York River Estuary York River Breakwaters including VIMS shoreline project 2010 C. Scott Hardaway, Jr. Geologist

Upload: hoangthuy

Post on 02-Jan-2017

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: York River Breakwaters and VIMS Shoreline

York River EstuaryYork River Breakwaters including VIMS shoreline g

project 2010

C. Scott Hardaway, Jr.Geologist

Page 2: York River Breakwaters and VIMS Shoreline

Shoreline ErosionShoreline Erosion

Page 3: York River Breakwaters and VIMS Shoreline

Shoreline ErosionShoreline Erosion

Page 4: York River Breakwaters and VIMS Shoreline

Management StrategiesManagement StrategiesBulkheadsBulkheads

Page 5: York River Breakwaters and VIMS Shoreline

RevetmentsManagement StrategiesManagement Strategies

Revetments

Page 6: York River Breakwaters and VIMS Shoreline

RevetmentsManagement StrategiesManagement Strategies

Revetments

Page 7: York River Breakwaters and VIMS Shoreline

StormYorktownYorktown

Storm

Page 8: York River Breakwaters and VIMS Shoreline

Post StormYorktownYorktown

Post Storm

Page 9: York River Breakwaters and VIMS Shoreline

Pre Project 1994YorktownYorktown

Pre-Project, 1994

Page 10: York River Breakwaters and VIMS Shoreline

BreakwatersDesign CriteriaDesign Criteria

Annual Significant Storm Tangential

Beach R/R =0 81

Breakwaters

Storm

Farshore

F t h

gWinds Winds Beach

90°

90°

ROrthogonal

R/R =0.81O

Annual Significant

Fetch

StormFetchFetch

Windows

SMB Output (H&T)RCP WAVE I t

90°

90°

Control Line (R )O

Wave Crest Line

Wave Orthogonal DiffractionPoint Spiral

B hAnnual Storm

Resultant Wave Vectors H&at Site

RCPWAVEBathymetric

Grid

RCP WAVE Input

LB

G

o t

Possible HeadlandAlignment Possible Extentof Headland

pBeachSection

al

Tangent Section

Tang

BW BW

SpiralSection

GB

Mb

L =BW LengthG =Bay GapM =IndentationB =Beach Width

B

B

b

m

Spi ra

angent

Project Upland

Bm

Page 11: York River Breakwaters and VIMS Shoreline

Post ProjectYorktownYorktown

Post Project

Page 12: York River Breakwaters and VIMS Shoreline

Chesapeake Bay Chesapeake Bay Breakwater DataBreakwater Data

BaseBase

Selected Sites

Page 13: York River Breakwaters and VIMS Shoreline

BreakwatersDesign CriteriaDesign Criteria

A'

Breakwaters

A'

Gb

Lb

Xb hB

Base of Bank

MHWTombolo BW

A - A'BW

o

BW

AMb

Tombolo

Gb Breakwater gapXb Distance offshore C breakwater to original MHWMb Maximum bay indentation

BW Breakwater

LCL

To

Base of Bank or Bulkh

Bm

BI

Salie

nt

Mb Maximum bay indentation, C breakwater to MHW

Bl Initial beach width, base to bank to MHWBm Present beach width, base to bank to MHWhb Water depth from bottom to MHW at breakwater

Lb Breakwater crest lengthL

Toe of Beach

Present MHWOrig inal MHW

ulkhead

hb Water depth from bottom to MHW at breakwater

Page 14: York River Breakwaters and VIMS Shoreline

1 0

1.65

1.0

Page 15: York River Breakwaters and VIMS Shoreline

Based on Wind/Wave DirectionRelationshipsRelationships

Unidirectional Wind Wave Climate

Based on Wind/Wave Direction

• Mb:Gb Range: 1:1.6 to 1:2.5; average = 1:1.9

• Lb:GbLb:GbRange: 1:1.5 to 1:2.0; average = 1:1.8

Bimodal Wind Wave ClimateBimodal Wind Wave Climate• Mb:Gb

Range 1:1.0 to 1:1.7; average = 1:1.4Lb:GbLb:GbRange : 1:1.0 to 1:1.5; average = 1:1.2,

