yello belt %282%29

40
Question Option 1 Option 2 Option 3 Option 4 Option 5 66807 1.2 3.4 233 87 / 328 14 / 87 87 / 14 328 / 87 87 ÷ 328 14 / 87 Boundaries Define Validity Known risks All of above In a six sigma process, there are ______defects per million opportunities SWOT is an acronym for: strengths, weaknesses, opportunities , threats statistics without tables sensory Weibull ordinal tools success wields optimal teams none of the above There are 14 different defects that can occur on a completed time card. The payroll department collects 328 cards and finds a total of 87 defects. 87 / (328 × 14) There are 14 different defects that can occur on a completed time card. The payroll department collects 328 cards and finds a total of 87 defects. 87 ÷ (328 × 14) 87 / 14 .1,000,0 00 87*1,000, 000 /(14*328) A random sample of 2500 printed brochures is found to have a total of three ink splotches. The rate of ink splotches in PPM 1,000,000/ (2500*3) (2500/ 1,000,000)* 3 (3/2500)*1, 000,000 (3 *2500)/1,000, 000 A business case of portion of a project charter would be likely to contain: A summary of strategic reasons for the project A problem or goal statement Resources available to team. Six sigma project methodologies normally begins with what initial step? Problem definition Project charter Champion approval Sampling plans are routinely selected based on their: Applicabili ty None of above In the measurement of distance between 2 points, which of the following factors is LEAST likely to be influenced by the person making the Precision of measurement Accuracy of measurement Calibration of measurement True distance between two points. The primary factor in the successful implementation of six sigma is to have The necessary resources The support and leadership of top management Explicit customer requirement s A comprehensive training program.

Upload: rajni-bhagat

Post on 18-Jan-2016

430 views

Category:

Documents


17 download

TRANSCRIPT

Page 1: Yello Belt %282%29

Question Option 1 Option 2 Option 3 Option 4 Option 5

66807 1.2 3.4 233

SWOT is an acronym for:

87 / 328 14 / 87 87 / 14 328 / 87

87 ÷ 328 14 / 87

Boundaries

Define

Validity Known risks Applicability All of above

In a six sigma process, there are ______defects per million opportunities

strengths, weaknesses, opportunities, threats

statistics without tables

sensory Weibull ordinal tools

success wields optimal teams

none of the above

There are 14 different defects that can occur on a completed time card. The payroll department collects 328 cards and finds a total of 87 defects. DPU =

87 / (328 × 14)

There are 14 different defects that can occur on a completed time card. The payroll department collects 328 cards and finds a total of 87 defects. DPMO =

87 ÷ (328 × 14)

87 / 14 .1,000,000

87*1,000,000 /(14*328)

A random sample of 2500 printed brochures is found to have a total of three ink splotches. The rate of ink splotches in PPM is:

1,000,000/(2500*3)

(2500/ 1,000,000)*3

(3/2500)*1,000,000

(3 *2500)/1,000,000

A business case of portion of a project charter would be likely to contain:

A summary of strategic reasons for the project

A problem or goal statement

Resources available to team.

Six sigma project methodologies normally begins with what initial step?

Problem definition

Project charter

Champion approval

Sampling plans are routinely selected based on their:

None of above

In the measurement of distance between 2 points, which of the following factors is LEAST likely to be influenced by the person making the measure?

Precision of measurement

Accuracy of measurement

Calibration of measurement

True distance between two points.

The primary factor in the successful implementation of six sigma is to have

The necessary resources

The support and leadership of top management

Explicit customer requirements

A comprehensive training program.

Page 2: Yello Belt %282%29

Mean Median Range

Median Mode Average

68% 95% 99.73% 80%

CTQs are defined by

A-B-D

All of above

Project scope helps to:

Business case Schedule

Interviews Surveys On-call meetings

Goal statement SIPOC Scope

All of above

All of above

Apart from the standard deviation what is the measure for variation

Process capability

Which if the following gets affected MOST by extreme values.

Standard deviation

For a perfectly normal distribution, how many % of data points should lie between +/- 2 standard deviations?

What does the letters in the acronym SIPOC stand for?

Define Supplier; Input; Procedure; Output; Customer

Supplier; Input; Process; Output; Customer

Select; Investigate; Proceed; Obey; Control

Select; Inspect; Process; Obey; Control

None of the above

Project Champion

Finance analyst

Company’s objective

The Project team keeping the Customer's view in mind

Which are the elements of a project charter?

Business Case & Problem Statement

Goal statement and project scope

Data collection plan

Project milestones

What are the key drivers of a project selection?

