…. an electrifying example pricing multiple triggers larry schober
TRANSCRIPT
…. an electrifying example
Pricing Multiple Triggers
Larry Schober
Pricing Multiple Triggers ... an electrifying example
2
Pricing Multiple Triggers
• Make some observations about multiple trigger coverage.
• Highlight some features of multiple trigger coverage through an example.
Pricing Multiple Triggers ... an electrifying example
3
Pricing Multiple TriggersGeneral Observations
• Multiple triggers customize coverage.
• Triggers need not be (and usually are not) the typical insurance triggers.– Laser in on revenue drivers = enterprise risk mgt.
• Examples of multiple triggers for an:– Insurance company
– Electric utility
• How do we proceed?
Pricing Multiple Triggers ... an electrifying example
4
Pricing Multiple TriggersGeneral Observations
• Various triggers• Feedback or correlation between triggers• Triggers brought together in an integrated model
.
.
.
Trigger 1
Trigger 2
LossCalculation
Feedback Feedback
Trigger n
General Model
FeedbackFeedback
Pricing Multiple Triggers ... an electrifying example
5
Multiple Trigger ModelForced Outage Example
• In our example, we will focus on– A real life situation where triggers might interact– How do we model the triggers
• How we can integrate the triggers in an overall loss model
• Data sources and nature of data used to construct the model
• A structural model for the triggers, which has the virtue of a flexible framework.
– Techniques (bootstrapping, weather)– Hedging alternatives
Pricing Multiple Triggers ... an electrifying example
6
Multiple Trigger ModelForced Outage Example - What Are Triggers?
• The example we’re going to look at has 2 triggers (combination of events that work together to cause a loss):1. Power plants fail to produce power, or are
“forced out”
2. Cost of purchasing the replacement power on the open (spot) market is high.
- AND -
Pricing Multiple Triggers ... an electrifying example
7
Multiple Trigger ModelForced Outage Example - How Can We Model the Triggers?
• Forced outages, the first trigger, is part of the boiler and machinery coverage.– Utilities try to estimate outages in predicting system reliability
• Spot prices, the second trigger, have been deregulated since 4/1/98.– Only a two year history - not a whole lot of historical data - and
it’s extremely volatile.– Historical range of $40-60/mwh spiked briefly in 1998-99 to
$5-10,000/mwh
Pricing Multiple Triggers ... an electrifying example
8
Multiple Trigger ModelForced Outage Example -Revisit Generalized Model
• Trigger 1: outage on a covered plant• Trigger 2: spot price for electricity> strike
.
.
.
Trigger 1
Trigger 2
LossCalculation
Feedback Feedback
Trigger n
General Model
FeedbackFeedback
outage
spike
Pricing Multiple Triggers ... an electrifying example
9
Report: New Risks Challenge Actuarial Models
- P/C BestWeek 4/17/2000
• Actuaries should develop simulated models when pricing newly emerging risks.
• Without historical data, actuaries must find new ways to price emerging markets.
Pricing Multiple Triggers ... an electrifying example
10
Multiple Trigger ModelForced Outage Example - How Can We Model the Triggers?
• A structural simulation of the power system for the spot price. – Bootstrapped from past data
– Spikes not bootstrapped, conditions are
– Historical data collected by national and federal agencies - much of it publicly available.
• A parametric simulation for the generator outage trigger.
Pricing Multiple Triggers ... an electrifying example
11
U.S. Power SystemBackground - North American Electric Reliability Council (Nerc)
NERC Regions
WSCC
ERCOT
Texas Interconnect
MAPP
SPP
SERC
FRCC
NPCC
ECAR MAAC
MAIN
Western InterconnectEastern Interconnect
Pricing Multiple Triggers ... an electrifying example
12
U.S. Power System
• Data sources– Federal energy regulatory commission (FERC)– North american electric reliability council
(NERC)– Nuclear regulatory commission (NRC)– Utility’s own data
Pricing Multiple Triggers ... an electrifying example
13
Multiple Trigger ModelForced Outage Example
• Investigations into the causes of the price spikes in the summer of 1998 focused on:– demand: unusually warm weather early in the
cooling season.– supply: abnormally large number of nuclear
plants down.– transmission system: impaired by storms.
