advanced superconducting cable system for urban power...

32
AmpaCity Project Advanced Superconducting Cable System for Urban Power Supply Frank Schmidt EPRI Superconductivity Conference October 2013

Upload: others

Post on 26-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • AmpaCity Project

    Advanced Superconducting Cable System

    for Urban Power Supply

    Frank Schmidt

    EPRI Superconductivity Conference

    October 2013

  • NEXANS PROPRIETARY Houston – October 2013 – 2

    Agenda

    AmpaCity Project Overview

    Techno-economical Study

    AmpaCity Installation

    HTS System Design

    AmpaCity Project Status

    Conclusions

  • NEXANS PROPRIETARY Houston – October 2013 – 3

    AmpaCity Project Objectives

    Installation of 10 kV, 40 MVA (2.3 kA) HTS system in German city

    Essen

    Project started in September 2011 with duration of 4.5 years

    Commissioning before end of 2013

    Demonstration period of at least 2 years

    Funded by the German Federal Ministry of Economics and Technology

    Investigation of technical feasibility of HTS systems in distribution

    grids

    Comparison of investment between MV HTS and conventional HV

    systems

    Evaluation of operational advantages during demonstration period

    Assessment of further HTS system applications

  • NEXANS PROPRIETARY Houston – October 2013 – 4

    Project Team and Responsibilities

    RWE

    Specification of HTS system to be installed in distribution grid

    Field test of HTS system connecting two substations

    Nexans

    Development of HTS cable including type test of all components

    Manufacturing of HTS cable system and HTS fault current limiter

    KIT

    HTS tests and characterization

    AC loss measurements and modeling (FEM 2D and 3D)

  • NEXANS PROPRIETARY Houston – October 2013 – 5

    Ampacity project overview

    New grid concept

    MV

    HV HV

    MV

    introducing

    superconducting

    MV cables

  • NEXANS PROPRIETARY Houston – October 2013 – 6

    Conventional 110 kV cable

    12

    00

    600

    175 175125 125

    10

    50

    650

    85

    0

    125125 100 100100 100

    145

    200

    400

    70

    0

    100 100

    Techno-economical study

    3 solutions considered

    Conventional 10 kV cables Superconducting 10 kV cable

  • NEXANS PROPRIETARY Houston – October 2013 – 7

    A

    D E

    40 MVA

    J

    B

    C

    F

    IHG

    40 MVA

    40 MVA 40 MVA 40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    5,0 km

    6,2 km

    4,6

    km

    2,6

    km

    2,7

    km

    3,0

    km

    3,1

    km

    2,2 km

    3,6 km

    2,6

    km

    4,3 km

    3,2 km4,7 km

    A

    D E

    40 MVA

    J

    B

    C

    F

    IHG

    40 MVA

    40 MVA 40 MVA 40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    A

    D E

    40 MVA

    J

    B

    C

    F

    IHG

    40 MVA

    40 MVA 40 MVA 40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    5,0 km

    6,2 km

    4,6

    km

    2,6

    km

    2,7

    km

    3,0

    km

    3,1

    km

    2,2 km

    3,6 km

    2,6

    km

    4,3 km

    3,2 km4,7 km

    Economic Study - Urban Grid with HV Cables

    Future grid structure has

    been designed based on

    Conventional 110 kV

    cables

    Superconducting 10 kV

    cables

    Perquisites: same

    redundancy (n-1)