Voice of customer

Employee survey results

Business critical Ys

Customer satisfaction survey results

Identify team members

Identify the boundary of the project

    Eliminate non-value adding activities

Scope value added activities

None of above

The CTQ for the customer was "Defect Free Delivery ". The Project team wants to improve this CTQ given by the customer. Which Project Y measure best reflects the CTQ?

Number of Customer Complaints

Number of Post Delivery Defects

CSS ratings on a survey

Cost involved in warranty Claims

None of above

Which among the following is NOT a part of Project Charter?

Scope statement

Goal statement

Operational definition

The most expensive VOC collection tool is

Customer complaints

In a Project Charter the boundaries of the project are given under which of the following option

Problem statement

Business case

CTQs are customer needs translated into critical process requirements that are:

Specific and measurable

Short and specific

Effective and efficient

None of above

Which of the following questions does the business case help answer:

Why is this project important to do?

Why is this important to do now?

What are the consequences of not doing it now?

None of above

Page 3: Yello Belt %282%29

A "Process" in a SIPOC is:

A SIPOC is used to :

customer CTQs Measures Customers

QFD Process Map FMEA Kano Model

Supplier Processor Manager Customer GB

QFD Feedback Escalations Observations Survey

Surveys Phone calls Interviews

Project Goal Project Scope Project Heading Timelines

All of the above

Interviews Surveys Focus Groups

Charter Run Chart SIPOC QFD

Define Interview Survey

the materials, resources or data required to produce an output

the internal or external recipient of a product or service

One that takes inputs, adds value and produces an output

Is the product or service produced

AS - IS Process map

Study variation in the process

Analyze root causes

Check for out of control situations

Demonstrate MSA

Finds out the major touch-points in current process

One of the deliverables of Define Phase

High Level Process Map

Root Cause identification

Solution Generation

Process Improvement

Pareto Chart

Process scope must include:

Value added & non-value added analysis

Process start and stop points

Project Risks are identified using

Cause & Effect Diagram

The key deliverables of the Define Phase in a Six Sigma project are:

Determine goals of your project and high level process map

Determine project CTQs

Both the above

None of the above

The recipient of the process output is

To learn what is important to customers, which VOC tool would you ideally choose:

Which is not a method for collecting VOC data

Personal Visits

Advertisement

Which of the following are not included in the project charter?

Tools to be used

Which of the following tools should be used to obtain Voice of the Customer data

Surveys, Interviews or Focus Groups

Customer Relation Complaints

Meetings with client

None of the above

Which of these is a quantitative VOC tool:

Weekly customer reviews

Customer steering committee meetings

Which of these tools is not likely to be used in the Define phase:

Least effective way of data gathering about customer information is:

Weekly reviews

Customer Complaint Data

None of the above

What are the two types of data you will encounter?

Variable and Special

Variable and Attribute

Variable and Common

Special and common

None of the above

Page 4: Yello Belt %282%29

VOC CTQ SIPOC Defect

Clear Output DPU TPO DPMO

Variance Median Span Range

House of Quality Covers

Defect density is an:- Discrete data

Customer Minitab Process

99.73 68 1 95 99966

Mean Median Mode Risk

Mean Median Sigma Level DPMO

When we translate Voice of Customer information into measurable characteristics, what is produced?

Operational Definition

How do we describe a CTQ to ensure consistent interpretation by more than one individual?

Using a Golden Rule

Using a Gage R&R

Using an Operational Definition

Using Pareto Principle

Clarifying it with Black Belt

Parts per million is also named commonly as:

Total Opportunities

Which one of the following is not a measure of variation (spread) in a distribution?

Customer requirements, product characteristics, competitive analysis

DOE, force field analysis, competitive analysis

Product characteristics, defect level, Sigma level

Customer requirements, field failure rate, MTBF

None of the above

The fundamental concept of Six Sigma is:

Emphasis on controlling the Output

Taking decisions based on feelings

All problems can be solved using DMAIC

Y = f(X) methodology

All of the above

Number of test cases failed in an:-

Continuous data

Discrete data

Continuous data

Specification Limits are specified by:

Control Limits Distribution of data

What percentage of data gets covered between +/- 1 Sigma on the normal curve?

The value occurring most frequently in a data set is:

Variable Data

The outcome of any Six Sigma project is to:

Reduce variation in the process

Shift process mean towards Target

Reduce Defects

Ensure Customer Satisfaction

All of the above

Which of these explains a "SPECIAL CAUSE" of variation?