• At the least, we should address these issues.
Pricing Multiple Triggers ... an electrifying example
14
Multiple Trigger ModelForced Outage Example
• A structural simulation of the power system for the spot price. – Supply-demand model for how much electricity costs.
• Supply = available generating capacity• Demand = ƒ (temperature by region of the U.S)• Region’s demand > region’s supply “spike” on the region
– Needs to be a national model - balancing transfers (transmission) from other regions stabilize prices - also potentially not just one region as trigger.
• Transmission system capacity constraints• Weather: temperature and windstorm
Pricing Multiple Triggers ... an electrifying example
15
Multiple Trigger ModelForced Outage Example - Structural simulation of Power System
• Demand - varies largely by temperature
• as temperatures rise, demand for cooling
• as temperatures fall, demand for heating
• differs by region• not the same by day
– weekday vs. weekend
Demand vs. Temperature by NERC Region - workdays
-
25,000
50,000
75,000
100,000
125,000
40 50 60 70 80 90 100
Daily High Temperature (F)
Pea
k D
eman
d (
Mw
)
MAPP
Main
ECAR
SPP
WSCC
ERCOT
SERC
FRCC
MAAC
NPCC
Pricing Multiple Triggers ... an electrifying example
16
Multiple Trigger ModelForced Outage Example - Structural simulation of Power System
• Supply - outages (reductions in capacity) are applied by individual generator– using average by class of generator for
uncovered capacity.– by generator, all across the U.S. and tied back
to region.– same concept applied to covered plants - don’t
use average, use generator’s own “experience”.
Pricing Multiple Triggers ... an electrifying example
17
Multiple Trigger ModelForced Outage Example - Structural simulation of Power System
• Availability of each generator is simulated by day for a whole year
• Capacity = sum of all available generators
• Nuclear capacity is separately simulated– different durations than fossil (coal/gas) plants
Pricing Multiple Triggers ... an electrifying example
18
Multiple Trigger ModelForced Outage Example - Structural simulation of Power System
• Need to perform any balancing transfers to surrounding regions– optimize capacity subject to shortfalls.– transmission capacity is an additional constraint.– transmission capacity is reduced for:
• line load: reduced for temperature
• windstorm: even localized, will impair transmission balancing capability
Pricing Multiple Triggers ... an electrifying example
19
Multiple Trigger ModelForced Outage Example
• A parametric simulation for the generator outage trigger.– Top-down approach: forced outage rates from
previously mentioned data resources applied uniformly
– Structural approach (bottom-up) could be applied:• Model each component of the generating plant
• More of an engineering approach - not as good a predictor of availability as forced outage rate (NERC)
Pricing Multiple Triggers ... an electrifying example
20
Multiple Trigger ModelForced Outage Example - Motivation Behind Supply-demand Model
Capacity Shortfalls as an Indicator of Spot Price Jumps(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
4,000
8,000
12,000
Pea
k D
eman
d (
Mw
)
Control Area Peak Demand
Capacity
Demand
Capacity Shortfalls as an Indicator of Spot Price Jumps(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
4,000
8,000
12,000
Pea
k D
eman
d (
Mw
)
Control Area Peak Demand Control Area Capacity (Seasonal)
Capacity
Demand
Capacity Shortfalls as an Indicator of Spot Price Jumps(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
4,000
8,000
12,000
Pea
k D
eman
d (
Mw
)
Control Area Peak Demand Control Area Capacity (Seasonal)
Capacity
Demand
Capacity Shortfalls as an Indicator of Spot Price Jumps(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
4,000
8,000
12,000
Pea
k D
eman
d (
Mw
)
Control Area Peak Demand Control Area Capacity (Seasonal)
Capacity
Demand
Capacity Shortfalls as an Indicator of Spot Price Jumps(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
4,000
8,000
12,000
Pea
k D
eman
d (
Mw
)
Control Area Peak Demand Avg Daily Spot Control Area Capacity (Seasonal)
Capacity
Demand
Pricing Multiple Triggers ... an electrifying example
21
Multiple Trigger ModelForced Outage Example - Motivation Behind Supply-demand Model
Maximum Temperature and Spot Price(January - December 1998)
$10
$100
$1,000
$10,000
1/1/98 2/1/98 3/1/98 4/1/98 5/1/98 6/1/98 7/1/98 8/1/98 9/1/98 10/1/98 11/1/98 12/1/98
Date
$/M
wh
(lo
g s
cale
)
0
20
40
60
80
100
Max
Dai
ly
Tem
per
atu
re (
oF
)
Avg Daily Spot Max. Temp.
