1539pk 2003 major power grid blackouts in north america and europe copyright © p. kundur this...
TRANSCRIPT
1539pk
2003 MAJOR POWER GRID 2003 MAJOR POWER GRID BLACKOUTS IN BLACKOUTS IN
NORTH AMERICA AND EUROPENORTH AMERICA AND EUROPE
Copyright © P. KundurThis material should not be used without the author's consent
1539pkMPB- 2
August 14, 2003 Blackout of Northeast US August 14, 2003 Blackout of Northeast US and Canadaand Canada
1539pkMPB- 3
14 August 2003 Blackout 14 August 2003 Blackout of Northeast US - Canadaof Northeast US - Canada
Approximately 50 million people in 8 states in the US and 2 Canadian provinces affected
63 GW of load interrupted (11% of total load supplied by Eastern North American Interconnected System)
During this disturbance, over 400 transmission lines and 531 generating units at 261 power plants tripped
For details refer to: "Final Report of Aug 14, 2003 Blackout in the US and Canada: Causes and Recommendations", US-Canada Power System Outage Task Force, April 5, 2004. www.NERC.com
1539pkMPB- 4
NERC Regions Affected: NERC Regions Affected: MAAC, ECAR, NPCCMAAC, ECAR, NPCC
1539pkMPB- 5
Conditions Prior to BlackoutConditions Prior to Blackout
Electricity demand high but not unusually high
Power transfer levels high, but within established limits and previous operating conditions
Planned outages of generating units in the affected area: Cook 2, Davis Bess plant, East Lake 4, Sammis 3 and Monroe 1
Reactive power supply problems in the regions of Indiana and Ohio prior to noon
Operators took actions to boost voltages
voltages within limits
System operating in compliance with NERC operating policies prior to 15:05 Eastern Daylight Time
Aug 14, 2003 US-Canada Blackout
1539pkMPB- 6
Blackout Started in MidwestBlackout Started in Midwest
1539pkMPB- 7
Sequence of EventsSequence of Events
The Midwest ISO (MISO) state estimator and real-time contingency analysis (RTCA) software not functioning properly from 12:15 to 16:04
prevented MISO from performing proper "early warning" assessments as the events were unfolding
At the First Energy (FE) Control Center, a number of computer software problems occurred on the Energy Management System (EMS) starting at 14:14
contributed to inadequate situation awareness at FE until 15:45
The first significant event was the outage of East Lake generating unit #5 in the FE system at 13:31:34
producing high reactive power output
voltage regulator tripped to manual on overexcitation
unit tripped when operator tried to restore AVR
cont'd
Aug 14, 2003 US-Canada Blackout
1539pkMPB- 8
East Lake 5 Trip: 1:31:34 pmEast Lake 5 Trip: 1:31:34 pm
ONTARIO
2
1
ONTARIO
1539pkMPB- 9
Initial line trips in Ohio, all due to tree contact:
Chamberlin-Harding 345 kV line at 15:05:41
Hanna-Juniper 345 kV line at 15:32:03
Star-South Canton 345 kV line at 15:41:35
Due to EMS failures at FE and MISO control centers, no proper actions (such as load shedding) taken
Critical event leading to widespread cascading outages in Ohio and beyond was tripping of Sammis-Star 345 kV line at 16:05:57
Zone 3 relay operation due to low voltage and high power flow
Load shedding in northeast Ohio at this stage could have prevented cascading outages that following
Sequence of Events Sequence of Events cont'dcont'd
Aug 14, 2003 US-Canada Blackout
1539pkMPB- 10
(3:05:41)(3:32:03)
Star- S. Canton (3:41:35)
1539pkMPB- 11
Sammis-Star(4:05:57.5)
1539pkMPB- 12
Tripping of many additional 345 kV lines in Ohio and Michigan by Zone 3 (or Zone 2 set similar to Zone 3) relays
Tripping of several generators in Ohio and Michigan
At 16:10:38, due to cascading loss of major lines in Ohio and Michigan, power transfer from Canada (Ontario) to the US on the Michigan border shifted
power started flowing counter clockwise from Pennsylvania through New York and Ontario into Michigan
