assessing the hydraulic transient performance of water and wastewater systems · pdf...

166
ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS USING FIELD AND NUMERICAL MODELING DATA by Djordje Radulj A thesis submitted in conformity with the requirements for the degree of Master of Applied Science Graduate Department of Civil Engineering University of Toronto © Copyright by Djordje Radulj 2010

Upload: hahanh

Post on 12-Mar-2018

229 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND

WASTEWATER SYSTEMS USING FIELD AND NUMERICAL MODELING DATA

by

Djordje Radulj

A thesis submitted in conformity with the requirements for the degree of Master of Applied Science

Graduate Department of Civil Engineering University of Toronto

© Copyright by Djordje Radulj 2010

Page 2: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

ii

Assessing the Hydraulic Transient Performance of Water and

Wastewater Systems Using Field and Numerical Modeling Data

Djordje Radulj

Master of Applied Science

Graduate Department of Civil Engineering

University of Toronto

2010

Abstract

A large proportion of water and wastewater systems have traditionally been analyzed and designed

without the consideration of the nature, risk, and potential consequence of hydraulic transients.

Recent advancements in numerical hydraulic modeling have spawned a specialty hydraulic field

based on numerical transient analysis. The current practice within this field often lacks physical

understanding and can be misguided by both the current knowledge, technology based limitations,

and by the sole reliance on numerical models. This thesis aims to provide insights into some of the

shortcomings of current practice and to develop the importance and application of field data based

confirmations. The thesis examines the advances in the current field oriented technology for

recording transient pressures, and provides examples and insights on how this data can be used both

in conjunction with numerical modeling and on its own as a first step to a proposed frequency based

transient risk assessment methodology. The thesis establishes definitions and a preliminary

methodology for a Transient Risk Index.

Page 3: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

iii

Acknowledgments

I have always appreciated a good and direct summary, and therefore please accept the following

form of acknowledgement to the individuals that have contributed to the completion of this work:

• Prof. Bryan Karney – for the opportunity, trust, time, technical guidance, and overall

flexibility.

• Prof. Barry Adams – for the quick, efficient and constructive review, and the initial pre-

thesis thought process inspiration.

• Direct and Indirect Contributors and Reviewers: Bryon Singh, George Illaszewicz,

Andrew O’Connor, Arash Alkozai, and Ahmad Malekpour – for all your contributions

(large and small) and overall support that made this a lot easier and more efficient.

• Fabian Papa – for the support, resources, and overall guidance and direction.

• My Family: Petar, Vesna and Sonja Radulj (and others…) – for your support behind the

scenes that made all of this significantly easier and obviously…possible.

• Brittany Dupak – for the constant reminders to just get it done; and for everything else in

life and this world.

Thank you all!

Page 4: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

iv

Table of Contents

Abstract .............................................................................................................................................................. ii

Acknowledgments .......................................................................................................................................... iii

Table of Contents ........................................................................................................................................... iv

List of Tables .................................................................................................................................................. vii

List of Figures ............................................................................................................................................... viii

Abbreviations .................................................................................................................................................... x

Chapter 1 Introduction ............................................................................................................................. 1

1.1 Background and Context ..................................................................................................................... 1

1.2 Significance of Topic ........................................................................................................................... 1

1.3 Organization .......................................................................................................................................... 2

Chapter 2 Overview of Hydraulic Transients ....................................................................................... 4

2.1 Definition and Overview ..................................................................................................................... 4

2.2 Type of Systems .................................................................................................................................... 6

2.2.1 Water Supply and Transmission Systems ............................................................................ 6

2.2.2 Water Distribution Networks ............................................................................................... 8

2.2.3 Wastewater Forcemain Systems.......................................................................................... 10

2.3 Risks Due to Transients .................................................................................................................... 10

2.3.1 Background ............................................................................................................................ 10

2.3.2 Traditional Risk Analysis ..................................................................................................... 12

2.4 Transient Protection Options and/or Equipment ........................................................................ 14

2.5 Hydraulic Transient Analysis Approaches ...................................................................................... 22

2.5.1 Do-Nothing ........................................................................................................................... 22

2.5.2 Rule-of-Thumb and Standard Convention ....................................................................... 23

2.5.3 Numerical Modeling ............................................................................................................. 25

2.5.4 Field Data and Investigation ............................................................................................... 28

2.5.5 Hybrid ..................................................................................................................................... 29

2.6 Summary .............................................................................................................................................. 30

Chapter 3 Current Analysis Shortcomings .......................................................................................... 31

3.1 Steady State Models ............................................................................................................................ 31

3.2 Average and Maximum Day Demands ........................................................................................... 34

3.3 Current Design Approach ................................................................................................................. 38

Page 5: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

v

3.3.1 Steady State Design Loads ................................................................................................... 39

3.3.2 Transient Modeling Approach ............................................................................................ 40

3.3.3 Wastewater Design Considerations .................................................................................... 44

3.4 Lack of Confirmation and Monitoring ............................................................................................ 47

3.4.1 Confirmation, Validation and Calibration ......................................................................... 48

3.4.2 Performance Monitoring ..................................................................................................... 50

3.5 Summary .............................................................................................................................................. 52

Chapter 4 Water Quality Issues ............................................................................................................. 53

4.1 Background ......................................................................................................................................... 53

4.2 Important Pathogens ......................................................................................................................... 55

4.3 Case Study and Discussion ............................................................................................................... 56

4.4 Summary .............................................................................................................................................. 59

Chapter 5 Advances in Field Work ...................................................................................................... 62

5.1 Traditional Field Work Approach .................................................................................................... 62

5.2 Modern Pressure Monitors and Comparison ................................................................................. 63

5.3 Pipetech TP-1 Transient Pressure Monitor .................................................................................... 72

5.4 Sample Data ........................................................................................................................................ 79

5.4.1 Long-Term Histories ............................................................................................................ 80

5.4.2 Individual Events .................................................................................................................. 87

5.4.3 Unique Events ....................................................................................................................... 92

5.5 Sample Statistics .................................................................................................................................. 96

5.5.1 Event Summaries .................................................................................................................. 96

5.5.2 General Event Statistics .................................................................................................... 100

5.6 Summary ........................................................................................................................................... 105

Chapter 6 Validation of Numerical Models ..................................................................................... 106

6.1 Case Study I: Region of Peel .......................................................................................................... 106

6.1.1 Background ......................................................................................................................... 106

6.1.2 Analysis ................................................................................................................................ 107

6.1.3 Discussion ........................................................................................................................... 113

6.2 Case Study II: Region of Durham ................................................................................................. 115

6.2.1 Background ......................................................................................................................... 115

6.2.2 Analysis ................................................................................................................................ 116

Page 6: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

vi

6.3 Case Study III: Mexico City ........................................................................................................... 120

6.3.1 Background ......................................................................................................................... 120

6.3.2 Analysis ................................................................................................................................ 120

6.4 Case Study IV: Wastewater Forcemain ........................................................................................ 123

6.4.1 Background ......................................................................................................................... 123

6.4.2 Analysis ................................................................................................................................ 124

6.5 Summary ........................................................................................................................................... 128

Chapter 7 Transient Risk Index ......................................................................................................... 129

7.1 Purpose and Background ............................................................................................................... 129

7.1.1 The Nature of System Failure .......................................................................................... 129

7.1.2 Pressure Class Design for Isolated Transient Events ................................................... 130

7.1.3 Pressure Class Design for Cyclic Loading ...................................................................... 131

7.1.4 Importance of Risk Assessment ...................................................................................... 132

7.2 Requirements, Parameters, and Definitions ................................................................................ 133

7.2.1 System and External Influences ....................................................................................... 133

7.2.2 Single Transient Event Parameters ................................................................................. 135

7.2.3 Multiple Transient Event Parameters ............................................................................. 137

7.3 Methodology .................................................................................................................................... 140

7.4 Sample Results ................................................................................................................................. 143

7.5 Discussion ........................................................................................................................................ 144

7.6 Summary ........................................................................................................................................... 147

Chapter 8 Summary and Conclusions ............................................................................................... 148

References .................................................................................................................................................... 151

Page 7: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

vii

List of Tables

Table 4-1: Air Valve Chamber Water Sampling Test Results ................................................................... 58

Table 5-1: Pressure Monitor Comparison Summary ................................................................................. 64

Table 5-2: Pressure Monitor Comparison Summary (cont’d) .................................................................. 65

Table 5-3: Transient Pressure Monitor Ranking for Long-Term Applications ..................................... 71

Table 5-4: Sample TP-1 Pressure Record Settings ..................................................................................... 77

Table 5-5: Unplanned Transient Event Summary – La Caldera PS (Mexico City) ............................... 98

Table 5-6: Transient Event Pressure Summary – Tlahuac/Mixquic Well Systems (Mexico City) ...... 99

Table 5-7: Detailed Event Summary – Region of Peel System .............................................................. 100

Table 5-8: General Short-Term Statistics – Tlahuac & Mixquic Wells (Mexico City) ........................ 101

Table 5-9: General Long-Term Statistics – La Caldera PS (Mexico City) ............................................ 101

Table 5-10: General Long-Term Statistics – Region of Peel System .................................................... 102

Table 5-11: Detailed Long-Term Statistics – Lakeview WTP (Region of Peel) .................................. 103

Table 7-1: Sample Pipe Pressure Class Properties (Mielke, 2004) ......................................................... 131

Table 7-2: Fatigue Load Factors for PE Pipe (PIPA, 2002) ................................................................... 132

Table 7-3: Single Transient Event Parameter Definitions ...................................................................... 136

Page 8: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

viii

List of Figures

Figure 2-1: Sample Water Transmission System (Mexico City) .................................................................. 7

Figure 2-2: Sample Water Distribution Network (Region of York) ........................................................... 9

Figure 2-3: Traditional Transient Analysis Solution Approaches ............................................................ 27

Figure 3-1: Wave Velocity v. Air Content (Wylie and Streeter, 1993) ..................................................... 46

Figure 3-2: Sample Vapour Pressure Sensitivity Analysis for a Wastewater System ............................. 47

Figure 4-1: Air Valve Chamber Water Sampling Locations ..................................................................... 57

Figure 4-2: Air Valve Chamber Water Sampling Test Result Comparison ............................................ 58

Figure 4-3: Comparison of Total Coliform Concentrations ..................................................................... 60

Figure 4-4: Comparison of E. coli Concentrations .................................................................................... 60

Figure 4-5: Comparison of Enterococci Concentrations .......................................................................... 61

Figure 4-6: Comparison of Clostridium Perfringens Concentrations ..................................................... 61

Figure 5-1: TP-1 Transient Pressure Monitor Components ..................................................................... 73

Figure 5-2: Typical TP-1 Installation in the Field ...................................................................................... 73

Figure 5-3: Sample Calibration Pressure Profile ......................................................................................... 75

Figure 5-4: TP-1 Pressure Monitoring Equipment Settings ..................................................................... 76

Figure 5-5: Pressure v. Time Plots for Different TP-1 Settings ............................................................... 78

Figure 5-6: Pressure v. Time Plots for the Same Event but with Different Time Scales ..................... 79

Figure 5-7: Sample Transient Pressure History – Hanlan PS (Region of Peel) ..................................... 81

Figure 5-8: Sample Transient Pressure History – Lakeview WTP (Region of Peel) ............................. 82

Figure 5-9: Sample Transient Pressure History – Glen Cairn PS (City of Ottawa) .............................. 82

Figure 5-10: Sample Transient Pressure History – La Caldera PS (Mexico City) – 2 Months ............ 83

Figure 5-11: Sample Transient Pressure History – La Caldera PS (Mexico City) – 2 Days ................. 84

Figure 5-12: Sample Transient Pressure History – Mixquic Well No. 13 (Mexico City) ...................... 84

Figure 5-13: Sample Transient Pressure History – Ajax WSP (Region of Durham) – 3 Months ....... 86

Figure 5-14: Sample Transient Pressure History – Ajax WSP (Region of Durham) – 3 Days ............ 86

Figure 5-15: Typical Pump Start-Up – Ajax WSP (Region of Durham)................................................. 88

Figure 5-16: Typical Pump Shut-Off – Ajax WSP (Region of Durham) ................................................ 88

Figure 5-17: Typical Pump Shut-Off at High Point – La Caldera Pipeline (Mexico City) ................... 89

Figure 5-18: Typical Pump Switch – Harwood PS (Region of Durham) ............................................... 89

Figure 5-19: Power Failure Event without Upsurge – Ajax WSP (Region of Durham) ...................... 91

Figure 5-20: Power Failure Event with Upsurge – Hanlan PS (Region of Peel) ................................... 91

Page 9: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

ix

Figure 5-21: Multi Pump Shut-Off, From 2 to 1 to 0 Pumps – La Caldera PS (Mexico City) ............ 92

Figure 5-22: Complete System Shutdown – La Caldera PS (Mexico City) ............................................. 93

Figure 5-23: Single Well Shutdown – Mixquic Well No. 4 (Mexico City) .............................................. 93

Figure 5-24: Progressive Check Valve Failure – La Caldera PS (Mexico City) ...................................... 95

Figure 5-25: Distribution System PRV Adjustment – North Richmond Hill PS (Region of York) .. 95

Figure 5-26: Pump Control Logic Change – Montreal Road PS (City of Ottawa) ............................... 96

Figure 5-27: Sample Cumulative Pressure Distribution – Lakeview WTP (Region of Peel) ............. 104

Figure 6-1: Model v. Field Event Pressure Validation – Streetsville PS (Region of Peel) .................. 110

Figure 6-2: Model v. Field Event Pressure Validation – MV900 Chamber 8 (Region of Peel) ........ 110

Figure 6-3: Model v. Field Event Pressure Validation – Hanlan PS (Region of Peel) ........................ 111

Figure 6-4: Model v. Field Event Pressure Validation – BS1500 Chamber 8 (Region of Peel) ........ 111

Figure 6-5: Model v. Field Event Pressure Validation for 2 Pumps – Hanlan PS (Region of Peel) . 112

Figure 6-6: Model v. Field Event Pressure Validation for 2 Pumps – BS1500 (Region of Peel) ...... 112

Figure 6-7: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 1 .. 117

Figure 6-8: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 2 .. 119

Figure 6-9: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 3 .. 119

Figure 6-10: Model v. Field Comparison (2 Pump to 1 Pump) – La Caldera PS (Mexico City) ....... 122

Figure 6-11: Model v. Field Comparison (1 Pump to 0 Pumps) – La Caldera PS (Mexico City) ..... 122

Figure 6-12: Model v. Field Comparison (2 Pumps to 0 Pumps) – La Caldera PS (Mexico City).... 123

Figure 6-13: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 1 ..................... 125

Figure 6-14: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 2 ..................... 126

Figure 6-15: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 3 ..................... 127

Figure 6-16: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 4 ..................... 128

Figure 7-1: Single Transient Event Properties & Parameters ................................................................. 135

Figure 7-2: Multiple Transient Event Properties & Parameters ............................................................. 138

Figure 7-3: Transient Risk Index Schematic ............................................................................................. 141

Figure 7-4: Sample Preliminary TRI Graph for the Lakeview Zone 1 and 2 Systems ....................... 144

Page 10: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

x

Abbreviations

AC Air Chamber

ADD Average Day Demand

ARV Air Release Valve

ANSI American National Standards Institute

ASCE American Society of Civil Engineers

ASME American Society of Mechanical Engineers

ASTM American Society for Testing and Materials

AV Air Valve

AWWA American Water Works Association

AWWARF American Water Works Association Research Foundation

BPS Booster Pump Station

CAV Combination Air Valve

CPP Concrete Pressure Pipe

DI Ductile Iron Pipe

DWF Dry Weather Flow

EPS Extended Period Simulation

FSI Fluid Structure Interaction

GIS Geographic Information System

GMT Greenwich Mean Time

GPS Global Positioning System

HAC Hydro-Pneumatic Air Chamber

HB Horizontal Bend

HDPE High Density Polyethylene Pipe

HGL Hydraulic Grade Line

HLPS High Lift Pump Station

HP High Point

I&I Inflow and Infiltration

LAN Local Area Network

LLPS Low Lift Pump Station

LP Low Point

MDD Maximum Day Demand

Page 11: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

xi

MHD Minimum Hour Demand

MLD Mega Litres Per Day

MOC Method of Characteristics

MRI Moment of Rotational Inertia

O&M Operations and Maintenance

OWWA Ontario Water Works Association

PDA Personal Digital Assistant

PHD Peak Hour Demand

PVC Polyvinyl Chloride Pipe

PS Pump Station

Pv Full Vacuum Pressure Limit

Pw Working Pressure

RPM Revolutions per Minute

SAV Surge Anticipation Valve

SCADA Supervisory Control and Data Acquisition

SD Standard Deviation

SPS Sewage Pumping Station

SRV Surge Relief Valve

TDH Total Dynamic Head

TP-1 Transient Pressure Monitor Unit

TransAM Transient Analysis Model

TRI Transient Risk Index

USB Universal Serial Bus

UPS Uninterruptible Power Supply

VFD Variable Frequency Drive

VB Vertical Bend

Vp Vapour Pressure

WCM Wave Characteristics Method

WDS Water Distribution System

WTP Water Treatment Plant

WSP Water Supply Plant

WWF Wet Weather Flow

WWTP Wastewater Treatment Plant

Page 12: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

1

Chapter 1 Introduction

1.1 Background and Context

The title of this thesis, “Assessing the Hydraulic Transient Performance of Water and Wastewater

Systems Using Field and Numerical Modeling Data” is rather long and appears to be

comprehensive. The reason for this is primarily the fact that the document covers a wide range of

issues pertaining to hydraulic transients in water and wastewater systems. Nonetheless, the core and

unifying theme of this work is the benefit of, and the need for, an increase in hydraulic transient

based field work. The goal of such field work is to fill-in the gaps that currently exist in numerical

modeling, and to subsequently and concurrently improve the long-term performance of water and

wastewater systems.

The content of this work derives from a strong academic interest and influence, but also from direct

industry experience. The goal of the thesis is to demonstrate the current shortcomings in the

industry’s approach to addressing transients, and to blend the current (and often practical) needs of

industry with recent technological advances and academic research. This thesis aims to provide

context for these issues, as well as to establish a road map for several key and important topics

within the realm of numerical and field hydraulic transient data. This thesis does not aim to provide

an extensive discussion and an answer to all of the individual topics, but rather aims to show how

each topic plays an integral role in the analysis process and the assessment of overall system

performance.

1.2 Significance of Topic

The topic of hydraulic transients falls within the field of hydraulics and water resources, which in

turn falls within the more general field of environmental engineering. From this hierarchal point of

view, environmental engineering explicitly focuses on improving the welfare of society in the areas

pertaining to the environment and the planet. Water and wastewater are essential engineering

components of the present society, and the branch of hydraulics is an important field that addresses

the physical challenges of engineering such systems.

Page 13: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

2

While technically and academically challenging, hydraulic transients comprise a small proportion of

all hydraulic based studies. This is mostly due to their rare and relatively minimal impact (in

comparison to other tasks) on the overall analysis and design time and cost of an engineering

project. However, from the point of view of a water and wastewater system’s performance,

efficiency and safety, and from the point of view of the potential cost implications to both a system

owner and society, hydraulic transients are extremely important and often overlooked.

The task of performing a hydraulic transient analysis as part of all hydraulic system designs has only

recently been widely accepted, but with this acceptance also comes an increase in physical

misunderstanding, malpractice and carelessness. The sole reliance by engineers on hydraulic models

built by others has proven to be dangerous, and the lack of attention to both the details of analysis

as well as to the real life (i.e., in-situ) systems is troublesome. The focus of this thesis is to address

many of these troubling issues and to provide context on why they are important and on how they

can be improved. To that end, the overall importance of the topic should be relatively clear.

1.3 Organization

As noted earlier, this thesis is a collection of important and relatively specialized topics on hydraulic

transients; topics that focus on assessing the hydraulic transient performance of water and

wastewater systems. Each of the chapters in this document aims to provide a practical discussion of

the relevant topic, such that the advances in technology and academia can actually be readily

implemented in the industry.

Chapter 2 overviews hydraulic transients and hydraulic transient analysis and then moves towards a

brief discussion of the different types of hydraulic systems. The chapter provides context on this

topic, by considering the risks, protection options and analysis approaches.

Chapter 3 provides a critical assessment of current practice, through the focus on the shortcomings

of numerical models, assumptions, and analysis/design approaches. The chapter reaffirms the

importance of field observations.

Chapter 4 takes a brief aside from assessing hydraulic transients, and continues along the path of

field investigation to bring light to the water quality concerns that are associated with negative

Page 14: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

3

pressures. This chapter summarizes a field study regarding the pathogen intrusion risks in air valve

chambers during negative transient events.

Chapter 5 directs its focus on the core of the thesis topic – the advances and uses of transient

pressure monitoring technology. The chapter ultimately summarizes the transient pressure data and

statistics acquired through several case studies.

Chapter 6 proceeds to expand on the previous chapter by introducing and comparing numerical

modeling results to the actual field results, thereby leading to the idea and practice of model

validation and/or calibration. The chapter relies on several case studies that bring light to some of

the main issues in the validation of numerical transient models.

Chapter 7 develops the methodology for a preliminary transient risk index; an index that can be used

to assess the hydraulic transient risk of a water (or wastewater) system using continuous transient

pressure monitoring. It provides the necessary transient pressure recording logic and transient event

definitions, as well as the type of improvements required to formally implement such an approach.

Chapter 8 summarizes the conclusions from the thesis and the research to-date, and reaffirms the

contributions of this work towards both research and industry practice.

Page 15: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

4

Chapter 2 Overview of Hydraulic Transients

2.1 Definition and Overview

Hydraulic transients have traditionally been referred to as water hammer and in some cases as

pressure or hydraulic surges. Presently, these non-steady pressure events are more often than not

referred to as hydraulic transients, and the act of performing a representative analysis (and design) is

therefore referred to as a hydraulic transient analysis, or in a simpler form, a transient analysis. Such

an analysis is typically performed in order to determine the overall risk due to transients and to

provide recommendations on how this overall risk can be minimized and/or possibly eliminated.

A hydraulic transient analysis can be performed on any fluid system, but it is the fluid and the type

of system that determines the appropriate analysis method. Some examples of fluid systems that

often require a transient analysis include:

• Water supply and transmission systems;

• Water distribution networks;

• Pressurized wastewater systems (e.g., forcemains);

• Wastewater effluent systems;

• Combined (surcharged) sewer systems;

• Oil and gas pipelines;

• Hydroelectric plants;

• Open channel flow systems (e.g., rivers and streams);

• Jet fuel distribution systems;

• Steam, heating and cooling pipelines;

• Well and groundwater systems.

This document focuses on the impact and application of hydraulic transients in water and

wastewater systems, and in particular, to large scale municipal systems. According to Chaudhry

(1987) and to McInnis and et al. (2004), a non trivial physical distinction can be made between three

types of water and wastewater systems: closed conduit or pressure pipe systems, open channel

Page 16: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

5

systems with a free surface, and combined systems with regions of free surface and pressurized flow

(i.e., mixed systems). While the latter two are indeed fascinating and challenging topics, this

document focuses on closed conduit pressurized water and wastewater systems because of their

widespread existence and unique physical challenges/attributes.

In the context of closed pressurized systems, hydraulic transients are the means by which pressures

and flows are adjusted. In basic terms, transients mark transitions between steady state conditions,

and such transitions are the source of the special attention. The transition from a steady state

condition (i.e., a condition in which the key parameters do not change significantly over time) can be

smooth or rough, predictable or unexpected, and most importantly, it can subject a system to a high

level of stress and an increased risk of failure. In fluid systems, these changing parameters (or

variables) are mostly flow and pressure. As a general principle, the rate that a fluid enters a pipe

segment must be equal to the rate that it leaves this same segment, or else an accumulation of fluid

would result. Furthermore, steady state condition is achieved by the equilibrium of three key

physical quantities: force, momentum, and energy.

During a transient event the fluid inflow or outflow in some part of the system is disturbed via a

change in, or addition of a boundary condition, and this leads to a local imbalance that allows mass

to accumulate or deplete. Such an imbalance in pressurized flow can only be accommodated

through two components: fluid compressibility and pipe extension. However, since fluids like water

are not easily compressed, and since pipelines do not easily expand, this imbalance typically results in

large pressure forces. The pressure forces are translated into pressure waves, and these pressure

waves propagate through the system. The rate of pressure wave propagation is rather quick,

typically between about 250 and 1250 m/s. This fluid and system property is often termed

wavespeed or wave celerity, and its exact value depends on the compressibility of the fluid and the

elastic properties of the pipe. The resulting transient pressures, which can be both positive

(upsurge) or negative (downsurge) are then superimposed on the existing steady state system

pressures. If the system is not capable of handling these pressure magnitudes or changes, then it is

subjected to a higher risk of failure. Eventually, the energy (strain and kinetic) resulting from the

pressure waves dissipates and decays due to the friction in the system, and ultimately establishes a

new steady state condition.

Page 17: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

6

2.2 Type of Systems

The following subsections further define and distinguish three types of important closed pressure

systems that are often the subject of a transient analysis. The systems types are:

1. Water Supply and Transmission Systems;

2. Water Distribution Networks; and

3. Wastewater Forcemain Systems.

The goal of these subsections is to briefly illustrate the hydraulic differences between these systems,

and to bring attention to important considerations for a hydraulic transient analysis and design.

2.2.1 Water Supply and Transmission Systems

Water supply and transmission systems have traditionally been a key area of focus for hydraulic

engineers, through the typical tasks of investigation, analysis and design. Most great urban areas

were developed in proximity to a water source such as a lake, river, groundwater aquifer, and/or

ocean. However, due to constraints such as unfavourable topology, distance, etc., the water supply

sources and the consumers often required a strong engineering link; a link achieved through

dedicated water transmission systems. Water transmission systems have become even more

prevalent and important in the modern era, as existing and new communities search for additional

water sources.

Water transmission systems generally comprise long and large conduits that transfer raw or treated

water from the source location, to another location closer to the population or urban area. In such a

case, the source location may be an actual water source, or an intermediate reservoir, water

treatment plant (WTP), etc. Similarly, the ultimate discharge point can be a reservoir, WTP,

distribution system, pump station, etc. The transmission conduits have historically been dedicated

conveyance systems, and therefore without many connections or interconnections. These

conveyance systems can include: pumped pipeline systems, pressurized gravity systems, or free

surface gravity conveyance systems. These large diameter conduits are typically referred to as

transmission mains, feedermains, or pipelines, rather than watermains – a term which is typically

reserved for small diameter water pipes only.

