1 exam prep construction planning, equipment, and...
TRANSCRIPT
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 1
1 Exam Prep
Construction Planning, Equipment, and Equipment Methods
Tabs and Highlights
These 1 Exam Prep Tabs are based on Construction Planning, Equipment, and Methods, 7th
Edition.
Each Tabs sheet has five rows of tabs. Start with the first tab at the first row at the top of the page; proceed
down that row placing the tabs at the locations listed below. Place each tab in your book setting it down one
notch until you get to the bottom of a page. Then start back at the top again. After each Tab, under "Reason" is a
brief explanation of the purpose of the tab, and/or items to highlight in the section.
Special Note to our Students: If you are a 1 Exam Prep student, here is how to really get the most from these 1
Exam Prep Tabs. Follow the above instructions, but before placing the tab, find the tab's topic in the outline of
your appropriate module. Now locate and highlight several items listed in the outline just before the topic, and
just after. See how the topic fits in the outline and how it relates as a concept to the broader concept spelled out
in the outline. If you take a few minutes to do this, when you take the test key words in the test questions will
remind you of where the information is in the manual!
1 Exam Prep Tab Page # Reason
List of Abbreviation Inside cover
Machines Make 1
It Possible
6 “The future of equipment technology or innovation can be
divided into three broad categories: Level of control…,
Amplification of human energy…, Information
processing.”
7 “ The laser and the global positioning system (GPS)
guidance will become more common and reduce the need
for surveyors.”
10 Safety
12 Planning Equipment Utilization
Fundamental Concepts of 17
Equipment Economics
17 “To be successful, equipment owners must carefully
analyze and answer two separate cost questions about their
machines: ….”
20 Equation for Single Payments:”To calculate the future
value F of a single payment P after n periods at an interest
rate I, these formulas are used……”
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 2
1 Exam Prep Tab Page # Reason
21 Formulas for Uniform Series of Payments
28 Elements of Ownership Cost: “The most significant cash
flows affecting ownership cost are…{1-6}”
Purchase Expense: “ The cash outflow the firm
experiences in acquiring ownership of a machine is the
purchase expense.”
29 Salvage Value: “Salvage value is the cash inflow a firm
receives if a machine still has value at the time of its
disposal”
31 Straight-Line Depreciation: “The equations are…”
32 Tax Code Depreciation Schedules: Table 2.1 Tax Code
Depreciation Rates
34 Elements of Operating Costs: Operating cost is the sum
of those expenses an owner experiences by working a
machine on a project.”
35 Fuel: Table 2.2 Average fuel consumption cost – wheel
loaders.”
45 Repairs: Table 2.3 Breakdown of machine cost over
service life.”
48 Rent and Lease Considerations
Planning for Earthwork 60
Construction
60 Planning: “The goal of planning is to minimize resource
expenditures required to successfully complete the project
and to ensure that the work is accomplished in a safe
manner. Planning is necessary in order to… {1-8}.”
61 Safety
63 Earthwork Planning: “Project work elements are defined
in physical terms: volume of stripping, soil excavation,
rock excavation, embankment, waste material, etc. This is a
project material take-off or quantity survey.”
“Mass excavation involves moving a substantial volume of
material and the excavation work is a primary part of the
project.”
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 3
1 Exam Prep Tab Page # Reason
63 “Structural excavation is a different type of undertaking.”
65 Graphical Presentation of Earthwork:”Three kinds of
views are presented in the contract documents to show
earthwork construction features: 1. Plan view…2. Profile
view…3. Cross section view…”
67 Planimeter: “ A Planimeter is a drafting instrument that is
used to move a tracing point around the perimeter of the
plotted area.”
71 Stripping: “The upper layer of the material encountered in
an excavation is often topsoil (organic material), resulting
from decomposition of vegetative matter. Such organic
material is commonly referred to as stripping.”
75 Mass Diagram: “On a mass diagram graph, the horizontal
dimension represents the stations of a project (column1,
Table 3.1) and the vertical dimension (column 12, Table
3.1) represents the cumulative sum of excavation and
embankment from some point of beginning on the project
profile. The diagram provides information concerning…{1-
3}.
