advanced foundation engineering report

Upload: tahir-yildiz

Post on 07-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Advanced Foundation Engineering Report

    1/19

    INTRODUCTIONThis report is prepared to analyze all geotechnical conditions of the railway bridge

    which is planning to be built at Tpra zone in zmit, Turkey. This research contains many

    detailed information about the project such as site condition reports, stability

    analyses,possible problems about the construction, alternative solutions for all problems etc.

    At this project, two boreholes were opened and taken samples so that the soil profile

    and the engineering properties of the soil could be determined. Many in-stu and laboratory

    tests were applied on this samples. CPT is the main test in order to obtain engineering

    properties for the bearing capacity, settlement, liquefaction and heaving capacity. SPT is also

    applied for determining soil profile of the site and deciding the soil type of the site. Correlated

    SPT values were used for calculations and classifications. General geology of the site is also

    investigated and the seismisity of the zone is explained in detail.

    Possible soil problems such as bearing capacity problem, settlement problem and

    permeability problem were considered to be appear in the site while construction. Therefore

    many alternative solutions were determined and advised for a safe structure with a long

    service life without any problem.

  • 8/3/2019 Advanced Foundation Engineering Report

    2/19

    PROJECT INFORMATION

    1) Location: Project is planned to be applied in Tpra-zmit

    2) Climate: Marmara type of climate is usually observed. Very hot and very low amounthof precipitation can be seen in summer whereas cold and rainy winters. Yearly average

    precipitation is about 700 mm and average temperature 14.6 C.

  • 8/3/2019 Advanced Foundation Engineering Report

    3/19

    3) Structural Informations: An approacing way which will be approximately 160 mtlength to be built for the railway overpass section.Kilometres for the approaching way

    is 0+060 to 0+221.35. Height of the approaching way is about 7.5 metres nearby the

    bridge abutment. The possible stress is considered to be occured in soil is estimated as

    160-170 kPa at this section.

    CPT TESTS

    Cpt tests were applied at four different zone at the site. Tip area of the cone is 10 cm

    and the surrounded area is 150 cm. Determination of the soil layers, bearing and

    settlement behaviours are observed by these tests. Undrained shear strength and

    angle with elevation and depth is shown below.

  • 8/3/2019 Advanced Foundation Engineering Report

    4/19

    SPT TESTS

    SPT tests were applied at two points where is close to the bridge abutment. The

    location of the boreholes are so important that these varies are critical for deciding soil

    properties nearby the bridge abutments. Correlated SPT N values with depth and

    elevation is shown in the graphs below. See borehole reports(Appendix)

  • 8/3/2019 Advanced Foundation Engineering Report

    5/19

    Seismisity of The Area:

    zmit is at the first degree earthquake region. Structures must be designed related to

    the possible strong earthquake forces. Therefore, all design criteria about the

    seismisity are listed below:

    1) Active horizontal earthquake acceleration() should be taken as 0.4 g2) Local soil class can be taken as Z3 according to CPT and the other test results3) Soil group is classified as D-C4) Spectrum Periods are taken as =0.15 , =0.60 according to Z3 type soils.ENGINEERING INVESTIGATIONS

    Engineering properties of the construction site is evaluated in bearing capacity,

    settlement, heaving potential.

    Bearing Capacity

    Bearing capacity analyses are applied according to Terzaghi bearing

    capacity formula.

    Terzaghi Method:

    The bearing capacity for shallow foundations:

    . . . . . . .

    , = Shape Factors

    =Unit Weight Above the Foundation Base

    = Foundation Depth

    Foundation Width

    , , = Bearing capacity Factors

    Undrained Shear Strength

  • 8/3/2019 Advanced Foundation Engineering Report

    6/19

    For Clays;

    For Sands;

    Bearing capacity for sands are greater than clays. Therefore critical bearing capacity

    can be calculated according to clays.

    At first 8 metres foundations is considered to be constructed:

    SPT/N~8, c=50 kPa, K=1, =0 >>>Nc=5.7, Nq=1.0, 18 kN/m3, min Df= 0.7m

    Factor of Safety can be taken as 2.0.Then;

    Qall=300/2=150 kPa

    When the structural loads are analysed for the areas the approaching way height (H) is

    greater than 6 mt, the bearing capacity problem is about to occur. Therefore soil

    stabilization is necessary for these regions.

    Settlement:

    For settlement analysis CPT values are used. For the expecting foundation base

    stresses are calculated as CPT-1,H=7.3m>>160 kPa, CPT-2,H=5.8m>>130 kPa,

    CPT-3, H=2.3m>>60 kPa, CPT-4, H=1 m>>35 kPa. Foundation Width(B) is taken as 8

    mt at settlement analysis by using Janbus tangent modulus method.

  • 8/3/2019 Advanced Foundation Engineering Report

    7/19

    CPT No Wall Height(m)

    Stresses at the

    Foundation Base

    (kPa)

    Calculated

    Settlements(cm)

    1 7.3 160 19.9

    2 5.8 130 7.8

    3 2.3 60 16.7

    4 1 35 18.5

    According to the results, settlements at some sections are not in acceptible values(s=10

    cm). Therefore,at this regions soil improvement should be applied to prevent large

    settlements.

    Soil Improvement Methods:

    1) Dynamic Compaction Method2) Prefabricated Sand Drains+ Preloading Method3) Low Densification Potential Granular Backfill (Soil Replacement)4) Jet Grouting or Deep Mixing (DSM) high modulus columnsDynamic compaction method is not advised because of the existance many gas and oil

    tanks around. Sand drains+preloading method is not a suitable choice for improvement

    because of the limited time of the construction. Therefore, soil replacement and jet-

    grouting methods can be choosen.