Page 18: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

7

Water supply and transmission systems are designed to overcome any elevation differences (i.e.,

static head) and head losses (e.g., due to appurtenances and friction). In such systems, the head loss

due to the friction of the pipe often governs the hydraulics. The limiting design of a dedicated

transmission system is typically the maximum velocity of the fluid (e.g., about 2 m/s), and this

limitation therefore often leads to a significant size requirement. As an example, the regional area of

greater Mexico City, which boasts a population of nearly 20 million, partially relies on a water

transmission system by the name of the Cutzamala Aqueduct. This system, which is pictured in

Figure 2-1, comprises two parallel 2500 mm gravity pipelines, and conveys water over a distance of

150 km from the Cutzamala River Basin to Mexico City. This large scale water transmission system

is operated within a flow range of 10 to 20 m3/s – or in other words, a large quantity of water.

Figure 2-1: Sample Water Transmission System (Mexico City)

The nature and risk of hydraulic transients in water transmission systems is system specific, but the

general characteristics depend on whether the water is pumped or delivered via gravity. In general,

pumped systems are subject to the risk of pump station based flow adjustments, including pump

trips, power failures, valve operations, etc. Gravity systems are mostly at risk from poor valve

operational protocols and control. The key distinction between a pure or dedicated water

transmission system and some of the other types of water and wastewater systems is the continuity

of the transient induced pressure wave. Pressure waves travel back and forth along the dedicated

conveyance line(s) with little or no fragmentation and/or dissipation. The transient pressure waves

Page 19: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

8

(and therefore their magnitudes) are relatively easy to predict if the other system properties (e.g.,

friction factors, flow rates, etc.) are known with some level of certainty.

A subset of a water transmission system is a water collection system. Such a system collects raw

water from multiple wells and well fields and conveys it to a holding reservoir or WTP. While these

systems typically contain many branched transmission lines, they are less isolated, and therefore the

typical transient conditions and risks are slightly different. The difference comes in the form of the

potential pressure wave origin (i.e., due to multiple well pumps), pressure wave propagation

direction, and the amplification potential due to the presence of branched dead ends.

Transmission systems are not only present in rural and inter-basin transfer areas such as the one

shown in the previous Mexico City example, but also in dense urban areas such as first world

metropolitan centres. In these systems, dedicated transmission pipelines are used to transfer treated

water from a lower pressure zone to a higher pressure zone and from one pump station to the next.

In such a case, the transmission pipelines are typically of the pumped variety, and at times can be

interconnected to the local water distribution networks.

2.2.2 Water Distribution Networks

Water distribution systems and water transmission/supply systems have a lot of properties in

common. First, they obviously convey water that is ultimately directed for consumption. Second,

both of these systems are exposed to the risk of hydraulic transients, even if transients are explicitly

considered and designed for. On the other hand, these two types of water systems also have

significant and distinctive differences when it comes to both their physical characteristics and the

response to such hydraulic transient based risks.

Water distribution systems are typically defined as smaller scale potable water systems that comprise

a network of pipes. Due to the health requirements arising from direct consumption, the potable

nature of the fluid media necessitates that these types of systems be of the pressurized variety. In

most distribution systems the requirements of maintaining a certain level of pressure necessitates the

reliance on pumped systems. The reliance on pumps acts to introduce additional boundary

conditions, which if altered, can act to introduce additional transients and risks to the system.

Page 20: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

9

Water distribution systems typically contain pump stations or booster pump stations, more

complicated networks (loops or branches) of smaller diameter pipe (e.g., 400 mm or less), service

connections to ultimate consumers (e.g., households, industry, etc.), storage elements (e.g., tanks or

reservoirs), and additional appurtenances (e.g., flow control valves, fire hydrants, etc.). Figure 2-2

presents a typical layout of a part of a water distribution system in a large metropolitan area.

Figure 2-2: Sample Water Distribution Network (Region of York)

The increased complexity of a distribution system makes the hydraulic transient response much

different, and more difficult to ascertain or predict directly. Unlike transmission systems that

contain a small number of pipes and boundary conditions (and therefore a relatively small number

of possible sources of transients), distribution systems are by their very nature hydraulically complex.

In these systems, transient risks can arise from a variety of sources, including those pertaining to

supply, conveyance and demand. Fortunately, the complexity of these systems is often beneficial

when it comes to their transient based response. This is because complex pipe networks act to both

fragment and dissipate transient pressure waves, through both additional frictional sources and flow

paths. The overall character and magnitude of water distribution system transients is dependent on

a host of factors, including the amount of storage, the interconnectivity of the network and the

system demand relative to the supply and conveyance capacity. Overall, while these types of systems

are similar to water transmission systems, they should undoubtedly be treated differently from the

point of view of both hydraulics and hydraulic transients.

Page 21: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

10

2.2.3 Wastewater Forcemain Systems

Wastewater systems come in many forms and varieties, and therefore their hydraulic properties can

significantly vary. Wastewater operations and flows range from those that are driven by gravity in

open channels to those that are fully pressurized in closed conduits, and with intermediaries which

are referred to as mixed flow regimes. While the latter two of these are hydraulically interesting,

their hydraulic transient response is significantly different than those of water transmission and

distribution systems, and will therefore not be considered as part of this thesis.

Pressurized wastewater systems can be closed conduit or open channel, the former of which is more

commonly referred to as wastewater (or sewage/sanitary) forcemain systems. These systems are

hydraulically similar to water transmission systems in that they typically comprise one or two

dedicated pipelines (forcemains) that convey the fluid from a pump station to a downstream

receiving location such as a sanitary sewer manhole, outlet, treatment plant or another pump station.

These systems can often include a limited number of pump stations and branch forcemains. Most

wastewater forcemain systems are installed in areas in which the topography precludes the use of

gravity driven sanitary sewers, and in many instances, these pumped systems work against a relatively

low static head and mostly act to overcome the frictional head loss.

The risk due to hydraulic transients in wastewater forcemain systems is relatively similar to those of

water transmission systems. These risks mostly arise due to changes in boundary conditions such as

those arising from pump failures or line filling, or due to other unplanned events such as forcemain

breaks or premature air valve closure. For additional detail on wastewater forcemain design

considerations, please refer to Section 3.3.3.

2.3 Risks Due to Transients

2.3.1 Background

There are two main reasons why system owners should care about hydraulic transients. First, the

magnitude of the high and low pressures associated with transient events is often large enough to

cause serious damage to system components, devices and pipeline segments. Second, but just as

important, these transient pressure fluctuations can be controlled and managed by reasonable and

Page 22: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

11

strategic investment in a surge protection system and through logical and controlled system

operation.

Any hydraulic transient analysis and design, whether achieved via modeling or field work, should

always consider both the positive (upsurge) and negative (downsurge) pressure potential. Only a few

surge protection devices can actually mitigate both of these transient pressure risks, and therefore an

understanding of their limitations is required. The positive pressure concerns have traditionally been

the dominant concern because of the obvious connection between unexpectedly high pressures and

pipe/component failure. However, negative transient pressures, especially those that are sub-

atmospheric (i.e., partial or full vacuum), should also be avoided in order to:

i) Minimize the added stress on the pipes, fittings, and devices;

ii) Reduce the magnitude of any reflected positive pressures (i.e., return upsurges);

iii) Prevent the formation of vapour cavities that can collapse and lead to significant

positive pressure transients;

iv) Minimize fatigue stresses on the pipe that can lower the ultimate strength of the

pipe and allow future upsurges to cause a break;

v) Prevent the possibility of an ‘intrusion event’ that can lead to a public health risk

and/or to the drawing in of contaminated water and/or soil particles;

vi) Prevent a partial or full pipe collapse due to vacuum conditions that would lead

to significant leakage, service disruption and/or loss of capacity;

vii) Prevent the potential wear and tear on the inside mortar and liners of pipes, as

well as on gasket and other joint elements; and

viii) Minimize the propagation of small cracks or breaks that can increase leakage and

therefore reduce the economic performance and overall efficiency of the system.

Negative transient pressures are often difficult to completely eliminate, but in most water and

wastewater systems their duration should be reduced and minimized. In that sense, it is often the

product of the negative pressure magnitude and its duration that should be minimized.

Transient events in typical water and wastewater systems occur as a result of any flow change or

disruption, and these changes are often brought on due to a change in a boundary condition. The

Page 23: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

12

following is a partial list of events that can induce transient pressure fluctuations and subject a

system to a high stress (and potential failure):

• Power failure event that causes a pump to trip (i.e., turn off);

• Power failure event that causes an automated valve to suddenly close or open;

• Rapid change in the water level of a storage element such as a reservoir or tank;

• Pipeline (watermain, forcemain, etc.) break or failure;

• Improper operation of a fire hydrant;

• Mechanical failure of a pump or valve;

• Rapid expulsion of air through an air valve, or, indeed, any other valve;

• Rapid valve closure or opening;

• Constant speed pump start-up against a fully open valve;

• Premature or rapid check valve closure (i.e., slam)

• Repetitive valve cycling (i.e., chattering);

• Rapid filling or draining of a pipeline;

• Surge protection device failure; and

• Excessive fluid discharge via a surge device.

Managing the risk of hydraulic transients requires assessing the threat and assigning appropriate

protection measures. It requires the analysis of all the different events that can cause transients, and

the estimation of the consequences of their failure. The following subsection outlines the traditional

methodology for such an assessment, while the subsequent chapters further elaborate on some of

the shortcomings of a typical hydraulic transient analysis.

2.3.2 Traditional Risk Analysis

In its simplified mathematical form risk is a product of the probability of a negative (from the

perspective of the system) event occurring, and the subsequent consequences of such an event.

Despite its mathematical nature, risk is often subjectively assessed and defined. Given the number

of factors involved in a total or performance based failure of water and wastewater systems, it is

often quite difficult to isolate a single causal event and equally as difficult to directly link specific

events to consequences. Therefore, the term risk itself only provides an indication of possibilities

Page 24: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

13

rather than a certainty in the outcome. Rowe (1979) defines risk as the “potential for the realization

of unwanted consequences from impending events”.

From the point of view of hydraulic transients, risk is similarly often subjectively described due to

the uncertainties in quantitatively predicting the probability of occurrence and the impact of the

consequence. In other words, the potential worst-case consequence of a specific transient event is

understood, but the probability of such an event occurring and the likelihood that it will combine

with other factors to yield the worst-case consequence, is difficult to quantitatively predict. As such,

traditional transient risk assessments often take the form of scenarios or risk-consequence matrices.

Although risk assessment of hydraulic transients is informally performed via a transient analysis, its

traditional methodology is scenario and surrogate based. Consideration is rarely given to a

comprehensive risk analysis of all transient events, and how such a combination can lead to a system

or performance failure. Thorley (2004) outlined a twelve step systematic methodology for assessing

and managing transient risks in hydraulic systems. This type of methodology must act to address

questions such as:

1. What impending events could give rise to these situations?

2. What is the probability that they will occur?

3. Does it matter?

4. If so, what can be done about them?

The problem with the above questions (and associated qualitative methodology) is two-fold. First,

questions 2 and 3 can rarely be answered in a quantitative manner, as the frequency of occurrence

(i.e., loading) and the consequence are not only difficult to determine, but are also rarely a function

of only hydraulic transients. Second, the methodology is driven by a single worst-case event, and

disregards the joint impact of many different transient (and non-transient) events and/or causes.

Other authors such as Lee et al. (2009), Fleming et al. (2005), and Kirmeyer et al. (2001), have

focused on specific risks from hydraulic transients such as intrusion during low pressure events. In

such cases, the specific risks were indeed correlated to the probability of occurrence and the

consequence. Furthermore, the risks were attributed to a few system parameters and/or metrics.

The best quantitative risk analysis in this field of study can likely be attributed to the traditional

Page 25: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

14

fatigue analysis of plastic pipes (e.g., PVC, HDPE, etc.). In such an analysis (and resulting design

standard), the consequence in the form of a plastic pipe failure is directly tied to the frequency and

magnitude of pressure loading (both normal operating and transient). In other words, the

acceptable loading conditions are defined by the magnitude and number of pressure cycles (see

Bowman 1990 and Jeffrey et. al 2004). In the realm of CPP pipe, risk assessments of pipe failures

can directly be tied to the operating pressure regime, the frequency and magnitude of transient

pressures, and the current condition of the pipe (e.g., with the assistance of a wire break condition

assessment and analysis). Zarghamee and Fok (1990), and Zarghamee et al. (2003), developed a

finite element model that correlates a variety of the above mentioned external parameters, and

provides a quantitative risk analysis via potential failure curves and limit states. Chapter 7 describes

some of these quantitative risk analysis methodologies in more detail, and ultimately proposes a field

data derived and index based transient risk assessment of existing systems.

While the difficulty of performing a transient risk assessment has been briefly discussed above, it is

equally, if not more important to address Thorley’s last question on what can be done to minimize

any such risk. Once an analysis is performed and some form of transient risk has been identified,

the next step is to make design and/or operational modifications in order to reduce the consequence

of any such event(s). The following section provides a discussion on the typical options for

transient protection, both in the form of devices/equipment, and specific design strategies.

2.4 Transient Protection Options and/or Equipment

The direct (or traditional engineering) approach to hydraulic transient protection is commonly

understood from a physical perspective as it relies on the design and installation of dedicated surge

protection equipment and/or devices. However for the most part, the current practice relies on

rules-of-thumb and is based on a narrow selection of options. A proper transient protection design

should consider all possible options, and these options should then be narrowed down to a few that

are applicable in the system. The few remaining options should then be analyzed in detail across

several criteria. This section summarizes a partial list of typical surge protection options and

approaches that should at least be preliminarily considered during a design and/or upgrade of a

water (and to some extent wastewater) system. As noted in the previous section, not all equipment

and approaches target the same (or all) hydraulic transient concerns, and hence there exists a clear

trade-off between performance, applicability and ultimately cost.

Page 26: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

15

1. Do-Nothing (i.e., dealing with the consequences as they occur)

This strategy requires no initial or dedicated investment in surge protection or control, but may

accumulate greater costs in maintenance and repair of system components damaged from transient

events. Since every pipeline system is unique it may be the case that for some systems a do-nothing

approach is valid given the nature of the system.

2. Improved Operation and Training (i.e., learning to use the system more gently)

Includes practices such as slowly opening and closing valves and highly controlled ramp-ups and

shutdowns of pumps. Transients arise from imbalances between flow entering and leaving a pipe

segment. Any system operation that quickly changes flow conditions can induce a transient. Gentle

system operations allow flow to gradually change in the pipeline thereby minimizing any imbalance

in flow. This is particularly relevant to filling, draining and valve operations.

3. Increased Pipe Strength and Rating

Increased pipe rating is a protection strategy that is relevant to proposed systems and systems where

a pipe break has occurred and needs to be repaired. As the name suggests, this strategy involves

choosing a pipe with a working pressure rating strong enough to safely withstand the maximum

theoretical transient pressures. Even though most pipes have an ultimate strength greater than the

rated working strength, it is best practice not to encroach upon this built-in factor of safety.

Implementation of the strategy assumes that the transients will be handled by the pipe only.

4. Less Rigid Pipes (Lower Wave Celerity)

The maximum and minimum theoretical change in head produced by a sudden transient event is

directly proportional to the wavespeed. The wavespeed is the sonic velocity of a liquid flowing

through a pipe and is a function of the pipe wall elasticity. Rigid pipes have greater wavespeeds than

less rigid pipes. As such, the theoretical maximum and minimum transient pressures can be greater

for rigid pipes than for flexible pipes if all else is the same. However, reality is often more complex

than this simple rule would imply.

5. Surge/Pressure Relief Valves

These types of valves are designed to automatically open at a predetermined high pressure setting.

Springs, counterweights or automatic hydraulic pilots can be used to set the opening pressure. The

Page 27: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

16

release of water (to the atmosphere, suction line or well/reservoir) can alleviate excessively high

pressures in a pipeline.

6. Surge Anticipation Valves

Surge anticipation valves function the same way as surge relief valves except that they are designed

to open at a predefined low pressure setting in anticipation of a returning upsurge. If the valve cycle

of opening and closing are properly set, the valve will be completely open in time for the transient

upsurge, and then close slowly when the pressure drops to normal. This type of valve must be used

with caution because they have been known to make low pressures situations worse.

7. Rate of Rise Surge Anticipation Valves

These types of valves are often confused with the surge anticipation valves because their goal is to

anticipate an upsurge. These valves are designed to sense a rapid increase in pressure as the surge

wave returns and to open fully with no stroke limiters on the valve opening. It must be ensured that

the valves open fast enough on rate of rise to be fully open when upsurge arrives.

8. Automatic Air Release (Outflow) Valves

Automatic air release valves are placed at points in the pipeline where air can accumulate, be it

significant high points or rapid changes in pipe slope. They are designed to automatically open and

release trapped air, and to close again once the pipe is full of water. Even though they do not

necessarily offer direct transient protection they can have an impact on transient performance. If

the air is expelled too quickly a phenomena known as “air slam” may occur as the water column

rejoins.

9. Automatic Air Vacuum or Vacuum Breaker (Inflow) Valves

An air vacuum valve opens automatically when the internal pipe pressure drops to atmospheric

pressure. This valve allows air to enter the pipe thereby providing protection against possible pipe

collapse caused by negative pressures.

10. Automatic Combination Air Valves

Combination air valves contain both an air release component and an air vacuum component. This

type of valve can expel trapped air in a pipeline, as well as to allow the air to both enter a pipeline if

Page 28: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

17

the pressures drop below atmospheric and to leave once the pressures rise above atmospheric.

These valves come in many configurations, including single and dual body designs.

11. Automatic 3-Stage or Non-Slam Air Valves

Three stage air valves operate similarly to conventional air valves except that air is released through

two increasingly smaller orifices. This three stage release of air is designed to reduce the occurrence

of “air slam” in the valve and/or pipeline. These valves include a high capacity air release and

vacuum breaking capability together with a specifically designed anti-shock orifice to provide

controlled air release during the critical moments prior to the elimination of the remaining air

pocket. Variations on the non-slam design exist.

12. Conventional Check Valves

Check valves are designed to allow flow to travel in one direction only. The simplest forms include

a flap that closes under its own weight. Conventionally, they are primarily placed downstream of a

pump to prevent backflow when the pump is not in service. One benefit of a check valve is that it

prevents line draining. From a transient perspective this is beneficial because it can reduce transients

at pump start-up.

13. Dampened Check Valves

Dampened check valves are also known as slow closing or surge check valves. When a pump fails

and flow reverses, a properly functioning check valve will close to prevent backflow. If the closure

is too abrupt, then the valve slams, therefore creating another possibly dangerous transient event for

both the system and the valve itself. The goal of these types of valves is to minimize or eliminate

this undesirable event. These valves come in many forms including spring-loaded, tilted disk and

swing flex.

14. Dashpot Controls

Dashpots are the mechanisms that control check valve closure and prevent slamming. They usually

consist of a rod and hydraulic cylinder. An air and oil reservoir is utilized to provide return force for

the rod when the valve is closing. This ensures a more controlled valve closure through the

provision of a cushion.

Page 29: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

18

15. Pressure Regulating Valves

Not to be confused with pressure reducing, relief or sustaining valves, these types of valves are used

to throttle the flow during pump start-ups. The goal of a pressure regulating valve is minimize the

operation of a pump at a point on the pump curve corresponding to a high flow and a low (or zero)

head. In doing so, these valves allow the flow to establish and therefore minimize the transients

associated with events such as line filling.

16. Valve By-Pass Lines

Large in-line valves are often difficult to control especially when they are almost closed. Such

problems can be minimized by the addition of one or two smaller valves mounted in a parallel by-

pass orientation. This strategy has proven very positive during line filling and system restarts.

17. Pump By-Pass Lines

Pump bypass lines are designed to prevent the build-up of high pressures on the suction side of a

pump and cavitation on the discharge side during a downsurge. They are useful in low-head systems

where the pump suction line operates under positive pressures. Bypass lines are installed parallel to

the pump connecting the suction line to the discharge line. They contain a check valve that only

permits water to flow from the suction side of the pump to the discharge side. The check valve is

activated when the suction head exceeds the discharge head thereby providing a source of water to

mitigate low pressure events on the discharge side or high pressure events on the suction side.

18. Increased Pump Inertia

Pump inertia is a measure of the resistance a pump has to a change in the rate of rotation. The

greater the inertia the longer it will take for a pump to come to a complete stop once the power

supply has been cut off. By increasing the inertia of a pump the pump run down time is extended.

This is advantageous from a transient perspective because water is being pushed through the system

(albeit at a decreasing rate) even after a pump trips. This volume of water can greatly decrease the

initial downsurge and the resultant upsurge. Increasing the pump inertia is most easily done through

the initial design stage in which the pumps are sized by taking into account the inertia.

19. Flywheels

In the context of transients, a flywheel is a weight added between the motor and pump to increase

the mass being rotated and thus the pump inertia. The increased inertia increases the rate of pump

Page 30: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

19

slowdown and therefore the magnitude of the resulting transient. Flywheels are good alternatives

for increasing inertia when the actual inertia of the designed pumps cannot be increased. Flywheels

are more easily installed with non-submersible pumps. Some manufacturers are hesitant to warranty

a pump if a flywheel in installed.

20. Electronic Capacitors

Electronic capacitors are made to drive the motor of a pump in the event of a power failure, thereby

limiting surge pressures. These devices essentially act as "electronic flywheels". This proprietary

technology is currently relatively rare and unproven.

21. Variable Speed or Frequency Drives

When power is available, pumps with variable frequency drives can be ramped up and shut down in

a slow and controlled manner. This feature reduces the instantaneous change in flow conditions

whenever a pump is turned on or off. This reduces the imbalance in flow and can decrease the

severity of transients at start-up and shutdown. These types of drives may also have additional

benefits with respect to efficiency, energy consumption and resonance/vibration. However, such

devices do not necessarily mitigate the surge pressures associates with power failures.

22. Soft-Start Starters

Soft starters reduce the load and torque in the power train of the pump motor during start-up.

These are superficially similar to variable speed drives in that they reduce the mechanical stress on

the motor and shaft, as well as the electro-dynamic stresses on the electrical accessories. Unlike

variable speed drives, soft starters cannot vary the speed of the motor once the motor is up to

speed.

23. Backup Power

Backup power can be used to maintain pump operation in the event of a primary power failure.

This strategy improves system reliability by avoiding down time following a power failure. Backup

power is typically achieved by the use of a second parallel power source, such as a diesel generator.

24. Alternate Pump Drive System

Alternate pump drive systems attempt to minimize the risk of a multiple and concurrent failure of

pumps during a power failure event. Unlike in the case of backup power, this strategy requires that

Page 31: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

20

at least one pump is primarily powered by an alternate drive and/or power source, such as natural

gas or diesel. This strategy is typically used during peak hour operating conditions for a specific

peak hour pump.

25. Open Surge Tanks

Open surge tanks are protection devices that can relieve both excess and minimum transient

pressures. The simplest form of open surge tank is a vertical standpipe connected to a pipeline.

When pressure in the pipeline increases, the water level in the surge tank increases and when

pressures in the pipeline decrease the surge tank provides a supply of water to reduce the minimum

pressures. Transient pressures are dampened out by fluid friction as the water level in the tank

fluctuates up and down. Because they are open, this type of surge tank must be designed sufficiently

tall so that it will not overflow.

26. Traditional Air Chambers (Hydro-Pneumatic Pressure Vessel/Tank)

Traditional air chambers represent a modification to open surge tanks, and can come in several

different configurations including vertical, horizontal and spherical. In high head systems the height

requirement of an open surge tank may be prohibitive from a construction, safety or economic point

of view. An air chamber is basically a closed top surge tank with a volume of both air and water. In

the traditional air chamber, the air is usually kept under pressure by means of a compressor. During

an upsurge the air acts as a cushion and absorbs some of the excess pressures. During a down surge

the tank provides a supply of water to mitigate low pressures in the pipeline. Air chambers must be

designed such that the tank will not empty during a transient event and suck air into the system.

27. Bladder Type Air Chambers (Hydro-Pneumatic Pressure Vessel/Tank)

A bladder type air chamber functions in a similar manner to a traditional air chamber with

compressor. This tank, however, is equipped with a bladder that is pressurized such that under

normal operating conditions it maintains the desired air volume. In this type of air chamber the air

and water phases are separated and the air does not have to be refilled.

28. One-Way (Feed) Tanks

One-way surge tank or feed tank can be of the open or closed type surge vessel previously discussed.

The purpose of this device is limited compared to other surge tanks in that it only functions to

minimize the low pressure characteristic of a transient downsurge. A check valve only allows flow

Page 32: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

21

to travel from the tank into the pipeline during low pressure events. As such, this vessel does not

protect against transient upsurges.

29. Storage Tanks or Reservoirs

Storage tanks buffer a pipeline from an imbalance in supply and demand. In an emergency situation

when supply is cut off (i.e., power failure) a storage tank can provide a supply of water. Elevated

storage tanks especially can help maintain positive system pressures in the pipeline downstream of

their location.

30. Specific Device Strategies

These types of strategies can be uniquely employed at specific pump stations, storage tanks or on

unusual transmission lines. For example, a check valve can be located between pressure zones to

provide a backup or emergency supply of water, or to prevent a high point from draining during

power failure. The check valve could be designed to be closed under normal operations. If pressure

should drop in the higher pressure zone however, the check valve would open and permit water to

flow from the low-pressure zone into the high-pressure zone. As another example, a check valve

can be employed as a control measure allowing for redundancy in air chamber operation and

protection across different pressure zones at the same pump station.

31. Route Alignment

System topology often governs the ultimate alignment and profile of main transmission lines, and

this initial design decision is often the cause of many future transient problems. For example, a

decision to tunnel rather than to build across a hill may prove to be beneficial with respect to the

future transient response, because this might eliminate the troublesome system high point that

would almost always have problems with negative pressures.

32. Specific Pressure and Zone Based Strategies

These types of strategies are more easily employed during the master planning and system design

stages. The decisions on zone boundaries and on where to put important boundary conditions such

as pump stations or tanks have a great impact on the response of transients. For example, one

strategy might be to equip an elevated tank in higher zone with a pressure reducing valve in order to

eliminate the need for a lower zone transmission line. Another strategy may be to add an additional

booster pump station or to change the design location of another.

Page 33: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

22

33. Distribution System Interconnection Strategies

This strategy relies on the fact that long transmission mains are extremely susceptible to transient

pressure fluctuations. Its goal is to interconnect the transmission system into the distribution

system, therefore allowing for additional sources of pressure wave dissipation. It also can be used to

enable bypass from one zone to another to relieve short-term downsurge conditions, providing

sufficient positive pressure head is available.