77 Balance Lines: “a balance line is a horizontal line of
specific length that intersects the mass diagram in two
places.”
84 Spread Production: “Such groups of equipment are
referred to as an equipment spread.”
85 Summary
Soil and Rock 90
91 Glossary of Terms
93 Types of Geotechnical Materials: Table 4.1 Unified soil
classification system
93 Symbol Classification
95 Soil Weight – Volume Relationships: Figure 4.1 Soil
mass weight and volume relationships
97 Soil Limits: Table 4.2: AASHTO soil classification system
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 4
1 Exam Prep Tab Page # Reason
99 Volumetric Measure: Table 4.3 Representative properties
of earth and rock
101 Compaction Specification and Control
102 Compaction Tests: “The laboratory compaction test that is
accepted by highway departments and other agencies is the
Proctor test.
103 Compaction Control: “Field verification test of achieved
compaction can be conducted by any of several accepted
methods: sandcone, balloon, or nuclear.”
104 Nuclear Compaction Test: “Nuclear methods are used
extensively to determine the water content and density of
soils. The instrument required for this test …can be read
directly from the digital display.”
104 “Advantages of the nuclear method when compared with
other methods include the fact that it …{1 -4}.”
105 GeoGauge: The GeoGauge is a portable instrument that
provides a simple, rapid, and precise means of directly
measuring lift stiffness and soil modules.
107 Amount of Water Required: “it is essential to determine
the amount of water required to achieve a soil water content
within the acceptable moisture range for compaction.”
111 Summary
Compaction and Stabilization 115 Compaction of Soil and Rock: “Obtaining a greater soil
Equipment unit weight is not the direct objective of compaction. The
reason for compaction is to improve soil properties to
…{1-5}.”
116 Glossary of Terms
116 Types of compacting Equipment: “Applying energy to a
soil by one or more of the following methods will cause
compaction: {1-4.}”
117 Table 5.1 Soil types versus the method of compaction
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 5
1 Exam Prep Tab Page # Reason
121 “Vibration has two measurements – amplitude, which is
the rate of the movement, or the number of vibrations
(oscillations) per second or minute (vpm).”
128 Roller Production Estimating: “The production formula
for a compactor is …..”
129 Dynamic Compaction: “The densification technique of
repeatedly dropping a heavy weight onto the ground
surface is commonly referred to as “dynamic compaction.”
131 Soil Stabilization: “The two primary methods of stabilizing
soil are:…{1-2}”
“Fly ash is a by-product in the production of electricity
from burning coal.”
133-134 Lime Stabilization Construction Procedures: “Lime
treatments can be characterized into three classes: …{1-3}”
134 “The basic steps in lime stabilization construction are…{1-
7}.”
138 Summary
Machine Equipment Power 140
Requirements
141 Payload: “The payload capacity of construction excavation
and hauling equipment can be expressed either
volumetrically or gravimetrically.”
144 Rolling Resistance: Table 6-1 Representative rolling
resistances for various types of wheels and crawler tracks
versus various surfaces.”
147 Total Resistance: Table 6.2 The effect of grade on the
tractive effort of vehicles.”
153 Rimpull: “Rimpull is a term that is used to designate the
tractive force between the tires of a machine‟s driving
wheels and the surface on which they travel.”
165 Summary
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 6
1 Exam Prep Tab Page # Reason
Dozers 171
172 Performance Characteristics of Dozers: “Dozers are
classified on the basis of running gear: …{1-2}.”
174 Table 7.1 Dozer –type utilization comparison.
182 Stripping: “Dozers are excellent machines for stripping,
which is the removal of a thin layer of covering material.”