These causes are inherent in the process

If these causes are present, the process is predictable

This is because of something specific and has a significant effect from these causes

Each of these contribute a specific & consistent part of the total variation

None of the above

The best measure of "Central Tendency" is:-

Standard Deviation

Page 5: Yello Belt %282%29

GE AMEX Motorola General Motors Toyota

DFSS stands for

50 32 40 10 60

40 10 32 20 60

Mean mode St DEV Range Kurtosis

CTQ stands for

CTQs are derived from Histogram Pie Chart

Broad or vague Very focused Can’t say It's Good

Broad or vague Very focused Can’t say It's Good

The goal of Six Sigma is to Center Process A & B A only not B

Pareto Histogram PFMEA Pie Chart

9 9.5 10 10.5 12

Binary Data Cannot Say

50,000 5,000 500 50 5

Which company adopted Six Sigma for the first time?

Defect For Six Sigma

Design for Six Sigma

Define For Six Sigma

Derived From Six Sigma

None of the above

Given the data set 10, 20, 20, 30, 40, 60. Calculate the Range

Given the data set 10, 20, 20, 20, 40, 60. Calculate Mode

Which of the following is highly dependent on extreme values

"I am always on hold or transferred to the wrong person" is a reply received from VOC. The specific Need statement would be

Add additional Menu item to your Voice system

Put an operator to answer calls round the clock

Customer gets the correct person the first time

Use e-mail instead of Phone

None of the above

Criteria Technology Quantity

Critical Terms to Quality

Critical to Quality

Chance to Quantify

Currency to Quantify

   VOC    Pareto Control Charts

Rate the following problem statement on how focused or broad it is. ”Late room service between 6.00AM and 8.00AM on weekdays at the Royal Palm Hotel”

Somewhat focused

Rate the following problem statement on how focused or broad it is. ”Poor service at the Royal Palm Hotel”

Somewhat focused

The goal of a six sigma program is to make the process

Capable & Stable

Cross functional

more Automated

more standardized

Next generation

Reduce Variation

None of the above

Tool used to map High level Process

Process flow Chart

For the data set "20,5,6,9,4,10,10,12,14,11,19,6,9,5,14,9", the median is:

Turnaround time would be an example of

Continuous Data

Discrete Data None of the above

There is 1000 LoC in a program. There are 5 such programs like this. In all 250 defects are found. Find the DPMO

Page 6: Yello Belt %282%29

Probability Six Sigma

Defects Defectives Opportunity Unit

Increase Decrease Remain Same Should be 1

8 and 11 9.5 and 12.5 9 and 12 10 and 11

5/4.2 4.2/5 8.2/8 13/12.4

99.73 68 1 95 99.966

Reproducibility Repeatability LC error Gauge error

Reproducibility Repeatability LC error Gauge error

Ignore

Normality testing is done to:

Check whether the data follows a normal distribution

Check whether the data is correct

Check for vital X's

Check the validity of measurement system

None of the above

A branch of applied statistics dealing with planning, conducting, analyzing, and interpreting controlled tests to evaluate the factors that control the value of a parameter or group of parameters:

Random Experiment

Design of Experiments

Hypothesis Testing

Which among these is example of continuous data?

Name of people in a forum

Number of employees in a office

Defect severity

Cycle time for testing

Test case passing criteria

A software has 100 LOC. These 100 lines are:

Sample Size

After the improvement is made the Std. Dev. Is expected to:

Depends upon the defect definition

Calculate the control limits from below data:- Mean = 11; Sigma = 0.5

None of above

If the control limits of a process is 8.2 (LCL) and 12.4(UCL) and the specification limits are 8 and 13; what Would be the process capability?

None of above

What percentage of data gets covered between +/- 2 Sigma on the normal curve?

Measurement variation due to operators is also called as:-

None of above

Measurement variation due to gauge is also called as:-

None of above

A typical action after Run chart shows “7 or more points in a row continuously increasing or continuously decreasing indicate a trend” would be:

Find out if measurement device is stuck.

Find out what was different about the process during that time

Stop collecting data

Page 7: Yello Belt %282%29

Ignore

Pareto Rule states that

USL LSL All of the Above

Z value

FMEA stands for

Failure Effects is defined as

A typical action after Run chart shows “A sequence of 7 or more points having the same value” would be:

Find out if measurement device is stuck.

Find out what was different about the process during that time

Stop collecting data

80% of problems are due to 20% causes?

80% of causes are due to 20% problems?

80% of work is done by 20% of people?

None of the above?

In a control chart when a data point falls beyond UCL it signifies

Process out of control?

Process under control?

Both a and b is true?

None of the above?

