    Project : ER 296 Sentosa Gateway (Remaining Progress Plan)

    SECTOR 6

    (A,B)

    Construction D-Wall 84 nos

    12 panel

    Utlity & Road Diversion

    Utlity & Road Diversion 20.6 panels/ month

    Utlity & Road Diversion 13 panels/ month

    Construction D-Wall 26 nos

    BC 40

    Utlity & Road Diversion 14.3 panels/ monthConstruction D-Wall 43 nos Low head

    SECTOR 1

    Bored Pile Work 12 Nos

    Construction D-Wall 42 nos

    13 panel

    Utlity & Road Diversion

    30 30

    D - Wall

    Rebar D-Wall cage Fabrication

    SECCTOR

    3

    Utlity & Road Diversion

    30 30 30 30 30 3030 30 30 30 30 3030 30 30 30 30 3030 30 30 30 30 30

    June July August September October

    30 30 30

    December January February March April MayJune July August September Oct ober NovemberDecember January February March April MayJ une J ul y Augus t S epte mber October Novembe r

    21th 06, 2013

    Description Panel No.

    2013 2014 2015

    RemarkPrevious

    Driving the horizontal

    Driving pipe

    (Vertical & Bottom)6 Nos

    Driving the horizontal

    pipe

    (Bottom)

    6 Nos

    Driving the vertical pipe 4 Nos

    Driving the vertical pipe 2 Nos

    2 Nos

    Driving the vertical pipe 4 Nos

    Driving the vertical pipe 4 Nos

    1 Lane

    Driving the horizontal

    pipe

    (Top)

    6 Nos

    Driving the horizontal

    pipe

    (Top) 2 Nos

    Driving the vertical pipe

    Construction D-Wall 68 nos

    SECTOR 6

    (C)

    Mob. Plants & Set up

    Machine

    14 panels/ month

    Construction D-Wall 42 nos

    Driving the horizontal

    pipe

    (Bottom)

    6 Nos

    Driving the horizontal

    pipe 6 Nos

    Driving the vertical pipe 4 Nos

    Driving pipe

    (Vertical & Bottom)2 Nos

    Driving the vertical pipe 4 Nos

    Driving the vertical pipe 4 Nos

    Driving the vertical pipe 6 Nos

    Driving the vertical pipe 2 Nos

    2 lane

    Driving the horizontalpipe

    (Top)

    1 Nos

    Driving the pipe 4 Nos

    Driving the pipe 6 Nos

    ppe

    (Bottom)

    s

    Steel support fram &

    Excavtion1 L/S

    Demolish

    working platform

    Shield TBM

    Lane

    2 Lane

    *Excavation Ability : Lowhead BC cutter( Sector 5: 0.45m/hour) / BC cutter(Sector 3: 1.0m/hour)

    *D-Wall construction unit price : ###

    *Schedule is changeable depend on site condition & Main con.

    *Operation 2shift(Worrking hour : 20 hour)

    *Every 2 weeks 1 day off day : No standby finished Excavation pannel - operation casting team.

    REV.00

    Remark

    BC2+Grab1 BC2+Grab1 BC2+Grab1 BC1+Grab1 BC1+Grab1 BC1+Grab1Machinery BC2+Grab1 BC2+Grab1 BC1+Grab1 BC1+Grab1

    6/51 1/524/23 4/27 4/31 2/33 6/39 6/451/1 4/5 6/11 6/17 2/19

    4/27 2/29 6/35 6/41 3/44

    Nos PIPE BOX11/11 2/13 2/15 4/19 4/23

    3 35/4 51 3 63/ 451 3 95/ 451 415/ 451 435 /45 1 451 /45 123 5/4 51 26 9/4 51 2 89/4 51 3 03/ 451 3 17/ 451

    28 32 20 20 16

    Panels235 34 18 14 14 18

    Steel support fram &

    Excavtion1 L/S

    D-Wall

    Driving the horizontal

    pipe

    (Bottom)

    6 Nos

    Driving the horizontal

    pipe

    (Bottom)

    1 Nos

    ( ottom)