34. Shock, Vibration and Resonance Strategies

These specific strategies deal with complications that may or may not arise from transient flow

conditions. Some of these strategies may include: base isolation of pumps, extra lengths of pipe,

changes in natural frequency of devices, and thrust blocking and/or rubber pad absorption of

undesired loads.

The above detailed list of transient protection devices and risk mitigation approaches essentially

represent the options that an engineer, designer, and/or system owner have to consider. However,

in order to identify the risk and then subsequently determine the appropriate solution from this (and

additional) list of options, the same individual(s) must first determine the type of analysis approach.

2.5 Hydraulic Transient Analysis Approaches

The previous section provides an overview on what hydraulic transients are, as well as outlines some

of the resulting risks and protection options. The next topic that needs to be addressed is the one

pertaining to the available options for performing a hydraulic transient analysis. The following

subsections outline typical analysis approaches that have been previously, and are currently, being

used in practice. While the analysis approaches are not the main focus of this thesis, they are still

briefly described in order to provide context for the following chapter on the shortcomings of

current analyses.

2.5.1 Do-Nothing

Through historical practice, the hydraulic transient analysis of a water and wastewater system could

easily have been cast as a decision making task. In other words, the question of whether or not to

consider and address hydraulic transient concerns has traditionally been made directly or implicitly.

Page 34: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

23

To that end, most rational decision making (and therefore rational analysis and design) typically

considers the option of doing nothing. In the realm of transient analysis, the do-nothing option is

defined as not considering the impacts of hydraulic transients but also as not doing anything to

protect against their risks. While the first of these is strongly fading away due to better education

and engineering standards, the second is still prevalent due to economic, social and professional

limitations.

The do-nothing transient analysis approach essentially states that transients are likely not significant

in the particular system at hand, and that if something does happen as a result of transients, it will

then be addressed accordingly. The do-nothing approach is focused on the prospect of short-term

cost savings in both the engineering professional services and in the capital or construction cost of

potential protection options. The resolution of any resulting problem(s) may simply be in the form

of a physical repair that returns the system to its status quo, or may be in the form of an alternative

analysis approach that leads to a different solution. While the do-nothing approach to hydraulic

transients is not recommended for most water and wastewater systems, it does serve a purpose in

some trivial cases. The question that needs to be addressed is whether or not the individual(s)

making the decision for this approach are knowledgeable and experienced enough to do so, or

whether or not the decision is based on a preconceived bias or lack of understanding.

2.5.2 Rule-of-Thumb and Standard Convention

The next hydraulic transient analysis approach can be described as a step-up from the do-nothing

approach. This approach of using standard convention and rules-of-thumb for the analysis and

design of water and wastewater systems essentially accepts the fact that hydraulic transients can pose

a risk, but also assumes that such a risk is quite predictable and constant for most systems. The

standard conventional rules and rules-of-thumb aim to quantify both the risk (e.g., magnitude and

characteristic of a transient event) and the nature and size of the required protection. The following

is a sample and partial list of common rules-of-thumb that are often employed in practice in one

form or another. (A detailed discussion on why these may not apply to all systems is outside of the

focus of this thesis and is therefore not provided here, however, a partial discussion is provided in

Karney and McInnis, 1990.)

Page 35: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

24

• The risk due to excessive transient pressures can be estimated by the simple

Joukowsky expression (∆H = a∆v/g) relating the pressure fluctuation to a sudden

change in velocity.

• Flexible pipe should be chosen over rigid pipe due to its greater expansion and its

lower wavespeed.

• For rigid pipe such as CPP, the transient pressures should be assumed as 40% above

the maximum operating pressures.

• Higher wavespeed values should always be used for predicting a transient response

because they are more conservative.

• Air valves can be sized on conservative maximum flow rates that are used to represent

filling and draining scenarios. Simple equations relating the required valve size as a

function of the flow rate can be summarized in simple graphs or slide rules.

• One size of air valve is best for an entire system.

• All surge protection devices should be designed for peak flow/operating conditions.

• The shorter the pipe length the lower the risk due to transients.

• Maximize the number of system appurtenances such as elbows and tees and lower the

overall risk due to transients.

• Minimize the fluid velocity and therefore lower the risk due to transients.

• Interconnect systems (e.g., into distribution networks and loops) and eliminate the

need for additional transient analysis.

• Install SRVs at all pump stations, and size the SRVs as a fraction of the discharge

piping size.

• SRVs automatically act to limit the maximum surge pressures to the level of the

chosen high pressure set-point.

• Doubling the number and size of any surge protection device in the system will act to

lower the risk of hydraulic transients.

• HAC volumes can simply be designed as a percentage of the total fluid volume in the

system.

• If an option exists, always choose the larger surge protection option.

Page 36: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

25

As is the case with the do-nothing approach, the standard convention and rule-of-thumb approach

attempts to apply rules that are often applicable in simple systems to other more complex hydraulic

systems. As Karney and McInnis (1990) note: “Traditional wisdom for identifying worst-case

scenarios is based on elementary equations, rules-of-thumb, or common sense; in other words,

simple relations that may have little or no bearing on the performance of more complex systems”.

The true problem with the rule-of-thumb approach to transients is that no two hydraulic systems are

the same, as every system is partially unique. For example, consider the implication of one of these

rules in a water system with storage, and in the same water system without storage (i.e., a closed

system). The transient response between the two systems is undoubtedly different. The reason that

this approach is still commonly used is because it is geared at the root sense of engineering.

Engineering has long been a profession of logic, common sense, and prescriptive analysis and

design. It is the prescriptive nature of these rules that attracts their end users, believers and

practitioners.

2.5.3 Numerical Modeling

Numerical hydraulic modeling rose to prominence as a result of both the increasing complexity of

the required hand calculations, as well as the unwillingness to experiment on real-life systems in the

field. As Walski (2006) noted, “engineers throughout the early 20th century were able to design and

analyze the hydraulics of a functioning water distribution system using a combination of

simplifications, rule-of-thumb, and conservatism. The ability of engineers to construct systems

exceeded the profession’s ability to analyze them.” Concurrent with the increasing complexity of

hydraulic systems was the advancement in technology, especially in the powers of computing. The

field of numerical hydraulic modeling was thus born and it has never looked back since.

In the recent decade, numerical modeling has been regarded as the standard convention for

hydraulic analysis and design. It relies on the construction and utilization of a computer model; a

model which seeks to portray the physical system through a mathematical representation of its key

properties and parameters. In the realm of water or wastewater systems, the numerical models

encode system properties such as length, connectivity, roughness, demand, boundary conditions,

etc., and are ultimately then used to solve an analysis, design, or optimization objective. The

complexity of models can vary through their detail, physics, and overall assumptions.

Page 37: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

26

Typical hydraulic transient models (i.e., full water hammer models) represent a single (albeit a more

complex) type of a numerical hydraulic model. These models are more complex than steady state,

EPS, quasi-steady and rigid column models, but in practice they are frequently not employed to their

full mathematical and physical potential. More specifically, traditional numerical transient models

are typically (but not always) limited to single phase, one-dimensional flow, steady friction, constant

wavespeed, and do not take into account fluid structure interaction (FSI). The reason for this is

simple – in most systems, the additional accuracy does not warrant the additional complexity. In

other words, we can often make the same type and level of decision using a simpler model.

Traditional hydraulic transient models typically fall within the time domain analysis spectrum and

rely on unidirectional analysis. These models are mathematically based on two quasi-linear

hyperbolic partial differential equations known as the dynamic and continuity equations. The

numerical solutions to these equations generally fall into the following broad categories: method of

characteristics (MOC), wave characteristics method (WCM), finite difference techniques and finite

element methods (McInnis et al., 2004). For a summary chart of traditional transient analysis

solution approaches, please refer to Figure 2-3. The choice of solution method strongly depends on

the complexity of the system (and therefore the accuracy required), the computing time, and the

experience required. Nonetheless, in most water and wastewater applications, the MOC is the most

widely accepted solution approach; a solution approach that is incorporated into several commercial

(and private) transient software analysis packages. The main rival to the MOC models are the WCM

models; models based on a method that tracks the event or disturbance based on wave propagation

mechanics (i.e., almost, but not quite algebraic water hammer), rather than through a time-space

grid. The commercial software packages that implement the WCM are sold on the notion of a faster

computing time for water systems consisting of large distribution networks.

Numerical transient modeling is an effective means by which a system can be analyzed and/or

designed without inflicting a physical change. In this common transient analysis approach, the

engineer can look at various design options and alternatives. Numerical models enable a proper

sensitivity analyses, future condition representation, and much easier review than any other transient

analysis approach. These are just some of the reasons why numerical transient analysis has become

the industry norm.

Page 38: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

27

Figure 2-3: Traditional Transient Analysis Solution Approaches

The above advantages of this approach are unfortunately also accompanied by some often

unrealized limitations. First, numerical transient models are highly theoretical, and if not validated

or calibrated, they may represent a different reality than the one intended. Second, numerical

models and software packages are increasingly becoming more and more user friendly, to the point

Page 39: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

28

where any amateur engineer (or even technician) can start to feel comfortable in performing such

analysis and design. In other words, numerical transient models can bring comfort and prescriptive

simplicity to unqualified individuals, and therefore possibly make the end objective equally as

troubling as the previously discussed analysis approaches (i.e., do-nothing and standard convention).

Some shortcomings of the current numerical modeling approach to transient analysis and design are

further discussed in Chapter 3.

2.5.4 Field Data and Investigation

As noted earlier, the primary concern with the standard numerical modeling approach to transient

analysis is the theoretical (and often academic) nature of these models. A possible solution to this

dilemma is to rely on actual field data analysis. Before the age of numerical models, difficult

hydraulic systems were often troubleshot in the field using either a trial and error approach, or with

the implementation of a physical model. Ironically enough, it was the risks arising from field

troubleshooting and the cost of physical modeling that partly gave rise to the numerical analysis

approach that is now the norm. The industry simply needed an analysis tool that reduced the time

and cost commitment, while also reducing the potential liability associated with poor analysis/design

and the poor results that were often attributed to field work.

The question that should be asked at this point is simple: Why is this field approach to transients still

considered if the numerical analysis approach has been shown to be widely accepted? The answer

partly lies in the previously mentioned shortcoming of the numerical approach, but also in the

advancement of field sensor technology. The modern field sensor technology (such as high

frequency transient pressure monitors) allows the system owners and designers to listen to their

existing systems and to optimize their newly designed and constructed systems. Transient pressure

monitors can gauge the pulse of the system by continuously monitoring transient pressures at key

system locations. The continuous (or even limited) transient pressure monitoring can bring insights

on the level and frequency of most hydraulic transient risks, while at the same time act to provide

clear answers to design uncertainties such as surge protection size, physical parameters (e.g.,

wavespeed or friction), etc.

The field data analysis and investigation approach to transient analysis cannot solve all of the design

problems, but sometimes it can more directly and decisively solve some. More importantly, it can

Page 40: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

29

close the theoretical limitation loop for all design problems. For an expanded discussion of the field

work approach, including the type of field pressure monitors and sample output, please refer to

Chapter 5 and Chapter 6.

2.5.5 Hybrid

The previous sections outline and describe four (4) distinct types of transient analysis approaches:

do-nothing, rule-of-thumb, numerical modeling, and field work. All of these approaches have been

shown to be effective in many types of engineering problems, but none of these can be classified as

a fool-proof solution method. The numerical modeling approach is currently the most widely used

approach, as it is the most effective in bridging the gap between doing nothing and doing everything

at the lowest cost. However, numerical modeling has not completely eliminated the need for the

other three approaches. The do-nothing approach is still commonly used for simple and/or older

systems, in which the cost of repair is just part of the business. The rule-of-thumb and standard

convention approach has a wide use that is similar to the do-nothing approach, and quite applicable

to certain types of systems. More importantly, it is often an excellent method for preliminary

analysis and/or screening of alternatives.

The field work approach has recently experienced a resurgence in its application due to the

advancements in, and availability of, modern sensor technology. This resurgence has brought light

to some of limitations and risks of numerical modeling, and is attempting to substitute parts of the

modeling process with field based studies and reviews. While it will likely never (nor should it ever)

replace the numerical modeling approach, it can act to supplement and confirm the theoretical

predictions and assumptions of the actual system.

The obvious limitations of the four analysis approaches can be avoided if these approaches are

combined into one type of transient analysis. Such a transient analysis can be classified as a

“Hybrid” method, in that its goal is to draw the best from all approaches. A hybrid transient

analysis is nothing new, as engineers have often combined parts or all of the approaches to solve

transient related problems. However, such an approach is currently not promoted, as the industry

mostly relies on numerical modeling outputs. Any good engineer or designer should be able to use

all tools that they have at their disposal when it comes to a hydraulic transient analysis. Therefore,

such an engineer should consider implementing the do-nothing approach for certain systems. They

Page 41: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

30

should also use rules-of-thumb and standard convention for preliminary reviews and initial design,

and as part of numerical and field work based estimations and design. Lastly, the engineer should

also supplement most numerical based analyses with field based confirmations, and vice versa. Such

an integrated approach can, and will, lead to the design of more cost effective and reliable water and

wastewater systems.

2.6 Summary

The focus of this chapter is to provide a widespread background introduction to hydraulic transients

and the current variance in the industry’s approach to considering these important hydraulic events.

The chapter initially provides a definition of hydraulic transients, and establishes the link between

these events and the risk to water and wastewater systems. The chapter then proceeds to define and

discuss the properties of three (3) key types of common fluid systems: water transmission, water

distribution, and wastewater forcemains. The hydraulic transient conditions and risks in these

systems are identified in order to explain and support one of the general themes of this document –

that no two systems are the same and that a design and/or analysis of any such system must

therefore consider a variety of transient analysis approaches.

The chapter proceeds in identifying the types of risks, while at the same discussing the general

concept of risk and providing a general understanding how this risk has traditionally been identified

and dealt with. In essence, it provides a critical assessment of the qualitative nature of traditional

transient risk identification and mitigation. The chapter then presents a long list of transient

protection devices and system design approaches, in order to not only provide an indication of the

complexity of system protection options, but also as a means of providing context to the decision

making process.

The chapter concludes with a discussion of the different types of transient analysis approaches that

can (and often are) considered, and identifies five (5) of these which are most commonly employed

in the industry. The central focus of this discussion is the current trend towards numerical

modeling, and how this trend can be both dangerous and narrow minded. The chapter essentially

establishes the need for a hybrid (or multi-faceted) approach to hydraulic transient analysis; one that

relies not only on theoretical numerical modeling, but also on the actual in-situ field performance of

the system and the engineering expertise of the analyst.

Page 42: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

31

Chapter 3 Current Analysis Shortcomings

The focus of this chapter is to demonstrate a few of the most direct and often overlooked

shortcomings in the analysis and design for hydraulic transient conditions, including some of which

are typically rooted at the steady state level. With that in mind, it should be noted that this chapter

does not attempt to provide a deep theoretical analysis of current steady state analysis techniques;

techniques which have been the subject of numerous studies and publications over the past few

decades. The overall goal of this chapter is to identify key analysis topics (from the point of view of

transients) that the industry has still not grasped or given much thought to.

3.1 Steady State Models

The design task of performing a hydraulic transient analysis more often than not relies on the use of

an existing or newly constructed numerical hydraulic model. Most water and wastewater system

owners such as municipalities or utilities have progressed to the point at which they currently own

and maintain a numerical hydraulic model of their water and wastewater systems. The type and

complexity of the models can significantly vary from one owner to another, but more often than not

(especially for large water systems) the numerical models are derived from an asset management

frame of mind. In other words, the hydraulic models are constructed in great detail using

commercial software for reasons other than those pertaining to pure hydraulics. The commercially

available software packages are always evolving and their capabilities are significantly increasing

through their GIS, CAD and geospatial connectivity. These extensive capabilities lead to large

system wide asset management (or component based) numerical models; models which are then also

used for the hydraulic analysis and design tasks.

The existing complex numerical hydraulic models are usually of the steady state or extended period

simulation (EPS) variety. These models can vary (or include options) for: the design year or year of

operation, actual (current) or predicted (future) system demands and flow rates, daily variations in

hydraulic conditions (e.g., reservoir levels, diurnal demand curves), etc. As a result, steady state

models can be so complex as to contain as many as 100,000 nodes (i.e., junctions) and links (i.e.,

pipe segments) for a variety of possible operating scenarios. The important question to be asked is,

are these models suitable for a hydraulic transient analysis?

Page 43: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

32

In order to answer the above question, one must first look at the limitations of the steady state

models. Steady state model limitations can be broken down into two categories: assumptions and

complexity. In the first category, steady state models undoubtedly contain assumptions on both the

system’s physical condition, and hydraulic condition and capability. The physical realities assume

that the model comprises all proper components, and that these components are properly

represented in the numerical model. Examples of physical properties which are typically estimated

and assumed can include some of the following:

• Exact location and length of all pipe segments;

• The type, location, and physical properties of system appurtenances such as flow

control valves, valve chambers and interconnections, etc.;

• Actual pump curves and pump properties;

• Type of pipe, year of installation, and physical condition;

• Open or closed connection points within the system; and

• Location and allocation nature of demand points.

If physical assumptions such as those listed above are not true, or even just significantly different,

then the results predicted by the steady state model may not be accurate enough. If the physical

system properties and the steady state results are not accurate, then a hydraulic transient analysis

based on such a model may be improperly used to make an important design decision. (As is the

case with any analysis or design, the uncertainty can more often than not be accounted for through a

proper sensitivity analysis of the critical assumptions and parameters).

The second group of assumptions under the first category are those pertaining to the system

hydraulics, and these can include some of the following:

• Pipe friction factors such as Hazen-Williams or Darcy-Weisbach;

• Actual (or lack there of) minor head loss coefficients for appurtenances;

• Total flow rates from source locations (e.g., pump stations);

• Flow rate contribution from all different sources;

• Actual system demands (see following section) and their diurnal timing;

• Fluid levels in storage elements;

Page 44: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

33

• Pump sequencing and operational logic; and

• System flow and pressure control logic.

As is the case for the physical system assumptions, these assumptions can also significantly affect the

predicted steady state results, and therefore any additional analysis or design – such as a

supplemental transient analysis. The second category of steady state model limitations pertains to

the previously noted idea of complexity. The complexity in the steady state models that are derived

from asset management purposes arises due to multiple reasons, including:

• The complexity arising from the sheer size of the model, including the number of

nodes, links, boundary conditions, etc. The use of such a model for a transient

analysis becomes prohibitive due to either model run-time and/or the reality of

properly interpreting (and actually believing) the results.

• The complexity arising from the deterministic nature and the automatic spatial

allocation of demands, including those demands of insignificant magnitude.

• The complexity arising from the type of demand, and the various peaking factors and

diurnal demand curves.

• The simplification of an EPS model to a single period model, which requires the

assumption of the most common operating and demand conditions.

• Complexities arising from multiple sub-systems, including combined pressure zones

and the lack of pressure zone delineation.

• Complexity arising from too much detail, including the presence of service connection

and intermediate nodes that provide no additional information with respect to

elevation, demand, or simply – hydraulics.

• The complexity arising from successive model updates and changes, including those

pertaining to physical system changes, operational changes, future design years, etc.

The master planning and decision making approach that originally drives the creation

of such models is prone to inadequate model maintenance, validation, and calibration.

More often than not, the models contain system components that should not be there,

or model components that are significantly different.

Page 45: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

34

• The complexity arising from the lack of model change tracking, both within the model

itself, as well as by the modeller (owner or consultant). In many cases, the individuals

that create the models are not the model end users.

In general, the proliferation of numerical steady state hydraulic models for water and wastewater

systems has come to the point where the models themselves essentially make the decisions. More

often than not, a modeller is inclined to say something along the lines of “But the model says, or the

model predicts…,” etc. The irony here is that hydraulic models can essentially predict anything that

the user wants them to predict, and therefore the sole reliance on the model outputs without the

consideration of both the physics, and the previous model developments and limitations, is quite

dangerous.

In the end, the lesson that should be taken from this section is that steady state models undoubtedly

have their limitations. Steady state models are not all the same, and are not fit for every purpose.

Most steady state hydraulic models are of the simplest physical form, and lack the physical

understanding and developmental progress that has been extensively presented in academic

publications. Many steady state hydraulic models are rarely if ever properly (or at all) validated or

calibrated with field results, and are then unfortunately often used as the stepping stone for a

hydraulic transient analysis. Therefore to answer the question that was posed earlier (i.e., Are these

models suitable for a hydraulic transient analysis?) – the answer is…not always. Hydraulic transient

models must be fit-for-purpose, and therefore the typical steady state models must be properly

adjusted and validated. The following section takes a step back to look at one of the most important

steady state model assumptions – the deterministic demand.

3.2 Average and Maximum Day Demands

The traditional design of water supply, treatment and distribution systems has been accomplished

using a multi-step approach; one that has often relied on a single objective optimization of a system.

As with most circulation and consumption systems, the design is driven by a mix of input and

output characteristics. In water systems, the output properties (from the point of view of the

system) are most often the current and/or future/potential water demands; outputs that essentially

determine the required design inputs such as water supply and storage. The analysis and design of

such systems is therefore highly dependent on quantifying the expected water demands. In

Page 46: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

35

traditional (and most commonly) applied analysis and design, such demands are deterministically

quantified across the life of the system. While many studies (e.g., Lansey et al. 1989 and Goulter

1992) have demonstrated the negative impact of a deterministic demand assumption, and while

many other studies (e.g., Babayan et al. 2005, and Giustolisi et al. 2009) have presented various

theoretical approaches (e.g., genetic algorithms, Monte Carlo simulations, etc.) to stochastic and

multi-objective based design of water (and wastewater) systems, the fact still remains that most of

these systems are still designed based on deterministic constraints such as demand. In his Ph.D.

dissertation on multi-objective stochastic design, Filion (2006) provides an excellent literature review

of both the risks and potential solution approaches to dealing with the demand variable (among

many of the other analysis and/or design variables).

In reality (i.e., outside of the academic and progressive realm), the current and still unchanged design

philosophy is to design water systems by taking into account the peak conditions and constraints

during the life of the system; constraints such as forecasted water demands. One of the most

important demands and forecasts is that of the average base case, which is referred to as average day

demand (ADD). ADD is the primary demand component in design and is defined as “the total

annual quantity of water production for an agency or municipality divided by 365” (Ysusi, 2000). All

other variations in demand (e.g., maximum week, maximum day, maximum hour, etc.) can be

derived in the same manner or represented as a percentage of the ADD. For example, maximum

day demand (MDD) is defined in a similar manner, but it incorporates the maximum 24-hour period

in a given year. The meaning and application of the ADD term seems simplistic, but its origin (and

hence complete justification) is relatively unknown. Similarly, the interpretation of the MDD term is

conceptually clear, but the factors that feed this interpretation are more complicated. Both of these

quantities are system and time specific, and are influenced by expected and/or random events. In

other words, a water demand is not actually a deterministic variable; rather it is just assumed to be.

All widely accepted water system design handbooks refer to the ADD term without giving a single

line or thought as to its origin. The references acknowledge that this quantity is highly important

and that it is part of the first step of determining the rate of water consumption. The well published

1954 Water Supply and Wastewater Disposal (and its 1966 successor) by Fair and Geyer, may be one

of the earliest books which does not explicitly refer to the above term. The authors initially note

that “the capacity and of individual system components is set by what is expected of them”. This

statement, be it vague, at least gives partial justification. However, the book does refer to a

Page 47: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

36

synonymous “average daily rate”, meaning that the use of the ADD term in design has been around

for quite some time.

Modern day water system design references typically only define the ADD quantity (along with the

other permutation quantities), and in some instances also elaborate on how (but not why) it is used.

A relevant partial list of such references includes the following:

• Water Distribution Systems Handbook (1999), ed. by Larry W. Mays.

• Urban Water Demand Management and Planning (1998), by Duane D. Baumann, John J.

Boland, and W. Michael Hanemann.

• Advanced Water Distribution Modeling and Management (2003), by Haestad Methods.

• Introduction to Urban Water Distribution (2006), by Nemanja Trifunovic.

• History of Water Distribution (2006), by Thomas M. Walski (AWWA Journal).

• Water Encyclopedia: 5 Volume Set (2005), ed. by Jay H. Lehr and Jack Keeley.

• Toronto's Water Efficiency Plan (2002), by Toronto Water.

• Distribution System Water Storage Tank Sizing: How Large is Too Large? (2006), by Baxter

& Woodman Consulting Engineers (ISAWWA-IWEA 2006 Joint Water Conference).

In order to determine an ADD for the system one must evaluate all respective water system uses

that contribute to the output. This quantity includes direct residential and industry consumption,

unaccounted water (such as leakage), fire fighting and other emergency requirements. The

quantification of leakage is highly dependent on metering or audits, or else its magnitude is merely

an educated estimate based on available data. Fire demands are derived from highly sensitive

surveys performed by the insurance industry. They are also often expressed as a percentage of the

MDD. Both of these factors essentially confirm the fact that this quantity comprises a level of

uncertainty (and therefore inherent risk), and that its deterministic use for design is merely a form of

simplification.

Many different techniques can be used to determine actual (albeit still deterministic) consumption

rates, and some of these include: analysis of historical data (billing or metering records), similarity

comparisons with other municipalities, unit consumption demands, extrapolation from regional

models/studies, and small scale surveys of individual and/or industry use. If historical data

Page 48: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

37

(computerized or manual) is unavailable, unreliable or incomplete, then the most common practice

is to apply standard per capita consumption while at the same time taking into account different land

use patterns. This approach is simplistic in that it depends on population forecasting and on

predetermined unit consumption rates. Present population census data is fairly reliable, but future

population forecasting is inherently probabilistic in nature. It is therefore highly influenced by

random future events and factors that bring uncertainty to any resulting prediction. The unit

consumption rates are also only averages, and can drastically vary not only on the regional scale but

also on the local scale.

Unlike the ADD, the MDD is used as a design quantity for the purpose of meeting changes in

demand variations. This demand is intended to take into account that one specific day, or period of

days, when the demand is much higher than the average. For example, in North America this

demand may take into account that one hot day in July when many residents are watering their lawns

and yards. As conceptually simple as it may seem, such a typical day does not exist. In reality, years

do not simply repeat themselves, and this is now clearly evident with the ongoing effects of climate

change. As a result, such an estimate should be based on a random variable – that is, as a probability

of occurrence. This estimate is significantly influenced by events such as the one described above,

but also by events beyond a municipality’s or utility’s control or thought. These unexpected events,

whether government policy changes or unusual weather patterns, may also have a systematic effect

on the MDD quantity; an effect that this estimate is not built to take into account.

