25 Holyoke McCabe Enterprises Part A: Overview Building Overview Regulatory Context Existing Conditions Part B: Approach First Phase: Stabilize Part C: Development Scenarios Scenario 1: Incremental Scenario 2: Full Redevelopment Part D: Pro Formas 3.1 106-120 High St.

Upload: others

Post on 08-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

25HolyokeMcCabe Enterprises

Part A: Overview Building Overview Regulatory Context Existing Conditions

Part B: Approach First Phase: Stabilize

Part C: Development Scenarios Scenario 1: Incremental Scenario 2: Full Redevelopment

Part D: Pro Formas

3.1 106-120

High St.

Page 2: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

26 Holyoke McCabe Enterprises

Page 3: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

27McCabe Enterprises Holyoke | 106-120 High Street

Part A: Overview 106 - 120 High Street

Building Overview

106-120 High Street consists of four Italianate structures, that are a contributing part of the High Street Historic District of Holyoke. The four buildings were designed and built to pres-ent the appearance of a single unified block. The buildings are a part of what was once an important commercial district in Holyoke in the mid-1800’s to early 1900’s. There was original-ly a fifth structure in this row at 122-124 High Street, however this building was torn down and is now a vacant lot.

106-108 High Street, is the more elaborate of the four struc-tures, with a slightly taller corbeled cornice and decorative window heads. This detail is typical of a Civil War era period building, but the date of construction is unknown. It is esti-mated in the MACRIS database to have been built between 1860-1870.

The adjacent 110-120 High Street buildings are likewise four stories, but are slightly lower in elevation and less ornate in detailing. They are estimated in the MACRIS database to have been built in the 1870’s.

204.0296.0

5

5 56.74

56.74

24.25

24.79

73.86

73.32

48.88

48.88 48.88 48.88

48.88 48.88

24.44

24.4424.44

24.44

90.0100.0

73.32

73.3273.32

73.32

24.4424.44

24.44 24.4424.42 24.42

24.4224.42

48.88

48.8848.88

48.88

150.0

196.0 196.0

150.0

150.0

80.0

80.0

80.0

48.5

49.024.88

122.17

122.17

44.0

54.05

49.46

39.42

24.74

55.27

25.33

42.03

42.04

HIGH ST

LYM

AN

ST

LYM

AN

ST

MAPLE ST

1

5

14

7

14A

6

1

6

1378

1

1918

123

1716

4

15

854.11

4

Property Location

22

122.17

122.17

22

6

Image from the Massachusetts Historical Commission Archives

Page 4: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

28 McCabe EnterprisesHolyoke | 106-120 High Street

Regulatory Context

106-120 High Street is located in the BC Downtown Business zoning district, as well as the Downtown Smart Growth Zoning Overlay (40R) District. Permitted uses in the BC Down-town Business zone include retail, personal services, business or professional offices, banks, financial services, restaurant, convenience store, and residential uses. The Downtown Smart Growth Zoning Overlay District seeks to encourage mixed-use development, redevelopment and adaptive re-use of existing structures. Mixed-use development is allowed as-of-right at this site. Accessory parking uses are also allowed as of right.

The parking requirements for the Downtown Smart Growth Zoning Overlay District state that 1 parking space per residential unit shall be provided. A reduction in parking require-ments is permitted, if it can be demonstrated that lesser parking will not cause excessive con-gestion or endanger public safety. Moreover, reduction in the parking requirement will be considered if a positive environmental benefit exists with less parking.

Commercial parking requirements for the BC Downtown Business zone require 1 parking space for every 300 gross SF of retail or office space, or parking space for every gross 400 SF of a personal services establishment. The existing street level gross square footage amounts to 7,880 SF. Under existing requirements, 26 parking spaces would be required for retail stores on the ground level. The Holyoke Planning Board has the authority to grant reductions in the parking space requirement. Since the 106-120 High Street buildings were first erected in 1860s-1870s, prior to enactment of zoning and used for mixed-used development (ground floor commercial and upper level residential), one could posit that the parking requirements may not apply to this series of buildings if the original uses continue. The ground level is currently used for retail stores.

The 106-120 High Street site includes a “vacant” lot at the corner of High Street and Oliver, which could be used for parking. Six parking spaces can be accom-modated on this property, with perhaps an additional space squeezed in. This would provide a planting buffer along High Street, but would require additional curb cut access off of Oliver Street. Parking in the lower level with access from the alley is another approach for a few more spaces. From a market perspective, reha-bilitation of the upper stories for housing will require some provision of convenient parking for residential users on site

106-120 High Street is outside the flood plain. There are no known wetlands or protected vegetation or wild-life in the vicinity.

This series of buildings is located within the North High Street Historic District, listed on the National Register of Historic Places. As such, any assistance us-ing state or federal funds, including historic tax credits,

Holyoke Zoning Map

Page 5: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

29McCabe Enterprises Holyoke | 106-120 High Street

will trigger review by the Massachusetts Historical Commission (MHC) so that the reno-vation and rehabilitation work is consistent with the historic architectural character of the building. Consultation with MHC at the outset typically more cost effective, particularly if use of the 20% historic tax credits is anticipated. MHC and the National Park Service must certify all 20% historic tax credit projects. Use of the 10% federal historic tax credit does not require certification.

106-120 High Street facade.

Oliver Street elevation and adjacent lot.

Page 6: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

30 McCabe EnterprisesHolyoke | 106-120 High Street

106 - 120 HIGH STREET

General 106-120 High Street consist of four mixed-use buildings with ground level commercial/ retail space and what was once upper level housing space. The buildings are four-story brick Ital-ianate structures (c. 1870). The historic details of the facades include brick quoins, segmen-tal-arched windows and bracketed cornices.

Basement The basement was not accessible on the visit, so conditions are unknown. Exterior base-ment walls were observed from the alley at the rear of the building: walls are in poor condi-tion and require extensive patching, repair and re-pointing.

First Floor The first floor of all four buildings is occupied by a single retail space (convenience store) operated by the building owner. There are some original elements such as the entry doors at 106 High and steel or cast iron columns on several storefronts, while others have been re-placed over time with a range of materials. Currently only one of the storefronts, 114-116 High, is used as the entry to the shop. On the interior, walls have been opened up between the four buildings in order to function as a single space. A number of structural modifications seem to have been made on the interior. In some spaces original ceiling finishes remain intact and could be refurbished. Generally the space is operational but would benefit from upgrades.

Second Floor Some demolition has been done on the second floor of 106-108 High. While many of the original partitions remain, the space is in disrepair and in need of complete renovation. The second floor of 110-112, 114-116 and 118-120 High. 114-120 High are in use as a furniture show-room, while 110-112 is mainly used for storage. Second floor of these buildings are in need of renovation and code upgrades.

Third Floor Upper levels were accessed in 106-108 and 114-116 High Street. In 106-108 High, walls on the third floor have been stripped down to studs in some areas, particularly in the stairwell on the southwest side where fire damage is evident. In 114-116 High, all partitions on the third floor have been stripped down to the studs; ceiling and floor finishes have been removed; all plumbing fixtures and most pipes have been removed as well.

Fourth Floor Upper levels were accessed in 106-108 and 110-112 High Street. In 106-108 High, almost all partitions and most of the ceiling finishes have been completely removed; fire damage is evident on the southeast wall and roof framing. In 110-112 High, all partitions on the third floor have been stripped down to the studs; ceiling and floor finishes have been removed; all plumbing fixtures and most pipes have been removed as well.

Roof Access to the roof was not available. In the two buildings where upper floors were accessed, there was evidence of roof leaks, suggesting a need for repair or replacement of the roof along with repairs to interior damage. Cap/ flashing repairs appear to be needed for all buildings.

Stairs & Elevators

106-120 High Street represent 4 individual buildings, each with their own circulation. None of the buildings has an elevator. Each has a main stair running the length of the northeast side of the building and accessed through an entry from High Street. A separate basement access stair down from the first floor also runs along the northeast side of the building. Con-dition of staircases varies, and not all were accessible at the time of the visit.

Exterior Minor re-pointing needed to exterior brick walls on the northwest elevation. Moderate re-pointing needed on exterior brick walls on southwest elevation of building. Some parapet wall repair needed. Extensive repair and re-pointing needed on the southeast face of build-ing along the alleyway (basement and first floor levels). Masonry in need of cleaning/ power washing.

Systems Heating equipment in the basement was not accessible on the visit and could not be as-sessed. Electrical panels similarly were not accessible. Electric was not readily visible either.

The building is in need of an updated sprinkler system and a fire safety system was no visible.

Structural Floor and stair framing in 106-108 High Street has been compromised by a fire. The fire damage is mainly in the stairwell on the southwest side of the building, and throughout the fourth floor. Foundations were not accessible for observation. Framing that was visible in 110-120 High was in fair to good condition, however, size of framing members may be insuffi-cient for current code standards.

Other There is a vacant lot to the southeast adjacent to 120 High Street. Ideally this lot could be combined with the 104-120 High properties as part of a redevelopment scenario.

exis

tin

g c

on

dit

ion

s

Page 7: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

31McCabe Enterprises Holyoke | 106-120 High Street

Top: elevation of 106-108 High Street.

Middle: ground level storefront details.

Bottom: southeast elevation at rear alley.

Page 8: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

32 McCabe EnterprisesHolyoke | 106-120 High Street

106 - 108 High Street

Interior conditions on upper levels of 106-108 High Street.

Page 9: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

33McCabe Enterprises Holyoke | 106-120 High Street

110-112 High Street

Interior conditions on upper levels of 110-112High Street.

Page 10: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

34 McCabe EnterprisesHolyoke | 106-120 High Street

110-112 High Street

Interior conditions on upper levels of 110-112 High Street. Lower right image shows roof conditions at rear.

Page 11: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

35McCabe Enterprises Holyoke | 106-120 High Street

114-116 High Street

Interior conditions on upper levels of 114-116 High Street.

Page 12: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

36 McCabe EnterprisesHolyoke | 106-120 High Street

106 - 120 High Street

Top, middle: interior of ground floor business showing historic ceiling details.Bottom: second floor furniture showroom and storage area showing damaged ceiling.

Page 13: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

37McCabe Enterprises Holyoke | 106-120 High Street

APPROACH: 106 - 120 HIGH STREET

First Phase Approach

Provide basic improvements / stabilization for buildings (all addresses).

General Protect building structure

• Identify source of water leaks (roof, windows, flashing) and repair to make building water-tight. • Properly board any broken windows on upper floors.

Clean-up/ refresh ground floor storefronts

• Repaint entrances; doors and ground floor woodwork, window and store frames.• Provide new signage and exterior lights.

Second through Fourth Floors

Upper level make-safe

• Clean-up entry areas on street level and at rear exits. • Remove and dispose of all debris in vacant spaces, including debris at stairwells.• At ground level business area, clean/ re-merchandise to provide clear path of travel and access to second means of egress.• At occupied second floor areas move furniture and other items to ensure a clear path of travel to stairs and exits.

first phase

firs

t p

has

e: s

tab

ilize

• improve storefronts

• properly board broken windows

upper levels: remove trash and clear stairs/ paths of egress

retail level: provide clear paths of egress

Part B: Approach 106 - 120 High Street

Page 14: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

38 McCabe EnterprisesHolyoke | 106-120 High Street

Scenario 1

Renovate/ redevelop each building incrementally

SCOPE: 106 - 120 HIGH STREET

Overview Scenario 1 proposes renovating each of the four buildings incrementally based on market demand. Buildings would include a retail/commercial space on the ground level, and upper level residential.

Basement The basement would remain primarily space for building services. It could provide storage or support space for the retail/commercial component, particularly as the exposed rear alley allows for excellent service access for deliveries.

First Floor The first floor of each building would be renovated for commercial use. Phasing of the de-velopment would allow the existing business to consolidate to remaining storefronts while construction of the first storefront is in progress. The new retail area could then be leased to a new tenant after renovation.

Second through Fourth Floors

In this scenario, the second through fourth floors would be developed as housing. Units could be sold as condos, or rented as apartments. 110-120 High most likely would be devel-oped with one unit per floor, and two bedrooms per unit. 106-108 High has the potential for two units per floor due to its larger floor plate.

Systems In this scenario, each building would have its own new systems installed: new fire protection and life safety systems are needed. New electrical and plumbing required throughout; new HVAC will be required.

106 - 120 HIGH STREET: BUILDING AREAS (sf)

Basement First Second Third Fourth Total

106-108 High 1,970 1,970 1,970 1,630 1,630 9,170

110-112 High 1,970 1,970 1,970 1,490 1,490 8,890

114-116 High 1,970 1,970 1,200 1,200 1,200 7,540

118-120 High 1,970 1,970 1,200 1,200 1,200 7,540

33,140

scen

ario

1: i

ncr

emen

tal

Part C: Development Scenarios 106 - 120 High Street

Page 15: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

39McCabe Enterprises Holyoke | 106-120 High Street

23'-6"

High Street elevation.

Scenario 1: ResidentialUnit Layouts

(Second Floor)

106-108 110-112 114-116 118-120

900sf 900sf

1,090sf

900sf

670sf

Page 16: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

40 McCabe EnterprisesHolyoke | 106-120 High Street

SCOPE: 106 - 120 HIGH STREET

Overview Scenario 2 proposes a complete redevelopment of the properties at 106-120 High Street. Given the condition of the interiors of the properties, the need for extensive upgrades to meet current life-safety and energy codes, and the poor condition of the brick exterior walls at the rear of the building, full redevelopment may prove to be the best course of action.

The buildings sit within the North High Street Historic District, and care to preserve sig-nificant features that contribute to the overall district would be required. In this case, the facades and cornice line along High Street would need to be maintained. Changes to the storefront will need to replicate look and organization of historic storefronts.

Adjacent property could also be considered as part of the redevelopment effort. The vacant lot to the southwest could be acquired for parking or as are for additional development.

Basement The basement would include space for building service including utilities and trash. Given the full story difference in grade elevation between High Street and the rear alleyway (run-ning between Lyman and Oliver Streets), parking at the basement level below the building could easily be accommodated.

First Floor The first floor would be developed as retail / commercial space in keeping with the historic pattern of the streetscape and the storefront openings of the historic facades. With rede-velopment, stairs, elevators and circulation for the four addresses can be combined and will provide an economy of space.

Second through Fourth Floors

With complete redevelopment of the site, programming for the upper floors is much more flexible. The second, third and fourth floors could be developed as commercial office, institu-tional or residential depending on market demand.