Which of the following are types of Specification Limits

Both USL and LSL

Which of the following is the correct definition of repeatability

Difference between different readings of same operator

Difference between different readings of multiple operators

Difference between same readings of multiple operators

Average of difference readings of same operator

Which of the following is the correct definition of reproducibility

Same part measured by more than one operator with same instrument

Same part measured by more than one operator with different instrument

Different parts measured by more than one operator with same instrument

Different parts measured by more than one operator with different instrument

Which of the following is not the attribute of Measurement System Analysis?

Continuous Gage R&R

Discrete Gage R&R

Repeatability and Reproducibility

Which of the following options is not correct?

Gage R&R fails for Repeatability

Gage R&R fails for Reproducibility

Gage R&R fails for both repeatability and reproducibility

Gage R&R fails for Linearity

Which of the following is not the correct application of Process Mapping Tool

To eliminate redundant activities

Document improved process

Identify X variables

Investigate errors done by people

Failure Mode and Effect Analyse

Failure Mode and Effect analysis

Failure Method and Effect Analyse

Failure Method and Effect Analysis

All possible types of failure

Impact of failure mode

Severity of failure mode

Occurrence of failure mode

Which of the following options is true

Mean is a measure of Spread

Mean is a measure of variance

Mean is a measure of range

None of the above

Page 8: Yello Belt %282%29

DPMO stands for

Both a and b

RPN stands for

Opportunity Defect Variable Attribute

Define Measure Analyze Improve Control

Pareto Chart Scatter Diagram Run Chart

Increase Remain same Flactuate Reduce

Which of the following is the correct definition of process capability

The ability of a current process to meet customers requirement

The ability of the designed process to meet customers requirement

The future ability of a process to meet customers requirement

Defect per monthly opportunity

Defective per monthly opportunity

Defect per million opportunity

None of the above

Which of the following is the correct objective of sampling

To draw conclusions about population based on a sample

Shortcut to complete six sigma project

None of the above

Which of the following is not the right reason to do sampling

Collecting all data is impractical

Collecting all data is not feasible in destructive testing

Is not possible to collect all data in process industry

Sampling is only way of completing six sigma project

The three types of ratings (used to calculate the RPN) for a FMEA are:

Criticality, RPN, Severity

Criticality, Severity, RPN

RPN, Criticality, Severity

Severity, Occurrence, detectability

Does not matter; Higher number wins.

Pareto Principle suggests that:

80% reasons cause 20% problems

All reasons for critical for improvement

Data focus is more important than process focus

20% reasons cause 80% of the problems

Read Post Reciept

Risk Process Negotiation

Risk Priority Number

Risk Process Numerics

Road Path Navigation

Any product characteristic that deviates outside of specification limits is:

Standard Deviation.

In which of the phase of DMAIC would you find the Root Cause of the problem?

The charting of a data set in which most of the data points are concentrated around the average (mean), thus forming a bell-shaped curve

Standard Deviation

Normal Distribution

Which of these is not a form of sampling?

Random Sampling

Stratified Random Sampling

Segmented Random Sampling

Rational Sub grouping

Systematic Sampling

A risk has detectibility as 1. It means:

Detection is easy

Detection is tough

Detection is impossible

Noting can be infered

None of the above.

Once mitigation action on FMEA has been taken the RPN should

Page 9: Yello Belt %282%29

Customer Minitab Process

Mean Median Mode Risk

All of the above.

money all of the above

Discrete data

VOC CTQ SIPOC Defect

An Overseer

In Y = f (X), X is

6 3

Specification Limits are specified by:

Control Limits Distribution of data.

The value occurring most frequently in a data set is:

Variable Data

The Company is spending lot of time in correcting and paying warranty costs for Post Delivery Defects. Which is an example of Continuous data if we have to correct the situation?

No. of tasks with Zero Post Delivery Defects

No. of tasks with 0 - 5 , 5 - 10 , 10- 15 defects

No. of post delivery defects in each task

Which of these explains a "SPECIAL CAUSE" of variation?

These casues are inherent in the process

If these causes are present, the process is predictable

This is because of something specific and has a significant effect from these causes

Each of these contribute a specific & consistent part of the total variation

None of the above.

Which of this is NOT a correct statement?

If DPMO increases, Sigma Level goes down

If Process Mean shifts towards Target, Yield decreases

If variation increases, Sigma Level goes down

If Yield increases, Defect Rate goes down

None of the above

Your choice of VOC tool depends on:

Time constraints

Size of Population

none of the above.

Measuring downtime of an application is an example of:

Continuous data

When we translate Voice of Customer information into measurable characteristics, what is it?

Operational definition.

