· web viewin answering the question -- and once again, these are the planning criteria that you...
TRANSCRIPT
ONTARIOENERGYBOARD
FILE NO.: EB-2007-0707
VOLUME:
DATE:
BEFORE:
2
September 9, 2008
Pamela Nowina
Ken Quesnelle
David Balsillie
Presiding Member
Member
Member
112345678
9
10
11
12
13141516
EB-2007-0707
THE ONTARIO ENERGY BOARD
IN THE MATTER OF Sections 25.30 and 25.31 of the Electricity Act, 1998;
AND IN THE MATTER OF an Application by the Ontario Power Authority for review and approval of the Integrated Power System Plan and proposed procurement processes.
Hearing held at 2300 Yonge Street,25th Floor, Toronto, Ontario,on Tuesday, September 9, 2008,
commencing at 9:02 a.m.
------------------VOLUME 2
------------------
B E F O R E:
PAMELA NOWINA PRESIDING MEMBER
KEN QUESNELLE MEMBER
DAVID BALSILLIE MEMBER
11234567891011121314151617181920212223242526
27282930313233343536
A P P E A R A N C E S
JENNIFER LEA Board CounselDAVID CROCKER
DAVID RICHMOND Board StaffVIOLET BINETTENEIL McKAY
GEORGE VEGH Ontario Power Authority (OPA)MICHAEL LYLEGLEN ZACHERJAMES HARBELLKRISTYN ANNIS
STEVEN SHRYBMAN Council of Canadians
JAY SHEPHERD School Energy Coalition (SEC)JOHN DeVELLIS
DAVID POCH Green Energy Coalition, PembinaKAI MILLYARD Foundation and Ontario Sustainable
Energy Association (OSEA)
ANDREW LOKAN Power Workers' Union (PWU)JUDY KWIKRICHARD STEPHENSON
BASIL ALEXANDER Pollution ProbeMURRAY KLIPPENSTEINCORY WANLESSKENT ELSON
TOM BRETT Association of Power Producers ofCARLTON MATHIAS Ontario (APPrO)
PETER THOMPSON Canadian Manufacturers & ExportersVINCE DeROSE (CME)NADIA EFFENDI
1212345678910111213141516171819202122232425262728293031323334353637383940414243444546
A P P E A R A N C E S
MARK RODGER Alliance of Energy Consumers (Association of Major Power Consumers of Ontario, AMPCO; Canadian Chemical Producers' Association; Cement Association of Canada (Ontario); Industrial Gas Users Association, IGUA; Ontario Federation of Agriculture, OFA; Ontario Forest Industry Association; Ontario Mining Association; Stone, Sand and Gravel Association of Ontario
IAN MONDROW City of TorontoELISABETH DeMARCO
MICHAEL BUONAGURO Vulnerable Energy Consumers' Coalition (VECC)
JOHN CYR City of Thunder Bay, NorthwesternNICK MELCHIORRE Ontario Municipal Association
(NOMA), Town of Atikokan
ROBERT WARREN Consumers Council of Canada
KELLY FRIEDMAN Electricity DistributorsRAUL AGARWAL Association
JOHN RATTRAY Independent Electricity SystemPAULA LUKAN Operator (IESO)
TIM MURPHY Canadian Solar IndustriesAMANDA KLEIN Association
CHARLES KEIZER Brookfield Energy Marketing Inc., Great Lakes Power Ltd. (GLPL)
DOUG CUNNINGHAM Nishnawbe Aski Nation
ALEX MONEM Saugeen Ojibway Nations (SON)ARTHUR PAPE
PETER FAYE Lake Ontario WaterkeeperJOANNA BULL
1212345678910111213141516171819202122232425262728293031323334353637383940414243444546
A P P E A R A N C E S
JENNIFER AGNOLIN NorthwatchVIVIENNE BALL
JEFF ROSEKAT First Nations Energy AllianceCHERIE BRANTGENEVIEVE LE COMTE
JIM HAYES Society of Energy ProfessionalsJO-ANNE PICKEL
SARAH DOVER Provincial Council of Women of Ontario (PCWO)
MICHAEL ENGELBERG Hydro One Networks Inc. (HONI)BLAIR McDONALD
DAVID GOURLAY Newfoundland and Labrador Hydro
DAVID STEVENS Enbridge Gas DistributionDENNIS O'LEARY
PAUL MANNING National Chiefs Office, Assembly of First Nations
FRED CASS Ontario Power Generation (OPG)
ANDREW TAYLOR Ontario Waterpower Association, Canadian Wind Energy Association
DAVID MacINTOSH Energy Probe
ALSO PRESENT:
Dr. JAN CARR Ontario Power AuthorityMIRIAM HEINZ
TOM ADAMS Alliance of Energy Consumers
CHRIS BUCKLER Electricity Distributors' Association
GRACIA JANES Provincial Council of Women of Ontario
1212345678910111213141516171819202122232425262728293031323334353637383940414243444546
I N D E X O F P R O C E E D I N G S
Description Page No.
--- Upon commencing at 9:02 a.m. 1
Preliminary matters 1
ONTARIO POWER AUTHORITY - PANEL 2, RESUMED 6
A. Shalaby, A. Pietrewicz, Previously Sworn
Continued cross-examination by Ms. Lea 6Cross-examination by Mr. Crocker 8
--- Recess taken at 10:25 a.m. 49--- On resuming at 10:45 a.m. 49
Procedural matters: 59
Cross-examination by Mr. Poch 66
--- Luncheon recess taken at 12:14 p.m. 101--- Upon resuming at 1:47 p.m. 101
--- Recess taken at 3:12 p.m. 152--- On resuming at 3:30 p.m. 152
Procedural matters 190
--- Whereupon hearing adjourned at 4:40 p.m. 192
123412345678910111213141516171819202122232425262728293031323334353637383940
E X H I B I T S
Description _______Page No.
EXHIBIT K1.3: BOARD STAFF CHART. 1
EXHIBIT NO. K2.1: GEC CROSS-EXAMINATION MATERIALS FOR PLAN DEVELOPMENT 65
EXHIBIT NO. K2.2: LIST OF DIRECTIVE AND LETTERS 66
123412345678910111213
U N D E R T A K I N G S
Description Page No.
UNDERTAKING NO. J2.1: TO PROVIDE A LIST OF EXISTING DIRECTIVES THAT AUTHORIZE CONSERVATION PROCUREMENT 77
UNDERTAKING NO. J2.2: TO PROVIDE AVOIDABLE PLANNED CAPACITY AS IS PRESENTED IN DRAFT FORM IN K2.1, PAGE 1121
UNDERTAKING NO. J2.3: TO PROVIDE COMPARATIVE SAFETY STATISTICS FOR ENERGY PRODUCTION FOR ELECTRICITY GENERATION DOCUMENT 155
NO
123412345678910111213141516171819
Tuesday, September 9, 2008
--- Upon commencing at 9:02 a.m.
MS. NOWINA: Please be seated.
Good morning, everyone. Today is day 2 of the oral
portion of the review of the Integrated Power System Plan,
the IPSP. The Ontario Power Authority is seeking the
Board's approval of the Integrated Power System Plan and
certain procurement processes. The Board has assigned file
number EB-2007-0707 to this application.
Today we continue with the cross-examination of
panel 2 on plan overview and development.
Now, those of you who were here yesterday will notice
that we have moved the witness panel to my left and Board
Staff has moved to the right. That's with the feeling that
the mikes on this side may not be quite as strong as the
mikes on the other side. However, I would ask the witness
panel to please speak up, use your loudest voice for us.
It's very important that you be heard, both here and in the
other room and over the Internet.
Are there any preliminary matters?
PRELIMINARY MATTERS:
MS. LEA: I have a very minor matter, Madam Chair, of
an administrative nature. Those folk who are receiving the
transcript, Exhibit K1.3 made it into the record yesterday.
That was the Board Staff chart, but it didn't make it into
the index of the transcript. So I would ask that that minor
correction be made, please.
EXHIBIT K1.3: BOARD STAFF CHART.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
11
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MS. NOWINA: All right. We will do that. Any other
preliminary matters?
MR. VEGH: I have one, Madam Chair.
I provided Ms. Lea with the copies of materials that I
wanted to speak to this morning, as well as I provided
counsel for NOMA with the materials, because it does address
the NOMA issues. I don't know if you have the materials
with you.
--- Ms. Lea passes documents to Board Members.
MR. VEGH: I don't plan to go through these materials
in detail, but they lay out the correspondence between
myself and counsel for NOMA.
The preliminary matter that I am addressing has to do
with the lack of prefiled evidence filed by NOMA in this
proceeding, and its counsel's proposal to lead prefiled
evidence through evidence-in-chief and not through -- sorry,
to lead its evidence through evidence-in-chief and not
through prefiled evidence.
I just want to provide some context for this concern,
and then ask for your Board's direction on the next steps.
The evidence filed by NOMA in accordance with the Board's
procedural order for intervenor evidence - I think it was
filed August 1st - consisted of a book of materials.
It did not indicate what evidence NOMA was going to
provide in the form of prefiled evidence, like every other
party in this case, just a book of materials that were to be
referred to.
NOMA later advised -- and on that book of materials,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
21
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
because it did not consist of any evidence, there were no
interrogatories asked. There was no statement of what the
evidence was.
NOMA later advised that it would be providing five
witness panels, but, again, it did not provide the evidence
of what those witness panels were going to say.
So I wrote to NOMA or to counsel for NOMA on August
27th, and you have that letter in the package I provided
this morning, asking for the evidence, pointing out that
every other party in this case -- I think there have been 22
other parties who filed prefiled evidence. Every other
party filed prefiled evidence in accordance with the Board's
requirements, and that NOMA hadn't.
So I asked NOMA to provide that evidence. NOMA replied
to this request on August 29th, and I won't take you through
all of the -- that reply has an attachment which sets out
areas of discussion that the evidence -- that the witnesses
propose to cover in evidence, but, again, not their
evidence. We don't know what they're going to say, just the
topics for discussion.
I raised this matter, again, with counsel for NOMA
yesterday. Counsel provided another letter this morning,
dated September 9th, which was also in the package I
circulated. I apologize, the printing of this letter is a
bit off kilter, but you will see it's the same thing. It's
a list of topics to be addressed and not prefiled evidence.
There is still not much direction provided in this list of
topics.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
31
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
So, for example, if you look at, say, page 4, there is
a description about what technical matters the evidence will
be provided on. It says: Rod Bosch, Ontario Hydro
operating manager for northwest region, will give evidence
on the need for dispatchable generation, what is and will be
base-load generation, absence of OPA modelling, but, again,
not a statement of what that evidence is, just the topics
that it needs to cover.
The result is, today, after the hearing has started, we
still don't know what is NOMA's evidence. We're not in a
position to file interrogatories, because we don't have that
evidence. And I raise this today, because, unless the
appropriate evidence is provided, unless something is done
rather immediately, the OPA will have to ask the Board to
rule that the NOMA panel cannot give evidence in this case.
The OPA does not seek that result. I don't think that
that is in the public interest. There are people in the
northwest who want to make a presentation to this Board,
want the Board to consider their issues, and the OPA thinks
that there should be an airing of these issues.
The OPA has staff, has a very good working relationship
with the members of NOMA, the people on the ground in the
northwest, and they want to continue that relationship.
But the treatment of the evidence in this case must be
done in an orderly way and compliant with the OEB
requirements, and everyone else has had to follow those
rules and counsel for NOMA should be required to, as well.
And if they don't, then we're not going to have a very good
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
41
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
hearing of those issues, because the evidence will be
presented in-chief and we will have to deal with it cold,
and that is not how this Board works.
So what I would ask this Board to do is to direct NOMA
to file its evidence in accordance with the requirements, in
accordance with Board practice and in accordance with what
every other party has done in this case.
And it's clear that my conversations with counsel for
NOMA are not going to lead to this happening voluntarily, so
I would like the Board's direction, and I propose a schedule
that the evidence be filed by September 19th. That's next
Friday. That's well after the time frame for everyone else
filing evidence, but, as I said, it is important that this
evidence go in.
The OPA can provide interrogatories by October 3rd. I
know that is a long time, but OPA staff is, frankly, quite
busy right now with the hearing, so this is done on evenings
and weekends, and then responses by October 10th.
I understand that the NOMA -- the trip to the northwest
to consider NOMA's evidence will be towards the end of the
month, so that should provide sufficient time to be able to
prepare cross-examination.
Thank you, Madam Chair. That is the matter I wanted to
address.
MS. NOWINA: Thank you, Mr. Vegh. For NOMA, Mr. Cyr,
Mr. Melchiorre? Mr. Cyr?
MR. CYR: Good morning, Madam Chair and Panel.
MS. NOWINA: Is your mike on, sir?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
51
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. CYR: It is.
MS. NOWINA: Go ahead.
MR. CYR: Good morning, Madam Chair and Panel.
We have no problem with the schedule that Mr. Vegh has
outlined, and there certainly is no intention to create any
difficulty here. We will comply.
MS. NOWINA: So you will be providing evidence by
September 19th?
MR. CYR: If not before.
MS. NOWINA: Thank you very much. Mr. Vegh, I think
that deals with the issue, does it not?
MR. VEGH: Thank you.
MS. NOWINA: Thank you. Any other preliminary matters?
Ms. Lea, Mr. Crocker, you want to resume your cross-
examination? We are still with Ms. Lea.
ONTARIO POWER AUTHORITY - PANEL 2, RESUMED
Andrew Pietrewicz, Previously Sworn
Amir Shalaby, Previously Sworn
CONTINUED CROSS-EXAMINATION BY MS. LEA:
MS. LEA: Thank you. As always happens when you don't
close your cross-examination on one day, you always think of
another question to ask.
And I wonder if I could beg my colleague Mr. Crocker's
indulgence to just ask you a question on a topic I didn't
touch on yesterday.
I wanted to ask you about the procurement process
slide, and again this is, I think, at a high level, but I am
looking at slide 113 of your presentation. Let me know if I
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
61
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
need to go to the procurement panel with this, but, as I
say, I hope it is a high-level matter.
In the third bullet point of slide 113, it is indicated
that the following procurements will be made under
directives, and it's listed as "all conservation
procurements and all renewable supply procurements".
So there are no conservation or renewable sources of
supply procured under the procurement process, at least
until the next filing of the IPSP. Do I understand that
correctly?
MR. SHALABY: Yes. There are sufficient directives to
attain conservation and renewable resources into the next
several years, that is consistent with the plan at this
time. So there is no additional authority required to
procure either renewables or conservation.
MS. LEA: Okay. Then you do list three sources of
supply that will be procured in the last bullet point of the
slide, the combined gas cycle turbine or single cycle gas
turbine in the GTA, the single cycle gas turbine in
Kitchener-Waterloo Cambridge-Guelph and the reliability
contract with OPG respecting Lennox. Those are the only
non-renewable resources procured as far as this IPSP goes
that you are planning to procure if the IPSP is approved.
MR. SHALABY: Those are the projects that we seek
authority from this Board to procure.
MS. LEA: Now, I gather that past the next filing of
the IPSP presuming for a moment that that is in 2010, there
will be additional things to be procured; that's your
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
71
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
anticipation?
MR. SHALABY: Yes.
MS. LEA: Hmm-hmm. And the approval that you are
seeking of the procurement processes, as I mentioned to you
yesterday, will extend past this IPSP into the filing of the
next one, as far as you are aware?
MR. SHALABY: Meaning what specifically?
MS. LEA: The IPSP itself is required to be filed every
three years but the procurement process is not.
MR. SHALABY: Correct.
MS. LEA: I am presuming it extends until you seek an
amendment or somehow else it is amended.
MR. SHALABY: That's my understanding, yes.
MS. LEA: So the procurement process that you are
seeking to have the Board approve, applies to these three
sources of supply that are in this present IPSP, as well as
sources of supply that will appear in future IPSPs?
MR. SHALABY: Until or unless amended, yes.
MS. LEA: Thank you.
MS. NOWINA: Mr. Crocker.
CROSS-EXAMINATION BY MR. CROCKER:
MR. CROCKER: Thank you, Madam Chair, Members of the
Panel.
Gentlemen, I would just like to start by giving you,
letting know what I am going to be asking you about this
morning, what I want to canvas with you. I want to talk
about sustainability, environmental sustainability and
environmental protection as the OPA was required to consider
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
81
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
in developing the plan and in fact how you did consider it,
as you developed the plan.
Initially, I want to talk to you about your use of
sustainability, the word sustainability, and environmental
sustainability and determine how the two concepts go
together.
Are they the same thing? Are they something different?
And let me just ask you that question initially and then we
can go to the material.
Describe to me how you did use sustainability and how
environmental sustainability fits with that. I invite
either of you to respond to any of my questions.
MR. SHALABY: Thank you. The term "sustainability" is
broader than environmental sustainability. One of the
concepts of sustainability is to look at more than just
economics or more than just social impacts or more than what
the literature would call socio-ecological impacts, the
impacts on the ecology, so the environment. The other
broadened description of environment include economics and
people and the natural environment, or you drop the word
"environmental" and you say "sustainability" and under it
you would have the broader description.
So we considered sustainability as a broad concept that
embraces more than just economics, more than just society
and people, and more than just the natural environment, all
three of them together in an interrelated way.
MR. CROCKER: All right. If you go to your Exhibit G
at tab 3, at schedule 1, you say in the introduction right
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
91
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
at line 1, you say:
"This exhibit describes how the OPA considered
safety, environmental protection, and
environmental sustainability..."
MR. SHALABY: Yes.
MR. CROCKER: "... in its development of the integrated
power system plan." Do you see my reference?
MR. SHALABY: Yes, I do.
MR. CROCKER: Okay. What aspect of the environment are
you speaking of there?
MR. SHALABY: Environmental protection is a little more
specific. Environmental protection is the natural
environment in the meaning of the Ontario regulations and
the governance of environmental protection, regulations and
oversight.
MR. CROCKER: What about environmental sustainability?
MR. SHALABY: We wanted to echo the same words that are
in the directive, in regulation 424/4, so we reproduced it
the same way at this stage, but we considered it broadly.
"Environment" in a more broad context.
MR. CROCKER: Okay. If you go to C-10-1, and we -- and
you go to page 9, your heading is, "Concept of
sustainability."
MR. SHALABY: Yes.
MR. CROCKER: Okay. Tell me what you are talking about
there, and what follows in the document.
MR. SHALABY: This is the evolution of the concept, the
broad concept of sustainability. Our tracking of how it
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
101
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
evolved from the early '70s, our understanding of its
application internationally and to understanding what the
concepts are and what the framework for applying
sustainability is and how could we apply that framework to
electricity planning.
What we sought was applying a very powerful and a very
elaborate concept in development into the electricity
planning, and that's the attempt that we are making at this
stage.
MR. CROCKER: Is it, is that use of sustainability
different than environmental sustainability?
MR. SHALABY: No. Not if you either broaden the
definition of environmental or drop it altogether. It's the
voice carrying? Is the voice experiment works?
MS. NOWINA: Does everyone hear Mr. Shalaby? Everyone
looks happy, Mr. Shalaby. Well, they can hear your voice,
Mr. Shalaby.
[Laughter]
MS. NOWINA: I will correct myself.
MR. SHALABY: I think they're happy.
MR. CROCKER: Then I can look, then, at your discussion
in C-10-1 for a requirement to comply with the provisions of
Reg. 424, can I?
MR. SHALABY: That was our interim thinking in 2006.
This is a discussion paper that we took feedback on and
evolved our thinking further into the evidence in this
particular hearing B-3-1, for example and so on. This was
our thinking at the time and the evolution of thinking
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
111
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
continued.
MR. CROCKER: All right. Let's go to B-3-1, then.
If we go to page 5 of B-3-1, you ask the question, at
line 17: "How was sustainability considered in the
development of the IPSP?" Once again, this is
"sustainability" and "environmental sustainability" used
interchangeably, is it?
MR. SHALABY: Yes.
MR. CROCKER: I can look to what you have discussed
here to see whether compliance has occurred with respect to
the requirement of the regulation?
MR. SHALABY: Yes.
MR. CROCKER: Okay. If we go to the regulation, and I
don't know whether you have it in front of you, but I will
-- if you haven't, I will read you what I am concerned with
anyway.
MR. VEGH: Perhaps for the assistance of the panel, I
think the regulations are set out in the back of the Board's
guidelines.
MR. CROCKER: Okay.
MR. VEGH: Exhibit A-3-1.
MR. QUESNELLE: Microphone, Mr. Vegh.
MR. CROCKER: Are you with me?
MR. SHALABY: Yes.
MR. CROCKER: Okay, the regulation says - I am looking
at section 2, sub 1 to start:
"In developing an Integrated Power System Plan
under subsection 25.3(1) of the act, the OPA shall
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
121
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
follow directives that have been issued by the
minister under subsection 25.30(2) of the act and
shall do the following ..."
And 7 says:
"Ensure that safety, environmental protection and
environmental sustainability are considered in
developing the plan."
What I would like to know is how you use the word
"consider". What did you feel your obligations were to
consider the two elements that I am talking about,
environmental sustainability and environmental protection?
MR. SHALABY: Are you sure we want to go over that
again?
MR. CROCKER: Well, I would like you to tell me.
MR. SHALABY: The scoping phase of this hearing spent
enormous amount of time on that specific question and I hate
to upset the apple cart. I mean, there was a -- what we did
in planning, apart entirely from the legal discussion on
this --
MR. CROCKER: That's what I would like you to tell me,
what you did in terms of planning.
MR. SHALABY: Yes. What we did is we looked at in what
way safety -- let's talk about safety and environmental
protection first. Is that your question, or do you want to
go to sustainability only?
MR. CROCKER: If you would like to talk to me about
safety and environmental protection, please do, and then you
can talk to me about environmental sustainability
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
131
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
afterwards.
MR. SHALABY: We looked at all three, but we found that
there is a large degree of governance, regulations,
tradition in Ontario in relation to safety and in relation
to environmental protection.
We also found that in discussing the literature on
safety, for example - we reviewed some of the literature on
safety - that safety will not be a differentiating factor in
picking technologies or picking options for electricity
planning.
We refer to that -- or it is referred to in the Stratos
review. There is an institute in Switzerland called the
Paul Scherrer Institut that collects safety statistics for
electricity generating technologies, and they go into the
life cycle of all of the generating technologies.
And their conclusions are they really are a subject of
-- what they find is that the fossil generation chains have
higher safety incidents than non-fossil generating chains,
but it really is a function of construction practices, a
function of oversight in the country.
So they divided the statistics between the OECD
countries and non-OECD countries, and found a stark
difference owing to the safety practices and construction
practices and operating practices.
All of that led us to conclude that it is all in the
oversight, it is all in the governance, it is all in the
regulations to do with safety and environmental protection,
training, audits, reporting, rehearsals. There is all kinds
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
141
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
of things in the safety and environmental protection that is
well developed in Ontario, and we're satisfied that the
infrastructure and the governance is in place to look after
those.
There is nothing that differentiate a gas-fired
generation from a nuclear-fired generator from a
hydroelectric or wind turbine at the planning stage. They
all are governed in ways that ensure safety and
environmental protection.
So that's one avenue.
We found a lot less developed thinking around
sustainability, specifically. We found it more developed in
the federal scene. The federal legislation adopts the word
"sustainability" and applies it to air, land and water
quality in some of the federal environmental legislation.
None of the Ontario legislation or regulations that we
examined refer explicitly to sustainability. So
sustainability was less developed as a concept, explicitly
at least. What we found is that it is implicit in many
things that Ontario does, reduction of emissions, reduction
of pollution, consideration of future generation, the well
being of -- it is implicit in many of the things that
Ontario does, but not as explicit as safety and
environmental protection.
So we dedicated more time to understanding the concept
and its applicability to electricity planning.
So that's why we dedicated more time and more paper to
describing sustainability than to environmental protection
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
151
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
and safety, although we considered all three very
rigorously.
If I move on to how we considered sustainability, very
simply, we understood the evolution of the concept, the
history of the literature. It started in United Nations
conferences on human development and environment. 1972 is
marked as one starting point.
The literature -- I can take you back to books that are
written in 1920s, but let's take the 1972 conference in
Stockholm, where environment and economic development were
seen to be clashing, particularly in Third World country
development projects where economic development was seen to
have environmental damage and has inequity in the societal
benefits that it generates. That's the origin of the
thinking, the origin of trying to grapple with societal,
environmental and economic development.
The thinking evolved and was completed a step forward
in the Brundtland Commission report in 1987, and in the Rio
Earth Summit in '91/'92, and further from there we found the
review and discussion at the University of Waterloo.
The University of Waterloo environmental studies people
came to speak with us in 2005. They were preparing a
comprehensive survey of sustainability frameworks. We found
that useful to learn the language of sustainability, to
learn how other people applied it elsewhere, and to guide us
into applying the concept to electricity planning.
So that's how we considered sustainability, evolution,
understand the concept, understand the framework for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
161
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
applying it, and then applying it to this particular plan.
MR. CROCKER: Okay. I think I understand what you have
done up to the point of how you applied it, and that's, in
fact, what I would like to talk to you about as we go
forward.
But when you say "consider", or when the regulation
says "consider", what you have just described to me is how
you considered it; is that correct?
MR. SHALABY: That is how the plan has considered it,
yes.
MR. CROCKER: Okay. And what did you understand your
requirement to be with the expression "in developing the
plan"?
Did you think you had an obligation beyond what you
have just described to me, or do you think you have -- you
satisfied your obligation in how you described it to me?
MR. SHALABY: We satisfied the obligation. We
considered it while developing the plan, not after
developing the plan.
We considered it in working with the options that we
worked on, and in putting the plan together and in
presenting it to Ontarians in this forum here.
MR. CROCKER: You said something earlier in your answer
to the question I just asked you, which reflects something
that you said yesterday morning, as well, when you were
going through your slide deck, and I just want to make it
clear that I understand you.
You said that environmental protection, particularly,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
171
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
and environmental sustainability, as well, were not factors
that the OPA used in differentiating among choices in the
IPSP; is that correct?
MR. SHALABY: I suspect you meant safety and
environmental protection.
MR. CROCKER: No, I meant environmental protection and
environmental -- and sustainability, but correct me if I am
wrong.
MR. SHALABY: No, sustainability -- sustainability was
reflected in the planning criteria, and the planning
criteria differentiated between options and plans.
MR. CROCKER: Okay. Then we will follow that along.
MR. SHALABY: So sustainability was translated -- the
key translation was to move from sustainability concepts and
requirements into a context-specific set of criteria, to
move from the literature, from ideas, to application, to
electricity in Ontario in 2007.
That's where the specific criteria that we developed
were put in place.
MR. CROCKER: Okay.
MR. SHALABY: And those started differentiating between
options and plans.
MR. CROCKER: Okay. We will follow that along more
carefully as we go.
MR. SHALABY: Right.
MR. CROCKER: My recollection of the scoping discussion
and the position of the Board with respect to "consider" was
that you would -- your requirement was to weigh and
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
181
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
evaluate. Is that a fair description of what the OPA did?
MR. SHALABY: Yes.
MR. CROCKER: Okay. I would like to go, then, to B-3-1
and look with you at the methodologies that the OPA used and
how you applied particularly environmental sustainability.
We will get to environmental protection later on in this
discussion, but environmental sustainability to the IPSP.
As I understand it, you considered a broad range of
issues with respect to sustainability and then you kind of
settled on Professor Gibson's discussion of sustainability
and worked from broad concepts to more site-specific or
context-specific issues. Is that a fair description of what
you did?
