advanced superconducting cable system for urban power...
TRANSCRIPT
-
AmpaCity Project
Advanced Superconducting Cable System
for Urban Power Supply
Frank Schmidt
EPRI Superconductivity Conference
October 2013
-
NEXANS PROPRIETARY Houston – October 2013 – 2
Agenda
AmpaCity Project Overview
Techno-economical Study
AmpaCity Installation
HTS System Design
AmpaCity Project Status
Conclusions
-
NEXANS PROPRIETARY Houston – October 2013 – 3
AmpaCity Project Objectives
Installation of 10 kV, 40 MVA (2.3 kA) HTS system in German city
Essen
Project started in September 2011 with duration of 4.5 years
Commissioning before end of 2013
Demonstration period of at least 2 years
Funded by the German Federal Ministry of Economics and Technology
Investigation of technical feasibility of HTS systems in distribution
grids
Comparison of investment between MV HTS and conventional HV
systems
Evaluation of operational advantages during demonstration period
Assessment of further HTS system applications
-
NEXANS PROPRIETARY Houston – October 2013 – 4
Project Team and Responsibilities
RWE
Specification of HTS system to be installed in distribution grid
Field test of HTS system connecting two substations
Nexans
Development of HTS cable including type test of all components
Manufacturing of HTS cable system and HTS fault current limiter
KIT
HTS tests and characterization
AC loss measurements and modeling (FEM 2D and 3D)
-
NEXANS PROPRIETARY Houston – October 2013 – 5
Ampacity project overview
New grid concept
MV
HV HV
MV
introducing
superconducting
MV cables
-
NEXANS PROPRIETARY Houston – October 2013 – 6
Conventional 110 kV cable
12
00
600
175 175125 125
10
50
650
85
0
125125 100 100100 100
145
200
400
70
0
100 100
Techno-economical study
3 solutions considered
Conventional 10 kV cables Superconducting 10 kV cable
-
NEXANS PROPRIETARY Houston – October 2013 – 7
A
D E
40 MVA
J
B
C
F
IHG
40 MVA
40 MVA 40 MVA 40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
5,0 km
6,2 km
4,6
km
2,6
km
2,7
km
3,0
km
3,1
km
2,2 km
3,6 km
2,6
km
4,3 km
3,2 km4,7 km
A
D E
40 MVA
J
B
C
F
IHG
40 MVA
40 MVA 40 MVA 40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
A
D E
40 MVA
J
B
C
F
IHG
40 MVA
40 MVA 40 MVA 40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
5,0 km
6,2 km
4,6
km
2,6
km
2,7
km
3,0
km
3,1
km
2,2 km
3,6 km
2,6
km
4,3 km
3,2 km4,7 km
Economic Study - Urban Grid with HV Cables
Future grid structure has
been designed based on
Conventional 110 kV
cables
Superconducting 10 kV
cables
Perquisites: same
redundancy (n-1)
Economic viability compared
-
NEXANS PROPRIETARY Houston – October 2013 – 8
5,0 km
6,2 km
4,6
km
2,6
km
2,7
km
3,0
km
3,6 km
6,8 km
3,2 km
4,7 km
A
D
E
J
B
C
F
I
H
G
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
40 MVA
40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA40 MVA
40 MVA
40 MVA
3,0
km
8,4
km
2,7
km 2,6
km
5,0 km
6,2 km
4,6
km
2,6
km
2,7
km
3,0
km
3,6 km
6,8 km
3,2 km
4,7 km
A
D
E
J
B
C
F
I
H
G
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
40 MVA
40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA40 MVA
40 MVA
40 MVA
A
D
E
J
B
C
F
I
H
G
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
110 kV OHL
110 kV UGC
10 kV UGC
110 kV busbar
10 kV busbar
Bus tie (open)
40 MVA
40 MVA 40 MVA
40 MVA
40 MVA
40 MVA40 MVA40 MVA
40 MVA
40 MVA
3,0
km
8,4
km
2,7
km 2,6
km
Economic Study - Urban Grid with MV HTS
Cables
Dispensable devices for new grid concept
• 12.1 km of 110 kV cable systems
• 12 x 110 kV cable switchgear
• 5 x 40 MVA, 110/10 kV
transformers
• 5 x 110 kV transformer switchgear
• 5 x 10 kV transformer switchgear
Additionally required devices for new grid concept
• 23.4 km of 10 kV HTS cable
system
• 16 x 10 kV cable switchgear
• 3 x 10 kV bus ties
-
NEXANS PROPRIETARY Houston – October 2013 – 9
> Comparison of the 3 options based on NPV method
> Investment costs and operating costs (maintenance and losses)
> 40 years
> 2 % yearly increase
> 6.5 % interest rate
> 65 €/MWh
Tota
l N
PV
in M
€
103.2
87.7
93.7
Techno-economical study
Conclusion
Real estate value
represents additional
benefit for the HTS
technology
-
NEXANS PROPRIETARY Houston – October 2013 – 10
AmpaCity Installation in Essen,
Germany
Luftbild: "Darstellung aus HK Luftbilder / Karten Lizenz Nr. 197 / 2012 mit Genehmigung
vom Amt für Geoinformation, Vermessung und Kataster der Stadt Essen vom 13.02.2012"
Technical specification
- 1 km distance between substations
- 10 kV system voltage
