06_dilg_salintubig - design guidelines for water supply system
TRANSCRIPT
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
1/23
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
2/23
SPRING BOX DESIGN: The appropriate type of intake box suitable for the
spring is selected from the Standard Type of Springs, depending upon the actual condition in the
field.
Spring box should be provided with adequateoverflow pipe so as not to damage the spring box intimes where the spring discharge increases due toexcessive rains or where the aquifer level isfluctuating.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
3/23
SPRING BOXDESIGN 1:
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
4/23
SPRING BOXDESIGN 2:
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
5/23
TYPICAL WELL DESIGN:
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
6/23
SELECTION OF CASING DIAMETER:
Maximum discharge rate for certain diameters
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
7/23
PUMP DESIGN:
Pump size should be determined byWell Yield
Number of Operating Hours
Fill and Draw or Float System
Hydraulic Zones
Delivery Pressures
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
8/23
Determination of Pump Discharge:
If the pump is used directly to supply water to the distribution system, the capacitymust be equal to PHD
If the water distribution system has areservoir, the pump capacity must be equalto MDD
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
9/23
Pump Selection:
Centrifugal Pumps , If TDH = < 6 meters
Jet Pumps, If TDH = 6 to 20 meters
Submersible Pumps, If TDH = > 20 meters
TDH is the sum of the depth of pumping water
level + maximum reservoir elevation + frictionlosses
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
10/23
Calculate Pump Capacity:
Power (Kw) = 9.8 x (1/eff) x Q x TDH
Power (HP) = Kw/0.746
Where:
Q = Discharge (cms)TDH = Total Dynamic Head (m)eff = Pump Efficiency
Pump Efficiency:
Centrifugal Pump:
30 60%
Jetmatic Pump:20 30%
Submersible Pump:50 60%
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
11/23
DESIGN OF RESERVOIR:
Reservoirs are employed in the distribution system tomeet the peak demand (if water source is available), toequalize pressure and to store water.
The elevation of the bottom tank is computed to be atleast equal to but preferably higher than the elevation of the farthest and highest tap in the system plus theminimum pressure head plus the total head losses fromthe point up to source.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
12/23
Reservoir Design Procedure :
Location of the Reservoir It should be located, if possible at the elevated places and or central to thedistr ibution system, for economic reason.
Calculate Reservoir CapacityThe capacity should not be more than the necessary to supplement the
ADD to the system during times of peak demand.Rule of thumb = Reservoir capacity should be at least 25% of ADD
Determine type of Reservoir It maybe Elevated or Ground Level Reservoi r type. The volume of storage,
location, material and choice of type of reservoir depend primarily on costand what is available.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
13/23
PIPELINE DESIGN:
In applying the design minimum requirements for the design of pipeline,
the following should be considered:
It must be designed to handle the PHD of the service area
The minimum Pressure at the remotest end of the system (tap stand
or communal faucet) shall not be less than 2.0 meters
The pipeline must be designed considering that the Maximum
Velocity in the pipe is 3m/s for main pipes and distribution pipes.
Ensure that there is no negative hydraulic gradient or negative
pressure in the pipelines.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
14/23
Pipeline Design Procedure:
Calculate the flows in the laterals and main pipes using the
PHD
Calculate pipe diameters corresponding to the pipe flow using
the Hazen-Williams Equation Formula
Check Maximum Velocity in pipe should not be 3 m/s
Check Headloss due to friction
Choose appropriate route to the storage reservoir or to thedistribution system and add the losses of all sections along
the route to get the total head loss.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
15/23
Pipeline Design Procedure:
Compute losses such that the pressures at the reservoir and at the
distr ibution system meet the design cri teria. If pressure are to high
reduce the size of the pipe.
If losses are too large, the reservoir may be too high or the pump
required may be large, redesign the pipelines using larger diameters
until the losses are reasonable.
Determine the location of the valves, fitt ings, etc. Normally air release
valves are located at the peak and sag port ion along the pipeline.
Blow-offs should be located at end points or lowest point. If possible
blow-offs should be near the drainage outfall.
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
16/23
Hazens William Formula:
hL= 10.667 x Q^1.852
x L
C^ 1.852 x D^ 4.87
Where:
Q = flow in cmsL = Length in m
C = Friction CoefficientD = Diameter in meters
Recommended Pipe C Values(New Pipes)
Pipe Material DiameterRecommended
C-Values
Plastic> 300 mm 150
< 300 mm 140
Iron> 300 mm 140
< 300 mm 130
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
17/23
EXAMPLE 1
Barangay A100 HH
Barangay B120 HH
Barangay C80 HH
Barangay E350 HH
Barangay F400 HH
Barangay D200 HH
Proposed Source 2 - aDeep WellConfirmed yield, 10 lps
Proposed Source 1Spring, 12 km awayConfirmed yield, 20 lps
Proposed Source 2 - bDeep WellConfirmed yield, 8 lps
reservoir
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
18/23
EXAMPLE 1
No ROW problem anticipated All identified water sources have confirmed yields, and of acceptable water qualityWater rights can be secured by LGUWater source site are free from environmental and socialconstraints
Proposed Service Area, 5 Barangays(# OF PAX/HH =5.5)
A 550 pax 100 HHB 660 120C 440 80D 1,100 200E 1,925 350F 2,200 400
Proposed Water Sources:
1. Spring5 kms awaysufficient elevationconfirmed yield, 20 lps
2. Groundwater Well no. 1 10 lps, 50 m away
Well no. 2 8 lps, 250 m
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
19/23
EXAMPLE 1
Population Projections
Water Demand:at 110 liters/cap/dayadd 30% non-revenue water
BarangayName Population Households Population Households Population Households Population Households
A 550 100 584 106 629 114 638 116B 660 120 701 127 755 137 766 139C 440 80 467 85 503 91 510 93D 1,100 200 1,168 212 1,258 229 1,276 232E 1,925 350 2,044 372 2,202 400 2,233 406F 2,200 400 2,336 425 2,516 457 2,552 464
TOTAL 6,875 1,250 7,300 1,327 7,863 1,430 7,975 1,450
Year 1 Year 5 Year 10 Year 15
Water Demand Projection (lps)BarangayName
A 0.91 0.97 1.04 1.06
B 1.09 1.16 1.25 1.27C 0.73 0.77 0.83 0.84D 1.82 1.93 2.08 2.11E 3.19 3.38 3.64 3.70F 3.64 3.87 4.16 4.22
TOTAL 11.38 12.08 13.01 13.20
151 5 10
Growth Rate:Year 5 = 1.21%Year 10 = 1.35%Year 15 = 0.99%
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
20/23
EXAMPLE 1
Key Questions (1/2)
How many barangays would be servedSocial/politicalWater source availabilityCost constraint
Would the source be sufficient to supply thedemand
First year, immediate and long-terms (design
horizon)Most advantageous source option (groundwater,spring or combination)
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
21/23
EXAMPLE 1
Key Questions (2/2)
Development PlanStaged implementation or full implementationCost requirement (consider source option)
Investment CostOperation and Maintenance Cost
Probable water tariff
Financial & Economic IndicatorsWillingness-to-connect and willingness-to-pay
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
22/23
EXAMPLE 1
Other Considerations
Reservoir RequirementsMaybe needed to provide supplemental flowduring peak periods
Or simply to balance pressures during peakflowsNormally sized at 20% to 30% of the averageday demandShould consider fill-and-draw systems or float systems
-
7/28/2019 06_DILG_Salintubig - Design Guidelines for Water Supply System
23/23
END OF PRESENTATION