alaska highway pipeline project update presentation to the alaska state legislature joint committee...
TRANSCRIPT
ALASKA HIGHWAY PIPELINEPROJECT UPDATE
Presentation to the
Alaska State Legislature Joint Committeeon
Natural Gas Pipelines
ALASKA HIGHWAY PIPELINEPROJECT UPDATE
Presentation to the
Alaska State Legislature Joint Committeeon
Natural Gas Pipelines
July 18, 2001
Agenda
Review ANGTS Advantages
Overview of Alaskan Benefits of ANGTS
Current Status
Withdrawn Partners Issue
Open Access
Potential State Participation
Potential Gas Delivery to South Central Alaska
Path Forward for ANGTS
Questions and Answers
Alaskan Northwest Natural Gas Transportation Company Corporate Ownership
Westcoast Energy Inc.
Foothills Pipe Lines Ltd.
TransCanada PipeLinesLimited
ANNGTC
ANGTS Advantages
Earliest Timing
Flexible Framework
Land Tenure
Best Route
ANGTS Advantages
Earliest Timing
ANNGTC/Foothills was selected by the United States and Canada to construct and operate the ANGTS and have secured the following: Federal Lands ROW Federal ROW on State lands FERC Certificate NEB Certificate US Corps 404 permits Yukon ROW British Columbia Map Reserve
Each of these components could be expected to require 18 to 36 months to secure after a green field application is submitted.
ANGTS Advantages
Flexible Framework
The ANGTS framework provides an existing, tested and accepted framework for expediting the delivery of ANS gas to the Lower 48
Canada has repeatedly reaffirmed its intention to fulfill its commitments reflected in the ANGTS framework
The ANGTS framework allows for updates to the existing U.S. and Canadian regulatory framework to modify the project, including initial required shipping capacity, the use of updated technology, environmental review, open access and negotiated rate structure
The ANGTS sponsors are committed to working with the State, ANS producers and other potential shippers to develop a project that achieves the commercial and economic objectives of all parties
YUKON
NWTB.C.
NUNAVUT
ALBERTA
SASKATCHEWAN
Whitehorse
Prudhoe Bay
Inuvik
Kingsgate
Monchy
Fort Nelson
Fairbanks
Boundary Lake
Beaver Creek
Gordondale
Caroline
ALASKA
ANGTS Advantages
Land Tenure
ALASKA Federal Grant
• 434 miles have been acquired of which–261 miles remain under Federal authority–173 miles have been transferred to the State
• 5 Compressor Station Sites and • 1 Meter Station Site has also been acquired
State Application• Approximately 200 miles under active application
• 2 Compressor Station Sites and • 1 Meter Station Site included in application
Other Lands• Approximately 110 miles to be acquired
YUKON • Foothills holds a grant of easement for the entire ROW in Yukon.
• Compressor Station sites, temporary and other permanent sites are protected as Reservations by Notation for the Project
NORTH B.C. • Foothills holds Map Reserves on all provincial Crown lands within this segment of the Project.
ANGTS Advantages
Best Routing
Best alternative for delivering Alaskan gas to the Lower 48 Can be constructed with proven technology Has been extensively reviewed Relies on existing infrastructure Will minimize adverse environmental effects Delivers gas to Alaskan consumers
ANGTS Advantages
Best Access to North American Pipeline Grid
Access to the North American grid enhances the success of the Alaska Highway Pipeline
Foothills, TransCanada and Westcoast have built and operate most of the gas pipelines in Canada
Offers expanded market opportunities for Alaska Gas
Foothills, TransCanada and Westcoast recognized as experienced, reliable and cost effective pipe builders and operators.
Alaskan Benefits
Based on $3 to $5 mmbtu gas price range over 25 years
Increase in Gross State Product $55 to $122 billion
Increase in employment 26,000 person years
Increase in state and local gov’t revenues $12 to $29 billion
Increase in gross revenues for Alaskan Producers $36 to $103 billion
Gross revenue gains to Gas Producers through earlier (3 years) connection $4 to $12 billion
Current Status
ANGTS Update
Finalizing state lands right-of-way
Negotiating a Memorandum of Understanding with Joint Pipeline Office
Continuing dialogue with: Government officials in Ottawa and Washington Aboriginal Communities ANS Producers ANNGTC Withdrawn Partners
Current Status
Discussions with Gas Producers/Shippers
Ongoing discussions with North Slope Producers
Contact with other interested parties such as exploration and development companies, power generators and power marketers
Current Status
Discussions With Aboriginal Communities
Continuing to build upon positive relationships Foothills has developed over two decades
Building support through discussion of the community benefits of pipeline development
Withdrawn Partners Issue
ANNGTC Withdrawn Partners have right to recover monies under certain circumstances
It is recognized that the Withdrawn partners issue needs to be addressed in the overall commercial resolution of this pipeline development.
This is an issue between ourselves and the Withdrawn partners
The process to re-enlist Withdrawn Partners has begun and although in the early stages, so far we have seen some encouraging signs.
Open Access
Alaska’s interests best served by continued gas exploration and development
Access to pipeline vital to E&P activity
Financing for the initial pipeline will require long-term shipping contracts
Additional future capacity provided by: Additional compression Looping Combination of both
Additional capacity will be available to all on an open access basis
As a pure pipeline service provider, it is in Foothills interests to provide expanded capacity to meet demand
Potential State Participation
We understand the State is looking at ways to directly participate in a pipeline development
There are several ways the State could participate in the ANGTS As a lender or guarantor As a shipper As an equity partner
ANNGTC/Foothills would consider discussion of these or other matters of interest to the State
Gas to South Central Alaska
Current gas demand in South Central is approximately 220 Bcf per year
This volume could be delivered via a 16-inch spur line connected to the ANGTS near Fairbanks
As a pure pipeline service provider, it is in Foothills interests to serve additional supply and market areas whenever it is economic to do so
Path Forward for ANGTS
Foothills
Continuing to work toward goal of commercial alignment with Producers and potential Shippers
Finalizing state lands ROW
Building support in Canada for two stand alone arctic pipelines
Recommendations to Joint Committee
Publicly encourage gas producers and pipeliners to bring collective strengths to the table and accelerate development of the ANGTS
Support the conclusion that only ANGTS meets the Governor’s goal of earliest possible start for the pipeline project
Questions