GMD Experience

March 13, 1989 to Present

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

2FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

March 13, 1989

• Transformer - 500/138kV Auto

– Abnormal sounds observed.

– Removed from service due to

high combustible gas

readings.

– Paint discolored due to tank

heating.

– Analysis was subject of a

paper presented at IEEE PES

Summer meeting on

7/29/1989.

• Ten 138kV shunt capacitor

banks tripped.

• All are located in northern

Virginia or central Maryland

in or near areas of low Earth

conductivity.

Area of capacitor tripping

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

3FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Analysis of Transformer Currents – March 13, 1989

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

4FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Capacitor Bank Trips – March 13, 1989

• Ten 138kV grounded-

wye shunt capacitor

banks tripped.

– Unbalance protection

schemes operated due to

high harmonic current

flow in the bank neutrals.

– Thermal damage to

neutral current

transformers and

secondary circuitry.

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

5FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Mitigation Measures – Post 1989

Following the March, 1989 event, the following was done:

– DC neutral current monitoring was installed on all EHV

autotransformers in the Potomac Edison area and on selected

transformers in the other, non-igneous rock areas.

– Protection circuitry changes to allow system operators to enable

sudden pressure and gas accumulator tripping of the EHV

transformers.

– Capacitor protection control circuitry was modified to allow system

operators to disable the neutral unbalance protection.

– Filtered (60Hz) and normal unfiltered (RMS) current transducers

were added to provide real-time readings of capacitor neutral

fundamental and harmonic current.

– Operating procedures were put in place for the operators’ use during

periods of high GIC currents.

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

6FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Mitigation Measures – Post 1989

Locations with Transformer

Neutral GIC Monitoring

Locations with Capacitor

Neutral Current Monitoring

Area of capacitor tripping

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

7FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

GIC Observations - 1990

Relative GIC magnitudes recorded - 1990

Average response of all disturbances

1-22-1990 to 4-14-1990

1

23

4

1-T1 2-T1 2-T2 3-T1 4-T1 4-T2 4-T3 4-T4 4-T5

Area of Igneous Rock Geology

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

8FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Transformer Tripping due to gas accumulation 2001-2004Substation 1 now with three Autotransformers - Only one (different from 1989

event) trips due to gas accumulation during GIC activity.

11-5-2001 11-24-2001

10-30-2003 11-6-2004

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

9FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Recent GMD Activity - 4/23/2012Comparison of GIC recorded at 4 different locations

1 2

34

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

10FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Recent GMD Activity - 4/23/2012

Location 2 RMS Current

Location 1 RMS Current

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

11FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

FirstEnergy GMD Activities

• EPRI Participation

– Geomagnetic Disturbance Project

• Regular attendance on GMD monthly conference calls.

– Sunburst Project

• Installation of Sunburst nodes.

• Working to make non-Sunburst GIC monitoring data available.

• Regular attendance on Sunburst monthly conference calls.

• Attendance at annual meetings.

• NERC

– Attendance at NERC GMD workshop

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

12FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

FirstEnergy GMD Activities

• System Operations

– Operating Procedures

• Transformer neutral currents are continuously monitored through Scada and alarm at 10 amps DC.

• 138kV Grounded-Wye capacitor bank RMS and 60Hz neutral currents are monitored through Scada at select locations.

• FE works with PJM to Identify that a GMD event is in progress :

– Change the system configuration – reduce loading on susceptible transformers.

– Remove susceptible capacitor neutral unbalance protection from service.

– Enable EHV transformer sudden pressure and gas accumulator tripping.

– Place reactive sources into service.

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

13FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

FirstEnergy GMD Activities Monitoring Equipment

FirstEnergy GIC MonitoringSunburst GIC Monitoring

FirstEnergy and Sunburst GIC Monitoring

Capacitor Neutral Current Monitoring

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

14FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

FirstEnergy GMD Activities

• Engineering Activities

– Upgrade all older style capacitor neutral unbalance protection

to microprocessor over-current relays.

• Eliminates the need to remove unbalance protection during periods of

high harmonic currents.

– Investigate the use of substation microprocessor relays and

Digital Fault Recorders to monitor the Var consumption of

EHV transformers during periods of high GIC flow.

– Identify protection equipment that is subject to misoperation

as a result of GIC.

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

15FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

FirstEnergy GMD Activities

• Transmission Planning

– Create model to identify locations where high GIC

currents can be expected.

– Perform analysis using PSLF GIC add-on

• Identify maximum transformer reactive consumption due to GIC

– Perform loadflow and dynamics simulations to identify:

• Identify buses with voltages below Planning Criteria limits due to

increased transformer reactive loading associated with GIC and

misoperation of protective equipment (base case, N-1 and

common mode contingencies).

• Evaluate impact on reactive margins.

Presentation for FirstEnergy

System Operations May 2011 Transmission System Assessment: Summer 2011

16FirstEnergy Presentation

IEEE/PES Substation Committee

April 29, 2013

Geo-Magnetic Disturbances

Questions?