MR. SHALABY: We found the publication of this book
just at the same time that we were looking for a way to
translate the concept into practical guidance. That is what
the book attempts to do, is to, you know, when you read the
introduction and the preamble to the book, is to marry
sustainability concepts to environmental assessment
practitioners, the practice of environmental assessment to
sustainability concepts. And it surveys the practices
worldwide and it brings some case studies to light. So it
was a very useful document that we found to come our way at
a time where we needed an application guide, and that was
one of the guides that we used in developing our thoughts
and documenting our application.
MR. CROCKER: Did you retain Professor Gibson?
MR. SHALABY: He advised us in a -- something called
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
191
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the sustainability advisory group. He was a member of an
advisory group of five that worked to advise us for two days
in 2006.
MR. CROCKER: All right.
MR. SHALABY: We did not retain him beyond that. He
spoke to us in 2005 as a guest lecturer, to our planning
group on literally the eve of releasing the supply mix
advice in December of 2005. Other colleagues from
environmental studies in Waterloo spoke to us before that.
MR. CROCKER: All right. If you go to page 8 of
Exhibit B, tab 3, you have cited table 1, "Requirement for
progress towards sustainability." That is Gibson's work, is
it not?
MR. SHALABY: It is. It is a summary of that. The
complete citation is elsewhere, and we expand on it. We
have the full description elsewhere.
MR. CROCKER: You used –-
MR. SHALABY: The book is available as well.
MR. CROCKER: You used those concepts, did you not, in
terms of establishing your broad criteria to --
MR. SHALABY: What these requirements -- requirements
are one of the things that a framework for sustainability
would require. There are other things. But the
requirements provided us with the language of sustainability
as an example.
I mean, this language here is new to us, in planning,
in this particular form.
So it provided us with the language of sustainability
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
201
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
and what the concepts are. Description of the concept of
intergenerational equity, the concept of livelihood
sufficiency, the concept of socio-ecological stability, all
of these are concepts that -- the language is different and
more in the language of sustainability. And the description
of what the words mean in more expansive terms. So it was
very helpful to us in that regard.
What the idea is, is to consider these requirements
when planning or when developing a project, or when applying
sustainability to a particular plan like the electricity
plan that we are presenting here today.
MR. CROCKER: Same concepts appear in C-10-1 at page
11, I think.
MR. SHALABY: I will take your word for it, yes.
MR. CROCKER: How then, as we go through this process,
to get from these broad concepts to the planning criteria
you ultimately used, how did you then consider what
Professor Gibson had done, the work that he had done, beyond
simply providing you with language?
MR. SHALABY: It is the -- the framework, as we
understood it, was to understand that these are
requirements. When you want to consider sustainability,
consider these requirements. Consider them together.
And develop criteria that are context-specific. And
the cases of the Voisey's Bay mine development is an
illustration of concept-specific, context-specific criteria.
The Mackenzie Valley pipeline, there is a case study on that
as well, how the criteria were developed for the Mackenzie
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
211
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Valley pipeline. There are other cases in world development
in the book as well, villages and different other irrigation
projects and health projects and so on.
So the key is that the practitioner, the people who are
applying this, know the context. They know what matters in
their context, and what is relevant in their context.
Can they develop criteria that take into account these
requirements while developing their criteria? And that's
what we have done.
We think the criteria that we developed, the six
criteria we developed, are consistent with these
requirements.
And we went through some description in Exhibit B-3-1,
to describe how is it that the criteria that we developed
are consistent with these requirements or can be made to
include attention to these requirements. So that's a leap
from literature and concepts and theory into practice, and
the practice is knowing the context for electricity.
And the context for projects is much richer. The
literature on projects is much richer than the context for
plans. Applying sustainability concepts to plans is a lot
thinner a practice in history than to projects. So Voisey's
Bay is a project. The Mackenzie Pipeline is a project. To
do a strategic plan -- the book describes the application to
strategic plans, but -- not in the same depth as it is to
projects when there are affected water sheds, affected
people, affected airsheds, affected roads and so on that are
specific.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
221
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
So the application to a plan is context-specific thing
that we brought into the criteria that we had.
The fact that we're working within government
directive, the fact that it is electricity, electricity has
peculiar things and specific things about it that has to be
applied. All of these things -- I described the context
yesterday in my slides. We applied that. We applied the
requirements and the understanding of sustainability to come
up with six criteria that are consistent with these
requirements.
MR. CROCKER: Okay. And those --
MR. SHALABY: The mapping is not one-to-one and that is
not algorithmic and it is not hard-wired or anything else
like that and that's how we understood the application of
sustainability: Understand the requirements, understand
your context, and come up with criteria that are consistent
with those requirements. And that's what we did.
MR. CROCKER: Okay. I am still not 100 percent sure I
understand how you got from the broad to the narrow, but we
will go back to it again, I think.
Those criteria are set out, I believe, on page 12 of B-
3-1.
MR. SHALABY: Those are the planning criteria; you are
correct.
MR. CROCKER: Okay. How long did it take the OPA to
get from the broad concepts that Gibson and others may have
given you, to the development of these criteria?
MR. SHALABY: The development --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
231
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. CROCKER: And how many people were involved?
Describe the process of it.
MR. SHALABY: The process is an iterative one, is an
evolutionary one. I described that yesterday. These
criteria evolved over time.
They evolved from the very first documents that we
issued on planning in 2005. We had criteria there.
We had criteria in the scoping document for
consultation in 2006, the overview document, which is an
exhibit in this proceeding as well. So we had criteria
there.
Then we had criteria going into consultation. So it
has evolved over time.
We wanted openness to be a criteria and transparency
and consultation and listening. We used these words at
various times.
We consolidated that now into the language of
sustainability that we see in front of us.
We had environmental performance as a criteria all
along. We consolidated that into the criteria that we see
in front of us. So it took, I would say, two years from the
beginning of the set of criteria in 2005 to another set in
the middle of 2006, to another set in late 2006.
That's the evolution of our thinking about criteria to
guide planning. Along the way, we had the sustainability
thinking inform us in conceptual ways to start, and a little
more structured way along the way, and, finally, after
consultation with stakeholders, we settled on these planning
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
241
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
criteria.
MR. CROCKER: How was that plan developing at this
point? Were you working on developing the plan at the same
time?
MR. SHALABY: Yes. Yes.
MR. CROCKER: You were?
MR. SHALABY: Yes, we were. We had a preliminary plan
in 2006. We had scenarios and options that we developed in
2005. All of that is iterative and in parallel, as well.
MR. CROCKER: Isn't it more traditional to develop the
planning criteria, and then develop the plan in that
context, as opposed to developing them both together or
considering them both together?
MR. SHALABY: It is, and we had criteria. We had
criteria all along. The criteria crystallized. The
criteria developed over time. So did the plan. We were not
-- we were not developing without criteria to start.
We did in 2005, we did in the middle of 2006, we did in
late 2006, and we stated the criteria that we were working
with all along. Just the wording of them, the evolution of
the thinking, and how we use them became more structured and
more crystallized as we went along.
MR. CROCKER: Okay.
MR. SHALABY: And enriched by our understanding of
concepts and ideas as we went along, and stakeholder input
and all of the things that we considered in developing the
final set of criteria.
MR. CROCKER: Okay. Let's go through these six
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
251
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
criteria and see how they manifest themselves in the
prefiled material specifically.
Let's start with feasibility. On page 14 of B-3-1,
your heading at line 7 is:
"How is feasibility taken into account in
developing the IPSP?"
Do you see that?
MR. SHALABY: Yes.
MR. CROCKER: You say, in the middle of that paragraph:
"For transmission OPA undertook corridor level
assessments of specific study areas to establish
feasibility from an environmental perspective."
You take us to E-3-1, E-3-3, E-3-10.
MR. SHALABY: Yes.
MR. CROCKER: Let's go there for a little bit and
follow that along and see where we get.
MR. SHALABY: I will very quickly refer you to the
transmission panel that is coming up, but we can --
MR. CROCKER: Let's start the discussion, and I am sure
that you will deflect what you are not comfortable
answering, not that I can see anything that you are not
comfortable answering, but maybe there is something.
MR. SHALABY: Yes.
MR. CROCKER: But you will deflect what you think is
more appropriate to the transmission panel.
MS. NOWINA: Mr. Crocker and Mr. Shalaby, I have a bit
of a concern that Mr. Shalaby could answer every question
and he could be here for the next six weeks, and we would
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
261
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
never get to the other panels.
So it is partly Mr. Shalaby's comfort, but I would
suggest partly, also, the reasonableness of addressing this
in the panel which is supposed to be looking at an overview,
as opposed to a panel which has technical expertise and will
be dealing with the details later.
So I just remind you of that, I will also remind you,
Mr. Crocker, of the estimate that Board Staff gave me for
their cross-examination. If you ask Mr. Shalaby to answer
every question in detail, it may take longer than you had
estimated.
MR. CROCKER: I am going to try to stick to
environmental sustainability, actually, rather than some of
the other issues.
MS. NOWINA: Which is not addressed later, all right.
Thank you.
MR. CROCKER: Yes.
MR. SHALABY: We have E-3-1.
MR. CROCKER: You are ahead of me. That's where we're
going. I haven't got there yet.
E-3-1 is the north-south transmission reinforcement.
MR. SHALABY: It is, yes.
MR. CROCKER: Okay. And if we could turn to page 25?
MR. SHALABY: I have that.
MR. CROCKER: You deal with Ontario Regulation 424/04
requirements?
MR. SHALABY: Yes.
MR. CROCKER: You say in -- and I will leave most of
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
271
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
this discussion to the transmission panel, but you say in
the last paragraph, starting at line 22, "Hardy Stevenson",
and just for clarification, that is not an individual, but
that is an environmental planning company?
MR. SHALABY: It is both an individual and a planning
company.
MR. CROCKER: Okay. "...performed an environmental
analysis..."
MR. SHALABY: I mean, there are two individuals. It's
names of two individuals.
MR. CROCKER: It's Hardy and Stevenson?
MR. SHALABY: That's right, yes.
MR. CROCKER: "...performed an environmental analysis
and concluded that there were no significant
corridor restraints that would prevent development
of a transmission line from the Sudbury area to
the GTA in an environmental acceptable manner. In
arriving at this conclusion, Hardy Stevenson
assessed potential environmental impacts in four
study areas."
Can I ask you to tell me, please, what were the terms
of reference given to Hardy Stevenson? What were they
supposed to do?
MR. SHALABY: The concept of environmental assessments
described in this particular proceeding -- and I would refer
the Board to the transmission panel, but for projects that
were going to go into environmental assessments within the
next five years, an additional requirement was stated in the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
281
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
regulation; that is, to do a planned environmental
assessment or strategic environmental assessment, or some
assessment of the feasibility. We considered it to be the
feasibility of building transmission from one place to
another.
So the specific --
MR. CROCKER: Can I cut you short, just for the
purposes of keeping within my timelines?
MR. SHALABY: Right.
MR. CROCKER: Feasibility, then, can I take it that
feasibility for the purposes of this project only dealt with
the -- for the purposes of brevity, the environmental
assessment requirements; that is, the section 8 requirements
of the regulation, not section 7 requirements?
MR. SHALABY: Section 7 is what -- what is -- section
7, that is safety, environmental protection and
sustainability?
MR. CROCKER: Right, yes. It did?
MR. SHALABY: No. It looked at land use and
environmental impact, natural environmental impact from --
and social, cultural features along the way, as well.
MR. CROCKER: From a paragraph 7 point of view - that
is, environmental protection and environmental
sustainability - or paragraph 8 point of view - that is,
where there are environmental assessments going to be done,
they had to do that assessment work? Which of the two?
MR. SHALABY: They focus more on 8. I need them to
describe their scope of work more fully. My understanding
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
291
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
is they focussed more on paragraph 8.
MR. CROCKER: Not on paragraph 7?
MR. SHALABY: I would leave them to describe that,
whether it included 7 or not.
MS. NOWINA: Excuse me, Mr. Crocker, before we do that,
before we leave it to the transmission panel, I would like
to clarify something.
According to our schedule of what each witness panel is
addressing - Mr. Vegh, you may want to respond to this - OPA
has identified that this panel is dealing with the
sustainability question.
So the point here is, if we leave these questions to
the transmission panel, is it the OPA's intention that they
will answer questions on sustainability as it relates to
transmission?
MR. VEGH: So if I can answer that, I think the concern
was that the question was asking for the terms of reference
for the actual study carried out, and there was some
legalistic issues around paragraph 7 and paragraph 8.
I thought the general gist was feasibility and how
feasibility was taken into account, and practical
applications of that and the planning criteria.
So if the question is, What does feasibility mean as a
planning criteria, I think the question is appropriate to
this panel. And this panel can probably provide some
general overview what the areas were that were taken into
account. But you will see in each particular chapter on all
of the resources - the conservation resources, supply
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
301
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
resources, transmission resources - there is a portion in
each chapter on how those criteria were applied for each
particular issue. How were all of the planning criteria
applied for conservation, for supply resources, and for
transmission?
So if the question is: How were the planning criteria
applied to make specific decisions within those chapters? I
believe that those questions are appropriate for the witness
panels that deal with those chapters. If the question is,
more general level: How are the planning criteria arrived
at, what do they consist of? Then I would suggest those
questions are appropriate for this panel.
MS. NOWINA: If the question was: How is
sustainability considered in relation to these transmission
projects? That's more appropriate for that panel?
MR. VEGH: Well, sustainability, again, leads to the
planning criteria. So the specific panels will be able to
address how the planning criteria was applied. The way in
which that planning criteria relates to sustainability, is
really outside of their scope and that would be more for
this panel.
So I think the question to the other panels would be:
How did you apply the planning criteria? And they won't
really be in a position to defend how the planning criteria
relate to the considerations of sustainability. They're
planners.
So that more global question, is really for this panel.
Once this panel is completed, the future panels that deal
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
311
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
with the specific resources aren’t going to be able to shed
a lot more light on sustainability and, for example, how
sustainability informed the concept of feasibility. They
know what feasibility means within their specific context
and how -- applied that criteria to the choices that they
had to make, but wouldn't really be able to say feasibility
is tied to sustainability by reference to sort of chapter
and verse of different primary sources.
MS. NOWINA: Did that discussion help you at all,
Mr. Crocker?
MR. CROCKER: It did. And I cut Mr. Shalaby short
because he was going to get into a discussion of section 8
concerns which I thought were more appropriate for the
transmission panel.
I will ask you a broad question. The only reason I
went to Exhibit E was because you directed me –- you, the
OPA, directed me to in the paragraph that I cited.
Describe to me, then, how issues of sustainability are
considered under the heading, under the planning criteria
rather than the heading, feasibility, and if it is of any
assistance, you can use the transmission examples that you
provided or any other example that you feel more comfortable
with.
MR. SHALABY: I will go back to some of the slides we
presented yesterday.
The quote that we have and the -- it's a common sense
thing. If you try and address sustainability requirements
with options that are not feasible, it just -- it doesn't
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
321
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
address the sustainability requirements and does not address
the context-specific needs. I mean, it's almost a
commonsensical thing, that the tool kit has to be viable and
you have to have confidence that the recommendations you are
making are feasible and the source of that confidence and
practicality of it differs, depending on what the option is
and what the timeline is and how much of it you need and so
on.
So I am not sure whether I am addressing the specific
concern that you have, or not, beyond saying: A plan does
not address any requirements if it is not feasible. An
option that is not feasible is not going to correct anything
or address anything, or do any -- have any impact on
customers, good or bad.
MR. CROCKER: If we turn that around, if I look for how
the OPA considered environmental sustainability when
applying the planning criteria feasibility, where do I find
that? How do I find that?
MR. SHALABY: One specific thing is the lead times. So
we do not say, we do not say standards for electricity
efficiency are going to be in place in 2010. All of them.
We know it takes time and it takes time to have an
impact on consumption of electricity. That's a lead time
consideration. It takes time for more efficient buildings
to be built, and for more efficient fridges to be bought,
and used, and to have an impact on electricity use. It
takes time.
We do not say you can build nuclear, new nuclear in
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
331
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
2009. It takes ten years to have the first units of new
nuclear on line.
So the lead time is one very obvious way feasibility is
applied to the plan. Is that the kind of information you
are looking for?
MR. CROCKER: Well, I am in your hands. You tell me
what you think I am looking for.
MR. SHALABY: Well, so that's a concrete example. The
other concrete examples have to do with feasibility of
supplying the resources that are needed to supply the
generating stations.
Natural gas is an example. It's an issue in this
proceeding and an issue with stakeholders. Is
infrastructure for natural gas sufficient to fuel the
natural gas fleet that we are proposing in 2010, 2012? Will
it meet the requirements? That's another issue on
feasibility.
Will it or will it not? You cannot build natural gas
stations without sufficient pipes and storage, and this
Board had a large proceeding on the interface between
electricity and gas issues, to ensure exactly that
feasibility and to plan for it, particularly the storage
aspects and the delivery aspects.
So that's another example of feasibility of options and
assuring the feasibility of supply of electricity from the
options that were specified. Those are two examples. I can
go on and give you more, if you like.
MR. CROCKER: No. If you are comfortable with your
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
341
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
answer, then I am comfortable with it.
MR. SHALABY: I want to know whether your question was,
that satisfies your question? Because your question was
less than totally crystal clear in my own mind at least.
MR. CROCKER: Well, I am going to leave the issue I
think to others who are going to follow up on that and I am
going to move on.
MR. SHALABY: All right.
MR. CROCKER: Let me just ask one sort of follow-up
question. If I were to go through all of the transmission
examples that you listed in that paragraph, E-3-1 to E-3-10,
the -- what I am going to find is a discussion of issues
with respect to the requirements in paragraph 8 of the
regulation, not 7; is that correct?
MR. SHALABY: Yes.
MR. CROCKER: Okay. Then let's leave that, then, to
the transmission panel.
Let's go on to reliability. In answering the question
-- and once again, these are the planning criteria that you
on behalf of the OPA, and the OPA is suggesting, in this
prefiled material, was applied in the context of, or to
reflect environmental sustainability. I am not
misinterpreting, am I?
MR. SHALABY: You are not misinterpreting.
MR. CROCKER: Okay. Then if we go to reliability --
MR. SHALABY: I am not going to split hairs about
reflect, consider, consistent with. Let's go beyond that
for now, but they are consistent with the requirements for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
351
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
sustainability.
MR. CROCKER: Okay.
MR. SHALABY: Yes.
MR. CROCKER: You say, on page 15 of B-3-1, at -- yes,
page 15, line 15, you describe how or you ask the question:
"How was reliability taken into account in developing the
IPSP?" You say, "This determination is based on assessment
of future demand," and you give the example of D-1-1, "a
projection of how the current and planned resources will
perform over time," in D-3-1, "and assessment of future
uncertainties to a determination of the planning reserve
requirements," in D-2-1.
Then you go back, again, to Exhibit 5 -- I'm sorry,
Exhibit E-5-1, E-5-6. These are transmission projects.
MR. SHALABY: Correct.
MR. CROCKER: D-1-1, D-3-1, D-2-1, those are
forecasting, are they not? Forecasting?
MR. SHALABY: Assessment of requirements, yes.
MR. CROCKER: Okay. Explain to me where I find issues
of environmental sustainability when I look at those aspects
of the plan. Where do I see the consideration of
environmental sustainability?
MR. SHALABY: If we go back to the requirements list,
the sustainability requirements, providing people with
necessities in life, livelihood, the words "livelihood",
"sufficiency" and "opportunity", providing that everywhere
in Ontario, not just specific places in Ontario, so equity
in providing reliable supply, providing that over time to
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
361
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
future generations, as well as current generations - that
is, intergeneration - so providing reliable electricity
everywhere in Ontario provides for requirements for
sustainability.
Sustainability requires that people have access to what
they need to live well and to live a productive and safe and
healthy life, and electricity certainly does that, and
providing reliable electricity everywhere in Ontario for
every time period between now and 2025 certainly contributes
to that requirement.
That's where you find it. So we assess the
requirements for people. We assess how to meet these
requirements, every time, everywhere and for every year in
the plan.
MR. CROCKER: And that falls within the OPA's
definition or description of environmental sustainability,
does it?
MR. SHALABY: That is a requirement of sustainability,
is to consider whether people have enough to live a decent
life, a safe life, and it's distributed equitably within a
geographic or -- jurisdiction and considers future
generations.
So this is why I am saying it is not a one-to-one.
It's not a mapping of requirements to criteria, but
certainly having reliable electricity in Ontario for 20
years to all of the people of Ontario is consistent with
many of these requirements.
MR. CROCKER: All right.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
371
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: So while reliability is an old concept
and people said, Well, we always had reliability as a
planning criteria, well, it turns out that sustainability
requires reliable supply of electricity, sufficient
electricity, distributed everywhere in Ontario, to this
generation and next.
So while -- the criterion is something that we used in
the past, and it turns out that it is consistent with many
requirements of the sustainability when you understand
sustainability in the way that we did.
MR. CROCKER: All right. Let's do the same thing with
respect to the next planning criteria, which is flexibility.
MR. SHALABY: Correct. That now addresses a different
set of requirements, and that's adaptability, precaution,
planning for uncertainty, being ready for the world to
unfold in ways different than you foresee, and not being
surprised by that and cornered into unpalatable options.
Plan sufficiently that when uncertainties emerge, you have
good options and you respond well.
That is, roughly speaking, what flexibility provides
for. That is consistent with sustainability requirements.
MR. CROCKER: At B-3-1, at line 3, you ask the
question:
"What are the typical uncertainties considered in
determining resource requirements?"
MR. SHALABY: Line 3 of what page, so I can follow?
MR. CROCKER: Seventeen.
MR. SHALABY: Okay. Yes.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
381
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. CROCKER: And you describe them in the following
six or seven lines, or so, and I am going to ask you the
same question. Where do I see a discussion of environmental
sustainability when the planning criteria of flexibility is
applied or is discussed by the OPA?
MR. SHALABY: Well, the page previous, page 15, the
discussion starting at page 15 describes the link between
sustainability requirements and flexibility. Is that the
nature of the question that you are...
MR. CROCKER: I think my question was pretty clear. We
have developed a pattern now. I think the question was
clear. You do your best to answer.
MR. SHALABY: Can you go over it again?
MR. CROCKER: Yes. When I look at the application of
the planning criteria flexibility, when you -- in the
prefiled material or in any other material, in determining
how the IPSP was developed, where do I see a discussion of
sustainability -- I'm sorry -- yes, sustainability or
environmental sustainability?
MR. SHALABY: You see it in the link that we have
between the sustainability requirements and the development
of the planning criteria, so not in the application of the
criteria, but in the development of the criteria. So we go
from requirements to criteria. Then you apply these
criteria.
In every section, every panel that will be appearing in
front of you will describe how they applied the criteria.
So that's how sustainability is applied.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
391
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
It is applied through the criteria.
MR. CROCKER: Once again, then, I take you back to one
of the earlier questions I put to you.
Isn't it normal to establish the criteria, and then
develop the, in this case, plan, in the context of those
criteria rather than the other way around as you have just
described?
MR. SHALABY: We always had criteria. I answered that
earlier. We had -- flexibility was one of our criteria from
day 1 --
MR. CROCKER: All right.
MR. SHALABY: -- and managing risks. We called it
managing risks, we called it flexibility, we called it
adaptability, along the way. This was always a criterion.
In fact, it was accorded a specific discussion in the early
discussions of the planning papers and it is throughout our
planning discussion.
So it is entirely consistent with what you described.
We always had criteria and we always developed plans
according to these criteria. Both of them evolved over
time. Both the description of them and the application of
them evolved over time.
MR. CROCKER: Okay. I will just ask the question with
respect to flexibility one more time and I won't ask it
again.
If I were to look, then, in the material, I won't find
a specific discussion of how sustainability was considered
by the planning criteria flexibility. It was the other way
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
401
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
around? The planning criteria was developed in the context
of a sustainability framework; is that right?
MR. PIETREWICZ: Sorry, can you please repeat the
question?
MR. CROCKER: I am not sure I can.
MS. NOWINA: I can read it back, and I think it might
be helpful to break it into -- you asked two questions, Mr.
Crocker. We will do them one at a time.
What you said is:
"If I were to look, then, in the material, I won't
find a specific discussion of how sustainability
was considered by the planning criteria
flexibility. It was the other way around?"
That is the first question.
MR. SHALABY: Sustainability considered by the planning
criteria flexibility? Sustainability requirements talk
about adaptability, precaution, adaptation, respect for
uncertainty. So if we go to page 8 of B-3-1 -- why don't
you go through that?
MR. PIETREWICZ: Perhaps I can be helpful.
MR. CROCKER: Please speak up, Mr. Pietrewicz.
MR. PIETREWICZ: Sure.
As Mr. Shalaby was trying to point out, the plan itself
was developed to reflect flexibility.
As we pointed out in our presentations yesterday,
flexibility and adaptive capability of the plan itself is a
salient feature of the plan, and we have illustrated that.
We have explored flexibility and adaptive capabilities
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
411
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
through the explanation of scenarios, among other things,
and proposed that the plan should be flexible enough to meet
a range of resource requirements across a variety of
potential futures.
That treatment of flexibility, I think, is
acknowledging what is described in B-3-1 as a planning
criteria called "flexibility", which traces, I think, its
origin in the sustainability language to what we have listed
in Exhibit B-3-1 on page 8 in table 1. And that larger,
sort of more -- less context-specific criteria or
requirement of sustainability was called precaution
adaptation.
So in other words, the plan itself is meant to embody
flexibility. That flexibility is one of our planning
criteria, which is outlined in B-3-1 on page 12, table 2.
And those criteria were developed in consideration of a
larger sort of constellation of sustainability requirements
that are detailed in table 1 on page 8 of B-3-1, and one of
those requirements is precaution and adaptation, which we
applied specifically and we called it flexibility.
MR. CROCKER: Thank you. Madam Chair, I can't
remember, is now the time when you wanted to take your
morning break?
MS. NOWINA: 10:30 is when I planned it, but if this is
a good time for you we can do it now.
MR. CROCKER: It makes no difference. I just lost
track of exactly when.
MS. NOWINA: 10:30.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
421
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. CROCKER: Okay.
All right. The next planning criteria is cost. Once
again, can you explain to me how -- can you explain to me
how the concepts of, the concept of environmental
sustainability is reflected in the application of, or in the
development of if you are more comfortable with that, the
planning criteria cost?
MR. SHALABY: Yes. Again, cost is one of those
criteria that has been around in most planning exercises.
It's a common one. It has applied for -- for many, many
planning cycles before the formal requirement to consider
sustainability.
So what we find is, again, the livelihood, sufficiency
and opportunity is a criterion that says: Can people afford
electricity? Is electricity affordable? As I said
yesterday, that's a subjective and a difficult question to
answer in its entirety, in terms of the entire population of
Ontario, every customer, every industrial customer, every
school board, and every consumer. But generally, the costs
of electricity would affect affordability of electricity in
Ontario.
So keeping in mind the requirement to provide for
livelihood, sufficiency and opportunity to Ontarians, cost
is a factor in that. And information about cost would
inform us on whether, in fact, electricity is contributing
to livelihood, sufficiency and contributing to opportunities
in Ontario, or not. That's one way.
There are other more subtle ways, the way we assess
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
431
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
costs, deals with the long term.