The Black Belt's role in coaching the team can be best described as:

A non-supportive role that assures complete success

Coach, teacher, helper and supporter

Assessing team work

Dependent, Cause, Control

Independent, Problem, Effect

Independent, Cause, Problem

Dependent, Symptom, Output

_______ no. of standard deviations can be fitted between the mean & Specification Limits for a 6 Sigma Process

Can be determined only if both USL & LSL are specified

Cannot be determined

The primary objective of the Business Case is to

highlight the problem / failure to the Management

explain why it is important to work on this project.

explain the business opportunities to the Management

get necessary funds allocated for the new projects.

Page 10: Yello Belt %282%29

i, ii, iii, iv i, iii, ii, iv iii, ii, i, iv i, iv, iii, ii

As DPMO goes down

i,ii, iv, iii ii, iv, iii, i iv, iii, ii, i iv, i, ii, iii

Run charts Scatter plot Fish bone diagram

all the above

Pareto Chart uses Discrete data Either a or b Both a and b

Purpose of FMEA tool is

Definition & prioritization of CTQs can be effectively accomplished in the following sequence: 1) Collect VOC Data2)Targeting of customers3)Customer Segmentation4)Translation of VOC into specific needs

Process Capability goes up

Process Capability goes down

Process Capability can either go up or go down

None of the above

The correct sequence of execution for the Analyze phase is 1)VA - NVA analysis of "AS IS" process2)Understanding & descibe the variation3)Narrowing down to the root casues4)Identification of all possible causes

Variation caused due to special cause can be distinguished using

Pareto diagram

Normally distributed data indicates that

there is no process variation

the process is centered

the data set is under the influence of common causes

Find the Mean, Median for the following data set2, 5, 10, 12, 15, 20, 30, 25, 50, 55, 40, 60

Mean = 27, Median = 20

Mean = 27, Median = 22.5

Mean = 22,5, Median = 25

Mean = 27, Median = 27

Continuous data

5 Why method is one of the methods to do the

Root Cause Analysis

Cost Benefit Analysis

Pay-Off Matrix

None of the above

Control Limits and Specification Limits

are never equal to each other

some times equal to each other

are always equal to each other

are interchangable

to improve the quality, reliability and safety of the evaluated products

to help prioritize improvement efforts

to help prioritize and focus on eliminating product and process concerns and/or

helps prevent problems from occuring

all the above

Page 11: Yello Belt %282%29

Any of the above

i, ii, iii ii, iii, iv i, ii, iv i, ii, iii, iv

Variable Data Attribute Data

Pareto Chart Scatter Plot

As DPMO goes down

Process analysis all the above

What is a CTQ? The input of a process

A tool to identify sources of variation

A customer’s requirement which is converted into a product or service characteristic

A tool used to gather and understand customer needs

The primary objective of Six Sigma Methodology is

To achieve process centering & reduce process variation

To establish relationship between various process elements

To improve the process

Which of the following statements is true with respect to Project Charter1)Project Charter is a time-bound document2)Project Charter sets the expection for the team3)Project Charter keeps the team aligned with organizational objectives4)Project Charter clearly specifies the problem statement & the scope of the project

Which of the following statements is true :

Continuous data is not capable of being meaningfully subdivided into more precise increments.

The normal distribution is used with continuous data

The normal distribution is used with discrete data.

Discrete data is capable of being meaningfully subdivided into more precise increments.

Which of the following data types can be subdivided into more precise increments

Both of the above

None of the above

Graphical representation of vital few v/s trivial many is called

Cause & Effect Diagram

Affinity Diagram

Process Capability goes up

Process Capability goes down

Process Capability can either go up or go down

None of the above

allows deep investigation into the process

reveals the utilization of time & resource by the process

helps in finding out redundancies, inefficiencies, bottlenecks & delays

Page 12: Yello Belt %282%29

all the above

all the above

Discrete data Variable data Both a & b

Variation in a process

Response plan Error proofing All the above

Pilot is

Process stability

i, ii, iii, iv i, iii, iv, v i, ii, iii, iv i, iii, iv, vi

Scatter plot Check sheet Process map

Gage R & R

Pugh Matrix Pareto Chart

Histogram Run Chart Scatter Plot Box Plot

Scatter diagram is a tool used for

analysis of data collected over a period of time

trending purpose

finding out the relationship between Ys & Xs

Process Map analysis helps finding out

value added work

non-value added work

value enabling work

Calculation of DPMO is applicable is applicable in case of

None of the above

occurs only due to common causes

occurs only due to special causes

occurs due to a combination of common causes & special causes

none of the above

A process can be effectively controlled by implementing

100 % inspection

a test of all or part of a proposed solution on a large scale

a test of all or part of a proposed solution on a small scale

a test of all or part of a solution on a small scale

a test of all or part of a solution on a large scale

Sigma is a statistical unit of measure for representing

Process capability

Process variation

Process centering

Define Phase in a DMAIC Methodology is characterized byBusiness CaseDesigning of check sheetMilestonesEstablish Project YUnderstanding variationProcess mapping