If historical data is available, its statistical analysis undoubtedly also yields a probabilistic output for

the ADD and the MDD. Unfortunately in both cases (historical or non-historical) and for both

demands, this quantity is always presented as a single deterministic value; a value that is then further

used to determine all other inputs characteristics. For example, a design flow may be prescribed as a

maximum of a) the MDD plus fire flow demand or b) the peak hour demand (PHD). If the

probabilistic MDD is added to the probabilistic fire flow, one cannot be fully certain of the variance

and risk contained within the ultimate design value. Similarly, the PHD also falls in this category as

it is either: a) derived from the same data as the ADD or b) a percentage of the ADD (via peaking

factors). The later case does often include a range, but is still dependent on the original ADD input.

The random nature of these quantities is almost always overlooked for the purpose of simplifying

the task at hand. For example, it is not unusual for a basic design handbook to note something

similar to the statement below:

Page 49: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

38

"The daily, weekly, and annual cycles are never repeated in exactly the same way;

however, for design purposes a sufficient accuracy is achieved if it is assumed that all

water needs are satisfied in a similar schedule during one day, week, or year”

(Trifunovic, 2006).

Even though these concepts are definitely not new, the unfortunate truth is that most water systems

are still designed to meet regulations and guidelines; guidelines which still simplify the demand to a

single deterministic value as a function of time (i.e., system expansion or year).

While this variable is actually quite important in the overall analysis and design, it is often simply

overlooked as a fixed design quantity. The term “average day” is almost benign in that its history is

never discussed. It has been an idea and/or methodology that is rarely disputed or questioned, but

more importantly it has been used as a basic quantity without an associated level of variance (and

therefore probability). A lot of information and assumptions go into determining the ADD, yet its

final end use is extremely simplistic. Its justification may be simple or it may be complex, but it is

certainly not freely discussed or questioned. Similarly, the idea of MDD is conceptually simple as it

is supposed to take into account the system stresses that are beyond the expectations contained

within the average day. However, this quantity too is influenced by a variety of probabilistic and

unpredictable factors and events, and is therefore statistically vague. Without basing the design

approach on a stochastic framework, one must at least understand that the ADD and MDD (and all

demands derived from that point on) are probabilistic and hence that they carry an associated level

of uncertainty. As the previous statement indirectly implies, these simplifications are useful if and

only if, they are accurate and representative estimates of the true random nature of demand. In the

end, the key test is the sensitivity of decisions made with these assumptions. In the context of this

thesis, these assumptions feed the decisions that are derived from a subsequent hydraulic transient

analysis and design.

3.3 Current Design Approach

As discussed earlier, traditional engineering design has often relied on worst-case design loading;

loading which is typically set out by a regulated design code, guideline, or practice. Research,

innovation and technological improvements have made engineering design easier, but the basic

theory and design approach has unfortunately not changed much. Whether we are talking about

Page 50: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

39

designing a bridge or a water transmission system, the least variable (i.e., the most restricted) aspect

of the design comes through the determination of loads. Once a general design concept has been

agreed upon, the detailed design is typically highly dependent on a pre-specified set of deterministic

loads such as weight, seismic quake, wind, pressure, flow, etc.

3.3.1 Steady State Design Loads

The design of a water system, whether it consists of components pertaining to supply, transmission

or distribution, has long suffered through the question of what loading is appropriate. Nowhere is

this clearer than in North America, where water is treated as a right and where as a result, a water

system’s required capacity is typically determined by a relatively arbitrary worst-case design load; a

load driven by a deterministic assumption or forecast of demand.

The determination of the worst-case load typically first requires the quantification of an average or

typical load (as discussed in an earlier section). Long-term population and industry forecasting is

used to predict the size of a future service area, and these extrapolations are then typically multiplied

by a per capita or per industry consumption rate. A standard consumption rate in North America

may be 300 to 400 litres per capita per day. Even though this approach can rely on historical

analysis of data, its ultimate application is purely deterministic. When the service areas are multiplied

by the deterministic consumption rates, a rather benign quantity is born: the ADD. This baseline

load directly feeds into all other design loads, including the previously discussed MDD, PHD, and

minimum hour demand (MHD). Once cast, it is a combination of these loads that ultimately

determines the size of the water system components such as water treatment plants, feedermains,

pump stations, reservoirs, and ultimately for the purpose of this thesis – the surge protection.

However, these design loads are also by their very nature variable, and therefore the conventional

design of a water system is left without any other option than to use a worst-case variation of this

load. With the diurnal nature of demand (and therefore pressure), the difference between PHD and

MHD can be many fold. Even more troubling is that original design loads are rarely confirmed or

monitored post construction and/or operation, and lessons are infrequently learned. As a result, the

conservative load based design of water systems has yielded a sleuth of under-used system

components that are more difficult and costly to operate. (A good example of such components

comes in the form of dedicated transient protection equipment, which is typically designed via

numerical hydraulic transient analysis techniques.) Filion (2006) summarized the worst-case

Page 51: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

40

deterministic demand design shortcoming best through a synonymous explanation of a “longitudinal

analysis”; a term best explained via the following simple statement:

“Since a major goal in design is to provide an acceptable level of service throughout the life

of a system, it may be more useful to estimate the hydraulic reliability of a network over its

entire design life rather than the end of it”.

3.3.2 Transient Modeling Approach

The field of hydraulic transients has long been considered as a “black box” of a topic. The

traditional and true expertise in this field has often been limited to a few specialists and within other

fluid systems, and its importance is only now truly gaining widespread traction in standard water

transmission and distribution systems. The increased requirement for the considerations of

transients in design has quickly brought on the need for engineers to develop this expertise in order

to be competitive. At the same time, the advances in, and acceptance of, computer modeling has

never been higher. With these two driving factors, the field of transient analysis has quickly

progressed to the development of an unwritten design strategy – the worst-case scenario design with

the aid of a computer model.

A transient analysis of a water system requires the understanding of the system characteristics; an

understanding that is nowadays always summarized within a comprehensive steady state computer

model. It is the combination of this steady state hydraulic model and the previously discussed

deterministic design loads that drives the decision making and design process for water systems.

The proliferation of hydraulic modeling arose from the need to “predict” the future without

intruding on, or risking the performance of, a real life system. The advances in research and in

technology have spawned an entire branch of hydraulics which is simply referred to as modeling.

Whether or not we are talking about models for asset management, master planning, computational

fluid dynamics, transient analysis or system optimization, the purpose of any model is still only to

mimic nature through mathematics and to be able to do it in a non-intrusive manner. Every model

should have its own purpose and goal, and nowhere is this clearer than in hydraulic transient

modeling. However, this important prerequisite is quickly fading because the scale and complexity

of hydraulic models is rapidly increasing and because the North American industry is again quickly

shifting towards rehabilitation and optimization of existing infrastructure.

Page 52: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

41

A standard transient analysis typically relies on a previously constructed steady state model that

contains all system characteristics pertaining to pipes, elevations, and boundary conditions. This is

probably the most overlooked step in a standard transient analysis. Given the traditional

deterministic nature of the steady state model outputs, the subsequent transient model inputs are

therefore themselves also assumed to be deterministic. Very little thought is actually given to the

uncertainties and variability of steady state modeling parameters such as roughness, leakage, demand,

reservoir levels, etc. Uncertainty in water distribution system parameters is usually ignored and the

most likely parameter value is selected and used in the analysis and design (Grayman, 2005). The

best one can hope is that the steady state model has been calibrated or at least partially calibrated for

a current design year. These steady state model parameters in turn affect other more critical

hydraulic transient values such as the initial velocity.

All transient numerical modeling packages solve a set of two governing non-linear partial differential

equations. The two most accepted and used procedures for solving the equations are the before

mentioned MOC and WCM models. Depending on the code, the steady state model might have to

be simplified in order to reduce the run-time of the transient model simulation. For example, a

boundary intensive WCM solution typically requires orders of magnitude fewer calculations and is

often much quicker in solving large systems with many pipe lengths and nodes (Wood et al., 2005).

This type of transient analysis approach relies on the pure belief that computer power can overcome

anything, and often leads to individuals performing detailed transient analysis on asset management

models in excess of 30,000 links and nodes. The ultimate question comes down to whether or not

the results are believable and/or realistic when it comes to actual in-situ (or future) field conditions.

The model simplification process is typically referred to as skeletonization for surge purposes; the

rules for which are relatively unclear and often contradictory of the general hydraulic equivalency

theory. Skeletonization can be performed manually or through the aid of computer algorithms,

however this theory is predicted based on steady state equilibrium and does not consider the

implications of pressure wave interactions throughout the system and at important boundary

conditions (Jung et al., 2007). Furthermore, it is difficult to simplify a model for all the worst-case

transient conditions, especially if the simplification precedes any analysis (Karney and McInnis,

1990). Once the steady state model for the surge analysis is finalized, assumptions and estimates on

several key transient related parameters have to be made. These may relate to: pump run times,

pump and motor inertias, acoustic wavespeeds, vapour pressures, valve characteristics, etc. These

Page 53: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

42

parameters are often uncertain and are also used as surrogates for other more variable and non-

modelled parameters such as air content, true energy dissipation, unsteady friction, sediment

content, etc. Even if all of the system characteristics and parameters are determined and/or

assumed, the final question for a transient analysis still comes down to what to design the system

for, and at what load?

Unlike steady state loading that is in the form of system demand and therefore supply, transient

loads (or events) arise in different forms through different sources, and it is therefore very difficult

to consider all potential risks. Nevertheless, a power failure event that impacts the flow conditions

has often (but not always) been found to be the most consequential of all transient events. Some

will argue that this event has achieved such a lofty status only since it is more likely to occur, but also

since its physics are easier to model within a numerical software package.

Power failures must be considered inevitable over the long life of a water and wastewater system,

because they are by their very nature unpredictable events. Thus the consideration of a power

failure precludes a more direct avoidance of its occurrence and substitutes as a worst-case surrogate

for potentially less damaging routine or non-routine pump and valve operations. Nevertheless,

power failures can occur at almost any operating condition, for which the variables may include: the

magnitude of the system demand and/or flow, the water level in reservoirs and tanks, the number of

pump stations operating, the number of pumps operating per pump station, and the status of

dedicated surge protection equipment. As systems and their representative models increase in size

and complexity, the number of design scenarios that arise from these numerous variables quickly

becomes overwhelming. As a result and an example, a computer model aided transient analysis may

typically consider a combination of scenarios based on the following options (i.e., variables):

i) Global system power failure or local pump station power failure;

ii) PHD or MHD (i.e., reservoir/tank filling); and

iii) Current or future year system characteristics (e.g., system layout, flow rates, etc.).

These transient analysis design variables lead to eight distinct scenarios and therefore to at least eight

possible design loads. The number of permutations can significantly increase depending on the

nature of the change in system characteristics. For example, if an analysis must consider a capital

Page 54: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

43

construction and phasing plan consisting of three new watermains, then the analysis may have to be

repeated for each phase of construction and therefore operation.

The design year and system demand typically determines how many pump stations and individual

pumps would operate during such a scenario, and therefore establish the conditions during which

the surrogate power failure event can occur. The ultimate surge protection recommendations and

design are then made on the worst-case level of risk from the scenarios considered. To get to this

ultimate design load, several predictions and assumptions have already been made on steady state

system demand, system characteristics, steady state system parameters, transient parameters and

transient events. Since real systems contain many unrepresented dissipation mechanisms, this

approach can lead to conservative and over designed systems which are rarely monitored or learned

from. In the end, a transient analysis using numerical modeling is only as good as its model inputs;

inputs which are truly not deterministic and therefore highly variable. Unfortunately, most practical

design procedures are not of an academic nature, and cannot afford the budget or the time to

consider all likely events. In other words, a comprehensive sensitivity analysis is typically not an

option. Lastly (and as is discussed in Chapter 7), even if the loads for a hydraulic transient analysis

can be determined, the industry stills struggles with quantifying the frequency of this loading.

Conventional detailed design is often thought of as being relatively restrictive, in that the decisions

made at this stage have significantly less impact than those made earlier on in the process.

Nevertheless, a detailed design that is driven by deterministic or worst-case loads can also have a

significant impact on the future cost and the performance of any water (or wastewater) system. The

deterministic design of these systems and the subsequent worst-case load design for transient

conditions have a potential to significantly increase the long-term cost through inadequate,

inefficient and/or highly conservative system components. Furthermore, these designs are rarely, if

ever confirmed or monitored. Instead, a surrogate in the form of computer aided hydraulic

modeling is seen as the optimal solution for design and rehabilitation. With the complexity of the

systems and their respective hydraulic models increasing, a new and complimentary approach for

transient analysis and design of existing water system components is needed. The most logical base

for the new approach is to learn from actual system evolution, and to use this knowledge to

determine future levels of risk.

Page 55: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

44

3.3.3 Wastewater Design Considerations

The previous subsections explicitly focused on some of the shortcomings of the current hydraulic

transient analysis and design practice in municipal water systems. Since pressurized wastewater

systems typically also fall in the realm of standard hydraulic transient analysis, they too require

dedicated attention. Wastewater systems are quite similar to water systems in that their fluid media

is after all, mostly water. The difference in the fluid media is primarily through the gas and sediment

content. However, the difference in the design and analysis of wastewater systems is based on other

system properties such as layout, operating methodology, and most importantly, design loads.

Unlike in the case of water systems, the operation of wastewater systems is not driven by the end

user or by downstream system demands, but rather through the supply, or more properly referred to

as the sewage “generation rate”. The generation rate consists of the actual sewage produced within

the upstream drainage area, and the external inflow and infiltration (I & I) that results from wet

weather flow (WWF) conditions. As a result, pumped wastewater systems are designed on the basic

premise that the pump station storage should be not exceeded. In other words, the pump station is

designed to convey the always changing inflow in order to ensure a maximum utilization of its

storage element’s volume. Therefore, actual wastewater pump station flow rates (and thus the

system flow rates) are always changing. The result is that sewage pump stations almost always

operate intermittently, and that the peak flow rates are only achieved during WWF conditions. In

other words, most wastewater systems are not optimally designed for regular (DWF) conditions, bur

rather for the peak (WWF) events.

Pressurized (i.e., pumped) wastewater systems are typically much simpler than water distribution

systems in that they are more often than not comprise a single pump station and a single (or

twinned) forcemain. The forcemain(s) typically discharge to a gravity sewer or outfall, via either an

open atmosphere manhole or a vortex suppressor. In the latter case, back pressure on the system

from the downstream end is greater.

Systems such as the ones described above are typically designed on two steady state level criteria.

The pump station itself is designed for a maximum discharge capacity that is governed by the

estimated peak factored WWF inflow rate. The forcemain itself is designed on the same possible

peak flow rate vis-à-vis minimum and maximum velocities in the pipe (variable throughout design

Page 56: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

45

standards, but typically between 0.6 m/s and 2 m/s). These steady state design criteria are then

extended to the transient analysis; an analysis that then determines the protection requirements via

the worst-case discharge load. The worst-case system load is typically modelled in such a way that

the discharge (i.e., the flow) rate is maximized. A peak flow rate and therefore velocity usually (but

not always) yields the greatest potential transient magnitudes, if a power failure event scenario is the

design event of choice. In order to achieve the maximum flow rate, the models are typically set with

the maximum number of pumps in operation and with the lowest system head losses. In order to

achieve the minimal system head loss, minor head loss is ignored and the friction head loss terms

such as the Hazen Williams C-factors are set at values equivalent for brand new pipes (e.g., 140 or

150). The shortcoming in this approach is that most peak flows are rarely, if ever, achieved within

the first part of the system’s life. When (or if ever) the peak design loads are actually achieved, the

system has aged significantly, and the friction in the pipe (especially in true sewage fluid media) has

increased. The conclusion here is that, most hydraulic transient analysis loads (and therefore

designs) are highly conservative, especially if one also considers the actual likelihood of a

hypothetical design scenario, such as the following:

A power failure of all pumps will occur when the system is newly constructed, when the

friction losses are minimized, and when the peak design WWF inflow rate is maintained

for a sufficient period of time such that the pump station outflow (i.e., discharge) rate is

equal to the peak inflow rate.

In addition to the conservative design loads, the current practice for numerical transient analysis of

wastewater systems typically assumes that the sewage fluid is essentially identical to pure water.

While mostly true, such an assumption is a poor one in the context of composition, sediments,

wavespeed, vapour pressure, and negative pressure potential.

Besides H20, wastewater also contains gases (e.g., air and hydrogen sulphide) and sediments that can

not only affect the capacity of the forcemain, but also its transient behaviour and performance. The

most direct transient impact of additional gases is the inherent reduction in the wavespeed. As

shown in Figure 3-1 below, the addition of air into a pressurized system can have a dramatic impact

on the assumed wavespeed.

Page 57: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

46

If not properly considered, a typical and reasonable assumption for the value of wavespeed that is

based on the pipe material (e.g., 1000 m/s for rigid pipe and 350 m/s for flexible pipe) can be very

dangerous on two fronts. First, it can drastically impact the predicted maximum and minimum

transient pressure envelopes, as a lower wavespeed significantly affects the pressure wave

characteristic. Second, in most cases a lower wavespeed would also yield a longer transient pressure

oscillation time and therefore it can significantly affect design and operational protocols that are

based on timing. For example, if a standby period following a power failure is predicted based on a

typical working assumption such as 10 L/a, where “L” is the length of the forcemain and “a” is the

wavespeed, then a lower in-situ value for “a” can significantly underestimate such a prescribed

standby time. A detailed numerical and physical example of this notion is presented in Chapter 6.

Figure 3-1: Wave Velocity v. Air Content (Wylie and Streeter, 1993)

The other mentioned assumption pertains to the vapour pressure (i.e., the boiling point) of the fluid.

While this parameter is dependent on both elevation and temperature, it is also dependent on the

physical composition of the fluid. For a wastewater system, the typically assumed value of 0.4 m

H20 may not be suitable, and therefore this typically requires a proper sensitivity analysis. An

example of such an analysis for a wastewater system is shown in Figure 3-2.

Page 58: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

47

Figure 3-2: Sample Vapour Pressure Sensitivity Analysis for a Wastewater System

In this case, the maximum transient pressures at certain points in the system were significantly

dependent on the vapour pressure when it approached a relatively high vale of 5 m H20. While it is

a distraction to this thesis to consider this system in detail, these numerical results do imply that an

important sensitivity exits in practice that is typically neglected in analysis. In summary, the assumed

value for the vapour pressure can potentially affect the predicted transient pressure envelopes, and

therefore a distinction between the modeling of a water and wastewater system must be made on

this account.

3.4 Lack of Confirmation and Monitoring

Chapter 2 establishes an introduction on the brief history of numerical hydraulic transient modeling

and also provides insights into some numerical modeling limitations, risks and shortcomings. The

key point raised is the often theoretical nature of such an exercise, and therefore the need for

improved field data derived validation, confirmation, and monitoring. This section provides specific

examples of some of these shortcomings and risks, in order to justify the need for more transient

field pressure monitoring. The section is broken down into two separate subsections: i)

confirmation, validation and calibration, and ii) performance monitoring.

Page 59: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

48

3.4.1 Confirmation, Validation and Calibration

Of what use is a model if it does not represent reality, or, at best, is blindly assumed to do so? While

the answer should be obvious, the (unfortunate) reality is that uncalibrated theoretical models are

often used in most detailed transient analyses and designs. As the previous sections have shown, a

numerical transient analysis is typically at the mercy of someone else’s (e.g., an owner’s) hydraulic

steady state model; a model that is typically not calibrated and may also be out of date. The direct

result of this fact is a poor starting base for a transient model. Nonetheless, for the purpose of this

section, the steady state model limitations are set aside and attention is given to additional and

subsequent transient model limitations.

Ideally, all theoretical models such as hydraulic transient models should be calibrated to match the

actual field conditions. In simple terms, model calibration can be defined as model adjustments that

result in a better match between actual and predicted system performance. In reality, the calibration

process is often difficult to achieve due to limitations in time, money and the quality of data.

Furthermore, the calibration of a hydraulic model is actually not a simple process and is often open

to error in application and judgement. As Walski et al. (2000) noted in the Water Distribution

Modeling Handbook, the subjective adjustment of system parameters to match a calibration

objective can lead to models being improperly calibrated. From the point of view of a transient

analysis, the word calibration is therefore quite misleading. Such an exercise is almost always

difficult to perform, and the end objective is almost always difficult to achieve. Comprehensive

hydraulic transient calibration techniques, including those such as genetic algorithms and inverse

transients, are still considered as academic and are limited to simple systems. Why then is the word

“calibration” always used to describe the action of correlating field data to numerical modeling data?

The answer is simple – there is a reassurance in seeing or hearing the word “calibration” before or

after the words “numerical modeling”. The inherent assumption here is the obvious belief that

models will likely always continue to just be theoretical and mathematical representations of reality.

In the realm of hydraulic transient analysis, the process of calibration should be subdivided into

three (3) distinct objective levels: calibration, validation and confirmation. The term “calibration”

should be reserved for the traditional comprehensive exercise in which the steady state and transient

conditions are completely matched to a wide range of system performance criteria and operating

conditions. The term “validation” should be used to refer to basic transient model adjustments such

Page 60: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

49

as those pertaining to key parameters such as roughness, wavespeed, moment of inertia, etc. The

term “confirmation” should simply be used to refer to field observations for the purpose of

assessing transient performance. In summary, the following field and numerical data comparison

levels should be adopted:

Confirmation – the use of field data to access risk and performance,

while using the model as a starting base.

Validation – the adjustment of specific and sensitive model

parameters for the purpose of ensuring some

agreement between the model and the field data.

Calibration – the use of specific comprehensive techniques(s) to

adjust model performance across a wide range of

operating conditions.

The full calibration level is very difficult to achieve and is almost always not warranted for most

analysis and design. However, the validation level of field work should always be set as the target

for any detailed transient analysis and design, in which the chosen primary approach is theoretical

numerical modeling. Unfortunately, this type of model validation is rarely performed and important

system decisions are solely made without the physical understanding and connection to the actual

system. To that end, the omission of the numerical and field data validation step in a transient

analysis can lead to a variety of errors and risks, including those pertaining to inadequate design and

extremely conservative design. A partial list of some potential errors and risks is summarized below:

• Actual versus model predicted steady state operating conditions (i.e., flows and pressures);

• Actual versus assumed acoustic wavespeed values, especially in systems containing a

significant amount of air (e.g., wastewater);

• Actual versus model predicted energy dissipation mechanisms and levels, including actual

contributions from interconnected systems (e.g., distribution network);

• Actual versus model predicted, calculated, or manufacturer prescribed pump and motor

moment of inertia values;

• Effects of non-steady friction on transient response;

Complexity & Accuracy

Page 61: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

50

• Actual versus model predicted or assumed valve timing and operation (e.g., SRV closure

times and set-points);

• Actual versus model predicted or assumed pump control timing (e.g., VFD ramp-up times

or pump control valve closure times);

• Actual versus model predicted transient event durations and their impact on design

recommendations (e.g., required post-event standby timing);

• Actual versus model predicted positive and negative transient pressure envelopes;

• Nature and impact of check valve slam;

• Actual versus model predicted negative pressure durations; and

• Much more.

The above list of considerations for a transient analysis illustrates the importance of performing

supplementary field work up to a minimum level required for validation. Without this, the

numerical modeling approach to hydraulic transient analysis is incomplete and risky. Chapter 6

provides explicit examples of numerical and field data validation using real life systems.

3.4.2 Performance Monitoring

This second subsection continues with the goal of confirming the need for transient based field

investigation and correlation. While the first subsection focuses on the traditional confirmation of

numerical models, this subsection focuses on the actual confirmation of system performance. Once

a system has been analyzed and designed, and once recommendations have been implemented, the

traditional approach has been to react only if a significant problem arises. In other words, the

hydraulic transient performance of systems is rarely monitored in the long-term, and previous

decisions are rarely, if ever, re-evaluated in light of future in-situ conditions.

Surge protection devices, such as those described in Chapter 2, are designed based on information

available at the time of analysis. Since all hydraulic systems are dynamic, such assumptions may no

longer hold true in the future as the system conditions evolve. As a result, it is logical to assume that

the adequacy of the original surge protection should be periodically revisited as the system ages.

Surge protection devices, equipment and strategies can comprise a significant capital cost in the

original system design, and therefore they should always be monitored for their actual in-the-field

Page 62: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

51

performance. Unfortunately, this is currently rarely done on a long-term performance assessment

basis. Primary surge protection equipment such as HACs or SRVs are inspected and maintained

based on prescribed intervals, but these maintenance plans are only geared towards ensuring that the

equipment is operational. In practice, little is actually done to monitor the performance of

prescribed transient protection and this is mostly due to the short-term frame of mind approach that

is often adopted by the owner, engineer and operator. Just like in the case of numerical model

validation, hydraulic transient field investigation strategies such as continuous pressure monitoring

can be (and should be) used to access the long-term performance of both the prescribed surge

protection, and the entire system. Examples of the possible benefits of continuous transient based

performance monitoring are as follows:

• Assessment of pre and post surge protection transient conditions;

• Assessment of equipment/device degradation and transient protection performance;

• New equipment calibration during commissioning stage;

• Recording and review of unexpected transient events and risks;

• Review of the impact of rare operational events protocols such as draining or filling;

• Determination of faulty surge protection equipment (e.g., non-performing air valve);

• Assessment of the quality of long-term air management;

• Recording of specific transient event frequency (e.g., power failures);

• Assessment of operational protocols following specific transient events;

• Information for improved valve timing;

• Long-term deterioration of pump performance, including vibration, trip frequency and cavitation;

• Frequency of unexpected transient events (e.g., power failure);

• Typical pump operating schedules;

• The nature and timing of the pump discharge valve operation;

• General operational protocols, including valve operation and pump changes;

• Steady state pressure changes (e.g., difference between pump(s) on and off);

• Long-term changes in the extent of transient wave energy dissipation across system;

• Long-term calibration of changing numerical models; and

• Much more.

Page 63: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

52

The above list of possible benefits for transient based performance monitoring illustrates the

importance of revisiting original designs and the ease by which system problems can be identified

before they pose a more significant risk to a system. The second half of Chapter 5 provides a few

sample statistics that can be derived from continuous transient pressure monitoring and Chapter 7

proposes a preliminary transient risk assessment methodology that is also derived from such an

exercise. The following chapter takes a brief aside towards the need for more field work by looking

into potential water quality issues arising from poorly performing transient protection systems.

3.5 Summary

The main purpose of this chapter is to expand on the previously established understanding of

hydraulic transients and hydraulic transient analysis approaches. The chapter begins by discussing

how numerical transient modeling is significantly dependent on the ever expanding field of hydraulic

steady state modeling. This discussion provides examples of the key assumptions and parameters of

steady state modeling and demonstrates how some of these could significantly impact any transient

analysis considerations that subsequently follow.