OFFICE: New construction of office space is one option. Depending on user, total leasable area would be in the range of 4,500 - 5,000 sf

RESIDENTIAL: Construction of new residential is shown for upper floors. In this scenario, there is a fair amount of flexibility regarding occupancy type. Floor plates could be divided into smaller units for an assisted living or adult care home. Or, they could be designed as larger market rate units.

Systems Complete new building systems: HVAC, plumbing, electric, and fire protection are needed. Scale of redevelopment will require an elevator.

scen

ario

2: f

ull

red

evel

op

men

t

residential commercial (retail or office)

Scenario 2

retain facades

all new construction

Page 17: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

41McCabe Enterprises Holyoke | 106-120 High Street

106-120 High Street Pro Forma

The first set of pro formas presented for 106-120 High Street uses the Incremental Hybrid Scenario which focuses on base stabilization of the buildings including life safety measures and upgrading of the storefronts on the ground level. Two different methods of financing were assessed, a conventional financing approach with a 5% loan amortized over twenty years and a low-interest loan with a 4.25% loan, again amortized over a twenty year period. Each alter-native calls for a ten percent owner’s equity investment of approximately $23,000. The initial cost estimate for base stabilization improvements is $204,000.

Revenue in the Incremental Hybrid Scenario is based on leasing the ground level storefronts at $7.50/SF. The four storefronts are currently 100% occupied with the owner-run general store/convenience store that serves neighborhood residents. This rent level is based on the assump-tion that owner-occupied businesses tend to charge themselves a lower rent than market rate. Market rate retail rents in downtown Holyoke are in the neighborhood of $8 to $12.00/SF depending upon location and quality of the space. As storefronts are rehabilitated, the owner could opt to continue to use all four storefronts or to consolidate retail operations, and lease one or more storefronts at market rate rents.

A summary comparing the two alternatives for financing the Incremental Hybrid approach for 106-120 High Street follows.

106-120 High Street – Incremental Hybrid Scenario

Option Base Stabilization

Financing Tool Conventional

FinancingLow Interest

Loan Financing

Total Hard & Soft Costs $204,039 $204,039

Total Permanent Financing Need $227,482 $226,486

Interest Rate 5.00% 4.25%

Net Operating Income $35,104 $35,104

Loan Amount $204,733 $203,837

Annual Debt Service $18,015 $16,830

Debt Service Cost Per SF of Leased Area $2.42 $2.26

Debt Service Cost Per Building SF $0.54 $0.51

Funds Available Annually for Reinvestment in Building. Improvements $17,089 $18,275

Owner’s Equity* $22,748 $22,649

Part D: Pro Formas 106 - 120 High Street

Page 18: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

42 McCabe EnterprisesHolyoke | 106-120 High Street

Full Redevelopment Approach Summary

The analysis of the full redevelopment examined four alternatives, namely:

• Scenario 2A: Full redevelopment of all four buildings with ground level retail and upper level residential, with a total of 15 residential units.

• Scenario 2B: Full redevelopment of all four buildings, using a phased approach starting with one building. Uses will be ground-level retail and upper-story residential.

• Phase I in Scenario 2B begins the phased full redevelopment with106-108 High Street, the building to the furthest north, and analyzes the feasibility of undertaking one building at a time. 106-108 High Street is the largest of the four buildings, with a total of 9,170 SF.

• Phase IV in Scenario 2B begins the phased full redevelopment with 118-120 High Street, the most southern building which adjoins the vacant lot on Main Street and Oliver. 118-120 High Street has 7,540 SF, like is neighbor, 114-116 High Street. This is the smaller of the set of buildings.

• Scenario 2C: Full redevelopment of all four buildings with ground level retail and upper level office, with a total of 17,380 gross SF of office that could be rented to several large or many smaller users.

The bedroom mix and type of the proposed fifteen residential units includes four efficiency/studio units and 11 two-bedroom units. The same bedroom/size mix is used for each of the alternatives, 2A, 2B-phase I; and 2B-phase IV.

The financial feasibility of the phased approach was tested with the two end buildings, which happened to include the largest and smallest buildings by area. A phased approach was ana-lyzed since the full redevelopment of all four buildings identified a huge financing gap that appeared unrealistic to close. Unfortunately, the full redevelopment approach, even with a phased approach of one-building at a time proven financially unworkable, as well. The results of the financial feasibility analysis are summarized in the following table.

Page 19: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

43McCabe Enterprises Holyoke | 106-120 High Street

106-120 High Street Full Redevelopment Approach Summary

Scenario 2A 2B 2B 2 C

Phase I IV

Description

Full Renovation with Ground Floor Retail & Residential (15 units)

Incremental Renova-tion with Ground floor Retail beginning with 106-108 High Street (6 residential units this phase, 15 total)

Incremental Renova-tion with Ground floor Retail, 3 residential units in this phase, 15 total)

Full Renovation with Ground Floor Retail & Upper-Story Office (3 levels)

Total Hard & Soft Costs $10,239,886 $9,159,028 $9,159,028 $10,019,395

Total Costs of Permanent Financing $11,130,493 $2,774,619 $2,253,032 $10,907,797

Equity Requirement $1,000,000 $200,000 $200,000 $1,000,000

Return on Equity 3.6% 9.3% 4.3% 4.9%

Gap $(5,570,936) $(844,962) $(948,082) $(2,381,704)

Key Challenges

Greater initial equity and financing required. Requires major Historic Tax Credits and NMTC allocation. Low market rate rent structures.

Residential and retail rent structure low; inefficient floor plates. Off-street parking

Residential and retail rent structure low; inefficient floor plates. Off-street parking.

Locating an office user; Parking. Re-quires major Historic Tax Credits & NMTC al-locations. Low market rate rent structures.

Page 20: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

44 McCabe EnterprisesHolyoke | 106-120 High Street

Page 21: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170 110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890 114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540 118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 3rd floor 5,520 4th floor 5,520 Basement 7,880 Total 33,140

Hard CostsAcquisition* -$ Site Work -$ Construction Hard Costs 124,100$ General Conditions, Bonds, Insurance, Overhead 16,009$ Escalation 0.06 7,446$ Permits 1,364$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & EquipmentDesign & Pricing Contingency 22,338$ LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 171,257$

1Stabilization of building with securing building envelope and life safety code compliance. Conventional

Incremental Hybrid Approach

McCabe Enterprises Holyoke | 106-120 High Street 45

Page 22: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

1Stabilization of building with securing building envelope and life safety code compliance. Conventional

Incremental Hybrid Approach

Soft CostsArch'l & Engineering 5.00% 6,205$ Other Consultants 1.50% 1,862$ Project Management 3.50% 4,344$ Legal 1.00% 1,241$ Utilities 0.25% 310$ Marketing -$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 1,561$

SUB-TOTAL SOFT COSTS 32,782$

Total Hard & Soft Costs, before Financing Costs 204,039$

Loan Financing CostsLegal, Escrow, Title 10,000$ Loan Fees 1% 1,928$ Appraisal 5,000$ Interest Construction Loan 12 months 5.00% 6,515$ Permanent Financing Need 227,482$

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor Retail * 7880 7.50$ 59,100$ Basement (storage) 1.25$ -$ Office -$ Residential -$ Sub-Total 59,100$

7.5% Discount for Vacancies 7.50% (4,433)$ Effective Gross Income 54,668$

ExpensesMaintenance 10% 5,467$ Taxes 8,630$ Utilities 7.5% 4,100$ Management 2.5% 1,367$ Net Operating Income 35,104$

106-120 High Street Initial Operating Income for Phase 1 Stabilization Using Incremental Hybrid Approach

46 Holyoke | 106-120 High Street McCabe Enterprises

Page 23: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

1Stabilization of building with securing building envelope and life safety code compliance. Conventional

Incremental Hybrid Approach

FinancingDebt Service Coverage 1.25Amount Available for Debt Service 28,083$ Maximum Loan at Debt Service Constant $425,506Financing Gap/(Surplus) (Loan Need less Amt of Loan w DSC) (198,025)$ Actual Loan 204,733$ Annual Debt Service Payment 18,015

Amortization Period 20 yearsInterest Rate 5.00%Debt Service Constant 6.600%

Cash Flow -- Year OneEffective Gross Income 54,668$ Net Operating Income 35,104$ Annual Debt Service 18,015$ Surplus/deficit 17,089$ To be reinvested in annual bldg. improvementsYear 1 Return on Equity 75.1%

SOURCES & RETURNSConventional Loan 204,733$ Equity Requirement 22,748$ Owner Equity Contribution

Sub-Total 227,482$

Sources to be Identified -$

State Abandoned Bldg. Tax Deduction

17,089$������������

10% tax deduction of renovation costs of buildings that are 75% or more vacant as to personal or corporate MA income. Benefit is variable as to the tax rate of the Owner.

Surplus Funds for Continual Annual Building Improvements

* 106-120 High Street is an owner-occupied commercial building. The owner operates a retail convenience/general store in all four storefronts. Owner occupants tend to charge themselves below market rental rates.

McCabe Enterprises Holyoke | 106-120 High Street 47

Page 24: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170 110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890 114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540 118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 3rd floor 5,520 4th floor 5,520 Basement 7,880 Total 33,140

Hard CostsAcquisition -$ Site Work -$ Construction Hard Costs 124,100$ General Conditions, Bonds, Insurance, Overhead 16,009$ Escalation 0.06 7,446$ Permits 1,364$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & EquipmentDesign & Pricing Contingency 22,338$LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 171,257$

1Stabilization of building with securing building envelope and life safety code compliance. Low Interest

Incremental Hybrid Approach

48 Holyoke | 106-120 High Street McCabe Enterprises

Page 25: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

1Stabilization of building with securing building envelope and life safety code compliance. Low Interest

Incremental Hybrid Approach

Soft CostsArch'l & Engineering 5.00% 6,205$ Other Consultants 1.50% 1,862$ Project Management 3.50% 4,344$ Legal 1.00% 1,241$ Utilities 0.25% 310$ Marketing -$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 1,561$

SUB-TOTAL SOFT COSTS 32,782$

Total Hard & Soft Costs, before Financing Costs 204,039$

Loan Financing CostsLegal, Escrow, Title 10,000$ Loan Fees 1% 1,918$ Appraisal 5,000$ Interest Construction Loan 12 months 4.25% 5,529$ Permanent Financing Need 226,486$

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor Retail * 7880 7.50$ 59,100$ Basement (storage) 1.25$ -$ Office -$ Residential -$ Sub-Total 59,100$

7.5% Discount for Vacancies 7.50% (4,433)$ Effective Gross Income 54,668$

ExpensesMaintenance 10% 5,467$ Taxes 8,630$ Utilities 7.5% 4,100$ Management 2.5% 1,367$ Net Operating Income 35,104$

106-120 High Street Initial Operating Income for Phase 1 Stabilization Using Incremental Hybrid Approach

McCabe Enterprises Holyoke | 106-120 High Street 49

Page 26: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 PhaseBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

1Stabilization of building with securing building envelope and life safety code compliance. Low Interest

Incremental Hybrid Approach

FinancingDebt Service Coverage 1.25Amount Available for Debt Service 28,083$ Maximum Loan at Debt Service Constant $453,544Financing Gap/(Surplus) (Loan Need less Amt of Loan w DSC) (227,058)$ Actual Loan 203,837$ Annual Debt Service Payment 16,830

Amortization Period 20 yearsInterest Rate 4.25%Debt Service Constant 6.192%

Cash Flow -- Year OneEffective Gross Income 54,668$ Net Operating Income 35,104$ Annual Debt Service 16,830$ Surplus/deficit 18,275$ To be reinvested in annual bldg improvementsYear 1 Return on Equity 80.7%

SOURCES & RETURNSConventional Loan 203,837$ Equity Requirement 22,649$ Owner Equity Contribution

Sub-Total 226,486$

Sources to be Identified -$

State Abandoned Bldg Tax Deduction

18,275$������������

10% tax deduction of renovation costs of buildings that are 75% or more vacant as to personal or corporate MA income. Benefit is variable as to the tax rate of the Owner.

Surplus Funds for Continual Annual Building Improvements

* 106-120 High Street is an owner-occupied commercial building. The owner operates a retail convenience/general store in all four storefronts. Owner occupants tend to charge themselves below market rental rates.

50 Holyoke | 106-120 High Street McCabe Enterprises

Page 27: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170 110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890 114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540 118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 Residential 3rd floor 5,520 Residential 4th floor 5,520 Residential Basement 7,880 Support space for 1st flr retail + ParkingTotal 33,140

Hard CostsAcquisition* -$ Site Work -$ Construction Hard Costs 6,320,072$ General Conditions, Bonds,Insurance, Overhead 815,289$ Escalation 0.06 379,204$ Permits 69,428$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & Equipment 228,591$Design & Pricing Contingency 1,010,553$ Escalation to mid point (2 yrs) 336,854$ LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 9,159,991$

2AFull Redevelopment:15 Upper-Level Residential Units with Street-level Retail

McCabe Enterprises Holyoke | 106-120 High Street 51

Page 28: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2AFull Redevelopment:15 Upper-Level Residential Units with Street-level Retail

Soft CostsArch'l & Engineering 7.25% 458,205$ Other Consultants 1.50% 94,801$ Project Management 5.00% 316,004$ Legal 1.00% 63,201$ Utilities 0.25% 15,800$ Marketing 1.00% 63,201$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 51,424$

SUB-TOTAL SOFT COSTS 1,079,895$

Total Hard & Soft Costs, before Financing Costs 10,239,886$

Loan Financing CostsLegal, Escrow, Title 10,000$ Loan Fees 1% 99,510.88$ Appraisal 5,000$ Interest Construction Loan 18 months 5.0% 776,097$ Permanent Financing Need 11,130,493$

Operating Income for Scenario 2A

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor retail 7880 10.00$ 78,800$ Basement (storage) 1.25$ -$ Resl --1 bdrm 0 10,488$ -$ Resl -- 2 brdm 11 12,408$ 136,488$ Resl -- 3 bdrm 0 13,944$ -$ Studio/Efficiencies 4 8,796$ 35,184$ Sub-Total 250,472$

7.5% Discount for Vacancies 7.50% (16,147)$ Effective Gross Income 234,325$

ExpensesMaintenance 10% 23,433$ Taxes 8,630$ Utilities 7.5% 17,574$ Management 2.5% 5,858$ Net Operating Income 178,831$

52 Holyoke | 106-120 High Street McCabe Enterprises

Page 29: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2AFull Redevelopment:15 Upper-Level Residential Units with Street-level Retail

FinancingDebt Service Coverage 1.25Amount Available for Debt Service 143,064$ Amount of Loan at Debt Service Constant $2,220,808Annual Debt Service Payment 143,064

Amortization Period 30 yearsInterest Rate 5.00%Debt Service Constant 6.442%

Cash Flow -- Year OneEffective Gross Income 234,325$ Net Operating Income 178,831$ Annual Debt Service 143,064$ Surplus/deficit 35,766$ Year 1 Return on Equity 3.6%

SOURCES & RETURNSNew Market Tax Credits 450,000$ $1M NMTC allocation sold at $.55/$1 of credit less add'l legal ($100,000)Historic Tax Credits -- Federal 1,268,876$ 20% of HRTC eligible basis sold at $.60 of equity per $1 of creditState Historic Tax Credits 600,000$ Allocation of $1,000,000 anticipated at $0.6 per $1 of creditEquity Requirement 1,000,000$ Private Equity or Community Investment Grant for EquityPermanent Loan 2,220,808$ Conventional Financing, 5% at 30 yearsSRECs 19,872$ 1 time payment for SRECS for entire complex

Sub-Total 5,559,557$

Sources to be Identified (5,570,936)$

(371,396)$ Required subsidy per housing unit.