____________ is used for organizing & grouping of data

Affinity diagram

Variation in measurement obtained when one operator uses the same measurement process

Gage Reproducibility

Gage Repeatability

Gage Reliability

Mapping the Wants to Needs and thus arriving at prioritization Xs is done through

Affinity Diagram

Process Capability Analysis

__________ is a sequential time series plot of data which provides some statistical analysis data

Page 13: Yello Belt %282%29

Variation in a process

All the above

Key benefit of the Piloting all the above

occurs only due to common causes

occurs only due to special causes

occurs due to a combination of common causes & special causes

none of the above

Techniques used for sub-process mapping

Process flow chart

Alternate path method

Cross-functional map

reducing the risk of failure

increase in opportunity for feedback

refining the implementation plan

Which of the following tools should be used when a team is generating and prioritizing a list of options that include highly controversial issues?

 Brainstorming    Affinity diagrams  

 Nominal group technique  

 5 whys  

The primary factor in the successful implementation of six sigma is to have

 the necessary resources  

 the support and leadership of top management  

 explicit customer requirements  

 a comprehensive training program  

Which of the following tools would be most appropriate for collecting data to study the symptoms of a problem?

 Check sheet    Flow diagram  

 Force-field analysis  

 Activity network diagram  

Positional, cyclical, and temporal variations are most commonly analyzed in

SPC charts    multi-vari charts  

 cause and effect diagrams  

 run charts  

The most important aspect of functional requirements is that they describe a single, measurable performance describe how a product or service should operate be traceable to the voice of the customer provide upper and lower performance limits Which of the following control charts is most appropriate for monitoring the number of defects on different sample sizes?

 u    np    c    p  

Which of the following is most important in evaluating and understanding design intent?

 Identifying the functional requirement  

 Brainstorming failure modes  

 Conducting computer simulations  

 Developing FMEA  

Page 14: Yello Belt %282%29

If a process follows an exponential distribution with a mean of 25, what is the standard deviation for the process?

 0.4    5.0    12.5    25.0  

Which of the following activities is value-added?

 Setup    Process    Storage    Inspection  

A black belt plans to test the performance of workers before and after training. Which of the following hypothesis tests should be used to determine whether the training actually improved the workers’ performance?

 2-sample z test  

 2-sample t test  

 Paired t test    F test

The purpose of using control charts is to

 determine if a process is performing within specifications  

 evaluate process performance over time  

 determine how to recreate the process  

 detect the causes of nonconformities  

Data being used in the initial set-up of a process are assumed to have a normal distribution. If the nominal (target) is set at the center of the distribution, and the specification limits are set at ±3σ from the center, then the Cpk is equal to

 –0.25    1.00    1.33    1.67  

Which of the following is defined as continuous, incremental improvement?

 Kanban    Kaizen    JIT    Kaikaku  

To assess the significance of factors in either a fractional- or a full-factorial experiment structure, a black belt can use

analysis of variance (ANOVA)  

 fault tree analysis (FTA)  

 failure mode and effects analysis (FMEA)  

 evolutionary operation (EVOP)  

Which of the following performance measures is most appropriate for evaluating the tangible effects of a six sigma project?

Cycle time    Team member absentee rate  

 Employee morale  

 Unsolicited compliments from customers

Which of the following is the best way to enhance the long-term availability of a machine?

 Machine repair  

 Total productive maintenance  

 Computerized SPC systems  

 Increased operator training  

Page 15: Yello Belt %282%29

Typically, which of the following activities is done earliest in the formation of a project team?

 Select the team  

 Identify the objective  

 Identify the sponsor  

 Allocate the resources  

A black belt is developing a failure mode and effects analysis (FMEA) for the hamburger preparation station in a fast-food restaurant. The following ratings were developed for the low-heat temperature failure mode. Severity = 9Occurrence = 2Detection = 1What is the risk priority number (RPN) for this FMEA?

 4    6    12    18  

Which of the following statements is true about the theory of constraints?

 It views a system in terms of discrete processes.  

 Most constraints are physical.  

 Most constraints are the result of policies.  

 It focuses on continuous improvement.  

Which of the following describes the 95% confidence interval of a 20% absentee rate in a department with 30 people?

 6% to 34%    8% to 32%    13% to 27%    17% to 23%

Which of the following types of variation is LEAST likely to occur in sequential repetitions of a process over a short period of time?