Overall Average Mb:Gb = 1:1.65Lb:Gb = 1:1.40

Page 16: York River Breakwaters and VIMS Shoreline

YorktownYorktown19 May 1999

Page 17: York River Breakwaters and VIMS Shoreline

17 Oct 2010YorktownYorktown17 Oct 2010

Page 18: York River Breakwaters and VIMS Shoreline

29 Oct 2010YorktownYorktown29 Oct 2010

Page 19: York River Breakwaters and VIMS Shoreline

29 Oct 2010YorktownYorktown29 Oct 2010

Page 20: York River Breakwaters and VIMS Shoreline

Other York River Other York River BW SitesBW Sites

From Google EarthBW SitesBW Sites

Page 21: York River Breakwaters and VIMS Shoreline

Gloucester Point 1937

Page 22: York River Breakwaters and VIMS Shoreline

Virginia Fisheries Lab 1951

Page 23: York River Breakwaters and VIMS Shoreline

Gloucester Point 1968

Page 24: York River Breakwaters and VIMS Shoreline

VIMS 1965

Page 25: York River Breakwaters and VIMS Shoreline

VIMS bulkhead 1964

Page 26: York River Breakwaters and VIMS Shoreline

VIMS East Jan 1 1978VIMS East Jan 1, 1978

Page 27: York River Breakwaters and VIMS Shoreline

Northeaster April 26 1978Northeaster April 26, 1978

Page 28: York River Breakwaters and VIMS Shoreline
Page 29: York River Breakwaters and VIMS Shoreline

VIMS East Sill July 1980

Page 30: York River Breakwaters and VIMS Shoreline
Page 31: York River Breakwaters and VIMS Shoreline

VIMS EastJan 1984

Page 32: York River Breakwaters and VIMS Shoreline
Page 33: York River Breakwaters and VIMS Shoreline

VIMS West 1983

Page 34: York River Breakwaters and VIMS Shoreline

VIMS West BwsMay 1986

Page 35: York River Breakwaters and VIMS Shoreline

Ferry Pier: Isabel

Page 36: York River Breakwaters and VIMS Shoreline

VIMS East Post Isabel

Page 37: York River Breakwaters and VIMS Shoreline

VIMS East Post Isabel

Page 38: York River Breakwaters and VIMS Shoreline

2003Gloucester Point/VIMSGloucester Point/VIMS

2003

Page 39: York River Breakwaters and VIMS Shoreline
Page 40: York River Breakwaters and VIMS Shoreline

Ernesto: Sept. 1, 2006

Page 41: York River Breakwaters and VIMS Shoreline

Shoreline Management PlanVIMSVIMS

Shoreline Management Plan

Page 42: York River Breakwaters and VIMS Shoreline
Page 43: York River Breakwaters and VIMS Shoreline
Page 44: York River Breakwaters and VIMS Shoreline
Page 45: York River Breakwaters and VIMS Shoreline
Page 46: York River Breakwaters and VIMS Shoreline

2010Gloucester Point/VIMSGloucester Point/VIMS

2010

Page 47: York River Breakwaters and VIMS Shoreline

Pre ProjectVIMSVIMS

Pre-Project

Page 48: York River Breakwaters and VIMS Shoreline

During ConstructionVIMSVIMS

During Construction

Page 49: York River Breakwaters and VIMS Shoreline

During ConstructionVIMSVIMS

During Construction

Page 50: York River Breakwaters and VIMS Shoreline

Post ConstructionVIMSVIMS

Post Construction

Page 51: York River Breakwaters and VIMS Shoreline

VIMS West: 2010VIMS West: 2010

Page 52: York River Breakwaters and VIMS Shoreline

VIMS East: Post-construction: 2010

Page 53: York River Breakwaters and VIMS Shoreline

VIMS East: January 2011VIMS East: January 2011

Page 54: York River Breakwaters and VIMS Shoreline
Page 55: York River Breakwaters and VIMS Shoreline
Page 56: York River Breakwaters and VIMS Shoreline

Summary for York RiverExisting Shore StructuresExisting Shore Structures

Summary for York River

Bulkheads•10.5 miles

Riprap Revetments•14 miles

Breakwater Sites• 21 sites along the York RiverBreakwater Systems s tes a o g t e o e• Minimum site length 300 ft• Maximum site length 3,200 ft

•3.3 miles

• Number of BW units, 102• Number of Bays, 102

Page 57: York River Breakwaters and VIMS Shoreline