McCabe Enterprises Holyoke | 106-120 High Street 53

Page 30: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 Residential 3rd floor 5,520 Residential 4th floor 5,520 Residential Basement 7,880 Support space for ground level commercial Total 33,140

Hard CostsAcquisition* -$ Site Work -$ Construction Hard Costs 5,614,232$ General Conditions, Bonds, Insurance, Overhead 724,237$ Escalation 0.06 336,854$ Permits 61,700$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & Equipment 113,285$ Design & Pricing Contingency 1,010,553$ Escalation to mid point (2 yrs) 336,854$ LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 8,197,715$

2 BIncremental Full RedevelopmentResidential with Street level Retail Phase I

54 Holyoke | 106-120 High Street McCabe Enterprises

Page 31: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2 BIncremental Full RedevelopmentResidential with Street level Retail Phase I

Soft CostsArch'l & Engineering 7.25% 407,032$ Other Consultants 1.50% 84,213$ Project Management 5.00% 280,712$ Legal 1.00% 56,142$ Utilities 0.25% 14,036$ Marketing 1.00% 56,142$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 45,777$

SUB-TOTAL SOFT COSTS 961,313$

Total Hard & Soft Costs, before Financing Costs 9,159,028$

Cost Allocation of Hard & Soft Costs to Enable Incremental Implementation by Building

SF Bldg Area Percentage

Cost Allocation Phase

106-108 High Street 9,170 27.7% 2,534,348$ I110-112 High Street 8,890 26.8% 2,456,963$ II114-116 High Street 7,540 22.8% 2,083,859$ III118-120 High Street 7,540 22.8% 2,083,859$ IV

Loan Financing Costs for Phase ILegal, Escrow, Title for Phase I 10,000$ Loan Fees 1% 27,471$ Appraisal 5,000$ Interest Construction Loan 18 months 5.0% 197,800$ Permanent Financing Need for Phase I 2,774,619$

Operating Income for Phase I, Scenario 2B

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor retail 7880 8.50$ 66,980$ Basement (storage) 7880 1.00$ 7,880$ Resl --1 bdrm 0 10,488$ -$ Resl -- 2 bdrm 2 12,408$ 24,816$ Resl -- 3 bdrm 0 13,944$ -$ Studio/Efficiencies 4 8,796$ 35,184$ Sub-Total 134,860$

7.5% Discount for Vacancies 7.50% (7,476)$ Effective Gross Income 127,384$

McCabe Enterprises Holyoke | 106-120 High Street 55

Page 32: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2 BIncremental Full RedevelopmentResidential with Street level Retail Phase I

Expenses for Phase I, Scenario 2BMaintenance 10% 12,738$ Taxes 8,630$ Utilities 7.5% 9,554$ Management 2.5% 3,185$ Net Operating Income 93,278$

Financing for Phase I, Scenario 2BDebt Service Coverage 1.25Amount Available for Debt Service 74,622$ Amount of Loan at Debt Service Constant 1,158,370$ Annual Debt Service Payment 74,622$

Amortization Period 30 yearsInterest Rate 5.00%Debt Service Constant 6.442%

Cash Flow -- Year OneEffective Gross Income 127,384$ Net Operating Income 93,278$ Annual Debt Service 74,622$ Surplus/deficit 18,656$ Year 1 Return on Equity 9.3%

SOURCES & RETURNS New Market Tax Credits 112,500$ NMTC allocation sold at $.55/ $1 of credit less add'l legal ($25,000/phase)Historic Tax Credits -- Federal 288,916$ 20% of HRTC eligible basis sold at $.60 of equity per $1 of creditState Historic Tax Credits 150,000$ Allocation of $250,000 anticipated at $0.6 per $1 of creditEquity Requirement 200,000$ Owner/Private Equity or Community Investment Grant for EquityPermanent Loan 1,158,370$ Conventional Financing, 5% at 30 yearsSRECS 19,872$

Sub-Total 1,929,657$

Sources to be Identified (844,962)$

1 time payment for SRECS for entire complex (Assumes rehab begins withPhase 1, 106-108 High St. , if this is a later phase, SRECS cannot be counted as revenue twice.)

Current market conditions and costs do not support incremental development starting with Phase I (106-108 High St.), using a phased approach for Full Redevelopment.

56 Holyoke | 106-120 High Street McCabe Enterprises

Page 33: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170 110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890 114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540 118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 Residential 3rd floor 5,520 Residential 4th floor 5,520 Residential Basement 7,880 Support area for ground level com'l or leased storageTotal 33,140

Hard CostsAcquisition* -$ Site Work -$ Construction Hard Costs 5,614,232$ General Conditions, Bonds, Insurance, Overhead 724,237$ Escalation 0.06 336,854$ Permits 61,700$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & Equipment 113,285$Design & Pricing Contingency 1,010,553$ Escalation to mid point (2 yrs) 336,854$ LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 8,197,715$

2 BIncremental Approach to Full RedevelopmentResidential with Street level Retail Phase IV

McCabe Enterprises Holyoke | 106-120 High Street 57

Page 34: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2 BIncremental Approach to Full RedevelopmentResidential with Street level Retail Phase IV

Soft CostsArch'l & Engineering 7.25% 407,032$ Other Consultants 1.50% 84,213$ Project Management 5.00% 280,712$ Legal 1.00% 56,142$ Utilities 0.25% 14,036$ Marketing 1.00% 56,142$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 45,777$

SUB-TOTAL SOFT COSTS 961,313$

Total Hard & Soft Costs, before Financing Costs 9,159,028$

Cost Allocation of Hard & Soft Costs to Enable Incremental Implementation by Building

SF Bldg. Area Percentage

Cost Allocation Phase

106-108 High Street 9,170 27.7% 2,534,348$ I110-112 High Street 8,890 26.8% 2,456,963$ II114-116 High Street 7,540 22.8% 2,083,859$ III118-120 High Street 7,540 22.8% 2,083,859$ IV

Loan Financing Costs for Phase IVLegal, Escrow, Title for Phase I 10,000$ Loan Fees 1% 22,307$ Appraisal 5,000$ Interest Construction Loan 12 months 5.0% 131,867$ Permanent Financing Need for Phase I 2,253,032$

Operating Income for Phase IV, Scenario 2 B

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor retail 1970 15.50$ 30,535$ Basement (storage) 1970 1.00$ 1,970$ Resl --1 bdrm 0 10,488$ -$ Resl -- 2 bdrm 3 12,408$ 37,224$ Resl -- 3 bdrm 0 13,944$ -$ Studio/Efficiencies 0 8,796$ -$ Sub-Total 69,729$

7.5% Discount for Vacancies 7.50% (5,230)$ Effective Gross Income 64,499$

58 Holyoke | 106-120 High Street McCabe Enterprises

Page 35: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2 BIncremental Approach to Full RedevelopmentResidential with Street level Retail Phase IV

ExpensesMaintenance 10% 6,450$ Taxes 8,630$ Utilities 7.5% 4,837$ Management 2.5% 1,612$ Net Operating Income 42,970$

FinancingDebt Service Coverage 1.25Amount Available for Debt Service 34,376$ Amount of Loan at Debt Service Constant $533,620Annual Debt Service Payment 34,376

Amortization Period 30 yearsInterest Rate 5.00%Debt Service Constant 6.442%

Cash Flow -- Year OneEffective Gross Income 64,499$ Net Operating Income 42,970$ Annual Debt Service 34,376$ Surplus/deficit 8,594$ Year 1 Return on Equity 4.3%

SOURCES & RETURNSNew Market Tax Credits 112,500$ NMTC allocation sold at $.55/$1 of credit less add'l legal ($25000/phase)Historic Tax Credits -- Federal 288,916$ 20% of HRTC eligible basis sold at $.60 of equity per $1 of creditState Historic Tax Credits 150,000$ Allocation of $250,000 anticipated at $0.6 per $1 of creditEquity Requirement 200,000$ Owner/Private Equity or Community Investment Grant for EquityPermanent Loan 533,620$ Conventional Financing, 5% at 30 yearsSRECs 19,872$

Sub-Total 1,304,907$

Sources to be Identified (948,125)$

(316,042)$ Required additional subsidy per floor or per housing unit.

1 time payment for SRECS for entire complex (Assumes rehab begins with Phase IV (118-120 High St.) , if this is a later phase, SRECS cannot be counted as revenue twice.)

McCabe Enterprises Holyoke | 106-120 High Street 59

Page 36: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

SF per floor & building Bsmt Ground Floor 2nd Flr 3rd Flr 4th Flr Total106-108 High Street 1,970 1,970 1,970 1,630 1,630 9,170 110-112 High Street 1,970 1,970 1,970 1,490 1,490 8,890 114-116 High Street 1,970 1,970 1,200 1,200 1,200 7,540 118-120 High Street 1,970 1,970 1,200 1,200 1,200 7,540

Assessed ValuationLand 25,600$

Roof Area 7,880 Building 189,900$ Extra Features 1,600$

Gross Leasable Space 25,260 Total 217,100$

Building Area SF Proposed UseGround floor (street) 7,880 Continued use as retail2nd floor 6,340 Office3rd floor 5,520 Office4th floor 5,520 OfficeBasement 7,880 Support space for 1st flr retail + parkingTotal 33,140

Hard CostsAcquisition* -$ Site Work -$ Construction Hard Costs 6,320,072$ General Conditions, Bonds, Insurance, Overhead 815,289$ Escalation 0.06 379,204$ Permits 69,428$ Demolition -$ Hazardous Materials/Abatement -$ Tenant Improvements -$ Furniture, Fixtures & Equipment 8,100$Design & Pricing Contingency 1,010,553$ Escalation to mid point (2 yrs) 336,854$ LEED Premium (not applied) 3% -$

SUB-TOTAL HARD COSTS 8,939,500$

2CFull Redevelopment:Upper Story Office with Street-level Retail

60 Holyoke | 106-120 High Street McCabe Enterprises

Page 37: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2CFull Redevelopment:Upper Story Office with Street-level Retail

Soft CostsArch'l & Engineering 7.25% 458,205$ Other Consultants 1.50% 94,801$ Project Management 5.00% 316,004$ Legal 1.00% 63,201$ Utilities 0.25% 15,800$ Marketing 1.00% 63,201$ Real Estate Taxes 17,259$

Soft Cost Contingency 5.00% 51,424$

SUB-TOTAL SOFT COSTS 1,079,895$

Total Hard & Soft Costs, before Financing Costs 10,019,395$

Loan Financing CostsLegal, Escrow, Title 10,000$ Loan Fees 1% 97,305.97$ Appraisal 5,000$ Interest Construction Loan 18 months 5.0% 776,097$ Permanent Financing Need 10,907,797$

Operating Income for Scenario 2 B

Units/ SF AverageAnnual Rent

Annual Gross Income

1st floor retail 7880 10.00$ 78,800$ Basement (storage) 1.25$ -$ Office 17,380 15.00$ 260,700$ Sub-Total 339,500$

7.5% Discount for Vacancies 7.50% (25,463)$ Effective Gross Income 314,038$

ExpensesMaintenance 10% 31,404$ Taxes 8,630$ Utilities 7.5% 23,553$ Management 2.5% 7,851$ Net Operating Income 242,600$

McCabe Enterprises Holyoke | 106-120 High Street 61

Page 38: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Site 106-120 High StreetLand Area 9,757 ScenarioBuilding Footprint SF 7,880 aggregatedFloors 4 Buildings 4

2CFull Redevelopment:Upper Story Office with Street-level Retail

FinancingDebt Service Coverage 1.25Amount Available for Debt Service 194,080$ Amount of Loan at Debt Service Constant $3,012,732Annual Debt Service Payment 194,080

Amortization Period 30 yearsInterest Rate 5.00%Debt Service Constant 6.442%

Cash Flow -- Year OneEffective Gross Income 314,038$ Net Operating Income 242,600$ Annual Debt Service 194,080$ Surplus/deficit 48,520$ Year 1 Return on Equity 4.9%

SOURCES & RETURNSNew Market Tax Credits 2,650,000$ $5M NMTC allocation sold at $.55/$1 of credit less add'l legal ($100000)Historic Tax Credits -- Federal 1,243,489$ 20% of HRTC eligible basis sold at $.60 of equity per $1 of creditState Historic Tax Credits 600,000$ Allocation of $1,000,000 anticipated at $0.6 per $1 of creditEquity Requirement 1,000,000$ Private Equity or Community Investment Grant for EquityPermanent Loan 3,012,732$ Conventional Financing, 5% at 30 yearsSRECs 19,872$ 1 time payment for SRECS for entire complex

Sub-Total 8,526,093$

Sources to be Identified (2,381,704)$

62 Holyoke | 106-120 High Street McCabe Enterprises

Page 39: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

209HolyokeMcCabe Enterprises

appendix

A1 HUD Lead-Based Paint Fact Sheet

A2 Flood Plain Map

A3.1 Cost Estimate: 106-120 High Street

A3.2 Cost Estimate: 276 High Street

A3.3 Cost Estimate: 200 Race Street

A3.4 Cost Estimate: 380/ 380R Dwight Street

A.4 Pro Forma Definitions

A

Page 40: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

210 Holyoke McCabe Enterprises

A1 HUD Lead-Based Paint Fact Sheet

Page 41: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

211HolyokeMcCabe Enterprises

A1 HUD Lead-Based Paint Fact Sheet

Page 42: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

212 Holyoke McCabe Enterprises

Page 43: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

HolyokeMcCabe Enterprises 213

flood plainmap

A2

Page 44: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

214 Holyoke McCabe Enterprises

Page 45: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

215HolyokeMcCabe Enterprises

FIRM Map with Study Building Locations Identified

study building

106-120 High

200 Race

380/380R Dwight

274 High

Page 46: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

Page 47: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe Enterprises Holyoke | Appendix