185 Dozer Production Estimating: “The factors that control
dozer production rates are…{1-3}”
191 Dozer Production Estimating Format
199 Land-Clearing Production Estimating
203 Safety during Clearing Operations
207 Determining the Thickness and Strength of Rock
Layers
213 Summary
Scrapers 222
223 Scraper Types
233 Scraper Production Estimating Format
247 Operational Considerations
250 Summary
Excavators 253
253 Hydraulic Excavators
260 Calculating Shovel Production
268 Selecting a Hoe: “In the selection of a hoe for use on a
project the following must be considered…{1-4}.”
271 Calculating Hoe Production
274 General Information
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 7
1 Exam Prep Tab Page # Reason
277 Operating Specifications
279 Loader Production Rates: Table 9.10 Fixed Cycle times
for loaders
281 Calculating Wheel Loader Production
291 Summary
Trucks and Hauling 296
Equipment
302 Capacities of Trucks and Hauling Equipment: Table
10.1 Example specifications for a large off-highway truck
303 Truck Size Affects Productivity
305 Calculating Truck Production: “The following is a
format that can be used to calculate truck production.”
Number of Bucket Loads
309 Production Issues: “A number of other factors must be
considered when matching excavators and hauling units.
- Reach of the excavator
-Dumping height of the bucket
-Width of the bucket”
317 Summary
Finishing Equipment 320 General Information
322 Moldboard: “The moldboard, commonly referred to as the
blade, is the working member of the grader. A rotating
circle carries the moldboard.”
327 Tire Inflation: Table 1.1 Proper gear ranges for grader
operations
329 Grader Safety
330 Safety Rules: “Listed next are specific safety rules for
grader operations….”
330 General Information: “The gradall is a utility machine
that combines the operating features of the hoe, dragline
332 Safety
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 8
1 Exam Prep Tab Page # Reason
334 Summary
Drilling Rock and 337
Earth
338 Glossary of Drilling Terms
341 Drill Bits: “The bit is the essential part of a drill, as it is the
part that must engage and disintegrate the rock.”
Carbide-Insert Bits: “Carbide-insert bits are available in
four grades in order of increasing hardness.”
Table 12.1 Carbide-insert bit grades
342 Rock Drills: “Drills use three methods to cause
fragmentation of rock: (1) percussion, (2) rotary grinding,
and (3) abrasion.”
346 Drilling Methods and Production
348 Drill Penetration Rates: “The critical rock properties that
affect penetration rate are:
- Hardness
-Texture
-Tenacity
-Formation
Table 12.2 Moh‟s scale for rock hardness
350 Estimating Drilling Production
352 Table 12.8 Fixed drilling times
358 GPS and Computer Monitoring Systems
365 Microtunneling
367 Safety
368 Summary
Blasting Rock 372
374 Glossary of Blasting Terms
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 9
1 Exam Prep Tab Page # Reason
375 Commercial Explosives: “Commercial explosives are
compounds that denote on introduction of a suitable
initiation stimulus.
376 Table 13.1 Water resistance classes of dynamite explosives
377 “There are four main categories of commercial high
explosives: (1) dynamite, (2) slurries, (3) ANFO, and (4)
two-component explosives.”
377 Slurries: “This is generic term for both water gels and
emulsions.”
378 ANFO
401 Safety
403 Summary
Aggregate Production 407 Introduction: “Four functions are required to accomplish
the desired results: {1-4}.”
410 Jaw Crushers: Table 14.2 The major types of crushers
415 Gyratory Crushers: “Gyratories are the most efficient of
all primary-type crushers.”
419 Roll Crushers: “A roll crusher consists of a heavy cast-
iron frame equipped with either one or more hard-steel
rolls, each mounted on a separate horizontal shaft.”
425 Special Aggregate Processing Units
427 Feeders: “There are many types of feeders …{1-4}.”
431 Scalping Crushed Stone: “The term scalping, as used in
this chapter, refers to screening operation. Scalping
removes, from the main mass of stone to be processed, that
stone that is too large for the crusher opening.”
439 Summary
Asphalt Mix Production 443
And Placement
444 Glossary of Asphalt Terms
446 Structure of Asphalt Pavements
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 10
1 Exam Prep Tab Page # Reason
447 Flexible Pavements: “Pavements are designed to meet the
following objectives: {1-5}.”