3700 MW of reverse power flow to serve loads in Michigan and Ohio, which were severed from rest of interconnected system except Ontario
Voltage collapsed due to extremely heavy loadings on transmission lines
Cascading outages of several hundred lines and generators leading to blackout of the region
Sequence of EventsSequence of Events
Aug 14, 2003 US-Canada Blackout
1539pkMPB- 13
Power Transfers Shift at 4:10:38.6 pmPower Transfers Shift at 4:10:38.6 pm
1539pkMPB- 14
Generator Trips to 16:10:38Generator Trips to 16:10:38
1539pkMPB- 15
Generator Trips - Next 7 SecondsGenerator Trips - Next 7 Seconds
1539pkMPB- 16
Northeast Completes Separation from Northeast Completes Separation from Eastern InterconnectionEastern Interconnection
4:10:43 - 4:10:45 pm4:10:43 - 4:10:45 pm
1539pkMPB- 17
Generator Trips - After 16:10:44Generator Trips - After 16:10:44
1539pkMPB- 18
End of CascadeEnd of Cascade
Areas Affected by the BlackoutService maintained
in some area
Some Local Load Interrupted
1539pkMPB- 19
Primary Causes of BlackoutPrimary Causes of Blackout(as identified by the US-Canada Outage Task Force)(as identified by the US-Canada Outage Task Force)
1. Inadequate understanding of the power system requirements:
First Energy (FE) failed to conduct rigorous long-term planning studies and sufficient voltage stability analyses of Ohio control area
FE used operational criteria that did not reflect actual system behaviour and needs
ECAR (East Central Area Reliability Council) did not conduct an independent review or analysis of FE's voltage criteria and operating needs
Some NERC planning standards were sufficiently ambiguous that FE could interpret them in a way that resulted in inadequate reliability for system operation
cont'd
1539pkMPB- 20
Causes of Blackout Causes of Blackout cont'dcont'd
2. Inadequate level of situation awareness:
FE failed to ensure security of its system after significant unforeseen contingencies
FE lacked procedures to ensure that its operators were continually aware of the functional state of their critical monitoring tools
FE did not have adequate backup tools for system monitoring
3. Inadequate level of vegetation management (tree trimming)
FE failed to adequately manage tree growth into transmission rights-of-way
resulted in the outage of three 345 kV lines and one 138 kV line
cont'd
1539pkMPB- 21
Causes of Blackout Causes of Blackout cont'dcont'd
4. Inadequate level of support from the Reliability Coordinator
due to failure of state estimator, MISO did not become aware of FE's system problems early enough
did not provide assistance to FE
MISO and PJM (Regional Transmission operator) did not have in place an adequate level of procedures and guidelines for dealing with security limit violations due to a contingency near their common boundary
1539pkMPB- 22
September 23, 2003 Blackout of September 23, 2003 Blackout of Southern Sweden and Eastern DenmarkSouthern Sweden and Eastern Denmark
1539pkMPB- 23
The Transmission Grid in The Nordic The Transmission Grid in The Nordic CountriesCountries
1539pkMPB- 24
Blackout of 23 September 2003 in Blackout of 23 September 2003 in Southern Sweden and Eastern DenmarkSouthern Sweden and Eastern Denmark
Pre-disturbance conditions:
system moderately loaded
facilities out of services for maintenance:
400 kV lines in South Sweden
4 nuclear units in South Sweden
3 HVDC links to Germany and Poland
The first contingency was loss of a 1200 MW nuclear unit in South Sweden at 12:30 due to problems with steam valves
increase of power transfer from the north
system security still acceptable
Five minutes later (at 12:35) a disconnector damage caused a double busbar fault at a location 300 km away from the first contingency
resulted in loss of a number of lines in the southwestern grid and two 900 MW nuclear units
