Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
SUSTAINABLE URBAN PUBLIC TRANSPORT
Presentation to The 2nd ACP/EC/UN Habitat Tripartite Conference 4th September, Kigali, Rwanda
By Eng. D. A. Odeck, Manager (Special Projects)
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
Challenges arising from current public transport situation
Social Segregation/ Unequal access/ poor or unused NMT facilities/ Lack of safety and security
Air and noise pollution
Excessive energy consumption
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
Challenges arising from current public transport situation
Traffic congestion
unavailability and high cost of land along main corridors
mushrooming of slums
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
Efforts towards sustainable public transport solutions
Master Plan for Urban Transport in the Nairobi Metropolitan Area for 2006 -2025 Recommended Improvement of Transport system through
•better route assignment •corridor improvement •introduction of shuttle bus •mode interchange area improvement
Feasibility Study for Mass Rapid Transit System for the Nairobi Metropolitan Region of 2011
CRITERIA RECOMMENDATION CORRIDOR
PHPDT > 5,000 BRT Mombasa, Limuru & Langata Roads
PHPDT > 12,000 LRT Jogoo & Outer Ring Roads
PHPDT > 30,000 METRO Thika & Juja Roads
MIXED METRO/ BRT Ngong Road
MIXED LRT/ BRT Waiyaki Way
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
The Mass Rapid Transit Options
Range of construction cost (millions USD per km) Source: GTZ Guide
BRT – Bus typically operating on exclusive right-of-way at surface level with grade separation provided at intersections LRT – Rail car(s) typically operating on exclusive right-of-way at surface level with overhead electrical connectors METRO – Heavy rail transit system operating on grade separated tracks that are located principally underground.
- 50 100 150 200 250 300 350 400
BRT
LRT
METRO
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
The Athi River –Nairobi Railway Station- Kikuyu Corridor
•45km long running north-westerly along the Red line •Includes branch line to JKIA and loop in Nairobi CBD
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
Status of the Athi River –Nairobi Railway Station- Kikuyu Corridor project: Design activities ongoing
•45km long running north-westerly along the Red line •Includes branch line to JKIA and loop in Nairobi CBD
Source
: GTZ
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
BEST PRACTISE BRT INFRASTRUCTURE
Source: Transmilenio, Bogota
•Dedicated lanes on median •Passenger safe crossing structures •Overtaking lanes at station
Source: Transmilenio, Bogota
•Fare prepayment •Safe & clean stations
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
BEST PRACTISE BRT INFRASTRUCTURE
Source: Beijing
•Good brand and strong identity •Several doors for boarding •Universal access
Source: Guanghzou
•Passenger information •Multiple routes on same corridor
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
BEST PRACTISE BRT INFRASTRUCTURE
Source: Nantes
•Park & Ride schemes •Bike share stations
Source: Guanghzou
•Control centre •Intelligent transport Systems
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
CONTRIBUTION OF BRT TO SOLVING CURRENT URBAN TRANSPORTATION CHALLENGES
S/No. Problem How BRT will contribute to solution
1 Air and noise pollution BRTS to use fuels with low emissions (CNG).
Passenger information systems negate need for touting.
2 Excessive energy consumption Reduction in use of personal cars
3 Social segregation/ unequal
access/ Lack of safety and
security
Better BRT passenger/ NMT facilities integration
4 Traffic congestion Reduction in use of personal cars
Better parking regimes
5 unavailability and high cost of
land along main corridors
Acquisition for road expansion will be unnecessary in the short term.
In the long term, new unoccupied corridors may be identified
6 Mushrooming of slums Low income workers will afford regulated service and could stay in
cheaper but decent peri-urban housing
Component Design Project data Design Progress Completion of Design/ Probable
start of Construction
Remarks
Capacity enhancement of A104 from JKIA to
Likoni Road junction
Consultant: Gibb Africa
Ltd in association with Associated
Consultants
Contract price: Kshs 91,750,763.45 and
USD 217,442.00
Commencement Date: 1st June 2012
Progress to date; 25%
Certified Amount:
Ksh 32,112,767.20 and
USD 76,104.70
(25% Advance plus
10% inception)
Completion date: 25th June 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Inception report submitted July 2012.
- Draft Preliminary Design submitted Feb 2013.
-Estimated cost of construction Ksh.9.2Billion
- Addendum for BRT detailed design under review.
Capacity enhancement of A104 Likoni road to
James Gichuru Road Junction
Consultant: COWI in
association with Otieno Odongo and Qutep
Contract price: Kshs 82,284,240.00 and
EURO 809,100.00
Commencement Date: 15th March
2012
Progress to date; 30%
Certified Amount:
Ksh. 45,256,322.00 and EURO 445,005.00
(25% Advance plus 10% inception and 20%
preliminary)
Completion date: 4th July 2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
- Final Preliminary design report submitted October 2012
- Estimated cost of construction is USD 270 million
- estimated cost of elevated roadway (viaduct) is USD 44 million per km.
- Addendum for BRT detailed design under preparation
Capacity enhancement of A104 James Gichuru
Road junction to Rironi Junction
Consultant: Eser Project
And Engineering Co. Inc. in Association With
Bosphorus Technical Consulting Corporation
Contract price: KShs 113,033,265.00
Commencement Date: 22nd May
2012
Progress to date; 30%
Certified Amount:
Ksh 39,561,642.75
(25% Advance plus 10% Inception and 20%
preliminary)
Completion date: 3rd September
2013
*additional time for detailed design for BRT
may be necessary
Probable start of construction:
March 2014
-Inception report submitted in May 2012.
- Draft Preliminary design report submitted December 2012
- Estimated cost of construction is Ksh 11.3 billion
- Addendum for BRT detailed design under preparation
Kisumu Northern Bypass Consultant: Sheladia
Associates Inc in association with Abdul
Mullick Associates
Contract price:
US$ 82,621.36 and KES
23,537,996.98
Commencement Date: April 2012 –
Phase 1
October 2012 – Phase 2
Progress to date; 15%
Certified Amount:
KES 2,353,799.69 and
US$ 8,262.14
Completion date: 6th June 2013
Probable start of construction:
November 2013
-ESIA and RAP reports submitted May 2012.
- sectional draft preliminary reports submitted April 2013
THANK YOU FOR ATTENTION