The chapter proceeds to provide a discussion on two of the most often overlooked hydraulic

assumptions and design considerations; the concepts of system demand and design loads. The

discussion centers on the industry’s general acceptance of vague and arbitrary demand quantities and

terms, and how these quantities are typically then used in combination with scenario based transient

loading to conduct a hydraulic transient (i.e., risk) analysis. The chapter concludes with a critical

discussion on the lack of actual system (i.e., in-situ) monitoring, both from the point of numerical

model calibration and overall system performance and risk assessment. In summary, the chapter

establishes the overall need for an increase in field based consideration of hydraulic transient

performance and risk for water and wastewater systems.

Page 64: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

53

Chapter 4 Water Quality Issues

4.1 Background

The advances in the general knowledge and/or awareness of transients, as well as the advances in

field based analysis, has given rise to a variety of important topics. One of these interesting topics,

albeit non-hydraulic in nature, is that of water quality during low pressure events. In this area of

study, hydraulic transients present themselves as a risk that is not in the form of excessive system

pressures. However, this chapter of the thesis provides a brief aside and illustrates how transients

can pose a different type of risk in the form of potable water contamination.

Legislation must be both proactive and active in the prevention and minimization of the risk that is

associated with the contamination of potable water in transmission and distribution systems. One

of the often unconsidered and/or discarded water quality concerns is that pertaining to pathogen

intrusion during negative transient pressure events. A negative pressure within a pipe is defined as a

pressure that is below atmospheric or zero gauge. During such an event, the pipe and the fluid

inside the pipe is exposed to the risk of outside contamination; contamination that comes in the

form of pathogen intrusion. Pathogen intrusion has been extensively studied and legislated, but the

risk still exists due to the uncertainties pertaining to chlorine residuals. An excellent study into and

recommendations against general pathogen intrusion in a distribution system is presented by

Kirmeyer et al. in the 2001 AWWARF project and publication no. 436.

The risk for pathogen intrusion during negative pressure conditions can, and has previously been

introduced through hydraulic transient events. As is shown through modeling and field

observations in the subsequently documented chapters, routine and non-routine operations of water

systems can continuously subject the potable water to low and negative pressures. As a result, the

overall risk of pathogen intrusion is simply increased during a low pressure transient event.

Several studies and publications have looked into the potential routes of pathogen intrusion during

transient events. One of the most extensive reviews of such conditions has been performed over

the years by the Ecole Poly Technique in Montreal. Using the isolated water network of the City of

Laval, the researchers conducted several transient field tests and water sampling in conjunction with

Page 65: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

54

several other organizations, including AWWARF. The best analysis of the risks of pathogen

intrusion during transient events is presented in a 2007 Ph.D. dissertation by Marie-Claude Besner.

As a quick background summary, the two most critical routes for pathogen intrusion during negative

pressure events are through:

1. Soil contamination via a high groundwater table; and

2. Contamination through flooded air valve chambers.

As part of transient pressure monitoring that was conducted in the Region of Peel (see Chapters 6

and 7 for more detail), a subset study was also conducted in order to determine the nature and risk

of contamination through flooded air valve chambers. Air valves are important system devices that

are unfortunately often misunderstood, misrepresented, and therefore misused (Radulj, 2007). The

purpose of an air valve in a water system can be three-fold: to routinely vent air during regular

system operation, to exchange air during transient conditions, and to expel air during filling. All

three of these air valve operating conditions require that the pipe and system be exposed to the

environment. As a general note, most air valves are typically installed within dedicated valve

chambers, and in most cases at locations at which the pipe profile is a high point.

The previously mentioned risk of contamination is only present in the case where the pressures in

the pipe are lower than that of the external atmosphere. In other words, the risks exist only if the

internal pressures are negative. Flooded air valve chambers provide an easy pathway for

contaminated water to enter the potable water system during the period of time at which the internal

pressures are negative. The level of risk is a function of the magnitude of this negative pressure

(e.g., partial vacuum to full vacuum), its duration, and the frequency of occurrence. This overall risk

usually comes in the form of pathogen intrusion.

Unlike the slow process of soil contamination via a high groundwater table, pathogen intrusion

through flooded air valve chambers can be and has been shown to be quick. The severity (i.e.,

frequency and concentration) of the pathogen determines the risk of the contamination, because

most potable water systems in North America are operated with a certain level of chlorine residual.

If the pathogen concentration is significant, the system is at a higher risk of intrusion. The case

study presented at the end of this chapter analyzes several flooded air valve chamber water samples.

The pathogens considered in this analysis are briefly discussed in the following section.

Page 66: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

55

4.2 Important Pathogens

The following section provides a brief description of the likely and potential pathogens that can

pose a risk to a water system through flooded air valve chambers. The description of the following

organisms is derived from a variety of sources, including Viessman et al. (2005), MWH (2005) and

Fraser et al. (2010): Total Coliforms, Escherichia Coli, Enterococci and Clostridium Perfringens.

Total Coliform

Total coliform refers to coliform bacteria from three origins: feces, soil and other origin. Coliform

bacteria are indicator organisms in public water supplies and are evidence that the water supply has

been contaminated by human or animal (i.e., warm-blooded) feces. Coliform bacteria are used as an

indicator organism because laboratory analysis for pathogens is difficult to perform and for some

pathogens it is impossible to perform. If a sample of water tests positive for total coliform it is

subsequently tested for the presence of fecal coliform and Escherichia coli.

Escherichia Coli (E. coli)

E. coli is a bacterial pathogen that belongs to the Enterobacteriaceae family. Escherichia coli live in

the intestinal tract of warm-blooded animals and are normally beneficial to the human body because

it suppresses the growth of harmful bacteria and even produces vitamins. There are varieties of E.

coli, however, that are pathogenic in human beings. E. coli can enter a water system through runoff

containing animal feces, and evidence suggests that E. coli may potentially also survive and grow in

distribution system biofilms.

Enterococci

Enterococci are bacteria that are found in the intestines of both humans and animals and they

generally do not grow in the environment except in tropical climates. They are a normal part of the

intestinal flora but are also the cause of some serious infections. Enterococci bacteria are anaerobic

organisms that can grow in many different environments and have been shown to survive longer

than E. coli.

Page 67: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

56

Clostridium Perfringens

Clostridium Perfringens is a micro organism that grows both on food and in the environment. The

organism produces a toxin that if ingested can produce non-inflammatory gastroenteritis. Because

their spores persist for long periods in the environment, C. perfringens can result in false positives

and may be less suitable as an indicator of recent fecal contamination.

4.3 Case Study and Discussion

With the above concerns in mind, a water sampling and testing study was undertaken in the Region

of Peel in order to determine the nature and risk of pathogen intrusion. Several air valve chamber

locations were chosen in consultation with the operations staff and with previous condition

inspection reports. The sampling locations were chosen from a master list of problematic air valve

chamber locations. This master list was narrowed down to a shorter list of accessible chambers (i.e.,

chambers with easy access, not at a busy road, etc.); most of which were then visited and inspected

prior to the sampling. The goal of this selection process was to find air valve chambers that were

often flooded.

In total, standing water was sampled and tested at ten (10) air valve chambers in the Region of Peel,

and these locations are shown in Figure 4-1. Given the time constraint associated with the sampling,

shipping, and testing, the majority of the chosen chamber locations were concentrated in the East

side of the Peel transmission line system. The sampling took place on September 29 and 30 of 2008,

and six (6) 1 L sample bottles were collected at each of the locations. The weather conditions during

the first day of sampling were dry, but the day did follow a week of rain. The second day was

extremely wet, but most of the samples were taken in the early morning and prior to the rainfall.

The collected samples were kept cold and shipped via same day delivery to the Institut Armand-

Frappier (INRS) in Laval for testing. This is where the previously mentioned studies originated, and

hence why their valuable experience was drawn upon. The samples were all tested for the four (4)

previously discussed pathogens. The water quality test results are shown in Table 4-1, and are

compared with a similar study in the City of Laval (courtesy of Marie-Claude Besner) in Figure 4-2.

Page 68: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

57

Figure 4-1: Air Valve Chamber Water Sampling Locations

Page 69: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

58

Table 4-1: Air Valve Chamber Water Sampling Test Results

Figure 4-2: Air Valve Chamber Water Sampling Test Result Comparison

Sample IDTotal

ColiformsE. coli Enterococci

Clostridium

perfringens

HN2100 Chamber # 1A 16,500 50 3,110 6

BS1500 Chamber # 2 1,100 <5 395 <2

BS1500 Chamber # 8A 1,950 255 38 <2

BS1500 Chamber # 8 165,000 <5 10 <2

EB1050 Chamber # 16 12,000 <5 6 <2

BS1200 Chamber # 15 650 <5 6 <2

NB900 Chamber # R1 21,500 5 170 <2

NB900 Chamber # 8B 450,000 135 1,240 4

NB900 Chamber # 9B <5* <5* 120* <2*

SV1050 Chamber # 13 1,365,000 4,500 4,260 2

- All results are in cfu/100ml

*Turbid sample, possible interference

Page 70: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

59

The above results are typical of very dirty storm water runoff; runoff that may or may not contain

animal fecal matter. The tested pathogens are good indicators of fecal coliforms and therefore may

not be the best indicators for other organisms and viruses. Expert review of the above results has

preliminarily concluded that the risk does exist, but that more comprehensive studies should be

performed. This has, and will continue to bring the risk attention to water system legislators. It

should not be a surprise if local authorities impose their own legislation that directs that all air valve

chambers be maintained in a dry state.

The selected pathogens would most likely be disinfected by the chlorine residual, if proper chlorine

residual is present and if mixing is sufficient in the pipe. However, if these pathogens are indeed

present in these concentrations, then other more dangerous pathogens may be as well. Some of

these other pathogens cannot be disinfected by chlorine residuals. Furthermore, if these other

pathogens have this same intrusion pathway (i.e., through air valves during negative pressures), then

this water quality risk is undoubtedly present. The above nature (i.e., locations and timing) of

sampling is in no way scientific, comprehensive or conclusive, and therefore it may not be indicative

of the risk across this system, or other systems. Many factors such as weather, location, chamber

condition can affect the test results. As a result, a more comprehensive investigation is highly

recommended in order to remove any liability associated with not being proactive, but more

importantly, to protect the public and those dependant on the municipal water supply.

As additional proof of the inherent risk and uncertainty, these results can also be statistically

compared to the previously mentioned Laval study, and to typical raw water and wastewater results.

These comparisons (again courtesy of Marie-Claude Besner) are presented in the following figures,

and are broken down by pathogen. The high variability in the Peel results is indicative of the

relatively small sample size, and the larger size and complexity of the system.

4.4 Summary

This chapter provides a brief aside to the transient analysis theme of the thesis, but does so with a

transient risk and field work related topic pertaining to pathogen intrusion into potable water

systems through flooded air valve chambers. This general topic of pathogen intrusion during low

pressure transient events has been at the forefront of current research and this chapter demonstrates

through a case study in the Region of Peel that the typical risk of intrusion through air valves is

Page 71: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

60

indeed quantifiable, albeit at the same time relatively mild due to the surface runoff characteristics of

the standing water.

Figure 4-3: Comparison of Total Coliform Concentrations

Figure 4-4: Comparison of E. coli Concentrations

T ota l col i form s

M edian

25%-75%

Non-Outl ier Range T CLaval T CPeel

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

5.5

6.0

6.5

To

tao

l co

lifo

rms (

log

CF

U/1

00

ml)

E. co l i

M edian

25%-75%

Non-Outl ier Range ECLaval ECPeel ECRaw ECWW

0

1

2

3

4

5

6

7

8

E.

co

li (lo

g C

FU

/10

0m

l)

Page 72: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

61

Figure 4-5: Comparison of Enterococci Concentrations

Figure 4-6: Comparison of Clostridium Perfringens Concentrations

En teroc oc ci

M edian

25%-75%

Non-Outl ier Range EntLaval

EntPeel

EntRaw

EntWW

0

1

2

3

4

5

6

7E

nte

roco

cci (lo

g C

FU

/10

0m

l)

Clostrid ium perfringens

M edian

25%-75%

Non-Outl ier Range CPLaval CPPeel CPRaw CPWW

0

1

2

3

4

5

C.

pe

rfrin

ge

ns (

log

CF

U/1

00

ml)

Page 73: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

62

Chapter 5 Advances in Field Work

5.1 Traditional Field Work Approach

The general acceptance of, and the movement towards numerical hydraulic modeling has been partly

due to the advances in the accuracy, computational speed, and overall user friendliness of numerical

software packages. Another key and important driving force towards this change has been the

traditional difficulty (and at times the cost), of performing the desired and/or required field work.

Field work has generally been difficult to perform due to several reasons. First, it always has and

still does, require proper planning and scheduling. The scheduling task requires the co-operation of

multiple parties, including the system owner, the system operator, and other consultants and/or

researchers. Without this, field work is typically either rushed or significantly delayed, and if delayed,

it is typically always hurried during the most critical stage. Second, field work is always at the mercy

of the actual in-situ conditions. For example, if the work is being performed outside it is likely to be

affected by the weather. Weather conditions such as extremely low temperatures or excessive

rainfall can make even a simple data logger installation difficult. Similarly, even if the work is

performed indoors (e.g., within a pump station), it is always dependent on the physical and operating

conditions of that day. Physical conditions may include the lack of access, power source, pressure

taps, and dry space. The operating conditions can dictate what can and cannot be done. For

example, only a certain number of pumps may be operated when the water level in a downstream

reservoir is high. All of these general constraints have made the historical and the current field work

practice challenging.

Traditional or historical transient pressure monitoring relied on a variety of instruments that were

not only bulky, but also complicated. Some examples of these include transducers whose signal was

captured by an electronic transfer box and then recorded by a chart reader. While accurate, a device

such as this was not easily portable or installed. Furthermore, every individual component requires

proper and individual calibration. Lastly, all of the individual components also require the

transmitted signals to be individually synchronized and correlated by the receiving units.

Page 74: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

63

Advances in technology, and more specifically in electronics, has clearly made a positive impact

towards the reduction in the size of these units. The modern pressure monitoring units typically

comprise three key components: a pressure transducer, a data logger and a power source. The

pressure transducers are also often referred to as electronic pressure gauges, pressure sensors,

pressure transmitters, etc. However, these pressure transducers are specifically designed for the

recording of transient pressures, in that their speed of recording (typically expressed as a frequency

in Hz) is higher than normal. Nonetheless, the modern sensors and loggers have allowed for a

much simpler and less invasive installation within a water (or wastewater) system, and have therefore

re-enabled the previously forgotten option of assessing the transient pressure conditions of a system

through the use of field work. The following section describes and compares the commercially

available modern transient pressure monitoring equipment, for the purpose of identifying a

technology capable of assisting in the long-term performance evaluation of fluid systems.

5.2 Modern Pressure Monitors and Comparison

The transient pressure monitor market is not significant in size, and therefore most technological

advances in this area have been as a result of either research or individual built-for-purpose

application of a proprietary idea. The advances in these technologies have arisen via different and

generally more profitable industries, including heating, cooling, and transportation. These other

industries have traditionally experienced the need for high frequency and real time data.

Nonetheless, there currently exist several prominent instrumentation manufacturers that officially

produce and market transient pressure monitors for a wide range of industries. Table 5-1 and Table

5-2 present a two-page comparison summary of the most popular transient pressure monitors that

are currently available on the market for the general use within the water and wastewater industry.

The comparison is made based on the goal of continuous long-term pressure monitoring.

The comparison tables include the following pressure monitoring units, each comprising a column:

Pipetech TP-1 (Pipetech), Omega CP-PRTRANS (Omega), Radcom RDL1071 L/3 (Radcom),

Telog HPR 31i (Telog), Madgetech PRTRANS1000 (Madgetech) and Cla-Val X142PT (Cla-Val).

While marketed differently, the Omega and Madgetech units are actually the same, and therefore will

only be referred as Omega from here on. The following paragraphs briefly describe and discuss

each of the pressure monitor features (i.e., the rows), and ultimately attempt to determine which unit

is best for what type of application.

Page 75: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

64

Table 5-1: Pressure Monitor Comparison Summary

Page 76: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

65

Table 5-2: Pressure Monitor Comparison Summary (cont’d)

Page 77: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

66

Manufacturer

The manufacturers of transient pressure monitors range from small research companies to large

scale water and wastewater equipment providers and instrumentation companies. While all of the

manufacturers have distributors around the world, all but Radcom (U.K.) are actually headquartered

in the U.S.A. There is no clear advantage with respect to name or location.

Base Price

The base price comparison includes the minimum number of components required to properly

install and run the equipment. This price in Canadian dollars typically includes the pressure

transducer or sensor, data logger, power source, data download (e.g., cable) and software. The

Omega and Cla-Val monitors come in under the $1,000 mark, while the Radcom and Telog loggers

are essentially priced in the $2,000 to $3,000 range. The Pipetech unit clearly does not win in the

price category, with its $6,000+ price point. One point worth noting is that the listed prices are

those as quoted by local distributors. As a result, the actual price from the original manufacturer

(i.e., without the middle man mark-up) would likely be less. Nonetheless, the price advantage is to

Omega and Cla-Val.

Varieties, Options and Installation

The purpose of this category is two fold. First, it is to list and/or acknowledge additional (i.e., non-

basic) options and models. Second, its intent is to also list unique and important benefits and

complications for actual field installations. Most units come with an optional submersible sensor,

while only some of the units come with submersible data loggers. This option is important for field

installations within chambers that are, or can potentially become, flooded. The Pipetech unit has an

advantage with the additional options, but due to its bulky size, it is also more difficult to install and

store. The Telog unit has the advantage with its easy hydrant connector feature.

Sensor Information

While most of the units can probably be reconfigured with any pressure sensor or gauge, this

category compares the basic sensor that is provided with the unit. The sensor construction is highly

variable and can include ceramics, silicon, and strain gauges. While the analogue gauge for the

Radcom is out of date, there is no clear advantage for the rest. A proper comparison requires a

long-term performance analysis.

Page 78: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

67

Sensor Range

A variety of pressure sensor ranges can be purchased for most units, and these should typically be

chosen for the specific application. For example, since the accuracy is based on the full pressure

range, a high pressure range sensor may not be accurate enough for low pressure applications. The

key aspect of this category is whether or not the sensors can record negative (i.e., sub-atmospheric)

pressures. The advantage in this case is to the Pipetech, Telog and Cla-Val units.

Sensor Accuracy

As partially noted above, the accuracy of the pressure recording is dependent on the range of the

sensor. The accuracy of the sensor is typically given as a percentage (plus or minus) of the full scale

or range. Therefore a typical 0.25% value for the sensor accuracy is less important for smaller

pressure ranges. With its lower 1% accuracy, the Cla-Val unit is at a disadvantage to the others;

other units between which there is no clear distinction.

Data Logger Features

This category examines additional data logger features that are not separately analyzed. While not all

of these are listed, the Pipetech, Telog and Cla-Val have inherent positive features that make them

slightly better than the other two.

Data Download

The recorded and stored data is typically downloaded with a wired connection; a connection which

every one of the units is capable of. However, the Pipetech also has a wireless download feature via

a portable PDA that gives it a partial advantage over the others. The advantage is only partial,

because the wired connection option for the Pipetech is via a difficult computer LAN connection.

The Omega and Cla-Val units have an advantage with the easy to use USB connection and

download, which is more modern and faster than the serial connection of the other two units.

Software and Data Type

All software is capable of properly opening and displaying the data. However, every one of the

software packages have unique issues that make them difficult to use at times. Nonetheless, the

advantage in this category goes to the Pipetech unit because the software converts the stored data to

a database (rather than text file) format. Databases are excellent ways of storing a large number of

Page 79: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

68

data points. While such a system may not be the simplest for short duration recordings, it is indeed

the best for long-term continuous pressure monitoring.

Pressure Units

The pressure readings are recorded as signal outputs from the transducers, and the data loggers then

store the data in different forms. In the end, the most important aspect of this category is whether

or not the software package can display a variety of units. The Pipetech unit is at a clear

disadvantage with its psi (gauge) only display, while the Radcom and Telog units have the advantage

with the user defined unit feature which allows the data to be presented in any pressure unit.

Recording Frequency

The frequency of recording is what distinguishes transient pressure monitors from the regular and

standard pressure transducers. High frequency recording is required in order to properly capture the

properties of the transient pressure waves and events. If the frequency is not high enough, then the

resulting pressure profiles will not be detailed enough, and would possibly also miss recording the

maximum and minimum transient pressures. The recording frequency should be distinguished from

the sampling frequency (or rate). While a monitor can sample at a high frequency, it may not

actually be able to record or store the data at such a rate. With respect to absolute magnitudes, the

Pipetech and Omega units have a clear advantage because of their 100 Hz (i.e., 100 times per

second) recording frequency. Similarly, the Cla-Val unit is limited to only 8 Hz (8 per second). The

last point worth mentioning is that a high frequency such as 100 Hz is not required for most water

and wastewater applications, since a lower frequency such as 20 Hz can typically provide the same

level of detail. Furthermore, certain intermediate frequency ranges can be subject to electrical

interference from other sources at the location of installation. Such things as fluorescent lighting

and pump vibrations can interfere with the pressure transducer signals and cause erroneous readings.

High Frequency Control

The most important feature for a transient pressure monitor during long-term transient pressure

monitoring is the capability of only recording the transient pressures at the high frequency. While

continuous high frequency recording is neat and interesting, the quantity of the resulting data is

excessive. This leads to extremely large data files, and longer processing and analysis times. As a

result, a transient pressure monitor should ideally be able to record at two different rates: slowly

during periods of low pressure fluctuation (i.e., steady state) and fast during periods in which the

Page 80: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

69

pressure is unsteady (i.e., transient). This category evaluates the frequency control logic. The clear

winner is the Pipetech unit for its moving window statistical analysis approach. The frequency

control for most of the other units is based on a pressure band, range, or window; set points which

are all quantified on a single starting value of pressure. The following two sections break this

frequency control capability down to start and stop record triggers.

Start Record Trigger

The start record trigger is the type of control logic that tells the data logger when to record at the

desired high frequency. As mentioned earlier, the logger should only record at high frequency

during the period of the transient event. Most start record triggers are based on absolute pressure

differences (negative, positive or both). However, the different monitors determine the absolute

pressure difference start points on a wide range of characteristics, including: current pressure values,

range of previous pressure values, specific number of previous pressure samples, and preset time

period of recording. Some of the units also contain start record triggers based on pressure bands.

Nonetheless, the Pipetech unit is the clear winner in this category because of its statistical approach

that allows the user to set the start record triggers based on both absolute pressure and standard

deviation. These metrics are calculated based on a user prescribed number of previous samples.

Stop Record Trigger

While most units are capable of reasonably distinguishing between a ”regular” pressure and a

pressure that meets some of the start record trigger criteria, most of the units are actually not

properly capable of stopping the high frequency of recording at the end of the transient event. For

example, the Cla-Val and Radcom units simply continue to record at the high frequency once the

start record trigger has been met and maintained. The absolute pressure value stop record trigger

for the Omega unit does not take into account that future background (or steady state) pressures

may not actual be the same as those during the initial stage. While, an improvement, the predefined

time period based stop record trigger for the Telog unit requires the user to understand the duration

of a transient event prior to witnessing it. As a result, the Pipetech unit also wins in this category

due to its standard deviation based stop record trigger. Nonetheless, even this trigger is not

foolproof in that it is dependent on the other previously mentioned statistical settings. A standard

deviation that is based on a set of high frequency recordings may be subject to premature stoppage

at a point at which the transient pressures are actually in the vicinity of the background pressure

Page 81: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

70

magnitudes (i.e., of same magnitude but still transient in nature. (What is really needed here is a

standard deviation based stop record trigger that also takes into account a minimum duration.)

Other Set Points

This category examines other record features that do not necessarily fall within the start or stop

control logic. In addition to the Pipetech unit, the winners in this category are also all the other

units except for Radcom. The most useful feature is that of a timed and/or delayed start for the

recording.

Power Supply

The properties of the prescribed power supply determine the length of time for which the unit can

be installed in the field. The specific Lithium Ion batteries for the Omega, Telog and Cla-Val units

are not only portable and built-in, but also last for a significant duration. Most of these can last in

excess of a year with a medium frequency range of recording. Units such as the Cla-Val are easily

charged via an USB connection. The Pipetech unit is at a significant disadvantage due to its

significant power requirement. While it is typically powered via DC power, its bulky backup battery

options are limited in their recording duration.

The above comparison summary has served to provide an understanding on the features that the

modern suite of transient pressure monitors is manufactured with. While an ideal unit does not yet

exist, each of the listed units has their own advantages and disadvantages. Some units are better

suited for short-term transient pressure tests, while others for long-term continuous transient

pressure monitoring. Some units are easier to install while others are easier to calibrate and/or

maintain. Nonetheless, for the sake of comparison, Table 5-3 ranks the five (5) different transient

pressure monitor units based on the previously discussed and compared categories. The ranking is

based on the single purpose of continuous pressure monitoring and is rather subjective through

direct and anecdotal experience of the author.

The units with the best feature in each category was assigned a value of three, the worst with a value

of one, with those in between being assigned an intermediate value of two. The rankings are in no

way scientific since the categories were rather arbitrary and at times repetitive, and because the

categories were equally weighed. Nonetheless, even with its excessive cost, bulky size and significant

power requirement, the Pipetech TP-1 can be said to be the best commercially available monitor for

Page 82: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

71

long-term continuous transient pressure monitoring of water and wastewater systems. On the other

hand, the Radcom RDL1071 L/3 significantly trails behind the rest of the units. Overall, if the data

control logic and features of the Pipetech TP-1 could be combined with the ease of use features

from the Cla-Val or Telog units, the industry would then have close to an ideal device for

continuous transient pressure monitoring. (It is likely that such a device already exists, but that it is

not commercially available.)

As a cautionary note, the author admits to a partial (yet unintentional bias) that derives from

different degrees of direct and indirect experience with the five listed units. As a result, the author

accepts no responsibility for the subjective ranking of these units at this time. Nonetheless, while

different, each unit can and does serve a purpose in some form of transient pressure monitoring.

For example, if the investigation goal is to record transient pressures during a quick field test, then a

transient pressure monitor capable of recording at high frequency for the entire time may be all that

is required. In summary, this comparison and ranking is made solely on the requirement for long-

term transient pressure monitoring.

