appendix 1: location & site plans - cape eaprac bardolino/bar/h... · 2016-05-09 · +27 (0) 44...
TRANSCRIPT
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 1: LOCATION & SITE
PLANS
Drawn ReferenceDateCheckedMelissa Mackay
SianHolder August 2015 MOS365
Map Index
Western CapeProvince
Eastern CapeProvince
North CapeProvince
Notes- Map Scale is 1 : 40 000 when printed on A3.- Aerial Image courtesy of Google Earth Pro 2015- Imagery date September 2013.- Cadastral data courtesy of Surveyor General 2015- Closest Metar wind station is located at the
Location PlanBardolino Lifestyle Village
Erf 3972, Dias StrandMossel Bay
± 0 500 1,000 1,500 2,000250Meters
Erf_3972
Legend
MosselbayMunicipality
Mossel Bay
Mossel BayHarbour
Dias Strand
N2To Albertinia
N2
N2
N2To George
Site co-ordinates:34°09'18.42"S22°06'21.88"E
PetroSA TankFarm
Pinnacle Point
Hartenbos
Drawn ReferenceDateCheckedMelissa Mackay
SianHolder August 2015 MOS365
Map Index
Western CapeProvince
Eastern CapeProvince
North CapeProvince
Notes- Map Scale is 1 : 20 000 when printed on A3.- 1:50k Topographical data courtesy of SurveyorGeneral
1:50 000 Topographical PlanBardolino Lifestyle Village
Erf 3972, Dias StrandMossel Bay
± 0 280 560 840 1,120140Meters
Erf_3972
Legend
MosselbayMunicipality
80
72
4.95General Residential 1 81 2,747.72
6.603,659.74801Frail Care
82 100.00TOTAL 55,474.11
3.061,695.4874-79
Private Open Space
%AREA (m²)ERF NO.ERVEN
PROPOSED ZONINGS
ZONING
21.1111,712.70821Transport Zone II
45.25Group Housing 73 1-73 25,101.68
80
00
85
00
90
00
95
00
10
00
0
10
50
0
11
00
0
11
50
0
12
00
0
15
00
0
15
50
0
16
00
0
16
50
0
16
50
0
17
00
0
8
00
0
11
00
0 11
50
0 12
00
0
12
50
0
13
00
0
13
50
0
14
00
0
14
50
0
15
00
0
15
50
0
12
50
0
13
00
0
13
50
0
14000
14500
16
00
0
17
00
0
81
82
17m
8m
11m
11m
11m
11m
8m
8m
8m
8m11
m
1
43
18
19
20
21
22
2324
25
26
27
28
29
3031
32
33
36
37
35 34
5
17
16
15
13
12
11
10
9
8
7
6
80
73
71
69
68
67
66
65
64
63
62
61
60
59
58
57
56
55
54 5150
495253 48
38 39 40
4142
47
464544
43
77
1:1500
DV
FEB 2016
759/MOS/15/TEK/SKF/SDP2_V7MV
DESIGNED:DESIGNED:
DATUM:DATE:
PLAN NR:PLAN NO:
GETEKEN:DRAWN:
This drawing is the copyright of DELplan Consulting.Do not scale from it but refer to figured dimen-
sions. All measurements must be checked and confirmedby a Professional Land Surveyor. Any discrepenciesshould please be reported to DELPlan immediately.
Die kopiereg van hierdie tekening behoort aan DELplanConsulting. Moenie daarvan afskaal nie,
maar verwys na afstande soos aangedui. Alle afmetingsmoet deur 'n Professionele Landmeter nagegaan en be-vestig word. Enige teenstrydighede moet asseblief dade-
lik aan DELplan rapporteer word.
COPYRIGHT: KOPIEREG:
Tel: 044 873 4566 • Email: [email protected]
AANHANGSEL
A3 Scale:
Voorgestelde ontwikkeling virPurperwinde Beleggings (Pty) Ltd
Erf 3972, Hartenbos
Terreinontwikkelingsplan
PROJECT:
DESCRIPTION:
TITLE:
PROJEK:
BESKRYWING:
TITEL:
NOTES: NOTAS:
76
2
14
78
TWEE KUILEN
ENTRANCE TO
INDUSTRIE ROAD 16,00m
4028
KARVEEL CRESCENT
4043
4042
4041
4034
40334032
4027
4026
4025
3987
3986
3985
3984
3983
3982
4216
3991
REMAINDER OF PORTION 1
3176
570
568
277
3025
2891
2896
4193
4122
4121 4120 4119 4118 41174116
411541144113411241114110
MAIN ROAD No 7 32,00m
137
136
135
134
132
4309
DIAZ DRIVE 16,00m
DIAZ DRIVE 30,00m
42184310
CL SEWER SERVITUDE 5,00m
4320
43184319
HARTENBOS TOWNSHIP
EXT. 12
3981
4125
4124/R
4215 4214 4213 4212 4211 4210 4209 4208 4207 4206
41954194
DIAZ DRIVE 16,00m
4031
4030
4029
4016
4006
3980
3979
3978
3977
3976
3975
39743973
HARTENBOSCH
79
STORMWATER
STORAGEAREA
DAM
133
265/R
3687
SWARTTOBIE
4124/R
4124/R
4792
4123
4963
4964
4965
4966
4967
4968
4969
4970
4971
4972
4973
4974
4975
4976
4310
74
75
8m
11m
11m
11m
11m
143/R
264
4035
4036
Protected Vegetation 19.0310,566.79
7
Protected vegetation as part of private open space system.covering 11,423.22m².
1
14
13
12
11
10
9
8
7
6
5
4
3
2
AMBULANS
WAG-AREA
tdtdwm
ONTVANGSteels
VERPLEEGSTERS
ONTVANGS
SITKAMER EN
WAGKAMER
teels
VRIESKAMER
KOELKAMER
EETSAALteels
VULLISWERF
granoliet
BINNEHOF
DROOGWERF
plaveisel
TEEKAMER
teels
MANS
teels
WERKERS DAMESteels
NOOD
KRAGOPWEKKER
KAMER
granoliet
WAS EN STRYKKAMER
teels
1:100 hel ling
DAMES
teels
WERKERS MANS
teels
MEDIESESTOOR
SKOONMAAKMIDDELS
granoliet
SPENS
LINNESTOOR
ramp op
ADMIN
KANTOOR
teels
BETUURDER
KANTOOR
teels
KONFERENSIEKAMER
teels
KANTOOR
yk
wm
AMBULANS
ROLSTOEL
PARKERING
ramp opramp op
GOEDERE OPLAAI
EN AFLAAI SONE
ramp op
SLOESH
STOOR
ramp op ramp op
MANSSAAL
DAMESSAALSIEKEBOEG / ONDERSOEKKAMER
KAMER 1KAMER 2KAMER 3
KAMER 4KAMER 5KAMER 6KAMER 7KAMER 8KAMER 9KAMER 10
KAMER 11 KAMER 12 KAMER 13 KAMER 14 KAMER 15 KAMER 16 KAMER 17
KOMBUIS
teels
gasstowe
voorbereiding oppervlaktes
voorbereiding oppervlaktes
bedienluik
LINNE DROOGWERF
NOOD WATERTENKS
VULLISWERF
granoliet
SEKURITEIT
teels
1
2
3
4
5
6
7
8
9
10
ramp op
ramp op
ROLSTOEL
PARKERING
TEEKOMBUIS
VULLIS IN
VULLIS UIT
ONDERDAK STOEPteels
ONDERDAK STOEP
teels
ONDERDAK STOEP
teels
ONDERDAK INGANG
teels
MOTORHUIS EN
WERKSWINKEL
granoliet
ramp op
gassilinders
UIT
IN
ROLSTOEL TOILET
TOEKOMS
TIGE UITB
REIDING
MEDIESE AFVAL
GROENTEWAS
teels
35
34 33 32 31 30 29 28 27 26 25 24 23 22 21
20
19
18
17
16
15
14
13
12
11
TWEE KUILEN
BOULEVARDPLACE
DIAZ INDUSTRIA
DIAZSTRAND
1234567
8 9 10 11 12 13 14 15
21222324252627
28 29 30 31 32 33 3435
3637
3839
4041424344
45 46 47 49
5051
5253
5455
56
57
6364
65
6667
68
69
70
71
72
7374
75
7677
78
79
80
8182
83
84
85
8687
88
89
90
91
92
9495
9697
98
99
DAM
FRAILCARE DEVELOPMENT
[Erf 1490m²]
Maximum Coverage 37.5%
therefor 560m² with bulk
of 0.75 therefor building of
1,120m²
OPEN SPACE
EN
TR
AN
CE
BEACH BOULEVARD EAST
EN
TR
AN
CE
TO
TW
EE
KU
ILE
N
N
16000
16000
16
00
0
16
00
0
16000
16000
16000
16
00
0
7524m²
OPEN SPACE488m²
OPEN SPACE
229m²
ROAD
SURFACE =
8,062m²
TOTAL ERF AREA:
55 478m²
16 17
18
19
20
93
5960
61
62
48
58
OPEN SPACE
746m²
OPEN SPACE
615m²
OPEN SPACE
527m²
OPEN SPACE
470m²
OPEN SPACE
986m²
OPEN SPACE
198m²
OPEN SPACE
1511m²
OPEN SPACE
330m²
OPEN SPACE
313m²
OPEN SPACE
672m²
OPEN SPACE
413m²
ROAD
RESERVES
SURFACE =
2,488m²
PROTECTED VEGETATION
NEW ROAD SURFACES
NEW OPEN GREEN SPACES
NEW FRAILCARE DEVELOPMENT
INDIVIDUAL ERVEN
© COPYRIGHT RESERVED
S.A.C.A.P.REG. NOMMER
PrArch 20875
• WRITTEN NOTICE MUST BE OBTAINED FOR ANY AESTHETICAL AND STRUCTURAL
CHANGES FROM COETZEE ALBERTS ARCHITECTS (PTY) LTD AND THE APPOINTED
ENGINEER ON SITE. COPYRIGHT BELONGS TO COETZEE ALBERTS ARCHITECTS
(PTY) LTD. NO DEVIATION FROM THESE PLANS WILL BE PERMITTED.
• THE DESIGN OF THIS DRAWING REMAINS THE PROPERTY OF COETZEE ALBERTS
ARCHITECTS (PTY) LTD.
• LEVELS AND DIMENSIONS TO BE USED ONLY. ANY DISCREPANCIES ARE TO BE
REPORTED TO ARCHITECT AND BE RESOLVED BEFORE BUILDING WORK
COMMENCES.
• WRITTEN DIMENSIONS TO BE USED ONLY. NO DIMENSIONS MAY BE SCALED.
• ALL WORK TO COMPLY TO SANS 10400 AND SANS 204.
• VERTICAL D.P.C. TO BE FIXED AT CHANGES IN ALL LEVELS.
• INSPECTION EYES TO ALL DRAINAGE AND SEWAGE PIPE WORK TO BE
ACCESSABLE AND TO BE SUITABLY MARKED AT GROUND LEVEL.
• ALL PIPE WORK TO CONFORM TO SANS 10400 AND SANS 204 AS WELL AS
SPECIFICATIONS.
• VENTELATION TO COFORM TO SPECIFICATIONS OF THE NBR.
• THE FALL OF THE SITE IS ACCORDING TO THE SURVEYER.
• DETERMINE FINAL POSITION OF MUNICIPALITY SEWAGE CONNECTION ON SITE.
• DETERMINE POSITION OF EXISTING SEWERLINE, BEFORE BUILDING.
• CONCRETE LINTELS OVER EVERY WINDOW, DOOR AND OPENING.
• FLOORPLAN SECTION 1,8m FROM UNFINISHED FLOOR LEVEL.
PROJECT
DRAWING
SCALE DATE DRAWN DESIGNED
DRAWING NR.
7704
+27 (0) 44 690 4437
e-mail: [email protected]
IT IS THE EXPRESSED CONDITION OF THE AGREEMENT THAT ALL
WORKS:TO BE STRICTLY IN ACCORDANCE WITH THE N.B.R. SANS
10400 MINIMUM STANDARDS.
THE DESIGN OF THIS DRAWING IS COPYRIGHT AND REMAINS THE
PROPERTY OF CoetzeeAlberts Architects
ALL DIMENTSIONS AND SETTING OUT DIMENSIONS TO BE CHECKED
ON SITE AND ANY DISCREPENCIES TO BE REPORTED TO THE
ARCHITECTS BEFORE COMMENCEMENT OF ANY CONSTRUCTION OR
MANUFACTURING ON OR OFF SITE.