The approach of using levelized cost gives similar
weight to long-term benefits and cost as to present costs
and benefits. If you use an accounting technique for
describing "cost" -- I don't want to get into a whole lot of
amortization and interest depreciation, but if you used an
accounting description of costs you would come to a
different assessment than if you used a levelized assessment
of cost. A levelized cost gives importance to the future.
A social discount rate gives more weight to future
values than a high discount rate, as an example. So these
are other ways in which the way we applied cost is
consistent with considering the future, with giving weight
to future value and future cost. The way we did Monte Carlo
assessment or uncertainty assessment in the cost category is
consistent with considering uncertainties and the impact of
uncertainties.
So while the word "cost" is a traditional criterion,
you find the way we applied it, the way we considered cost,
the way we considered uncertainty in the cost is consistent
with some of the requirements for sustainability.
I can go further and say that the price of electricity,
of the commodity, at least, is uniform in Ontario. Delivery
may be different, but it is intergenerational, uniform
availability of electricity in Ontario at similar price.
So you can say the cost description captures a number
of the requirements for sustainability.
MR. CROCKER: Were the planning criteria that we're
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
441
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
discussing here applied equally? That is, they were
weighted equally, in terms of your analysis? Or were there
elements -- some of those criteria given more weight than
others?
MR. SHALABY: They were addressed sequentially. We did
not get into weighting of criteria. That's, in fact,
one of the learnings we had from the sustainability
requirements in literature, is that trying to meet all of
the requirements, try and meet all of the criteria, and for
that reason we didn't present you with alternatives that we
set up and shoot down and say: That doesn't meet the
criteria. It is more productive to develop alternatives and
plans that meet all of the criteria.
Why develop plans that we know will not meet the
criteria? It is a good academic exercise, it is a good
study, but I think it is more productive to put our energy
into developing plans and alternatives that meet the
criteria, all of them.
So there is -- and that was a learning that we had.
Try and not to trade off one criteria against the other
early on. Do the trade-offs only if you have to and only if
necessary. But going in, attempt to meet all of the
criteria, attempt to find options and plans that meet all of
the criteria.
So that was our going-in assumption and that is why we
did not get into alternatives but got into a solid plan that
meets all of the criteria.
Now back to the sequential going-through the criteria.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
451
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
If something was not feasible, it stopped there. It does
not get subjected to other criteria evaluation. It doesn't
pass the first filter.
So we had the notion of filters. Right. Then we went
into reliability. If the plan is not reliable, and not
flexible, those two together are requirements that were
important to meet. It did not get into being costed and
being evaluated for that.
Finally, when a plan is feasible, it is flexible, is
reliable, and we assess its cost, we see whether we need to
differentiate, is there anything more that can be said about
sustainability, about environmental performance or about
societal acceptance? We decided, for the plan that we
presented, that all of the options that we present, the
entire plan is societally acceptable for the four reasons we
mentioned yesterday and we continued to mention today and we
described the performance, the environmental performance.
We described the emissions and we track them over time.
So that's the sequence we went through, if that is a
way of using the criteria going forward, and we described
that in Exhibit A-2-2.
MR. CROCKER: Following along then in the same vein,
where are the elements of environmental sustainability when
you applied the criterion of environmental performance?
MR. SHALABY: Where are the elements of environmental
sustainability? Well, identifying information, being
transparent about information is a requirement for
sustainability.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
461
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
So providing information in an open forum like this and
disclosure of information completely is in itself satisfying
a requirement of sustainability.
MR. PIETREWICZ: I think, more specifically, the
environmental performance results that describe the
scenarios considered are presented in Exhibit G-2-1. G-2-1
called -- under the plan performance section.
There you will find how the OPA tracked the variety of
environmental indicators associated with the operation or
simulated operation of each of these plans, and it includes
things that Mr. Shalaby referenced yesterday, including
greenhouse gasses, and waste, water use, radioactivity, and
particulate matters.
MR. SHALABY: Madam Chair is looking for the reference.
I think it is G-3-1 that has a performance indicator. I
didn't think I needed to correct it but if you are going to
go through the trouble, maybe we should.
MS. NOWINA: It is important to have it correct on the
record as well, Mr. Shalaby.
MR. SHALABY: The --
MR. CROCKER: If I could just follow up, with Mr.
Pietrewicz.
MR. SHALABY: Yes.
MR. CROCKER: How then did sustainability factor in to
the analysis of environmental performance?
MR. SHALABY: The socio-ecological system integrity is
about the -- whether the emissions and the rates of
consumption of resources, that is between that and the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
471
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
resource maintenance and efficiency. There are two
criteria, two requirements. One is socio-ecological system
integrity. One is resource maintenance and efficiency.
So the question is: Are the emissions and -- the
environmental emissions from, and lands use and water use
and airshed loading that is predicted over the next 20 years
consistent with socio-ecological system integrity, or not?
And the conclusion we have is that if emissions are
going down, that can only be a good thing. The -- most of
the emissions are going down. The only thing that is going
up is land use, and the thing that is staying steady is
radioactivity and water use for cooling.
So while we did not perform an assessment of -- socio-
ecologic assessment of the impact of the emissions, we
observed that the plan is taking most of the emissions down,
the air emissions, the mercury, the solid waste, is -- and
we identified that the land use is the element that is going
up during that plan, and we showed the feasibility of using
land for renewables and for transmission.
So if that helps, that is where the criterion comes in.
We note, as well, all of the environmental regulations --
this meets all of the environmental regulations. We note
that it meets government policy. So meeting government
policy, meeting all of the specific environmental
regulations, and trending down over time, these are all
three indicators of environmental performance that we think
is a good environmental performance of the plan.
MR. CROCKER: Okay. I am not going to follow this
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
481
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
through to the last planning criteria, and I will -- I am
going to move on to another area, the last area I want to
talk about, so this may be a good time to break.
MS. NOWINA: It is. We will take a break now and
resume at 10:45.
--- Recess taken at 10:25 a.m.
--- On resuming at 10:45 a.m.
MS. NOWINA: Please be seated.
You may continue, Mr. Crocker.
MR. CROCKER: Thank you, Madam Chair, Members of the
Panel.
I would just like to complete the discussion in this
area, and then I have just two other areas briefly to
discuss with you.
I asked you questions sequentially, that is dealing
with each of these planning criteria sequentially which may
have encouraged you to answer this way, but I gather, from
your answers, that you did, in fact, apply the criteria
individually to the sustainability concepts. Is that
correct?
MR. SHALABY: Apply the criteria sequentially to the
sustainability concepts.
MR. PIETREWICZ: I think, Mr. Shalaby mentioned earlier
that the first two criteria of feasibility and reliability
were certainly sort of pass/fail type of criteria.
If the plan or the components of the plan under
consideration was not feasible, it wouldn't have been
considered.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
491
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Similarly, reliability itself was, as your question
indicates, considered on its own, to answer the question: Is
this plan reliable? Or are these components reliable?
Then the other criteria, the other four criteria, for
example, cost, were considered both in terms of making
discretionary resource choices, those are choices that the
OPA has some discretion over.
For example, renewable choices, and that's described in
Exhibit D-5-1, or for example when deciding on the
incremental amount of base-load requirement to be supplied
by nuclear. That was a cost decision, an analysis made in
Exhibit D-3-1, attachment 1. So, yes, certainly cost was
one of those things that, where applicable, we did treat
individually, and then later on expressed the cost of the
plan itself in an exhibit G-2-1. Yes.
Flexibility, as well, was one of the criteria that we
used and it was treated more at a plan level. But there are
discussions throughout the evidence of whether flexibility
is a distinguishing criteria in making specific resource
choices.
MR. CROCKER: If I were to say to you that a more
traditional planning approach to the issue of -- issues such
as sustainability, particularly with respect to
sustainability, would be to apply all of the criteria to
each of the sustainability concepts, such as the ones
provided by Gibson, would you agree with that?
MR. SHALABY: The criteria are a practical guide that
is context specific.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
501
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
They are the way -- the tools that we will apply to
planning that will reflect and be consistent with
sustainability principles and requirements.
So that's the way you should look at the criteria.
The criteria alone, if we gave a system planner the
criteria alone, they will not know what to do with it.
If we give them, sorry, if we give them the
requirements, the eight requirements, if we give somebody
the requirements to be -- socio-ecological stability and
intragenerational equity and said: Design a system plan,
they will not know what to do with that. We had to
translate that into something they can do something with.
And that's a context-specific, something that relates
to electricity, to planning, to Ontario, to 2007, to the
government policy that we have today that we have to meet.
So that's the relationship between requirements and
criteria.
MR. CROCKER: Okay. I want you to go with me, briefly,
to C-10-1, please. I would like you to go to page 40.
MS. NOWINA: Mr. Crocker for the record, what document
is that? Is that one of the IPSP reports?
MR. CROCKER: I'm sorry. It's a discussion paper,
sustainability discussion paper, discussion paper 6.
MS. NOWINA: Thank you.
MR. SHALABY: What page?
MR. CROCKER: Page 40. I gather, from reading the
discussion paper, that SENES Environmental Consultants were
retained by the OPA, to do -- perhaps you can tell me,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
511
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
describe to me the retainer. What were they asked to do?
MR. SHALABY: They were generally asked to estimate the
environmental emissions that arise out of the various
electricity options that we are considering in the plan.
MR. CROCKER: So the last paragraph on page 40, you
say:
"While the terms of reference for the engagement
were extensive, SENES provided a raw score by
technology for the life cycle environmental impact
of each generation technology on each category."
Describe to me what that means, please.
MR. SHALABY: It's -- the raw score is -- hang on a
second.
MR. CROCKER: Just so you understand why I am asking
you this.
MR. SHALABY: Yes.
MR. CROCKER: I just want to understand what they did
for you, because they suggest on the first full paragraph on
the following page:
"SENES recommended a weighting scheme based on the
European Commission’s exhaustive study of the life
cycle impacts of different generation options."
And I wonder what that was and how, if at all, that
factored into, their recommendations factored into what the
OPA did.
MR. SHALABY: Thank you for elaborating the purpose.
SENES did two studies for us: One that we considered
in the supply mix advice, and this reference here is to the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
521
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
first study that SENES did. That is volume 4 of the supply
mix advice documents as correctly referenced here.
They then did a more detailed and more Ontario-specific
assessment on options, and that is part of the evidence in
G-3-1, it is an attachment to G-3-1. So SENES did two
pieces of work.
The first piece, in 2005, was built on international
experience, indicative numbers that are referenced in the
literature, and it had two dimensions to it that we did not
go into in as much detail in the latter phases. One was
life cycle assessment and the other one was the scoring
according to the health impacts, European Commission's study
of life cycle impacts.
So it was broader in scope, in that it was life cycle.
It assigned scores to air emissions, land use,
radioactivity, water use and so on, that permitted scoring
the environmental impact of an option against another
environmental impact of another option on a basis that could
be comparable in, numerically at least. So that is what the
first study was.
We moved on to more specific Ontario technology, more
specific technologies that will be used in the plan. So for
example the specific gas turbines, specific combustion
turbines, specific nuclear technology in Ontario rather than
the generic nuclear technology that was referenced in the
first phase. And so on. What we discovered was in the
second phase that the life cycle data was less available for
Ontario-specific options than it was internationally.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
531
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
We also concluded that the operational phase was more
compatible with mixing the new options with the existing
options and it was certainly the dominant environmental
impact for most options. So we did an alteration
methodology, as we went through.
MR. CROCKER: What was the scoring for, to tell you
what?
MR. SHALABY: If you adopted the scoring, if you
accepted that the scores determined or are indicative of the
health impact on population, then something with low score
would have less health impact than something with high
score.
MR. CROCKER: And was this kind of study considered by
the OPA when considering various options, the sustainability
issues with respect to various options?
MR. SHALABY: It was considered in the early stages of
developing vastly different scenarios in the supply mix
stage, so, for example, a case with a lot of natural gas, a
case with a lot of nuclear, a case with more renewables,
less renewables.
When all of the options were open in very large degree
of different mixes, we considered it at that stage. We did
not consider it when the decisions that were facing us were
very focussed, and the big decisions of how much gas, how
much renewables, how much conservation were already decided.
So we didn't consider it in the latter stages.
They were also controversial and did not meet with a
lot of consensus at the end of the day.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
541
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. CROCKER: Okay. Let's go from there, then, to the
last sort of evolved -- to the last area I want to talk to
you about, and that deals with your slides 14 and 15 from
yesterday.
MR. SHALABY: Yes.
MR. CROCKER: You say in 14 that you did not
differentiate alternative choices for the planning
decisions, as all options comply with environmental
requirements.
MR. SHALABY: Yes.
MR. CROCKER: Okay. What environmental requirements
are you talking about?
MR. SHALABY: These are environmental protection
requirements, and government policies to do with greenhouse
gasses, for example, those would be examples of
environmental requirements.
MR. CROCKER: Okay. So just so that I am clear, you
equated -- let me ask you the question without suggesting
the answer.
Did you equate environmental compliance with the
requirement to consider environmental protection in
Regulation 424?
MR. SHALABY: Yes.
MR. CROCKER: And, also, just to be clear, there was
-- there were no differences on the basis of environmental
requirements among alternative choices?
MR. SHALABY: There are differences in the amount of
emissions, but the old environmental protection
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
551
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
requirements, they are all environmental regulations and
requirements in Ontario.
So there were different -- we showed that a plan under
high load growth or a high conservation scenario would have
higher CO2 emissions or lower CO2 emissions. A plan with
delayed nuclear would have less radioactivity in a number of
years than others.
So they have different environmental emissions, but all
of them are well within regulations, environmental
protection regulations, and environmental policies of the
government.
MR. CROCKER: All right. I think I understand you now.
So you didn't prefer one that might have been better
environmentally to another, as long as both complied?
MR. SHALABY: We didn't know what "better
environmentally" means. If you are not allowed to trade one
emission for another, add a numerical value to one -- is use
of an acre of land better or worse than 2 kilograms of CO2?
We didn't know the answer to that, and for that reason you
couldn't trade them off.
MR. PIETREWICZ: Another specific example would be
something like comparing wind and water, which we do in
Exhibit D-5-1. Now, sort of intuitively one can imagine
that water would involve -- water power would involve
perhaps more water use, whereas wind power may involve more
land use.
They both comply with environmental requirements, but I
don't think we distinguished the water and wind on the basis
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
561
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
of trading off water use versus land use.
MR. CROCKER: Okay, I understand.
The next slide you say, "By recognizing the" -- this is
the slide that deals with the social acceptance. You say:
"By recognizing the lack of specifics at the
planning stage that differentiate planning
decisions and focussing on acceptability of
broader plans..."
And then you say in the fourth bullet, "taking further
approvals into account."
These further approvals, are they environmental
assessment approvals, for instance? What are they?
MR. SHALABY: For example, yes.
MR. CROCKER: Are there others?
MR. SHALABY: There are municipal approvals or land use
approvals. There is Planning act approvals.
An electricity project is subject to a very long list
of requirements and approvals at the implementation stage.
MR. CROCKER: Okay. Then you say in the next bullet:
"Societal acceptance issues are identified, but
they did not differentiate alternative choices for
planning decisions."
Once again, I just want to understand what you mean.
You didn't -- no choices that you made were based on -- I
will ask it the other way around.
Societal acceptance didn't factor into or was not a
factor you considered when making choices within the plan?
MR. SHALABY: It's a factor we considered in developing
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
571
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the plan, but it did not differentiate a little more gas, a
little less gas, a little more conservation, a little less
conservation, because all of it was within government
directive.
All of the options and alternatives we discussed and
described for you in the plan, all of the eventual layout of
the plans, is within government direction. And government
direction and policy is a primary indication of societal
acceptance, as far as plans are concerned, in our
estimation.
So the way the plans developed, whether they developed
along the path of 2A or 3A or 4B or 1B, all of that was
considered acceptable, because it complies with government
directive, and because all of it will be subject to further
approval, and because all of it is done in an open and
transparent way and all of it is subject to the
comprehensive governance capability in Ontario for
environmental, labour, social matters.
MR. CROCKER: Thank you. Thank you, Madam Chair,
members of the Panel.
MS. NOWINA: Thank you, Mr. Crocker. That completes
Board Staff's cross-examination?
MS. LEA: Yes.
MS. NOWINA: Thank you. Mr. Poch, I believe GEC is up
next for cross-examination.
MR. POCH: Thank you, Madam Chair.
PROCEDURAL MATTERS:
MS. NOWINA: Before you begin, Mr. Poch --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
581
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: I know where you are going, Madam Chair.
That is exactly where I am going.
MS. NOWINA: All right. I will let you go there first.
MR. POCH: I was going to say, Madam Chair, obviously
one could have an interesting discussion about regulatory
incentives, but these questions of controlling time and what
-- the incentives it gives for counsel and witnesses and so
on. I am very mindful of the concern you have raised.
I have -- frankly, my estimate is -- it is a simple --
I have very little idea how long this is going to take. My
sense from the cross-examination I have just heard is I may
be fairly accurate, because it does seem to be taking some
time to get things nailed down.
I would like to say, though, Madam Chair, I will in a
moment hand out a little outline of my cross, which let's
you know the topics I propose to cover, so I am also
cognizant of what you said about not getting into too much
detail on matters that we'll deal with later, because we
will inevitably then have repetition, which would be
undesirable.
I am going to ask my colleague, Mr. Millyard, to hand
up to you and to others a page, which is basically just the
table of contents to my cross-examination headings, so I can
lay before you what I am proposing to address with this
panel and hopefully respect that distinction.
It is, of course, a grey area, what's here and what is
there, but I should say my approach is that this is not just
an overview panel. This is the plan development panel, as
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
591
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
well as the sustainability panel.
So I do propose to cover topics which have to do with
how, from a planning -- how the planning protocols dealt
with trade-offs between different options. When we get into
the details of how they have costed something, or what have
you, for a given option, I will try to place myself and
leave that for the subsequent panels, but it will be
necessary to pull some examples of how they have
differentially dealt with things, different kinds of
options, because that is a prime concern for us in terms of
the planning considerations.
I don't know -- do you have that in front of you now,
Madam Chair?
MS. NOWINA: Before we go into it, Mr. Poch, just so
others in the room know why Mr. Poch and I are having this
discussion. He has given us an estimate of 480 minutes for
this cross-examination, which is a fairly lengthy period of
time.
Mr. Poch, I am going to ask something of you. I would
ask you, tomorrow morning, after you have had the experience
of today's cross-examination, to give me another estimate
that is perhaps more realistic than the estimate that you
now have, because you will have the experience of today to
base it on.
MR. POCH: I will undertake to do my very best, Madam
Chair. Of course that will help others prepare and know
when they are up as well, apart from your need to keep
control of this process, which I sympathize with.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
601
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
If people have it in front of them, this table of
contents which I thought just might be helpful so people
could follow along and the Board would have a sense of how
the different questions fit into where I am headed. The
first point is, there is one title that didn't get updated
and it is item 1A should read, "Approvals sought: Scope and
discretion."
As you will see, I intend to touch on approvals sought
in effect of the update, much as Ms. Lea already has, and
hopefully not repeat too much then turn to sustainability
which I understand this is the primary panel for.
We want to talk about how the plan as a whole addresses
uncertainty, how the plan as a whole complies with some of
the specific directives. And then section 5, we want to do
what I was talking about a moment ago, which is just compare
and contrast how different options were dealt with, either
even-handedly or differentially, on a number of criteria.
I have a few matters -- I have given it a separate
heading just to try follow the issues list, but these are
perhaps more in the nature of just determining where we go
on these, that's a short piece.
Some questions on costing, and I won't be asking here
to get into any detail about what the costs are, just to
understand what went into the cost, what didn’t go into the
costs, and so on. Then a couple of wrap-up pieces on the
breadth of what's been done in the planning process. So I
hope that helps everyone follow along and apologies in
advance for this being so long.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
611
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MS. NOWINA: Thank you, Mr. Poch. You might also keep
in mind we will break for lunch at 12:15.
MR. POCH: Thank you, Madam Chair.
MS. NOWINA: Yes, Mr. Vegh.
MR. VEGH: Thank you. This is the first I have seen of
this list. We have worked out arrangements with other
counsel and offered it to Mr. Poch as well that if they
would like to have a sidebar conversation about which panels
they should be cross-examining on which issues or which IRs,
we have spent time with them to help walk through that.
It's unfortunate we didn't get the opportunity here. I
will just sort of telegraph now as I quickly look at this
list, issues 5, 6, and 7, and 8, and 9 do seem to deal
extensively or do deal with issues that are extensively
addressed in the subsequent chapters.
So rather than raising an issue every time, a question
is raised that might be dealt with in more detail, the panel
may be in a position to do that as these questions do arise,
but it does look to me like there are detailed planning
decisions being addressed in these categories, in
particular.
And I just wanted to raise that now at the outset. I
don't want to spend all of the time during the cross-
examination standing up and objecting. But it could be at
the end of the day, as well, as you indicated and we have
more information, we could sit down with Mr. Poch and help
him direct some of these issues to the appropriate panels.
MS. NOWINA: Or even as early as lunch hour, perhaps
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
621
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
you and Mr. Poch could have that discussion if you believe
it would be helpful.
MR. VEGH: I would be happy to do, Madam Chair.
MR. POCH: I thought we had that conversation when we
chatted briefly about this general question of these trade-
offs between options in a corridor discussion I had with Mr.
Vegh, but obviously he feels he can give me greater
direction, I am happy to listen to that.
Madam Chair, there will be four or five -- I think it
is five or six exhibits that I provided to my friends and
all of the parties and hopefully the Board got a couple of
days ago, I am wondering if we should just distribute them
now and as we get to the -- they're stapled in a bundle but
as we get to the particular ones, maybe we could assign them
numbers.
Does that make sense?
MS. NOWINA: Let's have them here. Are they already on
the record, Mr. Poch?
MR. POCH: They were sent out electronically Sunday
evening to everybody.
MS. LEA: They haven't been given an exhibit number
yet.
MS. NOWINA: We have them in the evidence already
before us?
MS. LEA: I will assign exhibit numbers.
Mr. Poch, what's an appropriate title for the bundle of
documents that we have?
MR. POCH: That's what I was just asking. Perhaps I
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
631
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
should address this to you, Ms. Lea, which is your
preference for keeping track of things.
We could give it a single number, or it might -- I am
wondering if the record would be cleaner if we give
different items a separate number. It is up to you.
MS. LEA: The difficulty is, Mr. Poch if it is all
stapled together and it is all going to be submitted to one
panel, you might as well give it one number. Is it
paginated? No. Okay. So you will just have to guide us to
the appropriate part. I think that is easier than trying to
pull it all apart now.
MR. POCH: Let's call it cross-examination materials
-- GEC Pembina cross-examination materials on plan
development.
MS. LEA: GEC, I will leave it at that, if that's all
right, GEC cross-examination materials for plan development.
MR. POCH: Yes. Just as a consequence of what's
happened in the last few hours we have one more we would
like to add, which I didn't obviously distribute in advance,
but it is just a couple of pages off the OPA's website. So
I don't think there will be any problem.
MS. LEA: So I would like to begin then by giving that
first bundled of materials stapled together exhibit number
K2.1.
EXHIBIT NO. K2.1: GEC CROSS-EXAMINATION MATERIALS FOR
PLAN DEVELOPMENT
MS. LEA: And the OPA looks like a list of directives
and other --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
641
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: That's correct.
MS. LEA: So ... just a moment, please.
List of directive and letters. Call it K2.2. List of
directives and letters.
MS. NOWINA: OPA list of...
MS. LEA: It has OPA on the title but the directives
are from the minister, so that will be Exhibit K2.2.
EXHIBIT NO. K2.2: LIST OF DIRECTIVE AND LETTERS
MS. LEA: Thank you, Mr. Poch.
CROSS-EXAMINATION BY MR. POCH:
MR. POCH: Thank you. Mr. Shalaby, perhaps I will
start with you. Just some general matters. I take it you,
I think, commented on your long involvement in system
planning. I take it you were actively involved in Ontario
Hydro's demand spot plan, the balance of power plan
development --
MR. SHALABY: Yes.
MR. POCH: -- back in the -- around 1990?
MR. SHALABY: Yes.
MR. POCH: What was your role in that?
MR. SHALABY: I was coordinator of the plan development
and plan review.
MR. POCH: So in a sense you were in charge of that
exercise, that planning exercise?
MR. SHALABY: Not the entire planning exercise, the
technical parts of it. The analytical and planning parts of
it, yes.
MR. POCH: And have you, in your work with Ontario
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
651
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Hydro, did you have involvement with the nuclear division at
any point in your career?
MR. SHALABY: No.
MR. POCH: No. I can't imagine why I thought that,
but...
MR. SHALABY: I had one rotation in design and
development, one rotation in research department. They were
-- I was at generating stations but I was not working on the
nuclear side.
MR. POCH: Let's turn then to the first area of scope,
and Ms. Lea covered with you -- you're asking for approval
for two gas plants for, in a sense, a transfer of
responsibility for Lennox from the IESO contracting to OPA
procuring; do I have that right?
MR. SHALABY: Yes.
MR. POCH: Could you just -- then you mentioned there
is some preparatory work on transmission. Can you just
explain what the nature of that approval is you are seeking?
It's not a facilities approval?
MR. SHALABY: Is this the development work on
transmission?
MR. POCH: Yes.
MR. SHALABY: The development work in transmission is
something that we're pointing out at this stage for
transmitters to start working on alternatives to meet that
requirement.
So we're not seeking approval for it. It's
transmitters that would be seeking approval for that, if
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
661
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
they wish, in their own revenue requirements or in their own
hearings.
MR. POCH: You're not procuring anything with respect
to transmission?
MR. SHALABY: No, we're not.
MR. POCH: All right. You're seeking approval of that
aspect of the plan in the hope that that will assist Hydro
One and others obtain whatever approvals they need?
MR. SHALABY: We have two objectives, and that is to
point to the transmission that is likely to be required to
incorporate the renewables, in particular, and to have that
work started in good time to enable the rest of the plan
objectives to be achieved; and, in addition, the second
objective, that it will help others put their projects in
context for this, for whatever section 92 or other approvals
that they need, yes.
MR. POCH: You are not seeking any approval at this
time from this Board for -- to enable procurement of
combined heat and power; correct? I'm thinking of the
larger than 10 megawatt variety.
MR. SHALABY: We have a directive for 1,000 megawatts
and another directive for 100 megawatts combined heat and
power already. We are not seeking additional procurements
in that regard, yes.
MR. POCH: All right. Similarly for CDM?
MR. SHALABY: For conservation, we have directives on
conservation that will enable the targets for 2010 to be
met; that's correct.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
671
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: Can we turn to that -- well, let me first
ask you this.
The -- is it your understanding that once this Board
has given you -- has approved a plan, whether a plan may or
may not be approved, then that's -- you're going to be going
forward -- other than the existing minister's directive,
that is going to be your authority for procurement and
action? You won't be able to have resort -- there won't be
any new minister's directives?
MR. SHALABY: I cannot speculate whether there will be
additional ministerial directives or not.
MR. POCH: Maybe this is a matter for me; I can discuss
it with Mr. Vegh and we can clarify that. It was my
interpretation of the act that that section of the act is no
longer in play.
MR. VEGH: Madam Chair, that is a legal issue. I am
not sure -- I am sure we will address it in argument,
perhaps. I am not sure if you want that addressed now. If
you would, I would be happy to comment on it.