 Cyclical    Positional    Temporal    Seasonal  

Poka-yoke is best defined as

 improving machine efficiency  

 reducing field failures to virtually zero  

 capturing the voice of the customer  

 preventing controllable defects  

A measurement system analysis is designed to assess the statistical properties of

 gage variation    process performance  

 process stability  

 engineering tolerances  

Which of the following best describes a controlled variable whose influence on a response is being studied?

 Replicate    Version    Level    Factor  

For a process,  = 35.0 and σ = 5.00. If the subgroup size is n = 5, what is the value for the upper control limit for the process?

 37.24    37.89    41.71    52.50

Page 16: Yello Belt %282%29

Mathematically, the LEAST informative of the four measurement scales is

 ratio    nominal    ordinal    interval  

A six sigma project to reduce billing statement expenses has shown the need to hire two additional mailroom clerks. Based on this information, which of the following metrics should be used to measure the financial benefits of the project?

 Cost of poor quality  

 Return on investment  

 Net present value  

 Internal rate of return  

A tree diagram can be used to do which of the following?

 Allow a team to identify root causes even when no credible data exist  

 Show a causality relationship  

 Present data from a check sheet  

 Reveal the true level of a problem’s complexity  

Which of the following terms is used to describe the risk of a type I error in a hypothesis test?

 Power    Confidence level  

 Level of significance  

 Beta risk  

Which of the following is a component of a visual factory?

Product specifications  

 Zero defect policies  

 Just-in-time policies  

 Equipment service manuals

When σ = 10, what sample size is needed to specify a 95% confidence interval of ±3 units from the mean?

 7    11    32    43  

Which of the following is the best technique for improving the precision of a designed experiment when the experimental material is not homogeneous?

 Blocking    Confounding  

 Randomization  

 Fractionalizing  

After the major headings of a tree diagram have been broken into greater detail, what is the next step that should be taken?

 Assemble the right team  

 Review the diagram for logical flow and completeness  

 Revise the problem statement  

 Choose the tree diagram goal statement  

A six sigma team has been formed to improve an existing process. Which of the following tools should the team use first to gain a clear understanding of the current process?

Flowchart    Pareto chart    Process FMEA  

 Latin square DOE  

Page 17: Yello Belt %282%29

A store uses signs at specific points in its storage area to indicate when products need to be ordered. This practice is an example of

 kanban    poka-yoke    checkpoints    hoshin  

A method that changes data without significantly reducing accuracy or precision is known as

 bias adjustment  

 statistical efficiency  

 blocking    coding  

A company’s accounts payable department is trying to reduce the time between receipt and payment of invoices. If the team has just completed a flowchart of the process and identified the critical steps, which of the following tools should be used next?

 Fishbone diagram  

 Scatter diagram  

 Box and whisker plot  

 Histogram  

When a team consists of five black belts and eight quality engineers, how many unique meetings could be held consisting of one black belt and two quality engineers?

 40    80    140    280

The primary reason that most companies implement six sigma is to

reduce defects    improve processes  

 improve profit  

 increase customer satisfaction  

For consumer products, an increase in the percentage of returned goods most likely equates to an increase in

 product not meeting specifications  

 end-user dissatisfaction  

 internal reject rates  

 nonconforming material costs  

Legal requirements specify that a bottled product must contain at least the volume printed on the label. A bottling company wants to reduce the amount of overfilled bottles. On the basis of the data above, what is the most effective strategy to accomplish this task?

Decrease the target fill volume only  

 Decrease the target fill variation only  

 First decrease the target fill volume, then decrease the target fill variation  

 First decrease the target fill variation, then decrease the target fill volume  

Page 18: Yello Belt %282%29

Both a and b Both b and c Both a and c

Define

In measurement system analysis, which of the following pairs of data measures is used to determine total variance?

 Process variance and reproducibility  

 Noise system and repeatability  

 Measurement variance and process variance  

 System variance and bias  

Which of the following tools is used extensively in quality function deployment (QFD)?

 Affinity diagram  

 Matrix diagram  

 Cause and effect diagram  

 Activity network diagram  

What is Design for Six SigmaChoose Your Answer: a) A methodology for designing or redesigning products,services, or processesb) A alternate way to plan for a Six Sigma DMAIC initiativec) A natural progression to continually root out hidden dollars to the bottom line

None of the above

A commonly reported problem associated with Six Sigma projects deals with:

A failure to complete any project charter documentation

A desire to complete projects on time

A requirement that projects must be $100,000 in value

A lack of business impact for the company

The Pareto chart is a widely used quality tool and its principles have been used in many projects. Which of the following is an appropriate application of a pareto chart?