Table 5-3: Transient Pressure Monitor Ranking for Long-Term Applications

Page 83: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

72

5.3 Pipetech TP-1 Transient Pressure Monitor

As previously discussed, the Pipetech TP-1 Transient Pressure Monitor, from herein only referred to

as TP-1, is the best commercially available unit on the market for the purpose of continuous long-

term transient pressure monitoring of water and wastewater systems. This section describes the

recording control logic and features of the TP-1 device in order to provide a better context for the

long-term transient pressure monitoring data, analysis, and discussion that follow.

The TP-1 device and associated equipment is specifically designed to provide detailed transient

pressure profile information, including maximum and minimum pressure magnitudes, event

duration, and event character (including phase, etc.). The TP-1 equipment comprises several key

components that are required for a typical installation within a pump station:

1. High-Frequency Pressure Transducer (Sensor) - capable of detecting pressures

between -14.7 psi (-10.4 m H20) vacuum and 500 psi (351 m H20), at rates of up to

approximately 100 Hz. The sensor connects to the TP-1 logger through a wired

connection cable.

2. TP-1 Smart Data Logger and Control Box - capable of monitoring the pressures

measured by the sensor while only recording when prescribed (minimum) statistical

start and stop triggers are met. It also allows for wired data download using a laptop,

wireless data download using a PDA, or external remote access via the internet.

3. Deep Charge Battery and/or UPS - provides power to the control box, even during a

system power failure. Two batteries can be connected in parallel to provide extended

and/or sole power for a remote installation such as a transmission line chamber.

4. PDA Unit - for changing record settings and time, and for downloading the data from

the control box.

5. Wi-Fi Antenna - for transmitting the signal to the PDA.

6. Manual Pressure Gauge - for calibrating the TP-1 unit.

7. 2-in-1 Modem and Router – for remote access connection via the internet.

Page 84: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

73

The above discussed components of the TP-1 monitors are shown below through sample field

installation photographs.

Outdoor (Left) and Indoor (Right)

100 Hz Pressure Transducer

Manual Pressure Gauge

Back-Up Battery Power

TP-1 Control Box

Figure 5-1: TP-1 Transient Pressure Monitor Components

Figure 5-2: Typical TP-1 Installation in the Field

Page 85: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

74

The simplest (and often most beneficial) installation of a TP-1 is achieved at a water or wastewater

pump station. The overall benefits of an indoor installation are significant, and they include: easy

access to a primary power source, ease of entry, protection against unfavourable weather and field

conditions (e.g., frost or flooding), etc. Within a pump station, a TP-1 is typically best installed on

either the common discharge and/or suction header pipe. These common pressure locations are

typically key for determining the timing, magnitude and frequency of transient events caused by

pump operations, pump changes, and power failures. For example, a common discharge header

location is better than an individual pump discharge pipe location because it is downstream of the

check valve(s). As a result, such a location enables the recording of all transient pressures in the

system, even if a specific pump is not in operation.

In an ideal installation, the pressure transducer should be installed at the bottom (or side) of the

pipe, where gasses such as air cannot build up and subsequently affect the transient pressure

measurements through a dampening effect. If such a tap location is unavailable, the air in the

transducer connection line must regularly be bled out. This requires that the transducer not be

connected in a direct loop, in which the air cannot be manually released. In other words, a T-

connection such as that shown in one of the previous figures is best.

Most sensors are factory pre-calibrated, while others must be re-calibrated following the installation

especially if previously used. Upon a successful installation, the following steps are taken for the

quick calibration of each unit:

1. Isolate the transducer using the fittings and release all pressure.

2. Set the TP-1 pressure in the monitor to zero using the PDA.

3. Reintroduce the transducer to the actual system pressure.

4. Bleed all air from the fittings.

5. Using a manual gauge (or regular digital gauge if installed) as a benchmark,

adjust the TP-1 pressure accordingly in the PDA.

6. Synchronize the TP-1 time with the preset time on the PDA.

A true (i.e., initial) calibration of any pressure transducer should expose the transducer to a wide

range of pressures, including the minimum and maximum pressures that each unit is capable of

Page 86: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

75

recording. This is typically best achieved using a hydraulic hand pump, and through a step-wise

calibration procedure, as shown in a pressure versus time plot in Figure 5-3.

Figure 5-3: Sample Calibration Pressure Profile

Each pressure transducer is connected to the TP-1 control box, which dynamically calculates the

average pressure detected by the sensor and then uses this information to determine the rate at

which it logs the readings. The following parameters are the user-defined control features, and are

illustrated through the PDA’s input interface in Figure 5-4:

• Start Record: indicates whether the TP-1 should record at the high-frequency rate as

soon as it starts (manual) or only when a deviation from the background pressure is

experienced (auto);

• High Frequency (msec): the rate at which transient events are recorded;

• Start Threshold (SDx10): indicates the amount that the pressure can deviate from the

background level standard deviation before being considered as a transient pressure

(and therefore event);

• Absolute Difference (psi): indicates the minimum change in pressure required for the

consideration as a transient pressure (and therefore event);

Page 87: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

76

• Stop Record: indicates whether recording of transient events stops after a defined

interval (manual) or is controlled by threshold and absolute difference values (auto);

• Manual Record Time (sec): indicates how long transient events are recorded for, if

the Stop Record is set to manual;

• Stop Threshold (SDx10): works

similarly to the start threshold, but

indicates when the high frequency

recording should stop;

• Background Sample Rate (msec):

indicates how frequently the

background pressure is calculated;

• Background Record Rate (sec):

indicates the rate at which the samples

are recorded while the pressure is

within the background levels; and

• Number of Samples Averaged:

determines the sensitivity of the

background pressure to normal

fluctuations.

The proper selection and calibration of the above settings and parameters is crucial because it can:

1. Eliminate random pressure noise associated with steady state (background)

pressures; pressures that are always changing;

2. Ensure that all significant transient events are recorded;

3. Ensure that all transient events are recorded from the beginning to the end;

4. Eliminate the need to always record at the highest frequency and sample rate,

thereby reducing the size of the data file(s); and

5. Minimize the amount of power being drained from the battery supply (if solely

battery powered).

Figure 5-4: TP-1 Pressure Monitoring Equipment Settings

Page 88: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

77

The following table summarizes two samples of the initial settings that were used for two pump

station installations in the Region of Durham. These settings were ultimately determined through

trial and error during the first week of installation and were subsequently adjusted on an individual

installation basis.

Table 5-4: Sample TP-1 Pressure Record Settings

Setting/Parameter Ajax WSP Harwood PS

Start Record Mode Auto Auto

Start High Frequency Rate (msec) 100 100

Start Threshold (SD X 10) 10 10

Absolute Difference (psi) 6 5

Stop Record Mode Auto Auto

Manual Record Time (sec) 180 5

Stop Threshold (SD X 10) 2 2

Background Sample Rate (msec) 500 500

Background Record Rate (sec) 120 120

Samples Averaged 50 50

Once the TP-1 units are calibrated, and after the data has been recorded and downloaded, it must be

analyzed. In order to analyze the data, a graphical software package by the name of QAnalyze is

used to produce graphs of Pressure (psi) versus Time (date and time). The blue data is classified as

steady state (i.e., background) pressures and the red data is classified as transient (i.e., unsteady)

pressures. The above calibration settings are the main variables (albeit, user defined) that determine

the type of pressure and therefore the colour of the plot. More specifically, if the settings are too

sensitive then the data will be mostly red (transient). If the data is not sensitive enough, then the

data will mostly be blue (background). The key is to prescribe the settings so that all significant

transient events are recorded in full, and so that minor noise in steady state operation (i.e., plus or

minus a few psi) is not recorded. The following two figures show the difference between sensitive

and less sensitive settings, for two different locations.

Page 89: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

78

Figure 5-5: Pressure v. Time Plots for Different TP-1 Settings - Sensitive (above), Less Sensitive (Below)

Similarly, the scales for the Pressure and Time axes can be manually adjusted (i.e., zoomed in and

out), as to allow for a more detailed representation of any specific transient event. For example, the

following four figures show the same event, but in progressively greater detail (i.e., shorter time

frame and smaller scale).

Page 90: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

79

- Longest Time Period (Top Left) to Shortest Time Period (Bottom Right)

5.4 Sample Data

This section aims to provide actual sample field data consisting of transient pressure monitoring

results. All sample pressure series graphs shown in this section were acquired in the field using the

previously discussed Pipetech TP-1 transient pressure monitoring technology. The graphs present

the recorded pressure in the units of psi, as per the recording logic described in the previous section.

This section is divided into the following three (3) subsections:

i) Long-Term Histories – Samples of transient pressure recordings over several

days and/or months;

ii) Individual Events – Samples of transient pressures recordings during individual

routine or non-routine events; and

iii) Unique Events – Samples of transient pressure recordings during unique system

events.

Figure 5-6: Pressure v. Time Plots for the Same Event but with Different Time Scales

Page 91: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

80

5.4.1 Long-Term Histories

Long-term transient pressure histories can provide excellent insights on the daily, monthly and yearly

operational patterns of water and wastewater systems. The TP-1 pressure monitoring equipment is

ideally suited to record transient pressure histories by actively delineating between steady state and

transient pressures, thereby conserving the recording memory. Transient pressure history plots (via

the inherent transient pressure database recordings) can be used to assess the true long-term

performance of systems by recording a variety of different types of events, including routine or non-

routine, planned or unplanned, and frequent or infrequent. In the end such data can be used to

complete a transient risk assessment, and as discussed in Chapter 7, can also be instrumental in a

proposed metric such as the Transient Risk Index (TRI).

Figure 5-7 presents a 5-month transient pressure history at Hanlan PS in the Region of Peel,

Ontario, Canada. Hanlan PS is an older station in a pressure zone that is currently experiencing a

high rate of water demand growth. The combination of its age, increased flow output, transmission

system connectivity, and lack of dedicated transient protection, makes this station a high transient

risk location within the Peel system. This can easily be observed in the 5-month pressure history; a

history that contains a significant number of transient events (shown in red). The normal (i.e.,

steady state) operating pressures at the discharge point typically varies between 55 psi and 65 psi

(depending on the number of pumps in operation), but in this time period the positive transient

pressures often exceeded 80 psi and the negative transient pressures often reached a significant level

and duration of partial vacuum conditions. Hanlan PS is currently in the process of a capacity and

equipment upgrade, one which will also see the addition of a significant HAC volume. The addition

of HACs will act to control the rate, magnitude, and frequency of transient pressure fluctuations,

and therefore the transient pressure monitoring will be able to provide a clear comparison of pre

and post upgrade conditions.

Figure 5-8 presents a sample 4-month transient pressure history at another key pump station in the

Region of Peel, called Lakeview. The Zone 2 system of the HLPS at the Lakeview WTP is the

source of the highest pressure and flow rate in the Peel system, and would therefore theoretically be

at a high risk due to transients. Fortunately, the station is protected by HACs with a 400 cu. m

volume, which act to control and dampen any significant pressure fluctuations arising from transient

events such as power failures, demand changes, and routine pump operation. When compared to

Page 92: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

81

the Hanlan PS plot in Figure 5-7, the sample transient pressure history at Lakeview can be classified

as being less severe, especially if one considers the more complex hydraulic conditions and the fact

that y-axis scales for the two plots shown are actually different. The Lakeview HLPS Zone 2 system

typically operates at normal pressure range of 160 to 170 psi and it rarely experiences any significant

positive or negative transient pressure fluctuations.

Figure 5-9 presents a shorter 1-month pressure history at a much smaller pump station in the City of

Ottawa, called Glen Cairn. Glen Cairn PS feeds a relatively smaller (and lower demand) pressure

zone than either Hanlan or Lakeview; a zone which is also located at the end of the City’s hydraulic

system. In combination with its direct connection to the distribution system, the lower flow output

of this station generally places it in a lower transient risk category. The pressure history at Glen

Cairn is significantly different than those of Hanlan or Lakeview, thereby further confirming the

assertion that no two hydraulic systems are the same. If they were, then their typical transient

pressure response over the long-term would be more similar.

Figure 5-7: Sample Transient Pressure History – Hanlan PS (Region of Peel)

Page 93: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

82

Figure 5-8: Sample Transient Pressure History – Lakeview WTP (Region of Peel)

Figure 5-9: Sample Transient Pressure History – Glen Cairn PS (City of Ottawa)

Page 94: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

83

Figure 5-10 and Figure 5-11 present a transient pressure history at the La Caldera PS in Mexico City,

Mexico. La Caldera is a large pump station that conveys pumped well field water from a receiving

reservoir over a large hill and to the distribution system. Its single pipeline and high static head

place it a high risk to transient pressures. The first figure presents a short 1-month pressure history,

and the second figure provides a sample 2-day pressure history. The majority of the frequent and

similar transient pressure events are a result of operator initiated pump changes. The inflow to the

station is highly variable due to an unreliable well field supply. When combined with the single fixed

speed pump size, this unsteady inflow makes for a difficult operation; an operation that requires

repetitive cycling between 1 and 2 pumps in order to ensure that the reservoir does not overflow

and/or that it does not completely drain. The larger transient events are due to frequent power

failures, and these events can yield positive transient pressures that are 60% greater than the normal

operating pressures. Transient field pressure monitoring such as this can not only yield valuable

information on the magnitude and frequency of all transient pressures, but it can also provide

insights into unique and unexpected events such as check valve failures, etc. (please refer to the

following subsections).

Figure 5-10: Sample Transient Pressure History – La Caldera PS (Mexico City) – 2 Months

Page 95: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

84

Figure 5-11: Sample Transient Pressure History – La Caldera PS (Mexico City) – 2 Days

Figure 5-12: Sample Transient Pressure History – Mixquic Well No. 13 (Mexico City)

Page 96: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

85

Figure 5-12 presents a 1-month pressure history at Well Pump No. 13 in the Mixquic well field of

Mexico City. A pressure monitoring location at a well field can often record a variety of transient

events; events whose origin is often difficult to determine due to the sheer number of well pumps in

the system. A transient event induced at one well location will have a different pressure profile than

an event induced at a different well, but nonetheless, all transient events will be felt across the entire

well field due to its hydraulic interconnectivity. Transient pressures at this location (i.e., at Mixquic

Well No. 13) are often amplified due to its location at an upstream dead-end of a well water

collector branch pipeline. For more detailed and sample transient events at this particular location,

please refer to the following subsections.

Figure 5-13 presents a 3-month transient pressure history at a key location in the Region of Durham,

Ontario, Canada. The pump station at the main Ajax WSP water supply source is directly connected

to the distribution system. As discussed in Chapter 2, distribution systems can act to de-fragment

and partially dissipate transient pressure wave energy, thereby minimizing the magnitudes of any

transient events. As shown in the Ajax WSP figure, the discharge pressures are relatively stable and

typically range between 100 psi and 120 psi in accordance to the number of pumps in operation and

the flow rate (both of which are a function of system demand). Figure 5-14 shows a sample 3-day

pressure history at the same location. This type of pressure history is synonymous with a diurnal

demand pattern of water distribution systems in that the demand changes induce a change in the

operation of the supply system. This in turn leads to a pump change; a pump change which is

achieved by a transient pressure event that moves the system operation from one steady state to

another.

Page 97: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

86

Figure 5-13: Sample Transient Pressure History – Ajax WSP (Region of Durham) – 3 Months

Figure 5-14: Sample Transient Pressure History – Ajax WSP (Region of Durham) – 3 Days

Page 98: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

87

5.4.2 Individual Events

Long-term transient pressure histories comprise extended durations of normal (i.e., steady state)

operating periods, and depending on the location, a certain number of transient pressure

fluctuations referred to as transient events. This subsection provides sample field pressure profiles

for a variety of individual transient events.

Figure 5-15 presents a sample pressure profile for a typical controlled pump start-up, as recorded at

the Ajax WSP in the Region of Durham, Ontario, Canada. In this case, a constant speed pump was

started against a mostly closed discharge control valve (e.g., butterfly or gate valve). This type of

start-up subsequently relies on the slow and continuous opening of the discharge valve and enables a

smooth transition from one operating condition to the next. As shown in the graph, this transition

is smooth due to the length of time (> 1 minute) required to establish the new flow rate. The end

result is the avoidance of the rapid pressure change (i.e., a transient event) that is typically associated

with an uncontrolled pump start-up. Transient field pressure monitoring can therefore be used to

adequately test and configure pump start-up protocols by adjusting the speed and duration of the

discharge valve opening.

Figure 5-16 presents a transient pressure profile for a typical pump shutdown at the same Ajax WSP

location. The pump shutdown is similar to the previous pump start-up in that it relies on the use of

the discharge control valve. In this case, the transient event comprises two distinct phases: a smooth

pressure reduction followed by an unsteady pressure fluctuation consisting of a rapid pressure drop

prior to the final valve closure. Since the last 10% of a valve closure is the most significant, the

current valve closure settings at this location are clearly not optimized. The field transient pressure

monitoring can be used to identify and improve such operating protocols, thereby minimizing the

frequency and magnitude of more routine pump stops.

Figure 5-17 presents a transient pressure profile for another pump shutdown event. In this case, the

pressures are recorded at a high point of the La Caldera pipeline in Mexico City, and the routine

pump shutdown is not aided by discharge valve control. As a result, the initial downsurge pressure

wave is more pronounced and it is also observed at the downstream location.

Page 99: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

88

Figure 5-15: Typical Pump Start-Up – Ajax WSP (Region of Durham)

Figure 5-16: Typical Pump Shut-Off – Ajax WSP (Region of Durham)

Page 100: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

89

Figure 5-17: Typical Pump Shut-Off at High Point – La Caldera Pipeline (Mexico City)

Figure 5-18: Typical Pump Switch – Harwood PS (Region of Durham)

Page 101: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

90

Figure 5-18 presents a pressure profile for a routine pump switch at the Harwood PS in the Region

of Durham. This controlled operation consists of a routine pump shutdown immediately followed

by a routine start-up of a different pump. The smooth and curved nature of the transient pressure

change is indicative of a sufficient valve closure and opening duration, and is a trademark of good

pump control. Figure 5-19 and Figure 5-20 present a transient pressure profile for a power failure

induced pump trip at two different types of systems. The first pressure profile was recorded at the

pump station of the Ajax WSP in the Region of Durham; a station that is directly tied into the

distribution system. The second pressure profile was recorded at Hanlan PS in the Region of Peel; a

station that comprises a significant transmission only system. In addition to the obviously

significant magnitudes of the power failure induced downsurge events, the two figures provide a

clear example of how different the positive upsurge reflections can be. In the Ajax WSP case, the

reflected upsurge is essentially non-existent – primarily due to the added benefit of the distribution

system based pressure wave fragmentation and energy dissipation. In the Hanlan PS case, the lack

of distribution system attenuation leads to a more pronounced upsurge event; an event that can

impose a more severe consequence. In both cases, the transient pressure monitoring identified the

presence and character of the power failure induced transient risk.

Figure 5-21 presents a transient pressure profile for a sequence of planned emergency pump trips at

the La Caldera PS in Mexico City. The planned pump trip sequence was implemented as part of

planned transient field tests in order to determine the risk and magnitude of power failure induced

transient events. The first transient event is a result of a single pump trip from 2 pumps down to 1

pump. The second transient event is a result of a single pump trip from 1 pump down to 0 pumps.

As expected, the second transient event is more pronounced in both the magnitude and duration

than the first, and this is due to the range of the flow rate change. In this particular case, the first

pump change reduced the flow rate from approximately 800 L/s down to 500 L/s, and the second

pump change further reduced the flow rate from 500 L/s to 0 L/s. The complete stoppage in the

flow requires a longer period of pressure adjustment, thereby inducing a longer duration of pressure

wave propagation. In this case, transient pressure monitoring provided insights into both the

character of a pump trip induced transient event(s), as well as the duration of pressure fluctuation

following such an event. This type of data can also be used to estimate the transient event standby

period and the actual in-situ wavespeed. The almost perfect cyclic and attenuating nature of the

pressure fluctuation is characteristic of a simple transmission type water system.

Page 102: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

91

Figure 5-19: Power Failure Event without Upsurge – Ajax WSP (Region of Durham)

Figure 5-20: Power Failure Event with Upsurge – Hanlan PS (Region of Peel)

Page 103: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

92

Figure 5-21: Multi Pump Shut-Off, From 2 to 1 to 0 Pumps – La Caldera PS (Mexico City)

5.4.3 Unique Events

The previous section provides examples of typical transient pressure events in water systems,

including both planned and unplanned, and routine and non-routine events. For example, while a

power failure induced transient event can be rare and is not considered routine; it is rarely unique or

unexpected. Power failures are by their very nature unpredictable, but likely. This section provides

examples of unique transient events or overall system changes that induce unique transient pressure

responses.

Figure 5-22 presents a 1-month transient pressure history at the La Caldera PS in Mexico City. In

this pressure history, a long duration pressure change is clearly evident. The system depressurization

is due to unplanned system maintenance that resulted in the complete shutdown and dewatering of

the hydraulic system. The long-term continuous transient pressure monitoring was able to record

this unplanned event, and was subsequently used to review the draining and filling protocols

(pressure details for which are not shown).

Page 104: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

93

Figure 5-22: Complete System Shutdown – La Caldera PS (Mexico City)

Figure 5-23: Single Well Shutdown – Mixquic Well No. 4 (Mexico City)

Page 105: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

94

Figure 5-23 presents a transient pressure history for an unknown well shutdown at the Mixquic well

field in Mexico City. In this case, the entire well field was taken out of service in order to

troubleshoot its operation. The lack of pressure (i.e., 0 psi gauge) downstream of the check valve

pump location indicates that the well line was indeed depressurized. Figure 5-24 shows the pressure

profile for an unexpected but progressive check valve failure at the previously discussed La Caldera

PS. The check valve began leaking in the early hours of the morning, prior to finally bursting and

flooding the facility. The complete system shutdown and restart took place in excess of 1.5 hours.

The check valve failure was progressive and not catastrophic, and the continuously increasing

leakage acted to dissipate the self-induced transient pressures. This is an indirect example of how

system based leaks act as natural pressure relief points.

Figure 5-25 presents a discharge pressure history at the North Richmond Hill PS, located in the

Region of York, Ontario, Canada. The pressure history illustrates a clear change in the typical pump

station operating pressure profile at the 1/3 mark of the graph. Pump schedules and modes of

operation were investigated, but these indicated that no significant change took place at the pump

station. Upon a detailed system investigation, it was determined that at this exact recorded point in

time, a pressure zone boundary PRV was adjusted in the downstream distribution system. The

adjustment of the PRV induced a significant change in the system curve, and therefore shifted the

operating point of the constant speed pumps at the station. The end result was an obviously more

significant transient response during routine pump operations. This required the revision of the

pump control logic, including the discharge valve opening and closing durations. A change such as

this would likely not have been observed without the continuous transient pressure monitoring.

Figure 5-26 presents a discharge pressure history at the Montreal Road PS, in the City of Ottawa,

Ontario, Canada. In addition to the obvious transient pressure fluctuations, this plot illustrates a

significant change in the operating mode. The middle section corresponds to a one month period in

which the mode of operation was changed from VFD control to pressure control. In the pressure

control mode, a constant speed pump (which is equivalent to a VFD controlled pump at max speed)

is used to feed a closed pressure zone. The evident response is characterized by a higher discharge

pressure and a greater fluctuation in the steady state pressures. The wider range of fluctuation is a

direct result in the loss of precise control that a VFD typically provides; control which is required to

accommodate diurnal demand changes in the closed (i.e., without storage) pressure zone.

Page 106: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

95

Figure 5-24: Progressive Check Valve Failure – La Caldera PS (Mexico City)

Figure 5-25: Distribution System PRV Adjustment – North Richmond Hill PS (Region of York)

Page 107: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

96

Figure 5-26: Pump Control Logic Change – Montreal Road PS (City of Ottawa)

5.5 Sample Statistics

5.5.1 Event Summaries

Continuous transient pressure monitoring over a long-term period can yield a long list of transient

events that represent a host of planned and unplanned operation activities. For example, one year

of pressure monitoring may provide between 500 and 2000 events that would subsequently need to

be reviewed, and if found to be serious and/or questionable, would also have to be correlated to

system operations via logbook and SCADA records. Table 5-5 presents a summary list of all

unplanned (and possibly unique) recorded transient events at the La Caldera PS in Mexico City, over

a period of approximately 5-months. The table lists the specific events along with their date and

time of occurrence, as well as four (4) key pressure profile characteristics: original steady state

pressure, minimum transient pressure, maximum transient pressure, and final steady state pressure.

Page 108: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

97

A list such as this one needs to be compiled and then correlated to the pump station operations and

the activity during those days and times.

Table 5-6 presents a similar transient event summary list, as recorded at the Tlahuac and Mixquic

well fields in Mexico City. Every significant event (i.e., an event that is large in magnitude or

duration or simply unique) is presented, along with its minimum and maximum transient pressures

at six (6) different pressure recording locations. The locations represent different well stations

across the well fields. If the hydraulic transient behaviour of the system is at least partly known (i.e.,

via experience or via modeling), a simultaneous event comparison at different locations can provide

a significant amount of information on the source, duration, and dissipation of transient events.

Table 5-7 presents a short list of the most critical transient events that were recorded in the Region

of Peel’s water system during the summer of 2008. The table not only provides additional

information such as the total event duration and the duration of negative pressures (if applicable),

but it also correlates the specific events to SCADA records and system operation. For example, the

transient event that dropped the pressures at the ST1500 Chamber 9 location to -8 psi for a duration

of 13 seconds was caused by a simultaneous trip of three operating pumps.

Page 109: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

98

Table 5-5: Unplanned Transient Event Summary – La Caldera PS (Mexico City)

* All pressures are in units of kg/cm2

Page 110: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

99

Table 5-6: Transient Event Pressure Summary – Tlahuac/Mixquic Well Systems (Mexico City)

Page 111: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

100

Table 5-7: Detailed Event Summary – Region of Peel System

5.5.2 General Event Statistics

In addition to identifying the details (e.g., properties and causes) of individual transient events, long-

term transient pressure monitoring can provide useful and interesting statistics on the types and

properties of all transient events recorded. Table 5-8 provides a simple list of event statistics at

eight (8) well field locations in Mexico City. While the sample size (i.e., duration of pressure

recording) is relatively short, the simple statistics do provide insights into the different levels of

pressures experienced in the system, as well the frequency of the formation of negative pressures.