Pricing Multiple Triggers ... an electrifying example
22
Multiple Trigger ModelRevisit General Model
.
.
.
Trigger 1
Trigger 2
LossCalculation
Trigger nGeneral Model
Feedback
Feedback
Feedback
Feedback...
Supply(capacity)by region
(5b) + (5c)
Demandby region
(5a)
TransmissionOptimizedShortfall
(5d)
Trigger 2Spot PriceJump-diffusion
Model
(5e)
Trigger 1Covered Capacity
(Forced Outages)
(5f)
LossCalculation
applying:o deductibleso coinsuranceo retentions
o limits
(6)
Weather
Trigger 1
Trigger 2
LossCalculation
Temp. Windstorm
Trigger nGeneral Model
Non-covered Capacity(Forced Outages)
Feedback
Feedback
Feedback
Feedback...
Supply(capacity)by region
(5b) + (5c)
Demandby region
(5a)
TransmissionOptimizedShortfall
(5d)
Trigger 2Spot PriceJump-diffusion
Model
(5e)
Trigger 1Covered Capacity
(Forced Outages)
(5f)
LossCalculation
applying:o deductibleso coinsuranceo retentions
o limits
(6)
Weather
Trigger 1
Trigger 2
LossCalculation
Temp. Windstorm
Trigger nGeneral Model
Non-covered Capacity(Forced Outages)
Feedback
Feedback
Feedback
Feedback
Trigger 3Precipitation
Pricing Multiple Triggers ... an electrifying example
23
Multiple Trigger ModelForced Outage Example
• Spot price model– Jump-diffusion = frequency severity model– The frequency of a jump or spike is defined by
the frequency of shortfall– The severity of the spike or “diffusion” is a
function of the magnitude of shortfall– Not deterministic, but probabilistic around the
average.• Pareto, lognormal, ...
Pricing Multiple Triggers ... an electrifying example
24
Multiple Trigger ModelForced Outage Example
• Loss Calculation– simulation in a spreadsheet - keeps it accessible– apply limit, deductible, other policy terms
• Iterations– typically convergence at 10-20,000; higher for
more “customization”
• Loss Cost– loss cost = sample mean + % sample std. dev.
Pricing Multiple Triggers ... an electrifying example
25
Multiple Trigger ModelTechniques - Bootstrap
• Bootstrapping– Resampling from past data (empirical
distribution)– Conditions leading up to a spike are sampled
from past actual data.– Spike amounts are NOT sampled from past data
• Only 2 years of spikes
Pricing Multiple Triggers ... an electrifying example
26
Multiple Trigger ModelTechniques- Weather
• You can incorporate:• Southern oscillation: sample la niña (el niño) years
• (N) year cycles: sample every N years
• Multi (k) year policy: sample (k) consecutive years; not (k) independent years
• Adjust past temperatures upward before resampling to reflect warming trend
• Warming trend not disputed, but cause is disputed
• Possibly sample only latest (adjusted) years
Pricing Multiple Triggers ... an electrifying example
27
Multiple Trigger ModelHedging Multiple Trigger Coverage
• By their very nature, these are customized covers and fairly unique.
• Hard to find perfect match for your exposure. • If the buyer could find it, why buy insurance?
• “Basis risk” in trying to hedge one exposure.• Risk of a difference between the performance of a hedge and
the losses sustained from the hedged exposure.
• Customization can make insurance “solution” preferable to capital market “solution”.
Pricing Multiple Triggers ... an electrifying example
28
Multiple Trigger ModelConclusions
1. More variables in multiple trigger coverage.• Simpler is still better.
2. Dependence between triggers is problematic.
3. Framework should allow for expansion of variables.
4. Wake-up call: pricing of risks with little data is not new, but there is more of it as pressure is applied from competing markets looking for involvement in risk management.