06_dilg_salintubig - design guidelines for water supply system

Upload: tarhata-m-pantao-kalim

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    1/23

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    2/23

    SPRING BOX DESIGN: The appropriate type of intake box suitable for the

    spring is selected from the Standard Type of Springs, depending upon the actual condition in the

    field.

    Spring box should be provided with adequateoverflow pipe so as not to damage the spring box intimes where the spring discharge increases due toexcessive rains or where the aquifer level isfluctuating.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    3/23

    SPRING BOXDESIGN 1:

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    4/23

    SPRING BOXDESIGN 2:

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    5/23

    TYPICAL WELL DESIGN:

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    6/23

    SELECTION OF CASING DIAMETER:

    Maximum discharge rate for certain diameters

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    7/23

    PUMP DESIGN:

    Pump size should be determined byWell Yield

    Number of Operating Hours

    Fill and Draw or Float System

    Hydraulic Zones

    Delivery Pressures

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    8/23

    Determination of Pump Discharge:

    If the pump is used directly to supply water to the distribution system, the capacitymust be equal to PHD

    If the water distribution system has areservoir, the pump capacity must be equalto MDD

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    9/23

    Pump Selection:

    Centrifugal Pumps , If TDH = < 6 meters

    Jet Pumps, If TDH = 6 to 20 meters

    Submersible Pumps, If TDH = > 20 meters

    TDH is the sum of the depth of pumping water

    level + maximum reservoir elevation + frictionlosses

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    10/23

    Calculate Pump Capacity:

    Power (Kw) = 9.8 x (1/eff) x Q x TDH

    Power (HP) = Kw/0.746

    Where:

    Q = Discharge (cms)TDH = Total Dynamic Head (m)eff = Pump Efficiency

    Pump Efficiency:

    Centrifugal Pump:

    30 60%

    Jetmatic Pump:20 30%

    Submersible Pump:50 60%

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    11/23

    DESIGN OF RESERVOIR:

    Reservoirs are employed in the distribution system tomeet the peak demand (if water source is available), toequalize pressure and to store water.

    The elevation of the bottom tank is computed to be atleast equal to but preferably higher than the elevation of the farthest and highest tap in the system plus theminimum pressure head plus the total head losses fromthe point up to source.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    12/23

    Reservoir Design Procedure :

    Location of the Reservoir It should be located, if possible at the elevated places and or central to thedistr ibution system, for economic reason.

    Calculate Reservoir CapacityThe capacity should not be more than the necessary to supplement the

    ADD to the system during times of peak demand.Rule of thumb = Reservoir capacity should be at least 25% of ADD

    Determine type of Reservoir It maybe Elevated or Ground Level Reservoi r type. The volume of storage,

    location, material and choice of type of reservoir depend primarily on costand what is available.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    13/23

    PIPELINE DESIGN:

    In applying the design minimum requirements for the design of pipeline,

    the following should be considered:

    It must be designed to handle the PHD of the service area

    The minimum Pressure at the remotest end of the system (tap stand

    or communal faucet) shall not be less than 2.0 meters

    The pipeline must be designed considering that the Maximum

    Velocity in the pipe is 3m/s for main pipes and distribution pipes.

    Ensure that there is no negative hydraulic gradient or negative

    pressure in the pipelines.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    14/23

    Pipeline Design Procedure:

    Calculate the flows in the laterals and main pipes using the

    PHD

    Calculate pipe diameters corresponding to the pipe flow using

    the Hazen-Williams Equation Formula

    Check Maximum Velocity in pipe should not be 3 m/s

    Check Headloss due to friction

    Choose appropriate route to the storage reservoir or to thedistribution system and add the losses of all sections along

    the route to get the total head loss.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    15/23

    Pipeline Design Procedure:

    Compute losses such that the pressures at the reservoir and at the

    distr ibution system meet the design cri teria. If pressure are to high

    reduce the size of the pipe.

    If losses are too large, the reservoir may be too high or the pump

    required may be large, redesign the pipelines using larger diameters

    until the losses are reasonable.