THIS DRAWING MAY NOT BE SCALED. ONLY FIGURED DIMENSIONS
MAY BE USED.
www.coetzeealberts.co.za
NOTES:
ARCHITECT SIGNATURE CLIENT SIGNATURE
&
1 : 750
F:\
01
- P
roje
cts\
14
-34
[D
iaz
de
ve
lop
me
nt]
\02
- D
raw
ing
s\S
DP
[1
4-3
4,
Dia
z B
ea
ch]
Re
v 2
.rv
t
LIFESTYLE DEVELOPMENT ON ERF 3972, DIAZ
BEACH, MOSSEL BAY
SDP
T.ALBERTS
14-34-14-C001 Rev 2
2014/10/16 CAA
ZONING TABLE
ERF 3972 - DIAZ BEACH, MOSSEL BAY
Required by Scheme Regulation Project Provides
Building Lines
Street - 4.5m
Sides - 4.5m
Back - 4.5m
Building Lines
Coverage
37.5%
Erf 3972 - 55, 478m²
Therefor maximum: 20,804.25m²
Maximum Floor Factor [bulk]
Coverage
Street - 4.5m
Sides - 4.5m
Back - 4.5m
Height Height
3 Storeys 2 Storeys
Maximum Floor Factor [bulk]
Parking Parking
1 gross parking bay per 60m² of the total
floor area if an office function is included; 2
gross parking bays per 3 beds in the case of a
hospital; or a pro-rata combination.
Erf 3972- 0.75
Therefor maximum area: 41,608.5m²
Density
Maximum of 30 units per Hectar
Erf 3972 - 5,5478m² or 5,5478 Ha
Therefor 166 units maximum
Density
Single Residential: 99 - Units
1 2 3 4 5 6 7 8 9 10
11
121314151617181920
21 22 23 24 25 26 27 28 29 30
303132333435363738
39 40 41 42 43 44 45 46 47
48495051525354
5556
5758
5960
6162
63 6465
6667
6869
707172
7374
75
7677
7879
80
8182
8384
85
86
87
8889
90
91
92
93
94
95
9697
9899
100
101
102
103
104
105
106
107
108
109110
111
112
DAM
FUTURE DEVELOPMENT
OPEN SPACE
OPEN SPACE
OP
EN
SP
AC
E
OP
EN
SP
AC
E
EN
TR
AN
CE
BEACH BOULEVARD EAST
EN
TR
AN
CE
TO
TW
EE
KU
ILE
N
N
18
50
01
00
00
16
00
01
60
00
10
00
0
16000
16000
16000
16
00
0
16
00
0
16000
16000
16000 16000
16
00
01
60
00
16000
16000
16
00
0
1600016000
15854
© COPYRIGHT RESERVED
S.A.C.A.P.
REG. NOMMER
PrArch 20875
• WRITTEN NOTICE MUST BE OBTAINED FOR ANY AESTHETICAL AND STRUCTURAL
CHANGES FROM COETZEE ALBERTS ARCHITECTS (PTY) LTD AND THE APPOINTED
ENGINEER ON SITE. COPYRIGHT BELONGS TO COETZEE ALBERTS ARCHITECTS
(PTY) LTD. NO DEVIATION FROM THESE PLANS WILL BE PERMITTED.
• THE DESIGN OF THIS DRAWING REMAINS THE PROPERTY OF COETZEE ALBERTS
ARCHITECTS (PTY) LTD.
• LEVELS AND DIMENSIONS TO BE USED ONLY. ANY DISCREPANCIES ARE TO BE
REPORTED TO ARCHITECT AND BE RESOLVED BEFORE BUILDING WORK
COMMENCES.
• WRITTEN DIMENSIONS TO BE USED ONLY. NO DIMENSIONS MAY BE SCALED.
• ALL WORK TO COMPLY TO SANS 10400 AND SANS 204.
• VERTICAL D.P.C. TO BE FIXED AT CHANGES IN ALL LEVELS.
• INSPECTION EYES TO ALL DRAINAGE AND SEWAGE PIPE WORK TO BE
ACCESSABLE AND TO BE SUITABLY MARKED AT GROUND LEVEL.
• ALL PIPE WORK TO CONFORM TO SANS 10400 AND SANS 204 AS WELL AS
SPECIFICATIONS.
• VENTELATION TO COFORM TO SPECIFICATIONS OF THE NBR.
• THE FALL OF THE SITE IS ACCORDING TO THE SURVEYER.
• DETERMINE FINAL POSITION OF MUNICIPALITY SEWAGE CONNECTION ON SITE.
• DETERMINE POSITION OF EXISTING SEWERLINE, BEFORE BUILDING.
• CONCRETE LINTELS OVER EVERY WINDOW, DOOR AND OPENING.
• FLOORPLAN SECTION 1,8m FROM UNFINISHED FLOOR LEVEL.
PROJECT
DRAWING
SCALE DATE DRAWN DESIGNED
DRAWING NR.
7704
+27 (0) 44 690 4437
e-mail: [email protected]
IT IS THE EXPRESSED CONDITION OF THE AGREEMENT THAT ALL
WORKS:TO BE STRICTLY IN ACCORDANCE WITH THE N.B.R. SANS
10400 MINIMUM STANDARDS.
THE DESIGN OF THIS DRAWING IS COPYRIGHT AND REMAINS THE
PROPERTY OF CoetzeeAlberts Architects
ALL DIMENTSIONS AND SETTING OUT DIMENSIONS TO BE CHECKED
ON SITE AND ANY DISCREPENCIES TO BE REPORTED TO THE
ARCHITECTS BEFORE COMMENCEMENT OF ANY CONSTRUCTION OR
MANUFACTURING ON OR OFF SITE.
THIS DRAWING MAY NOT BE SCALED. ONLY FIGURED DIMENSIONS
MAY BE USED.
www.coetzeealberts.co.za
NOTES:
ARCHITECT SIGNATURE CLIENT SIGNATURE
&
1 : 750
Y:\
01
- P
roje
cts\
14
-34
[D
iaz
dev
elo
pme
nt]
\02
- D
raw
ings
\SD
P-A
lte
rna
tie
f.rv
t
lifestyle development diaz beach
SDP
CAA
14-34-14-C001
09/29/14 CAA
1 : 750
01 - SITE PLAN1
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 2: ARCHITECTURAL
GUIDELINES
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
1
Architectural Guideline for the proposed new Lifestyle Development known as
Bardolino
Stand 3972 Hartenbos (Diaz Beach)
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
2
INDEX
1. Background.................................................................................3 2. Definitions and Regulatory framework …....................................4 3. Review and Design scrutinizing process.....................................5-6
a. The Process is as follows: b. Building plan requirements:Background
4. Building Parameters.....................................................................7 a. Building lines b. Coverage c. Height d. Building Widths e. Parking
5. Architecture and Building elements.............................................8-11 a. Main Building Elements
i. Walls ii. Windows iii. Doors iv. Roof v. Balustrades & Balconies vi. Columns vii. Heat pumps & Air-conditioning units
b. Main Landscaping Elements i. Boundary walls, Fences & Screens ii. Retaining walls iii. External Decks iv. Hard surfaces v. Swimming pools & Water features vi. Planting
c. Generators 6. Landscaping................................................................................12
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
3
1. Background The development is located in the heart of a predominant holiday area of Mossel Bay, known as Diaz Beach. While it is located in the centre of this popular area the site is well isolated form the surrounding area because of lush natural vegetation. The development sits on a high point sloping East toward the sea. With the property being a development earmarked for a Lifestyle estate for retired people is sets out to create and enhance this sense of seclusion and safety. The developer has the aim to create the sense of place which is seen at the Italian area of Bernardino, but within the local context of Mossel Bay, South Africa. Key characteristics which are taken from the area of Bardolino and seen as inspiration for this development are:
Relaxed atmosphere Temperate Climate Natural Surrounding
The sense of place speaks of a site which overlooks toward the sea in the East and protected from the urban landscape to the West. The development aims to enhance the views, Northern sun and be known for large private open spaces, Because of the protected Milkwood trees large areas are dedicated to the enhancement and flourishing of the biome, also referred to as a green corridor. Therefore the erven are kept to the minimum as the intention is to create spaces for people to engage and grow as a community, rather than being isolated into each individual erven. To ensure this the buildings are staggered as much as possible within the variety of each type of unit, but creating and maintaining a suitable street definition. No street boundary walls are permitted and minimal inter unit/erf boundaries to enhance the sense of private open spaces. Only minimal erf fences are proposed as to allow for enclosure of pets. Landscaping of units are to be done only with local indigenous plants found in the close proximity to the development and local biomes. This will further encourage natural bird and wildlife. This document sets out to ensure the aesthetic and design quality of the new buildings to be erected in the development. It can however be updated at any time as deemed suitable by the HOA. Only the latest document will be valid and all previous versions will be disregarded.
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
4
2. Definitions and Regulatory framework This document sets out the design framework and aesthetic as well as characteristics to be adhered to ensure that the developers intended vision and sense of place is achieved. These guidelines in no way aim to supersede of overrule any statutory of regulatory frameworks. All relevant legislation and legal parameters such as the following will be relevant.
National Building Regulations SANS 10400 Municipal By-law and Zoning parameters Compliance with the Architecture Act No 44of 2001
'HOME OWNERS ASSOCIATION' (HOA) means Bardolino Lifestyle Estate Home Owners Association 'OWNER' Owner means the registered owner of erven in the development. 'AGENT' The agent means an architectural company appointed by the developer of Bardolino Lifestyle Estate or his successor in title, who shall act as adjudicator to approve proposed building work in terms of the aesthetic requirements and this design manual. The appointed adjudication architectural design company is: Practice: Pro-Plan Drawing Office in conjunction with Hidegard Swanepoel Address: Pro-Plan Drawing Office, Montague Place, 106 Montague Street, Mossel Bay, 6500 Phone: 044 691 1820 e-mail: [email protected] 'COUNCIL' Council means the local authority of Mossel Bay. (Mossel Bay Municipality) 'MANAGING AGENT' A representative person/company of legal entity acting as an administrative agent of the HOA for the management of the development. BUILDING WORK' Any construction work to be carried out, whether it is a new building or any alterations & additions, including any aesthetic changes made to any structure within the development 'DWELLING UNIT' The primary structure to be erected on each erf. 'COVERAGE' Coverage means the total percentage area of the site that is covered by buildings measured over the outside walls and covered by a roof. An eave overhang or other projection of maximum 1m wide shall be excluded in the calculation of the permissible coverage.. 'NATURAL GROUND LEVEL' Natural ground level means the level of the ground before any work has taken place. Levels determined by the surveyor after completion of the civil works by the developer shall be deemed to be the correct and final levels for the determination of the height restriction. 'BUILDING LINE' Building line means the line delimiting the area measured from the boundary of a land unit within which no building or other structure may be erected. 'STREET BOUNDARY' Street boundary means the boundary of a site or a land unit, which is also its boundary with a street. 'SIDE BOUNDARY' Side boundary means any other boundary other than street boundary or rear boundary. 'REAR BOUNDARY' Rear boundary means the boundary line opposite the street boundary.
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
5
3. REVIEW AND DESIGN SCRUTINIZING PROCESS Any design of any building work to take place within the development has to be submitted to the HOA. No additions will be allowed to any building without the consent of the HOA and the Local Authority. No double storey buildings will be allowed. The author of the plans is to be in line with the Architectural Professions Act No 44 of 2001 with the Framework of Works requirements. Only registered persons with SACAP may submit building plans.
a. The Process is as follow: i. Scrutinizing Fee paid in full to the HOA. ii. The initial Sketch Plans of proposed building work are to be submitted to the HOA or the
Managing Agent as appointed by the HOA. iii. Plans will be reviewed by the Agent and feedback given back via the HOA or Managing Agent. iv. Municipal Documentation can be drafted and again submitted to the HOA or Managing Agent
based on the approved Sketch Plans or any comments / conditions contained therein. v. Plans will be reviewed by the Agent and recommendations made to the HOA or Managing Agent
which will give final feedback. vi. During the construction process the Agent will conduct inspection at key points. vii. All Building Work shall be carried out according to the CONTRACTOR'S CODE OF CONDUCT. viii. Once the Building Work has been completed and all inspection has been completed a FINAL
APPROVAL will be issued and Building Deposit less any damage or costs will be repaid. No approval shall imply approval in terms of National Building Regulations or Local Authority and will remain the responsibility of the author.
b. Building Plan Requirements: All drawings shall be compiled as per local authority and national building regulations requirements with the following additional information to enable suitable illustration of the design intent, textures, finishes and relevant clarity
i. Site Plan: ● Indicate Surrounding Green areas and landscaping, including abutting HOA property
information ● Building lines ● Storm water management ● Sewerage ● Building Widths ● Paving & Hard Landscaping elements
ii. Floor Plans:
● Paving & Hard Landscaping elements ● All Sewerage & concealment thereof ● Yard Walls ● Boundary Walls, Fences & Screens
iii. Elevations: ● Building Lines ● Height Restriction ● All Sewerage & concealment thereof ● Differing textures with suitable hatching and legend ● Paint Colours ● Roof Pitch ● Gutter Downpipes ● Detailed Finishing Specifications
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
6
● Yard Walls ● Boundary Walls, Fences & Screens
iv. Sections: ● Building Lines ● Height Restriction ● All Sewerage & concealment thereof ● Roof Pitch ● Yard Walls ● Boundary Walls, Fences & Screens
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
7
4. BUILDING PARAMETERS
a. Building lines Building lines as applied by Mossel Bay Municipality Zoning Scheme shall apply with further restriction as follow for single residential erven only:
i. Street: 2m ii. Sides: 1.5m iii. Back: 1.5m
b. Coverage
Single Residential Unit: Maximum coverage of an erf: 60% General Residential units: Maximum coverage on erf: 60% Other Zones: 50%
c. Height All zones: Only Single Storey buildings are permitted
d. Building Widths All Residential buildings in the development are to be kept to a maximum wall plate to wall plate width of 6.5m to ensure suitably fragmented expression in elevation as well as plan.
e. Parking Parking are to be provided as required in terms of the Mossel Bay Zoning Scheme and the requirements as set out in the ROD as issued by Mossel Bay Municipality.