Table 5-9 presents statistics for 5-months of transient pressure monitoring at the La Caldera PS in

Mexico City. Standard statistical parameters such as the mean and standard deviation are not only

useful towards determining the level of risk that hydraulic transients impose on the system, but can

also be used in the future in order to continuously track the evolution of the system. In other

words, this particular system can be further monitored indefinitely in order to determine the change

No. TP1 LocationSource

StationDate Time

Average

Pressure

(psi)

Min

Pressure

(psi)

Max

Pressure

(psi)

Total

Event

Duration

Negative

Pressure

Duration

Detailed Operation and

Information

5 Streetsville PS Streetsville July 15 11:25 AM 66 22 78 3:23 N/A

6MV900

Chamber 8Streetsville July 15 11:26 AM 34 5 47 3:23 N/A

16HG1500

Chamber 11Lorne Park July 22 2:54 PM 40 10 51 0:09 N/A

1430 - # 2,4,5 - OFF;

1455 - total shutdown;

23ST1500

Chamber 9Herridge July 31 9:11 AM 16 -8 26 1:13 0:13

BEFORE - #1, 6, 8, 9 ON;

0910 - #1 (23 MLD) OFF, #8 (36

MLD) OFF, #9 (36 MLD) OFF;

0915 - #6 (68 MLD) OFF; #2 (23

MLD) ON, #5 (68 MLD) ON

27Beckett's

Sproule PS

Beckett's

SprouleAug 7 12:54 AM 62 7 73 1:22 N/A

BEFORE - #1 (27 MLD) ON, #2

(46 MLD) ON, #14 (90 MLD) ON;

#11 (90 MLD) ON

0055 - #11 OFF, #4 (46 MLD) ON

28 Hanlan PS Hanlan Aug 7 1:20 PM 59 -6 80 2:43 0:11

29BS1500

Chamber 8Hanlan Aug 7 1:21 PM 29 -24 81 2:43 0:40

33 Silverthorne PS Silverthorne Aug 17 4:34 AM 65 15 74 2:20 N/A0400-0455 - Failure, Gen's ON; #

1,3,4,5,6 TRIP

BEFORE - #3 (45 MLD) - ON

1125 - #6 (55 MLD) - OFF

AFTER - #7 (90 MLD) - ON

BEFORE - #1 (23 MLD) ON, #3

(35 MLD) ON, #5 (110 MLD) ON,

#9 (136 MLD) ON, #10 (136 MLD)

ON;

1425 - # 3, 5, 9, 10 FAIL / OFF, #

6 (126 MLD) ON, #7 (110 MLD)

ON but FAIL

Page 112: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

101

in such statistical parameters; a change that can possibly indicate system deterioration or a shift in

operational protocols. In the short-term, such statistics can be used to find answers to specific

transient pressure related questions. For example, why was the mean number of events per day in

July significantly less than in the rest of the months? This is counter intuitive because July is

typically a peak demand month in the Northern hemisphere, and therefore an initial hypothesis may

be that the system was limited in its operation, thereby reducing the likelihood of a transient event

occurring. (The answer in this case was actually that the performance of the upstream well field

pumps was consistent, and as a result the inflow to the La Caldera pump station was steadier,

meaning that the number of emergency pump operations was minimal.)

Table 5-8: General Short-Term Statistics – Tlahuac & Mixquic Wells (Mexico City)

Location ID

# of Days of Data

Average Pressure (kg/cm2)

Maximum Pressure (kg/cm2)

Minimum Pressure (kg/cm2)

Negative Pressure

Count

T1 25 4.5 8.2 -0.1 7

T6 31 2.5 4.3 -0.2 7

T14 32 2.1 3.7 -0.2 11

M6 5 2.6 7.8 0 3

M13 36 2.4 5.1 0.5 0

SC4 35 1.8 4.9 0.3 0

NT1 4 2.2 3.8 -0.1 1

NT2 2 2.2 2.7 1.1 0

Table 5-9: General Long-Term Statistics – La Caldera PS (Mexico City)

Page 113: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

102

Table 5-10 presents similar long-term (albeit) simple transient event statistics, as recorded in the

Region of Peel’s water system. The interesting point in this table is the duration of pressure

monitoring at some of the locations. For example, the 500+ days of continuous pressure

monitoring at the Lakeview WTP can be seen as a more meaningful indicator of the absolute

transient pressure magnitudes, as well as the frequency of negative pressure events.

Table 5-10: General Long-Term Statistics – Region of Peel System

Table 5-11 extends the previous Lakeview WTP discussion through a more detailed statistical

consideration of transient events in the first year of continuous transient pressure monitoring. The

more complex list of statistics is aimed at answering additional questions, such as:

• How close are the maximum transient pressures to the pipe pressure rating and how

often are the most severe of these pressures experienced?

LocationNo. of

Days

Average

Pressure

(psi)

Min

Pressure

(psi)

Max

Pressure

(psi)

No. of

Negative

Events

Streetsville LLPS 25 62 14 85 0

MV900 Chamber 8 20 35 -15 53 1

HG1500 Chamber 11 20 40 9 57 0

BS1500 Chamber 8 56 30 -24 81 6

Beckett's Sproule LLPS 36 62 4 79 0

Silverthorne LLPS 36 60 15 76 0

ST1500 Chamber 9 36 17 -8 32 2

Lakeview LLPS Z1 500+ 107 102 134 0

Lakeview LLPS Z2 500+ 170 151 197 0

Hanlan LLPS 200+ 57 -6 79 6

Page 114: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

103

• Are the maximum transient pressures increasing through time and are they

encroaching on the maximum pipe pressure rating? (i.e., is the additional structural

“capacity” decreasing?)

• Is there a correlation between the magnitude and/or the frequency of transient events

with the day of the week? (e.g., is the system at a higher risk during the week rather

over the weekend?).

• Is one pressure zone performing better than the other, and if yes, is it due to the

difference in the size and volume of HAC protection?

Table 5-11: Detailed Long-Term Statistics – Lakeview WTP (Region of Peel)

Figure 5-27 expands on the discussion of structural “capacity” at the Lakeview WTP by plotting a

curve that takes the form of a probability distribution function. Site 1 and Site 2 refer to the two

pressure zones, with Site 1 referring to the high pressure Zone 2 and Site 2 to the low pressure Zone

1. The y-axis represents the percentage of days of occurrence and the x-axis the maximum daily

pressure (transient or steady) as a percentage of the maximum pipe pressure rating. For example, if

the maximum recorded pressure in a single day was 180 psi, this pressure would account for 85% of

Page 115: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

104

the pipe pressure rating and therefore provide only a 15% buffer in structural capacity (not

considering any safety factors, etc.). The cumulative nature of the curves allows for a simple, but

visual comparison of the two pressure zones. For example, the break point in the curve of

approximately 12 % for Site 1 (Zone 2) is significantly lower than the 40% for Site 2 (Zone 1). This

illustrates that Zone 1 operates much closer to the ultimate operating threshold.

Figure 5-27: Sample Cumulative Pressure Distribution – Lakeview WTP (Region of Peel)

While a discussion such as the one above is still preliminary and general and prone to the errors and

variability associated with a small sample size, it can still provide key insights into both the transient

response of the system and the ultimate level of the hydraulic transient induced risk. The larger the

sample size (i.e., the duration of transient pressure monitoring) the more meaningful the statistics

become and the more complex the questions that can be asked. This type of methodology is the

building block for a statistic based risk assessment and this is further discussed in Chapter 7.

However, Chapter 6 first takes a step aside from field based transient pressure statistics and looks at

an alternate use of such data. In particular it addresses the important topic of numerical model

validation through the use of specific case studies in which the field transient pressure data was used

to adjust model assumptions and parameters.

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0% 10% 20% 30% 40% 50%

Percentage of Days

Maximum Daily Pressure as a Percentage of Pipe Rated Pressure

Site 1

Site 2

Page 116: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

105

5.6 Summary

The main purpose of this chapter is to demonstrate the capability and benefits of using field work

and actual system data to assist in the decision making process and with the hydraulic transient

analysis task. The chapter initially provides a brief overview of the traditional approach to transient

field work and then moves on to describe the trends and changes through a discussion of modern

technology. As part the discussion, six (6) different commercially available high frequency transient

pressure monitors are compared across a wide range of performance criteria, including cost, control

logic, etc. While the various transient pressure monitors are all relatively different and some are

shown to be significantly better than others for some of the criteria, only one of these, the Pipetech

TP-1 is demonstrated to be capable of properly recording transient pressures for a long period of

time (e.g., months).

The second half of the chapter provides a comprehensive summary, including actual real life

examples, of the Pipetech TP-1 monitoring capabilities. The summary examines a variety of topics,

including calibration, parameter adjustments for recording, sample long-term transient pressure data

and statistics. Many of the small case studies in this chapter provide indications of why this type of

work is beneficial, and therefore presents how and why it should be used as a tool for field based

transient risk assessments.

Page 117: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

106

Chapter 6 Validation of Numerical Models

This chapter provides examples of numerical hydraulic transient model validation using the

previously discussed high frequency pressure recordings from the field. The nature and importance

of transient model validation is presented through a series of different case studies, in which the

field data is used to validate and adjust the initial modeling results; results which are then

subsequently used to make other more difficult transient analysis and design decisions. In essence,

the field data was used to validate that the theoretical mathematical model actually represented

reality. The overall goal of this chapter is to reaffirm the importance of field work for a typical

transient analysis by showing how computer models can sometimes be inadequate, conservative, and

incomplete, but also how they can sometimes be complimentary to the proposed field work.

All field data was acquired through planned transient field tests or long-term transient pressure

monitoring, in which unique or planned transient events were observed. For example, as part of a

planned field test program, power failure induced trips of one or more operating pumps were

simulated at a specific pump station. The transient pressures were typically recorded at the discharge

header and/or at another point downstream (e.g., forcemain, transmission main, etc.), using one of

the transient pressure monitors described in Chapter 5. The numerical modeling data was simulated

using one of two different transient software packages: TransAM or H20Surge. The transient

models were developed from either existing steady state models or from steady state models

specifically developed for the system being considered.

6.1 Case Study I: Region of Peel

6.1.1 Background

The Region of Peel is a large and growing regional municipality with a current population in excess

of a million. The Region operates the water (and wastewater) system, including supply, transmission

and distribution for three local municipalities. The potable water is treated from a surface water

source and distributed along a significant distance using a partially separated transmission and

distribution pipe network. The transmission system carries the water from one pump station to

another, and each pump station also distributes the water locally within the specific pressure zones.

Page 118: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

107

The detailed hydraulic model for the system contains tens of thousands of links broken down and

isolated into a number of pressure zones. A typical pressure zone may have between 1000 and 3000

links. The steady state model is partially calibrated for the current year and is also expanded for a

future planning year.

As part of a larger transient system study, the Region commissioned specific transient field tests and

pressure monitoring at a few of its pump stations and feedermains in pressure zone no. 3. The

resulting field data and numerical model analysis and validation were performed using the WCM

based H20Surge software package, and the results are presented below. The modeling results

presented for this case study are those pertaining to the original (unadjusted) model, in order to

illustrate the risk of not validating or adjusting a theoretical model.

6.1.2 Analysis

As part of this case study, individual transient events from specific transient field tests and

continuous pressure monitoring in pressure zone no. 3 were chosen for the initial validation and/or

confirmation of the numerical model. The chosen events were recorded at either Streetsville PS or

Hanlan PS. Many of the events observed during the continuous pressure monitoring were often of

the same source (e.g., a single pump trip) and many could not be subsequently correlated to a cause

and/or operational activity. As a result, three (3) unique, known, and predicable events were chosen

and these are briefly described below:

Event No. 1: Single Pump Trip at Streetsville LLPS

The results of this transient event and the numerical model validation are shown in Figure 6-1 and

Figure 6-2. The first figure shows the pressure profile as recorded at the source (Streetsville PS) and

the second figure shows the pressure profile as recorded at a downstream feedermain high point

location (MV900 Chamber 8). This event was caused by a planned transient field test. Before the

test, the only operating LL pump was pump no. 6; a pump with a rated capacity of 55 MLD. At

11:05 AM pump no. 6 was tripped, thereby simulating a power failure event during a single pump

operation. At 11:17 another LL pump, pump no. 8, was started.

At the source location, the single pump trip resulted in a significant downsurge with a range of 45

psi and a subsequent reflected upsurge with an ultimate peak that was 15 psi above the original

Page 119: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

108

operating pressure. The initial transient pressure wave travelled downstream and was also recorded

at the second valve chamber location. At this location, the transient pressure range actually

increased, with the peak pressure being 20 psi greater than the original operating pressure and the

minimum pressures reaching full vacuum conditions. The second of these is primarily due to the

higher elevation and therefore the lower initial operating pressures. While the original (unadjusted)

model performed quite well for the source location, its results for the downstream location were

significantly off in both the transient range/magnitude and overall phase. There are numerous

factors at play in this case, including the lack of steady state model calibration, the improper

assumption of key transient parameters, and the realistic impact of system devices such as air valves.

Event No. 2: Single Pump Trip at Hanlan LLPS

The results of this transient event and the numerical model validation are shown in Figure 6-3 and

Figure 6-4. The first figure shows the pressure profile as recorded at the source (Hanlan PS) and the

second figure shows the pressure profile as recorded at a downstream feedermain high point

location (BS1500 Chamber 8). This event also occurred during a planned transient field test. Before

the test, two large LL pumps were in operation, namely pumps no. 9 and no. 10; each of 136 MLD

rated capacity. At 11:14 AM pump no. 9 was routinely shut-off (i.e., in a controlled manner), and at

11:16 AM pump no. 10 was tripped, thereby simulating a power failure event during a single pump

operation. Five minutes later, two other LL pumps were turned on.

The single large pump failure event at Hanlan LLPS induced negative pressures across the system,

including pressures in the full vacuum range at the downstream chamber location. The initial part of

the field versus model pressure profiles is quite similar, especially when one considers the maximum

and minimum pressures. However, in this section of the graph the model predicted a quicker and

longer duration downsurge event, likely owing to the conservative pump inertia assumptions. The

more evident dissimilarity between the two data sets is the excessive model noise in the second part

of the plots. The model continuously predicted re-occurring negative pressures, rapid pressure

fluctuations, and clearly unrealized positive upsurge pressures (e.g., up to a peak of 110 psi). For

example, the maximum upsurge pressures never exceeded the initial operating pressures due to real

system dissipation. The clear difference in the transient pressure wave phase also shows how

complex the wave interaction in this system is, and how models can overestimate transient risks;

Page 120: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

109

risks which a real system can often minimize. The follow up subsection further discusses the general

trends in this overall case study.

Event No. 3: Multiple Pump Trip at Hanlan LLPS

The results of this transient event and the numerical model validation are shown in Figure 6-5 and

Figure 6-6. The first figure shows the pressure profile as recorded at the source (Hanlan PS) and the

second figure shows the pressure profile as recorded at a downstream feedermain high point

location (BS1500 Chamber 8). This unplanned event was a direct result of a mechanical problem

with a large pump. Before the event, the operating LL pumps (and rated capacity) were: no. 5 (110

MLD), no. 9 (136 MLD) and no. 10 (136 MLD). At 2:25 PM these three LL pumps simultaneously

tripped. Shortly after, another two LL pumps, pumps no. 6 and no. 7 were started, but no. 7 failed.

The multiple pump failure event at Hanlan LLPS induced negative pressures across the system,

including pressures in the partial to full vacuum range at the station and at the downstream chamber

location. The plots also bring light to a possible pressure recording malfunction, especially if one

considers the -20 psi (or so) pressure recorded at the downstream location. While extended and

severe magnitude full vacuum conditions (i.e., less than 14.7 psi) are possible in very clean water,

they are highly unlikely in this type of potable water system, especially with the typical presence of

air and some nucleation sites.

The transient response and dissimilarities between the field data and modeling data are quite similar

to the previous event case. However, the multiple pump failure is evidently more severe, especially

in the subsequent upsurge reflections and possible vapour cavity formation and collapse. The

maximum pressures at both the locations were in the 80 psi range, and the sharp pressure rise in the

second graph is indicative of a vapour cavity collapse at or near the high point. The other clear

observations again pertain to the overestimation of the nature and duration of the transient

pressures. The model predicted significant pressure fluctuations, while the system indicated

relatively rapid pressure energy attenuation. Additional insights into this type of model behaviour

are provided in the following subsection.

Page 121: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

110

Figure 6-1: Model v. Field Event Pressure Validation – Streetsville PS (Region of Peel)

Figure 6-2: Model v. Field Event Pressure Validation – MV900 Chamber 8 (Region of Peel)

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50

Pre

ssu

re (

psi

)

Time (seconds)

Streetsville LLPS - Single Pump (#6) Trip

Model

Field

-20.0

-10.0

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

0 10 20 30 40 50

Pre

ssu

re (

psi

)

Time (seconds)

MV900 Chamber 8 - Single Pump Trip (#6) at Streetsville LLPS

Model

Field

Page 122: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

111

Figure 6-3: Model v. Field Event Pressure Validation – Hanlan PS (Region of Peel)

Figure 6-4: Model v. Field Event Pressure Validation – BS1500 Chamber 8 (Region of Peel)

-20.00

0.00

20.00

40.00

60.00

80.00

100.00

120.00

0 10 20 30 40 50

Pre

ssu

re (

psi

)

Time (seconds)

Hanlan LLPS - Single Pump Trip (#10)

Model

Field

-20

-10

0

10

20

30

40

50

60

70

80

0 10 20 30 40 50

Pre

ssu

re (

psi

)

Time (seconds)

BS1500 Chamber 8 - Single Pump Trip (#10) at Hanlan LLPS

Model

Field

Page 123: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

112

Figure 6-5: Model v. Field Event Pressure Validation for 2 Pumps – Hanlan PS (Region of Peel)

Figure 6-6: Model v. Field Event Pressure Validation for 2 Pumps – BS1500 (Region of Peel)

Page 124: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

113

6.1.3 Discussion

The previously described field and model (unadjusted) validation plots are synchronized with respect

to the starting time, and are compared for a time period of 50 to 100 seconds. In general, the

unadjusted transient model is not significantly off from reality, but it does have a variety of concerns

from both ends of the traditional “conservatism” spectrum. The differences and similarities

between the model and field event plots, along with the inherent uncertainties and conclusions are

summarized below:

• The steady state pressures for some events and locations are different, thereby

confirming that the steady state model needs to be re-calibrated. A complete calibration

or even a good validation of a transient model requires a good calibration of the steady

state model. If the steady state model cannot predict the routine pressures, then the

transient model results cannot be taken by their absolute values. For example, in the

second sample event, the discrepancy in pressures is a direct result of the initial model

pressures being much greater than the field pressures.

• In most cases, the field pressures at downstream locations are lower than what the

model predicted. This may be due to many things in the field, including: higher pipe

roughness or reduced diameters, longer lengths of pipe, service connections, status

and/or operation of control, air valves, etc.

• Model validations are also strongly dependent on the presence and performance of

devices that are designed to, or simply can and do impact the surge conditions. The

model runs assumed that the existing pump station surge protection was working and

that the existing downstream air valves were not. Such an assumption cannot be proven

without a field inspection, but it can impact the results. For example, an air valve can

introduce a significant amount of air into the system, and this air can rapidly be expelled

thereby inducing a significantly higher pressure rise than predicted (or observed if vice

versa). Furthermore, the surge protection at the two stations consists of SRVs, and in

the model runs these devices did not act because the maximum pressure set points were

never reached.

• In most cases, the field and model pressures are quite close for the initial source

locations (i.e., at the pump stations).

Page 125: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

114

• The results for the Streetsville event show that the field and model pressures are quite

similar in terms of relative and absolute magnitudes. The two are slightly different

because they are out of phase in either the horizontal or vertical axis. Nonetheless, the

downsurge and initial reflections (i.e., the first 20 seconds) are quite synchronized. The

duration of low pressures caused by the downsurge are very close, and therefore provide

comfort to specific model assumptions such as inertia, layout, etc.

• The remainder of the plots (i.e., after the first 20 seconds) are out of sync because the

field pressures show that the subsequent reflections actually occurred much quicker.

This is always a good indication of a different than assumed wavespeed, different pipe

length or a different/additional major boundary condition within the system. Overall,

the Streetsville event is well predicted by the model.

• The two Hanlan events bring light to the problems and uncertainties of numerical

transient modeling. Assuming that the steady state model is reasonably close and that

the field results are indeed trustworthy, the numerical model is shown to be highly

conservative in many situations. This is the case for most models in that they cannot

predict the system uncertainties which tend to reduce the impact of transients. For

example, small leaks within a system or transmission through boundary condition

components can act to reduce the energy of the pressure waves, but these types of

things are rarely modelled or considered.

• The four Hanlan plots clearly establish that actual system conditions allow for a

significant attenuation of transient pressures; additional attenuation that the model does

not predict. The system has been shown to dissipate the energy and to return to a

steady state much more quickly.

• The high frequency of the model data is unrealistic since it is being compared to the

field data which is recorded at 100 Hz (i.e., 100 times per second). These things

contribute to the model wearing off in the later stages.

• The opening and closing of check valves between numerical time steps is not something

that is easily predicted, or physically certain. Such things can lead to a numerical

instability that can produce excessive pressure oscillations such as those shown in the

two Hanlan events.

• The specific H20Surge transient modeling software (and its WCM solution approach) is

generally stable when the system unsteadiness arises mostly from inertial effects. As

Page 126: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

115

high frequency is introduced, the frictional approach of the “wave characteristic”

approach tends to cause wave reflections which react to other devices (such as those

previously described), thereby leading to rapid negative and positive fluctuations that are

characteristic of the “hashing” in an unstable numerical approach.

• The Hanlan events also show that the pump model assumptions for this station need to

be adjusted. This is shown by the difference in the steepness and length of the initial

downsurge events. The actual pump rundown time and inertia are probably higher than

those assumed and modelled.

• The model also limits the negative pressures to full vacuum of -14.7 psi gauge, which as

previously discussed is not always a good assumption. Even though the field results

below -14.7 psi cannot be completely trusted because they exceed the pressure

transducer range, the possibility of reaching such pressure values cannot be precluded.

A potable water system with few nucleation sites and very tight linings is more than

capable of maintaining full vacuum conditions, particularly for a short duration. When

the model limits the minimum pressures, it can often introduce a change in the

predicted positive pressures. This is similar to shifting the pressure envelope upwards.

Nevertheless, the key point for decision making is the fact that negative pressures in the

full vacuum range were predicted and have been shown to occur in the Peel system.

The above case study explanations of the model validation are often true for most systems, in that

most models cannot be expected to produce identical results. However, since the Peel transient

model results are very similar to the observed field results in both the event form and magnitude, the

model users eventually felt a greater sense of confidence in using this model, especially for the

ultimate task of performing a long-term transient planning level assessment. The following section

aims provides a more detailed field and model transient pressure validation, through a case study in

which the initial model was subsequently adjusted based on the field data.

6.2 Case Study II: Region of Durham

6.2.1 Background

The Region of Durham is another growing regional municipality that provides water and wastewater

services to a high number of customers in four (4) larger municipalities (and several small ones).

Page 127: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

116

The City of Ajax (and its water system) is one of these four municipalities, and it receives its potable

water from a surface water source via the Ajax WSP. Unlike in the case of the two specific pump

stations in the Region of Peel, the pump station at the Ajax WSP actually pumps treated water

directly into the distribution system. The Region of Durham commissioned a field transient

pressure monitoring study in order to determine the actual risk of transients, but also to validate the

transient model which would be used to make predictions (i.e., budget allocation) for the required

surge protection 30 years down the line. A high frequency TP-1 monitor was installed at the pump

station discharge header of the Ajax WSP, and naturally occurring transient events were recorded

and subsequently correlated to SCADA and system operation. The resulting field data and

numerical model analysis and validation were performed using the MOC based TransAM software

package, and the results are presented below.

6.2.2 Analysis

This subsection provides specific examples of how the raw transient field pressure data was used to

validate and adjust the numerical transient model. Operational and SCADA records could not

confirm the nature of several of the recorded transient events, and therefore the modeling exercise

was partially used to confirm the type and characteristics of a few pump shutdown events. Figure

6-7 presents a series of pressure profiles pertaining to a couple of pump shutdown events at the Ajax

WSP. The purple series pertains to a controlled shutdown of a single small pump (i.e., from 1

pump to 0 pumps). As expected, the routine shutdown (achieved via discharge valve control) of a

large pump yielded a continuous and smooth pressure reduction and did not produce a severe

transient pressure fluctuation. The green and the blue pressure series pertain to two independent

power failure events, of a small and a large pump, respectively. The typical downsurge pressure

profile was more significant for the larger pump failure (blue series) due to the greater change in

flow rate. The last series (red) presents an unadjusted model representation of a single large pump

power failure. While the ultimate minimum and maximum model predicted transient pressures are

essentially the same as those observed in the field for an actual large pump failure, the pressure

profile properties of the event are significantly different. The model under predicted the magnitude

of the initial downsurge and over predicted the magnitude and occurrence of subsequent negative

and positive wave reflections. If the model was not adjusted, its sample results would at first glance

appear to resemble a single small pump power failure, which in itself would make any subsequent

model predictions less than conservative. As a quick aside, all four series in this plot also show how

Page 128: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

117

a system that is connected to the distribution network can minimize any upsurge reflections. In this

case, neither one of the initial (or subsequent) upsurges ever come even close to exceeding the initial

operating pressure. This is quite different than the previous case study; a study that was based on a

water transmission type of system.

Figure 6-7: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 1

The hydraulic transient model was to be used for future year planning decisions and needed to be

adjusted in order to better represent the actual field conditions. Figure 6-8 presents partial results of

the model adjustment exercise, using the single large pump power failure transient event discussed

above. Such a task requires a sensitivity analysis of many individual model, hydraulic, and system

parameters, both on an individual and combined level. The blue series represents the field data and

the red series represents the original (unadjusted) model data. The purple and green series

represent the modeling results for two of the more influential model changes, namely the addition of

an SAV and the inclusion of additional air in the system. The SAV was originally excluded from the

model because it was assumed to act much like an SRV. An SRV is used to reduce positive transient

pressures, and it should rarely, if ever, affect the negative pressures. An SAV can and often does,

impact the downsurge pressures as it is set to anticipate the upsurge through opening at the onset of

a pressure drop.