MS. NOWINA: If you have some quick clarification, it
may help us, Mr. Vegh.
MR. VEGH: Okay.
The power of the minister to direct the OPA or to give
directives to the OPA to enter into procurement contracts is
in section 25.32(4) of the act. It's a transitional power.
I am trying to give you chapter and verse here. But,
in effect, the directive power authorizes the minister to
direct the OPA to enter into procurement contracts with
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
681
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
respect to initiatives that have been commenced by the
Crown.
So if the Crown starts off the initiative, the
directive can then go to the OPA to continue with the
initiative and procure the power.
And the timing of this refers to initiatives that are
commenced prior to the approval of the first IPSP. So you
go to the timing of the initiative being commenced, and I
can -- I am just...
So if you look at -- the section, in particular, is
25.32(4). It addresses the transition. It says:
"The minister may direct the OPA to assume, as of
such date as the minister considers appropriate,
responsibility for exercising all powers and
performing all duties of the Crown, including
powers and duties to be exercised and performed
through an agency of the Crown (a) under an RFP,
or (b) under any contract..."
Sorry. Sorry, I'm looking at (1):
"...that was issued or pursued after January 1,
2004."
So this is describing the government initiatives:
"...and before the Board's first approval of the
OPA's procurement process under 25.31(4)."
So once the Board approves a procurement process, the
minister is no longer in a position to start initiatives
that are -- that then end up in OPA -- directions to the
OPA.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
691
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
But initiatives that take place prior to the approval
of the procurement process can still be subject to a
directive of the Crown.
MR. POCH: Thank you, Madam Chair. I don't think we
have to have any argument about that. It was helpful that
we got that on the record at this point, because it does
inform where we are going.
MS. NOWINA: Mr. Quesnelle has a question.
MR. QUESNELLE: I was wondering, Mr. Vegh, if you can
give your interpretation of what the start of an initiative
would be and what would be the delineation of that versus an
actual directive.
MR. VEGH: I think when you look at the directives,
they usually refer to the initiatives. So the directive
will say -- I don't have one in front of me, but the
directive will say: The government has commenced its
initiative to carry out X activity, and then will direct
the OPA to take over that initiative from a date going
forward.
MR. QUESNELLE: It's very clear, and it is public, as
to what that date is? As far as you could see, it's not
something that is a work in progress, so to speak, leading
up to a directive. It is actually the announcement that the
government will direct?
MR. VEGH: Well, it becomes -- the directive itself is
what identifies the government initiatives. So governments
don't typically announce initiatives that they are carrying
on. For the purposes of the OPA, they don't report to the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
701
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
OPA or, you know, to the OEB on initiatives that are
ongoing.
You find out that the government initiative is being
transferred to the OPA at the time of the directive. So the
directive identifies the initiative.
MR. QUESNELLE: Okay. Just the wording of it, though,
you mentioned the commencement of an initiative would -- as
long as it predates the approval of the procurement process.
So the -- as you are putting it, the -- as long as
there is a directive that predates the approval, the
government is obviously still within its authority to do so?
MR. VEGH: No. Sorry. As long as the initiative
predates the approval. So if the initiative is being
carried out any time before this Board first approves a
procurement process, then that initiative can be -- find its
way into a directive to the OPA from the government.
MR. QUESNELLE: I guess that is what I am looking for.
How is it clearly defined as to -- how is the public aware
that that initiative is occurring?
MR. VEGH: Well, I am not sure I could answer that in
the sense of providing a list of all current government
initiatives.
So the directive is very transparent, so the directive
is clear and on the record, but the initiatives that are now
being carried out, I am not sure that there is a public list
of initiatives. We know some are fairly high profile, but I
can't say that there aren't others that are not -- have less
profile.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
711
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. QUESNELLE: Do you see that that raises any issues
with the Board's ability to understand what the environment
is that it is making its approval in the procurement?
MR. VEGH: I suppose, from the Board's perspective,
what the Board knows is that the OPA cannot, without a
government initiative, procure any resources that aren't
identified in the plan as resources that it wants to
procure.
There is political or a governance environment that we
all live in where the government does maintain that ability
to carry out its own initiatives. That basic ability to
carry out its initiatives is part of the common law of a
constitutional government. The executive can do that.
What this power does, what this legislative power does,
is allows the government to transfer that -- to transfer the
initiative to the OPA. So the legislation doesn't require
any greater publicity around government initiatives that
then occurred prior to the legislation.
So the legislation, I don't think it really tries to
constrain the government so much. It more tries to
constrain the OPA, to ensure that the OPA procurements are
being carried out in accordance with some governing
structure. The governing structure is either the government
itself, or the IPSP and the procurement process as approved
by the Board.
MR. QUESNELLE: Thank you.
MS. NOWINA: Mr. Poch.
MR. POCH: Thank you.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
721
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
So, Mr. Shalaby, I think we can agree, then, that apart
from any initiatives that the government has already
instituted and that it belatedly directs you to do, once
this Board issues its decision, assuming the plan is
approved in some form, your expectation is that you are
going to obtain your authority from the existing directives
and the many – that’s several dozen or two existing
directives, specific directives, and from the Board's
specific approvals and procurement process approval that you
are seeking?
MR. SHALABY: That's correct.
MR. POCH: Okay.
I am cognizant -- Madam Chair, you wanted to break at
12:15?
MS. NOWINA: 12:15.
MR. POCH: Fine. Let's look at that Exhibit K2.2,
which is the list of directives. I would just ask you to
confirm for me my understanding. I think you already
indicated that for combined heat and power, the directives
today are 1,000 megawatts plus another 100 megawatts. 1,100
megawatts; is that right? You don't have to find them. I
think the 100 is at April 10th, 2008.
MR. SHALABY: Yes, I can see the 100 on April 10th,
yes. The minute you say, You don't have to find them, that
is a sign for me to try to find them. I took that in
witness school, too.
MR. POCH: I was...
MR. SHALABY: April 10th is the CHP 3, we call it.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
731
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: April 10th of...
MR. SHALABY: And the other CHP is ahead of that. I
don't know the date of that.
MR. POCH: What I am going to suggest is that at some
point, I would just like it to be appropriate to get
clarified where these authorities are. I don't need it
right this moment on CHP.
If you could just help me find that, where the 1,000
is, that would be appropriate. If you want to take that
away and we will cover it later and come back to it later,
that would be great.
MS. LEA: Can I recommend, even if it remains within
this panel, that we list it as an undertaking?
MR. POCH: Sure, let get an undertaking to identify --
MR. SHALABY: June 15th, 2005. It's the third
initiative list of minister's directives to OPA.
MR. POCH: That's 1,000 megawatts.
MR. SHALABY: That has high efficiency heat and power
at the end of it.
MR. POCH: Thank you. I wanted to then look at the
conservation directives, and I can help you here. I have
done a little bit of this myself.
I have identified 1,000 megawatts of specific
directives with respect to conservation. And they are the
October 6th, 2005 for 100 megawatts. I am just going to put
these on the record and then ask you to accept it subject to
check. How is that? Take an undertaking?
MR. SHALABY: As a later time we will do that?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
741
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: You don't need to check right now. When I
am finished with this, I will ask for an undertaking that
you just confirm that we have covered them.
MR. SHALABY: Right.
MR. POCH: My information is October 6th, 2005, 100
megawatts -–
MR. SHALABY: The record has an interrogatory response,
all of the directives and conservation.
MR. POCH: Ah, can you point us to that?
MR. SHALABY: Maybe we can find that. The only thing
missing is what number it is and who asked it.
MS. NOWINA: Mr. Poch, it might be most helpful to go
ahead with your -- you go through it, subject to check, I am
sure that today sometime the OPA can check it and confirm
it.
MR. POCH: Thank you, Madam Chair. Let's proceed on
the assumption that I have done the math right. There is
1,000 megawatts that I found of conservation directives in
addition to the $400 million budget permission directive for
you to engage local distribution companies to deliver
conservation.
MR. SHALABY: I just want to take a minute to
understand whether those directives include customer-based
generation, for example, that is also considered
conservation.
So the RESOP directive or program is -- captures
resources that aren't classified as conservation. So what
you are mentioning may not be all the capturing capability
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
751
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
for conservation.
MR. POCH: Okay.
MR. SHALABY: Conservation is also enabled by many
other programs other than OPA programs but -- I don't know
where you are heading with all of this, but --
MR. POCH: I am just going to ask for an undertaking
rather than spending a lot of time dancing around. I think
it might be a little easier.
Perhaps we could get you -- get an undertaking that OPA
will provide a list of the directives that are existing that
authorize it to procure conservation. Is that acceptable?
MR. SHALABY: Yes.
MS. LEA: List of existing directives that authorize
conservation procurement, Undertaking J2.1.
UNDERTAKING NO. J2.1: TO PROVIDE A LIST OF EXISTING
DIRECTIVES THAT AUTHORIZE CONSERVATION PROCUREMENT
MR. POCH: Mr. Shalaby, perhaps you could remind us.
What's the expected or the hoped-for conservation goal by
2010?
MR. SHALABY: 1,350 megawatts --
MR. POCH: Right.
MR. SHALABY: -- in addition to the 2007 target.
MR. POCH: Right. Some of these directives would have
been with respect to conservation that was for the 2007
target?
MR. SHALABY: Well...
MR. POCH: The 2007 target was also 1,350?
MR. SHALABY: It was. So the cumulative target for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
761
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
2010 is 2,700 megawatts?
MR. SHALABY: If you add 1,350 and 1,350, that becomes
2,700, yes.
MR. POCH: All right. Thank you.
MR. SHALABY: The first 1,350 was dealt with in a way
different than the next 1,350. The first 1,350 was largely
underway before the inception of the OPA and before the
programs of the OPA. Again, I don't know what your purpose
of asking this, so --
MR. POCH: I will try to help you with that.
Throughout the evidence, you have repeatedly said, Our
plan includes the amounts that are in the -- the minimums
for conservation that are in the -- the minimums for
conservation that are in the directives, these benchmarks
for particular years, 2012 and 2025, I believe.
But you have insisted that if you can get more, you
will get more.
MR. SHALABY: Yes.
MR. POCH: Am I right? Sorry?
MR. SHALABY: Yes.
MR. POCH: And I just want to make clear that there is
a caveat on that, is there not, that you can only procure
more if you have either obtained ministerial directives, as
in the manner we have spoken of, or if it is included in
this plan and you asked this Board for authority to procure
more.
MR. SHALABY: Or we come in the next plan and ask for
additional authority. Yes. That's the update feature that
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
771
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
we talked about and is an integral part of how much
approvals we ask for.
MR. POCH: And realistically, you're not going to get
through another cycle of this and get the Board's next
approval for at least a couple years?
MR. SHALABY: You couldn't determine how long your
cross-examination will be today. I mean, you want me to
speculate, go that far out? Let's be fair.
MR. POCH: That was an excellent answer, even if it
wasn't the one they taught you at witness school. But we're
talking a good couple of years down the road, obviously.
MR. SHALABY: Yes.
MR. POCH: So --
MR. SHALABY: It doesn't prevent us from come for
interim approvals. I mean there are all kinds of ways of
-- if things are necessary between plans but let's assume
they come in in a couple of years, yes.
MR. POCH: I am just suggesting to you, though, that
you really don't have a lot of head room, do you, on
conservation? You've got, if I am right, 1,000 megawatts,
plus the 400 million and you've got to get 2,700 megawatts.
You've got 2,700 megawatts.
You don't have a lot of head room, in terms of the
approvals you have, to exceed that.
MR. SHALABY: That's not true, because the attainment
of conservation, first of all the RESOP contributes
conservation. That's another source of megawatts that can
be conservation.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
781
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Many of the contributions of conservation are going to
come through standards and codes. Those do not require
authority to spend OPA money. These are government
standards and approvals.
Many programs are carried out by a large number of
partners in the business, the local distributing utilities
that are here. They are strong advocates of conservation
and they do achieve under their own spending -- which is the
400 million that you talked about, and their own resources.
The federal government has programs. There are many
avenues of getting conservation other than the OPA authority
to spend dollars under those directives.
MR. POCH: All right.
MR. SHALABY: So that's -- particularly standards and
codes, particularly the federal government initiatives, and
particularly the RESOP.
MR. POCH: So you have given me that list of where you
think all of this conservation can come from. Have you made
estimates of all of that conservation and included it in
your load forecast?
MR. SHALABY: I would defer that to the load
forecasting and conservation panel how exactly they
considered all of that.
MR. POCH: All right, fair enough.
With respect to combined heat and power, I think you
have indicated that we're a little more certain about, about
1,100 megawatts of -- authority?
MR. SHALABY: Yes.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
791
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: And I take it there is less opportunity for
a lot of it to show up through other means than there is
with conservation?
MR. SHALABY: Many of these projects get developed by
customers on their own, at least historically. A large
number of combined heat and power projects are developed for
other purposes other than selling electricity through the
grid, but I would accept your premise that the new projects
are going to be developed under -- correct.
MR. POCH: Let me turn to Exhibit A-2-2, page 7.
MR. SHALABY: Are you going to put the exhibit up?
MR. POCH: Now, first of all, this is the section of
the evidence where there is a discourse on the OPA's view of
what this Board should and should not give direction on,
where it should show deference.
Is this the right panel to ask questions to about that?
MR. SHALABY: If it doesn't become a legal question, we
will attempt to answer.
MR. POCH: I just saw you put in evidence, so I wanted
to ask questions about the evidence.
MR. SHALABY: If the evidence is of a legal nature, I
will have limitations in answering.
MR. POCH: Who wrote this exhibit?
MR. VEGH: Sorry, just to be clear, Madam Chair, this
is in section A of the application, which is the
administrative section. The evidence section of the
application starts in section B and onwards. Just a
clarification, I think Mr. Poch was calling this evidence
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
801
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
and this is more of an overview document.
MS. NOWINA: So it is not evidence?
MR. VEGH: It is not evidence.
MR. POCH: Thank you. So then what is this? This is
-- perhaps Mr. Vegh can clarify.
Is this an opening statement? Is this a submission of
counsel? I would like to know what it is so we could
respond accordingly.
MR. VEGH: This is a document that was meant to provide
context and a description of the mandate of the OPA and the
OPA's view of the nature of the review of the IPSP.
It was thought that this would be a helpful outline for
parties, given this is the first IPSP, and these are some
the more fundamental issues that do arise, but there is
obviously a lot of legal issues in here that I expect will
be addressed in legal argument.
MR. POCH: Can I take this, then, as a submission of
counsel?
MR. VEGH: Well, it's a bit of a hybrid. I would take
it as an administrative document that sets out the scope of
the OPA's mandate and the OPA's view of the scope of the
OEB's mandate.
I am not sure what -- I think a lot of these issues
will be addressed in legal submissions, but I am not sure
what Mr. Poch is asking me to concede to by saying we will
treat this as submissions of counsel.
MR. POCH: I think that is fine, Madam Chair. I think
my friend has already indicated it is not evidence, and so
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
811
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
presumably no weight is attaching to it at this point. I
can just simply move on, then.
Now, could you turn to I-22-176? Here we asked you two
questions about a number of items, one, whether you view
them as to be within your planning discretion, and then,
secondly, we did ask you, twigged by the earlier discussion
we just had here, about whether or not you thought it
appropriate for this to be an area where the OEB ought to
give direction.
So I won't ask you, Mr. Shalaby, to give any legal
opinion on that, but just more your understanding of what's
being sought of the Board here in a less formal way, which
may be helpful in response to that.
Now, there is a list there of various points. I didn't
really get an answer, other than to say, Go to the issues
list.
So perhaps we can just take them quickly one at a time.
Definition of base load, is that something you view as
within your discretion, your planning discretion?
MR. SHALABY: You are going through the list that is in
the question?
MR. POCH: Yes.
MR. SHALABY: Yes.
MR. POCH: All right. And are you seeking any
assistance from the Board in that regard, any direction?
MR. SHALABY: When we're -- we described the totality
of our work as a methodology, a planning methodology, that
is here for consideration by the Board.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
821
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: All right. That is part of it?
MR. SHALABY: That is part of it.
MR. POCH: All right. So that's before the Board for
their deliberations; correct?
MR. SHALABY: It is.
MR. POCH: All right. I take it using less than 14,000
megawatts is within -- to some extent, within your
discretion?
MR. SHALABY: Yes.
MR. POCH: All right. We are going to come back to
that. Obviously, it is affected by recent events.
Now, the choice of whether or not to use local avoided
costs for areas where conservation would have a higher
value, and therefore increase its savings potential, is that
something in your planning discretion?
MR. SHALABY: It is in program implementation, and the
conservation panel can address that.
MR. POCH: All right. Is it something that you viewed
when you were developing this plan, the choice of whether to
develop a plan that looked at the potential in particular
pockets of the province where there is particular concern?
Is that -- that was within your discretion, whether to
address that or not?
MR. SHALABY: It is. It is. And we did address it by
assigning avoided costs of transmission and distribution and
losses, yes.
MR. POCH: All right. Did you allocate those avoided
costs to local areas to give a different avoided cost for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
831
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
specific --
MR. SHALABY: Not to that level of detail at the
generic tables, no.
MR. POCH: Okay, thank you.
The choice of which resources are treated as avoidable
within avoided costs calculation, I take it that is
something that is within your planning discretion?
MR. SHALABY: We're explicit about what it is that we
include as avoided, yes.
MR. POCH: It's a choice you make?
MR. SHALABY: We made the assumptions.
MR. POCH: It's a choice you are making?
MR. SHALABY: It's a set of assumptions, because it is,
What would we have done had conservation not been here?
So it is not a planning decision. It is an assumption
of what else would displace conservation.
MR. POCH: We will come back to the details of that
with your --
MR. SHALABY: It is, again, methodology.
MR. POCH: Okay. If I want to come back to the details
of that, that would be the conservation panel?
MR. SHALABY: Yes. That evidence is an attachment to
D-3-1.
MR. POCH: Okay.
MR. SHALABY: D-4-1.
MR. POCH: The choice to utilize larger co-gen, CHP, as
an option for intermediate and base load, that was something
-- that's something in your planning discretion?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
841
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: To utilize larger co-gen as a resource
option for intermediate or base load? Yes.
MR. POCH: All right. That is something you would
appreciate direction from the Board on, is it?
MR. SHALABY: Whether the, again, the methodology for
assessment of that potential and the assessment of its
feasibility --
MR. POCH: Okay.
MR. SHALABY: -- and it's economics, all of that is
explicit and we present the data.
MR. POCH: We will come back to that methodology later.
The consideration of whether to obtain imports from
neighbouring jurisdictions, and whether or not to seek, to
go after interconnection upgrades. That's something that
you felt was within your planning discretion?
MR. SHALABY: Consideration of imports is your
question, and that is part of what the OPA does and part of
their planning considerations, yes. Consider imports.
MR. POCH: All right, okay.
I take it obviously alternatives for base load, firming
of renewables or for peaking is something that is within
your discretion.
MR. SHALABY: Yes.
MR. POCH: I guess there is no debate, you have
discretion to go beyond the minimums in the directives for
CDM and renewables?
MR. SHALABY: Yes.
MR. POCH: It was within your discretion to choose a
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
851
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
plan that costs a bit more but would have fewer
environmental impacts or be otherwise more sustainability?
MR. SHALABY: Subject to you defining what fewer
environmental impacts and more sustainability is.
MR. POCH: Well, it was within your discretion to
define that and pursue that if you so chose.
MR. SHALABY: No. We didn't know what -- how -- I mean
we agreed with stakeholders that trading environmental
impacts is subjective matters.
MR. POCH: We will come back to that.
MR. SHALABY: All of the options have environmental
impacts.
MR. POCH: We will come back to that point. You chose
to agree with whatever stakeholder gave you that opinion.
That was your planning discretion.
MR. SHALABY: That was our planning discretion.
MR. POCH: You had discretion to do it another way.
You may have felt your hands were tied because you didn't
have the knowledge or tools, but you had that discretion.
MR. SHALABY: Right, right.
MR. POCH: All right.
Obviously, you’ve already said your methodology
therefore, I take it, the assumptions, how you decided to
cost various options, obviously that is within your
discretion, I take it there is no contest there?
MR. SHALABY: Yes.
MR. POCH: The choice to count particular externalities
in plan development and selection, whether or not you
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
861
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
monetized them, I take it that was within your discretion?
MR. SHALABY: If that means identification of
environmental factors to track?
MR. POCH: It could be environmental or other
externalities.
MR. SHALABY: What would an example of that be?
MR. POCH: Job creation, transference of risk, impacts
on society more broadly.
MR. SHALABY: We tracked a number of environmental
factors and chose not to do other factors that you are
talking about, yes.
MR. POCH: Right. So it was your -- it was in your
discretion, as to whether or not to both track but also to
include in your planning process externalities of the
various kinds that are potentially out there.
MR. SHALABY: Well, subject to our mandate as well. I
mean, the mandate of the OPA is not -- is not into some of
the factors that you are talking about.
MR. POCH: Well, I guess that is really what I'm asking
for. What did you feel is, you could have if you – again,
you might not have felt you had the tools at hand or you may
have not felt it was wise. But you had the discretion.
Was there some counting of externalities, is there some
constraint on you in that regard that I am unaware of? Can
you help us?
MR. SHALABY: Not knowing exactly what externalities
you're talking about, I mean, is it balance of trade for
Canadian products, is it --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
871
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: I think I gave you a couple --
MR. SHALABY: -- regional job development?
MR. POCH: I gave you two examples. Consideration of
job impacts in the province, consideration of transfer of
risks, creation of risks for -- an accounting of those risks
for either the financial community or the physical
community.
MR. SHALABY: We did not explicitly consider jobs, and
the creation of jobs.
The question on risks, I don't understand fully.
MR. POCH: But those were your choices not to consider
that.
MR. SHALABY: Yes.
MR. POCH: There was not a constraint that said you
can't look at those things and count them if you so choose.
MR. SHALABY: Well, a combination of our mandate and
the value added we can bring to bear, yes.
MR. POCH: All right. Thank you.
All right, let's move ahead and talk about the effect
of the update.
Prior to the August 29th update filing, you had
answered, in answer to -- I will ask you to turn this up I-
22-87, at page 3, lines 31 to 37 is I think where you cover
this.
MR. SHALABY: Can we see what the question is to start?
MR. POCH: Sure.
MR. SHALABY: This is --
MR. POCH: This is a long question where we asked you
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
881
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
about various aspects of nuclear costs and cost trends.
MR. SHALABY: Yes, we got it.
MR. POCH: Right. In that answer, you noted the
government's statement about pursuing an RFP for some -- the
potential new nuclear capacity at Darlington, and statement
with respect to what they foresaw for Bruce, the Bruce site.
And you cited the Board's earlier comments about the
expectation that nuclear power is obviously going to be a
matter of some provincial policy.
And I notice you were relying on that statement and
that statement said, What this proceeding can thoroughly
examine are the base-load requirements that drive the need
for nuclear development and the flexibility of the plan to
react to situations that alter the assumptions regarding the
need for and execution of nuclear projects.
I want to suggest that, now contrast what you cited
there by way of explanation as to what you thought the --
was on the table here was, with what you are now saying and
then ask your comments.
If you would turn to, if we turn to B-1-1, at page 4,
you now -- this is the last paragraph, page 4, line 11. It
is the updated, the August 29th update.
That paragraph recites the Board's comments about the
-- it wasn't going to review matters that were already the
subject of OPA procurement prescribed by ministerial
directive. And then said, as a result, the existing and
committed resources aren't subject to review. And you have
gone on.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
891
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
I think I can paraphrase the position you have taken
here in the hearing is to say -- you're now saying that the
recent announcements by government amount to -- you are
trying to shelter under that wording, you are trying to say
those amount to the same as the subject, being subject to
government procurement or OPA procurement, correct, and
therefore you are treating them as committed?
MR. SHALABY: So the question is?
MR. POCH: Have I understood you correctly? The
nuclear capacity in that announcement, you're saying it is
committed. It is off the table in this case for review.
MR. SHALABY: I described the purpose of putting the
categories of -- under government directive or pursued
directly by government or pursued directly by OPA. All of
that is to focus the scope of the decisions that are left to
the planning discretion of this hearing. So it is off the
table, in the sense of it is not a set of decisions that we
are addressing in the plan at this time.
MR. POCH: All right. I will come back to that in a
minute.
MR. SHALABY: In the slides I presented yesterday, it
is focussed on what remains as discretionary, rather than
what's below the line. What's below the line is being
pursued elsewhere, and we don't think it is productive to
pursue something being pursued elsewhere.
MR. POCH: You're not taking the position that it is
-- the Board's not allowed to review that. It is just you
think it is not productive, not a good use of our time and
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
901
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the Board's time?
MR. SHALABY: For the planning decisions that we have
discretion to pursue, it is the light green part of the bar
chart, not the dark green or the blue, yes.
MR. POCH: Right. With respect to -- I think called it
dark green. That is what you call committed; right?
MR. SHALABY: That's right.
MR. POCH: With respect to the committed resources that
are the subject of that government letter or announcement or
press release, or whatever it was, but that aren't, you
know, contracted for --
MR. SHALABY: Correct.
MR. POCH: -- you're saying it is not that the Board
can't review that, but it shouldn't?
MR. SHALABY: I mean, the Board will decide what it is
it wishes to review.
MR. POCH: Okay. Now, just in terms of the update, the
committed CDM and renewable capacity in your plan has
augmented by planned amounts and the combination of the two
adds up to the directive minimums in both cases; correct?
MR. SHALABY: It this -- for what year?
MR. POCH: For the end of plan, 2027 or whenever the
directive -- 2025, when whenever the directive --
MR. SHALABY: It is the directive. The directive
doesn't have minimum or maximum. It has an amount and we
meet that amount.
MR. POCH: Right. And it's the sum of committed -- in
those cases, conservation, CDM and renewable capacity, the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
911
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
sum of capacity and planned adds up to that minimum or adds
up to --
MR. SHALABY: Committed and planned.
MR. POCH: Committed and planned adds up to the
directive minimum?
MR. SHALABY: The target.
MR. POCH: The target, which is the minimums in the
directive?
MR. SHALABY: It's a target. It doesn't say minimum.
It says, You will achieve a target of...
MR. POCH: You are agreeing you can exceed those
targets?
MR. SHALABY: Yes. You are calling them a minimum.
I'm calling them a target.
MR. POCH: Let me ask you, then. Do you take the view
that your job is not very clear from the directive that you
are obliged to go and do your best to achieve that?
MR. SHALABY: To achieve the target, yes.
MR. POCH: Yes.
MR. SHALABY: Yes.
MR. POCH: That was your marching orders?
MR. SHALABY: That's the target.
MR. POCH: Okay. So the megawatts in the CDM and
renewables totals haven't changed with the issuance of
ministerial procurement directives? I'm not speaking --
they still only, in all -- they continue -- as the green,
the light green and dark green, might shift around, the
height of that histogram is always at the target?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
921
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: For renewables and CDM?
MR. POCH: Renewables and CDM.
MR. SHALABY: The update did not affect the achievement
of targets into 2025, yes.
MR. POCH: Right. Over time, what is in planned and
what is committed has changed, as a new directive issue, for
example, correct, but the total doesn't change?
MR. SHALABY: What is committed eats up from what is
planned; that's correct.
MR. POCH: Right. The mandatory amount, if I can use
that word -- I am equating the target in the supply plan --
supply directive as a mandatory amount. Obviously, if you
can't do it, you won't do it, but that's not changed?