TYPICLE SITE PLAN
outomatiese segment opskuifdeur
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
8
5. Architecture and Building Elements
a. Main Building Elements i. Walls
All building walls are to be constructed using masonry construction and no timber frame, concrete walling, steel frame or any alternative method of building construction will be permitted. External walls must be finished with plaster & paint. Large expanses of only plaster are not permitted. Plaster may only be smooth plaster. No other plasters such as Spanish plaster are allowed.
● Painting Colours All paintwork is to be pre-approved colours by developer. The colours are to be of a Natural Earth Colour that blend with the immediate surrounding context within which the development is situated. The purpose is that buildings should integrate in the landscape with the colours and not stand out. No bright colours will be allowed. Illustration of Typical Colours intended [For illustration purposes only]:
● Cladding
Cladding to create different textures on elevation is encouraged.
ii. Windows
Window proportions are to be preferably vertical. If windows with a horizontal proportion are proposed, the dividing mullions should create vertical glass panes. Only Charcoal epoxy aluminium windows are permitted. Preferred window proportions::
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
9
iii. Doors All doors to be vertically proportioned (except garage door) and in Charcoal epoxy aluminium. Garage to have an automatic open/closer. Preferred door proportions:
iv. Roof
Roof Design A roof must be scaled down to create a smaller scale building. The roof must have a pitch of 30 degrees minimum. Only pitched roofs are permitted and flat concrete sections may be used to link roof elements, but must then have a parapet surrounding and be restricted to a maximum of 15% of the total roofed area in plan. Any elements fitted or installed on a roof are to form an integral part of the roof design and must be the same pitch and matching colour.
Roof Covering Roofing material must be uniform for each unit. Only Concrete Tiles are allowed. Roofing material and colour are to be non-reflective.
Roof Overhang A minimum roof overhang of 600mm and a maximum of 1m are required. No clipped eaves are allowed.
Gutters, Downpipes & Fascias Gutters and downpipes are to be the same colour and match the colour of the roof. Material has to be seamless aluminium throughout. The fascias should be painted to match the roof colour and can only be a fibre cement profile.
Shading devices & Pergolas All shading devices must be clearly indicated on the drawings with sufficient detail and specification to be able to understand the construction thereof. Only shading devices of a suitable hardwood material will be permitted and with pre-approval an aluminium construction.
Chimneys & Cowls Chimneys to be well proportioned and be suitably scaled to the building design. It must be brick built and cladded with approved cladding and provided with a fixed turbo cowl as per diagram below.
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
10
Solar water collectors, Photovoltaic Panels
Any panels fitted to the roof are to be placed flat on the roof surface and no projection at a higher slope than the roof slope is allowed. Panels should be grouped together and cannot be scattered over the roof as individual elements. Only the solar collector or panel may be placed on the exterior of the roof. Any water storage unit, inverter,
power supply etc. has to be concealed in the roof space. Typical Solar collector & Geyser Alignment Typical Photovoltaic Panel Alignment
v. Balustrades & Balconies Balustrades must conform to the nature of the development and may only be Stainless Steel, Painted or pre-approved polycrete, painted to the approved colour scheme. No glass or aluminium handrails will be permitted. Handrail elements must be vertically proportioned.
POLYCRETE HANDRAIL STAINLESS STEEL HANDRAIL
vi. Columns Columns are to be of smooth plastered and painted or cladded with approved cladding. No fluted wooden columns will be permitted.
vii. Heat Pumps & Air-conditioning units Any heat pump or air-conditioning unit has to be screened off and may not be visible on any elevation.
b. Main Landscaping Elements i. Boundary Walls, Fences & Screens
No Boundary walls will be permitted for any internal erven. A perimeter wall/fence and suitable security barrier are provided around the main property. Any intermittent fences to keep pets inside a particular erf might be approved by the HOA on special request. These will be of a light weight design and be restricted to a maximum height of 1m from the natural ground line. The colour of this fence shall be of a green colour such to blend into the landscape. A yard wall of a set height of 1.8m shall be erected around the Yard on the side of the Kitchen. This wall is to be constructed of a solid masonry construction, plastered and painted both sides to match the house colours. The wall is intended as a screening wall for refuse bins, laundry, gas storage etc. and may not exceed 10m2
in plan size.
ii. Retaining Walls Any retaining wall may only have a visible section of maximum 1.2m. The landscape and surrounding area should be suitably shaped and retaining walls stepped or terraced to restrict vast expanses of wall. Use of brown retaining blocks for these structures is encouraged. Natural vegetation should also be used to limit
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
11
the harshness of any such required structure.
iii. External Decks Wooden decks are allowed in Belau or Grappa or suitable hardwood that requires no maintenance. Treated Pine may be used as sub structure but may not be visible. All sides to be closed to the ground, no structure may be visible.
iv. Hard surfaces All hard surfaces are to be cobble pavers of a grey colour.
v. Swimming Pools & Water features All swimming pools and water features are to conform to NBR or any Municipal By-Law. Any structure for such an element has to be within the building lines of the property.
vi. Planting All planting are to be as set out in the Landscaping Guideline.
vii. Generators Any generator has to be installed in such a place as not to be visible from any other property. The unit should also be suitably muffled as not to cause any disturbance to neighbours.
viii. Rainwater tanks Rainwater tanks are to be placed so that it is not visable from the street and downpipes from the roofs are to be lead to tanks against the walls. All tanks must be shown on plans and elevations. Typical Rainwater Tank and colour
----------------------------------------------------------------------------------------------------------------------------- ------------------- THESE GUIDELINES CAN BE CHANGED BY THE HOA TO KEEP IN TOUCH WITH NEW PRODUCTS AND REGULATIONS. ALL CHANGES MUST BE APPROVED AT AN ANNUAL GENERAL MEETING. ------------------------------------------------------------------------------------------------------------------------ ------------------------
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
12
6. LANDSCAPING
The natural environment of BARDOLINO is a variety of coastal thicket and fynbos which supports a diverse ecosystem, the most impressive of which is the bird life. The aim of the development is to re-establish the environment that has been damaged by the introduction of alien vegetation and general misuse. Despite the current state of the development and the long term vision of sharing in the benefits of a nature conservancy of such rich potential deserves to be treated with great respect. In order to realise this aim, the Home Owners' Association has taken the decision to institute certain protective measures that must be adhered to. One of the primary issues is that no plot should be cleared of all vegetation prior to the building, in order to prevent the loss of the small amounts of coastal thicket still left on the site of the development. Wherever possible, the natural coastal thicket should be protected and must be left on site within a two meter radius of the physical building on each property. The vision of the development is to blend into the natural environment to be able to coexist harmoniously with the milkwood and coastal thicket, once building is completed. Each garden will naturally develop it's own unique character comprising of both plants indigenous to the area as well as the greater coastal region. No Sideroxylone Inerme (Milkwood trees) may be removed, pruned or damaged in any way without permission from the Nature Conservation Department. No existing plants on erven may be removed prior to consultation with the Home Owners' Association. Plants on communal garden areas and road verges may not be removed or added to in any way. After building and the restricted paving, the only grass permitted for use as lawn is Cynodon dactylon, (kweekgras). All declared invasive plant species must be removed from erven and may not be cultivated. Only plant indigenous to South Africa may be cultivated. (See attached planting list for recommendations suitable for the area). Only natural pesticides and fertilizers may be used. Where terraforce is required, it must be planted to ensure that it fits in with the environment. The value of this rural treatment of restricted planting will be seen in both the future value of the property as well as the physical health and vitality of the natural environment and it's ecosystem. It allows for great variety and creativity within a structure that protects the natural habitat; a garden that is 'organic', able to flourish in the weather conditions and encourage an even wider variety of wildlife. SITE WORKS Site Enclosure / Tempoprary Fencing The boundries of each building site are to be identified by a Professional Land Surveyor. Each dwelling construction space, is to be enclosed by a shade cloth (shade net) 1.8m high to clearly define the area to be disturbed, and to avoid encroachment on neigbouring erven or damaging the surrounding planting. The fence must be maintained for the duration of the construction period. The fence must be removed immediately after construction has been completed. Topsoil Protection and Sand Stabilization Topsoil and organic material should be removed from the building platform area and carefully stored for re-use in landscape work. Al private outdoor areas immediately around the dwelling are to be properly stabilized with paving, gravel, grass or ground cover plants to prevent wind blown sand. Fill Material
Architectural Guidelines for Bardolino Lifestyle Development, Mossel Bay
13
Cutting and filling to the dwelling is to be so designed to minimize the necessity for imported fill. Material should imported from outside the area where required. No excavation of or to the common areas is permitted.
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 3: STORMWATER LAYOUT
Raadgewende Siviele en Strukturele Ingenieurs Consulting Civil and Structural Engineers
Verw: M2012 (10049000)/L1930 Ref: Meadestraat 73 Meade Street, George Posbus / PO Box 1889, George, 6530 Aandag: Mnr. Pieter Myburgh Tel: (044) 874 6517 Attention: Fax: (044) 873 3263 e-mail: [email protected] web: www.mvdsuidkaap.co.za B-BBEE: Level 3
Siviel en Struktureel / Civil and Structural Kantore te / Offices at: Direkteure / Directors: Mosselbaai Posbus / PO Box 730, Mossel Bay, 6500. Tel: (044) 691 2305/57 IM van Rooyen Pr Ing, BSc, B. Ing. Hons, LSAISI, LIMunISA, FWISA George Posbus / PO Box 1889, George, 6530. Tel: (044) 874 6517 DV Wessels Pr Ing, B. Ing, LSAISI Oudtshoorn Posbus / PO Box 1426, Oudtshoorn, 6620. Tel: 082 5791279 JA Steenkamp Pr Ing, B. SC, B, Ing, LSAISI CV Swart Pr Ing, B, Ing, LSAISI, LIMunISA
MVD Raadgewende Ingenieurs (Suid-Kaap) (Edms) Bpk.Reg. No. 2001/009891/07
04 September 2015 Die Munisipale Bestuurder Mosselbaai Munisipaliteit Posbus 25 MOSSELBAAI 6500 Beste Pieter VOORGESTELDE ONTWIKKELING VAN ERF 3972, HARTENBOS: HANTERING VAN DIE STORM WATER:
1. Ons verwys na die gesprek op Woensdag, 02 September 2015 te Mosselbaai, tussen ons Chris Swart en Danie Wessels en u en Carel Venter rakende bostaande. Ons lê graag die volgende aan u voor vir u oorweging en goedkeuring t.o.v. die hantering van die storm water vanaf die terrein.
2. Dreinerings Areas:
Soos op aangehegte tekening M2012/002A aangetoon word, kan die ontwikkelings area in drie dreinerings areas opgedeel word. Area A dreineer na die suidelike hoek, area B na die noordelike hoek en area C na die noordwestelike hoek. As gevolg van die groot aantal Melkhout bome op die terrein, mag daar op groot gedeeltes geen ontwikkeling plaasvind nie. Hierdie areas gaan as parke en oop areas behoue bly en is in groen aangetoon op die tekening.
3. Piek aflope: Die verwagte piek aflope tydens reën storms met ‘n herhalings periode van 1:10 jaar word op tussen 0.15m3/s tot 0.24m3/s beraam. Vir area A en B neem die afloop na verharding toe met ongeveer 0.06m3/s en 0.07m3/s onderskeidelik en vir area C neem dit af met ongeveer 0.03m3/s. Die aflope is dus oor die algemeen relatief laag en die toename in piekvloei ook baie laag (60 l/s tot 70 l/s) vir die twee areas waar daar wel ‘n toename is.
Page 2 of 3
4. Weg Syfering: Die gebied is grootliks sanderig van aard en daar word verwag dat die meeste water tydens reën storms net eenvoudig weg syfer. Vorige toetse gedoen in die omgewing om die dreinerings potensiaal van die insitu materiaal te bepaal het getoon dat die gemiddelde tyd vir 25mm water om weg te sak minder as 3 minute is. Gebaseer op SANS 0400-1990 se voorgestelde wegsakkings tempo’s tydens die ontwerp van sigdreinering, korrespondeer dit met ‘n potensiële tempo van wegsakking van 108 l/m²/dag.
