Riverbanks Zoo and Garden Phase II, Seals and Sea Lions

02.15-02.19

2016

RIVERBANKS ZOO AND GARDEN PHASE II, SEALS AND SEA LION EXHIBIT:

EXHIBIT POOL, VIEWING & HOLDING BUILDINGS

Perspective of the New SSL Exhibit from the Main Entrance Plaza

Perspective of the North End Of the SSL Exhibit

Perspective of the Exhibit from the Stadium Seating

Perspective of the West Entrance to the Viewing Building

Finishes Within the Viewing Building Completed

Final Architectural Inspection Complete Within the Viewing Building

Final Clean In Progress for the Interior of the Viewing Building

West End of the Upper Viewing Deck

South End of the Upper Viewing Deck

Entrance to the Keeper Platform at Upper Viewing

View of the Exhibit Pool from the Keeper Platform

View of the Holding Building from the Keeper Platform at Viewing

View of the Exhibit Pool Rockwork Entrance Stairs

Final Finishes Around the Exhibit Pool Underway

The Submerged Curing Process for the WetEdge Pool Bottom

Aluminum Ships Ladder Installed at the Shipping Container

Perspective of the Southwest Corner of the Viewing Building

New Hard and Softscape completed behind the Viewing Building

Perspective of the South Entrance to the Viewing Building

Softscape complete between the Holding and Viewing Buildings

Eastern Perspective of the Holding Building

Caging at the Holding Building Completed

Northeastern Perspective of the Holding Building

Architectural Punch of the Holding Building Complete

Final Clean Underway at the Holding Building

Architectural Punch of the Holding Building Complete

Hardscape Progressing Around the Holding Building

SSL Life Support Systems Completed

SSL Life Support Systems Completed

SSL Life Support Systems Completed

SSL Life Support Systems Completed

SSL Life Support Systems Completed

Riverbanks Zoo and Garden Phase III, Pedestrian Bridge

02.15-02.19

2016

RIVERBANKS ZOO AND GARDEN PHASE III, PEDESTRIAN BRIDGE PROJECT

Foundation Excavations Have Begun for the North Tower

Perspective of the New Front Entry from the North Tower Site

One Week Look Ahead The Architectural Punch Lists have been

created for the interior and exterior of both

the Holding and Viewing Buildings this

week. Final Clean is being performed on

both buildings as those items are being

worked off. The Hard and Softscape is

progressing around the site, working

towards the construction entrance behind

the LSS Building. The Commissioning for

the SSL Life Support Systems has begun

with Ted Maranda’s first visit to the site this

week.

Now that the clearing has been completed

and the erosion control measures placed,

the first footings for the Pedestrian Bridge

have been excavated on the North Elevator

Tower Side of the Rail Road tracks .