    Economic viability compared

  • NEXANS PROPRIETARY Houston – October 2013 – 8

    5,0 km

    6,2 km

    4,6

    km

    2,6

    km

    2,7

    km

    3,0

    km

    3,6 km

    6,8 km

    3,2 km

    4,7 km

    A

    D

    E

    J

    B

    C

    F

    I

    H

    G

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    40 MVA

    40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA40 MVA

    40 MVA

    40 MVA

    3,0

    km

    8,4

    km

    2,7

    km 2,6

    km

    5,0 km

    6,2 km

    4,6

    km

    2,6

    km

    2,7

    km

    3,0

    km

    3,6 km

    6,8 km

    3,2 km

    4,7 km

    A

    D

    E

    J

    B

    C

    F

    I

    H

    G

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    40 MVA

    40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA40 MVA

    40 MVA

    40 MVA

    A

    D

    E

    J

    B

    C

    F

    I

    H

    G

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    110 kV OHL

    110 kV UGC

    10 kV UGC

    110 kV busbar

    10 kV busbar

    Bus tie (open)

    40 MVA

    40 MVA 40 MVA

    40 MVA

    40 MVA

    40 MVA40 MVA40 MVA

    40 MVA

    40 MVA

    3,0

    km

    8,4

    km

    2,7

    km 2,6

    km

    Economic Study - Urban Grid with MV HTS

    Cables

    Dispensable devices for new grid concept

    • 12.1 km of 110 kV cable systems

    • 12 x 110 kV cable switchgear

    • 5 x 40 MVA, 110/10 kV

    transformers

    • 5 x 110 kV transformer switchgear

    • 5 x 10 kV transformer switchgear

    Additionally required devices for new grid concept

    • 23.4 km of 10 kV HTS cable

    system

    • 16 x 10 kV cable switchgear

    • 3 x 10 kV bus ties

  • NEXANS PROPRIETARY Houston – October 2013 – 9

    > Comparison of the 3 options based on NPV method

    > Investment costs and operating costs (maintenance and losses)

    > 40 years

    > 2 % yearly increase

    > 6.5 % interest rate

    > 65 €/MWh

    Tota

    l N

    PV

    in M

    103.2

    87.7

    93.7

    Techno-economical study

    Conclusion

    Real estate value

    represents additional

    benefit for the HTS

    technology

  • NEXANS PROPRIETARY Houston – October 2013 – 10

    AmpaCity Installation in Essen,

    Germany

    Luftbild: "Darstellung aus HK Luftbilder / Karten Lizenz Nr. 197 / 2012 mit Genehmigung

    vom Amt für Geoinformation, Vermessung und Kataster der Stadt Essen vom 13.02.2012"

    Technical specification

    - 1 km distance between substations

    - 10 kV system voltage

    - 2.3 kA operating current (40 MVA)