5. Storm Water Stelsel vir tye met laer reënval (“Minor System”):
Dié stelsels moet reën storms met tipiese herhalingsperiodes van 1:2 tot 1:5 jaar kan hanteer. Daar word voorgestel dat die storm water vir hierdie gebeurtenisse op die oppervlakte hanteer word. Die dwars helling van die paaie sal saam met die kontoere val en geen randstene word voorsien nie. Dit sal tot gevolg hê dat die afloop water eenvoudig net van die paaie af loop en geleentheid kry om op die groen areas weg te sak. Area A:
Die area het geen uitlaat nie en alle water wat hier val sal aan die suide kant van die ontwikkeling op dam. Die totale area wat hierheen dreineer, buiten net die ontwikkeling op erf 3972 wat 27 000m² is, is ongeveer 200 000m². Hiervan is ongeveer 90 000m² oop sanderige areas. Teen die tempo van wegsakking soos in punt 4 genoem, behoort daar dus ongeveer 50mm se reën per dag te kan weg syfer. Dit stem ooreen met ‘n een dag reënval met ‘n herhalingsperiode in die omgewing van 1:2 tot 1:5 jaar vir hierdie deel van die land (verwys na aangehegte “Point Rainfall Estimation”). Die toename in piekvloei vir die 1:10 jaar reën storm word beraam op 60 l/s. Die opvanggebied is relatief klein en ‘n tyd van konsentrasie van 6 minute is gebruik tydens die berekening van die piek afloop. Dit bring mee dat daar ‘n toename van ongeveer 32m3 piek afloop is. Om dit te demp word voorgestel dat ‘n retensiedam in die suidelike hoek gebou word. ‘n Oop area is op die uitleg vir hierdie doel voorsien waar ‘n dam met ‘n volume van 120m3 gebou kan word.
Area B:
Die area dreineer na twee bestaande retensiedamme in die noordelike hoek. Die damme loop oor in ‘n 300 mm HDPE stormwater pyp wat deur Pampoendorp loop en in die vlei noord van Pampoendorp uitmond. Die totale area wat hierheen dreineer, buiten net die ontwikkeling op erf 3972 wat 13 000m² is, is ongeveer 45 000m². Hiervan is ongeveer 9 600m² oop sanderige areas. Teen die tempo van wegsakking soos in punt 4 genoem, en met ‘n kapasiteit van tussen 50-100 l/s vir die stormwaterpyp deur Pampoendorp (wat ‘n konserwatiewe beraming van die stormwater pyp se kapasiteit is) behoort daar dus ongeveer 120mm se reën per dag geakkommodeer kan word. Dit stem ooreen met ‘n een dag reënval met ‘n herhalingsperiode in die omgewing van 1:20 jaar vir hierdie deel van die land (verwys na aangehegte “Point Rainfall Estimation”). Die toename in piekvloei vir die 1:10 jaar reën storm word beraam op 70 l/s. Die opvanggebied is relatief klein en ‘n tyd van konsentrasie van 6 minute is gebruik tydens die berekening van die piek afloop. Dit bring mee dat daar ‘n toename van ongeveer 38m3 piek afloop is. Om dit te demp word voorgestel dat die volume van die bestaande retensiedam vergroot word met ten minste 40m3.
Page 3 of 3
Area C: Hierdie area dreineer in die rigting van die spoorlyn, vanwaar die stormwater langs die spoorlyn af dreineer na die vlei noord van die ontwikkeling. Met die vergroting van die oop groen areas, neem die verwagte piekvloei af na ontwikkeling en word geen probleme voorsien nie.
6. Storm Water Stelsel vir tye van hoe reënval (“Major System”):
Die hele area in die omgewing van die voorgestelde ontwikkeling het ‘n laagtepunt op ‘n hoogte van ongeveer 8.0m aan die ooste kant van erf 3972. Sou ‘n reënstorm voorkom met so ‘n hoë intensiteit dat die water nie weg syfer weens versadiging, of deur die stormwater pyp deur Pampoendorp weg gevoer kan word nie, sal die water opdam en later die natuurlike dreinerings roete deur Pampoendorp na die vlei volg. Die kontrole punt in Pampoendorp wat oorkom moet word alvorens water kan dreineer uit die area is op ‘n hoogte van 9.37m. Om te verseker geen oorstroming van huise in die ontwikkeling vind plaas nie, word aanbeveel dat geen huis se vloervlak laer as 9.5m gebou word nie.
7. Ons vertrou bostaande inligting is voldoende om u in staat te stel om die genoemde ontwikkeling te ondersteun in terme van die beheer van stormwater. Indien u enige addisionele inligting verlang voorsien ons dit met graagte.
Die uwe MVD RAADGEWENDE INGENIEURS (SUID-KAAP) (EDMS) BPK
CV SWART (Pr. Ing)
point rainfall
POINT DESIGN RAINFALL ESTIMATION(Determined with Design Rainfall Estimation Software recommended in the 6th Edition of the SA Roads Agency Drainage Manual)
User selection has the following criteria:Coordinates: Latitude: 34 degrees 9 minutes; Longitude: 22 degreess 6 minutesDurations requested: 1 dReturn Periods requested: 2 yr, 5 yr, 10 yr, 20 yr, 50 yr, 100 yrBlock Size requested: 1 minutes
Data extracted from Daily Rainfall Estimate Database FileThe six closest stations are listed
Station Name SAWS Distance Record Latitude Longitude MAP Altitude Duration Return Period (years) Number (km) (Years) (°) (') (°) (') (mm) (m) (m/h/d) 2 2L 2U 5 5L 5U 10 10L 10U 20 20L 20U 50 50L 50U 100 100L 100U MOSSELBAAI (MAG) 0012220_W 4.0 39 34 10 22 8 437 94 1 d 51.8 51.5 52.0 76.1 75.7 76.4 94.6 93.7 95.6 114.4 112.4 116.5 143.4 139.4 148.0 167.9 161.8 175.5CAPE ST BLAIZE (VRT) 0012251_W 6.5 98 34 11 22 9 380 30 1 d 32.1 31.9 32.2 47.1 46.9 47.3 58.6 58.1 59.2 70.9 69.6 72.2 88.8 86.3 91.7 104.0 100.2 108.7SANDHOOGTE (PUR) 0012303_W 14.1 72 34 3 22 11 576 76 1 d 46.8 46.6 47.0 68.7 68.4 69.0 85.5 84.7 86.3 103.4 101.6 105.3 129.6 125.9 133.7 151.7 146.2 158.6GREAT BRAK RIVER 0012393_W 16.6 86 34 3 22 13 473 110 1 d 51.5 51.3 51.7 75.7 75.3 76.0 94.1 93.3 95.1 113.8 111.8 115.9 142.7 138.7 147.3 167.1 160.9 174.7KWEPERTUIN 0028150_W 18.8 71 33 59 22 3 440 198 1 d 59.0 58.7 59.3 86.7 86.3 87.1 107.8 106.8 108.9 130.4 128.1 132.8 163.4 158.9 168.7 191.4 184.4 200.1PINE GROVE (BOS) 0028207_W 23.4 40 33 56 22 6 718 287 1 d 63.9 63.0 64.6 94.4 93.5 95.2 118.5 116.8 120.5 145.0 140.9 149.4 185.2 176.0 195.3 220.3 204.9 237.2 Gridded values of all points within the specified block Latitude Longitude MAP Altitude Duration Return Period (years) (°) (') (°) (') (mm) (m) (m/h/d) 2 2L 2U 5 5L 5U 10 10L 10U 20 20L 20U 50 50L 50U 100 100L 100U
34 9 22 6 440 15 1 d 45.3 32.5 58.3 66.6 47.7 85.7 82.9 59.0 107.2 100.2 70.8 130.7 125.6 87.8 166.1 147.1 101.9 197.0 34 10 22 6 416 82 1 d 44.1 31.1 57.2 64.8 45.7 84.0 80.6 56.6 105.1 97.4 67.9 128.1 122.1 84.2 162.8 143.0 97.7 193.0 34 10 22 5 457 122 1 d 47.4 34.2 60.7 69.6 50.3 89.2 86.6 62.2 111.5 104.7 74.6 136.0 131.3 92.5 172.8 153.7 107.4 204.9 34 8 22 6 500 69 1 d 49.0 36.1 62.0 72.0 53.0 91.1 89.5 65.6 113.9 108.3 78.7 138.9 135.7 97.6 176.5 158.9 113.3 209.3 34 9 22 5 487 128 1 d 49.3 36.1 62.6 72.4 53.0 92.1 90.1 65.6 115.1 108.9 78.7 140.3 136.5 97.6 178.3 159.9 113.2 211.5 34 8 22 5 509 110 1 d 50.7 37.5 64.0 74.5 55.1 94.1 92.7 68.2 117.6 112.0 81.8 143.4 140.4 101.4 182.2 164.5 117.7 216.1
Page 1
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
Figure 1: Silt Fences
Figure 2: Temporary Stormwater Management
Figure 3: Management of Haul Roads
Figure 4: Demarcation Methods
APPENDIX 4: SITE MANAGEMENT
REQUIREMENTS
Cape EAPrac
General Silt Fence Specifications Environmental Management Programme
Cape Environmental Assessment
Practitioners (Pty) LtdFigure 1: Specifications for Silt Fences
Cross-section View
Natural / Undisturbed Vegetation.
Direction ofrunoff / flow
60
0m
m
20
0m
m
Mulch filled onion bag
Silt fence fabric
30
0m
m
Wooden ormetal stake
Galvanised wire tie-on’s
300mm
Fabric anchoragetrench to be backfilled andcompacted
The purpose of a silt fence is to create a temporary barrier to maintain sediment on a construction site in order to prevent soil erosion and pollution through sediment and nutrient loading. Silt fences are designed to detain sediment from the disturbed construction area and also prevent sheet erosion by decreasing the velocity of the run off.
?Silt fence fabric to consist out of 50% shade cloth or a geotextile such as biddim (if biddum is used, it is not necessary to place mulch bags).
?Wooden droppers are suitable for the stakes. If the construction program takes place over an extended time frame it may be necessary to use treated droppers or metal stakes.
?The support stakes should not be placed further than 700mm apart on the down slope side of the fabric.
?The fabric should be secured to the stakes using galvanised wire ties not further than 200mm apart.
?The fabric anchorage trench should be at least 300mm deep.
Technical Specifications
Planning, Placing and Maintenance?The silt fence is to be installed on all disturbed slopes where sheet erosion may take place.?This type of silt fence is not suitable for areas where water is concentrated. i.e. gulleys and storm-water outlets.?The silt fences should be along the contour lines?The rows of silt fences should be bowed to prevent erosion and loss of silt on the ends of the fence line.?Silt fences should be inspected weekly and before every forecast rainfall event. Any damage must be repaired
immediately.?Silt deposits should be cleared after each rainfall event. CLEARED SILT MUST NOT BE PLACED DOWN SLOPE
OF THE FENCE.
700mm
600m
m
Direction ofwater flow
Mulch bags tooverlap so that no gaps arepresent wheresilt can pass
Frontal View
Top of slope
Top View
Bottom of slope
Last 2m of each section of silt fence to turn uphillto avoid overflow of ponded sediment
Silt fence to be placed 1.5 - 2m awayfrom bottom (toe) of slope
A straw bale should be pegged at theend of each section of silt fence as anemergency overflow
If the height of the slope is more than 5m, additional silt fences will need to be placed on the actual slope.
Cape EAPrac
Temporary Stormwater Management - Specifications Construction EMP
Cape Environmental Assessment
Practitioners (Pty) Ltd
Figure 2: Specifications for Temporary StormwaterManagement During Construction
Inlet Protection
Drop Inlets Kerb Inlets
Direct
ion o
f w
ate
r flo
w
Directionof water flow
Fist layer of stonefilled perforated bags. to be filledwith 30mm crusherstone
Second layer of stone filled perforated bags, to be filled with 15mm crusherstone
Fist layer of stone filled perforated bags. to be filled with 30mm crusherstone
Second layer of stone filled perforated bags, to be filledwith 15mm crusher stone
If area surrounding inlet is not yethard surfaced, stone bags should be pegged to avoid shifting during heavy rain events.
- Should the inlet be positioned at a low point with water entering from a number of sides, a doublerow of stone bags (as detailed above) should be placed at each side where water enters.
- In low flow, high sediment areas, consideration should be given to cover the inlet structures withbiddum (this will only work in low flow areas.)
Outlet Protection
Stormwater outlet point (prior)to completion of final outlet structure
Day-lighting of stormwater outlet
150mm - 200mm rock loosely packed (90% single layer) cover within sandbag enclosed area
Heavy duty (40kg) sand bags packed to enclose rock
Sand Bags to be pegged with wooden or metal stakes to prevent movement
- The methodology referred to above is effective as a temporary measure to be used during construction and is in no way intended to replace the permanent measures that must be installed. These permanent measures must be constructed as per the engineers specifications.- Stormwater systems should ideally be constructed during low rainfall periods in order to allow for permanent protection measures to be put in place before the rainy season.- Consideration should be given to encase the outlet structure with a geo-fabric such as biddum. This should first be clarified with the site engineer to ensure compatibility with the stormwater system.
