Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Implementing an EnMS+SEAP approach

Prioritizing your actions

Evi Tzanakaki

Kostas Sioulas

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 2

SEAP DEVELOPMENT

1. Data recording/ baseline/diagnosis

2. Planning/ selection of actions

3. Implementation

Regulatory and management actions

Low cost measures for reducing consumption

Moderate/major energy retrofitting actions/projects

Combined and prioritized activities

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 3

PRIORITIZING SEAP ACTIONS

Criteria

Energy savings and environmental benefits/cost

Cost effectiveness accοrding to several methodologies (i.e. life cycle)

Replicability, pilot examples, showcases

Human and other resources

Capital cost/ financing opportunities

Realistic timeline/planning

Social benefits and municipal priorities

etc. etc. etc…

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 4

ENMS AS A TOOL FOR PRIORITIZING SEAP ACTIONS

Our show-case example: Municipality of Likovrisi-Pefki

Describing a step-by-step procedure

Credits: Vicky Amenta

Mechanical Engineer

Technical Department

Municipality of Likovrisi-Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 5

LIKOVRISI-PEFKI

General identity

A municipality in the Athens

metropolitan area with

4.126.000 m2 surface

31.000 population

212.000 m2 urban spaces

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

• Efficient energy

management

• which does not affect the

quality of services

provided

• to citizens who are aware

and active in

“environmental” aspects

Energy

management

improvement

• Public activities

• Private activities

SEAP

ISO50001

MAJOR MUNICIPAL PRIORITIES

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs Municipality of Likovrisi - Pefki

Commitment

• Put the vision in words

• The management should understand and support the effort (allocation of resources)

• The management should inspire/ convince the personnel

Management

• Decide the scope : buildings, cars & equipment, streetlights, some of them all of them?

• Set up the team

Energy data

• Decide the Baseline

• Collect data since the baseline date

• Make an energy profile for every consumption (i.e. equipment installed, users, hours of operation, etc.)

Monitoring

• Set goals for the future and plan measures in order to achieve them

• Decide key performance indexes

• Continuous monitoring of energy consumption

• Review the goals and assess achievements and failures

steps of the overall processSEAP

ISO50001

• PUBLIC + PRIVATE

• NO

• 2nd

YEAR

• YES

• YEARLY

• NO

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

the scope of actions

18 admin .

buildings/ 3

kindergartens / 19

school buildings

2.200 lamps

125W/250W

55 cars and

vehicles

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Data collection/ input/ management: a snapshot

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Data collection/ input/ management : a snapshot

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Data collection/ input/ management : a snapshot

0 5000 10000 15000 20000 25000 30000

ΓΥΜΝΑΣΙΟ ΛΥΚΟΒΡΥΣΗΣ

1Ο ΓΥΜΝΑΣΙΟ ΠΕΥΚΗΣ

2Ο ΓΥΜΝΑΣΙΟ ΠΕΥΚΗΣ

ΛΥΚΕΙΟ ΛΥΚΟΒΡΥΣΗΣ

1Ο ΛΥΚΕΙΟ ΠΕΥΚΗΣ

2Ο ΛΥΚΕΙΟ ΠΕΥΚΗΣ

Β ΒΑΘΜΙΑ ΕΚΠΑΙΔΕΥΣΗ - ΚΑΤΑΝΑΛΩΣΗ ΗΛΕΚΤΡΙΚΗΣ ΕΝΕΡΓΕΙΑΣ (KWh)

2014

2013

2012

2011

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Data collection/ input/ management : a snapshot

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Data collection/ input/ management : a snapshot

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

• Swimming pool: Immediate low cost measures: isothermic cover (40% energy

saving) – Study for use of other sources of renewable energy

Planned high cost measures: Use of renewable energy (geothermal)

• Streetlights: 240 streetlights with 250W lamps replaced

by 70W LED lamps

• Complete set of data for building “thematic” action plans:• Municipality transportation planning

• Fleet renewal planning

• Waste management and recycling

• Installation of solar panels in schools

• Assessment of new technologies e.g. e-mobility, etc.

achieved in 2013-2015

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

concluded in 2015

Municipality of Likovrisi - Pefki

• Energy improvement works in 3

public buildings in Pefki and 1 in

Likovrisi

• A training programme for the

municipality’s personnel

• School awareness actions

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

awareness actions 2015

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

• Large scale energy improvement works in 1 school

building in Likovrisi (summer 2016)

• Construction of a new school building, which implements

energy saving technologies

• Small scale energy improvement works in 2 school

buildings

• Small scale replacement of streetlights with LED lamps

scheduled for 2016

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 18

STILL TO BE SOLVED…Need for continuous training and awareness actions

Information system for real time energy data retrieval and processing

Funding for large scale projects , e.g. energy improvement in the

municipality building and the swimming pool, fleet renewal and fleet

management, etc.