106-120 High Street

costestimateA

3.1

217

Page 48: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

Page 49: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Feasibility Submission

Holyoke; 106-120 High Street BuildingPHASE 1 Stabilization

Holyoke, MA

Prepared for:

McCabe Enterprises

April 8, 2014

Page 50: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street BuildingPHASE 1 Stabilization 08-Apr-14Holyoke, MA

Feasibility Submission

MAIN CONSTRUCTION COST SUMMARY

Gross FloorArea

$/sf EstimatedConstruction Cost

PHASE 1 STABILIZATION

32,660 $3.80 $124,100

SITEWORK - No Work Assumed NIC

HAZMAT REMOVALS NICSUB-TOTAL 32,660 $3.80 $124,100

GENERAL CONDITIONS 8% $9,928BONDS 0.65% $807INSURANCE 1.25% $1,551PERMIT 1.00% $1,364

OVERHEAD AND FEE 3% $3,7236.00% $7,446

15% $22,338

TOTAL OF ALL CONSTRUCTION - PHASE 1 32,660 $5.24 $171,257

ESCALATION TOMID-POINT (assumed 2years)

DESIGN AND PRICING CONTINGENCY

BUILDING STABILIZATION COSTS

Summary Page 2 PMC - Project Management Cost

Page 51: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street BuildingPHASE 1 Stabilization 08-Apr-14Holyoke, MA

Feasibility Submission

ITEMS NOT CONSIDERED IN THIS ESTIMATE

Items not included in this estimate are:All professional fees and insuranceBuilding Permit costsLand acquisition, feasibility, and financing costsAll Furnishings, Fixtures and EquipmentItems identified in the design as Not In Contract (NIC)Items identified in the design as by othersOwner supplied and/or installed items (e.g. draperies, furniture and equipment)Rock excavation; special foundations (unless indicated by design engineers)Utility company back charges, including work required off-siteWork to City streets and sidewalks, (except as noted in this estimate)

The estimate is based on prevailing wage rates for construction in this market and represents a reasonable opinion of cost. It is not aprediction of the successful bid from a contractor as bids will vary due to fluctuating market conditions, errors and omissions,proprietary specifications, lack or surplus of bidders, perception of risk, etc. Consequently the estimate is expected to fall within therange of bids from a number of competitive contractors or subcontractors, however we do not warrant that bids or negotiated prices willnot vary from the final construction cost estimate.

This estimate includes all direct construction costs, general contractor’s overhead and profit and design contingency. Cost escalationassumes start dates indicated.

These Feasibility Construction cost estimates were produced from drawings, outline specifications and other documentationprepared by McCabe Enterprises and their design team dated March, 2014. Design and engineering changes occurring subsequentto the issue of these documents have not been incorporated in this estimate.

Bidding conditions are expected to be public bidding under Chapter 149 of the Massachusetts General Laws to pre-qualified generalcontractors, and pre-qualified sub-contractors, open specifications for materials and manufactures.

Summary Page 3 PMC - Project Management Cost

Page 52: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

PHASE 1 STABILIZATIONA10 FOUNDATIONS

A1010 Standard Foundations $0A1020 Special Foundations $0A1030 Lowest Floor Construction $0 $0 $0.00 0.0%

A20 BASEMENT CONSTRUCTIONA2010 Basement Excavation $0A2020 Basement Walls $0 $0 $0.00 0.0%

B10 SUPERSTRUCTUREB1010 Upper Floor Construction $0B1020 Roof Construction $0 $0 $0.00 0.0%

B20 EXTERIOR CLOSUREB2010 Exterior Walls $5,000B2020 Windows $2,900B2030 Exterior Doors $10,000 $17,900 $0.55 14.4%

B30 ROOFINGB3010 Roof Coverings $7,880B3020 Roof Openings $0 $7,880 $0.24 6.3%

C10 INTERIOR CONSTRUCTIONC1010 Partitions $0C1020 Interior Doors $0C1030 Specialties/Millwork $0 $0 $0.00 0.0%

C20 STAIRCASESC2010 Stair Construction $0C2020 Stair Finishes $0 $0 $0.00 0.0%

C30 INTERIOR FINISHESC3010 Wall Finishes $0C3020 Floor Finishes $0C3030 Ceiling Finishes $0 $0 $0.00 0.0%

D10 CONVEYING SYSTEMSD1010 Elevator $0 $0 $0.00 0.0%

D20 PLUMBINGD20 Plumbing $0 $0 $0.00 0.0%

D30 HVACD30 HVAC $0 $0 $0.00 0.0%

Holyoke 106 High Street Estimate PH1 Scope Page 4 PMC - Project Management Cost

Page 53: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

PHASE 1 STABILIZATIOND40 FIRE PROTECTION

D40 Fire Protection $0 $0 $0.00 0.0%

D50 ELECTRICALD5010 New Electrical Systems $10,000 $10,000 $0.31 8.1%

E10 EQUIPMENTE10 Equipment $0 $0 $0.00 0.0%

E20 FURNISHINGSE2010 Fixed Furnishings $0E2020 Movable Furnishings NIC $0 $0.00 0.0%

F10 SPECIAL CONSTRUCTIONF10 Special Construction $0 $0 $0.00 0.0%

F20 HAZMAT REMOVALSF2010 Building Elements Demolition $88,320F2020 Hazardous Components Abatement $0 $88,320 $2.70 71.2%

TOTAL DIRECT COST (Trade Costs) $124,100 $3.80 100.0%

Holyoke 106 High Street Estimate PH1 Scope Page 5 PMC - Project Management Cost

Page 54: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

PHASE 1 STABILIZATION1 GROSS FLOOR AREA CALCULATION2

3 Areas Below are for 106 - 120 High Street4 Basement 7,8805 1st Floor 7,8806 2nd Floor 5,8607 3rd Floor 5,5208 4th Floor 5,5209

10 TOTAL GROSS FLOOR AREA (GFA) 32,660 sf11

12

13 A10 FOUNDATIONS14

15 A1010 STANDARD FOUNDATIONS16 NoWork in this section17 SUBTOTAL -18

19 A1020 SPECIAL FOUNDATIONS20 NoWork in this section21 SUBTOTAL22

23 A1030 LOWEST FLOOR CONSTRUCTION24 NoWork in this section25 SUBTOTAL26

27 TOTAL - FOUNDATIONS28

29

30 A20 BASEMENT CONSTRUCTION31

32 A2010 BASEMENT EXCAVATION33 NoWork in this section34 SUBTOTAL35

36 A2020 BASEMENTWALLS37 NoWork in this section38 SUBTOTAL39

40 TOTAL - BASEMENT CONSTRUCTION41

4243 B10 SUPERSTRUCTURE44

45 B1010 FLOOR CONSTRUCTION46 NoWork in this section47 SUBTOTAL48

49 B1020 ROOF CONSTRUCTION50 NoWork in this section51 SUBTOTAL52

53 TOTAL - SUPERSTRUCTURE54

55

56 B20 EXTERIOR CLOSURE57

58 B2010 EXTERIORWALLS

Holyoke 106 High Street Estimate PH1 Scope Page 6 PMC - Project Management Cost

Page 55: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

PHASE 1 STABILIZATION59 New exterior signage 1 ls 5,000.00 5,000

60 SUBTOTAL $5,00061

62 B2020 WINDOWS63 Board up damaged windows 6 loc 150.00 900

64 Repair water leaks 1 ls 2,000.00 2,00065 SUBTOTAL $2,90066

67 B2030 EXTERIOR DOORS68 Repaint/repair exterior doors and storefront 1 ls 10,000.00 10,000

69 SUBTOTAL 10,00070

71 TOTAL - EXTERIOR CLOSURE $17,90072

73

74 B30 ROOFING75

76 B3010 ROOF COVERINGS77 Flat roofing78 Repair water leaks 7,880 sf 1.00 7,88079 SUBTOTAL $7,88080

81 B3020 ROOF OPENINGS82 NoWork in this section83 SUBTOTAL84

85 TOTAL - ROOFING $7,880868788 C10 INTERIOR CONSTRUCTION89

90 C1010 PARTITIONS91 NoWork in this section92 SUBTOTAL93

94 C1020 INTERIOR DOORS95 NoWork in this section96 SUBTOTAL97

98 C1030 SPECIALTIES / MILLWORK99 NoWork in this section100 SUBTOTAL101

102 TOTAL - INTERIOR CONSTRUCTION103

104

105 C20 STAIRCASES106

107 C2010 STAIR CONSTRUCTION108 NoWork in this section109 SUBTOTAL110

111 C2020 STAIR FINISHES112 NoWork in this section113 SUBTOTAL114

115 TOTAL - STAIRCASES116

117

118 C30 INTERIOR FINISHES119

120 C3010 WALL FINISHES

Holyoke 106 High Street Estimate PH1 Scope Page 7 PMC - Project Management Cost

Page 56: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

PHASE 1 STABILIZATION121 NoWork in this section122 SUBTOTAL123

124 C3020 FLOOR FINISHES125 NoWork in this section126 SUBTOTAL127

128 C3030 CEILING FINISHES129 NoWork in this section130 SUBTOTAL131

132 TOTAL - INTERIOR FINISHES133

134

135 D10 CONVEYING SYSTEMS136

137 D1010 ELEVATOR138 NoWork in this section139 SUBTOTAL140

141 TOTAL - CONVEYING SYSTEMS142

143

144 D20 PLUMBING145

146 D20 PLUMBING, GENERALLY147 NoWork in this section148 SUBTOTAL149

150 TOTAL - PLUMBING151152

153 D30 HVAC154

155 D30 HVAC, GENERALLY156 NoWork in this section157 SUBTOTAL158159 TOTAL - HVAC160

161

162 D40 FIRE PROTECTION163

164 D40 FIRE PROTECTION, GENERALLY165 NoWork in this section166 SUBTOTAL167

168 TOTAL - FIRE PROTECTION169

170

171 D50 ELECTRICAL172

173 D5010 ELECTRICAL SYSTEMS174 Exterior lighting 1 ls 10,000.00 10,000

175 SUBTOTAL $10,000176

177

178 TOTAL - ELECTRICAL $10,000179

180

181 E10 EQUIPMENT182

183 E10 EQUIPMENT, GENERALLY184 NoWork in this section

Holyoke 106 High Street Estimate PH1 Scope Page 8 PMC - Project Management Cost

Page 57: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 08-Apr-14PHASE 1 StabilizationHolyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

PHASE 1 STABILIZATION185 SUBTOTAL186

187 TOTAL - EQUIPMENT188

189

190 E20 FURNISHINGS191

192 E2010 FIXED FURNISHINGS193 NoWork in this section194 SUBTOTAL195

196 E2020 MOVABLE FURNISHINGS197 All movable furnishings to be provided and installed

by owner198 SUBTOTAL NIC199

200 TOTAL - FURNISHINGS201

202

203 F10 SPECIAL CONSTRUCTION204

205 F10 SPECIAL CONSTRUCTION206 SUBTOTAL207

208 TOTAL - SPECIAL CONSTRUCTION209

210

211 F20 SELECTIVE BUILDING DEMOLITION212

213 F2010 BUILDING ELEMENTS DEMOLITION214 Clean up exterior areas 1 ls 5,000.00 5,000215 Remove and dispose of all debris at all floors including

stairwells32,660 sf 2.00 65,320

216 Remove all vines from rear and side of buildings 1 ls 3,000.00 3,000217 Remove/ clean all graffiti from buildings 1 ls 15,000.00 15,000218 SUBTOTAL $88,320219

220 F2020 HAZARDOUS COMPONENTS ABATEMENT221 Excluded See Summary222 SUBTOTAL223

224 TOTAL - SELECTIVE BUILDING DEMOLITION $88,320

Holyoke 106 High Street Estimate PH1 Scope Page 9 PMC - Project Management Cost

Page 58: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Feasibility Submission

Holyoke; 106-120 High Street BuildingScope 1 and 2

Holyoke, MA

Prepared for:

McCabe Enterprises

March 16, 2014

Page 59: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street BuildingScope 1 and 2 16-Mar-14Holyoke, MA

Feasibility Submission

MAIN CONSTRUCTION COST SUMMARY

Gross FloorArea

$/sf EstimatedConstruction Cost

SCOPE # 1 INCREMENTAL RENOVATION

32,660 $171.90 $5,614,232

SITEWORK - No Work Assumed NIC

HAZMAT REMOVALS NICSUB-TOTAL 32,660 $171.90 $5,614,232

GENERAL CONDITIONS 8% $449,139BONDS 0.65% $36,493INSURANCE 1.25% $70,178PERMIT 1.00% $61,700

OVERHEAD AND FEE 3% $168,4276.00% $336,854

15% $1,010,553

PREMIUM FOR INCREMENTALWORK 10% $561,423

TOTAL OF ALL CONSTRUCTION - SCOPE #1 32,660 $254.41 $8,308,999

ESCALATION TOMID-POINT (assumed 2years)

DESIGN AND PRICING CONTINGENCY

RENOVATION OF EXISTING BUILDING(Residential on Upper Floors)

Summary Page 2 PMC - Project Management Cost

Page 60: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street BuildingScope 1 and 2 16-Mar-14Holyoke, MA

Feasibility Submission

SCOPE #2a FULL RENOVATION (Residential)

32,660 $193.51 $6,320,072

SITEWORK NIC

HAZMAT REMOVALS NICSUB-TOTAL 32,660 $193.51 $6,320,072

GENERAL CONDITIONS 8% $505,606BONDS 0.65% $41,080INSURANCE 1.25% $79,001PERMIT 1.00% $69,458

OVERHEAD AND FEE 3% $189,6026.00% $379,204

15% $1,137,603

TOTAL OF ALL CONSTRUCTION - SCOPE #2a 32,660 $267.04 $8,721,626

SCOPE #2b FULL RENOVATION (Office)

32,660 $168.01 $5,487,112

SITEWORK $0

HAZMAT REMOVALS NICSUB-TOTAL 32,660 $168.01 $5,487,112

GENERAL CONDITIONS 8% $438,969BONDS 0.65% $35,666INSURANCE 1.25% $68,589PERMIT 1.00% $60,303

OVERHEAD AND FEE 3% $164,6136.00% $329,227

15% $987,672

TOTAL OF ALL CONSTRUCTION - SCOPE #2b 32,660 $231.85 $7,572,151

RENOVATION OF EXISTING BUILDING(Residential on Upper Floors)

ESCALATION TOMID-POINT (assumed 2years)

DESIGN AND PRICING CONTINGENCY

RENOVATION OF EXISTING BUILDING

ESCALATION TOMID-POINT (assumed 2years)

DESIGN AND PRICING CONTINGENCY

Summary Page 3 PMC - Project Management Cost

Page 61: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street BuildingScope 1 and 2 16-Mar-14Holyoke, MA

Feasibility Submission

ITEMS NOT CONSIDERED IN THIS ESTIMATE

Items not included in this estimate are:All professional fees and insuranceBuilding Permit costsLand acquisition, feasibility, and financing costsAll Furnishings, Fixtures and EquipmentItems identified in the design as Not In Contract (NIC)Items identified in the design as by othersOwner supplied and/or installed items (e.g. draperies, furniture and equipment)Rock excavation; special foundations (unless indicated by design engineers)Utility company back charges, including work required off-siteWork to City streets and sidewalks, (except as noted in this estimate)

The estimate is based on prevailing wage rates for construction in this market and represents a reasonable opinion of cost. It is not aprediction of the successful bid from a contractor as bids will vary due to fluctuating market conditions, errors and omissions,proprietary specifications, lack or surplus of bidders, perception of risk, etc. Consequently the estimate is expected to fall within therange of bids from a number of competitive contractors or subcontractors, however we do not warrant that bids or negotiated prices willnot vary from the final construction cost estimate.