Cape EAPrac
Management of Haul and Access Roads during construction Environmental Management Programme
Cape Environmental Assessment
Practitioners (Pty) Ltd
Figure 3: Management of Haul and Access Control During Construction
Temporary gravel access and haul roads used during construction. The future permanent access and internal roads should be used as temporary access and haul roads until they are hard surfaced.
A 20m strip of 100mm rock should be packed from the existing municipal road towards theconstruction site. This will minimise the amount of mud and dust deposited on the municipal road.
Perimeter fence
Existing municipal road.
- Every effort to minimize dust pollution on the site must be undertaken.
- Construction vehicles must adhere to speed limits and minimization of haul roads must be implemented. During dry, dusty periods haul roads should be kept dampened to prevent excess dust.
- No potable water may be used for damping haul roads.
- As an alternative, products such as road environment dust suppressants (Reds) would be recommended in order to minimize the use of water for controlling dust pollution. This is to be determined by the ECO during construction as required.
Minimisation of Dust on Haul Roads
The most important environmental factor to be considered regarding access and haul roads, is the location thereof. Haul roads should be designed to make use of future permanent internal roads and access points.
The haul roads should never be construction in areas that will not be permanently transformed with the development. Nor should they be constructed in any sensitive area.
Another safety and environmental hazard caused by haul road surface is dust problems. Roads should be designed with enough fines to act as binders for the larger particles. However, an excess of fines will result in these particles being released to the atmosphere when repeated stress is applied by the equipment tires. All haul roads that do not have a “sealed” surface, will create dust. The dust problem is mainly dealt with byapplication of water.
Key Environmental Considerations for Haul Roads
Cape EAPrac
Demarcation of no-go Areas Environmental Management Programme
Cape Environmental Assessment
Practitioners (Pty) Ltd
Figure 4: Demarcation of No - Go Areas During Construction
Wooden Dropper
Danger Tape
Galvanised Wire
Galvanised Wire
Ground Level
10
00
mm 5
00
mm
Wooden Dropper
Danger Tape
Galvanised Wire
Galvanised Wire
Ground Level
10
00
mm
50
0m
m
Silt fence installed as per specificationsMulch Bags5
00
mm
Plate A: Showing a cross section of a typical method of demarcation of no-go areas.
Where demarcation is required on a downslope, it can be more cost effective to include the required silt protection mechanisms on the same support structure as the demarcation. This isdetailed in Plate B below and must be read in conjunction with the details onerosion control included in the previousdiagram.
G E N E R A L C O N S I D E R A T I O N S F O R DEMARCATION OF NO GO AREAS
?The demarcation must include all areas that are going to be disturbed in the total construction (including all service lines)
?The no -go areas may not be accessed by any person (including lunch, tea breaks etc.). Without the explicit written permission from te ECO.
?Maximum fines will be issued for any non compliance with regards to the no go policy.
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 5: ENVIRONMENTAL
GUIDELINES ON SITE
ENVIRONMENTAL DO’S ENVIRONMENTAL DON’TS
Work Site
Workers and equipment
to stay within site
boundaries
Do not enter no go areas
Materials &
Equipment
Use drip trays
Report spills
Do not create dust
Do not drive too fast
Store in camp at night
Check for leaks
Ensure loads don’t spill
Do not wash machinery or tools on site
Waste M
anagement
Use toilets provided
Don’t burn or bury waste
No fires on site
Report any other fires
Use bins provided for
cigarette butts & waste
Eat in designated area
Don’t eat at dam or river
Natural Environment
Save water
Use only drinking water
provided
Do not damage trees,
flowers or rocks
Protect animals and archaeological remains
Do not swim or wash in the dam or river
Danger & Emergencies
Know emergency procedures & no’s
Report accidents
No smoking near gas or
diesel
�
Be careful when working with hazardous substances
Fines will be issued for non-compliance with
environmental
specifications
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 6: WATER DEMAND DATA
TEMPLATE
Project:
Contractor:
Date:
No. of site personnel:
Mains water Volume Meter reading
Licensed water abstractions Volume Abstraction resource i.e. river, dam etc.
Water transported Volume Origin - where water was sourced.
Allocation of water Volume Re-use opportunities
Cleaning - tools
Cleaning - vehicles
Dust supression
Concreting
Ground works
Toilets, site camp
Other (specify)
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 7: ENVIRONMENTAL
LANDSCAPING
ALBERTINIA SAND FYNBOS Graminoids: Succulent herbs: Woody climber: Graminoids: SOUTHERN AFROTEMPERATE FOREST
STATUS: VULNERABLE Ficinia nodosa Crassula orbicularis Asparagus aethiopicus Cynodon dactylon STATUS: LEAST THREATENED
Tall Shrubs: Juncus kraussii krausii Graminoids: Cissampelos capensis Eragrostis capensis Scree and deep gorge:
Cassine peragua peragua Stenotaphrum secundatum Ischyrolepis sieberi Rhoicissus digitata Ficinia bulbosa Cunonia capensis
Leucadendron eucalyptifolium Megagraminoids: Woody succulent climber: Thamnochortus cinereus Metrosideros angustifolia
Leucadendron galpinii Phragmites australis GROOT BRAK DUNE STRANDVELD Sarcostemma viminale Podocarpus elongatus
Leucospermum praecox Typha capensis STATUS: ENDANGERED Semi-parasitic shrubs: MOSSEL BAY SHALE RENOSTERVELD Tall trees:
Nylandtia spinosa Herbs: Small trees: Osyris compressa STATUS: ENDANGERED Afrocarpus falcatus
Protea repens Berula erecta thunbergii Chionanthus foveolatus Soft shrub: Thicket clumps dominated by: Brabejum stellatifolium
Protea susannae Falkia repens Clausena anisata Hypoestes aristata Euclea undulata Cunonia capensis
Psoralea pinnata Geophytic herbs: Tall shrubs: Herbs: Putterlickia pyracantha Curtisia dentata
Low shrubs: Zantedeschia aethiopica Azima tetracantha Commelina africana Rhus lucida Ilex mitis
Aulax umbellata Cussonia thyrsiflora Geophytic herbs: Succulent trees: Nuxia floribunda
Chironia baccifera GARDEN ROUTE GRANITE FYNBOS Diospyros dichrophylla Brunsvigia orientalis Aloe ferox Ochna arborea arborea
Chrysocoma ciliata STATUS: ENDANGERED Euclea racemosa Chasmanthe aethiopica Aloe speciosa Olea capensis macrocarpa
Diospyros dichrophylla Tall shrubs: Grewia occidentalis Freesia alba Tall shrubs: Olinia ventosa
Erica baueri baueri Protea coronata Gymnosporia buxiflora Succulent herbs: Diospyros dichrophylla Podocarpus elongatus
Erica discolor Protea lanceolata Maytenus procumbens Crassula expansa expansa Rhus glauca Podocarpus latifolius
Erica sessiliflora Protea neriifolia Metalasia muricata Senecio radicans Low shrubs: Pterocelastrus tricuspidata
Erica versicolor Low shrubs: Morella cordifolia Herbaceous climber: Carissa bispinosa bispinosa Rapanea melanophloeos
Leucadendron meridianum Agathosma ovata Myrsine africana Cynanchum obtusifolium Elytropappus rhinocerotis Small trees:
Passerina rigida Erica discolor var. speciosa Mystroxylon aethiopicum Kedrostis nana Eriocephalus africanus var. africanus Allophylus decipiens
Syncarpha paniculata Erica formosa Olea exasperata Herbaceous succulent climber: Salvia muirii Brachylaena nerifolia
Geophytic herbs: Eriocephalus africanus Pterocelastrus tricuspidatus Pelargonium peltatum Succulent shrubs: Canthium inerme
Bobartia robusta Leucadendron salignum Putterlickia pyracantha Graminoids: Aloe arborescens Cassine peragua
Bulbine frutescens Mimetes cucullatus Rhus crenata Cynodon dactylon Crassula perforata Diospyros whyteana
Pteridium aquilinum Pelargonium fruticosum Rhus glauca Ficinia indica Succelent herbs: Gonioma kamassi
Graminoids: Syncarpha paniculata Rhus longispina Carpobrotus acinaciformis Lachnostylis hirta
Cynodon dactylon Semi-parasitic shrubs: Rhus lucida KNYSNA SAND FYNBOS Senecio crassulaefolius Metrosideros augustifolia
Elegia stipularis Osyris compressa Schotia afra var. afra STATUS: ENDANGERED Virgilia divaricata
Thamnochortus insignis Graminoids: Sideroxylon inerme Small tree: NORTH OUTENIQUA SANDSTONE FYNBOS Virgilia oroboides feruginea
Ficinia nigrescens Tarchonanthus littoralis Widdringtonia nodiflora STATUS: LEAST THREATENED Virgilia oroboides oroboides
CANCA LIMESTONE FYNBOS Low shrubs: Tall shrubs: Small trees: Tall shrubs:
STATUS: LEAST THREATENED GARDEN ROUTE SHALE FYNBOS Ballota africana Leucadendron eucalyptifolium Protea nitida Burchellia bubalina
Tall shrubs: STATUS: ENDANGERED Carissa bispinosa Metalasia densa Tall shrubs: Sparrmannia africana
Chrysanthemoides monilifera Tall shrubs: Chironia baccifera Low shrubs: Chrysanthemoides monilifera Geophytic herbs:
Protea lanceolata Leucadendron eucalyptifolium Clutia daphnoides Anthospermum aethiopicum Leucadendron eucalyptifolium Blechnum capense
Protea obtusifolia Metalasia densa Eriocephalus africanus var. africanus Berzelia intermedia Protea nerifolia Blechnum tabulare
Low shrubs: Protea aurea aurea Helichrysum teretifolium Erica glandulosa fourcadei Low shrubs: Clivia mirabilis
Acmadenia obtusata Protea coronata Lauridia tetragona Erica sessiliflora Leucadendron salignum Dietes iridioides
Diospyros dichrophylla Protea neriifolia Phylica axillaris Leucadendron salignum Phylica axillaris Rumohra adiantiformis
Lobostemon belliformis Rhus lucida Polygala myrtifolia Lobelia coronopifolia Felicia filifolia filifolia Tudea barbara
Phylica pubescens var. Orientalis Low shrubs: Succulent shrubs: Morella quercifolia Metalasia pulcherrima f. pallescens Woody climber:
Succulent shrubs: Anthospermum aethiopicum Aloe arborescens Muraltia squarrosa Graminoids: Asparagus scandens
Delosperma virens Elytropappus rhinocerotis Cotyledon orbiculata var. dactylopsis Oedera imbricata Rhodocoma fruticosa Graminoids:
Graminoids: Helichrysum cymosum Crassula perforata Protea cynaroides Ischyrolepis subverticillata
Ficinia truncata Leucadendron salignum Euphorbia burmannii Stoebe plumosa Megaherbs:
Pelargonium cordifolium Euphorbia mauritanica Tephrosia capensis Strelitzia alba
CAPE LOWLAND FRESHWATER WETLANDSPhylica axillaris Tetragonia fruticosa Herbs:
STATUS: LEAST THREATENED Selago corymbosa Zygophyllum morgsana Geranium incanum
Low shrubs: Geophytic herbs:
Senecio halimifolius Pteridium aqulinum
Plecostachys serpyllifolia
Suggested Plant Species for Best Practice Landscaping
PLEASE NOTE THAT THIS LIST PROVIDES FOR INDIGENOUS SPECIES AVAILABLE FROM YOUR LOCAL NURSERY AND SHOULD BE USED AS A GUIDELINE ONLY
SOUTHERN CAPE DUNE FYNBOS Leucospermum cuneiforme
STATUS: LEAST THREATENED Berzelia intermedia
Thicket clumps: Brunia nodiflora
Pterocelastrus tricuspidatus Acmadenia tetragona
Rhus lucida Anisodontea scabrosa
Sideroxylon inerme Erica discolor
Tarchonanthus littoralis Erica formosa
Tall shrubs: Erica gracilis
Olea exasperata Erica sparsa
Rhus crenata Erica versicolor
Rhus glauca Mimetes cucullatus
Rhus laevigata Protea cynaroides
Rhus lucida Senecio glastifolius
Low shrubs: Struthiola eckloniana
Agathosma apiculata Syncarpha paniculata
Agathosma ovata Geophytic herbs:
Anthospermum aethiopicum Pteriduim aquilinum
Chironia baccifera Watsonia fourcadei
Felica echinata Graminoids:
Helichrysum teretifolium Ficinia gracilis
Leucadendron salignum
Metalasia muricata
Morella quercifolia
Otholobium bracteolatum
Passerina rigida
Pelargonium betulinum
Phylica ericoides
Struthiola parviflora
Geophytic herbs:
Cyrtanthus loddigesianus
Cyrtanthus obliquus
Graminoids:
Ficinia dunensis
Thamnochortus cinereus
SOUTH OUTENIQUA SANDSTONE FYNBOS
STATUS: VULNERABLE
Small trees:
Widdringtonia nodiflora
Tall shrubs:
Chrysanthemoides monilifera
Leucadendron conicum
Leucadendron eucalyptifolium
Leucadendron uliginosum uliginosum
Metalasia densa
Protea neriifolia
Protea repens
Dodonaea viscosa var. augustifolia
Podalyria sericea
Pterocelastrus tricuspidata
Low shrubs:
Leucadendron comosum comosum
Leucadendron salignum
Leucadendron spissifolium fragrans
in these areas that can be used for rehabilitation and landscaping.
