yakima t.o.c. load assist
DESCRIPTION
Presenters: Michael Dixon Ben Gheliuc Group Members: Haidar Al Gharash Daniel Gheliuc Fue Her Zach McCurter Capstone Advisors: Faryar Etesami Evan Thomas Yakima Sponsors: Mark Elliot Chris Sautter. Yakima T.O.C. Load Assist. overview. Introduction / Background - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/1.jpg)
YAKIMA T.O.C. LOAD ASSIST
Presenters:Michael DixonBen Gheliuc
Group Members:Haidar Al GharashDaniel GheliucFue HerZach McCurter
Capstone Advisors:Faryar Etesami
Evan Thomas
Yakima Sponsors:Mark Elliot
Chris Sautter
![Page 2: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/2.jpg)
OVERVIEW Introduction / Background Internal/External Customers PDS Criteria House of Quality Technical Risk Management Project Timeline Summary
![Page 3: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/3.jpg)
BACKGROUND Current Yakima Designs.
![Page 4: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/4.jpg)
COMPETITORS Thule
![Page 5: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/5.jpg)
Malone
![Page 6: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/6.jpg)
PREVIOUS ATTEMPTS Yakima’s first load assist design
![Page 7: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/7.jpg)
![Page 8: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/8.jpg)
TARGET PERSONA Average 45 year old 5’ 2” woman
Paddles a sea kayakRides a bikeDrives a Subaru Outback
![Page 9: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/9.jpg)
INTERNAL CUSTOMERS Yakima PSU Capstone Team Dr. Evan Thomas Dr. Faryar Etasami PSU Machine Shop
![Page 10: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/10.jpg)
EXTERNAL CUSTOMERS Chris Sautter Mark Elliot Yakima Legal Department Yakima Financial Department End-User
Target Persona
![Page 11: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/11.jpg)
PDS CRITERIA Ergonomics
Ease of use for target personaMax load assist
CostTarget retail - $500
SafetyPinch points
Clear existing IP/Patents Testing
Yakima internal standards – ISO #
![Page 12: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/12.jpg)
HOUSE OF QUALITY
![Page 13: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/13.jpg)
TECHNICAL RISK MANAGMENT
Load Assist mechanism fails Clearence / height Weight Cost Testing
![Page 14: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/14.jpg)
PROJECT TIMELINETask Assign Date Finish Date Tasks due
Discussion of ideas and scope of project Dec-13-11 Jan-11-12
Internal and External Research Jan-9-12 Feb-3-12
Draft Design Jan-23-12 Feb-29-12
PDS Report Jan-16-12 Jan-30-12 Jan-30-12
PDS Report Presentation Jan-30-12 Feb-13-12 Feb-13-12
Evaluation Of Drafted Design Feb-13-12 March-5-12
Design/make Product Feb-20-12 March-15-12
End of the Term Progress Report Feb-27-12 March-12-12
Progress Report Presentation Feb-27-12 Feb-27-12 Feb-27-12
Presentation design to Sponsor March-12-12 March-14-12
Testing and Prototyping March-14-12 April-4-12
Redesigning Concept And Prototype March-21-12 April-18-12
Repeat Testing April-11-12 April-25-12
Manufacture Final Product April-25-12 May-23-12
![Page 15: Yakima T.O.C. Load Assist](https://reader034.vdocuments.net/reader034/viewer/2022051218/56815ea5550346895dcd32b2/html5/thumbnails/15.jpg)
QUESTIONS?