This estimate includes all direct construction costs, general contractor’s overhead and profit and design contingency. Cost escalationassumes start dates indicated.

These Feasibility Construction cost estimates were produced from drawings, outline specifications and other documentationprepared by McCabe Enterprises and their design team dated March, 2014. Design and engineering changes occurring subsequentto the issue of these documents have not been incorporated in this estimate.

Bidding conditions are expected to be public bidding under Chapter 149 of the Massachusetts General Laws to pre-qualified generalcontractors, and pre-qualified sub-contractors, open specifications for materials and manufactures.

Summary Page 4 PMC - Project Management Cost

Page 62: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 1 INCREMENTAL RENOVATIONA10 FOUNDATIONS

A1010 Standard Foundations $5,000A1020 Special Foundations $0A1030 Lowest Floor Construction $124,560 $129,560 $3.97 2.3%

A20 BASEMENT CONSTRUCTIONA2010 Basement Excavation $0A2020 Basement Walls $0 $0 $0.00 0.0%

B10 SUPERSTRUCTUREB1010 Upper Floor Construction $65,320B1020 Roof Construction $0 $65,320 $2.00 1.2%

B20 EXTERIOR CLOSUREB2010 Exterior Walls $470,000B2020 Windows $375,560B2030 Exterior Doors $36,000 $881,560 $26.99 15.7%

B30 ROOFINGB3010 Roof Coverings $115,320B3020 Roof Openings $1,500 $116,820 $3.58 2.1%

C10 INTERIOR CONSTRUCTIONC1010 Partitions $545,160C1020 Interior Doors $141,400C1030 Specialties/Millwork $143,192 $829,752 $25.41 14.8%

C20 STAIRCASESC2010 Stair Construction $520,000C2020 Stair Finishes $64,000 $584,000 $17.88 10.4%

C30 INTERIOR FINISHESC3010 Wall Finishes $408,250C3020 Floor Finishes $175,740C3030 Ceiling Finishes $277,960 $861,950 $26.39 15.4%

D10 CONVEYING SYSTEMSD1010 Elevator $0 $0 $0.00 0.0%

D20 PLUMBINGD20 Plumbing $375,400 $375,400 $11.49 6.7%

D30 HVACD30 HVAC $783,840 $783,840 $24.00 14.0%

Holyoke 106 High Street Estimate Page 5 PMC - Project Management Cost

Page 63: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 1 INCREMENTAL RENOVATIOND40 FIRE PROTECTION

D40 Fire Protection $160,640 $160,640 $4.92 2.9%

D50 ELECTRICALD5010 New Electrical Systems $522,370 $522,370 $15.99 9.3%

E10 EQUIPMENTE10 Equipment $25,380 $25,380 $0.78 0.5%

E20 FURNISHINGSE2010 Fixed Furnishings $99,000E2020 Movable Furnishings NIC $99,000 $3.03 1.8%

F10 SPECIAL CONSTRUCTIONF10 Special Construction $0 $0 $0.00 0.0%

F20 HAZMAT REMOVALSF2010 Building Elements Demolition $178,640F2020 Hazardous Components Abatement $0 $178,640 $5.47 3.2%

TOTAL DIRECT COST (Trade Costs) $5,614,232 $171.90 100.0%

Holyoke 106 High Street Estimate Page 6 PMC - Project Management Cost

Page 64: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION1 GROSS FLOOR AREA CALCULATION2

3 Areas Below are for 106 - 120 High Street4 Basement 7,8805 1st Floor 7,8806 2nd Floor 5,8607 3rd Floor 5,5208 4th Floor 5,5209

10 TOTAL GROSS FLOOR AREA (GFA) 32,660 sf11

12

13 A10 FOUNDATIONS14

15 A1010 STANDARD FOUNDATIONS16 Provide allowance for foundation repair along rear

alleyway where condition of brick indicates there mayhave been settlement.

1 ls 5,000.00 5,000

17 SUBTOTAL 5,00018

19 A1020 SPECIAL FOUNDATIONS20 NoWork in this section21 SUBTOTAL22

23 A1030 LOWEST FLOOR CONSTRUCTION24 Slab25 New conc. floor throughout basement 7,880 sf 12.00 94,560

26 Miscellaneous27 Include allowance for new sidewalks/steps at

entryways and storefront entry transitions.1 ls 30,000.00 30,000

28 SUBTOTAL $124,56029

30 TOTAL - FOUNDATIONS $129,56031

32

33 A20 BASEMENT CONSTRUCTION34

35 A2010 BASEMENT EXCAVATION36 NoWork in this section37 SUBTOTAL38

39 A2020 BASEMENTWALLS40 NoWork in this section41 SUBTOTAL42

43 TOTAL - BASEMENT CONSTRUCTION44

4546 B10 SUPERSTRUCTURE47

48 B1010 FLOOR CONSTRUCTION49 Allowance for structural upgrades throughout building 32,660 gfa 2.00 65,320

50 SUBTOTAL $65,32051

52 B1020 ROOF CONSTRUCTION53 NoWork in this section

Holyoke 106 High Street Estimate Page 7 PMC - Project Management Cost

Page 65: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION54 SUBTOTAL55

56 TOTAL - SUPERSTRUCTURE $65,32057

58

59 B20 EXTERIOR CLOSURE60

61 B2010 EXTERIORWALLS62 Moderate repointing needed on exterior brick walls on

southeast elevation of building. Some parapet wallrepair needed on southeast elevation.

1 ls 50,000.00 50,000

63 Full repointing and some patch/ repair work onSouthwest elevation (at empty lot) or possible pargingof surface.

1 ls 150,000.00 150,000

64 Two-story rear portion of 118-120 High requires majorrepairs to brick including patch, repair, replacement orreconstruction in some areas.

1 ls 50,000.00 50,000

65 Two-story rear portion of 110-116 High is currentlyparged or reconstructed with cement blocks. Masonrycondition should be reviewed from interior. Somepatching, repair or repointing is anticipated.

1 ls 25,000.00 25,000

66 Three-story rear portion of 118-120 High requiresmajor repairs to brick including patch, repair,replacement or reconstruction in some areas.

1 ls 100,000.00 100,000

67 Masonry in need of cleaning/ powerwashing onnorthwest elevation.

1 ls 20,000.00 20,000

68 New exterior wall assembly will require insulation tomeet the new Stretch Energy Code.

1 ls 75,000.00 75,000

69 SUBTOTAL $470,00070

71 B2020 WINDOWS72 Install new storefront glazing system on High Street

facades.576 sf 85.00 48,960

73 Installation of new energy-rated windows on HighStreet and rear alleyway elevations

32,660 sf 10.00 326,600

74 SUBTOTAL $375,56075

76 B2030 EXTERIOR DOORS77 Remove and replace existing exterior doors within

storefront double; glazed including hardware4 pr 7,500.00 30,000

78 Remove and replace existing Aluminum glazedexterior door; single (Allowance)

2 ea 3,000.00 6,000

79 SUBTOTAL 36,00080

81 TOTAL - EXTERIOR CLOSURE $881,56082

8384 B30 ROOFING85

86 B3010 ROOF COVERINGS87 Flat roofing88 Provide roof insulation and new roofing. 7,880 sf 14.00 110,32089 Miscellaneous Roofing90 Minor reconstruction of cornice cap required. 1 ls 5,000.00 5,00091 SUBTOTAL $115,32092

93 B3020 ROOF OPENINGS94 Roof ladder 1 loc 1,500.00 1,50095 SUBTOTAL $1,50096

97 TOTAL - ROOFING $116,82098

Holyoke 106 High Street Estimate Page 8 PMC - Project Management Cost

Page 66: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION99100 C10 INTERIOR CONSTRUCTION101

102 C1010 PARTITIONS103 09250 New partitions to all floors except first 24,780 sf 22.00 545,160104 SUBTOTAL $545,160105

106 C1020 INTERIOR DOORS107 New rated doors throughout as part of new partitions

for residential use.16,900 sf 6.00 101,400

108 Provide new rated doors at stair enclosures. 20 loc 2,000.00 40,000109 SUBTOTAL $141,400110

111 C1030 SPECIALTIES / MILLWORK112 Painted wood standing and running trim throughout. 32,660 gfa 0.50 16,330113 Toilet Partitions and toilet accessories 32,660 sf 1.00 32,660114 Backer panels in electrical closets 1 ls 1,000.00 1,000115 Allowance for exterior signage 2 loc 5,000.00 10,000116 Building directory 1 loc 3,000.00 3,000117 Bronze dedication plaque 1 loc 2,500.00 2,500118 Room Signs 1 ls 2,000.00 2,000119 Fire extinguisher cabinets 11 ea 350.00 3,850120 Miscellaneous structural repair/ reinforcement. 32,660 gfa 2.00 65,320121 Miscellaneous sealants throughout building 32,660 sf 0.20 6,532122 SUBTOTAL $143,192123

124 TOTAL - INTERIOR CONSTRUCTION $829,752125

126

127 C20 STAIRCASES128

129 C2010 STAIR CONSTRUCTION130 Newmetal pan egress stairs at rear stairwells; four

flights4 loc 120,000.00 480,000

131 Repairs to wood entry stairs and handrails, allbuildings

4 loc 10,000.00 40,000

132 SUBTOTAL $520,000133

134 C2020 STAIR FINISHES135 Allowance to refurbish existing stair case 16 flt 4,000.00 64,000136 SUBTOTAL $64,000137

138 TOTAL - STAIRCASES $584,000139

140

141 C30 INTERIOR FINISHES142

143 C3010 WALL FINISHES144 Ground floor restaurant space requires paint only.

Lobby at new entry to uppler levels requires someinstallation of new painted GWB partitions.

7,880 gfa 8.00 63,040

145 Allowance to install new wall finishes at the 1st floorlevel; mainly paint, some millwork finishes inrestaurant area, and tile in the toilet rooms andkitchen.

7,880 gfa 12.00 94,560

146 Wall finishes to residential spaces 16,900 sf 10.00 169,000147 Paint to new walls etc. 32,660 gfa 2.50 81,650148 SUBTOTAL $408,250149

150 C3020 FLOOR FINISHES

Holyoke 106 High Street Estimate Page 9 PMC - Project Management Cost

Page 67: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION151 Refinish existing floor at entry lobby to upper levels.

At restaurant space, wood floor in excellent conditionand only needs cleaning/ polish & buff.

7,880 sf 3.00 23,640

152 Allowance to install new floor finishes at theresidential areas

16,900 sf 9.00 152,100

153 SUBTOTAL $175,740154

155 C3030 CEILING FINISHES156 Moderate repairs to decorative tin ceiling at 114-120

High15,080 sf 2.00 30,160

157 New ceiling finishes throughout (level of finishdependent on re-use scenario).

24,780 sf 10.00 247,800

158 SUBTOTAL $277,960159

160 TOTAL - INTERIOR FINISHES $861,950161

162

163 D10 CONVEYING SYSTEMS164

165 D1010 ELEVATOR166 NoWork in this section167 SUBTOTAL168

169 TOTAL - CONVEYING SYSTEMS170

171

172 D20 PLUMBING173

174 D20 PLUMBING, GENERALLY175 Install new plumbing required for basement 7,880 sf 10.00 78,800

176 New accessible restrooms needed on floor 1. 2 loc 30,000.00 60,000

177 Provide new residential bathroom fixtures and allpiping etc. on all residential floors. (3 units/ floor)

16,900 gfa 14.00 236,600

178 SUBTOTAL $375,400179

180 TOTAL - PLUMBING $375,400181182

183 D30 HVAC184

185 D30 HVAC, GENERALLY186 Install a new energy efficient HVAC system. Each

building to have separate system.32,660 gfa 24.00 783,840

187 SUBTOTAL $783,840188189 TOTAL - HVAC $783,840190

191

192 D40 FIRE PROTECTION193

194 D40 FIRE PROTECTION, GENERALLY195 Building sprinkler system will require full upgrade. 32,660 gfa 4.00 130,640

196 New water service 1 ls 30,000.00 30,000197 SUBTOTAL $160,640198

199 TOTAL - FIRE PROTECTION $160,640200

201

202 D50 ELECTRICAL203

204 D5010 ELECTRICAL SYSTEMS

Holyoke 106 High Street Estimate Page 10 PMC - Project Management Cost

Page 68: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION205 Lighting - Interior commercial 15,760 sf 4.00 63,040

206 Lighting - Interior residential 16,900 sf 6.00 101,400

207 Lighting - Exterior architectural & sign lights at HighStreet elevation.

1 ls 10,000.00 10,000

208 Building will require new fire alarm panel, egresssignage and emergency lighting throughout.

32,660 gfa 3.00 97,980

209 Provide exterior site lighting at rear alleyway. 1 ls 5,000.00 5,000210 Full tel/ data/ cable installation required 32,660 gfa 1.50 48,990211 Building access/ security system installation. 32,660 gfa 1.00 32,660212 Upgrades to main electrical panel needed. 32,660 gfa 5.00 163,300213 SUBTOTAL $522,370214