Site specific identification of plant species is advisable to inform final planting lists.
This list is by no means comprehensive, there are many other species that occur
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 8: ALIEN INVADERS LIST & CATEGORIES WFW GUIDE TO CONTROL METHODS &
HERBICIDE SELECTION
ESTIMATED VOLUMES OF PRODUCT PER HECTARE ARE FOR A DENSE / CLOSED STAND OF THE SPECIFIC SPECIES. FOR LOWER INFESTATIONS VOLUMES SHOULD BE REDUCED ACCORDINGLY.
MEDIUM = 75% OF DENSE/ CLOSED SPARSE = 50% OF DENSE / CLOSED SCATTERED = 25% OF DENSE / CLOSED VERY SCATTERED = 10 % OF DENSE / CLOSED OCCASIONAL = 1 % OF DENSE / CLOSED
• FOR WATER BASED APPLICATIONS, ACTIPRON SUPER WETTER SHOULD BE ADDED WHERE RECOMMENDED ON THE LABEL. RATE PER HECTARE FOR DENSE / CLOSED STAND – 1.75 l / ha • FOR ALL WATER BASED TREATMENTS A SUITABLE DYE SHOULD BE ADDED WHEN NECESSARY TO ENSURE THAT ALL TARGET PLANTS ARE TREATED. RATE PER HECTARE FOR DENSE / CLOSED STAND - 350ml / ha • FOR DIESEL BASED APPLICATIONS, SUDAN RED DYE SHOULD BE ADDED. RATE PER HECTARE FOR DENSE / CLOSED STAND 300 ml / ha.
ANNEXURE A.
GUIDE TO CONTROL METHOD AND HERBICIDE SELECTION FOR ALIEN VEGETATION.
AMERICAN BRAMBLE (RUBUS CUNEIFOLUS.)
ESTIMATED TARGET PLANTS METHOD PRODUCT RATE COMMENTS PRODUCT / HECTARE
ALL PLANTS FOLIAR SPRAYS MAMBA(GLYPHOSATE 360g/l)
300ml /10 l WATER(6l / Ha)
SEE NOTE 6 l / ha
TOUCH DOWNGLYPHOSATETRIMESIUM 480g/l)
6l / ha SEE NOTE 6 l / ha
MATUREPLANTS
SLASH AND SPRAYREGROWTH
GARLON 4/ VIROAXE(TRICLOPYR ESTER480gm / l)
50ml / 10l WATER SEE NOTE 1.5 l / ha
NOTE:SPRAY ON ACTIVELY GROWING PLANTS.SLASH OLD GROWTH IN WINTER, AND SPRAYSPRING GROWTH WHEN ABOVE O.5 m TALL.
INKBERRY (CESTRUM LAEVIGATUM.)
ESTIMATEDTARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
SEEDLINGS HAND PULL
SINGLESTEMMED
BASALSTEM
GARLON 4 VIROAXE (TRICLOPYR
100ml / 10 l DIESEL
2 l / ha
LARGE TREES 480g/l)
ALL CUT STUMP TIMBREL 3 A * 300ml / 10 l 2 l / ha ( TRICLOPYR AMINE WATER
SALT 360 g /l)
CHOPPER 200ml / 10 l 1.5 l / ha (IMAZAPYR WATER
100g / l)
• CONSULT THE WFW TECHNICAL ADVISOR.
AUSTRALIAN MYRTLE (LEPTOSPERMUM LAEVIGATUM.)
TARGET PLANTS METHOD PRODUCT RATE COMMENTS
BIG TREES CUT DOWN CUT DOWN ATGROUND LEVELDO NOT APPLYHERBICIDE
BARBADOS GOOSEBERRY (PERESKIA ACULEATA.)
ESTIMATEDTARGET PLANTS METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE.___________________________________________________________________________________________________________________________________________
VINES CUT DOWN TO GARLON 4 VIROAXE
50ml/10 l BURN REMAINING 1.5 l
2m AND SPRAY (TRICLOPYR ESTER 480g/l) WATER PLANT MATERIAL.
FOLLOW UP SPRAYSMAY BE NECESSARY.
___________________________________________________________________________________________________
BEEFWOOD (CASUARINA EQUISETIFOLIA)
ESTIMATEDTARGET PLANTS METHOD PRODUCT RATE COMMENT PRODUCT / HECTARE
ALL TREES FRILL CHOPPER 1000ml / 10 l IMAZAPYR WATER 5L/Ha 100g / l)
BLACK WATTLE (ACACIA MEARNSII)
TARGET TREES METHOD PRODUCT RATE COMMENTS ESTMATED PRODUCT/ HECTARE
HAND PULL OR HOE OPEN STANDS
FOLIAR SPRAYUP TO 1 m TALL
MAMBA(GLYPHOSATE 360g/l)
150ml/ 10L WATER AVOID WATER COURSE 3 lCONTAMINATION
SEEDLINGS ANDSAPLINGS FOLIAR SPRAY
UP TO 2m TALLTOUCHDOWN(GLYPHOSATE TRIMESIUM480g/l)
3l/ ha 3 l
FOLIAR SPRAY GARLON 4 / VIROAXE 25 – 75ml/ 10L LOW RATE ON 0.5 – 1.5 lUP TO 1.5m TALL (TRICLOPYR ESTER
480g/l)WATER SEEDLINGS
SEE NOTE BELOW
YOUNG TREES FOLIAR SPRAY GARLON 4 / VIROAXE 75ml/ 10L 3 l(TRICLOPYR ESTER WATER
BIG TREES
INACESSABLETREES
CUT STUMP
FRILL
STEMTREATMENT
480g/l)TIMBREL 3 A *(TRICL0PHYR AMINESALT 360g / l)TIMBREL 3 A *(TRICLOPHYR AMINESALT 360g / l)
ECO – PLUG ∗
3l / 100lWATER
300ml / 10LWATER
1.5 l / ha
1.5 l / ha
INACESSABLE ORDANGEROUS AREAS
* CONSULT THE WFWTECHNICAL ADVISOR.
NOTE: USE GARLON 4 / VIROAXE IFGRASS SPECIES ARE PRESENT.
1.
BLUEGUMS (EUCALYPTUS SPP.)
TARGET PLANTS METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT/ HECTARE
SEEDLINGS HAND PULL
COPPICE FOLIAR SPRAY
BRUSH OFF *(METSULPHFURONMETHYL 500g / kg)PLUSMAMBA *(GLYPHOSATE 360 g /l)
200g / ha
+
3 l / ha
APPLY TO COPPICE 200 g / ha1.5 – 1.8 m TALL 3 l / ha
.
.
FELLED TREES
CUT STUMP CHOPPER(IMAZAPYR 100 g/l)
1250 ml / 10 lWATER
IF SPECIES KNOWN 6 l / haCHECK RATE ON LABEL
FRILL CHOPPER(IMAZAPYR 100g/l)
1250ml / 10 lWATER
IF SPECIES KNOWN 6 l / haCHECK RATE ON LABAEL
* CONSULT THEWFW TECHNICALADVISOR.
SPOT SPRAY COPPICE:16 LITRES WATER16 GMS BRUSH OFF1% MAMBA0.5% ACTIPRON
___________________________________________________________________________________________________
BRAZILIAN PEPPER TREE (SCHINUS TEREBRINTHIFOLIUS.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
ALL TREES BASAL STEM GARLON 4 /VIROAXE(TRICLOPYR ESTER
200ml / 10LDIESEL
WET UP TO 0.5m 1.5 l / ha STEM AND ROOTS
480g/l)
BUGWEED (SOLANUM MAURITIANUM.) 1.
ESTIMATEDTARGET PLANTS METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
HAND PULL
STARANE 200(FLUROXYPYR 200g/l)
12.5ml / 10LWATER
UP TO 1m TALL 0.5 l / ha
SEEDLINGS &SAPLINGS
FOLIAR SPRAY
MAMBA(GLYPHOSATE 360g/l )
50ml / 10LWATER
2 l / ha
TOUCH DOWN(GLYPHOSATETRIMESIUM 480g/l)
2l / ha SPRAY WHEN 2 l / ha500mm TALL
GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
50ml / 10LWATER
1.5 / ha
BUGWEED 2.
TARGET PLANTS METHOD PRODUCT RATE COMMENTS ESTIMATEDPRODUCT /HECTARE
STARANE 200(FLUROXYPYR 200g/l )
12.5ml / 10L WATER SPRAY WHEN 0.5 l / ha500mm TALL
CUT DOWN & SPRAY COPPICE
MAMBA(GLYPHOSATE 360g/l)
150ml / 10L WATER 3 l / ha
TOUCH DOWN (GLYPHOSATETRIMESIUM 480g/l)
2l /ha SPRAY WHEN 2 l / ha500mm TALL
BIG TREES
CHOPPER(IMAZAPYR 100g/l) 200ml/10l WATER
CUT SURFACE 1 l / haONLY
CUT STUMP
TIMBREL 3 A(TRICLOPYR AMINESALT 360g/l)
300ml / 10L WATER CUT SURFACE 2.25 l / haONLY
FRILLTIMBREL 3 A *(TRICLOPYR AMINE SALT360 g/l)CHOPPER (IMAZAPYR 100g/l)
* CONSULT THE WFW TECHNICALADVISOR.
300ml / 10L WATER
200ml / 10 l WATER
1.5 l / ha
1 l / ha
1.
C A C T I
ESTIMATESPECIES TARGET METHOD PRODUCT RATE COMMENTS PRODUCT/ PLANTS HECTARE
HARRISIA CACTUS(HARRISIAMARTINI.)
STANDINGPLANTS
SPRAYAPPLICATION
MSMA(MSMA 720gll)
GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
1 l / 20 lWATER
100ml / 10LWATER
10 l / ha
TREES UP TO 2 l / ha 1.5 m TALL
STEMINJECTION
MSMA(MSMA 720g/l)
1 l / 2 lWATER
2 l / ha
JOINTED CACTUS PLANTS SPRAY MSMA 1 l / 2 l 5 l / ha(OPUNTIAAURANTIACA.)
AND LOOSECLADODES
APPLICATION (MSMA 720g/l) WATER
2.
C A C T I
ESTIMATED SPECIES TARGET METHOD PRODUCT RATE COMMENTS PRODUCT /
PLANTS HECTARE______________________________________________________________________________________________________________________________
IMBRICATECACTUS(OPUNTIAIMBRICATA.)
WHOLE PLANT
MSMA(MSMA 720g/l)
1 l / 22 lWATER
10 l / ha
ROSEA CACTUS(OPUNTIA ROSEA.)
STANDINGPLANTS
SPRAY APPLICATION
CUT STUMP
MSMA(MSMA 720g/l)
1 l /22 l WATER
CUT PLANTS DOWN 2 l / haTO 100 – 150 mm.AND SPRAY CUTSTUMP
3.
___________________________________________________________________________________________________________________________________________
C A C T I
ESTIMATEDPRODUCT /
SPECIES TARGET PLANTS METHOD PRODUCT RATE COMMENTS HECTARE.
MSMA(MSMA 720g/l)
1l / 1lWATER
2 ml DOSES 12 l / ha
PRICKLEYPEAR
STANDINGPLANTS
STEMINJECTION
(OPUNTIAFICUS-INDICA)
MAMBA(GLYPHOSATE360g/l)
1l/2lWATER
2 ml DOSES 16 l / ha
TOUCHDOWN (GLYPHOSATETRIMESIUM 480g/l)
330ml / 10LWATER
2 ml DOSES 8 l / ha
NOTE: INJECT INTO 4– 12 PREMADE HOLESPER PLANT
4.
___________________________________________________________________________________________________
C A C T I.
ESTIMATED SPECIES TARGET METHOD PRODUCT RATE COMMENTS PRODUCT /
PLANTS HECTARE
SOURPRICKLEYPEAR
LARGE PLANTS STEMINJECTION
MSMA(MSMA 720g/l)
1l /1l 2 ml DOSES 8 l / haWATER SEE NOTE BELOW
(OPUNTIA STRICTA)SMALL PLANTS SPRAY
APPLICATIONMSMA(MSMA 720g/l)
1l / 30l 10 l / haWATER
NOTE: APPLY DOSES INTO 1 – 8 PRE-MADE HOLES IN PLANTS.