448 Aggregates
449 “The porosity of an aggregate affects the amount of asphalt
cement required in a mix.”
Definition of Porosity (located in margin, page 449)
450 Asphalts: “Asphalt cement is a bituminous material that is
produced by distillation of petroleum crude oil.”
451 Performance Grades of Asphalt Cements
452 Table 15.1 Performance grade asphalt cement
classifications
453 Asphalt Concrete; “Asphalt cements are used as the binder
in paving mixes. The asphalt cements usually represents
less than 10% of the mix by weight. However, …and acting
as a cushioning medium.”
Definition of Hveem (located in margin, page 453)
463 Asphalt Storage and Heating: When liquid asphalt is
combined with the aggregate for mixing, the temperature of
the asphalt should be in the range of 300
466 Definition of Base course (located in margin, page 466)
468 Asphalt Pavers
471 Screed: “The “floating” screed is free to pivot about its pin
connections.”
473 Paver Production
475 Rolling Temperature
479 Safety
479 Summary
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 11
1 Exam Prep Tab Page # Reason
Concrete and Concrete 483
Equipment
486 Table 16.1 Recommended slumps for various types of
concrete construction
487 Aggregates
490 Concrete Mixing Techniques
504 Chutes and Drop Pipes
505 Concrete Pumps
517 Finishing and Curing Concrete
521 Pavement Joints: “Contraction joints or shrinkage joints
in transverse direction across the paving lanes are normally
saw cut into the pavement.”
“Expansion joints, when required, are generally installed
by hand methods. Expansion joints are sealed with joint
filler to prevent foreign material from entering the joint and
rendering it ineffective for its intended purpose.”
524 Shotcreting: “Shotcreting is mortor or concrete conveyed
through a hose and pneumatically projected at high velocity
onto surface [10].”
„There are two methods of producing shotcrete: (1) the dry-
mix process and (2) the wet- mix process.”
525 Fly Ash
528 Summary
Cranes 533
563 Rated Loads for Tower Cranes
567 Weight
Center of Gravity
574 Crane Safety Program: “The company should address {1-
7}”
576 Summary
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 12
1 Exam Prep Tab Page # Reason
Draglines and Clamshells 580
581 General Information: “The greatest advantage of a
dragline over machines is its long reach for digging and
dumping.”
582 Description of a Dragline
588 Calculating a Dragline Production
597 Safety
598 Summary
Piles and Pile Driving 600 Glossary of Terms
Equipment
603 Classification of Piles: Table 19.1 Pile information by
type
603 Timber Piles: “Timber piles are made from the trunks of
trees.”
604 Concrete Piles: “Concrete piles may be either precast or
cast-in-place.”
605 Definition of Prestressing (located in margin, page 605)
637 Summary
Air Compressors and Pumps 639
641 Glossary of Gas Law Terms
642 Gas Laws
644 Glossary of Air Compressor Terms
656 Glossary of Pumping Terms
Planning for Building 675
Construction
677 Site Layout
678 Bid Package
688 Steel Erection
1 Exam Prep – Construction Planning, Equipment, and Methods, 7th Edition 13
1 Exam Prep Tab Page # Reason
699 Summary
Forming Systems 703 Classification: “Formwork for concrete can be classified
into two main types: conventional formwork and
industrialized formwork.”
705 Formwork and the Project Engineer
709 Definition of Wales (located in margin)
709 Definition of Ties (located in margin)
711 Material Cost
715 Table 22.2 Overall number of uses of forms and form
elements
719 Wall Forms: “Forming systems for walls can be grouped
into four main families: {1-4}”
719 Definition of Ganged forms (located in margin)
725 Table 22.6 Ratio of forming contact area to volume for
typical concrete elements.
745 Safety
747 Summary
Units with SI Names and 751
Conversion Factors (A)
English to SI 753
Conversion Factors (B)
U.S. Customary Unit 754
Equivalents (C)
Metric Unit 755
Equivalents (D)
Index 756