215

216 TOTAL - ELECTRICAL $522,370217

218

219 E10 EQUIPMENT220

221 E10 EQUIPMENT, GENERALLY222 Residential appliances 9 units 2,820.00 25,380223 SUBTOTAL $25,380224

225 TOTAL - EQUIPMENT $25,380226

227

228 E20 FURNISHINGS229

230 E2010 FIXED FURNISHINGS231 Entry mats & frames - recessed with carpet/rubber

strips200 sf 45.00 9,000

232 Residential casework Kitchens/baths 9 units 10,000.00 90,000233 SUBTOTAL $99,000234

235 E2020 MOVABLE FURNISHINGS236 All movable furnishings to be provided and installed

by owner237 SUBTOTAL NIC238

239 TOTAL - FURNISHINGS $99,000240

241

242 F10 SPECIAL CONSTRUCTION243

244 F10 SPECIAL CONSTRUCTION245 SUBTOTAL246

247 TOTAL - SPECIAL CONSTRUCTION248

249

250 F20 SELECTIVE BUILDING DEMOLITION251

252 F2010 BUILDING ELEMENTS DEMOLITION253 Extensive interior demolition required (walls, floor

finishes, some drop ceilings)32,660 gfa 4.00 130,640

254 Partial demolition of existing ground level storefrontsas part of refurbishment.

1 ls 15,000.00 15,000

255 Demolition of exterior stairs, platforms at rear alley. 1 ls 5,000.00 5,000

256 Demolition of former furnace room/ chimney at rearalley (1)

1 ls 10,000.00 10,000

257 Remove all vines from rear and side of buildings 1 ls 3,000.00 3,000258 Remove/ clean all graffiti from buildings 1 ls 15,000.00 15,000

Holyoke 106 High Street Estimate Page 11 PMC - Project Management Cost

Page 69: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 1 INCREMENTAL RENOVATION259 SUBTOTAL $178,640260

261 F2020 HAZARDOUS COMPONENTS ABATEMENT262 Excluded See Summary263 SUBTOTAL264

265 TOTAL - SELECTIVE BUILDING DEMOLITION $178,640

Holyoke 106 High Street Estimate Page 12 PMC - Project Management Cost

Page 70: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 2a FULL RENOVATION - ResidentialA10 FOUNDATIONS

A1010 Standard Foundations $5,000A1020 Special Foundations $0A1030 Lowest Floor Construction $159,560 $164,560 $5.04 2.6%

A20 BASEMENT CONSTRUCTIONA2010 Basement Excavation $0A2020 Basement Walls $0 $0 $0.00 0.0%

B10 SUPERSTRUCTUREB1010 Upper Floor Construction $163,300B1020 Roof Construction $0 $163,300 $5.00 2.6%

B20 EXTERIOR CLOSUREB2010 Exterior Walls $470,000B2020 Windows $375,560B2030 Exterior Doors $36,000 $881,560 $26.99 13.9%

B30 ROOFINGB3010 Roof Coverings $115,320B3020 Roof Openings $1,500 $116,820 $3.58 1.8%

C10 INTERIOR CONSTRUCTIONC1010 Partitions $545,160C1020 Interior Doors $141,400C1030 Specialties/Millwork $175,852 $862,412 $26.41 13.6%

C20 STAIRCASESC2010 Stair Construction $520,000C2020 Stair Finishes $64,000 $584,000 $17.88 9.2%

C30 INTERIOR FINISHESC3010 Wall Finishes $408,250C3020 Floor Finishes $341,220C3030 Ceiling Finishes $373,880 $1,123,350 $34.40 17.8%

D10 CONVEYING SYSTEMSD1010 Elevator $200,000 $200,000 $6.12 3.2%

D20 PLUMBINGD20 Plumbing $454,200 $454,200 $13.91 7.2%

D30 HVACD30 HVAC $718,520 $718,520 $22.00 11.4%

Holyoke 106 High Street Estimate Page 13 PMC - Project Management Cost

Page 71: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 2a FULL RENOVATION - ResidentialD40 FIRE PROTECTION

D40 Fire Protection $160,640 $160,640 $4.92 2.5%

D50 ELECTRICALD5010 New Electrical Systems $522,370 $522,370 $15.99 8.3%

E10 EQUIPMENTE10 Equipment $25,380 $25,380 $0.78 0.4%

E20 FURNISHINGSE2010 Fixed Furnishings $99,000E2020 Movable Furnishings NIC $99,000 $3.03 1.6%

F10 SPECIAL CONSTRUCTIONF10 Special Construction $0 $0 $0.00 0.0%

F20 HAZMAT REMOVALSF2010 Building Elements Demolition $243,960F2020 Hazardous Components Abatement $0 $243,960 $7.47 3.9%

TOTAL DIRECT COST (Trade Costs) $6,320,072 $193.51 100.0%

Holyoke 106 High Street Estimate Page 14 PMC - Project Management Cost

Page 72: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential1 GROSS FLOOR AREA CALCULATION2

3 Areas Below are for 106 - 120 High Street4 Basement 7,8805 1st Floor 7,8806 2nd Floor 5,8607 3rd Floor 5,5208 4th Floor 5,5209

10 TOTAL GROSS FLOOR AREA (GFA) 32,660 sf11

12

13 A10 FOUNDATIONS14

15 A1010 STANDARD FOUNDATIONS16 Provide allowance for foundation repair along rear

alleyway where condition of brick indicates there mayhave been settlement.

1 ls 5,000.00 5,000

17 SUBTOTAL 5,00018

19 A1020 SPECIAL FOUNDATIONS20 NoWork in this section21 SUBTOTAL22

23 A1030 LOWEST FLOOR CONSTRUCTION24 Slab25 New conc. floor throughout basement 7,880 sf 12.00 94,560

26 Miscellaneous27 New elevator pit 1 ls 35,000.00 35,000

28 Include allowance for new sidewalks/steps atentryways and storefront entry transitions.

1 ls 30,000.00 30,000

29 SUBTOTAL $159,56030

31 TOTAL - FOUNDATIONS $164,56032

33

34 A20 BASEMENT CONSTRUCTION35

36 A2010 BASEMENT EXCAVATION37 NoWork in this section38 SUBTOTAL39

40 A2020 BASEMENTWALLS41 NoWork in this section42 SUBTOTAL43

44 TOTAL - BASEMENT CONSTRUCTION45

4647 B10 SUPERSTRUCTURE48

49 B1010 FLOOR CONSTRUCTION50 Allowance for structural upgrades throughout building 32,660 gfa 5.00 163,300

51 SUBTOTAL $163,30052

Holyoke 106 High Street Estimate Page 15 PMC - Project Management Cost

Page 73: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential53 B1020 ROOF CONSTRUCTION54 NoWork in this section55 SUBTOTAL56

57 TOTAL - SUPERSTRUCTURE $163,30058

59

60 B20 EXTERIOR CLOSURE61

62 B2010 EXTERIORWALLS63 Moderate repointing needed on exterior brick walls on

southeast elevation of building. Some parapet wallrepair needed on southeast elevation.

1 ls 50,000.00 50,000

64 Full repointing and some patch/ repair work onSouthwest elevation (at empty lot) or possible pargingof surface.

1 ls 150,000.00 150,000

65 Two-story rear portion of 118-120 High requires majorrepairs to brick including patch, repair, replacement orreconstruction in some areas.

1 ls 50,000.00 50,000

66 Two-story rear portion of 110-116 High is currentlyparged or reconstructed with cement blocks. Masonrycondition should be reviewed from interior. Somepatching, repair or repointing is anticipated.

1 ls 25,000.00 25,000

67 Three-story rear portion of 118-120 High requiresmajor repairs to brick including patch, repair,replacement or reconstruction in some areas.

1 ls 100,000.00 100,000

68 Masonry in need of cleaning/ powerwashing onnorthwest elevation.

1 ls 20,000.00 20,000

69 New exterior wall assembly will require insulation tomeet the new Stretch Energy Code.

1 ls 75,000.00 75,000

70 SUBTOTAL $470,00071

72 B2020 WINDOWS73 Install new storefront glazing system on High Street

facades.576 sf 85.00 48,960

74 Installation of new energy-rated windows on HighStreet and rear alleyway elevations

32,660 sf 10.00 326,600

75 SUBTOTAL $375,56076

77 B2030 EXTERIOR DOORS78 Remove and replace existing exterior doors within

storefront double; glazed including hardware4 pr 7,500.00 30,000

79 Remove and replace existing Aluminum glazedexterior door; single (Allowance)

2 ea 3,000.00 6,000

80 SUBTOTAL 36,00081

82 TOTAL - EXTERIOR CLOSURE $881,56083

8485 B30 ROOFING86

87 B3010 ROOF COVERINGS88 Flat roofing89 Provide roof insulation and new roofing. 7,880 sf 14.00 110,32090 Miscellaneous Roofing91 Minor reconstruction of cornice cap required. 1 ls 5,000.00 5,00092 SUBTOTAL $115,32093

94 B3020 ROOF OPENINGS95 Roof ladder 1 loc 1,500.00 1,50096 SUBTOTAL $1,500

Holyoke 106 High Street Estimate Page 16 PMC - Project Management Cost

Page 74: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential97

98 TOTAL - ROOFING $116,82099100101 C10 INTERIOR CONSTRUCTION102

103 C1010 PARTITIONS104 09250 New partitions to all floors except first 24,780 sf 22.00 545,160105 SUBTOTAL $545,160106

107 C1020 INTERIOR DOORS108 New rated doors throughout as part of new partitions

for residential use.16,900 sf 6.00 101,400

109 Provide new rated doors at stair enclosures. 20 loc 2,000.00 40,000110 SUBTOTAL $141,400111

112 C1030 SPECIALTIES / MILLWORK113 Painted wood standing and running trim throughout. 32,660 gfa 0.50 16,330114 Toilet Partitions and toilet accessories 32,660 sf 1.00 32,660115 Backer panels in electrical closets 1 ls 1,000.00 1,000116 Allowance for exterior signage 2 loc 5,000.00 10,000117 Building directory 1 loc 3,000.00 3,000118 Bronze dedication plaque 1 loc 2,500.00 2,500119 Room Signs 1 ls 2,000.00 2,000120 Fire extinguisher cabinets 11 ea 350.00 3,850121 Miscellaneous structural repair/ reinforcement. 32,660 gfa 3.00 97,980122 Miscellaneous sealants throughout building 32,660 sf 0.20 6,532123 SUBTOTAL $175,852124

125 TOTAL - INTERIOR CONSTRUCTION $862,412126

127

128 C20 STAIRCASES129

130 C2010 STAIR CONSTRUCTION131 New metal pan egress stairs at rear stairwells; four

flights4 loc 120,000.00 480,000

132 Repairs to wood entry stairs and handrails, allbuildings

4 loc 10,000.00 40,000

133 SUBTOTAL $520,000134

135 C2020 STAIR FINISHES136 Allowance to refurbish existing stair case 16 flt 4,000.00 64,000137 SUBTOTAL $64,000138

139 TOTAL - STAIRCASES $584,000140

141

142 C30 INTERIOR FINISHES143

144 C3010 WALL FINISHES145 Ground floor restaurant space requires paint only.

Lobby at new entry to uppler levels requires someinstallation of new painted GWB partitions.

7,880 gfa 8.00 63,040

146 Allowance to install new wall finishes at the 1st floorlevel; mainly paint, some millwork finishes inrestaurant area, and tile in the toilet rooms andkitchen.

7,880 gfa 12.00 94,560

147 Wall finishes to residential spaces 16,900 sf 10.00 169,000148 Paint to new walls etc. 32,660 gfa 2.50 81,650149 SUBTOTAL $408,250

Holyoke 106 High Street Estimate Page 17 PMC - Project Management Cost

Page 75: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential150

151 C3020 FLOOR FINISHES152 Floor finish upgrades to other floors 15,760 sf 12.00 189,120

153 Allowance to install new floor finishes at theresidential areas

16,900 sf 9.00 152,100

154 SUBTOTAL $341,220155

156 C3030 CEILING FINISHES157 Ceiling upgrades to other floors 15,760 sf 8.00 126,080

158 New ceiling finishes throughout (level of finishdependent on re-use scenario).

24,780 sf 10.00 247,800

159 SUBTOTAL $373,880160

161 TOTAL - INTERIOR FINISHES $1,123,350162

163

164 D10 CONVEYING SYSTEMS165

166 D1010 ELEVATOR167 New five stop elevator 1 ls 200,000.00 200,000

168 SUBTOTAL $200,000169

170 TOTAL - CONVEYING SYSTEMS $200,000171

172

173 D20 PLUMBING174

175 D20 PLUMBING, GENERALLY176 Install new plumbing required for basement/first 15,760 sf 10.00 157,600

177 New accessible restrooms needed on floor 1. 2 loc 30,000.00 60,000

178 Provide new residential bathroom fixtures and allpiping etc. on all residential floors. (3 units/ floor)

16,900 gfa 14.00 236,600

179 SUBTOTAL $454,200180

181 TOTAL - PLUMBING $454,200182183

184 D30 HVAC185

186 D30 HVAC, GENERALLY187 Install a new energy efficient HVAC system. 32,660 gfa 22.00 718,520

188 SUBTOTAL $718,520189190 TOTAL - HVAC $718,520191

192

193 D40 FIRE PROTECTION194

195 D40 FIRE PROTECTION, GENERALLY196 Building sprinkler system will require full upgrade. 32,660 gfa 4.00 130,640

197 New water service 1 ls 30,000.00 30,000198 SUBTOTAL $160,640199

200 TOTAL - FIRE PROTECTION $160,640201

202

203 D50 ELECTRICAL204

205 D5010 ELECTRICAL SYSTEMS

Holyoke 106 High Street Estimate Page 18 PMC - Project Management Cost

Page 76: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential206 Lighting - Interior commercial 15,760 sf 4.00 63,040

207 Lighting - Interior residential 16,900 sf 6.00 101,400

208 Lighting - Exterior architectural & sign lights at HighStreet elevation.

1 ls 10,000.00 10,000

209 Building will require new fire alarm panel, egresssignage and emergency lighting throughout.

32,660 gfa 3.00 97,980

210 Provide exterior site lighting at rear alleyway. 1 ls 5,000.00 5,000211 Full tel/ data/ cable installation required 32,660 gfa 1.50 48,990212 Building access/ security system installation. 32,660 gfa 1.00 32,660213 Upgrades to main electrical panel needed. 32,660 gfa 5.00 163,300214 SUBTOTAL $522,370215