    1) Soil Replacement MethodIf this method can be applied settlements will be limited according to decreasing the

    soil layer can be consolidated. Therefore, 2 mt excavation will be applied under the

    foundation, then compacted granular backfill is constituted. Ground water table level

    should be considered while application too. For a uniform stres distribution with

    increasing bearing capacity and limited settlements, geogrid can be used between

    foundation base level and granular fill.

  • 8/3/2019 Advanced Foundation Engineering Report

    8/19

    Calculations according to criteria above are listed:

    H= Potential Shear Depth

    Weight Factors:

    Upper Layer: 2.0m/B=2.0/8.0=0.25

    Lower Layer:6.0/8.0=0.75

    Cumulative Soil Parameters:

  • 8/3/2019 Advanced Foundation Engineering Report

    9/19

    Factor of safety can be taken as 2.0:

    Qall= Qult/2=440/2=220 kPa

    According to bearing capacity results after soil replacement, approaching way is safe

    and the method is convenient.

    Settlement Analyzes:

    Using tangent modulus, settlements after 2 mt replacement is calculated as below:

    CPT No Wall Height(m)

    Stresses at the

    Foundation Base

    (kPa)

    Calculated

    Settlements(cm)

    1 7.3 160 5.5

    2 5.8 130 3.1

    3 2.3 60 4.4

    4 1 35 5.3

    Settlements is also limited by this soil improvement technique.

    During the application,because of the clay existance in lower layers, some compaction

    problems may occur. In order to prevent these problems. Geogrid application at the

    base of the granular fill base, 50 cm rock fill layer above the geogrid, and the geotextile

    application on the rock layer fort he purpose of seperation is advised. The backfill

    should be constructed on this layers to avoid possible compacting problems.

  • 8/3/2019 Advanced Foundation Engineering Report

    10/19

    2) Jet Grouting-Deep Mixing (DSM) Method:According to this application,the general informations and results are listed below:

    a) Jet Grouting Method- Diameters of jetgrout columns: 0.6 m- Distance between jetgrout columns (centre): 2.0m- Length of the columns: 10 m- Vertical Allowable Bearing Capacity of Each Column: 40 tonb) Deep Mixing (DSM) Method- Diameters of columns: 0.8 m- Distance between columns: 2.5m- Length of columns: 10 m- Vertical allowable Bearing Capacity of Each Column:70 tonSettlements after jetgrout-deep mixing(DSM) application is shown below:

    CPT No Wall Height(m)

    Stresses at the

    Foundation Base

    (kPa)

    Calculated

    Settlements(cm)

    1 7.3 160 9.6

    2 5.8 130 6.8

    3 2.3 60 3.7

    4 1 35 2.4

  • 8/3/2019 Advanced Foundation Engineering Report

    11/19

    APPENDIX

    A-BOREHOLE DOCUMENTS

    B-CROSS SECTION OF THE BRIDGE

    C-PLAN VIEW OF THE AREA

    D-KEY PLAN

    E-REINFORCED EARTH WALL PROFILE

    F-TANGENT MODULUS METHOD

    G-PHOTOS OF THE AREA

  • 8/3/2019 Advanced Foundation Engineering Report

    12/19

  • 8/3/2019 Advanced Foundation Engineering Report

    13/19

  • 8/3/2019 Advanced Foundation Engineering Report

    14/19

  • 8/3/2019 Advanced Foundation Engineering Report

    15/19

  • 8/3/2019 Advanced Foundation Engineering Report

    16/19

  • 8/3/2019 Advanced Foundation Engineering Report

    17/19

  • 8/3/2019 Advanced Foundation Engineering Report

    18/19

    Tangent Modulus Approach

    Settlements in cohesive and cohesionless soils can be analysed using the tangentmodulus method, which takes into account the non-linearity of the load-deformation

    relationship of most soils. Janbu (1963) has shown that the tangent modulus Mt can bedefined by the following relationship,

    Mt = m .r ( /r)(1 - j) (14)

    where m is a dimensionless modulus number, r is an arbitrarily chosen reference stress

    (100 kPa), is the vertical effective stress and j is a stress exponent. The strain

    increase of a soil layer caused by an increase of the vertical effective stress canbe calculated from

    = {[ ( 0 + ) /r] j - [0 /r] j }/( m . j ) (15)

    where 0 is the initial vertical effective overburden stress and is the increase of thevertical effective stress. For cohesive soils, values of the modulus number m and the

    stress exponentjcan be determined by conventional laboratory tests. For cohesionlesssoils, however, it is often difficult to obtain undisturbed soil samples and the results fromlaboratory tests are therefore uncertain. Thus, empirical values are often used toestimate the modulus number and the stress exponent, cf. Canadian FoundationEngineering Manual (1985), Table 4.

    Soil Type Stress Exponent,j

    Modulus Number,

    m

    Gravel 0,5 40 - 400

    Dense Sand 0,5 250 - 400

    Compact Sand 0,5 150 - 250

    Loose Sand 0,5 100 - 150

    Dense Silt 0,5 80 - 200

    Compact Silt 0,5 60 - 80

    Loose Silt 0,5 40 - 60

    Table 4. Typical Values for the Stress Exponent j and the Modulus Number m for

    granular soils, (after Canadian Foundation Engineering Manual, 1985)

    Copyright 1998-2009 GRV ABLegal disclaimer

  • 8/3/2019 Advanced Foundation Engineering Report

    19/19