At 12:37, voltage collapse in the eastern grid section south of Stockholm area
isolated southern Sweden and eastern Denmark system from northern and central grid
cont'd
1539pkMPB- 25
The Blackout in Southern Sweden and The Blackout in Southern Sweden and Eastern Denmark, September 23, 2003Eastern Denmark, September 23, 2003
At 12.30: Loss of a 1200 MW Nuclear Unit
1539pkMPB- 26
The Blackout in Southern Sweden and The Blackout in Southern Sweden and Eastern Denmark, September 23, 2003Eastern Denmark, September 23, 2003
At 12.35: Double bus-bar fault leading to-Loss of two 900 MW Nuclear Units
-Disrupture of the south-western grid
1539pkMPB- 27
The Blackout in Southern Sweden and The Blackout in Southern Sweden and Eastern Denmark, September 23, 2003Eastern Denmark, September 23, 2003
TenhultStrömma
Horred
Söderåsen
Barsebäck
Hemsjö
Simpevarp
Nybro
Kimstad
Glan
Kolstad
Hallsberg
Breared Alvesta
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
TenhultStrömma
Horred
Söderåsen
Barsebäck
Hemsjö
Simpevarp
Nybro
Kimstad
Glan
Kolstad
Hallsberg
Breared Alvesta
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
The voltage collapse
Maintenance work
The fault in Horred
Line outages due to:
Voltage Collapse
Isolated Subsystem
1539pkMPB- 28
The Blackout in Southern Sweden and The Blackout in Southern Sweden and Eastern Denmark, September 23, 2003Eastern Denmark, September 23, 2003
The blacked-out area after the grid separation at 12.37
1539pkMPB- 29
The isolated system had enough generation to cover only about 30% of its demand
voltage and frequency collapsed within a few seconds, blacking out the area
Impact of the blackout:
loss of 4700 MW load in south Sweden
1.6 million people affected
City of Malmo and regional airports and rail transportation without power
loss of 1850 MW in eastern Denmark
2.4 million people affected
City of Copenhagen, airport and rail transportation without power
Result of an (n-3) contingency, well beyond "design contingencies"
Blackout of 23 September 2003 in Blackout of 23 September 2003 in Southern Sweden and Eastern Denmark Southern Sweden and Eastern Denmark
cont'dcont'd
1539pkMPB- 30
September 28, 2003 Blackout of ItalySeptember 28, 2003 Blackout of Italy
1539pkMPB- 31
Italian System Blackout of Italian System Blackout of 28 September 200328 September 2003
Predisturbance conditions (Sunday, 3:00 am):
total load in Italy was 27,700 MW, with 3638 MW pump load
total import from rest of Europe was 6651 MW
Sequence of events:
a tree flashover caused tripping of a major tie-line between Italy and Switzerland (Mettlen-Lavorgo 380 kV line) at 03:01:22
Sychro-check relay prevented automatic and manual reclosure of line due to the large angle (42°) across the breaker
resulted in an overload on a parallel path
attempts to reduce the overload by Swiss transmission operators by network change was not successful
at 03:21 import by Italy was reduced by 300 MW but was not sufficient to mitigate the overload of a second 380 kV line (Sils-Soazza), which tripped at 03:25:22 due to sag and tree contact
cont'd
1539pkMPB- 32
the cascading trend continued and the power deficit in Italy was such that the ties to France, Austria and Slovania were tripped
the outages left the Italian system with a power shortage of 6400 MW
the frequency decay could not be controlled adequately by under-frequency load shedding
over the course of several minutes, the entire Italian System collapsed at 3:28:00
The blackout affected about 60 million people
total energy not delivered 180 GWh
worst blackout in the history of Italy
power was restored after 3 hours in the northern area and during the same day for most of Italy
Italian System Blackout of Italian System Blackout of 28 September 2003 28 September 2003 cont'dcont'd