MR. SHALABY: The directive did not change and the
amounts in the directive did not change.
MR. POCH: Right. What I am leading towards here is
what is avoidable, and we will get to that, but in terms of
your planning discretion, whether it's in committed or
planned, it doesn't really matter. It's your -- in terms of
your planning discretion, your plan is -- you know, shall be
designed to achieve that target or exceed it?
MR. SHALABY: Right, correct.
MR. POCH: Okay.
But in the case of this recent change with nuclear,
you're interpreting the effect of the potential capacity in
the government's RFP process as moving capacity from the
non-mandatory planned category to the mandatory committed
category, correct, in terms of your planning?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
931
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: I am not sure what mandatory and non-
mandatory is. I mean, these are terms we haven't defined.
MR. POCH: When it was in planned, it is avoidable.
When it is in committed, you are treating it as not
avoidable.
MR. PIETREWICZ: If I could just chime in here, the
total amount of nuclear to meet base-load requirements in
the directive has not changed. It was up to 14,000
megawatts in the directive, and it continues to be up to
14,000 megawatts.
The update that the OPA filed to B-1-1 sees no change
in absolute or total installed nuclear capacity relative to
the prefiled evidence of August 2007.
What has changed or what is reflected in the update is,
as you point out, an increased amount of committed nuclear,
and, therefore, a smaller requirement for planned nuclear
power.
MR. POCH: All right. In terms of how you interpret
your planning mission, am I correct you are interpreting
that as meaning, before the up to 14,000 was just what it
said, up to -- it was permissive up to that amount. You
could come in with a plan of less than 14,000; correct?
MR. PIETREWICZ: Yes.
MR. POCH: If you got a bunch of CDM, if you were more
confident about CDM, you would have included more CDM and
maybe less nuclear; correct?
MR. SHALABY: History demonstrates that.
MR. POCH: Right. Now, before, you could back off
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
941
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
nuclear to the point where you ran into the Bruce A contract
commitment. That really was committed?
MR. PIETREWICZ: Yes. In the original filing, the
committed nuclear was represented by the roughly 3,000
megawatts at the Bruce A facility.
MR. POCH: And now you take the view - correct me if
I'm wrong - that you can't back out nuclear below, what is
it, 10,000?
MR. SHALABY: Well, backing out nuclear, what does that
mean? I mean, we're not requesting a --
MR. POCH: I am asking about planning discretion,
whether you choose to go that route or not. You are
interpreting the government's announcement as saying, You
will include, as committed and not as avoidable the -- what
is it, the ten thousand and three hundred and -- sorry,
the --
MR. PIETREWICZ: In the case of --
MR. POCH: -- 10,249?
MR. PIETREWICZ: It is actually up to 9,800 megawatts,
or so.
MR. POCH: Excuse me, 9,800 megawatts.
MR. SHALABY: So the question is?
[Witness panel confers]
MR. POCH: Let me put it this way. You are treating
that announcement as if the directive now reads, No more
than 14,000 and no less than 9,800?
MR. SHALABY: No. You are giving --
MR. POCH: If I am overstating it, please tell me.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
951
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: You are overstating it. The directive
doesn't say that.
MR. POCH: Okay. Tell me, first of all, where I am
wrong on the directive.
MR. SHALABY: Well, the directive doesn't say no more
than and no less than. It just says no more than. The
directive has not changed.
MR. POCH: I wasn't suggesting the directive had
changed. I was using --
MR. SHALABY: I don't know where you are going with all
of this, so I'm just being careful. That's all.
MR. POCH: I am asking how you are treating this new
information. You are treating it as having the same effect
as if the directive had changed in terms of your planning,
in terms of what you feel you have discretion to do or
avoid?
MR. SHALABY: At this time, yes.
MR. POCH: At this time?
MR. SHALABY: Yes. We're focussing on the resources
that are yet to be planned, and we're providing ways of
enabling and ways of options to meet the remaining
requirements above what others are working on, yes.
MR. POCH: But my statement to you that you are
treating a government announcement as, in effect, creating a
minimum, that's now 9,800 for nuclear. I am accurate there?
MR. SHALABY: We are treating the announcement as
committed, yes. Not all of the committed things that we're
saying are -- in the category of committed are going to
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
961
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
materialize exactly as planned or as foreseen.
MR. POCH: Events can intervene, obviously, but in
terms of what you --
MR. SHALABY: Success rate will intervene. There are
many things that will intervene. We are just saying we
don't need to make -- to develop options to meet that.
There are options now to meet that portion of the graph,
let's develop options to meet the other remaining options of
the graph. It is more productive to work on the void space
than the space that is already occupied.
MR. POCH: You are taking that -- as you say, that
space is occupied. You are taking that as a reduction in
your discretion. It may not affect anything in your plan,
but it is a reduction in -- your viewing it as in effect a
reduction on your discretion?
MR. SHALABY: We indicated that we want to develop
options for Ontario to meet its needs going forward.
Somebody else is developing options to meet that portion of
the requirements. We're developing options to meet the
remaining portion of the requirements.
So again, not knowing what turns on all of this, I
don't know what to accept and what not to accept in what you
say.
MR. POCH: Don't worry about where I am going, Mr.
Shalaby, just listen to my question and answer that.
MR. SHALABY: Right, right.
MR. POCH: All right. Simply put -- I am not going to
beat that one to death. I think we understand your
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
971
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
position. Can we agree, beyond Bruce A, there are no
contracts to procure nuclear?
MR. SHALABY: There are no contracts to procure those
two nuclear commitments that are indicated, yes.
MR. POCH: There is no directive to you to procure?
MR. SHALABY: No directive, no.
MR. POCH: All right. And the government is not
obligated to procure, as far as you know?
MR. SHALABY: Not obligated.
MR. POCH: All right. And the government doesn't even
have a price quote yet, does it?
MR. SHALABY: They're discovering that through the
process.
MR. POCH: Exactly.
MR. SHALABY: That's one of the main advantages of this
process.
MR. POCH: Presumably one of the primary purposes of
the process; correct?
MR. SHALABY: Yes.
MR. POCH: Yes. And so do you think that the
government's announcement -- are you taking that to read the
government's going to procure this nuclear regardless of the
price?
MR. SHALABY: I can't speculate on that.
MR. POCH: Okay. Let's turn to the...
I am going to just turn to the figure 16 in I guess
this is B-1-1 updated, page 6. I'm sorry, it is not
page 6. It is page 34. Here you have provided the update,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
981
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
rather the correction adds the numbers in table 6, below
figure 16. Correct?
Can you just label that for us. What year is the --
are these numbers representing?
MR. PIETREWICZ: They are meant to represent the year
2027.
MR. POCH: Okay. Am I correct that this, these are the
-- these stacks of resources are -- would be associated with
case 1A?
MR. PIETREWICZ: Yes, I believe that is true.
MR. POCH: And that's where the assumption is that
Pickering B gets refurbished?
MR. PIETREWICZ: Yes. That is case 1A, is based on the
assumption that Pickering B is refurbished. Not on our
assumption.
MR. POCH: Where I am going to go next is to take you
through the...
MR. SHALABY: Just a minute.
[Witness panel confers]
MS. NOWINA: Mr. Poch, it's our lunch break time. How
much longer do you think you will take with this?
MR. POCH: This is a convenient point to break, sure.
MS. NOWINA: Good time to break? We'll get an answer
to the question, this question, and then we will break?
MR. POCH: I was just going to say, by way of
introduction, where I am going and maybe I will take say it
so the witnesses can contemplate it over the break if it’s
in the back of their heads. I am just going to take them
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
991
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
through that stack and ask, in each case, what is avoidable.
MS. NOWINA: All right. Why don't we do that after our
lunch break. We will break now for lunch and we will resume
at 1:45.
--- Luncheon recess taken at 12:14 p.m.
--- Upon resuming at 1:47 p.m.
MS. NOWINA: Please be seated.
Did any matters come up during the break? Mr. Poch,
are you ready to continue?
MR. POCH: I am. Thank you, Madam Chair.
Panel, just before the break we were just looking at B-
1-1, page 34, where you have the before and after stacks of
committed and planned resources, and you have it broken down
in a table with numbers on it. I was going to take you now,
just to ask you in each category what is avoidable.
I think we have already really dealt with the
conservation and renewable, in the sense that your plan is
at the minimum or targets in the directive. So it's not
intended that it be avoidable, let's put it that way; is
that fair?
MR. SHALABY: Okay, yes.
MR. POCH: Okay. So let's turn to gas. Can you just
explain, under...
Right. I have summed for gas existing, committed and
planned, and the numbers -- you can take them subject to
check, but the numbers move from 10,208 to 10,071. I am
wondering if you can just explain that drop that I -- at
least my math gives me.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1001
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. PIETREWICZ: I can venture to explain that drop.
I will be using roughly rounded numbers, but the drop
is a result of a couple of things.
The first is that in the initial filing there were 63
megawatts that had been procured under the CHP 1 procurement
that were erroneously identified as gas, whereas in
actuality they are biomass. This is a 63 megawatt Algoma
combined heat and power project. So that is one explanation
for the difference.
MS. NOWINA: Can I stop you for a moment, sir, and ask
if people can hear you? Can people hear Mr. Pietrewicz at
the back of the room? Yes? Good. Thank you.
MR. PIETREWICZ: Thank you.
That is one difference.
Another difference that I recall relates to the CHP 2
procurement, which, as we have identified earlier, is for up
to 500 megawatts of combined heat and power, and that is
reflected in the update as gas.
It could very well be that not all of it turns out to
be gas, but for purposes of this update for planning
assumptions, we've assumed that it could be all gas, 500
megawatts.
In the initial filing, the quantity was 586 megawatts,
the rationale being that the directive had been to procure
up to 1,000 megawatts of CHP. We had, in the CHP 1,
procured 414 megawatts. So that simply left 586 megawatts
remaining.
However, as reflected in the IPSP update, in this
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1011
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Exhibit B-1-1, we have now -- the OPA has a procurement
process under way to procure up to 500 megawatts. So it's
that 500 megawatts that is reflected in the update, rather
than the 586 which was just our sort of arithmetic estimate
of the balance.
So I believe those two factors should be the bulk of
the explanation.
MR. POCH: So let me just understand. CHP 2 on its
face is -- your directive is 500 megawatts?
MR. PIETREWICZ: Yes.
MR. POCH: The 414 was being pursued pursuant to what?
MR. PIETREWICZ: It is the CHP directive that Mr.
Shalaby pointed out.
MR. SHALABY: It's the actual awards of CHP 1. It's
the actual megawatts awarded to CHP 1.
MR. PIETREWICZ: Yes, thank you.
MR. POCH: Now we have 414 already in CHP 1, and you
are targeting 500 in CHP 2?
MR. PIETREWICZ: That's correct.
MR. POCH: So that is less than your -- the 1,100 we
spoke of earlier; correct?
MR. SHALABY: The procurements have a number to aim
for. They have discretion to go above the number. They
have a band around the number, and maybe the procurement
panel can get into that a little more.
MR. POCH: All right.
MR. SHALABY: The precision is only on -- 500 is a
round number, but they have discretion to go above it.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1021
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: Mm-hmm. But as a consequence, you have
actually lowered the amount of gas in your update and that,
in fact, has come out of -- apart from that misdescription
of the 63 biomass, it has come out of CHP; correct? Have I
got the gist of it?
MR. PIETREWICZ: In the accounting, yes. In addition,
there will be another 100 megawatts to be procured under the
CHP 3, some of which could be gas.
I believe in this update we've reflected it as -- I'm
sorry. It wouldn't be gas. It is a renewable CHP
procurement. So it would be 100 megawatts of renewable
procurement.
MR. POCH: A different pot, as it were.
Okay. So can I ask you, then, give me the bottom line
on gas? What portion of the resources listed in the right-
hand columns of table 6 on B-1-1 are avoidable, if I can use
that expression?
MR. SHALABY: What does "avoidable" mean? Avoidable by
what or under what conditions?
MR. POCH: Well, I am taking it -- I am assuming that
it's -- for the most part, resources that are committed, in
your view, are just that, committed. You are obliged by
directive or other -- as you said, other players?
MR. SHALABY: Being pursued by other avenues, yes.
MR. POCH: It's not within your discretion -- two years
from now, when you are back in front of the Board, you won't
necessarily have the opportunity to scale back that, because
it's marching to a different drummer?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1031
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: It depends how it develops elsewhere.
MR. POCH: Basically, it is outside of your control?
MR. SHALABY: Right.
MR. POCH: So that I am asking: What is still in your
-- presumably it is in your plan box -- that you feel is, if
-- you know, if, as you say, conservation goes well, this is
something you can back off?
That's what I am asking. Is it just the number in the
planned in the case of gas?
MR. SHALABY: It's generally what is called planned
resources, yes. Generally that.
MR. POCH: All right. In the case of gas, is it the
2525 that is listed there? Looking -- this is all about
what flexibility is in your plan.
MR. SHALABY: Yes.
MR. POCH: All right.
And now did any of the little changes that have
occurred on the gas front or -- affect or -- not necessarily
changes in the file number, but the timing in the interim
that have occurred, that are as of the moment, changed the
prospects for an earlier coal phase-out?
MR. SHALABY: Yes.
MR. POCH: Can you elaborate?
MR. SHALABY: The progress on the natural gas projects
that have started being procured four or five years ago, the
projects that -- the government RFPs in 2002, 2003, they're
starting to come on line. They're starting to develop in a
way that has higher degree of confidence that they would be
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1041
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
in service sooner than we might have expected two or three
years ago.
So the certainty by which we treat these resources is
higher now than it was two or three years ago.
MR. POCH: All right. So one of the rationales you
offer for coal is it's for insurance, as you call it,
insurance reserve?
MR. SHALABY: Yes.
MR. POCH: So I take it that that is somewhat less of a
driver at this point for keeping the coal plants on line?
MR. SHALABY: It's less of a -- the insurance
requirements are continuously being assessed and reassessed,
and they increase if other resources are not forthcoming.
They decrease if other resources are forthcoming.
MR. POCH: Can you put a number on this for us? At
this point in time, if you were asked to give us, before,
what was in the plan, assume that it was in the plan as coal
for insurance, and what it is now? Is that possible?
MR. SHALABY: It is possible, but before I do that, I
just want to indicate that as the time becomes closer -- so,
for example, considerations in 2009 are much more now in the
operating time horizon where the plant owner and operator,
Ontario Power Generation, has a lot of considerations of
what to do with that plan, how to do it, how to deploy it.
So it -- planning considerations become less of a
determinant of what happens to the plant and operating and
practical considerations become more pressing.
So it is up to the operators and the owners of the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1051
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
plant to determine how precisely to deploy the assets. But
the need for insurance is reduced roughly by 1,000 megawatts
in 2009, and roughly by about 1,500 megawatts in 2010, as we
sit today. All of that can go up, can go down, as this is
the dynamic nature of planning.
MR. POCH: That is certainly precise enough for our
purposes.
Turning to interconnections. Let me just explain. You
have 1,750 there, listed both in the before and in the
update.
My understanding was that - don't ask me to point in
the evidence where this is - but there had only been 500 in
and that further, that the 500 was really an artefact of the
market rules which either obliged or allowed current market
players to have 500 lined up as a contingency for themselves
to meet their commitments under the rules so I you assumed
it would be there for that reason.
Am I wrong? Has nothing changed or has something
changed in that regard?
MR. PIETREWICZ: Nothing has changed. The 500
megawatts you spoke of, you characterize correctly and that
500 megawatts, the sourcing acquisition of that 500
megawatts is described in the OPA's response to Board Staff
interrogatory 36.
The 1,750 or so that you referenced continues to
reflect the installed capacity of the 1,250 megawatts of the
Hydro Quebec interconnection, plus this 500 megawatts
totalling 1,750. But nothing has changed between now and
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1061
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the prefiled evidence, the August 2007 evidence.
MR. POCH: All right. So let me ask you this: You've
got installed capacity then, if you will, of 1750 in the
sense of transition giving you access to some potential
generation. Do I understand that you are treating it, for
planning purposes at only 500 as effective; is that right?
MR. PIETREWICZ: That's correct. For capacity planning
purposes, the IPSP counts on 500 megawatts of
interconnection support.
MR. POCH: And that's the 500 we spoke of that you know
is lined up by these market participants?
MR. PIETREWICZ: That's correct. The 500 that could be
lined up by these market participants, if it has to be.
MR. POCH: All right. So in essence, you have listed
it here, but in fact you are not presuming the 1,750 for
meeting your resource requirements? You are presuming 500
is helping you meet resource requirements in your plan?
MR. PIETREWICZ: Yes, that's correct.
MR. POCH: All right. And that 500 is not avoidable in
the sense that unless the market rules are changed so that
people no longer have that opportunity to protect themselves
with that? Is that fair?
MR. PIETREWICZ: Yes. I don't think it avoidable in
the sense that the OPA's not seeking to acquire this 500
megawatts. It simply -- it concludes that this 500
megawatts could be available to the system.
MR. POCH: Okay. Now, let's then turn to nuclear.
The D-6-1 at page 19 -- maybe we can get that up -- you
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1071
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
say -- line 11.
MR. PIETREWICZ: Sorry, which page again?
MR. POCH: D-6-1 at page 19, line 11. You say:
"Refurbishment decisions will not be made by the
OPA, but by nuclear plant owners or operators, the
first refurbishment decision expected in 2008
relates to Pickering B. If OPG decides not to
refurbish Pickering B, then the plan assumes that
the associated capacity of 2,064 megawatts will be
replaced as a later time by new nuclear
resources."
First of all, I understand that decision is now
expected in 2009, not 2008; correct?
MR. SHALABY: That's our understanding as well.
MR. POCH: All right. So your position, can I
summarize it, is that the decision that OPG will make,
rather, excuse me, to refurbish or not won't affect the
amount of nuclear capacity in your plan, just the timing?
MR. SHALABY: Roughly speaking, yes. I mean it adds up
to a few megawatts here and there across the way, but it's
made up -- what is lost in the refurbishment is made up by
new.
MR. POCH: In that scenario.
Is that something that is in your discretion? I think
you have certainly suggested -- my read of this it is not.
You're taking that as something that's will be a given --
MR. SHALABY: Whether it's refurbished or not is not in
our discretion.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1081
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: So it's not avoidable in the sense of OPA,
two years from now, looks like you can do better on CDM,
it's not something you can cancel?
MR. SHALABY: I'm still trying to -- the word
"avoidable" means things in the planning language that I am
trying to understand, in what sense you mean it. But the
decision to refurbish or not refurbish is in the hands of
the owners of the plant operators, yes.
MR. POCH: Okay. But as time goes on, certainly your
ability to influence that is going to decrease, is that
fair, if you have any.
MR. SHALABY: As time goes on decisions have to be
made, yes.
MR. POCH: Yes, of course.
MR. SHALABY: Yes.
MR. POCH: All right. So effectively that may be a
sunk decision, if you will, by the time we're --
MR. SHALABY: It will be?
MR. POCH: A decision that has been made by the time
you are looking at changing your forward plan --
MR. SHALABY: It may well be.
MR. POCH: -- for conservation? Yes.
MR. SHALABY: It may well be.
MR. POCH: Table 6 says there is 9,825 megawatts of
committed nuclear and 3,464 planned.
MR. PIETREWICZ: Which exhibit?
MR. POCH: Again, table 6 of page 34 of B-1-1. I am
slowly working my way through that table.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1091
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
I just read in the numbers that are there for committed
and planned nuclear.
I would like to just run through the nuclear resources
so we can see what's left in the planned nuclear and if it
is, indeed, avoidable or not. And I think we have just
dealt with the 2,064. I take it that 2,064 is in your -- is
that in planned or committed? The Pickering B
refurbishment.
MR. PIETREWICZ: Is the question is that roughly 2000
megawatts in the planned or committed section in this B-1-1
update?
MR. POCH: Yes.
MR. PIETREWICZ: It would be in the...
[Witness panel confers]
MR. PIETREWICZ: It would be in the planned section of
this table. The committed resources, nuclear resources in
this table, the updated table, would be the 3000 megawatts
of nuclear capacity at Bruce A that are currently committed
and currently contracted for.
MR. POCH: That's 3,040, to be precise?
MR. PIETREWICZ: Sure, sure. The additional 3,300
megawatts or so that would total the Bruce A or Bruce B, the
--
MR. POCH: Sorry to interrupt. The difference between
6,300 in the government statement and the 3,040 we just
spoke of?
MR. PIETREWICZ: Yes.
MR. POCH: All right. That's committed -- I'm sorry,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1101
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
that's committed?
MR. PIETREWICZ: Yes, that's correct.
MR. POCH: So the planned is Pickering and -- Pickering
B, and as we said, it may, while you have characterized it
as planned, it may de facto be committed in terms of
avoidability in the next round, as it were. Is that fair?
MR. PIETREWICZ: I wouldn't say the entirety of the
planned nuclear in this table --
MR. POCH: Sorry, I was really just repeating what we
already covered on the 2,064, Pickering B. And that's -- I
think you are anticipating my next question was, What else
was in the -- what else is in the planned there? The
difference between 3,464 and the 2,064, the 1,400, is that
what we have referred to as proxy nuclear?
MR. PIETREWICZ: In general. I don't think we
specifically refer to it as proxy nuclear. We have referred
to it as planned nuclear in the IPSP.
MR. POCH: Okay. But you have also got --
MR. SHALABY: For added clarity or complexity, the
combinations and permutations of how the nuclear capability
gets developed is not limited to the two or three scenarios
that you are describing, Pickering B plus 1,400, 3,500 at
Darlington minus this.
These are illustrative ways of getting to some of the
nuclear developments. There are many permutations and
combinations that are yet to be developed further.
MR. POCH: All right.
MR. SHALABY: These are illustrative and indicative,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1111
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
but not -- to name names and units and dates and so on, is
just interpreting more into them than is really meant.
MR. POCH: Okay. Well, let me just -- bear with me a
little more.
In the committed column, in addition to the two numbers
we just heard, the 3,040 for Bruce A and the 3,260, which I
will call Bruce B, either replacement or refurbishment,
you've got 2,000 to 3,500 for this potential capacity at the
Darlington site, nuclear capacity at the Darlington site;
correct? So there is 3,500 listed for that?
MR. SHALABY: Yes.
MR. POCH: All right. Now, what about the -- is it
3,524 to Darlington A right now?
MR. SHALABY: Close enough.
MR. POCH: All right. What about that? The
presumption is that that's going to be refurbished, is there
not?
MR. SHALABY: Well, this is where I am coming to, the
permutations and combinations. There are many, many ways of
making up the planned nuclear and the committed nuclear that
are yet to unfold, and it is probably not very productive to
exactly say what is it that's going to be procured at
Darlington site, or refurbished.
MR. POCH: I heard that, Mr. Shalaby. You don't have
to repeat yourself. I heard that message.
MR. SHALABY: Yes.
MR. POCH: I am just asking, the 3,524 at Darlington,
the existing Darlington plant, there is a presumption, is
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1121
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
there not, that it will be refurbished?
MR. SHALABY: Depends what else happens. If they build
new that is larger in size, maybe it wouldn't be. It
depends on all of the other things that will happen.
So the presumption of what happens here is similar to
what will happen at Pickering, or what will happen at Bruce
B and the new build. All of it is in play right now.
MR. POCH: Well, are you making the presumption that
the 3,500 new -- up to 3,500 new at Darlington is
necessarily a replacement for the existing?
MR. SHALABY: No.
MR. POCH: No. Okay.
And the decision on Darlington A refurbishment, I take
it that is analogous to the decision on Pickering B? It's
not really your decision to make?
MR. SHALABY: Whether to refurbish or build new is the
owner's decision, yes.
MR. POCH: Well, I think you have already -- okay. I
am distinguishing between -- let's call this announcement
the Darlington B, okay? The 2,000 to 3,500, let's call that
Darlington B.
So you're saying there is a decision to be had with
respect to Darlington A to refurbish it or potentially
replace it, and we're not take talking about Darlington B as
a replacement. We're talking about a different replacement;
correct?
MR. SHALABY: Yes.
MR. POCH: Okay. Well, my math, then, is that we've
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1131
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
got potentially 15,388 megawatts, if everything happened,
just the simple math.
And I think you have confirmed for me that basically
none of that is in your discretion; fair?
MR. SHALABY: All of that happens years from now. None
of that is -- you have made certain assumptions of what gets
refurbished and what gets --
MR. POCH: I'm agreeing. I am saying if it all
happened, and I'm not including the 1,400, by the way, just
the identifiable items that -- you know, Bruce A, Bruce B,
what I've called Darlington A and Darlington B and Pickering
B refurbishment, adds up to 15,388?
MR. SHALABY: You're assuming all of that would happen?
MR. POCH: If it all happened.
MR. SHALABY: Then the arithmetic you have is right.
MR. POCH: That's not in your discretion?
MR. SHALABY: It's not subject to this planning
discussion that we're into right now, no.
MR. POCH: All right. Can you answer my question?
It's not in your discretion?
MR. SHALABY: To do what?
MR. POCH: Two years from now, it's going to be in your
discretion to announce, We're not going to do one of those
things?
MR. SHALABY: If the government has a policy of having
nuclear stay at a certain corridor, a certain number, then
that's in the government's discretion. They own the
companies that make these decisions.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1141
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: I am suggesting to you, though, that there
is already more there, 1,400 more, than the maximum in the
directive for nuclear.
MR. SHALABY: Yes, I accept that.
MR. POCH: So there is really not any -- if we take
this announcement that the government has made in the way
that you are urging us to interpret it, there's really not
any way that we can have -- make room for more CHP or
conservation from the nuclear part of the pie?
MR. SHALABY: I'm surprised how we arrived at that
conclusion.
MR. POCH: Sorry, I couldn't hear.
MR. SHALABY: I'm surprised how you arrived at that
conclusion. I wouldn't reach that conclusion.
MR. POCH: There is no room that you can create. There
may be room the government or the OPA could create; let's
put it that way?
MR. SHALABY: There is room that conservation and CHP
can create.
MR. POCH: Well, you don't have any discretion to make
room for more CHP and -- I mean, assuming load isn't
growing, you know, beyond anybody's expectation, you don't
have any room, from the nuclear portion of your planning
pie, unless the government makes room for you, the way you
have interpreted what they're doing. It's not in your
discretion?
MR. SHALABY: I mean, if we come three years from now
and discover that there is more economic CHP and there is
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1151
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
more feasible and economic conservation, we put that forth.
And other decisions will take that into account, whether we
do it or the government does it, or the plant operators do
it. The plant operators are not going to build plants that
won't operate.
MR. POCH: Mr. Shalaby, I took it that the way you are
coming to this hearing before this Board is to say, Our job
is to build a plan, pose a plan to decide how much we have
to procure, and we're taking certain things out there as
given. Obviously what is already in the ground is given.
Things we have already been directed to do are given.
And I am suggesting you are treating the nuclear in the
same way. Whether it's in fact -- de facto, it is
contracted or not, you are treating it as a given.
MR. SHALABY: We're treating it as being worked on
elsewhere. It doesn't mean it is going to get built. It
doesn't mean it is going to get built to the schedule or the
specifications as you are describing.
People are developing options to be used as
appropriately and as other matters evolve. There is just
some other entities developing these options, and that's
namely the government.
MR. POCH: So just back to my simple question.