___________________________________________________________________________________________________
CAMEL THORN BUSH (ALHAGI CAMELORUM)
TARGET PLANTS METHOD PRODUCT RATE COMMENT ESTIMATED PRODUCT/HECTARE
___________________________________________________________________________________________________________________________________________
STANDS OF PLANTS GRANULAR MOLOPO GG 2 – 4 g / m2 RATE DEPENDS ON 20 – 40 Kg / ha APPLICATION (TEBUTHIURON CLAY CONTENT
200 g / kg)
NOTE: OBTAIN ASSISTANCE FROM SUPPLIER ON APPLICATION TECHNIQUES BEFORE APPLYING.
CLUSTER PINES (PINUS PINASTER.)
TARGET PLANTS METHOD PRODUCT RATE COMMENTS
ALL TREES CUT DOWN CLOSETO GROUND
DO NOT APPLYHERBICIDE TOSTUMPS
IN DIFFICULTTERRAIN
STEM ECOPLUG * ONLY ON SMALLTREES 10CM OR LESS.NOT EFFECTIVE ONLARGER TREES
* CONSULT THE WFWTECHNICAL ADVISOR.
GOLDEN WATTLE (ACACIA PYCNANTHA.)
TARGET TREES METHOD PRODUCT RATE COMMENTS
SEEDLINGS ANDSAPLINGS
HAND PULL OR HOE
BIG TREES CUT STUMP STUMP OUT (CYLINDROBASIDIUM
1 SACHET/ 400mlSUNFLOWER OIL
APPLY 1 – 2 DROPS PER STUMP
LAEVE) 2X10 SPORES PER SACHET
___________________________________________________________________________________________________
GREEN WATTLE ( ACACIA DECURRENS)
TARGET TREES METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT/ HECTARE
SEEDLING ANDSAPLINGS
HAND PULL OR HOE
TREES CUT STUMPTIMBREL*(TRICLOPYR AMINE SALT360g / l)
300ml / 10L WATER 1.5l / ha
* CONSULT THE WFW TECHNICAL ADVISOR
GUAVA (PSIDIUM GUAJAVA.)
ESTIMATED TARGET TREE METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
ALL TREES CUT STUMP CHOPPER(IMAZAPYR 100g/l)
1250ml / 10 l WATER
TREAT CUT 6 l / haSURFACE
HONEY MESQUITE (PROSOPIS SPP.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
CUT STUMP GARLON 4 VIROAXE
400ml / 10L DIESEL 3 l / ha
(TRICLOPYR ESTERALL TREES 480g/l)
SOIL APPLICATION MOLOPO S.C. * (TEBUTHIURON 5OO g / l)
* CONSULT THEWFW TECHNICALADVISOR.
1.5L / 8.5 L WATER LIGHT SOILS 2 l / haONLY IN RESTRICTEDAREAS
____________________________________________________________________________________________________________________________________1.______
TRIFFID WEED (CROMOLAENIA ODORATA.)___________________________________________________________________________________________________________________________________________
ESTIMATED
TARGET PLANTS METHOD PRODUCT RATE PRODUCT / HECTARE
SEEDLINGS
HAND PULL
MAMBA(GLYPHOSATE 360g/l)
100ml / 10L WATER 4 l / ha
FOLIAR SPRAY TOUCHDOWN(GLYPHOSATE TRIMESIUM 480g/l)
100m l / 10L WATER 4 l / ha
GARON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
37..5ml / 10LWATER
1.5 l / ha
2.
TRIFFID WEED ( CROMOLAENIA ODORATA.)
TARGET PLANTS METHOD PRODUCT RATE ESTIMATED PRODUCT/ HECTARE.
MAMBA 100ml / 10L WATER 4 l / ha (GLYPHOSATE 360g/l)
SLASH AND SPRAY TOUCHDOWN 100ml / 10L WATER 4 l / ha REGROWTH (GLYPHOSATE WHEN 500 mm TALL TRIMESIUM 480g/l)
GARLON 4 / VIROAXE 37.5ml / 10L 1.5 l / ha(TRICLOPYR ESTER 480 g/l) WATER
ESTABLISHEDPLALNTS
CUT STUMP CHOPPER 200 ml / 10 l WATER 1.5 l / ha (IMAZAPYR 100 g/l)
.
KUDZU (PUERARIA LOBATA.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE____________________________________________________________________________________________________________________
ACTIVELYGROWING PLANTS
SPRAY GARLON 4VIROAXE(TRICLOPYR ESTER480g/l)
50ml/10LWATER
WET THOROUGHLY 3 l / ha
LONG - LEAVED WATTLE ( ACACIA LONGIFOLIA )____________________________________________________________________________________________________________________
TARGET TREES METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT/ HECTARE
SEEDLINGS ANDSAPLINGS UP TO2m TALL
HAND PULL OR HOE
FOLIAR SPRAY GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
60ml/10L WATER
OPEN STANDS
2 l / ha
TREES
CUT DOWN ANDTREAT COPPICE
GARLON 4 / VIROAXE (TRICLOPYR ESTER 480g/l)
60ml/10L WATER
CUT LOW DOWN 2 l / haTO REDUCE COPPICE
CUT STUMP TIMBREL 3 A *(TRICLOPYR AMINESALT 360g / l)
300ml / 10L WATER
SEE NOTE BELOW 1.5 l / ha
FRILL TIMBREL 3 A *(TRICLOPYR AMINESALT 360g / l)
300ml / 10L WATER
1.5 l / ha
NOTE: TREES CUTCLEANLY LOW DOWN,DO NOT NORMALLYCOPICE
* CONSULT THE WFWTECHNICAL ADVISOR.
.
__________________________________________________________________________________________1.________
PORT JACKSON WILLOW (ACACIA SALIGNA.)
TARGET TREES METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT /
HECTARE
______________________________________________________________________________________________________________________________
HAND PULL OR HOE OPEN STANDS
MAMBA(GLYPHOSATE 360g/l)
2 – 4l / ha SPOT SPRAY 1.5% 2-4 l / ha SOLUTION
SEEDLINGSTOUCHDOWN
FOLIAR SPRAY (GLYPHOSATE TRI- 2 – 4 l / ha 2-4 l / haMESIUM 480g/l)
GARLON 4 / VIROAXE 50ml/10L l.5 l / ha(TRICLOPYR ESTER WATER SEE NOTE BELOW480g/l)
NOTE: USE GARLON 4 or VIROAXE, IF OTHER PIONEER GRASS SEEDLINGS PRESENT.
2.
PORT JACKSON WILLOW (ACACIA SALIGNA).
TARGET TREES METHOD PRODUCT RATE COMMENTESTIMATEDPRODUCT/HECTARE
SAPLINGS ANDYOUNG TREES
HAND PULL OR HOE
FOLIAR SPRAY
TOUCH DOWN(GLYPHOSATE)
GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
4 l/ha
50ml / 10L WATER
PLANTS UP TO 600mm HIGH
PLANTS UP TO 2mHIGH
4 l / ha
3 l / ha
BIG TREES CUT STUMP
FRILL
TIMBREL 3A(TRICLOPHYR AMINESALT 360 g/l)
TIMBREL 3A(TRICLOPHYR AMINESALT 360 g/l)
300ml / 10LWATER
300ml / 10L WATER
1.5 l / ha
1.5 l / ha
MAURITIOUS THORN ( CAESALPINIA DECAPETALIA.)
TARGET PLANTS METHOD PRODUCT RATE ESTIMATED PRODUCT/ HECTARE
TOUCH DOWN 3 l / ha 3 l / ha(GLYPHOSATE TRI-
SEEDLINGS FOLIAR SPRAY
MESIUM 480g/l)
GARLON 4 / VIROAXE(TRICLOPYR ESTER 480g / l)
50ml / 10l 1.5 l / ha WATER
MAMBA 150ml/10L WATER 3 l / ha(GLYPHOSATE 360g/l)
GARLON 4 / VIROAXE 50ml/10L 1.5 l / ha(TRICLOPYR ESTER WATER480g/l)
PLANTS UP TO FOLIAR SPRAY1m TALL MAMBA 3l / Ha 3 l / ha
(GLYPHOSATE360g/l)
YOUNG PLANTS ANDREGROWTH UP TO
FOLIAR SPRAY GARLON 4 / VIROAXE(TRICLOPYR ESTER
50ml / 10L 2 l / ha WATER
500mm AFTER 480g/l)SLASHING
TREES
* CONSULT THE WFW
CUT STUMP TIMBREL 3 A *(TRICLOPYR AMINESALT 360g / l)
300ml / 10L 1.5 l / ha WATER
TECHNICAL ADVISOR
QUEEN OF THE NIGHT ( CEREUS JAMACARU.)
ESTIMATED TARGET PLANTS METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE______________________________________________________________________________________________________________________________
LARGE PLANTS STEM INJECTION MSMA 1l / 2l WATER OCTOBER(MSMA 720g/l) 2ml / INJECTION TREATMENT.
1 INJECTION PER 2.5m STEM LENGTH
SMALL PLANTS SPRAY APPLICATION MSMA(MSMA 720g /l)
1l / 20l WATER OCTOBER TREATMENT 10 l / ha
RED EYE (ACACIA CYCLOPS)___________________________________________________________________________________________________
TARGET TREE METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT/
HECTARE
SEEDLINGS &SAPLINGS
HAND PULL OR HOE OPEN STAND
SPRAY GARLON 4 / VIROAXE 50ml/10L DENSE STAND 2l / ha(TRICLOPYR ESTER480g/l)
WATER
TREES UP TO 2m TALL
CUT LOW DOWN
FOLIAR SPRAYGARLON 4 / VIROAXE(TRICLOPYR ESTER
50ml/10L WATER
4l / ha
480g/l)
LARGE TREES CUT LOW DOWN DO NOT APPLY HERBICIDE
FRILL TIMBREL 3 A *(TRICLOPYR AMINESALT 360g / l)
300ml /10L WATER 1.5 l / ha
NOTE: CUT DOWN LOW, TO PREVENT COPPICING. * CONSULT THE WFW TECHNICAL ADVISOR.
1.
RED SESBANIA (SESBANIA PUNICEA.)
TARGET PLANTS METHOD PRODUCT RATE COMMENTS ESTIMATED PRODUCT / HECTARE.
MAMBA(GLYPHOSATE 360g/l)
150m l / 10L WATER 4 l / ha
SEEDLINGS FOLIAR SPRAYTOUCH DOWN(GLYPHOSATETRIMESIUM 480g/l)
4 l / ha 4 l / ha
GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
50ml / 10L WATER 2 l / ha
MAMBA(GLYPHOSATE 360g/l)
150ml / 10L WATER SPRAY WHEN 4 l / ha1m TALL
TREES SLASH ANDSPRAYCOPPICE
TOUCH DOWN(GLYPHOSATETRIMESIUM 480g/l)
4 l / ha 4 l / ha
GARLON 4 / VIROAXE(TRICLOPYR ESTER 480g/l)
50ml / 10L WATER SPRAY UP TO 2 l / ha2m TALL
NOTE: DO NOT SPRAY TREES UNDER BIO – CONTROL.
2.
RED SESBANIA
TARGET METHOD PRODUCT RATE COMMENT ESTIMATEDPRODUCT/HECTARE
TREES CUT STUMP
CHOPPER(IMAZAPYR 100g/l)
GARLON 4 / VIROAXE(TRICLOPYR ESTER 480g/l)
TIMBREL 3A *(TRICLOPYR AMINE SALT360g/l)
200ml / 10 l WATER
50ml / 10L WATER
100ml / 10LWATER
300ml / 10L WATER
DO NOT APPLY INRIPERIAN SITUATIONSWHERE WATERCONTAMINATIONCAN TAKE PLACE.
DO NOT APPLY INRIPERIAN SITUATIONSWHERE WATERCONTAMINATIONCAN TAKE PLACE.
DO NOT APPLY INRIPERIAN SITUATIONSWHERE WATERCONTAMINATIONCAN TAKE PLACE.
WHOLE STUMP
CUT SURFACE ONLY
CUT SURFACE ONLY
1.5 l / ha
1.5 l / ha
1.5 l / ha
2 l / ha
* CONSULT THE WFW TECHNICAL ADVISOR.
ROCK HACKEA (HACKEA GIBBOSA.) & SILKY HACKEA (HACKEA SERICIA.)
TARGET TREES METHOD
ALL PLANTS SLASH AND BURN, THEN HAND PULL SEEDLINGS.
SILVER WATTLE ( ACACIA DEALBATA)
ESTIMATEDTARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT / HECTARE.