    Determine the location of the valves, fitt ings, etc. Normally air release

    valves are located at the peak and sag port ion along the pipeline.

    Blow-offs should be located at end points or lowest point. If possible

    blow-offs should be near the drainage outfall.

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    16/23

    Hazens William Formula:

    hL= 10.667 x Q^1.852

    x L

    C^ 1.852 x D^ 4.87

    Where:

    Q = flow in cmsL = Length in m

    C = Friction CoefficientD = Diameter in meters

    Recommended Pipe C Values(New Pipes)

    Pipe Material DiameterRecommended

    C-Values

    Plastic> 300 mm 150

    < 300 mm 140

    Iron> 300 mm 140

    < 300 mm 130

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    17/23

    EXAMPLE 1

    Barangay A100 HH

    Barangay B120 HH

    Barangay C80 HH

    Barangay E350 HH

    Barangay F400 HH

    Barangay D200 HH

    Proposed Source 2 - aDeep WellConfirmed yield, 10 lps

    Proposed Source 1Spring, 12 km awayConfirmed yield, 20 lps

    Proposed Source 2 - bDeep WellConfirmed yield, 8 lps

    reservoir

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    18/23

    EXAMPLE 1

    No ROW problem anticipated All identified water sources have confirmed yields, and of acceptable water qualityWater rights can be secured by LGUWater source site are free from environmental and socialconstraints

    Proposed Service Area, 5 Barangays(# OF PAX/HH =5.5)

    A 550 pax 100 HHB 660 120C 440 80D 1,100 200E 1,925 350F 2,200 400

    Proposed Water Sources:

    1. Spring5 kms awaysufficient elevationconfirmed yield, 20 lps

    2. Groundwater Well no. 1 10 lps, 50 m away

    Well no. 2 8 lps, 250 m

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    19/23

    EXAMPLE 1

    Population Projections

    Water Demand:at 110 liters/cap/dayadd 30% non-revenue water

    BarangayName Population Households Population Households Population Households Population Households

    A 550 100 584 106 629 114 638 116B 660 120 701 127 755 137 766 139C 440 80 467 85 503 91 510 93D 1,100 200 1,168 212 1,258 229 1,276 232E 1,925 350 2,044 372 2,202 400 2,233 406F 2,200 400 2,336 425 2,516 457 2,552 464

    TOTAL 6,875 1,250 7,300 1,327 7,863 1,430 7,975 1,450

    Year 1 Year 5 Year 10 Year 15

    Water Demand Projection (lps)BarangayName

    A 0.91 0.97 1.04 1.06

    B 1.09 1.16 1.25 1.27C 0.73 0.77 0.83 0.84D 1.82 1.93 2.08 2.11E 3.19 3.38 3.64 3.70F 3.64 3.87 4.16 4.22

    TOTAL 11.38 12.08 13.01 13.20

    151 5 10

    Growth Rate:Year 5 = 1.21%Year 10 = 1.35%Year 15 = 0.99%

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    20/23

    EXAMPLE 1

    Key Questions (1/2)

    How many barangays would be servedSocial/politicalWater source availabilityCost constraint

    Would the source be sufficient to supply thedemand

    First year, immediate and long-terms (design

    horizon)Most advantageous source option (groundwater,spring or combination)

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    21/23

    EXAMPLE 1

    Key Questions (2/2)

    Development PlanStaged implementation or full implementationCost requirement (consider source option)

    Investment CostOperation and Maintenance Cost

    Probable water tariff

    Financial & Economic IndicatorsWillingness-to-connect and willingness-to-pay

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    22/23

    EXAMPLE 1

    Other Considerations

    Reservoir RequirementsMaybe needed to provide supplemental flowduring peak periods

    Or simply to balance pressures during peakflowsNormally sized at 20% to 30% of the averageday demandShould consider fill-and-draw systems or float systems

  • 7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System

    23/23

    END OF PRESENTATION