First of all, I take it that it's not your -- you don't
view it as your responsibility, then, to see that the 1,400
megawatt cap is honoured -- 14,000, excuse me. That's not
your job?
MR. SHALABY: The directive tells us to develop plans
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1161
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
that do not exceed 14,000. That's what we do.
MR. POCH: Okay.
MR. SHALABY: The plans we develop do not include
anything above 14,000.
MR. POCH: You're disavowing any responsibility for
telling these players out there to build or not build any of
these things, and I just added numbers up for you and they
go over 14,000.
MR. SHALABY: You're getting to the point of people can
do things that are different from the plan, and they
certainly can.
MR. PIETREWICZ: I wouldn't want to leave with the
misrepresentation that this sum that you totalled, this
15,000 plus, is what is reflected in the IPSP. It isn't.
The IPSP reflects a plan that plans for no more than 14,000
megawatts of nuclear.
MR. POCH: Okay. Really this is all in aid of the
question of how much flexibility you are going to have to
accommodate more conservation and combined heat and power
and renewable, if it is cheap enough, and where those
flexibilities arise in your plan. That's really the point
of my question. If there is anything further you can add in
that regard with respect to the nuclear, please feel free.
All right. Finally there is this unspecified 650. I
take it it is just what it is, 650, it is unspecified. It
is modelled as gas, though, is it?
MR. SHALABY: Yes.
MR. POCH: Obviously it is, in the discussion we have
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1171
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
been having, it is avoidable in the sense it is not even
specified yet.
MR. SHALABY: Yes.
MR. POCH: All right. We provided, in our exhibit
package -- excuse me, I am just getting mine.
In Exhibit K2.1, we just made an attempt before being
informed by your answers, to try to tally up what this
avoidable capacity is here.
I am not going to take you through this right now. I
would just ask if you could just -- leaving aside perhaps
for the sake of simplicity - I won't put you on the spot
again about what category we put nuclear in - but in the
other categories, could you, at your leisure, take a look at
that and just advise us if there is any changes we should be
making to that table for it to be a reflection of the
current situation.
MR. SHALABY: Changes to the table, that is the first
page.
MR. POCH: The first page, yes.
MR. SHALABY: Changes to what exactly, for what
purpose?
MR. POCH: Well, we had this discussion about what is
avoidable, where your flexibility is, matters that aren't
committed and that aren't -- for example, we had some
renewables in conservation that are -- not in your committed
box, they're in your planned, but in fact you don't have
flexibility because -- assuming you are honouring the
directive. We tried to capture what you do have flexibility
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1181
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
and conceivably control over and that you, you know, could
yield in future within your planning discretion in the next
round or -- and how that lays out when those commitments
would be made, and what they add up to but also working --
looking at it the other way, up to what times things can be
-- currently thought are avoidable. I am just wondering if
you could -- do you understand what this is purporting to
do?
MR. SHALABY: Yes, I do.
MR. POCH: You don't need to do it on the fly. Can you
just -- perhaps we can get an undertaking for OPA to look at
that, confirm or otherwise update that table.
MR. RICHMOND: Yes that would be undertaking J2.2 and
it is an update of avoided plan capacity.
MR. POCH: Avoidable planned capacity.
UNDERTAKING NO. J2.2: TO PROVIDE AVOIDABLE PLANNED
CAPACITY AS IS PRESENTED IN DRAFT FORM IN K2.1, PAGE 1
MR. POCH: As is presented in draft form in K2.1,
page 1.
MR. PIETREWICZ: I just want to make sure I understand
this a bit more clearly. Are you talking generically?
Avoidable in what sense? Avoidable in the sense that it is
not committed? Is that what you mean?
MR. POCH: Not committed or, as we have discussed,
otherwise not within your discretion to avoid.
I am going to move on to sustainability, and we're
going to -– well, let me start with this. You had a
discussion with Mr. Crocker already about the wording of the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1191
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
regulations and so on.
Can we agree also that another legislative piece of the
puzzle here with respect to sustainability is the
Electricity Act, section 1(g), which lists as an objective
"to promote economic efficiency and sustainability
in the generation, transmission, distribution and
the sale of electricity"?
You have to speak into the microphone.
MR. SHALABY: Yes. Thank you for reminding me.
MR. POCH: I think you have indicated, in your written
evidence certainly, but I think you have reiterated that you
view the planning -- basic way you have planned as in not
just informed but really built on a foundation of a goal of
pursuing sustainability?
MR. SHALABY: Yes.
MR. POCH: And you have indicated you started with
Professor Gibson's approach to defining the language of
sustainability, and then you drafted more project-specific
criteria. Is that fair?
MR. SHALABY: Context-specific criteria. We didn't
exactly start there. I mean, this framework came along in
early 2006. We have had our research and knowledge before
that, so it came along the way and added to our knowledge,
yes.
MR. POCH: Is it fair to say it kind of crystallized
it?
MR. SHALABY: Crystallized is good, yes.
MR. POCH: Professor Gibson and his associates suggest
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1201
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
that, in the evidence they have drafted for my clients in
this proceeding, have suggested -- I will start at very
general level -- that appropriate utilization of this
approach would require OPA to meet three tests. I am going
to read them in for you and ask you, before we get to
specifically what we did, whether you agree those three
tests are indeed appropriate.
I am taking these - you don't have to turn it up - they
appear in L-8-9 at page 24, and I am paraphrasing.
MR. VEGH: What is that reference again?
MR. POCH: L-8-9 at page 24. I am paraphrasing.
MR. VEGH: Can you give us a minute.
MR. POCH: Sure. And I apologize. This one, I don't
think, was on our PDF compilation for Ms. Heinz.
MR. SHALABY: Page 34?
MR. POCH: 24.
What I am going to ask you is whether you would agree
that it is indeed appropriate that you be held to this
standard. First, that planning was underpinned at the
outset by the basic objective to contribute positively to
sustainability.
MR. SHALABY: You're going to read all three?
MR. POCH: Why don't we take them one at a time. I
think it would probably be easier rather than tax everyone's
memory.
You agree that that is a test that is appropriate for
you to be held to? If we're reviewing whether or not you
utilized a sustainable approach here, that that is
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1211
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
reasonable?
MR. PIETREWICZ: Pardon me, Mr. Poch. Can you please
kindly point out the reference in the evidence?
MR. SHALABY: See this requirement comes throughout the
evidence and...
MR. POCH: I am not really -- my question doesn't turn
on where or whether indeed it appears in Professor Gibson's
evidence. You can treat it as just a question on its own.
Do you agree that it's reasonable -- if this Board
wants to test whether or not you've planned based on
sustainability, if --
MR. SHALABY: If you asked us whether we considered
sustainability...
MR. POCH: Well, let me ask you if you honoured
sustainability in your planning.
MR. SHALABY: We considered sustainability.
MR. POCH: You say you considered it.
MR. SHALABY: That's the test this Board --
MR. POCH: All right. I hear what you’re saying.
Let's start with that, then.
MR. SHALABY: -- what we did, and what we think we did,
and what this Board should determine. I am careful to
separate the two.
MR. POCH: Mr. Shalaby, we don't need to argue. Let's
use your word. In testing whether you have meaningfully
considered sustainability, do you think it is reasonable and
appropriate to ask and do you think it is a reasonable test
you should have to pass, that planning was underpinned at
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1221
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the outset by the basic objective to contribute positively
to sustainability?
MR. SHALABY: It's a reasonable expectation, to
indicate whether our planning enterprise altogether was --
what was the objective of it. It was the betterment of life
in Ontario. It was meeting the requirements of the people
in Ontario in a way that meets societal expectations.
MR. POCH: All right. Do you agree that is a
reasonable -- a reasonable -- as one arm of a test to see
you have done your job properly, that is a reasonable one to
pose?
MR. SHALABY: Not a bad one, yes.
MR. POCH: The next is that the objective -- not
objective of --
MR. SHALABY: Although the entire literature is talking
about movement towards sustainability. What we learned from
the discussions with people in this literature and this
business is that you don't attain. This is not a
destination. You move towards sustainability.
MR. POCH: No argument there, Mr. Shalaby.
MR. SHALABY: So whether the plan moves Ontario to
sustainability, I am prepared to take that as a test for
whether this plan does that or not.
MR. POCH: Right. And that objective - that is, the
plan was underpinned at the outset by the basic objective to
create to contribute to positive sustainability - that
objective was elaborated for practical application through
comprehensive sustainably-based evaluation and decision
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1231
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
criteria. Do you think that is a reasonable test?
MR. SHALABY: The words mean things specific to the --
to the authors of this 200-page report, and I think to treat
them in a superficial manner here may be -- not do service
to those listening to it for the first time.
So maybe you could explain what is meant by that. I
know there are very specific meanings to evaluative
criteria. These words mean very specific things in the
sustainability literature.
MR. POCH: With that caveat, would you agree it is a
reasonable test?
MR. SHALABY: Say the question again, please?
MR. POCH: The objective was elaborated for practical
application through comprehensive sustainability-based
evaluation and decision criteria?
MR. SHALABY: I don't understand this question. I
apologize. I have to write it down and I've got to reflect
on it. Too many meanings all in succession. I don't
understand what this means.
MR. POCH: Fine. Do you understand what
sustainability-based evaluation is?
MR. SHALABY: Not in the specific way that you applied
it here. No, I don't.
MS. NOWINA: Mr. Poch, it is in your evidence. If the
witness panel wants to go to it --
MR. POCH: Yes, you have that page reference, if that
helps you.
MR. SHALABY: Yes, I do. I just don't want to hasten
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1241
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
to accept a sentence that rolls together 16 different
concepts, and I know that does, without unbundling that and
carefully going through them.
MR. POCH: Well...
MR. SHALABY: We considered the requirements. The
evaluation part is something that we did not do.
MR. POCH: Well, let me just break it down for you.
Do you agree that you have decision criteria that
reflects sustainability?
MR. SHALABY: We have that, yes.
MR. POCH: I am not asking whether you have it or not.
I am just agreeing -- it is a reasonable query whether you
have done that right, where you have done that?
MR. SHALABY: We have planning criteria. If you call
those decision criteria, then, yes, we should have decision
criteria.
MR. POCH: Similarly, you should have evaluation
criteria for the various steps in your planning that
reflects you sustainability, the goal of moving towards
sustainability?
MR. SHALABY: I agree that you should evaluate, but
evaluation criteria is different than evaluation. So, for
example -- so you understand the theory side, on the
conceptual side, and I am leaping into the practical side.
MR. PIETREWICZ: If that's helpful, I am not exactly
clear on how evaluation criteria would differ from the
planning criteria that we have just discussed. Are they the
same thing?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1251
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: All right. If you -- I am not going to
venture an opinion, but your answer, if we get -- is that
you may be -- well be that your plan -- I think your answer
is your planning criteria are in fact evaluation and
decision criteria that reflect pursuit of sustainability.
That's your position, I take it; correct?
MR. SHALABY: We displayed performance of the plan
against various other criteria as a way of describing how
the plan performs, yes.
MR. POCH: And not just -- not after the fact -- not
just after the fact, but in how you developed your plan, you
would agree you should have done -- do your planning, do
your evaluation as part of your planning, and make your
decisions based on criteria that reflects sustainability.
You would agree that is a reasonable test and you have
purported to do that?
MR. SHALABY: I'm stuck on "evaluation".
MR. POCH: Maybe it's the choice of words. I am trying
to distinguish, and I think Professor Gibson was trying to
distinguish in his decision, the end point amongst
alternatives.
MR. SHALABY: Yes.
MR. POCH: And how you evaluate and --
MR. SHALABY: We call that --
MR. POCH: -- compare alternatives as you go.
MR. SHALABY: Sorry, Reporter. She asked me not to
interrupt you.
MR. POCH: Fair enough.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1261
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Apart from good manners, just to get the
transcript right.
Explaining criteria at the beginning; it's a
description of the performance of the plan at the end. We
have done that.
MR. POCH: Right.
MR. SHALABY: If that's what is meant by the test, then
I accept that to be a reasonable requirement.
MR. POCH: And, finally, Professor Gibson suggests and
his colleagues suggest that you should be -- these criteria
should be applied consistently through the planning process
and achieved reasonably in the ultimate plan; agreed?
MR. SHALABY: That's an innocent sounding test, yes.
MR. POCH: Okay, yes. Now, you started -- I have heard
you already say you started with this Professor Gibson's
eight -- I'll call them principles, and you devise these --
MR. SHALABY: Requirements. He calls them requirements
and so we do.
MR. POCH: Okay.
MR. SHALABY: You are objecting when we shorten things
and describe things differently, so I will do that again.
MR. POCH: Thank you, Mr. Shalaby, but the clock is
running.
MR. SHALABY: Okay.
MR. POCH: You devise six context-specific criteria,
feasibility -- they are feasibility, reliability,
flexibility, cost, environmental performance and social
acceptance; correct?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1271
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Yes.
MR. POCH: All right. Now, those six, can we agree
they're really fairly traditional electricity planning
criteria? You would have -- put another way, you would have
used those six in 1989 when you were doing the --
MR. SHALABY: We talked about that yesterday. Some of
them are traditional planning criteria.
MR. POCH: All of them, is it not the case? Did you
use all of those in 1989?
MR. SHALABY: We used three in 1989, to my memory.
MR. POCH: What of those would you not have considered
in your planning in 1989?
MR. SHALABY: This is now a historical perspective, but
the fact that --
MR. POCH: I am not worried about the formality of how
it was expressed at the time, Mr. Shalaby. I am really just
saying aren't all of these things obvious matters that you
would take into account in planning an electricity system?
MR. SHALABY: They are.
MR. POCH: Okay. And they have been obvious for
decades?
MR. SHALABY: Maybe sustainability has been obvious for
decades, as well, and we're just describing something that
has been practiced all along or could have been practiced
all along, yes. That's part of the discussion in the book,
as well.
MR. POCH: Sure. Now, turning to how you used these
six criteria, let's turn to Exhibit I-1-54. This is an
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1281
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
answer to Board Staff Interrogatory 54.
I am reading in A at line 20:
"The criteria of feasibility, reliability and
flexibility were applied to individual elements of
the IPSP and treated as primary planning
considerations. If a resource option met each of
these filters, the OPA then assessed the resource
under the criterion of cost to establish a rank
ordering for potential resources from lowest cost
to highest cost. Where a proposed resource was
not the lowest cost option, the OPA still had the
discretion of including it in the IPSP if its
inclusion could be justified on the basis of
improved environmental performance or social
acceptance."
So, first of all, I took from that - and correct me if
I'm wrong - that feasibility, reliability and flexibility
were initial screens that everything had to pass?
MR. SHALABY: Yes.
MR. POCH: All right. Then cost was the initial and
primary ranking criterion used for those resources that met
the first three screens.
MR. SHALABY: Yes.
MR. POCH: And that better -- it says -- the wording
there says that better environmental performance or social
acceptance could move the ranking of a resource up, but I
take it that, in fact, from your comments yesterday, that at
least as far as environmental performance goes, leaving
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1291
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
aside social acceptance and other broader considerations of
sustainability, environmental performance was not, in fact,
used to change ranking of options as between different
options?
MR. SHALABY: In the range we looked at, it did not.
MR. POCH: Okay.
And I take it that that read, if my read of that at
least doesn't have the possibility of options, passing the
first three screens is simply failing on environmental or
social, performance or social acceptance basis.
Am I reading something into there that is not there, or
-- did anything fail that you were looking at on the grounds
of environmental performance or – well, you said already
environmental performance wasn't, didn’t turn out to be a
factor. Did anything fail on social acceptance?
MR. SHALABY: I will answer that by way of referring to
the government directive. The government directive very
clearly focussed the mix of resources, the targets for
resources, the phasing out of coal. The government
directive did a lot of this work.
MR. POCH: Right. If I may, you said earlier, you felt
by meeting the directive, you were basically assuring
yourself that you were meeting social-acceptability
criteria; is that fair?
MR. SHALABY: That did a lot of the environmental work
and social acceptance work, yes.
MR. POCH: In your view did it do all of it, in other
words, obviate the need for you to do that job?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1301
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: It did most of it, yes.
MR. POCH: Well, can you give me --
MR. SHALABY: All of it in the planning -– and -- on
the planning level, yes.
MR. POCH: On the planning level all of it, yes.
MR. SHALABY: Okay.
MR. POCH: If we could move on to in the same
interrogatory but part B you say at line 13:
"As described in Exhibit C-4-1, page 37, the OPA
did not apply arbitrary weights for evaluating one
criterion against another. That exercise would
not have provided any meaningful guidance in
developing a plan that is economically prudent and
cost-effective."
Does that -- that suggests to me, and correct me if I'm
wrong, that the OPA interprets "economically prudent" and
"cost-effective" as not encompassing these other criteria of
any factors for environment and social acceptance.
MR. SHALABY: We interpreted "economically prudent" to
mean feasibility, reliability and flexibility.
MR. POCH: Okay.
MR. SHALABY: "Cost-effectiveness" is to do with cost
and the other two are not part of "economic prudence".
MR. POCH: Okay, then you answered my question.
If we turn to I-1-57, you have provided us with some
information on how you utilized environmental information.
You already answered both Mr. Crocker and myself on that
point, in a general sense.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1311
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Just to narrow it down a little more.
MR. SHALABY: Question.
MR. POCH: I will just read in the parts that I am
noting. You have three steps there --
MR. PIETREWICZ: Sorry. Pardon me. We are just
looking for the reference.
MR. SHALABY: 57 or 157?
MR. POCH: I have it as number I-1-57. Sorry.
MR. POCH: Tab 1, schedule 57, sorry.
MR. SHALABY: Oh, I-1, pause, 57.
MR. POCH: Yes. I didn't say "hyphen".
MR. SHALABY: Thank you.
MR. POCH: You have step 1, step 2, step 3. And if I
can just shorten them up so we can have a discussion about
it. Step 1 is, you collected the environmental indicated
data on a per-unit basis for each resource option; correct?
MR. SHALABY: Yes.
MR. POCH: Step 2 was, you quantified each indicator
for the aggregate of supply and transmission resources at
the plan level over the plan period.
MR. SHALABY: Yes.
MR. POCH: And then step 3 was you -- to test the
robustness of the plan, you evaluated and compared the
results of two sets reference conditions which was the A
cases, cases A and B, with and without Pickering B.
MR. SHALABY: That's correct.
MR. POCH: Sorry?
MR. SHALABY: Yes. I agree.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1321
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: All right.
So I think you have already indicated environmental
factors weren't at play in choosing between options. Is
this fair to say that your tallying and looking at
environmental implications really only was at the -- once
you had a plan, you it did it at the plan stage. You
tallied things at the plan stage? You didn't --
MR. SHALABY: Well, we went into this plan with a
preliminary plan, and we went to the preliminary plan with
options before that.
I mean the evolution of all of this is we knew where we
were heading. We -- this was not all a surprise and at five
minutes to 12:00, we found out what the environmental
performance was. We knew that going in, and in an iterative
fashion.
MR. POCH: Now, you said you didn't use environment to
select between options and -- you have said this a few times
on the record -- because, you said, because stakeholders
told you not to weight impacts.
MR. SHALABY: We agreed with them on that, yes. At
this stage, given the narrow range of the parameters, given
the small differences between what one mix of options would
result in and the other, in our view, we didn't think that
would differentiate, wouldn't add a whole lot of value at
this stage.
MR. POCH: Okay. You even say you agreed with us. So
let me take you to C, Exhibit C, tab 11, schedule 2,
attachment 27.1 at page 10.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1331
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
So it is Exhibit C, tab 11, schedule 2, attachment 27.1
at page 10. This is part of -- correct me if I'm wrong --
this is part of a submission that was made to you by one of
my clients, Pembina.
If you look at the second bullet on that page, it says:
"The plan should consider imposed and avoided
externalized environmental costs in its assessment
of the cost-effectiveness of CDM, renewable and
conventional options and overall plan costs and
impacts."
So some of us told you you should --
MR. SHALABY: We're trying to -- I know the clock is
running and it is your clock, but we have to catch up.
MR. POCH: That's arguable.
MS. NOWINA: Mr. Shalaby, I need to catch up too. I am
trying to find C-11. So the document is? I don't have it.
Okay. I don't have the discussion papers.
MR. SHALABY: Is it discussion paper 7?
MR. POCH: I have the one page in front of me so I
can't be very helpful in that regard.
MR. SHALABY: What page number is it?
MR. POCH: Your cite on it is C, tab 11, schedule 2,
attachment 27.1, page 10. It is coming up on the screen in
front of you. It may be faster that way.
MR. SHALABY: There we go. Commentary on page...
MR. POCH: Okay. I was just reading from the second,
the first sentence in the second bullet on that page.
MR. SHALABY: Can we get this? If we go to the top to
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1341
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
know who it is from and what the context is, that would be
helpful for us.
MR. POCH: That would be good confirmation for me too.
I have read that as being from -- prepared by Professor Mark
Winfield on behalf of the Pembina Institute which is one of
my clients; correct, Mr. Shalaby?
MR. SHALABY: Yes.
MR. POCH: And the passage I read into the record a
moment ago which is the second bullet on page 10, first
sentence of the second bullet on page 10, it is pretty clear
there that some of us were telling you that we do want you
to count these costs in your planning. Is that not the
case?
MR. SHALABY: So there are two thoughts in that bullet,
one about the portfolio of CDM. I don't think that is what
you are referring to.
MR. POCH: No. I was referring to the first sentence
there.
MR. SHALABY: Yes. I read the point, and we indicated
that we're not monetizing external --
MR. POCH: It doesn't speak of monetizing. It just
says it should consider --
MR. SHALABY: Yes.
MR. POCH: -- those costs.
MR. SHALABY: Yes.
MR. POCH: And --
MR. SHALABY: In the assessment of --
MR. POCH: I am making the simple point that you have
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1351
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
said so many times that, We agreed with the stakeholders,
but the stakeholders, there was no unanimity amongst
stakeholders?
MR. SHALABY: There was no unanimity amongst
stakeholders.
MR. PIETREWICZ: I think what Mr. Shalaby was
specifically referring to was the issue of weighting
environmental results.
MR. POCH: Right. Could you turn to Exhibit C, tab 4,
schedule 1, at page 37?
This is the exhibit that is entitled, "How the OPA
responded to the views of stakeholders." Correct?
MR. SHALABY: Yes.
MR. POCH: And at page 37 -- I have to get it on my
screen so I can see the part I was trying to find -- and,
sorry, I have lost the reference. If you just give me a
minute.
All right. In fact, I want to look at page 31. My
apologies. This is where you indicate how you responded to
stakeholders on the matter of environmental performance;
correct?
MR. SHALABY: Yes.
MR. POCH: First of all, you heard that it must include
a comprehensive analysis of the environmental performance
plan?
MR. SHALABY: Yes.
MR. POCH: This is your distillation of what you heard.
First of all, let me ask you that. This is your
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1361
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
distillation of what you heard?
MR. SHALABY: Yes.
MR. POCH: All right. You heard that the IPSP must
include a comprehensive analysis of the plan's environmental
performance. Did you do that?
MR. SHALABY: Yes.
MR. POCH: Where is that comprehensive analysis of the
plan's environmental performance?
MR. SHALABY: In Exhibit G-3-1.
MR. POCH: And you view that as comprehensive?
MR. SHALABY: Yes.
MR. POCH: Okay.
MR. SHALABY: Comprehensive and appropriate to the
planning stage. I mean, this is the point I spent a lot of
time on yesterday. At the planning stage, this is
comprehensive and appropriate.
At a project stage, you describe the type of land
affected, the type of watershed affected, the type of
environment and roads, and so on.
So subject to that understanding in that context, yes,
I consider the planning level to be comprehensive.
MR. POCH: We appreciate that there are certain details
which aren't knowable until you drill down to a project-
specific.
MR. SHALABY: Yes.
MR. POCH: But you can make generic assumptions?
MR. SHALABY: If it helps at the planning level, then
we will do that. If it doesn't help, then you don't.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1371
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: For the purpose of comparing options, you
would want to make generic assumptions, would you not?
MR. SHALABY: Yes, yes.
MR. POCH: Did you do so?
MR. SHALABY: We have a comprehensive assessment on all
of the environmental performance emissions that we thought
were important to track.
MR. POCH: Paragraph 3 says one of the things that
stakeholders told you, in your view, was that you should
ensure that all radioactive emissions and wastes have been
accounted for:
"The OPA's analysis should make a distinction
between the toxicity of the different kinds of
wastes."
Did you do that?
MR. SHALABY: We describe the emissions, the
radioactive emissions across the years. We describe the
amount of waste.
MR. POCH: Did you make a distinction between the
toxicity of the different kinds of waste? That's what the
specific point is.
MR. SHALABY: We describe waste both as radioactive
waste separate from other waste, yes, we did.
MR. POCH: And as far as you're concerned, that is a
distinction on toxicity, because you have labelled one
radioactive and the other airborne or waterborne, or
something else?
MR. SHALABY: We described the amounts of waste that
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1381
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
are fuel wastes from nuclear reactors in kilograms.
MR. POCH: If I want to understand what the toxicity of
what you are producing -- your plan is producing is, where
do I find that of wastes here? This is talking about
wastes, I believe.
Let's take the nuclear portion of your plan as an
example. If I want to know the toxicity of the nuclear
waste being produced, did you do that?
MR. SHALABY: No, we didn't get into the details of
toxicity analysis.
MR. POCH: Thank you. It says, "Evaluate environmental
effects on a life cycle basis." Did you do that?
MR. SHALABY: We did that in the first stages of
planning, but not in the second phase and for reasons that
we mentioned.
MR. POCH: I'm sorry, I don't recall those reasons.
Could you refresh my memory?
MR. SHALABY: Yes, I can. One of them is we did not
have data for Ontario, Ontario-specific data on life cycle.
The second one was compatibility in putting new options with
existing options. If we're going to evaluate the
performance of the plan, how would you do the life cycle
analysis of a plan -- a plant that is already built;
Darlington A, already operating?
MR. POCH: Mr. Shalaby, why would you want to?
MR. SHALABY: Because we're evaluating the performance
of the new options with the old options.
MR. POCH: Wouldn't the issue be to evaluate the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1391
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
options that lay before you, the choices that lay before
you, against one another?
MR. SHALABY: The options alone do not generate
emissions until they start operating.
MR. POCH: Yes.
MR. SHALABY: They only operate in concert with the
existing resources.
MR. POCH: Yes, I understand that. Well, obviously
some of the impacts of existing resources are unavoidable,
to the extent they have to do with the construction, for
example, of an existing resource, but its operation may
change in your plan and different plans, and so you could
certainly model that.
MR. SHALABY: I didn't hear the question. Go through
the four reasons or three reasons for why life cycle
assessment was less helpful at this stage than it was in the
previous time.
MR. POCH: I am just trying to understand your point
that you have difficulty -- you were suggesting you didn't
know how you would deal with existing versus new, and I am
saying -- I'm suggesting that the only issue is what's --
what choices lay ahead, what is avoidable, whether it is
from existing or new.
Obviously, some the impacts of existing are unavoidable
at this point, but still are?
MR. SHALABY: Yes, yes.
MR. POCH: I don't understand the difficulty you are
asserting.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1401
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: There is no difficulty. There is no
difficulty. It is more consistent to do the operating --
the operating performance. Let me get to the other two. So
no Ontario-specific data.
The more important one is the life assessment -- the
life cycle assessment that we performed in the first phase
indicated that the most significant impact is generally in
the operating phase.
