with the Provisioning Manual. Typically, but not solely, exchanged through the Routing Plan process.
• The allocation of Interconnect Capacity to transmission capacity by means of Tributary allocation charts as set out in the Provisioning Manual.
The information relating to these three areas are, in the main, exchanged within documentation set out within the Provisioning Manual.
TMP Information ownership & retention
The information that forms the TMP should be held by both BT and the CP in order for both to manage the interconnection between the two networks. Therefore, both BT and the CP are responsible for ownership and retention of this information.
Whilst the information between BT and the CP is for the most part exchanged within documentation set out within the Provisioning Manual, it is for each to identify the means with which such information is recorded within their own systems.
It is recognised by both BT and the CP that, from time to time, information may be lost or its accuracy be questioned. Therefore, it is accepted by both BT and the CP that requests for information exchange over and above the normal flow may occur. These requests are on an occasional basis and the scope is kept to a minimum in order to ensure that any such requests are reasonable. In such circumstances both BT and the CP would generally comply with requests of this nature.
www.btwholesale.com
AOB
3 November 2005