- 2.3 kA operating current (40 MVA)
Substation
Dellbrügge
Cable Joint
Substation
Herkules
-
NEXANS PROPRIETARY Houston – October 2013 – 11
40 MVA
40 MVA
40 MVA
40 MVA 110 kV 10 kV
10 kV
110 kV UGC
110 kV UGC
Substation
Herkules
Substation
Dellbrügge
Ampacity project
Present electrical configuration
-
NEXANS PROPRIETARY Houston – October 2013 – 12
40 MVA
10 kV
40 MVA 110 kV
10 kV
40 MVA
FCL 10 kV HTS UGC
110 kV UGC
Substation
Herkules
Substation
Dellbrügge
Ampacity project
Configuration with supercond. system
-
NEXANS PROPRIETARY Houston – October 2013 – 13
Substation Dellbrügge – Basement and
1st Floor
-
NEXANS PROPRIETARY Houston – October 2013 – 14
Substation Herkules – Front
-
NEXANS PROPRIETARY Houston – October 2013 – 15
Substation Herkules – Back
Empty trans-
former box
-
NEXANS PROPRIETARY Houston – October 2013 – 16
Joint Location
-
NEXANS PROPRIETARY Houston – October 2013 – 17
Cable Design
Dielectric Former
Screen
Outer LN2 Cooling
Cable Cryostat
Inner LN2
Cooling
Phase 1 Phase 2
Phase 3
-
NEXANS PROPRIETARY Houston – October 2013 – 18
Termination Design
Termination
Cryostat
Cooling
Inlet Phase 1
Phase 2
Phase 3
Cooling
Outlet
Measurement
Connection
Cable
Connection
Screen
-
NEXANS PROPRIETARY Houston – October 2013 – 19
Parameter Value
Rated power 40 MVA
Rated voltage 10 kV
Rated current 2.3 kA
Lightning impulse withstand
voltage 75 kV
Power frequency withstand
voltage 28 kV
Prospective peak short
circuit current 50 kA
Prospective short circuit
current 20 kA
Limited peak short circuit
current < 13 kA
Limited short circuit current < 5 kA
Limitation time 100 ms
Fault Current Limiter Design
-
NEXANS PROPRIETARY Houston – October 2013 – 20
> 4 kW cold power at 67 K
> Subcooled pressurized nitrogen
> Forced flow in closed circuit
> High availability and reliability
Cooling System Design
Pressure
Built-Up
HTS Cable
SFCL
Vacuum
Pump
lN2 Storage
Tank
Circulation
Pump
-
NEXANS PROPRIETARY Houston – October 2013 – 21
Status Cable Development
Pre-prototype cable
Manufacturing of 100 m pre-prototype cable was completed in June 2012
Installation of pre-prototype test setup (30 m cable loop with terminations) has been
finished
High voltage tests have been performed on pre-prototype test setup
Bending test on 20 m pre-prototype cable has been carried out
Cable sections from bending test have been dissected and inspected
Prototype cable
Manufacturing of prototype cable was completed in October 2012
Prototype cable was installed with joint and terminations in HV test lab
Type test of prototype cable setup was successfully finished
-
NEXANS PROPRIETARY Houston – October 2013 – 22
Test Setup Pre-Prototype Cable
-
NEXANS PROPRIETARY Houston – October 2013 – 23
Type Test Setup Prototype Cable
-
NEXANS PROPRIETARY Houston – October 2013 – 24
Prototype Termination
-
NEXANS PROPRIETARY Houston – October 2013 – 25
Prototype Joint
-
NEXANS PROPRIETARY Houston – October 2013 – 26
Type Test Sequence Prototype Setup
PD test at 20 kV (after 24 kV for 1 min)
20 Load cycles with 2.3 kA (3 phase)
PD test at 20 kV (after 24 kV for 1 min)
Lightning impulse test at ± 75 kV
AC voltage withstand test at 30 kV (4 h)
-
NEXANS PROPRIETARY Houston – October 2013 – 27
Cable Cryostats
-
NEXANS PROPRIETARY Houston – October 2013 – 28
AmpaCity – Cable Installation
-
NEXANS PROPRIETARY Houston – October 2013 – 29
AmpaCity – Fault Current Limiter
Installation
-
NEXANS PROPRIETARY Houston – October 2013 – 30
Application for funding at the German Ministery of Economics and Technology (BMWI) - March 2011
Project acceptance by BMWI with 43% funding on September 5th 2011
Manufacturing of Prototype - Q3 and Q4 2012
Successful type test beginning of 2013 – Start of cable system manufacturing
Ground breaking ceremony in Essen on April 9th, 2013
Installation of HTS System - Q3 and Q4 2013
Commissioning - Q4 2013
Grid operation - 2013 to 2015
Analysis of grid operating experience and discussion of further implementation steps - early 2016
AmpaCity – Status and Milestones
-
NEXANS PROPRIETARY Houston – October 2013 – 31
Superconductors have come out of laboratories and are now
ready to be incorporated in power grids
Superconducting systems constitute attractive alternatives to
conventional systems
Reducing operating voltages
Enabling new grid concepts
Reducing the number of inner city transformer substations
The economical viability of superconducting systems is
now achievable
Conclusion
-
Thank You For Your Attention