We're going to provide evidence to that in G-3-1 when
the operating performance comes in. Most of the impacts are
in the on operating phase.
MR. POCH: We will leave that to the -- I guess
Dr. Barber and others.
MR. SHALABY: Right, right.
MR. POCH: Okay, thank you.
Now, one of the other things that -- you were asked to
evaluate air quality rather than simply air emissions. Did
you do that?
MR. SHALABY: No. We evaluated emissions and we
indicated that that's a precursor to environmental impacts
and we did not evaluate impacts but rather the precursors.
MR. POCH: Okay. All right. Finally, if you move
ahead to the next section which is about how you responded
to stakeholder positions on sustainability as opposed to
environmental performance, and I am looking now at page 37,
paragraph 12. It says there that the advice you took from
stakeholders at the time was to provide definitions of the
planning criteria, and provide clear measures in
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1411
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
illustrating how each criterion has been weighted and
evaluated, explicitly evaluating trade-offs between
alternative resources and alternative plans.
Do you feel you did that?
MR. SHALABY: Yes. The answer says that we did, yes.
We provided definitions of the planning criteria. We
illustrated how the criteria had been applied.
MR. POCH: Well, did you weight -- place different
weightings.
MR. SHALABY: We did not numerically weight, no.
MR. POCH: Okay, thank you.
MR. SHALABY: We describe the reasons for that several
times already in the last day or two.
MR. POCH: Now, in your discussion with Mr. Crocker,
there seemed to be a tension in the dialogue, I think it is
partly a question of semantics and I would just like to
clear that up, in that there is tension between
sustainability, broadly defined, and environmental
sustainability.
Mr. Crocker seemed to be asking you specifically about
environmental sustainability, and I heard a lot of responses
where you turned to your six criterion that we have listed:
flexibility, reliability, and so on.
Those aren't specifically criteria for environmental
sustainability; correct? Those are intended to be your
criteria that captured the broader ambit of sustainability?
MR. SHALABY: Yes.
MR. POCH: All right. And I want to focus now on the
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1421
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
subset of sustainability that we would call "environmental
sustainability." Okay?
MR. SHALABY: We didn't distinguish between
environmental sustainability and sustainability.
Environmental sustainability, the way we understood it,
encompasses all sustainability criteria. It is not a subset
of anything. It is sustainability.
So maybe you can start by defining subset, what subset
is that? One of the important lessons we learned there are
no subsets. There is a lot of interconnected features to be
considered together.
MR. POCH: All right. Well, just then going back to
environmental criteria, I take it you are treating
environmental performance just as compliance; correct?
MR. SHALABY: As a...
MR. POCH: As compliance, with regulations.
MR. SHALABY: As information. Information that
indicates compliance, yes.
MR. POCH: All right. So it is kind of a pass/fail
test? You either comply or you don't?
MR. SHALABY: Yes.
MR. POCH: So I think you already agreed, you didn't
weight that in terms of choosing between options. You have
been very clear about that.
You tallied it, as we saw a few moments ago, you
tallied at the plan level; correct?
MR. SHALABY: Yes.
MR. POCH: You didn't set out to create an alternative
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1431
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
greener plan and then compare tallies there, did you, on
environmental performance?
MR. SHALABY: We didn't know what a greener plan is. I
mean all of the options we considered here have features
that are acceptable and are contributing to consumers'
welfare.
MR. POCH: Okay.
Now, you are aware that the regulation says ensure that
safety, environmental protection and environmental
sustainability are considered in developing the plan;
right?
You are nodding. I take it assent, obviously.
MR. SHALABY: Yes.
MR. POCH: I read that, and I want to make sure you do,
that it is not just about considering it after you developed
a plan and doing a tally.
It is about considering it as you develop the plan.
MR. SHALABY: Yes, yes, it's developing.
MR. POCH: All right. So even if some of your
stakeholders said, don't try to weight environmental
concerns in choosing between options, do you agree with me
that your marching orders from the regulation are that you
must, indeed, find some way to meaningfully consider it as
you develop the plan?
MR. SHALABY: Well, let's talk about the practical
junctions where that consideration is -- the consideration
of environmental performance comes into --
MR. POCH: Before we talk about the practical
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1441
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
constraints on that, that is marching order from the Reg, we
don't disagree about that.
MR. SHALABY: No, we don't.
MR. POCH: Go ahead and elaborate. What are your
practical constraints?
MR. SHALABY: Most of the generation options have
environmental impact of one sort or another. This is where
we decided not to weigh acreage of land versus tons of water
use or gallons of water use and emissions and so on. That is
where we decided not to put numerical variance on it.
The one option that did not have environmental impact
is conservation. Conservation passed hands down on cost, on
lead time, on acceptability and support in the community.
It did not meet environmental criteria to make it preferred
or advantaged in consideration in the integrated plan.
That's the one place where environmental criteria could
have, could have tipped an option against something else.
And it didn't need it.
MR. POCH: Well, just --
MR. SHALABY: It's an option we need to use the most.
MR. POCH: Just so we're clear. We agreed you didn't
weight and compare the impacts of different options,
environmental impacts of different options. We agreed the
marching order is that you shall consider it, environmental
sustainability, environmental protection in developing the
plan, and finally I think you already agreed earlier to my
friend, Mr. Crocker, that the Board was very clear in its
filing guidelines, that it was reading considered as meaning
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1451
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
weight and evaluate.
MR. SHALABY: We did not weight as putting numerical
values on it. That's not the sense of weighting as
considering.
MR. POCH: How did you weigh --
MR. SHALABY: Weigh, in the people of algorithms and
models is different than weigh in terms of considering
something.
MR. POCH: I think you said to me, said a number of
times on the record: In choosing between options,
environmental factors just didn't come into play.
MR. SHALABY: Did not differentiate. Did not
differentiate.
MR. POCH: Because you didn't propose any basis, any
mechanism by which you could compare.
MR. SHALABY: That's correct.
MR. POCH: Okay.
Now, I would like to turn briefly to social
acceptability and to turn to Exhibit I, tab 1, schedule 55,
Board Staff interrogatory 55. And at line 29, you say:
"Further assessment of the IPSP's social
acceptance will be conducted as part of the OEB's
regulatory proceeding through an open process that
provides a forum for public input to be considered
by an independent third party in a consistent,
comprehensive and transparent manner."
Well, obviously I am not going to take -- argue much of
that, but do I read it correctly as saying that this process
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1461
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
that we are in at the moment is an important part of where
the consideration of social acceptance takes place, in your
process, in your planning process?
MR. SHALABY: It is, yes.
MR. POCH: It is, okay.
So if the Board were to conclude from -- at the end of
this hearing that it would be preferable to change the mix
for reasons of -- whatever reasons, that in terms of what it
has learned about the social acceptance of your plan, what
is the mechanism for that to happen?
MR. VEGH: Sorry, if I could just -- if I could provide
clarification before the witness gives an answer. I don't
have a problem with the witness giving an answer, just the
statement that Mr. Poch made, if the Board makes a
determination for "whatever reasons". The Board's mandate
is clear, under the legislation, as to its evaluation of the
plan.
So rather than having Mr. Shalaby either agree or
disagree on whatever reason the Board may consider, perhaps
the question could be considered more broadly than that or
more narrowly than that.
MR. POCH: I wasn't suggesting the Board was going to
stray from its proper jurisdiction. Assuming the Board
within its jurisdiction concludes; how is that?
MR. SHALABY: I want to step back a second and observe
that the line of questioning seems that we are into very
hard options and lack of -- we talked about development of
options that overlap. Conservation can be this much or
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1471
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
larger. CHP can be this much or larger, and nuclear can be
this much or less.
So the notion of disqualifying options or not
considering options, I almost -- I almost -- I am thinking,
What is it that we didn't consider? What is it that -- the
options that we did not consider at this stage on the basis
of environmental or in weighing or not weighing anything
else?
Everything is in the race. Everything is being
considered, subject to -- subject to how it evolves, how its
feasibility works out.
So you make it sound that there are people who are left
at the door, not admitted to the party. That's not true.
So -- and I think of it as if the Board determines a
different mix. Different mix of -- for what? We were
saying conservation to --
MR. POCH: Mr. Shalaby, let me interrupt you.
MR. SHALABY: Right.
MR. POCH: Your evidence says this process is part of
how your planning process is going to take social acceptance
into that process.
MR. SHALABY: Right, right.
MR. POCH: I'm saying if, as a result of this process,
the Board, fulfilling the mandate you have written there for
it, in effect, finds change is appropriate, what's the
mechanism for the change at this stage?
MR. SHALABY: Depending on what they find and how they
direct, the mechanism will develop pursuant to that.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1481
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
You're asking me to speculate what is it they will find
and on what basis --
MR. POCH: I don't want to get into specifics --
MR. SHALABY: -- what to do about it.
MR. POCH: We're just agreeing. I am trying to keep
this at a very high level. We are agreeing -- You are
laying out there -- you're saying to the Board the
discussion of social acceptance isn't done. We assumed that
this hearing is where that -- an important part of it is
going to take place.
MR. SHALABY: Yes, yes.
MR. POCH: So I am just -- the other half of that is,
then, you must assume that the Board retains discretion.
It's appropriate for the Board to exercise discretion to
suggest or impose or refuse approval without such a change,
changes that reflect what it learns about social acceptance
in this process?
MR. SHALABY: Yes.
MR. POCH: I am reacting to the piece that's no longer
evidence by some unknown author that suggested the Board
show great deference, and I am just contrasting what you say
here.
MR. SHALABY: The decision of this Board is a very
important part of the review of the plan and of the
acceptability of the plan that we are proposing, absolutely.
I am not sure what is it that is being asked here. It isn't
obvious.
MS. NOWINA: Mr. Poch, on that note of the importance
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1491
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
of the Board, perhaps this is an appropriate time for us to
take our afternoon break.
MR. POCH: Thank you, Madam Chair.
MS. NOWINA: We will take a break and return at 3:30.
MR. ADAMS: Madam Chair, I wonder if I can just
interrupt before we break. I didn't want to disrupt Mr.
Poch.
MS. NOWINA: I recognize you, Mr. Adams.
MR. ADAMS: Thank you. I am here representing a large
coalition of organizations, several of which have
representatives that are listening in on the Internet.
I have been receiving notices that we have been having
difficulty receiving a clear signal.
This is a matter that has arisen before, before the
Board. I just wanted to put on the record that there is
concerns from our group.
MS. NOWINA: Thank you for letting us know, Mr. Adams.
We will see what we can do about it. We will break until
3:30.
--- Recess taken at 3:12 p.m.
--- On resuming at 3:30 p.m.
MS. NOWINA: Please be seated.
Mr. Poch.
MR. POCH: Thank you, Madam Chair.
Panel, I just wanted to touch on one other element of
that regulation that refers to safety.
You have equated compliance -- is it fair to say you
have acquainted compliance on the safety front as –- if
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1501
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
there is compliance, it doesn't then influence your choices
between options?
MR. SHALABY: We considered the analysis of safety of
different electricity options, as I indicated this morning,
and we found that the differentiation is not about the
choice of the energy option, but how is it built? How is it
constructed? How is it operated? That led us to the
conclusion that it is the governance of safety, it's the
administration of safety that matters rather than the choice
of options.
So that is the reason we went there.
MR. POCH: I am just thinking, I mean first of all, can
we agree that compliance with regulations does not equal no
impact. There is still a residual impact on whatever a
regulation may be, safety emissions, what have you; correct?
MR. SHALABY: That's a statement of fact, yes.
MR. POCH: Yes. And obviously there is different,
dramatically different kind of safety concerns with
something like a nuclear plant than there is with
conservation; correct?
MR. SHALABY: Correct.
MR. POCH: All right. You haven't tried to weigh
those, in terms of the nature of the risks and compare them
between these options and use that as a criteria for
selecting at the margin or...
MR. SHALABY: We understood that the safety risks are
managed by the governance of these institutions, the CNSC,
in the case of nuclear, the requirements in construction,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1511
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
operation, maintenance, audits -- all bring the risks to an
acceptable societal level.
MR. POCH: So you are treating that as therefore no
discernable difference between options on that front?
MR. SHALABY: Yes.
MR. POCH: Because it met regulations?
MR. SHALABY: And the data that we looked at in between
the period 1969 to the period 1997 or 1998, in the OECD
countries, does not distinguish very heavily between
countries.
MR. POCH: Which exhibit are you referring to?
MR. SHALABY: This is an exhibit not tabled here but
referenced in the Stratos review of the sustainability.
B-3-1, attachment 1, refers to Paul Scherrer Institut on
safety.
There was not a whole lot interest on the stakeholder
side so we didn't table that.
MR. POCH: All right. Would you be good enough to
provide a copy of that?
MR. SHALABY: We can.
MR. POCH: Thank you. If I could get an undertaking,
Madam Chair.
MS. NOWINA: Very well. MR. RICHMOND: It would be
J2.3.
UNDERTAKING NO. J2.3: TO PROVIDE COMPARATIVE SAFETY
STATISTICS FOR ENERGY PRODUCTION FOR ELECTRICITY
GENERATION DOCUMENT
MR. POCH: That's to file the --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1521
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MS. NOWINA: Do you know the name of the report, Mr.
Shalaby? Do you know the name of the report?
MR. SHALABY: Not accurately enough. But it is
comparative safety statistics for energy, energy production
for electricity generation.
MR. POCH: Thank you.
MS. NOWINA: Thank you.
MR. POCH: Okay.
MR. HARBELL: If I can help, it is on the record at
Exhibit B-3-1 attachment 1, page 21, the report is called,
"Comparison of severe accident risks in fossil, nuclear, and
hydroelectricity generation," prepared by the Paul Scherrer
Institut.
MS. NOWINA: The name, is at that exhibit number, not
the document itself; is that correct?
MR. HARBELL: The name of the document is: "Comparison
of severe accident risks, fossil, nuclear and
hydroelectricity generation."
MS. NOWINA: Thank you.
MR. POCH: So as I think the title implies an answer to
my earlier question, that doesn't tell us anything about the
comparison of those risks to, say, conservation or small
renewables?
MR. SHALABY: It did not consider those.
MR. POCH: No. Okay.
So then if you could turn to D, tab 5, schedule 1, page
41. D like David, tab 5, schedule 1, page 41, at line 16.
MR. VEGH: Do you have it?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1531
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Not the attachment. The exhibit itself,
just about – yes, we have it.
MR. POCH: All right. I am on page 41 of 64. And this
is where you were looking at the LUEC of wind and
determining whether or not it made sense at the margin to
consider adding more; correct?
MR. PIETREWICZ: Yes.
MR. POCH: All right. If you would just look at line
16, I think there is the conclusion there. It says:
"Therefore on the basis of the LUEC analysis,
adding wind resources beyond that needed to meet
the 2025 target would not be cost-effective. The
differences, however, are relatively small and the
conclusions should be subject to further analysis
in future plans."
That still holds true?
MR. SHALABY: Yes.
MR. POCH: So, Mr. Shalaby, would you agree that where
the differences at the margin are relatively small, the
choice of whether or not to give credit in your analysis
between options for things like environmental differences,
safety differences, social acceptability differences, could
be -- it's a critical choice. Would you agree?
MR. SHALABY: It could tip the balance one way or the
other if there are significant differences, yes.
MR. PIETREWICZ: I would like to point out in this
particular context, the question relates to whether the
renewables target of 15,700 megawatts should be exceeded.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1541
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
And in order to help answer that question, we -- the OPA
compared the cost of the sort of exceeding that target by an
incremental amount of wind versus the cost of a sort of more
conventional supply resource such as combined cycle gas, and
Mr. Poch correctly points out that we found while gas was
seen to be less expensive than wind, the differences were
pretty marginal.
It's important to note that this is a marginal
question. This is a question that arises once we arrive at
that 15,700 megawatt point.
The IPSP doesn't show that being the case until farther
out into the future and that's why it indicates that the
conclusion should be subject to further analysis. It's not
a question that we're being absolute on at this time.
MR. POCH: Okay, that is helpful, thank you.
MR. SHALABY: To expand on that. We're not initiating
the procurement of the gas that replaces the renewables at
this stage. Nothing much turns on that differential at this
time. So let's make the decisions further out.
MR. POCH: All right. Now, OPA -- you have indicated
your consideration of environmental factors was based on the
SENES work, and first of all, you specified what work --
the scope of work for SENES?
MR. SHALABY: Yes.
MR. POCH: And then you have noted in your materials
that you had, I guess it is Dr. or Mr. Mark Rosen do a peer
review of the SENES work?
MR. SHALABY: Yes.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1551
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: That appears at G-3-1, page 2.
Can you -- can we just turn to that.
MR. SHALABY: Yes, we have it.
MR. POCH: Just scroll down. Excuse me, sorry. Again,
we lost our place here.
MS. NOWINA: Why don't you come back to it, Mr. Poch,
if you can't find it?
MR. POCH: Sorry. Thank you, Madam Chair. I think I
have found it now. Yes, thank you.
Okay, I am looking at G-3-1, attachment 2 at page 3,
and Dr. Rosen there notes some limitations, and he notes
that the report doesn't address emissions associated with
the full life cycle of power generation options considered.
He's referring to the SENES report; correct?
MR. SHALABY: Yes.
MR. POCH: And that wasn't within the scope of the
SENES study. He notes that all types of gas --
MR. SHALABY: It was a desirable outcome. The data was
not there. I mean, we went through that once before. The
data is not available.
MR. POCH: Yes, and that not all types of gas use,
environmental emissions are considered, although he says
most important emissions are considered; correct?
MR. SHALABY: Yes.
MR. POCH: It doesn't express an opinion, does it,
anywhere, about the adequacy of the report for a planning
exercise?
MR. SHALABY: Can we scroll up? I think it says it
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1561
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
provides a good foundation in different places here. Let's
see.
MS. NOWINA: It says that towards the end, Mr. Shalaby,
if I can help you out, on the last page just before the
bullet points.
MR. POCH: It says it provides a good foundation for
future assessments and research and other activities. I
noted that.
But it is not -- it doesn't purport to be an opinion
letter on whether or not the SENES report is a reasonable
basis to plan your system on, does it?
MR. SHALABY: It supports that this is an appropriate
set of parameters to plan with, yes.
MR. POCH: I'm sorry, where do you see that?
MR. SHALABY: Well, can we get the page? Give me a
minute.
MR. POCH: Hmm-hmm.
MR. SHALABY: Second paragraph:
"I found the report to provide a sound and well
thought out study..."
MR. POCH: It doesn't say what for.
MR. SHALABY: "...of the direct environmental
emissions of the operating phase of a wide variety
of electrical-generating options in Ontario."
MR. POCH: He doesn't actually express --
MR. SHALABY: A reasonable approach is used in the
study. So --
MR. POCH: He's looking at it within the confines of
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1571
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the mandate that you gave SENES. Did SENES do a quality
report in responding to what you told them to do? That is
how I interpreted his opinion. Am I correct?
MR. PIETREWICZ: I don't want to get nitpicky here, but
I think this report is written in the context, as the
subject line on page 1 indicates, that the peer -- this is a
peer review of, in quotes, "supplementary environmental
impacts report" for the Integrated Power System Plan.
MR. POCH: Well, let me ask you, then.
If you look at page 3, it says -- he's referring now to
the SENES report, and he says:
"The report acknowledges that simply examining
data is one step in appreciating the impact of
environmental emissions and clearly points out
that emissions data need to be weighted relative
to impact criteria - example, human health, animal
health, planned and land harm cost - to allow a
better understanding of the impact to be
developed."
Now, it seems to me he's agreeing with -- he's making
observation that the SENES report is not sufficient unto
itself. Isn't that what that says?
MR. HARBELL: To be fair, sir --
MS. NOWINA: Microphone, please.
MR. HARBELL: Sorry, I think we should --
MR. POCH: I can read on.
MR. HARBELL: If we can read the last sentence, please,
it says:
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1581
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
"Other weighting factors could also be used..."
First sentence of the first paragraph:
"...and different individuals, agencies and
countries often disagree on the magnitudes and
types of weighing factors that are correct."
MR. POCH: Right. You have done that, and that's fine.
I have no objection at all.
Isn't it perfectly clear, from that full paragraph,
that he's saying, just tallying up these emissions, you
know, SENES has done a good job tallying the emissions.
They are within the ambit of their mandate, but that's not
sufficient. You have to weight them to be able to compare
them. You have to -- they're important, these criteria,
these things are. Am I misreading that?
MR. SHALABY: Not knowing what specific airsheds, what
specific water streams, not knowing enough about the
projects, going down that further step is less meaningful
and less relevant at this stage.
Without knowing these details, we're not going to step
as close as where you want us to be as the environmental
assessments or projects are going to do. There are
environmental assessments that will take that into
consideration.
MR. POCH: Those environmental assessments are all at
the project stage and they will do nothing, will they, to
inform us of our choice at the plan stage between options;
is that correct? Yes or no?
MR. SHALABY: Well, the plan level gets aggregate
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1591
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
indicators.
MR. POCH: Yes, you said all of that.
MR. SHALABY: Project specifics will get into the
impacts on the specific communities and their --
MR. POCH: Mr. Shalaby, my question is very simple.
The subsequent appraisals at the project level will not help
us in this exercise of developing a plan that chooses
between options. It might help some future planner when he
has that data, but it is not going to help us.
MR. SHALABY: It helps us to know that these appraisals
are going to be made.
MR. POCH: And what good will that be when they're
deciding whether to put the transmission line down corridor
A or B or move the --
MR. SHALABY: They can decide not to put it in corridor
A or B and not locate a power plant --
MR. POCH: How are they going to decide that if they
don't have the whole plan in front of them to decide what
the alternative is to transmission? They are not going to
be in a position to make that trade-off, are they?
MR. SHALABY: They will be in a position to decide what
the mitigating measures should be and what accommodation
should be and whether to reject the project right out or
not.
MR. POCH: Within the confines of a plan that has
already been made.
MR. SHALABY: Yes. That is the context, yes.
MR. POCH: Thank you very much. Let's move on to
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1601
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
uncertainty.
I think we may have a little closer meeting of the
minds in this section, let's hope. Maybe we can move along
a little faster.
First of all, I just want to list for you some -- some
of the uncertainties that I think you have identified and
just make sure we agree that these are some of the biggies
in your plan and that could have impacted on your planning
and could still impact on your planning.
One is nuclear cost and performance is obviously a big
factor in your plan. It is a big part of it.
MR. SHALABY: Yes.
MR. POCH: CDM achievability and timing?
MR. SHALABY: Yes.
MR. POCH: Can we agree that the cost uncertainty of
CDM is less important, as you have indicated, that your --
you are not getting near the limit of cost-effective CDM
until I think we're up about 150 percent of where you are
shooting for?
MR. SHALABY: You are reading off a specific list
somewhere?
MR. POCH: No. I am just -- just my compilation.
MR. SHALABY: Yes. Cost of CDM, we do not have a good
handle on the cost of CDM delivery at this time to consider
cost uncertainty a big factor at this time.
MR. POCH: Right. But I think the LUEC of your CDM
portfolio is something like 2.9 cents or something, it’s
well below the alternative.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1611
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: It is.
MR. POCH: The uncertainty around its cost is not a big
factor for you to have to wrestle with in planning.
MR. SHALABY: That's not at this stage, no.
MR. POCH: Right.
Now, for combined heat and power, we have the same
issues as CDM, we have uncertainties about achievability and
timing, but also cost, I would suggest.
MR. SHALABY: Yes, yes.
MR. POCH: All right. And perhaps there's --
subcategories there. To the extent that combined heat and
power uses fuel that was otherwise going to be burned anyway
or captures waste heat, obviously cost is less on
uncertainty; is that fair?
MR. SHALABY: Obviously.
MR. POCH: The marginal cost is less uncertain.
MR. SHALABY: That hasn't proven to be necessarily
true.
MR. POCH: Could you just -- I was just saying
comparing the two parts of combined heat and power, the kind
where you are doing incremental fuel burning and the kind
where you're not, obviously there is fuel cost uncertainty
in the one situation and not in the other. That is my only
point I was making.
MR. SHALABY: No. I am not agreeing with that.
MR. POCH: All right. Could you explain why, when you
are just capturing waste heat from a process that’s already
in place, that the, there is --
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1621
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: The waste heat is generated by a primary
fuel of some sort.
MR. POCH: My question was posited in a situation where
that primary fuel is being burned anyway. By an industry
that is raising steam, they’re raising steam whether you go
and help put in a CHP plant there, or not.
MR. SHALABY: If it's going to happen anyway?
MR. POCH: Yes.
MR. SHALABY: Then your premise is correct.
MR. POCH: Right.
Renewable costs and timing are both uncertainties in
your plan? Renewable generation? Both costs and timing?
MR. SHALABY: Yes. But also performance and
incorporation into the grid --
MR. POCH: Right.
MR. SHALABY: -- particularly to do with wind.
MR. POCH: Would you agree the biggest timing concern
with respect to renewables is really the timing associated
with the transmission to incorporate them?
MR. SHALABY: Yes.
MR. POCH: All right. Load is obviously a big
uncertainty in your planning exercise, the level of load.
MR. SHALABY: Yes, yes.
MR. POCH: Would you agree that technology evolution,
for loads, for generation, for efficiency technologies, for
the grid, all of these things are -- add uncertainties?
MR. SHALABY: Yes.
MR. POCH: So would you agree with all of these
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1631
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
uncertainties? Flexibility -- I think you already said
this, but flexibility is really a key value and
appropriately a key value in your planning?
MR. SHALABY: Yes.
MR. POCH: And I’d just like to give you a few items
and see if we can agree about these items for -- would tend
to increase flexibility. As flexibility, your plan would
tend to increase if it has more of these, of components with
these attributes.
One, shorter lead time options would tend to add
flexibility.
MR. SHALABY: If they have other attributes that are
good, yes. So this is --
MR. POCH: In each case, take it as given I'm agreeing
with you --
MS. NOWINA: Mr. Poch, please don't interrupt Mr.
Shalaby when he is answering the question.
MR. POCH: Sure. Go ahead, Mr. Shalaby.
MR. SHALABY: So, it is -- agreeing to one dimension at
a time will have me come at the end and say: But the short
lead time, but they have a CO2 emissions.
MR. POCH: I'm agreeing with you, but --
MR. SHALABY: So the totality of the criteria, the
totality of the performance has to be kept in place.
MR. POCH: Of course.
MR. SHALABY: But to use a, the notion of everything
else being equal, short lead time is better than long lead
time.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1641
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: Take that as a given in each case. I’m not
disagreeing. So a shorter lead time adds flexibility
including lead times for approvals, for example.
MR. SHALABY: Yes.
MR. POCH: Shorter construction time options lead to
added flexibility.
MR. SHALABY: Yes.
MR. POCH: Smaller size of increment increases
flexibility?
MR. SHALABY: Yes.
MR. POCH: Avoidability of sunk cost which is a bit of
an overlap with those other things --
MR. SHALABY: That reduces the regret in a way, yes.
MR. POCH: Reduces flexibility? Because you can -- it
is not all sunk. You can walk away easier?
MR. SHALABY: Yes, right.
MR. POCH: Long-term load following ability. So
options that sort of automatically respond to, as load
changes on the horizon? Those would --
MR. SHALABY: Operating flexibility is a value, yes.
MR. POCH: I am thinking even on a planning time frame.
If you have options that are more available or less
available depending on what happens to load, that is a
natural hedge, in your plan.
