201 the design of earthworks

Upload: farrah-azween-amin

Post on 05-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 201 the Design of Earthworks

    1/27

    The Design of Earthwork

    1

  • 8/2/2019 201 the Design of Earthworks

    2/27

    1.0 Introduction Earthwork: the processes whereby the surface of the earth is

    excavated and transported to and compacted at anotherlocation

    the introduction of the internal combustion engine, electricpower and hydraulic power have led to the development of awide range of earthwork plant (size, capacity and efficiency).

    scale: ranges from small works (the excavation of ditches andtrenches for drainage and pits and trenches for foundations) to

    the large earthworks (highways and dams).

    2

  • 8/2/2019 201 the Design of Earthworks

    3/27

    carried out at an early stage in a construction project,completion of the earthworks within the scheduled time is

    often the key to the completion on time of the whole project

    success often depends on:

    an adequate site investigation and preparing practical andsatisfactory designs of the earthworks

    the choice and efficient use of the correct types and size ofplant to meet the particular requirements of the site.

    BS 6031 gives recommendations on the design and constructionof earthworks in general civil engineering schemes

    3

  • 8/2/2019 201 the Design of Earthworks

    4/27

    2.0 The Design of Earthworks2.1 Site or route selection selection factors:

    the availability and cost of the land

    planning, design, construction, environmental and economicconsiderations (choice of dam sites and the routes forhighways and railways)

    the geological conditions and other geotechnicalconsiderations

    4

  • 8/2/2019 201 the Design of Earthworks

    5/27

    2.2 Environmental and economic considerations

    the design & construction and the cost of earthworks aregenerally dependant on:

    the environment in and around the site

    the ground conditions within the site

    the availability of materials for earthworks in the area.

    5

  • 8/2/2019 201 the Design of Earthworks

    6/27

    the landscape of the area should be taken into consideration,the earthworks should not disfigure but blend into the

    environment:

    suitable profiles of earthworks

    amenity embankments

    tree planting etc

    6

  • 8/2/2019 201 the Design of Earthworks

    7/27

    balance the amount of fill arising from cuttings with the amount offill required to construct the embankments - reduce the cost of

    earthworks:

    minimise the quantities of imported materials

    minimise material to be disposed of off-site

    consider natural and waste resources in the area, such as areproduced from the local mines, pits, quarries, power stations,etc. as fill required to construct the embankments

    to incorporate lower quality local materials than to importhigher quality materials from some distance away - reduce

    cost transportation and minimise disruption of the localenvironment (especially on larger schemes).

    7

  • 8/2/2019 201 the Design of Earthworks

    8/27

    Terangkan ciri-ciri sebuah projek kerja tanah yangdirekabentuk dengan baik.

    8

  • 8/2/2019 201 the Design of Earthworks

    9/27

    3.0 Design of cuttings and embankments3.1 Excavations carried out either as

    part of the permanent works (e.g. cuttings) or

    a temporary expedient in the construction of the works (e.g.for foundations and drainage)

    9

  • 8/2/2019 201 the Design of Earthworks

    10/27

    the sides of the excavations are required to remain stableduring their design life, can be achieved by

    excavating the material to a stable slope angle

    by retaining or supporting the material.

    10

  • 8/2/2019 201 the Design of Earthworks

    11/27

    3.1.1Slope

    the stability of slope (natural and cut) is controlled by:

    the nature, distribution, density and strength of the materials thatform the slopes

    the groundwater conditions or porewater pressures

    external or surcharge loadings,

    the strength and disposition of any discontinuities.

    11

  • 8/2/2019 201 the Design of Earthworks

    12/27

    the effects of cutting

    reduces the total stresses in the slope which leads to a reductionof the pore pressures - increases the stability of the slope in theshort term.

    pore pressures will tend to rise to a new equilibrium value and thematerials in the slope may weaken, leading to a reduction in the

    stability of the slope

    occur rapidly in granular soils and well jointed rocks and there willbe little difference in the long and short term stability - analyses ofthe stability of slopes carried out by effective stress methods

    12

  • 8/2/2019 201 the Design of Earthworks

    13/27

    occur slowly in cohesive soils and rocks due to low permeability(weeks or even decades) - total stress methods of analysis are

    used for the short term stability and effective stress methods forthe intermediate and long term.

    weathering and erosion of slopes should be allowed for in thedesign

    factors of safety applied to the design of slopes depend on:

    the extent and reliability of the knowledge of the groundconditions

    the consequences of failure

    a good level of investigation, a factor of safety of between1.3 and 1.4 would be appropriate

    13

  • 8/2/2019 201 the Design of Earthworks

    14/27

    Typical batters of excavated slopes (as a guide and should notbe taken for final design purposes)

    Material Slope batters* (vertical:horizontal)

    Permanent Temporary

    Massive rock 1.5:1 to vertical 1.5:1 to vertical

    Well jointed/bedded rock 1:2 to 2:1 1:2 to 2:1

    Gravel 1:2 to 1:1 1:2 to 1:1Sand l:25 to 1:1.5 1:25 to 1:1

    Clay 1:6 to 1:2 1:2 to 2:1

    14

  • 8/2/2019 201 the Design of Earthworks

    15/27

    3.1.2Retaining Structures

    Retaining and supporting structures (temporary works orpermanent works)

    able to withstand the pressures generated by the in situ andbackfill materials, surcharge loadings and ambient

    groundwater conditions.

    a factor of safety of at least 2 is usually adopted.

    ground anchors may be used as part of the retaining worksin both temporary and permanent excavations in soils and

    weak rocks.