HAND PULL OR HOE OPEN STANDSSEEDLINGS ANDYOUNG SAPLINGS
FOLIAR SPRAY GARLON 4 / VIROAXE(TRICLOPYR ESTER480g/l)
25 – 50 ml/10L WATER
LOW RATE ON 0.5 – 2l / haSEEDLINGS
TREES UP TO 1.5MTALL AND COPPICE
FOLIAR SPRAY GARLON 4 / VIROAXE(TRICLOPYR ESTER480c/l)
75ml/10LWATER
3l / ha
LARGE TREES
CUT STUMP
MAMBA(GLYPHOSATE360g/ l l
TIMBREL 3 A(TRICLOPYR AMINESALT 360g/l)
200ml/10LWATER
300ml/10LWATER
TREAT CUT 6l / haSURFACE
TREAT CUT 1.5l / haSURFACE
FRILL MAMBA(GLYPHOSATE 360g/l)
2L/10L WATER APPLY WITHIN 6l / ha30 MINUTES
___________________________________________________________________________________________________________________________________________
SISAL (AGAVE SISALANA)
TARGET PLANTS METHOD PRODUCT RATE COMMENT ESTIMATED PRODUCT/ REQUIRED
____________________________________________________________________________________________________________________
ALL SISAL INJECTION MSMA 2ml PER PLANT INTO BOLE 2 l / 1000 PLANTS (MSMA 720 g/l)
SYRINGA (MELIA AZEDRACH.)
ESTIMATED TARGET PLANTS METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
CHOPPER(IMAZAPYR 100g/l)
300ml/10l WATER TREAT CUT 2 l / haSURFACE
ALL TREES CUT STUMPFRILL
TIMBREL 3A *(TRICLOPYR AMINESALT 360 g / l)
300ml / 10L WATER 2 l / ha
SEEDLINGS REMOVE BYHAND
* CONSULT THE WFW TECHNICAL ADVISOR.
________________________________________________________________________________________________________________________
LANTANA (LANTANA CAMARA)
TARGET PLANTS METHOD PRODUCT RATE ESTIMATED PRODUCT / HECTARE.
HAND PULLOR HOE
SEEDLINGS MAMBA(GLYPHOSATE 360g/l)
300ml / 10L WATER 6 l / ha
FOLIAR SPRAY TOUCH DOWN(GLYPHOSATETRIMESIUM 480g/l)
ACCESS *
SELECTED AREAS ONLY
(PICLORAM K – SALT240g / l)
6l / ha
100ml / 10LWATER
6 l / ha
2l / ha
____________________________________________________________________________________________________________
LANTANA (LANTANA CAMARA) Cont.
LARGE PLANTS
FOLIAR SPRAY CUT STUMP
TOUCHDOWN (GLYPHOSATE TRIMESIUM 480g/l) ACCESS * (PICLORAM K – SALT 240g / l) CHOPPER (IMAZAPYR 100g/l) ACCESS * (PICLORAM K – SALT 240g / l) * CONSULT THE WFW TECHNICAL ADVISOR.
6l / ha 100ml / 10L WATER SELECTED AREAS ONLY 200 ml / 10 l WATER 100ml / 10L WATER SELECTED AREAS ONLY
6 l / ha 2 l / ha 1.5 l / ha 2 l / ha
GREY POPLAR (POPULUS SPP.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE SEEDLINGS FOLIAR
SPRAY GARLON* VIROAXE (TRICLOPYR ESTER 480g/l)
150ml/10L WATER
2l / ha
CUT STUMP
CHOPPER (IMAZAPYR 100g / l)
500ml / 10L WATER
1.5 l / ha
LARGE TREES
ALL
CUT STUMP FRILL
CHOPPER (IMAZAPYR 100g / l)
500ml / 10 L WATER
1.5 l / ha
* CONSULT THE WFW TECHNICAL ADVISOR.
BLACKWOOD (ACACIA MELANOXYLON.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE SEEDLINGS FOLIAR
SPRAY STARANE* 12.5ml/10L
WATER 0.5L/Ha
FRILL/STEM APPLICATION
GARLON VIROAXE (TRICLOPYR ESTER 480g/l)
200ml / 10 L DIESEL
1.5 l / ha
LARGE TREES
ALL
FRILL/STEM APPLICATION
GARLON VIROAXE (TRICLOPYR ESTER 480g/l)
200ml / 10 L DIESEL
1.5 l / ha
* CONSULT THE WFW TECHNICAL ADVISOR.
JACARANDA (JACARANDA MIMOSIFOLIA.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
ALL TREES AND SEEDLINGS
FRILL/CUT STUMP
CHOPPER (IMAZAPYR 100g / l)
1000ml / 10 L WATER
5L/Ha
PEANUT BUTTER TREE (SENNA SPP.)
ESTIMATED TARGET TREES METHOD PRODUCT RATE COMMENTS PRODUCT /
HECTARE
ALL TREES AND SEEDLINGS
CUT STUMP
CHOPPER (IMAZAPYR 100g / l)
500ml / 10 L WATER
3L/Ha
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 9: RECYCLING
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
PAPERMETAL CANS
GLASS
PLASTIC
TEXTILES
USED OIL
TYRES
CARDBOARD SCRAP METAL
BIODEGRADABLEPLANT WASTES
BATTERIES
OLDAPPLIANCES
WHAT CAN WE RECYCLE?
CAR BODIES
CONSTRUCTION &DEMOLITION WASTE
COMMONLYRECYCLEDMATERIALS
R 2A
LESSCOMMONLYRECYCLEDMATERIALS
Department of Environmental Affairs and Tourism
GUIDELINES ON RECYCLING OF SOLID WASTEDepartment of Environmental Affairs and Tourism
CAR WINDSCREENS, MIRRORSGENERAL WASTE MIXED WITHHAZARDOUS WASTE(eg: HEALTH CARE WASTE)
VERY DIRTYRECYCLABLES
LAMINATESeg: PAPER AND PLASTIC
WHAT CANNOT BE RECYCLED?
R 2B
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
PAPER RECYCLING
SPREAD OUT & DRY
SHRED & DIGEST
ROLL & SQUEEZE OUT LIQUID
USE PAPERPRODUCTS
WASHDE-INK
PUTTHROUGHROLLERSAND CUTTO SIZE
MAKE NEWPRODUCTS
RECOVER USEDPAPER
R 8B
PULP
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
PLASTIC RECYCLING
EACH TYPE OF PLASTICPROCESSED SEPARATELY
SHREDWASH SHREDDED
PLASTIC
MAKE NEWPRODUCTS
DRY
MELT
EXTRUDECOOL
CHOP INTOPELLETS
USEPLASTIC
PRODUCTS
RECOVER USED PLASTIC
R 8D
SORT INTO PLASTIC TYPES
Department of Environmental Affairs and Tourism
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
GLASS RECYCLING
USE GLASSPRODUCTS
RECOVER USEDGLASS (KEEP
COLOURS SEPARATE)
TRANSPORTTO FACTORY
BREAK UPGLASS
MELT IN FURNACE WITH NEW PRODUCTMOLTEN GLASS
MOULD GLASS INTO NEWPRODUCTS
MAKE NEWPRODUCTS
R 9D
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
BREAKDOWN OF ORGANIC MATTER
BACTERIA & FUNGIEARTHWORMS
COMPOST HEAP - TURNOVER TO AERATE!
USE COMPOSTTO ENRICHSOIL FOR
GARDENING
BAGGEDCOMPOST
SIEVE OUT THE FINER FRACTION
GRASS CUTTINGS,GARDEN AND
KITCHEN WASTE
R 10B
COMPOST
COMPOSTING OFBIODEGRADABLEPLANT WASTES
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
METAL RECYCLING
SHRED
WASH
SMELT
POUR INGOTS
MAKE NEWPRODUCTS
USE METALPRODUCTS
RECOVER USED METAL
R 9B
GUIDELINES ON RECYCLING OF SOLID WASTE
Dep
artment of E
nvironmental A
ffairs and Tourism
RECYCLING OF USED OIL
DEPOSIT INROSE MINI
TANKER
TRANSPORTTO OIL
RECYCLER
RECOVER OIL FRACTIONFROM WASTE FRACTION
USE OIL PRODUCTS(MOTOR OIL, HYDRAULIC
OIL, MACHINE OIL,GEAR OIL)
SLUDGE WASTE
STORE OIL
RECOVER USED OIL
R 10AROSE - RECYCLING OIL SAVES THE ENVIRONMENT
HAZARDOUSLANDFILL
SITE
Department of Environmental Affairs and Tourism
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 10: EAP CURRICULUM VITAE
Page 1 of 2
Melissa Cornwell Mackay
Personal
Details:
Date of Birth ID Number License Languages Health Computer Literacy
07 March 1971
7103070033084
Code 10 (no PDP at present)
English and Afrikaans
Excellent
Excel Word, PowerPoint, MS Projects, CRS bookings program, CorelDraw, Email and Internet, GIS, ArcView, SANBI’s BGIS online Land Use Decision Support and Google Earth Pro, Joomla website design.
Experience June 2008 – Present Currently one of the senior Environmental Consultants at Cape EAPrac in George in the Southern
Cape. Duties include baseline assessments, damage and rehabilitation assessments, Environmental Impact Reports and Applications with related public participation exercises, Coastal Waters Discharge Permits, Ecological Control on site, GIS mapping for development projects and processing and responses to Appeals on Environmental Authorisation.
Working knowledge of applicable legislation and policies. Facilitation of Environmental Impact Assessments in terms of the National Environmental
Management Amendment Act (NEMAA) and project management during process. Convener for the South Cape Weeds Forum, a joint forum with the Department of Agriculture to
promote the combating of alien weeds in the Southern Cape. Designed the company’s website (www.cape-eaprac.co.za) and manage and maintain content.
October 2006 – June 2008 Previously one of the two senior Environmental Consultants at HilLand Associates in George in
the Southern Cape.
April 2004 – September 2006 Floor supervisor, retail assistant and receiving clerk at Wordsworth Books in George. Managing the family farm. Was employed on a contract basis by Capricorn Fisheries in Cape Town as an onboard observer
on commercial fishing vessels operating from St Helena Bay and Cape Town harbour.
P.O. Box 2035 George 6530 Cell: 084 584 7419 Fax: 044 874 0432 Email: [email protected]
Curriculum Vitae – Melissa Mackay
Page 2 of 2
2
2000–2004 Western Cape Nature Conservation Board Tourism Manager
Responsible for all CapeNature tourism related activities and management in the Overberg Region.
Tertiary
Education
2011 - 2013 Saasveld Campus, NMMU George Successfully completed a BTech Nature Conservation. Subjects completed include Conservation Management I, Research Methodology (with
Distinction), Resource Management IV, Plant Studies IV, Freshwater Management IV (with Distinction) and Coastal and Marine Management I.
1994–1996 Saasveld Campus, PE Technikon George Successfully completed a National Diploma Nature Conservation.
Short
Courses
Problem Animal Control, Kalahari 1994
Field Ranger Training, included plant id, animal tracking, orienteering, first aid and weapons training 1996
Client Care and Communication, Cape Town, 2001
Human Resources Workshop, Cape Town 2003
Skippers License (theory only), Bredasdorp, 2002
Law Enforcement, Bredasdorp, 2002
Microsoft Excel XP Advanced, Cape Town, 2003
Microsoft PowerPoint XP Advanced, Cape Town, 2003
Commercial Fish Identification off South African Waters, 2004
Observer Protocols on land and at sea, 2004
Introduction to International Fishing Law, 2004
Safety at Sea, 2004
Introduction to ArcGis II, 2007
NEMA 2006 EIA Regulations 2007
NEMA 2010 EIA Regulations 2010
Joomla Web Design Course
Business Report Writing, 2011
NEMA 2014 EIA Regulations, 2014
Bardolino Lifestyle Village MOS365
Cape EAPrac Environmental Management Programme
APPENDIX 11: EMERGENCY SERVICES &
CONTACT DETAILS
Emergency Response / Disaster Management 10177Eden Control Room 044 805 5055 Eden Fire Services 044 801 6376
Police 10111Mossel Bay SAPS (George Road) 044 690 3334
National Disaster Management (Cell phone) 112Disaster Management (Provincial) 021 937 0800Life Bay View Private Hospital 044 691 3718Provincial Hospital 044 691 2011Ambulance 044 691 3170ER 24 Private Ambulance Service 084 124Mossel Bay Municipality 044 501 3000
Emergency (All hours) 044 606 5000Fire & Rescue Services 044 691 3722
Traffic Department 044 606 5201Water & Electricity 044 606 5041Electricty Disruption (after hours) 044 805 5073Sea Rescue (Provincial) 021 449 3500
NSRI Station 15 082 990 5954Mossel Bay Surf & Life Saving Club 083 462 1182Southern Cross Life Saving Club 082 740 7654Mountain Rescue (Provincial) 021 948 9900
Andrew 082 339 1240Rogan 082 323 4349
Child Emergency 0800 123 321Citizens Advice Bureau 021 422 0300SPCA 044 693 0824CapeNature 044 802 5310Marine & Coastal Management 044 691 2939Heritage Western Cape 021 483 9685Department of Water & Sanitation: Water Pollution 0800 200 200
Mossel BayEmergency and Important Numbers