MR. SHALABY: Yes.
MR. POCH: And then on an operating time frame, options
that diurnally and seasonally follow load would add, would
assist you?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1651
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Yes.
MR. POCH: All right.
All right. Now, I think it is pretty obvious where I
am going with some of that and I won't drag you through it
obviously. CDM enjoys many of those.
MR. SHALABY: Absolutely.
MR. POCH: Larger options like nuclear, I think we can
agree doesn't enjoy a lot of those, but as you have
indicated may have other attributes like its forecast cost
that persuade you to go for it.
MR. SHALABY: You use different options for different
purposes, yes.
MR. POCH: Yes. I just wanted to ask you a little bit
about combined heat and power. Can we agree that it does,
because it is a little bit unusual, it does have some of
those attributes about the ability to follow load on a
planning timeline and on a diurnal and seasonal operating
time frame, because it -- the opportunities for it tend to
be tied to the prevalence of loads, industrial loads, for
example, on the system?
MR. SHALABY: This is what option specifically now?
MR. POCH: I was looking at combined heat and power.
MR. SHALABY: Typically follows a steam load, yes.
MR. POCH: Hosted by a load, by a customer?
MR. SHALABY: Correct.
MR. POCH: So it naturally has those attributes.
MR. SHALABY: Yes.
MR. POCH: Okay. Now I would like to turn to
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1661
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
Exhibit D, tab 6, schedule 1, page 29.
And I am just reading from, under flexibility there,
starting on part-way through line 7, I think, is probably
the place:
"The larger unit capacities and relatively long
lead times for new build nuclear generation
inherently limit its flexibility. However,
planned flexibility exists in that provision is
made to accept additional conservation, renewable
and CHP resources to meet base-load requirements
should these be feasible. There is also
flexibility to accept new build nuclear base-load
resources earlier than assumed in the plan."
Can I sum up by saying that the recent addition that
you have made to the committed column for your nuclear, in
keeping with that paragraph and the discussion we just had,
tends to reduce plan flexibility?
MR. SHALABY: I am not sure I agree with that. I mean
it introduces the amounts of resources that we're planning
for, but does it reduce plan flexibility? Does it reduce
the ability to accept more conservation? I don't think so.
MR. POCH: All right. Okay. I had taken -- read you a
paragraph because it was about base-load requirements,
suggesting that -- it spoke to the very question.
MR. SHALABY: If base-load conservation, next time
we're here in the period of time is larger than we project
at this time, the requirements of base-load would be fewer.
If CHP is submitted to be larger, the estimates for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1671
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
base-load requirements would be lower.
MR. POCH: I am going to move on.
MR. SHALABY: Yes.
MR. POCH: Just on this question of flexibility. If
you could turn to Exhibit B, tab 1, schedule 1, at page 8.
This is your updated, your update exhibit, if you will.
At line 20 there, you say:
"This is a time of great uncertainty. With
significant forces affecting the demand forecast,
the current ambiguity in determining the
explanation for current demand levels affects
long-term estimates, as well. This shows the need
to plan to a range or band of forecasts and not
focus on a single set of numbers. The OPA will be
monitoring over the next few years activities
related to the above factors and will adjust its
planning assumptions when more clarity is gained."
First of all, I take it that you're saying that the
need for flexibility has increased?
MR. SHALABY: It's at a premium. It has always been
there, and we're highlighting yet another reason to retain
flexibility.
MR. POCH: It's increased since you drew the plan.
This is telling us the need for flexibility has increased.
MR. SHALABY: The uncertainty in economic conditions in
Ontario has become more evident.
MR. POCH: Yes.
MR. SHALABY: But the forecasters always knew that;
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1681
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
just the Globe and Mail now knows that.
MR. POCH: Well, I thought that -- it is citing, for
example, this current ambiguity which didn't exist before,
so there is a new found need for flexibility on your part;
is that not the case?
MR. PIETREWICZ: I think, if I can just state, the IPSP
itself I think recognizes the potential to have futures that
exhibit different load, whether as a result of different
amounts of conservation or due to fundamental economic
drivers for the load.
So I am not sure that what is being described here in
B-1-1 is necessarily distinct or outside of that recognition
that the IPSP already makes, and that's why the IPSP is
developed in the face of uncertainty and examines a variety
of scenarios, including scenarios of higher demand growth
and scenarios of greater success in achieving conservation
potential.
MR. POCH: All right.
I think what you just said to me is you viewed the plan
as sufficiently flexible to accommodate the kind of
uncertainty that is being discussed in that paragraph; is
that correct?
MR. SHALABY: Yes.
MR. POCH: All right. And I think I asked you just a
moment ago whether the new commitment that you have in your
plan on nuclear made the plan less flexible, and I am not
sure you agreed with me.
MR. SHALABY: We're not making a new commitment. We
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1691
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
are considering these resources to being -- these options of
being developed by others.
MR. POCH: The fact of this commitment as you perceive
it?
MR. SHALABY: Yes, the fact that other people are
pursuing options does not limit flexibility. It increases
flexibility. It increases the number of options open to
Ontario. That's the way we see pursuit of options is a good
thing. It's not a limiting thing.
MR. POCH: You have said that -- you said I think in
your oral evidence earlier that one of the roles of the plan
and of this Board's -- this discussion and the Board's
report will be that variety of stakeholders in industries
and institutions will be -- will take their lead from this;
is that fair?
MR. SHALABY: Will take?
MR. POCH: Will take their lead from this.
MR. SHALABY: Yes.
MR. POCH: All right.
MR. SHALABY: They will interpret the plan in ways that
will inform their business decisions.
MR. POCH: They have taken -- in fact, some presumably
have already taken their lead just from the tabling of your
plan, including the government, presumably?
MR. SHALABY: To some extent, yes.
MR. POCH: All right.
Indeed, if the government goes ahead and does in fact
proceed with all of these nuclear commitments, as you have
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1701
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
styled them, having placed some reliance on your advice, and
if load does not materialize as forecast, as we heard some
evidence might be the case, as we have discussed, isn't it
clear that we run the risk that the nuclear, to the extent
it is actually committed to, to go ahead and rely on what
you say - it's a good idea, let's sign some contracts -
that's going to then prevail at the margin against other
options?
MR. SHALABY: Once the decisions are made, yes, they do
now dictate what the future options are and the future
opportunities are.
MR. POCH: We are already seeing that with the
contracts that you have signed with Bruce for refurbishment.
There are penalty clauses in there for access to
transmission, and so it is incumbent upon you now to reserve
that transmission, the limited transmission there is, for
them until such time as you can -- somebody can add more;
correct? It prevails, because there is a contract. There
is a cost.
MR. SHALABY: I am not sure what the reference is to
the previous discussion. I mean, that's -- the parallel
between this question and the previous one is --
MR. POCH: You placed an orange zone over some
renewable development until transmission gets added coming
out of Bruce?
MR. SHALABY: Right.
MR. POCH: In the interim, it is Bruce that gets access
to that transmission, because they have a contract that says
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1711
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
if they don't, they're going to pay a penalty?
MR. SHALABY: Yes.
MR. POCH: Right? Okay.
And another place that this kind of competition gets
set up is with respect to -- between nuclear and between
efficiency and renewables is due to any constraint that
arises because of surplus base-load generation; correct?
MR. SHALABY: You mean conservation and nuclear?
MR. POCH: Between renewables and conservation on the
one hand, and nuclear on the other. You have to commit a
bunch of nuclear. It is actually committed.
It's not easy to manoeuvre. You have times during the
year when you have got more generation that isn't
manoeuvrable on the system than load, and that is called
surplus base-load generation; correct?
MR. SHALABY: Yes.
MR. POCH: So the more nuclear you have committed, the
more times there is going to be a competition between -- if
you will, between -- there is more of a constraint on your
pursuit of other options that would add to that problem?
MR. SHALABY: I will accept that, yes.
MR. PIETREWICZ: I would add that perhaps it is a
little more subtle than that. This competition that you
speak of would depend on things such as what the load is,
what types of actions could be taken, such as outages closer
to the real time frame, what kind of technologies were in
place on the system at the time.
So I am not sure that it is necessarily as you
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1721
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
describe, but it is more context dependent.
MR. POCH: I promise you we will come back to discuss
it in more detail. I am just identifying that as an area
where there is a potential competition for space, as it
were.
Okay. Then another kind of uncertainty is with respect
to escalation in your forecast -- forecasts, cost
escalation.
There are differences in the degree of cost uncertainty
as between options? Some have fuel price risks? Others are
more exposed to capital cost escalation?
MR. SHALABY: That's correct.
MR. POCH: Is it fair to say that energy efficiency
seems to share that pressure less? I am going to actually
-- well, first of all, let me see if you agree with the
general proposition that it is a little less susceptible to
that.
MR. SHALABY: I suspect you are right. I don't have a
basis for that, other than it's not a mega project and it's
not competing for the resources that are pushing
construction costs up.
MR. POCH: Okay. In K2.1 I have included something
that just happened across my desk the other day. It's the
page 2 of K2.1, which is our cross exhibit.
You don't really need to read it. It's an ad for what
they're calling a smart UPS, uninterruptible power supply,
the kind that a number of us -- probably most of us have,
protecting our computers from the unreliability of the grid.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1731
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
No offence intended.
Now, this is a new product that has just hit the
market, as I read, where the machine is smart enough to
sense the load on the main outlet that you plug your
computer into, and when that load drops enough because your
computer has gone asleep or you turned it off, it
automatically then switches off all of the other outlets for
all of your plug-in peripherals.
Do you understand what the technology purports to do?
MR. SHALABY: Generally speaking, yes.
MR. POCH: All right. I am not going to query you on
its potential or anything. I know it is not your panel.
MR. SHALABY: I understand.
MR. POCH: But it struck me that this is a good example
of how energy efficiency can often largely be about
innovation as opposed to, you know, building more stuff with
concrete and steel.
MR. SHALABY: Energy efficiency is indeed about
innovation, yes.
MR. POCH: Would you agree, in this one, the ad there,
they make the point of saying it is the same price as the
old one and it will save you 40 bucks in power over whatever
period. It hardly matters.
Would you agree that we're not witnessing a significant
escalation for a number of these kinds of technologies that
offer efficiencies? LCD screens are getting cheaper, not
more expensive.
MR. SHALABY: Correct.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1741
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. POCH: All right. And we saw --
MR. SHALABY: Everybody has a number on them, yes. As
a result, people have more than one.
MR. POCH: Hmm-hmm.
Last time you and I did this dance, Mr. Shalaby,
compact fluorescents were I think about 25 bucks a pop in
1989 dollars, and today they're probably about two and a
half dollars in 2008 dollars so they have come down about,
oh, 95 percent.
MR. SHALABY: Correct.
MR. POCH: So I think you have already agreed
escalation may be less a factor for energy efficiency.
Would you agree it is indeed we're likely to see some de-
escalation?
MR. SHALABY: In some technologies and some
applications, yes.
MR. POCH: Now, would you agree that copper, steel and
concrete, these inputs into generation resources have
experienced some significant escalation of late?
MR. SHALABY: Yes.
MR. POCH: That's kinds of an increasing concern for
-- I am sure for system planners; correct?
MR. SHALABY: That is -- I didn't hear the last part.
MR. POCH: Increasing concern for system planners.
MR. SHALABY: It is concern for people developing
generation projects and planners as well, yes.
MR. POCH: So would you agree that from a planning
protocol perspective, it might be appropriate that while,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1751
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
you know, while acknowledging -- I readily acknowledge it is
difficult to forecast escalation, would you agree it might
be reasonable to give some credit to options that are less
exposed to escalation risks?
MR. SHALABY: Yes.
MR. POCH: Okay.
MR. SHALABY: If it is conservation technologies that
you are referring to, they are the first directive priority
that we talked about, they're being pursued to the maximum
that we can place confidence in at this stage and would be
pursued beyond that. And as our confidence develops, they
will be updated.
So you have no argument at all that conservation is the
very best option to pursue.
MR. POCH: Would you agree it might be appropriate not
just to give it priority in development ranking, which you
indicate you have, but that it might be appropriate to give
it credit relative to other options? I am talking dollar
credit.
MR. SHALABY: The dollar credits will not change its
contribution in this plan, in that we’ve colloquially been
saying we're going to take all of the conservation we can
identify, all of the conservation that we can rely on at
this time. And the dollars is not a barrier at this time.
There is a huge advantage to conservation at this time.
MR. POCH: All of the costs we speak about, your
supply-side costs, are the input to the avoided costs
against which conservation measures get tested; correct?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1761
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: For reference, yes.
MR. POCH: That's what the planners and the delivery
people and the people in the field in some cases use when
they administer the TRC test which this Board, in its other
hearings, has heard too much about; right?
MR. SHALABY: Yes.
MR. POCH: All right.
So when the architect is deciding to specify how much
insulation to specify for a building, and he's having regard
to your program guidelines, what you will give your rebate
for or some design assistance or whatever, all of that is
going to be in the context of rules for a program or program
design that's had regard to that TRC test to have those
avoided costs; correct?
MR. SHALABY: You know well that these incentives do
not have very much to do with the TRC test.
MR. POCH: Fine. But the items that qualify do. How
much insulation you can add is going to be limited by when
it turns TRC negative.
MR. SHALABY: As counsel reaches for the button, I
suspect we are getting into a level of detail that a
subsequent panel will be better able to deal with.
MR. VEGH: Thank you, Mr. Shalaby.
MR. POCH: Let's take it as a given, then, and I will
confirm this with your conservation panel that either in the
delivery, the design or operation of conservation programs,
the depth of efficiency that gets applied in a give
situation or the number of measures or the type of measures,
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1771
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
or whatever, they bump into the limits of the avoided costs.
MR. SHALABY: actually – actually, that is not my
recollection. Very little bumps against the TRC. Very few
options are expensive enough, as expensive as supply.
Typically, most of the conservation is lower cost than
supply.
MR. POCH: I will take that up with the other panel.
MR. SHALABY: Right.
MR. POCH: To the extent anything does bump into that
limit, then the costing that you have put on, of your
various supply options and whether you credit more flexible
options against -- give it a credit or demerit in the
costing, would ultimately affect how much a consumer gets.
MR. SHALABY: Yes. To the extent there are some
options constrained by cost comparison, that would be --
that limit would be raised. But the practical experience is
there is very little of that, if any.
MR. POCH: All right.
Now, just in terms of that, if you could just turn back
to Exhibit K2.1, page 3. I guess it is page 4. It's the
page that has a chart showing -- entitled: "actual versus
predicted demand for electricity in Ontario, 1975 to 2010."
You have already brought to our attention that the
little bit on the right-hand bottom of that chart where you
are showing the -- in your exhibits you have shown how the
recent load has dropped now below your -- both your load
forecast and it's below your -- below the scenario that is
your high conservation or low load scenario as well; right?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1781
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Yes, yes.
MR. POCH: It is outside of the bounds that you did
sensitivity testing for?
MR. SHALABY: Yes.
MR. POCH: We just laid on here a couple of other
things. One is the little extra red line which is the
IESO's 2008 prediction they're predicting a trend that's
continuing. Correct?
MR. SHALABY: Subject to confirmation. I am assuming
you are transcribing this right, yes.
MR. PIETREWICZ: Just for clarity. I want to make sure
we haven't misspoke.
The forecast illustrated on this slide, I understand,
are the OPA reference forecasts. The reference and the low
reference forecast not yet inclusive of the contributions of
conservation.
MR. POCH: Yes. Then the --
MR. SHALABY: That comment applies to comparing
forecast to actuals. actuals are after conservation.
MR. POCH: Hmm-hmm.
MR. SHALABY: Forecasts, we better be clear whether it
is before or after conservation.
MR. POCH: Right, right. We will certainly check. I
think you are reading the label correctly.
MR. PIETREWICZ: Thank you.
MR. POCH: The other thing we overlaid on here, though,
in fact just on that point I take it your own evidence, you
filed material in B-1-1 which treats that correctly. We can
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1791
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
look to that if we want to see and make sure we have it
accurate so nothing turns on that part of this graph here.
The other thing we overlaid are these two points which
were the predicted high case and predicted low case in the
balance of power, the DSP exercise.
Do you recall that, Mr. Shalaby?
MR. SHALABY: Yes. Those points are before
conservation.
MR. POCH: Oh, okay.
MR. SHALABY: So after conservation, which is the right
comparator to what actually happens, is a better comparator.
MR. POCH: Can you provide us with that, what the DSP
10 percent likelihood low and high points were, after
conservation?
MR. SHALABY: I don't know that I have the documents
handy, but they're -- I can if it is relevant and useful.
MR. POCH: Conservation wasn't as nearly as big a term
in that plan as it is in this plan.
MR. SHALABY: Conservation programs may or may not have
been, but conservation, as in the productivity of the
economy and productivity of use of electricity, is a
different matter.
MR. POCH: That kind of conservation was in the load
forecast at that time; correct?
MR. SHALABY: Was -- did not get forecasted right.
MR. POCH: Right. So my point is, then, that then this
graph is fine, that those points are the 10 percent for the
load forecast exclusive of utility conservation, let's put
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1801
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
it that way?
MR. SHALABY: Yes.
MR. POCH: And --
MR. SHALABY: My recollection if you move the range
down a bit, then the actual observed is within the 10 to
90 percent, towards the lower probability.
MR. POCH: Right.
MR. SHALABY: But within 10 to 90. The point is the
same.
MR. POCH: Around your 10 percent likelihood mark?
MR. SHALABY: It's towards the lower probability, yes.
MR. POCH: Okay. All right.
And that was -- you and I both recall that plan was
withdrawn before the hearing even concluded, because that
was already unfolding, wasn't it?
MR. SHALABY: Yes.
MR. POCH: And the current plan, is it fair to say that
the plan was built -- I heard what you said with an emphasis
on flexibility, but it was built around the central forecast
that is your central load -- your reference load forecast?
MR. SHALABY: Reference, yes.
MR. POCH: Yes. Then you did this -- you had an
A plan and a B plan, depending on what happens with
Pickering?
MR. SHALABY: Yes.
MR. POCH: And the other plans that you have offered
-- the other cases you offered, I should say, in your
language, case 2A and B, for example, is for higher assumed
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1811
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
load growth, and 3A and B is for higher conservation, and 4
has to do with transmission.
In G-1-1 you have said you have done this to see what
possible plan adjustments -- to see that possible plan
adjustments can meet these cases; is that fair?
MR. SHALABY: Yes.
MR. POCH: All right. And so these are not entirely
new plans?
MR. SHALABY: It's a single plan.
MR. POCH: It's a single plan.
MR. POCH: Different conditions.
MR. POCH: You didn't optimize those other ones for a
particular alternative load forecast. You were simply
saying, If we have a change in load or we have a change in
one of these other factors, we're just going to test how the
single plan would respond and see that it could respond?
MR. SHALABY: Yes.
MR. POCH: Okay.
MR. PIETREWICZ: Recognizing that the more sort of
optimized, in quotes, or more detailed assessments would
follow.
MR. POCH: Right. You didn't do cost assessments of
these alternatives? You only did that in the main plan --
of the plan, let's say?
MR. SHALABY: Yes, the reference case.
MR. POCH: So in that sense, your testing of robustness
is not tested for how -- how costs might change
significantly or not.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1821
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: We did not describe those results. You
are correct.
MR. POCH: All right.
Now, you certainly didn't start with a range of futures
and develop a range of plans and test to find some kind of
-- well, let me back up.
I am aware that -- and correct me if I'm wrong. You
will certainly be more aware than I am. I think an example
is that the Pacific Northwest Power Planning Council, which
I think has a new name now, does an exercise where they --
they put probability bounds around virtually every
significant input into their plan.
I know you have done that on your reserve insurance
modelling, but they do it throughout their planning
exercise, and they must have a supercomputer or something,
because there must be thousands of permutations and
combinations, and they come up with a curve of costs and
risks and they look for the minimum point.
You haven't attempted anything like that kind of...
MR. SHALABY: I am not sure what they do, but we
haven't attempted cost minimization in the way of searching
for it amongst 1,000 alternatives.
We think we have reached cost minimization by choosing
the low cost option at the fork in the road when there is a
choice. We demonstrated the five forks in the road, that
there are choices, and if you make the right choices along
the way, you arrive at a low cost option.
MR. POCH: I understand. But they don't just look for
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1831
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
the lowest cost plan give our best estimate today. They
look at the lowest cost plan given a range of possible
futures, and then count -- they look for the lowest combined
cost and risk of cost of plan, which is not synonymous with
the lowest cost plan, given our --
MR. SHALABY: We have done estimates of this in the
supply mix advice work, and we have done estimates of this
in determining the base-load requirements, for example.
We have done estimates of viability and uncertainty in
cost.
MR. POCH: You did the probability that you -- as I
think I mentioned, you did that -- in your reserve
insurance, you have a probability scatter. And you have
done that, I think, in your -- you did a deterministic and a
probabilistic assessment of the crossover in gas and
nuclear, another point you did?
MR. SHALABY: Yes.
MR. POCH: But you didn't do it for a range of planned
futures and load futures, and what have you?
MR. SHALABY: We actually did. In the planned cost
section, we have a probabilistic range in costs.
MR. POCH: I guess I may not be making myself clear.
I think you may have already agreed to this. I
apologize if I am repeating myself, but you haven't done an
exercise where you posited a range of different potential
futures, developed a range of plans for those different
futures, and then did this kind of, you know, multivariate
stochastic analysis?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1841
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: At the earlier stage of the supply mix.
MR. POCH: Oh, you did?
MR. SHALABY: Yes. We have two scenarios in the supply
mix. They are different enough, variable enough.
MR. POCH: Then you haven't done that at this stage?
MR. SHALABY: Because the distinctions are small. We
developed a single plan that meets the requirements, yes.
MR. POCH: Now --
MS. NOWINA: Mr. Poch, how close are you to wrapping up
this bit of questioning?
MR. POCH: I have about another, oh, four or five
minutes on this section. I can break if you would prefer.
MS. NOWINA: Well, if you could complete it in four or
five minutes, that would probably make sense.
MR. POCH: Okay.
We have a little bit of mis-history, don't we, Mr.
Shalaby? In the past Ontario Hydro, we have seen they did
up a forecast base plan, a central line forecast, and would
you agree that in the end they've -- they built Darlington,
load fell away. They had to resort to things like special
discounted rates to sell off excess power or encourage
selling off excess power, and they all about withdrew from
conservation in response. That's the history?
MR. SHALABY: That's -- some of those facts are
certainly true.
MR. POCH: All right. With the benefit of 20/20
hindsight, a lot of DSM was foregone that would have been
cheaper than the Darlington costs turned out to be. Had we
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1851
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
been able to, at the time, have foresight, that would have
been DSM that was cheaper than Darlington turned out to cost
as an alternative?
MR. SHALABY: If you could project that to do something
cheaper than what you have done already, then what you are
concluding is correct, yes.
MR. POCH: All right. But at the time Darlington was
committed to, there was uncertainty about the cost potential
and achievability of CDM, and there was an estimate for
Darlington costs that was a fraction of its eventual costs.
That's what got us into that mess?
MR. SHALABY: That's part of the record, as well.
MR. POCH: All right.
MR. SHALABY: I am not accepting the description of
"mess".
MR. POCH: Got us to that point in reality, let's put
it that way. Fair enough.
Now, I just had one other little point here on
conservation. If we're looking at the difference between
those options, a megawatt of efficiency is not equivalent to
a megawatt of supply, right, because of the difference in,
for example, losses, especially peak losses?
MR. SHALABY: It can be adjusted. I mean, it depends
on a lot of things, but a megawatt is not a megawatt.
MR. POCH: Right, because a megawatt of conservation
avoids the losses of getting the generation to the end --
MR. SHALABY: It depends on whether it is coincident
with peak or not. Is it sustainable over a period of time
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1861
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
or not, and so on?
MR. POCH: To the extent it is coincident with peak,
obviously it has much greater value in that?
MR. SHALABY: If it's sustainable over 20 years, it has
a value the same as generation.
MR. POCH: Same is true of self generation that is co-
located with load?
MR. SHALABY: It has benefits in terms of losses, yes.
MR. POCH: Similarly, with respect to reserve, both of
those options have the ability -- they're small and
dispersed and located with load. They reduce your reserve
requirements?
MR. SHALABY: Right, yes.
MR. POCH: Planning reserve requirements. Okay. Just
to close, then, my experts have advised me, and they filed
their reports, that there is some perhaps 6,000 megawatts of
CDM that they believe is reasonable to plan on over the life
of this plan, beyond what you are planning on.
And Mr. Caston has suggested there is more than that
potential for CHP, there's been difficulties getting it,
absolutely, but if half of that is available we're up at
12,000 megawatts between those two and if we can avoid peak
losses at 20 percent rate, we're at a nice number of 14,000
megawatts just for a little resonance here.
If -- I know you are not going to readily accept those
numbers are achievable, but it is perfectly clear if those
kinds of numbers are achievable, your plan right now
couldn’t accommodate it, could it?
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1871
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
MR. SHALABY: Additional 14,000.
MR. POCH: Additional 14,000 megawatts.
MR. SHALABY: No.
MR. POCH: No, okay. Thank you, Madam Chair, I am just
about to move to interpretation of the directives and the
Reg and that is a good place to stop.
PROCEDURAL MATTERS:
MS. NOWINA: All right. Thank you. Before we leave,
Mr. Poch I have been thinking about the exchange between you
and Mr. Shalaby before the break. It was less than optimal
in my consideration for, in terms of helping the Board and
it didn't make me happy. We're going to be here together
for a long time and I thought I might indicate what might
make me happy, in future exchanges.
First, perhaps you could ask fewer leading questions or
ask more positive questions as opposed to the negative. For
example, such and such happened, didn’t it, or you didn't do
this. You might just ask what the OPA did do.
And I guess between both yourself and the witness,
please don't interrupt each other. Especially give the
witness time to pull their thoughts together, and if they
need to add a phrase afterwards, let's have enough of a
pause to know whether or not the witness would like to do
that.
And sometimes you would ask a question, and as
Mr. Shalaby started to give his answer, you would jump in
and give further explanation to your question. I don't
think you needed to do that. That may have been helping him
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1881
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345
more than you needed to and you could let him finish the
question.
So I think if you thought about those things, perhaps
tomorrow might go a little bit more smoothly and the rest of
our many days together.
MR. POCH: Thank you, Madam Chair. I will certainly
make best efforts. I admit to being -- pressuring myself,
watching the clock and maybe a little too much and not being
optimal in my pacing there.
MS. NOWINA: You are more or less first up and so my
directions to you are the same to everyone else as we go
forward.
Mr. Vegh, I had a question of you. We have been going
with 15 minute breaks. Is that working for your witnesses?
Is it long enough for your witnesses? You are not allowed
to talk to them. Witnesses, speaking for yourself and
colleagues going forward, is that workable for you?
MR. SHALABY: I think it is workable, yes. At this
pace it is workable. As long as we go home at 4:30, that's
good.
MS. NOWINA: We are trying to do that.
MR. SHALABY: Yes.
MS. NOWINA: We will try to maintain that. It is
efficient. I do like the hour-and-a-half for lunch because
I think it gives everyone the opportunity to get something
in between. Thank you very much.
We are now adjourned until 9 o'clock tomorrow morning.
--- Whereupon hearing adjourned at 4:40 p.m.
ASAP Reporting Services Inc.(613) 564-2727 (416) 861-8720
1891
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
282345