3 - lilama 69-3 dse tekla at dong yang project
DESCRIPTION
ÂTRANSCRIPT
![Page 1: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/1.jpg)
Tekla Structures for Steel detailing and
fabrication: DongYang project
Tekla User‘s Day – Hanoi, April 2013
Mr. Nguyen Vu Truong, Director of LILAMA69-3 DESIGN INDUSTRIAL & SYSTEMS
ENGINEERING JOINT STOCK COMPANY
![Page 2: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/2.jpg)
Content:
• Introduction of Lilama 69-3 DSE
• Tekla Structures at Lilama 69-3 DSE – The
milestones
• Tekla Structures for Dong Yang project
• Conclusions and Suggestion
![Page 3: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/3.jpg)
Introduction:
![Page 4: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/4.jpg)
![Page 5: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/5.jpg)
![Page 6: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/6.jpg)
![Page 7: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/7.jpg)
![Page 8: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/8.jpg)
![Page 9: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/9.jpg)
Mile stones with Tekla Structures:
• 04.2011: Model 35 buildings of Cong Thanh
cement plant project – subcontracted for
Polysius Vietnam
• 2012: Signed the contract with DongYang P&F
(Korea) to Design and Fabricate 3500 tons of
Steel Structures for HSGP and SSSP project
in AbudHabi – UAE
![Page 10: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/10.jpg)
Cong Thanh Cement Plant
![Page 11: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/11.jpg)
![Page 12: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/12.jpg)
![Page 13: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/13.jpg)
![Page 14: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/14.jpg)
Vincom Mega Mall project: Movies
![Page 15: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/15.jpg)
DongYang project:
• 6 Conveyors; 5 Transfer towers
• Finish the design work in December, 2012
• Plan to finish fabrication work in April, 2013
• 20 experienced Tekla users
• Using 3 main software:
- Tekla Structures for structural
Modeling and Detailing
- 3D Max for Architectural
- Autodesk Inventor for Mechanical work
![Page 16: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/16.jpg)
CV-1100/1200: Granule Collecting Conveyors
![Page 17: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/17.jpg)
CV-1100/1200: Movies
![Page 18: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/18.jpg)
CV-1100/1200: Granule Collecting Conveyors
![Page 19: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/19.jpg)
CV-1100/1200: Granule Collecting Conveyors
![Page 20: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/20.jpg)
CV-1300: Reclaimed Transfer Conveyor
![Page 21: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/21.jpg)
CV-2100/2200: Stacker & Reclaimed Conveyor
![Page 22: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/22.jpg)
TT-1: Transfer Tower No.1
![Page 23: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/23.jpg)
TT-1: Transfer Tower No.1
![Page 24: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/24.jpg)
TT-2: Transfer Tower No.2
![Page 25: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/25.jpg)
TT-2: Transfer Tower No.2
![Page 26: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/26.jpg)
TT-3: Railcar Loading Building
![Page 27: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/27.jpg)
TT-3: Railcar Loading Building
![Page 28: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/28.jpg)
Engineering schedule for HSGP+SSSP project:
Step 1: Create General Arrangement drawings by
CAD system for Structural and ME,EL, PP,…
![Page 29: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/29.jpg)
Engineering schedule for HSGP+SSSP
project: Stage 1: Create General Arrangement drawings by CAD system for
Structural and ME,EL, PP,…
![Page 30: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/30.jpg)
Step 2: Structural Analysis and Design
- Build structural model base on GA drawings, add loads, load
combinations
- Standard:
ANSI/AISC 360 - 05 Specifications for Structural Steel Buildings,
ASCE/SEI 7-10 Minimum design loads for buildings and other
structures, International Building Code 2006/2009 (IBC 2006/2009, ….).
![Page 31: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/31.jpg)
Step 3: Create Sketch drawings for structural
![Page 32: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/32.jpg)
Step 4: Build 3D Tekla model
Step 5: Create Engineering drawings: Check dimensions, profiles
![Page 33: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/33.jpg)
Step 6: Clash check with Mechnical model on Tekla via Reference model
![Page 34: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/34.jpg)
Step 7: Connection design and detailing in Tekla
Step 8: Create Erection drawings and check.
![Page 35: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/35.jpg)
Step 9: Create workshop drawing
We use 2 ways:
- Create Assembly that includes single part drawings as traditional way
in AutoCAD
* Non professional way and not easy for fabrication.
![Page 36: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/36.jpg)
- Create both Assembly drawings and Single part drawings
• Easy for fabrication • Easy to manage
![Page 37: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/37.jpg)
Suggestion:
Need help from HSD VIETNAM for Advanced functions in Tekla:
- Firm and project settings, - Collaborations,… To optimize Tekla’ potential
+ Check the clashing between weld and structural members ?
+ Suitable price for Tekla software Our trend: + In the next few year we will try to intergrate Tekla
software to CNC fabrication, create and manage schedule, erection simulation…
+ Use Tekla software as early as possible. + We will invest at least one Tekla license each year.
![Page 38: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/38.jpg)
Q&A ?
![Page 39: 3 - Lilama 69-3 DSE Tekla at Dong Yang project](https://reader034.vdocuments.net/reader034/viewer/2022051119/568bdd851a28ab2034b61ab9/html5/thumbnails/39.jpg)
Thank you!