A frequency based ranking of categories

An alphabetic based ranking of categories

A critically weighted ranking of categories

A financially weighted ranking of categories

With what initial step does Six Sigma project methodology normally begins?

Problem Definition

Project charter

Champion's Approval

Which table would you use to determine the confidence interval of the mean for sample size of 100 and standard deviation of 3:

t distribution table

z distribution table

chi-square distribution table

F distribution table

Page 19: Yello Belt %282%29

Delighters Dissatisfiers Satisfiers

Floor level A detailed level

Matrix Response Interaction Factor

Only if you had a much smaller sample like 5 or 15, and did not know the standard deviation, you would use the 't' table instead of the 'z' table. A customer satisfaction tool known as Kano Model is used for analysing customer requirements. Which of the following is not considered a kano model category:

Moments of truth

KANO model is an indicator of customer satisfaction and helps the organization in understanding the appropriate customer satisfaction level. The organization should however be aware that the Kano model CAN NOT:

Analyze customer needs and requirements

Determine the basic satisfiers for the customer

Meet the latent requirements for the customer

Detemine when the customer levels have risen

The process map known as SIPOC(suppliers,Inputs, Process, Outputs, Customers) provides team members with an understanding of the process. It is a view of the process taken at:

A very high level

The customers prespective

What is a project charter? Identify which ever correct.

   A description of the business need addressed by the project

The product that will be produced by the project, that is, characteristics of the value (product or service) that the project will create

  The relationship between the business need and the product.

  All the above   None of the above

A(n) ____________ is when there is an effect on Y while varying two or more Xs at the same time?

Page 20: Yello Belt %282%29

Control Chart Six Sigma

Sample Population

Sample Size Attribute Data Discrete Data Variable Data

What does SIPOC stand for?

FMEA is used in Improve phase Measure phase Analysis phase

scatter plot normality plot box plot control chart

An improvement process in which a company measures its performance against that of best-in-class companies, determines how those companies achieved their performance levels, and uses the information to improve its own performance.

Benchmarking

Cause and Effect Diagram

For a set of data, the average squared deviation from the mean, with a denominator of n-1.

Sample Variance

Normal Distribution

Countable observations, for example, number of defects.

In order for a problem to be solved correctly, which of the following must occur first?

The problem must be defined.

Relevant data must be gathered.

The measurement system must be validated.

The process must be mapped.

Which of the following measures can be used to find a quick approximation of the availability of a system?

Mean time to failure (MTTF) and mean time to repair (MTTR)

Failure rate and failure mode

Mission time and failure rate

Downtime and time to repair

Suppliers, Input, Process, Output, and Corporate

Stakeholders, Input, Process, Output, and Customers

Suppliers, Input, Policies, Output, and Customers

Suppliers, Input, Process, Output, and Customers

any of the DMAIC phases

Graphical representations of the variation in a process over time is referred as

Page 21: Yello Belt %282%29

3

1

1

4

3

1

2

4

4

2

Correct Option

Page 22: Yello Belt %282%29

3

3

2

2

4

5

5

2

2

4

1

4

1

4

Page 23: Yello Belt %282%29

5

5

1

4

4

3

4

1

3

3

4

2

2

4

2

Page 24: Yello Belt %282%29

2

3

4

2

1

4

2

2

1

2

3

5

3

2

Page 25: Yello Belt %282%29

3

2

1

4

4

3

3

1

3

1

1

3

4

2

1

1

Page 26: Yello Belt %282%29

1

4

4

3

2

2

1

4

1

2

3

Page 27: Yello Belt %282%29

2

1

1

4

1

1

4

4

4

2

2

4

Page 28: Yello Belt %282%29

1

3

1

4

4

4

3

2

3

3

3

1

4

Page 29: Yello Belt %282%29

1

3

3

3

2

4

2

2

3

3

1

2

Page 30: Yello Belt %282%29

3

1

2

1

3

2

1

1

1

5

Page 31: Yello Belt %282%29

3

1

4

2

1

2

1

4

Page 32: Yello Belt %282%29

3

4

3

3

3

2

1

4

2

2

1

2

Page 33: Yello Belt %282%29

3

4

4

Page 34: Yello Belt %282%29
Page 35: Yello Belt %282%29
Page 36: Yello Belt %282%29
Page 37: Yello Belt %282%29
Page 38: Yello Belt %282%29

3

4

1

3

2

Page 39: Yello Belt %282%29

1

4

2

4

3

Page 40: Yello Belt %282%29

3

1

3

1

1

4

4

4