    15

  • 8/2/2019 201 the Design of Earthworks

    16/27

    rock anchors and bolts may be used with or withoutadditional structural support to increase the stability of rock

    slopes.

    3.1.3Groundwater problems

    reduce the stability of slopes and retaining structures

    make the excavated material unsuitable or troublesome foruse as fill within the works.

    temporary or permanent dewatering and drainage measuresmay be needed.

    16

  • 8/2/2019 201 the Design of Earthworks

    17/27

    4.0 Embankments constructed from a wide variety of materials and for numerous

    purposes:

    load-bearing fills - roads and dams, require a higher factor ofsafety

    non-load bearing fills - stockpiles or amenity embankments

    17

  • 8/2/2019 201 the Design of Earthworks

    18/27

    major factors to be considered in the design of an embankmentare

    the stability

    the bearing capacity

    the settlement

    the trafficability

    the permeability.

    The stability of an embankment vary with time and obviouswhen it is constructed of or on cohesive soils becauseconstruction of embankment will lead to:

    increase of porewater pressures in the fill which may increase

    or decrease with time (affect the stability of the slopes)

    18

  • 8/2/2019 201 the Design of Earthworks

    19/27

    porewater pressures in the foundation soils which decreasewith time (settlement of foundation)

    4.1.1Stability

    analyses of the stability of embankments (and theirfoundations) must be carried out to determine the lowestfactors of safety for the ranges of height, materials of

    construction and foundation strata, with the porewaterpressures that may be generated during and after construction.

    actions can be made to increase the stability when the factor ofsafety is inadequate:

    reducing the angle of the side slopes

    constructing a berm at the toe of the slopes

    19

  • 8/2/2019 201 the Design of Earthworks

    20/27

    using fill of higher strength

    improving the strength of the fill by drying out or lime orcement stabilisation

    emplacing drainage layers within the fill to reduce porewaterpressures

    emplacing geotextiles within the fill to increase its overallstrength

    partially or totally retaining the fill.

    20

  • 8/2/2019 201 the Design of Earthworks

    21/27

    Typical slope angles used for embankments (a guide and shouldnot be taken for final design)

    Material Typical slope batters* (vertical:horizontal)

    Hard rock fill 1:1.5 to 1:1

    Weak rock fill 1:2 to 1:1.25

    Gravel 1:2 to 1:1.25

    Sand 1:25 to 1:1.5

    Clay 1:4 to 1:1.5

    4.1.2Bearing Capacity

    the bearing capacity of an embankment will only be importantwhere the surface is to be loaded (e.g. a road, railway orfoundations)

    21

  • 8/2/2019 201 the Design of Earthworks

    22/27

    for roads, railways and runways, the California bearing ratio(CBR) of subgrade reaction is used to determine the bearing

    capacity

    plate bearing or triaxial test data are used for foundations.

    bearing capacity of an embankment can be improved by:

    using better quality fill such as gravel or rockfiil in the upperlayers

    using material stabilised with lime or cement

    improved with techniques such as vibroflotation or dynamic

    consolidation.

    22

  • 8/2/2019 201 the Design of Earthworks

    23/27

    4.1.3Settlement of an embankment

    arises from:

    the settlement of the fill and/or the foundation strata

    permeable material: settlement will occur during constructionand can be compensated for by the placement of additional

    fill settlements continue for weeks or years after construction in

    low permeability soil, thus measures must be taken toaccelerate consolidation

    23

  • 8/2/2019 201 the Design of Earthworks

    24/27

    Soil Stabilization action can be taken when the magnitude or duration of the

    foundation settlements are excessive and/or the foundationsoils are unacceptably weak

    reducing the angle of the side slopes

    constructing a berm at the toe of the slopes emplacing geotextiles towards the base of the embankment

    to reduce its deformability

    the removal or displacement of soft or weak materials and

    their replacement with suitable fill

    24

  • 8/2/2019 201 the Design of Earthworks

    25/27

    the construction of a wide and deep trench filled withgranular material

    improvement of the ground by vibroflotation, dynamiccompaction or preloading

    controlling the rate of construction to allow time for thefoundations to consolidate and increase in strength

    decreasing the load applied to the ground by usinglightweight fill, such as pfa

    the emplacement of vertical drains and/or a horizontaldrainage blanket beneath the embankment to accelerate the

    dissipation of porewater pressures and settlement and toincrease the strength of the ground.

    25

  • 8/2/2019 201 the Design of Earthworks

    26/27

    5.0 Ground Improvement Techniques Partially sand replacement

    1 m to 1.5 m deep

    to provide a firm platform and to function as drainage

    layer

    Prefabricated vertical drains (pvd)

    installed at 1.2 m square grids and down to firm strata (25m to 30 m deep)

    0.5 m to 1.0 m surcharge to accelerate the consolidation(6 months)

    26

  • 8/2/2019 201 the Design of Earthworks

    27/27

    Geotextile

    high stength polyester woven geotextile

    to achieve the necessary FOS against slip failure

    help to reduce differential settlement

    Stone Column

    300 mm diameter at 1.2 m square grids

    to transmit loads to deeper stratum

    27