216

217 TOTAL - ELECTRICAL $522,370218

219

220 E10 EQUIPMENT221

222 E10 EQUIPMENT, GENERALLY223 Residential appliances 9 units 2,820.00 25,380224 SUBTOTAL $25,380225

226 TOTAL - EQUIPMENT $25,380227

228

229 E20 FURNISHINGS230

231 E2010 FIXED FURNISHINGS232 Entry mats & frames - recessed with carpet/rubber

strips200 sf 45.00 9,000

233 Residential casework Kitchens/baths 9 units 10,000.00 90,000234 SUBTOTAL $99,000235

236 E2020 MOVABLE FURNISHINGS237 All movable furnishings to be provided and installed

by owner238 SUBTOTAL NIC239

240 TOTAL - FURNISHINGS $99,000241

242

243 F10 SPECIAL CONSTRUCTION244

245 F10 SPECIAL CONSTRUCTION246 SUBTOTAL247

248 TOTAL - SPECIAL CONSTRUCTION249

250

251 F20 SELECTIVE BUILDING DEMOLITION252

253 F2010 BUILDING ELEMENTS DEMOLITION254 Extensive interior demolition required (walls, floor

finishes, some drop ceilings)32,660 gfa 6.00 195,960

255 Partial demolition of existing ground level storefrontsas part of refurbishment.

1 ls 15,000.00 15,000

256 Demolition of exterior stairs, platforms at rear alley. 1 ls 5,000.00 5,000

257 Demolition of former furnace room/ chimney at rearalley (1)

1 ls 10,000.00 10,000

258 Remove all vines from rear and side of buildings 1 ls 3,000.00 3,000259 Remove/ clean all graffiti from buildings 1 ls 15,000.00 15,000

Holyoke 106 High Street Estimate Page 19 PMC - Project Management Cost

Page 77: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2a FULL RENOVATION - Residential260 SUBTOTAL $243,960261

262 F2020 HAZARDOUS COMPONENTS ABATEMENT263 Excluded See Summary264 SUBTOTAL265

266 TOTAL - SELECTIVE BUILDING DEMOLITION $243,960

Holyoke 106 High Street Estimate Page 20 PMC - Project Management Cost

Page 78: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 2b FULL RENOVATION - OfficeA10 FOUNDATIONS

A1010 Standard Foundations $5,000A1020 Special Foundations $0A1030 Lowest Floor Construction $159,560 $164,560 $5.04 3.0%

A20 BASEMENT CONSTRUCTIONA2010 Basement Excavation $0A2020 Basement Walls $0 $0 $0.00 0.0%

B10 SUPERSTRUCTUREB1010 Upper Floor Construction $163,300B1020 Roof Construction $0 $163,300 $5.00 3.0%

B20 EXTERIOR CLOSUREB2010 Exterior Walls $470,000B2020 Windows $375,560B2030 Exterior Doors $36,000 $881,560 $26.99 16.1%

B30 ROOFINGB3010 Roof Coverings $115,320B3020 Roof Openings $1,500 $116,820 $3.58 2.1%

C10 INTERIOR CONSTRUCTIONC1010 Partitions $371,700C1020 Interior Doors $90,700C1030 Specialties/Millwork $175,852 $638,252 $19.54 11.6%

C20 STAIRCASESC2010 Stair Construction $520,000C2020 Stair Finishes $64,000 $584,000 $17.88 10.6%

C30 INTERIOR FINISHESC3010 Wall Finishes $323,750C3020 Floor Finishes $273,620C3030 Ceiling Finishes $249,980 $847,350 $25.94 15.4%

D10 CONVEYING SYSTEMSD1010 Elevator $200,000 $200,000 $6.12 3.6%

D20 PLUMBINGD20 Plumbing $319,000 $319,000 $9.77 5.8%

D30 HVACD30 HVAC $653,200 $653,200 $20.00 11.9%

Holyoke 106 High Street Estimate Page 21 PMC - Project Management Cost

Page 79: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CONSTRUCTION COST SUMMARYBUILDING SYSTEM SUB-TOTAL TOTAL $/SF %

SCOPE # 2b FULL RENOVATION - OfficeD40 FIRE PROTECTION

D40 Fire Protection $160,640 $160,640 $4.92 2.9%

D50 ELECTRICALD5010 New Electrical Systems $505,470 $505,470 $15.48 9.2%

E10 EQUIPMENTE10 Equipment $0 $0 $0.00 0.0%

E20 FURNISHINGSE2010 Fixed Furnishings $9,000E2020 Movable Furnishings NIC $9,000 $0.28 0.2%

F10 SPECIAL CONSTRUCTIONF10 Special Construction $0 $0 $0.00 0.0%

F20 HAZMAT REMOVALSF2010 Building Elements Demolition $243,960F2020 Hazardous Components Abatement $0 $243,960 $7.47 4.4%

TOTAL DIRECT COST (Trade Costs) $5,487,112 $168.01 100.0%

Holyoke 106 High Street Estimate Page 22 PMC - Project Management Cost

Page 80: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office1 GROSS FLOOR AREA CALCULATION2

3 Areas Below are for 106 - 120 High Street4 Basement 7,8805 1st Floor 7,8806 2nd Floor 5,8607 3rd Floor 5,5208 4th Floor 5,5209

10 TOTAL GROSS FLOOR AREA (GFA) 32,660 sf11

12

13 A10 FOUNDATIONS14

15 A1010 STANDARD FOUNDATIONS16 Provide allowance for foundation repair along rear

alleyway where condition of brick indicates there mayhave been settlement.

1 ls 5,000.00 5,000

17 SUBTOTAL 5,00018

19 A1020 SPECIAL FOUNDATIONS20 NoWork in this section21 SUBTOTAL22

23 A1030 LOWEST FLOOR CONSTRUCTION24 Slab25 New conc. floor throughout basement 7,880 sf 12.00 94,560

26 Miscellaneous27 New elevator pit 1 ls 35,000.00 35,000

28 Include allowance for new sidewalks/steps atentryways and storefront entry transitions.

1 ls 30,000.00 30,000

29 SUBTOTAL $159,56030

31 TOTAL - FOUNDATIONS $164,56032

33

34 A20 BASEMENT CONSTRUCTION35

36 A2010 BASEMENT EXCAVATION37 NoWork in this section38 SUBTOTAL39

40 A2020 BASEMENTWALLS41 NoWork in this section42 SUBTOTAL43

44 TOTAL - BASEMENT CONSTRUCTION45

4647 B10 SUPERSTRUCTURE48

49 B1010 FLOOR CONSTRUCTION50 Allowance for structural upgrades throughout building 32,660 gfa 5.00 163,300

51 SUBTOTAL $163,30052

Holyoke 106 High Street Estimate Page 23 PMC - Project Management Cost

Page 81: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office53 B1020 ROOF CONSTRUCTION54 NoWork in this section55 SUBTOTAL56

57 TOTAL - SUPERSTRUCTURE $163,30058

59

60 B20 EXTERIOR CLOSURE61

62 B2010 EXTERIORWALLS63 Moderate repointing needed on exterior brick walls on

southeast elevation of building. Some parapet wallrepair needed on southeast elevation.

1 ls 50,000.00 50,000

64 Full repointing and some patch/ repair work onSouthwest elevation (at empty lot) or possible pargingof surface.

1 ls 150,000.00 150,000

65 Two-story rear portion of 118-120 High requires majorrepairs to brick including patch, repair, replacement orreconstruction in some areas.

1 ls 50,000.00 50,000

66 Two-story rear portion of 110-116 High is currentlyparged or reconstructed with cement blocks. Masonrycondition should be reviewed from interior. Somepatching, repair or repointing is anticipated.

1 ls 25,000.00 25,000

67 Three-story rear portion of 118-120 High requiresmajor repairs to brick including patch, repair,replacement or reconstruction in some areas.

1 ls 100,000.00 100,000

68 Masonry in need of cleaning/ powerwashing onnorthwest elevation.

1 ls 20,000.00 20,000

69 New exterior wall assembly will require insulation tomeet the new Stretch Energy Code.

1 ls 75,000.00 75,000

70 SUBTOTAL $470,00071

72 B2020 WINDOWS73 Install new storefront glazing system on High Street

facades.576 sf 85.00 48,960

74 Installation of new energy-rated windows on HighStreet and rear alleyway elevations

32,660 sf 10.00 326,600

75 SUBTOTAL $375,56076

77 B2030 EXTERIOR DOORS78 Remove and replace existing exterior doors within

storefront double; glazed including hardware4 pr 7,500.00 30,000

79 Remove and replace existing Aluminum glazedexterior door; single (Allowance)

2 ea 3,000.00 6,000

80 SUBTOTAL 36,00081

82 TOTAL - EXTERIOR CLOSURE $881,56083

8485 B30 ROOFING86

87 B3010 ROOF COVERINGS88 Flat roofing89 Provide roof insulation and new roofing. 7,880 sf 14.00 110,32090 Miscellaneous Roofing91 Minor reconstruction of cornice cap required. 1 ls 5,000.00 5,00092 SUBTOTAL $115,32093

94 B3020 ROOF OPENINGS95 Roof ladder 1 loc 1,500.00 1,50096 SUBTOTAL $1,500

Holyoke 106 High Street Estimate Page 24 PMC - Project Management Cost

Page 82: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office97

98 TOTAL - ROOFING $116,82099100101 C10 INTERIOR CONSTRUCTION102

103 C1010 PARTITIONS104 09250 New partitions to all floors except first 24,780 sf 15.00 371,700105 SUBTOTAL $371,700106

107 C1020 INTERIOR DOORS108 New doors 16,900 sf 3.00 50,700

109 Provide new rated doors at stair enclosures. 20 loc 2,000.00 40,000110 SUBTOTAL $90,700111

112 C1030 SPECIALTIES / MILLWORK113 Painted wood standing and running trim throughout. 32,660 gfa 0.50 16,330114 Toilet Partitions and toilet accessories 32,660 sf 1.00 32,660115 Backer panels in electrical closets 1 ls 1,000.00 1,000116 Allowance for exterior signage 2 loc 5,000.00 10,000117 Building directory 1 loc 3,000.00 3,000118 Bronze dedication plaque 1 loc 2,500.00 2,500119 Room Signs 1 ls 2,000.00 2,000120 Fire extinguisher cabinets 11 ea 350.00 3,850121 Miscellaneous structural repair/ reinforcement. 32,660 gfa 3.00 97,980122 Miscellaneous sealants throughout building 32,660 sf 0.20 6,532123 SUBTOTAL $175,852124

125 TOTAL - INTERIOR CONSTRUCTION $638,252126

127

128 C20 STAIRCASES129

130 C2010 STAIR CONSTRUCTION131 New metal pan egress stairs at rear stairwells; four

flights4 loc 120,000.00 480,000

132 Repairs to wood entry stairs and handrails, allbuildings

4 loc 10,000.00 40,000

133 SUBTOTAL $520,000134

135 C2020 STAIR FINISHES136 Allowance to refurbish existing stair case 16 flt 4,000.00 64,000137 SUBTOTAL $64,000138

139 TOTAL - STAIRCASES $584,000140

141

142 C30 INTERIOR FINISHES143

144 C3010 WALL FINISHES145 Ground floor restaurant space requires paint only.

Lobby at new entry to uppler levels requires someinstallation of new painted GWB partitions.

7,880 gfa 8.00 63,040

146 Allowance to install new wall finishes at the 1st floorlevel; mainly paint, some millwork finishes inrestaurant area, and tile in the toilet rooms andkitchen.

7,880 gfa 12.00 94,560

147 Wall finishes to office spaces 16,900 sf 5.00 84,500148 Paint to new walls etc. 32,660 gfa 2.50 81,650149 SUBTOTAL $323,750150

Holyoke 106 High Street Estimate Page 25 PMC - Project Management Cost

Page 83: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office151 C3020 FLOOR FINISHES152 Floor finish upgrades to other floors 15,760 sf 12.00 189,120

153 Allowance to install new floor finishes at the officeareas

16,900 sf 5.00 84,500

154 SUBTOTAL $273,620155

156 C3030 CEILING FINISHES157 Ceiling upgrades to other floors 15,760 sf 8.00 126,080

158 New ceiling finishes throughout (level of finishdependent on re-use scenario).

24,780 sf 5.00 123,900

159 SUBTOTAL $249,980160

161 TOTAL - INTERIOR FINISHES $847,350162

163

164 D10 CONVEYING SYSTEMS165

166 D1010 ELEVATOR167 New five stop elevator 1 ls 200,000.00 200,000

168 SUBTOTAL $200,000169

170 TOTAL - CONVEYING SYSTEMS $200,000171

172

173 D20 PLUMBING174

175 D20 PLUMBING, GENERALLY176 Install new plumbing required for basement/first 15,760 sf 10.00 157,600

177 New accessible restrooms needed on floor 1. 2 loc 30,000.00 60,000

178 Provide new plumbing to office floors 16,900 gfa 6.00 101,400

179 SUBTOTAL $319,000180

181 TOTAL - PLUMBING $319,000182183

184 D30 HVAC185

186 D30 HVAC, GENERALLY187 Install a new energy efficient HVAC system. 32,660 gfa 20.00 653,200

188 SUBTOTAL $653,200189190 TOTAL - HVAC $653,200191

192

193 D40 FIRE PROTECTION194

195 D40 FIRE PROTECTION, GENERALLY196 Building sprinkler system will require full upgrade. 32,660 gfa 4.00 130,640

197 New water service 1 ls 30,000.00 30,000198 SUBTOTAL $160,640199

200 TOTAL - FIRE PROTECTION $160,640201

202

203 D50 ELECTRICAL204

205 D5010 ELECTRICAL SYSTEMS206 Lighting - Interior commercial 15,760 sf 4.00 63,040

207 Lighting - Interior office 16,900 sf 5.00 84,500

Holyoke 106 High Street Estimate Page 26 PMC - Project Management Cost

Page 84: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office208 Lighting - Exterior architectural & sign lights at High

Street elevation.1 ls 10,000.00 10,000

209 Building will require new fire alarm panel, egresssignage and emergency lighting throughout.

32,660 gfa 3.00 97,980

210 Provide exterior site lighting at rear alleyway. 1 ls 5,000.00 5,000211 Full tel/ data/ cable installation required 32,660 gfa 1.50 48,990212 Building access/ security system installation. 32,660 gfa 1.00 32,660213 Upgrades to main electrical panel needed. 32,660 gfa 5.00 163,300214 SUBTOTAL $505,470215

216

217 TOTAL - ELECTRICAL $505,470218

219

220 E10 EQUIPMENT221

222 E10 EQUIPMENT, GENERALLY223 NoWork in this section224 SUBTOTAL225

226 TOTAL - EQUIPMENT227

228

229 E20 FURNISHINGS230

231 E2010 FIXED FURNISHINGS232 Entry mats & frames - recessed with carpet/rubber

strips200 sf 45.00 9,000

233 SUBTOTAL $9,000234

235 E2020 MOVABLE FURNISHINGS236 All movable furnishings to be provided and installed

by owner237 SUBTOTAL NIC238

239 TOTAL - FURNISHINGS $9,000240

241

242 F10 SPECIAL CONSTRUCTION243

244 F10 SPECIAL CONSTRUCTION245 SUBTOTAL246

247 TOTAL - SPECIAL CONSTRUCTION248

249

250 F20 SELECTIVE BUILDING DEMOLITION251

252 F2010 BUILDING ELEMENTS DEMOLITION253 Extensive interior demolition required (walls, floor

finishes, some drop ceilings)32,660 gfa 6.00 195,960

254 Partial demolition of existing ground level storefrontsas part of refurbishment.

1 ls 15,000.00 15,000

255 Demolition of exterior stairs, platforms at rear alley. 1 ls 5,000.00 5,000

256 Demolition of former furnace room/ chimney at rearalley (1)

1 ls 10,000.00 10,000

257 Remove all vines from rear and side of buildings 1 ls 3,000.00 3,000258 Remove/ clean all graffiti from buildings 1 ls 15,000.00 15,000259 SUBTOTAL $243,960260

261 F2020 HAZARDOUS COMPONENTS ABATEMENT262 Excluded See Summary263 SUBTOTAL

Holyoke 106 High Street Estimate Page 27 PMC - Project Management Cost

Page 85: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

Holyoke; 106-120 High Street Building 16-Mar-14Scope 1 and 2Holyoke, MA

Feasibility Submission GFA 32,660

CSI UNIT EST'D SUB TOTALCODE DESCRIPTION QTY UNIT COST COST TOTAL COST

SCOPE # 2b FULL RENOVATION - Office264

265 TOTAL - SELECTIVE BUILDING DEMOLITION $243,960

Holyoke 106 High Street Estimate Page 28 PMC - Project Management Cost

Page 86: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

Page 87: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe Enterprises Holyoke | Appendix

pro formadefinitionsA

4

343

Page 88: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

Notes on Financing –

Definitions, Terms, Sources

Hard Costs. Hard Costs encompass the costs of rehabilitation, construction, site work, selec-tive (where needed), fixtures and equipment, hard cost contingency.