    Substation

    Dellbrügge

    Cable Joint

    Substation

    Herkules

  • NEXANS PROPRIETARY Houston – October 2013 – 11

    40 MVA

    40 MVA

    40 MVA

    40 MVA 110 kV 10 kV

    10 kV

    110 kV UGC

    110 kV UGC

    Substation

    Herkules

    Substation

    Dellbrügge

    Ampacity project

    Present electrical configuration

  • NEXANS PROPRIETARY Houston – October 2013 – 12

    40 MVA

    10 kV

    40 MVA 110 kV

    10 kV

    40 MVA

    FCL 10 kV HTS UGC

    110 kV UGC

    Substation

    Herkules

    Substation

    Dellbrügge

    Ampacity project

    Configuration with supercond. system

  • NEXANS PROPRIETARY Houston – October 2013 – 13

    Substation Dellbrügge – Basement and

    1st Floor

  • NEXANS PROPRIETARY Houston – October 2013 – 14

    Substation Herkules – Front

  • NEXANS PROPRIETARY Houston – October 2013 – 15

    Substation Herkules – Back

    Empty trans-

    former box

  • NEXANS PROPRIETARY Houston – October 2013 – 16

    Joint Location

  • NEXANS PROPRIETARY Houston – October 2013 – 17

    Cable Design

    Dielectric Former

    Screen

    Outer LN2 Cooling

    Cable Cryostat

    Inner LN2

    Cooling

    Phase 1 Phase 2

    Phase 3

  • NEXANS PROPRIETARY Houston – October 2013 – 18

    Termination Design

    Termination

    Cryostat

    Cooling

    Inlet Phase 1

    Phase 2

    Phase 3

    Cooling

    Outlet

    Measurement

    Connection

    Cable

    Connection

    Screen

  • NEXANS PROPRIETARY Houston – October 2013 – 19

    Parameter Value

    Rated power 40 MVA

    Rated voltage 10 kV

    Rated current 2.3 kA

    Lightning impulse withstand

    voltage 75 kV

    Power frequency withstand

    voltage 28 kV

    Prospective peak short

    circuit current 50 kA

    Prospective short circuit

    current 20 kA

    Limited peak short circuit

    current < 13 kA

    Limited short circuit current < 5 kA

    Limitation time 100 ms

    Fault Current Limiter Design

  • NEXANS PROPRIETARY Houston – October 2013 – 20

    > 4 kW cold power at 67 K

    > Subcooled pressurized nitrogen

    > Forced flow in closed circuit

    > High availability and reliability

    Cooling System Design

    Pressure

    Built-Up

    HTS Cable

    SFCL

    Vacuum

    Pump

    lN2 Storage

    Tank

    Circulation

    Pump

  • NEXANS PROPRIETARY Houston – October 2013 – 21

    Status Cable Development

    Pre-prototype cable

    Manufacturing of 100 m pre-prototype cable was completed in June 2012

    Installation of pre-prototype test setup (30 m cable loop with terminations) has been

    finished

    High voltage tests have been performed on pre-prototype test setup

    Bending test on 20 m pre-prototype cable has been carried out

    Cable sections from bending test have been dissected and inspected

    Prototype cable

    Manufacturing of prototype cable was completed in October 2012

    Prototype cable was installed with joint and terminations in HV test lab

    Type test of prototype cable setup was successfully finished

  • NEXANS PROPRIETARY Houston – October 2013 – 22

    Test Setup Pre-Prototype Cable

  • NEXANS PROPRIETARY Houston – October 2013 – 23

    Type Test Setup Prototype Cable

  • NEXANS PROPRIETARY Houston – October 2013 – 24

    Prototype Termination

  • NEXANS PROPRIETARY Houston – October 2013 – 25

    Prototype Joint

  • NEXANS PROPRIETARY Houston – October 2013 – 26

    Type Test Sequence Prototype Setup

    PD test at 20 kV (after 24 kV for 1 min)

    20 Load cycles with 2.3 kA (3 phase)

    PD test at 20 kV (after 24 kV for 1 min)

    Lightning impulse test at ± 75 kV

    AC voltage withstand test at 30 kV (4 h)

  • NEXANS PROPRIETARY Houston – October 2013 – 27

    Cable Cryostats

  • NEXANS PROPRIETARY Houston – October 2013 – 28

    AmpaCity – Cable Installation

  • NEXANS PROPRIETARY Houston – October 2013 – 29

    AmpaCity – Fault Current Limiter

    Installation

  • NEXANS PROPRIETARY Houston – October 2013 – 30

    Application for funding at the German Ministery of Economics and Technology (BMWI) - March 2011

    Project acceptance by BMWI with 43% funding on September 5th 2011

    Manufacturing of Prototype - Q3 and Q4 2012

    Successful type test beginning of 2013 – Start of cable system manufacturing

    Ground breaking ceremony in Essen on April 9th, 2013

    Installation of HTS System - Q3 and Q4 2013

    Commissioning - Q4 2013

    Grid operation - 2013 to 2015

    Analysis of grid operating experience and discussion of further implementation steps - early 2016

    AmpaCity – Status and Milestones

  • NEXANS PROPRIETARY Houston – October 2013 – 31

    Superconductors have come out of laboratories and are now

    ready to be incorporated in power grids

    Superconducting systems constitute attractive alternatives to

    conventional systems

    Reducing operating voltages

    Enabling new grid concepts

    Reducing the number of inner city transformer substations

    The economical viability of superconducting systems is

    now achievable

    Conclusion

  • Thank You For Your Attention