MEANWHILE…We perform a step by step approach , i.e. smaller scale projects for

energy improvement in public buildings

We are getting ready to submit proposals to national and EU co-funded

programmes

We are assessing new technologies, e.g. electric vehicles

We are designing pilot implementation projects, in order to carry on

feasibility studies

and one step beyond…

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 19

RESULTS OF PROCESS

We know exactly how much energy, what kind of energy, where and

why we consume

We have a deeper understanding of the energy profile of every building/

car/ streetlight

We have all the information for :

• A better use of energy

• Redesign / re-organise our services

• Making a priority list of where we should focus our efforts

• Making accurate calculations for the feasibility of each planned investment

• Understanding immediately where and why there has been a bad use of

energy at least at the big consumers

Energy Manager

final remarks

Municipality of Likovrisi - Pefki

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 20

ENMS AS A TOOL FOR PRIORITIZING ACTIONS

Public Sector example: Hellenic Ministry of Defense (MoD)

ISO 50001:2011 implementation

in the Hellenic MoD

(Military Energy and Carbon Management project

LIFE11 ENV/GR/000938)

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Project Budget: € 1.355.218

HMoD contribution: € 628.254

CRES contribution: € 174.355

EU contribution: € 552.609 (50% of the

eligible costs)

Duration: October 2012 – December 2016

www.life.mil.grCoordinating

Beneficiary

Associated

Beneficiary

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Energy Management

System (EnMS)

development and

implementation in the

non-operational

activities of 3 Military

Installations in Greece

ISO 50001 in line withArmed Forces mission& HMoD EnvironmentalPolicy

110 CW –Larissa AFB Thessaly360 buildings, 129,627 m2

Souda Naval Station, Crete183 buildings, 65,081 m2

«Triantafyllidi» Army Barracks, Xanthi, Thrace62 buildings, 18,894 m2

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 23

ISO 50001:2011 APPLICATION (P-D-C-A)

Planning Phase

Energy Policy

Energy Review

Energy PIs

Objectives, Targets

Action Plans

Energy objectives and targets with

action plans to achieve the objectives

and targets

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Energy Review & Action Plan

• Energy review - energy profile (Significant Energy Uses – SEU, electricity, heating fuels, transportation fuels, period 2008-2012)

• Data collection (2013) • Bottom up and top down approach (equipment, operating hours, energy

bills, infrastructure)• Baseline year (2011)• Opportunities for improvements, priorities • Action Plans (Energy Programmes, pilot projects) • Operational Control• Annual Energy Consumption report• Overall Target (at least 3% annual reduction of energy consumption)

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Opportunities prioritization

• The prioritizing method is up to organization

• Must be an on going and systematic process

• Focus on the most practical ideas (is time consuming and very difficult to process with every potential improvement)

• Determine criteria

• Use simple tools to apply criteria

• Apply criteria

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Determine criteria (the type and the number)

• No cost - low cost – investments (small wins first)• No cost measures or alternatives? (administrative measures, training,

awareness)

• Energy Saving measures?• Energy saving estimation• Investment cost• Return of investment• Timeline (duration of action implementation) • Possible military, safety, health, and environmental issues• Maintenance• Demonstration character

Document the criteria

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Prioritize Energy Opportunities

• One or two criteria can be enough (Go/No Go decision)

• Some times more criteria maybe required (a process is required for determining the relative importance of each criteria and how they will be evaluated, eg multicriteria analysis with equal or relative weighting, higher scores indicate higher opportunity)

Annually Process (Procedure P11)• Evaluate ideas (criteria: cost, payback period, energy saving,

timeline) • Prioritize opportunities (ranking)• Energy Programmes (list)• Energy Programmes approval & progressive implementation• Top Management review (effectiveness)

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs

Implement (indicative examples):

• Energy saving instructions,• Personnel training and awareness (regular process)• Energy upgrade (renovation) of Buildings• Lighting grid modernization• Administrative measures (more efficient use of given resources)• Rational use of energy• Metering (electricity, light, fuels)• Solar thermal systems• Autonomus PV

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 29

RESULTS OF THE PROCESS

PILOT PROJECTS

ENERGY SAVING

ENERGY

PERFORMANCE

CONTINUOUS

IMPROVEMENT

Supporting Local Authoritites in the Development and Integration of SEAPs with

Energy management SystemsAccording to ISO 500001www.500001seaps.eu

@500001SEAPs 30

THANK YOU FOR YOUR ATTENTION!