Construction Costs. Construction costs have been estimated by Project Management & Cost, a leading cost estimating firm with experience in experience estimating both private and pub-lic sector vertical construction, including rehabilitation. Construction costs are based on the conceptual plans contained in this report and include direct construction costs, general contractor’s overhead and profit and a design contingency. Costs have been escalated to the mid-point of a two-year period, assuming that it will take one-to-two years to ready the project for rehabilitation. The cost estimate represents a reasonable opinion of cost.

Demolition. Interior gutting, as needed, is included in the construction cost estimate. No building demolition is required in the projects.

Tenant Improvements. No costs were attributed as part of the redevelopment and rehabili-tation to tenant improvement and fit-out. The cost of tenant fit-out will be determined on a case-by-case basis and dependent upon the unique needs of each tenant. Tenant improve-ments are supplemental.

Furniture, Fixtures and Equipment. Fixtures and equipment for commercial bathrooms and for requisite plumbing and fixtures for residential housing units have been budgeted and described in the scope for each scenario.

Hard Cost Contingency. The hard cost contingency is budgeted at 10% of conceptual con-struction cost estimate.

Soft Costs

Architectural & Engineering. Architectural and engineering costs have been budgeted at 7.5% of construction costs, unless otherwise noted.

Other Consultants. Other consultants could include a surveyor, preservation consultant, code consultant, energy consultant, Licensed Site Professional, development or financing con-sultants. The exact constellation of consultant team will depend upon the specifics of each building. Costs are anticipated to be approximately 1.5% of construction costs.

Project Management. To successfully coordinate all project elements from design to final completion of renovation and rehabilitation, 5% of the construction budget has been allocated to project management services.

Legal fees. Legal services will be needed throughout the development process for contracts, construction, permitting land acquisition, review of easements, loan and financing documents,

344

Page 89: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe Enterprises Holyoke | Appendix

etc. One percent of construction costs have been allocated for legal services. In the event that the developer selects to use New Markets Tax Credits or historic tax credits, additional legal expenditures may likely be required.

Permit fees. Fees for building permits, gas, plumbing, wiring, site plan and zoning review will be necessary for the project to proceed with municipal and governmental approvals. Permit fees are included in the construction budget, and thus are zero percent in this soft cost budget.

Insurance. The contractor’s cost of insurance has been included construction hard costs bud-get. The property owner/developer should also retain insurance on the property during the course of development. As such, one-half of one percent (0.5%) has been budgeted for insur-ance costs.

Developer’s Fee. It is typical for a developer to derive a fee for their contribution in managing and assembling the project. Although developers’ fees can range from one to five percent of construction costs, a modest 1.5% is used in the pro forma. Although developer’s fees are standard, this cost has not be included in the pro forma analyses for base stabilization scenario under the Incremental Hybrid approach.

Utilities. The cost of utilities, heat, electric, water and sewer, for the building during the antic-ipated two year development and rehabilitation period are budgeted at one-half of one percent (0.5%) of construction costs.

Soft Cost Contingency. A contingency for soft costs is budgeted at one percent of construc-tion costs. The soft cost contingency is approximately 5.6% of all soft costs.

Marketing. As part of the redevelopment process, marketing costs to attract tenants should be anticipated. One percent of construction costs is budgeted for marketing expenses.

Real Estate Taxes. The cost of real estate taxes includes two years of projected real estate taxes and all outstanding taxes.

Operating Revenue Sources

Rental Income

The major source of operating funds for each building will be rental income based on the desired mix of uses for each scenario. We spoke to property owners and downtown tenants regarding current rents in downtown Holyoke and reviewed the current asking prices on avail-able properties. Projected rents are somewhat higher than current 2014 rents, since it will likely be two years before these properties will be ready for occupancy and leasing.

Several scenarios include residential housing and live/work space. For purpose of analysis, it is assumed that these units will be market rate rental housing. Rental housing is the only type of multi-family housing currently being financed in today’s marketplace. Thus, scenarios with residential condominium development were not prepared. Market rate housing and affordable housing rents using HUD’s FMR (Fair Market Rents) rents are similar. Thus, the pro formas focus on the feasibility of market rate housing.

345

Page 90: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

Monthly residential rents do not cover the cost of parking. Two properties intensively studied do not have land to provide parking. Tenants with cars or the developer would need to assume an additional $20 to $40 per month above apartment rents for parking. All properties are served by bus and are within two-and-one-half blocks of the Holyoke multi-modal transpor-tation center with PVTA (Pioneer Valley Transit Authority) buses serving Holyoke and nearby communities as well as inner-city bus service offered by Peter Pan. Inner city passenger train service by Amtrak is in the planning stages, with a planned stop in Downtown Holyoke within walking distance of the properties. Moreover, the City of Holyoke’s vision is for a walkable center city. The City is making steady progress towards pedestrian improvements to enhance walkability, most notably the Canalwalk. Thus, the pro formas for building rehabilitation do not incorporate the cost of parking.

The pro forma analyses in this report are based on the following triple net commercial rents and residential rents as follows.

Housing. The variation in monthly housing rental rates is attributable to the variation in the size of the unit.

Live-Work. Live-work space is priced on a per net SF basis.

SRECS

In addition to the typical rental income for commercial and residential tenants, each scenario includes revenue from SRECS. SRECS stands for Solar Renewable Energy Certificate. Mas-sachusetts has created a program where there is a market subsidy for the generation of solar energy which provides a tradable certificate, called an SREC that represents the clean energy benefits generated from a solar electric system, based on the number of 1000 kilowatt hours generated by the system. The amount of projected electricity at each location as to kilowatt hours was estimated based on the Massachusetts climate and the available roof top for solar. The value of SRECS was estimated at the minimum established base price per Massachusetts regulation.

Several of the buildings studied are multi-storied with flat roof tops that have very good sun exposure, which makes them ideal candidates for solar energy production. In two of the cases, construction of new roof systems is anticipated facilitating the deployment of photo voltaic panels for solar energy production. It is anticipated that photo voltaic systems can be installed on the roofs of each building with appropriate rooftop setbacks so that the solar panels are not visible from the street. Although there are federal tax credits for installation of renewable en-ergy, the value of these credits was not factored into the pro forma. The availability of federal solar tax credits expire December 31, 2016 and provide a 30% investment tax credit on allow-able costs. Solar tax credits and SRECs could contribute towards a stronger revenue stream.

Operating Expenses

Since these buildings are principally commercial in nature, it is assumed that tenants will be paying triple net leases (NNN), meaning the tenant will be responsible for payment of real es-tate taxes, building insurance and maintenance. Since leases are a negotiation between a land-

346

Page 91: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe Enterprises Holyoke | Appendix

lord and tenant, funds were nonetheless budgeted for maintenance and utilities, in the event of a vacancy or lease negotiation where the developer assumes some of the maintenance costs and uses a double-net (NN) lease instead. In residential leases, the landlord typically assumes payment of the taxes, common area utilities and general maintenance. Funds for operating expenses inclusive of maintenance costs, utilities, management fees, as well as a pro-rata share of real estate taxes attributable to the residential component are budgeted.

Financing

At the core of each financial scenario is a conventional market-rate financing component based on an interest rate of 5% for permanent financing (5.5% for construction loans) with a thirty year amortization schedule, and a minimum of ten percent equity, plus existing equity in the land and building. Twenty percent equity is the preferred standard by lenders. Property owners and developers may need to augment the equity levels noted in the pro formas. It is anticipated that some projects may utilize New Markets Tax Credits for additional equity or private partners.

In each case, the revenue stream generated by the existing competitive rents in Downtown Holyoke today do not generate sufficient revenue so that a project can rely solely on con-ventional bank financing. The pro formas contained within this report illustrate what could happen to “make the deal” work for each property.

Historic Tax Credits. In all cases it is assumed that the property owner/developer will make full utilization of both state and federal historic tax credits. Each building is over fifty years old and has played an important role in Holyoke’s history as one of America’s first planned industrial cities. The properties are either in a National Register Historic District, or adjacent to an existing district. Each building should be listed individually on the National Register of Historic Places, or at minimum determined to be eligible by the Massachusetts Historical Commission (MHC), to facilitate use of the historic tax credits. Use of historic tax credits requires that the building be renovated in accordance with the Secretary of Interior’s Standards for the Treatment of Historic Properties.

The specific value of historic tax credits may vary. The value of the federal historic tax credits assumes sale of historic tax credits to support the project based on 20% of the eligible basis for each project valued at sixty cents per $1.00 of credit. The amount of federal historic tax credits are automatic based on eligible expenses for a certified project done in accordance with the Secretary of Interior’s Standards.

The amount of state historic tax credits is based on a competitive application to the MHC for use on income-producing property, up to 20% of the cost of certified rehabilitation expendi-tures for state income tax credits. These properties are all projected to undertake substantial rehabilitation activities, which will exceed 25% of the property owner’s adjusted basis within a twenty-four month period, a program requirement. The Massachusetts State Historic Tax Credit program is a pilot program funded through 2017. Although it is not required for a property to be listed on the National Register of Historic Places, it must be deemed eligible for listing by MHC in order to use the tax credits. A small award of state historic tax credits is included in each pro forma.

347

Page 92: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesHolyoke | Appendix

New Markets Tax Credits. The New Markets Tax Credit (NMTC) program provides tax credits for the construction and redevelopment of commercial, industrial or mixed-use prop-erties in eligible census tracts. The federal government with the NMTC program is seeking to encourage the private sector to invest in lower income communities so as to spur revitalization and job creation. Although complex, NMTC are a very flexible tool and can be used for ei-ther debt or equity financing for a real estate project. The additional cost of legal services has been factored in each analysis. Prospective users of NMTC can contact an entity that has an allocation of NMTC credits. The allocatee becomes a lender/business partner in the project. Allocatees receiving NMTC in recent rounds in Massachusetts include Massachusetts Housing Investment Corporation (MHIC), Boston Community Capital, MassDevelopment as well as others. Several national entities have substantial NMTC allocations that can be used in Massachusetts, as well.

Additional Funding Sources. In some cases, additional funds will be required to enable the redevelopment of each of these properties. Specific funding depends in part on the public benefits of the project and the desired final use. The City of Holyoke receives an annual ap-propriation of Community Development Block Grant (CDBG) funds. CDBG is a potential source of strategic funding on a limited basis. Holyoke tens to use CDBG funds for commu-nity services assisting the City’s very poor.

Holyoke Gas and Electric have incentives for energy conservation and can be a partner in rede-velopment and rehabilitation. The Massachusetts Clean Energy Center can also be a resource.

348

Page 93: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe Enterprises Holyoke | Appendix 349

About theTeam

McCabe Enterprises provides strategic solutions in public financing, community planning and economic development to public and private sector clients with innovative and award-winning work. A wholly woman-owned consulting firm founded by Kathleen McCabe, AICP, EDP in 1990, McCabe Enterprises works with clients to develop customized solutions addressing the unique needs of each client and community. Our approach encompasses planning and economic analysis, financing, community consultation, with a focus on implementation. Our work includes market analysis, feasibility studies, downtown revitalization, public funding, urban renewal, neighborhood planning, industrial retention and redevelopment.

McCabe Enterprises can be reached at [email protected] or 617 469-9444.

McCabe Enterprises team members on the MassDevelopment Holyoke Consultancy include Kathleen McCabe, AICP, EDP and:

Jennifer Mecca, RA, is an architect and experienced urban designer with downtown, and neighborhood revitalization and redevelopment projects, including work with Boston Main Streets and Waterfront Square in Revere. Jennifer has been the urban designer for several re-development projects, in both urban settings and new development, in Massachusetts, New York, Virginia and Florida. She brings a breadth of redevelopment experience and work to enable communities to understand proposed redevelopment projects and their impacts.

Peter Bradley, LEED AP, is the principal and founder of Project Management & Cost, a cost estimating and project management firm. PM&C offers a full range of cost estimating, cost and project management services to building owners, real estate developers, architects, and financial institutions.

McCabeEnterprises

Page 94: 3.1 106-120 High St. - Holyoke Redevelopment · 2014. 8. 18. · 28 Holyoke | 106-120 High Street McCabe Enterprises Regulatory Context 106-120 High Street is located in the BC Downtown

McCabe EnterprisesMcCabe Enterprises | 12 Primrose St. Boston, MA 02131

617.469.9444 | www.plan-do.com

Prepared for:

The City of Holyoke, MA & MassDevelopment

June 2014

HolyokeBuilding Redevelopment Studies