Work Plan Development

Steve RobinsonHighway Utility Engineer, INDOT

June 11, 2015

2

Outline Learning objectives –why work

plan? Top five reasons why a work plan is

important What are the recent updates?

Target date, signing first or second page, emergency contact, pre-construction & post construction activity, etc.

Work plan development (Process): preparation, review, revision & approval.

Practical exercise

Why is a work plan Important?1. Because it is the law!

he 105 IAC 13-3-3 (b) (1): A work plan shall be

submitted whether or not any facility relocations are required.

It is not a matter of opinion or an option, it is the LAW.

Utilities are obligated to submit their work plans to accommodate a highway improvement project.

Why is a work plan Important ?2. Because it focuses on deliverables:

Target out of conflict date.

Pre-construction schedule.

Construction schedule.

Relocation drawing.

Cost estimate

Proof of property interest.

Why is a work plan Important?3. Because it is a signed

commitment/contract

A work plan is a signed commitment by a utility to accurately relocate its facilities on schedule.

Projects are let based on information obtained from utility work plans.

A utility may be held accountable, for utility related delay claims.

Why is a work plan Important4. No Surprises during construction:

Work plan is a major tool to avoid surprises during construction.

The utility team shall demonstrate due diligence in reviewing & approving work plans.

Last chance before construction stage!

Why is a work plan Important?5: Because we use the work plan as an

input:

Utility risk management report.

Gantt chart.

Utility special provision.

Utility coordination certificate.

A tool for resolution of scheduling and location conflicts

Preamble 105 IAC-13-2-19: Work plan is defined as a

plan of the utility to carry out facility relocation to accommodate an improvement project.

Use preliminary final project plan (Stage 3/90%).

Prepare and send letter Request Work Plan.

Use the most recent work plan template. Go to the INDOT website.

When is a work plan due? Sixty (60) days for a minor project; and

One hundred twenty (120) days for a major project.

An additional thirty (30) days will be allowed to furnish the work plan if coordination is required with another utility or utilities.

If a work plan is not received on time: contact the authorized representative and notify the oversight agent.

11

Work plan revision Non compatible work plans shall be returned

to the utility immediately.

The utility shall submit a revised work plan within 30 days.

If the revised work plan is not compatible, the UC will prepare an alternate work plan.

The utility shall accept/make changes to the alternate plan within 30 days.

12

Section 1: General Information

13

General info……cont’d

14

General info……cont’d

15

Section 2: Location info.

16

Section 3 & 4 Property interest & Work in

contract

17

Section 5: Pre-construction

18

Section 6: Construction

19

Section 7, 8, & 9: Attachments

$500,000.00 (Not Reimbursable)

20

Work Plan Review Ensure each work plan is

compatible with: INDOT permit requirements The project plans The construction schedule Other utility relocation work plans

Ensure the relocation scheme and cost for compensable work is reasonable

21

Section 10 & 11: Approval

22

Work Plan Approval Letter Relocation permit to occupy public

right-of-way.

Notice to proceed with preconstruction activities.

In rare cases a notice to proceed with construction activities.

23

Work plan addendums: Addendums can either be INDOT initiated or

utility initiated.

A utility shall submit a revised work plan with a new cost estimate (if reimbursable).

The utility coordinator shall review the addendum; and send it to the approval of the oversight agent.

If an addendum is issued during construction, a copy shall be sent to the construction engineer.

24

Work Plan Addendum Letter What is the change of work.

What is the cost.

Who is paying for it.

What is the impact on construction schedule.

Revise exhibits to executed agreements, if reimbursable.

Letter AWP Addendum No payment for additional work

without prior approval.

Any change of work needs an approved work plan addendum.

26

Notice to Proceed Does the work of the utility depend on

the schedule(s) of other utilities?

Are all the parcels needed by the utility acquired, ROE obtained?

Is the right-of-way cleared from trees & other obstructions, staked?

Does the work of the utility depend on the INDOT contractor?

27Questions?