0

20

40

60

80

100

120

0 20 40 60 80 100 120 140

Pressure (psi)

Time (sec)

Routine Shutdown Nov 20 (Large Pump)

Power Failure Feb 11 (Small Pump)

Power Failure Nov 2 (Large Pump)

Model Power Failure (Large Pump)

Page 129: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

118

As shown in the plot, the inclusion and modeling of the SAV significantly improved the model

predicted response of the initial downsurge. From a physical point of view this is expected, as the

SAV can (and in this case did) discharge a significant amount of fluid immediately following the

initial pressure drop, thereby further exacerbating the downsurge conditions. The second model

adjustment in the form of additional air in the distribution system (achieved by the addition of small

air pockets in the model via air valves and/or air chambers) acted to dampen the pressure

fluctuations resulting from any subsequent pressure wave reflections. From a physical point of view

this is also expected, as air pockets can (and often do) act as “cushions” in the system. While neither

one of the two simple model adjustments can be said to resemble the actual field results, their

individual attributes can be combined with additional parameter adjustments (see next figure and

discussion) in order to more precisely validate the transient model. This additional exercise was not

performed in this case due to uncertainties in the steady state model parameters. In fact the most

obvious difference between the field and model plots is in fact the steady state pressure following

the transient event. (It is likely that the steady state model under predicted the back pressure in the

system through low modelled reservoir levels, thereby showing lower operating pressures at the

source when the pumps are not in operation.) Nonetheless, the point of this figure is to illustrate

two simple examples of how model assumptions need to be tested and how subsequent adjustments

can target specific discrepancies in a typical transient event profile. Furthermore, in this particular

case the model adjustments acted to confirm the activation and subsequent negative impact of the

SAV at the Ajax WSP; knowledge which was later used to make appropriate design decisions.

The last plot, Figure 6-9, presents the results of a simple sensitivity analysis of the key system

wavespeed assumption that was originally made in the transient model. The original model

assumption of 1000 m/s (red series) was derived with the knowledge that the majority of the key

pipes in the system were rigid (e.g., CPP, DI, etc.). The green and purple series present the

modelled system response with a reduction of wavespeed; more precisely with wavespeed values of

750 m/s and 300 m/s. The 300 m/s wavespeed range is more typical of a flexible pipe system (e.g.,

PVC, HDPE, etc.), but can also be used to represent the presence of additional air (see previous

discussion). In order to more completely validate the model, this parameter adjustment would have

to be combined with the other two key parameters.

Page 130: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

119

Figure 6-8: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 2

Figure 6-9: Model v. Field Event Pressure Validation – Ajax WSP (Region of Durham) – Part 3

20

30

40

50

60

70

80

90

100

110

120

0 25 50 75 100 125 150 175 200

Pressure (psi)

Time (sec)

Ajax WSP - Large Pump Failure - Model AdjustmentsField

Model - Unadjusted

Model - 250 mm SAV

Model - Distributed Air

20

30

40

50

60

70

80

90

100

110

120

0 25 50 75 100 125 150 175 200

Pressure (psi)

Time (sec)

Ajax WSP - Large Pump Failure - Wavespeed ImpactField

Model: a=1000 m/s

Model: a=750 m/s

Model: a=300 m/s

Page 131: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

120

6.3 Case Study III: Mexico City 6.3.1 Background

The water supply to the greater Mexico City comprises a variety of sources, including the

conveyance from many well fields. At the outskirts of the city, the Tlahuac, Santa Catarina and

Mixquic well fields contribute water to a single pipeline and this pipeline then conveys this water to

the La Caldera Reservoir. At La Caldera, a set of three HL pumps convey treated water over a large

hill and into a distribution system. The utility commissioned a study to look into the transient

conditions at the La Caldera PS and pipeline; a study in which transient pressure monitoring would

be used to validate a numerical transient model. The numerical transient model would then be used

to evaluate future transient conditions following a planned upgrade, and to ultimately determine the

required surge protection. Unlike in the Peel and Durham case studies, this system is much simpler

from the point of view of hydraulics. At the time of analysis, the system consisted of three (3)

800HP vertical turbine pumps, a single 1200 mm diameter CPP pipeline with a length of 450 m, and

no additional system connections. A TP-1 monitor was installed at the discharge header, and the

resulting field data was used to validate a numerical model. The numerical analysis and validation

was performed using the MOC based TransAM software package, and the results are presented

below.

6.3.2 Analysis

The continuous transient pressure monitoring at the La Caldera PS recorded a variety of power

failure events; events that caused the pump(s) to trip and therefore induce a transient event. With

the properties of the rigid CPP pipeline, the relative short length (450 m), and the high static head

(80 m), the transient response following a pump trip can be classified as potentially severe. Figure

6-10 presents a model versus field transient pressure comparison for a single pump trip, from 2

pumps down to 1 pump. The unadjusted (i.e., as originally assumed) model results are generally in

good agreement with the field data. The slight differences in the minimum and maximum values are

likely due to several of the original steady state and physical system assumptions, including the

precise lengths, elevations, and pipe roughness.

Page 132: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

121

Figure 6-11 presents another model validation plot for a single pump failure event. However in this

case the pump change is from 1 pump to 0 pumps. Such a change is more significant because of the

inherent grater change in flow (and therefore velocity) that is a general property of parallel pump

operation. In other words, the reduction in flow to zero is much more significant. Several

interesting observations can be made from this plot. First, the transient response in this system is

relatively simple and predictable. A pump trip leads to a downsurge, and this downsurge propagates

through the system and returns as an upsurge. This process repeats until the pressure wave is

dissipated, and this process is relatively smooth, symmetric, and quite predictable. Second, the

unadjusted model results generally conform to the field results, but are out of phase and actually

predict intermediate reflections that are not present in the real system. The potential cause of this

discrepancy could be the representation of the pump station check valves. In the field, the check

valves for the non-operating pumps were found to be quite leaky. In the model, the non operational

pump check valves were initially modelled as dead ends, thereby creating additional reflection points.

Lastly, the model results slightly underestimate the minimum transient pressures. This is likely due

to assumptions on actual operating conditions (e.g., flow and head), as well as pump inertia values.

Nonetheless, the overall magnitudes, profile, and dissipation mechanisms in the two data sets do

confirm that the model is quite reasonable and that it can be used to further analyze future

conditions.

Figure 6-12 presents the pressure profile for a more severe two pump trip at the La Caldera PS.

While the modeling results again suffer with respect to the phase of the pressure wave and the

intermediate reflections (note initial rise due to a check valve slam in the model), the maximum and

minimum transient pressure magnitudes generally do match those observed in the field. The model

versus field validation provides and confirms several important insights into the overall transient

response in the system. The clear risk in this system pertains to the maximum upsurge pressures;

pressures which have been found to be twice that of the operating pressure, and greater than the

rated pressure of the pipe. Furthermore, the field data also confirms the quick nature of the

transient response via a calculated wavespeed in excess of 1100 m/s. This typical wavespeed value

confirms that any air in the system is indeed being discharged at the top of the hill, rather than being

trapped along the pipeline. In the end, it is information such as this that can be used to better refine

the model assumptions in order to more precisely predict a system response that cannot be

simulated. In this case, the utility relied on the model to predict a variety of potential transient

pressure conditions when three (3) pumps are in operation.

Page 133: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

122

Figure 6-10: Model v. Field Comparison (2 Pump to 1 Pump) – La Caldera PS (Mexico City)

Figure 6-11: Model v. Field Comparison (1 Pump to 0 Pumps) – La Caldera PS (Mexico City)

Model Validation - La Caldera Transient Pump Tests

0

20

40

60

80

100

120

0 2 4 6 8 10 12 14 16

Time (sec)

Pressure (m)

Field: Single Pump Trip (Two Pumps On)

Model Pump Trip

Model Validation - La Caldera Transient Pump Tests

0

20

40

60

80

100

120

0 5 10 15 20 25

Time (sec)

Pressure (m)

Field: Single Pump Trip (One Pump On)

Model Pump Trip

Page 134: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

123

Figure 6-12: Model v. Field Comparison (2 Pumps to 0 Pumps) – La Caldera PS (Mexico City)

6.4 Case Study IV: Wastewater Forcemain

6.4.1 Background

The previous three case studies considered the validation of numerical models for simple and

complex potable water systems. This particular case study examines a single wastewater forcemain

in Ontario, Canada; a 650 mm diameter CPP forcemain, with a total length of approximately 1.5 km.

The forcemain is relatively flat in profile, fed from a single pump station, and discharges the fluid to

a gravity system via a bulkhead and manhole. The utility commissioned a field based transient

assessment in order to determine the potential risk of failure; failure potential that was primarily

perceived to be due to the age of the pipe, but also due to criticality and location of this asset. A

TP-1 monitor was installed at the discharge header of the pump station, and the resulting field data

was initially used to assess the in-situ risk from hydraulic transients. The field data was then

subsequently used to validate a numerical model, a model that could then be used to assist in specific

Model Validation - La Caldera Transient Pump Tests

0

20

40

60

80

100

120

140

0 5 10 15 20 25

Time (sec)

Pressure (m)

Field: Double Pump Trip (Two Pumps On)

Model Pump Trip

Page 135: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

124

design decisions. The numerical analysis and validation was performed using the MOC based

TransAM software package and the results are presented below.

6.4.2 Analysis

The following figures present the results of a model validation and adjustment exercise, in which the

field data from a simulated power failure of a single pump is compared to the incrementally adjusted

model results. In all of the figures, the red series represents the recorded field pressure history at

the discharge header of the pump station.

Figure 6-13 presents a field versus model sensitivity analysis of the important wavespeed parameter.

The blue series represents the original modeling assumption of 1000 m/s – a value that is very

typical of a rigid CPP pipe. The evident discrepancy between the unadjusted model with a

wavespeed of 1000 m/s (blue series) and the actual field data (red series) can be described as both

significantly out of phase and not attenuating. The reasonably assumed wavespeed is indeed too

high and it leads the model to predict a much faster (and less attenuated) wave reflection period,

thereby ultimately leading to more pressure cycles. As the model wavespeed is incrementally

decreased to 300 m/s (orange series) and 150 m/s (green series), the pressure wave phase becomes

more in sync with the field data. From a physical perspective, a wavespeed in the 150 m/s range is

completely justified since this is close to the measured field value. In other words, the green series

is almost in phase with the red series. Such a low wavespeed is more characteristic of a flexible pipe,

but can also result from high air content (see previous discussion in Chapter 3). The amount of air

in this system is therefore significant, and predominantly due to it being a wastewater system, but

also because of the forcemain’s flat profile and lack of air valves.

While the wavespeed adjustment exercise essentially corrected the phase of the transient pressure

wave, it still did not account for the true pressure wave attenuation in the system. The amount of

energy dissipation in the real system is significantly increased by the previously discussed air content

(especially if at the downstream discharge end), but the numerical model cannot adequately take that

into account, especially if the air forms locally and in pockets. Nonetheless, the difference in

pressure wave attenuation can also be explained by how the model accounts for friction. Such a

discrepancy is characteristic of a water hammer model that employs a steady state friction formula to

compute friction loss during transient flow conditions (Axworthy and Chabot, 2004). Figure 6-14

Page 136: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

125

presents the validation results when an unsteady friction model is implemented. Maintaining a

constant wavespeed of 150 m/s and accounting for unsteady friction (blue series) leads to a

significantly better representation of the true pressure wave dissipation in this wastewater system.

While not perfect, these two concurrent transient model adjustments significantly improve the

model and field data correlation.

Figure 6-13: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 1

The previous two model adjustments predominantly accounted for the pressure wave phase and

dissipation. However, the model still under-predicts the first two positive pressure wave amplitudes.

In addition to the important physical system properties (e.g., length, diameter, etc.) and steady state

model assumptions (e.g., friction, flow, head, etc.), the transient model for a wastewater system can

also be adjusted to better account for vapour pressure, check valve slam, and air cavity formation

and collapse. The next pair of figures present a few alternative results of such an additional model

adjustment exercise; an exercise performed through several sensitivity analyses and concurrent trial

and error adjustments. Figure 6-15 shows the comparison results with the following model (blue

series) adjustments:

Page 137: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

126

• Vapour pressure (see Chapter 3) is increased to a very high value of 7 m;

• Wavespeed is set at 175 m/s;

• MRI is significantly reduced to 1 kg-m2 to take into account the new (and less

heavy) type of pump; and

• Unsteady friction assumption is preserved.

With the above transient parameter adjustments, the model better approximates the initial positive

upsurge value, while still preserving the pressure wave phase and dissipation mechanism.

Nonetheless, the model still under predicts the maximum transient pressure by almost 40% (12 psi).

From a physical perspective, the large upsurge magnitude recorded by the field pressure monitor is

likely due to a vapour cavity collapse. The field test observation records noted a significant air

presence and a loud and evident activation (i.e., hissing) of two CAVs within the station, following a

pump trip. As such, it is likely that the field data recorded a significant air pocket collapse following

the first return upsurge. This can further be adjusted in the model through the addition of the

proper air valves; air valves that would then be simulated to rapidly expel the air that they initially

allow to enter the system.

Figure 6-14: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 2

Page 138: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

127

Figure 6-15: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 3

Figure 6-16 presents results for a few additional and incremental model adjustments. It includes two

series (green and blue) that fine-tune the three previous parameters of wavespeed, MRI, and Vp.

More interestingly, these two model results also include an adjustment to the representation of the

check valve(s) at the pump station. In these cases, the check valve properties were changed such

that a partial reverse flow through the check valve(s) was possible, thereby increasing the magnitude

of the check valve slam and the subsequent rise in pressure.

Overall, the above discussed model adjustments act to significantly improve the original model

performance. While still not perfect, the model nonetheless is more representative and therefore

can better be used to make additional analysis and design decisions for this system. A complete

calibration is essentially impossible to achieve due to the number of variables. Furthermore, it

requires additional field data sets for confirmation. Otherwise, one can easily over compensate

through specific parameter adjustments, thereby making the model less representative as a whole.

Page 139: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

128

Figure 6-16: Model v. Field Comparison – Wastewater Forcemain (Ontario) – Part 4

6.5 Summary

Building upon the previous chapter’s examination of the benefits of using transient field work for

making important design and analysis decisions, this chapter provides a clear and useful link between

field data and numerical modeling. The resulting numerical model validation discussion in this

chapter essentially forms the basis of the previously proposed hybrid method for a transient analysis.

The benefits of combining field work with numerical model are presented through four (4) unique

case studies of actual (i.e., in-situ) systems. The case studies are carefully selected not only to

provide examples of the risks of solely relying on numerical modeling, but also to illustrate the

difference between a variety of system types (as is discussed in Chapter 2). While the numerical

validation examples are quite technical in nature, the overall chapter premise and conclusion is that

field data and modeling data must be combined, such that they can collectively be used to perform

comprehensive transient analysis and design.

Page 140: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

129

Chapter 7 Transient Risk Index

The previous chapters describe the importance of transient pressure monitoring and show how the

data acquired from such field work can be used to assist in the analysis and design of systems, as

well as to validate numerical transient models. The TP-1 equipment is shown to be the best for

long-term transient pressure monitoring, and this continuous pressure monitoring was anecdotally

shown to be useful for assessing the hydraulic performance of water and wastewater systems. This

chapter proposes that such long-term transient pressure data be used in a more direct and

statistically derived transient risk assessment. More specifically, it proposes the use of a Transient

Risk Index (TRI) in order to benchmark and compare the overall transient risk between similar

hydraulic systems.

7.1 Purpose and Background

7.1.1 The Nature of System Failure

The difficult task in conducting a transient risk assessment is estimating a realistic likelihood of

occurrence of an event, and the likely magnitude and timing of any resulting consequence(s).

Hydraulic transients are typically brought on by local changes, but their impact (and therefore risk) is

often felt across the entire hydraulic system. Furthermore, transient events present one form of risk;

a risk that is further compounded by other system risks, including those potentially arising from

poor design, improper construction, environmental conditions, poor operation, aging infrastructure,

and emergency events. As a result, it is not only an individual transient event that can directly lead

to a system or performance failure, but also the joint effect of multiple transient events in

combination with other system events and/or risks. Of course, the actual cause of a joint system or

performance failure is often difficult to ascertain immediately following the occurrence.

Furthermore, and possibly more importantly, the probability (or even, the frequency) of occurrence

and the timing of any resulting consequence are equally as difficult to predict for a joint system

failure. As an example, consider the 1979 near catastrophic failure at the Three Mile Island nuclear

plant, in which an unlikely and unpredictable series of events lead to a system failure. In this case, a

filter blockage caused a moisture leak, which tripped valves and shut down the flow of cold water

into the plant's steam generator. The primary backup system was not functioning on that day, and

the secondary backup relief valves got stuck and failed to properly close. Lastly, the primary backup

Page 141: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

130

system failure alarm was partially obstructed and the gauge for the relief valves malfunctioned.

Gladwell (1996) summarized the near catastrophic system failure as “a major accident caused by five

discrete events”, and the culprit as the way these “minor events unexpectedly interacted to create a

major problem”. Water and wastewater systems are often subjected to severe single event type of

risks, but also to risks arising from joint or series events such as the ones in the Three Mile Island

case.

The simplest and most direct synonymous quantitative application of the above idea is the case in

which a pipe break is solely caused by internal pipe pressure changes. Water and wastewater pipes

are typically designed to withstand a normal operating (often called “working”) internal pressure, but

also a short-lived transient pressure. The following subsection provides a brief summary on the

design of pipes for internal pressure in order to establish the general background understanding for

the purpose of the proposed TRI.

7.1.2 Pressure Class Design for Isolated Transient Events

The methodology for determining the required pressure rating for a pipe directly accounts for both

operating pressures and transient pressures. The current approach for pressurized pipe design relies

on the concept of pressure class. Pipe pressure class design is a performance based specification

that gives pipes a rating based on their ability to withstand internal pressures. It provides standard

criteria for manufacturing, for design, and for comparison across different material types with the

same performance expectations. In steel, DI, and CPP, the pressure rating is directly based on the

wall thickness of the pipe and the strength of the material. With a given design pressure that a pipe

will likely experience during operation, the designer can solve for a minimum thickness or simply

pick from a list of available pipes with specific pressure ratings. Each of the pipe pressure classes

includes an additional allowance for short-lived transient pressures. This “surge allowance” is

usually given as a percentage of the working pressure (Pw); a summary example of which is shown in

Table 7-1 (Mielke, 2004).

Page 142: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

131

Table 7-1: Sample Pipe Pressure Class Properties (Mielke, 2004)

For thermoplastic pipes, the pipe’s rating or pressure class is determined using design equations that

factor in the material’s strength, pipe wall thickness, and diameter. The strength of PVC and

HDPE pipes is usually determined through ASTM testing procedures (ASTM D1598, ASTM

D2837, ASTM D638); procedures that subject the pipe to an internal pressure and extrapolate the

strength after 100,000 hours. In determining a thermoplastic pipe’s pressure class, standards such as

AWWA C900 incorporate a surge allowance equivalent to a 2 ft/s instantaneous stoppage of water

in the pipe. However, most thermoplastic standards require testing the pipe up to 2 to 5 times its

pressure rating; a test that in most cases covers common isolated transients as well. Lastly, the

transient pressure build-up in thermoplastic pipes is considered lower than for other materials due to

the material’s behaviour under stress.

7.1.3 Pressure Class Design for Cyclic Loading

The risk of failure from cyclic surge pressures is usually not fully accounted for in most hydraulic

transient analysis of water and wastewater systems due to the lack of guidance available from many

standards (Murray et al., 2004). Since the number of cycles required for pipe failure is often quite

large, system designers tend to ignore the potential risk of fatigue failure resulting from repetitive

pressure cycling. As noted earlier, a failure that occurs due to pressure cycling will likely result due

to a series of events, and therefore inadequate design will rarely be proven as the sole cause of the

failure.

The standards that do cover fatigue from cyclical pressure loading often take a different approach.

The British and Australian codes explicitly mention cyclic loading from transient pressures. A

Page 143: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

132

number of studies (Jeffrey et. al. 2004, Kirby 1980, Bowman 1990, Zarghamee 1990, and Marshall

1998) have been conducted on thermoplastic pipes to determine their behaviour under cyclic

loading. These studies subjected pipes to a large number of cyclic loads and observed for signs of

failure. As a result, a number of failure curves have been produced from such studies, and these

curves typically show the amplitude of the pressure loadings and the number of cycles for failure.

An example of fatigue design load factors from the Plastics Industry Pipe Association of Australia is

shown in Table 7-2.

Table 7-2: Fatigue Load Factors for PE Pipe (PIPA, 2002)

7.1.4 Importance of Risk Assessment

The above pipe design approaches essentially look at the difference in the risk of failure due to both

overall internal pressure and internal pressure fluctuations. In a general sense, transient risks can be

divided into two broad categories:

1. Those associated with catastrophic failure from significant isolated surge events or a

catastrophic combination of many other joint but discrete events; and

2. Those associated with long-term fatigue or cycling failure from repetitive and frequent

pressure variations or combination of other joint discrete events.

While both of these transient induced failures are form of system risk, only the first is typically

considered in traditional transient analysis, especially if the analysis is driven by numerical modeling.

As discussed in Chapter 2, hydraulic transient analysis is typically performed based on anticipated

Page 144: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

133

worst-case scenarios; scenarios which are deemed to present the risk in category no. 1. The main

obstacle to a comprehensive transient risk assessment is the difficulty of addressing the statistics –

the probability of occurrence, the frequency of occurrence, and the magnitude of the consequence.

As a result, most transient analyses are rather quite qualitative in nature. This is where the

continuous transient pressure monitoring of actual systems can indeed be used to bridge the gap

between qualitative or subjective analysis and actual quantitative (or frequency based) assessments

that rely on acquired data. The objective of the subsequently discussed methodology is to address

the composite transient induced system risk; a risk that includes events that range from high

consequence but infrequent to those that are lower consequence but frequent.

7.2 Requirements, Parameters, and Definitions

In order to derive a useful and statistic based methodology for a transient risk assessment using field

pressure data (an example of which is the proposed TRI), several system and analysis requirements

must first be established. The requirements must differentiate between different types of systems

and must establish clear statistical definitions of parameters that are to be considered. The

parameter definitions must then be used to establish a consistent methodology for acquiring and

analyzing pressure data and for determining composite parameters than can be compared across

different systems.

7.2.1 System and External Influences

Hydraulic transient events and overall transient risks are unique and different for every system.

Unlike other areas of study such as rainfall and runoff analysis, travel time analysis, structural load

analysis, etc., the number of externalities that can significantly undermine a statistical analysis

approach for hydraulic transients is much greater. The occurrence, risk, and consequence of

transient events are influenced by a host of system properties and external factors, including, but not

limited to the following:

1. Type of fluid (e.g., potable water, wastewater, etc.);

2. Type of system (e.g., pressurized wastewater, water transmission, water distribution,

gravity, etc.);

3. Method and nature of system operation (e.g., pump changes, valve operations, etc.);

Page 145: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

134

4. System condition and location (e.g., strength of pipe and equipment, construction

quality, age of equipment, elevation, etc.);

5. Additional (non-transient) risks (e.g., soil aggressiveness, quality of water source,

awareness of transients, etc.);

6. Type and nature of surge protection; and

7. Multiple transient event occurrence and interference.

The above factors can significantly influence any statistical approach that is aimed towards

comparing the risk of one system to another. This is especially the case for the proposed TRI; the

methodology for which is described in the following section. Nonetheless, since this type of risk

assessment methodology is still in the preliminary stage, it is useful to make some general system

assumptions in order to develop the proper definitions. These definitions are based on a typical

system with the following properties:

1. A pressurized water or wastewater system in which transient events are induced by

routine and non-routine operations (e.g., valves, pumps, etc.).

2. Prior to any transient event, the pressure is relatively constant and can be defined as a

steady state starting point.

3. A transient event is defined as any pressure fluctuation that is quantifiably different

(i.e., meets minimum criteria) than the steady state pressure.

4. A typical transient event consists of a either an initial downsurge or an upsurge, and is

followed by period of pressure oscillation.

5. Any subsequent transient event that is an automatic reaction to an initial event is

considered as a separate and unique event.

6. Following the transient event, the system re-stabilizes at a new steady state that may or

may not be equal to the original steady state.

With the following basic and general system properties in place, the next step is to define specific

parameters. The following subsections present two important categories of parameter definitions:

1. Single Transient Event Parameters – used for defining statistical properties of any one

transient event.

Page 146: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

135

2. Multiple Transient Event Parameters – used for delineating between multiple transient

events and for defining field pressure monitoring and recording parameters.

7.2.2 Single Transient Event Parameters

Continuous transient pressure monitoring typically yields a significant amount of data; data that

consists of both steady state pressure fluctuations and transient events. In order to derive a TRI (or

any similar metric), specific parameters must first be defined for a “typical” transient event. Figure

7-1 presents a graphical illustration of a “typical” transient event, including important event

properties and parameters.

Figure 7-1: Single Transient Event Properties & Parameters

Page 147: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

136

Table 7-3: Single Transient Event Parameter Definitions

Notation Name Definition

Po Initial (Pre-Event) Steady State Pressure

Constant (or relatively constant) average background pressure before a single transient event.

PMIN Minimum Transient Event Pressure Magnitude

The absolute minimum pressure (crest) during a single transient event.

PMAX Maximum Transient Event Pressure Magnitude

The absolute maximum pressure (crest) during a single transient event.

PV Full Vacuum Pressure Full vacuum pressure limitation of -10.4 m H20 gauge or -14.7 psi gauge.

PF Final (Post-Event) Steady State Pressure

Constant (or relatively constant) average background pressure after a single transient event.

∆PMIN Transient Low Pressure Range

Maximum low pressure range (i.e., downsurge amplitude) during a single transient event.

∆PMAX Transient High Pressure Range

Maximum high (pressure range (i.e., upsurge amplitude) during a single transient event.

∆PSS Steady State Pressure Change

Difference between the initial and final steady state pressure magnitudes.

TEVENT Transient Event Duration Duration of transient event, from initial to final steady state pressure equilibriums.

TPERIOD Pressure Wave Period Average pressure wave period or cycle (i.e., duration between wave crests or wave troughs).

TNEGATIVE Negative Pressure Duration Summation of negative pressure (i.e., below atmospheric pressure or 0 gauge) durations for a single transient event.

With the above single event parameters and definitions in place, several additional, useful, and often

obvious relationships can be derived. These include the following:

1. ∆PMIN = Po - PMIN

2. ∆PMAX = PMAX - Po

3. ∆PSS = Po - PF

4. TPERIOD = 4L/a where L is the system length and a the wavespeed

5. TEVENT = nTPERIOD = n4L/a where is n the number of cycles during the event

With these definitions in place, simple event driven statistics such as the mean, standard deviation,

correlation coefficients, etc., can be calculated (see sample data in Chapter 5.5).

Page 148: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

137

7.2.3 Multiple Transient Event Parameters

The previously discussed parameters and definitions are relatively easy to understand and calculate

when the background (steady state) pressures are mostly constant and when a transient event is

relatively clear. The difficulty in the above approach arises when the background pressures are more

variable (i.e., moderately transient) and when multiple transient events occur within a short period of

time. If the transient pressure monitor in the field is set to continuously record at a high frequency

(e.g., 100 Hz), the resulting sample data set would render the single transient event definition, and

the associated parameters, much less clear. In such a case, a different and more rigorous

methodology would need to be established in order to statistically define what a transient event is.

Fortunately, this thesis has thus far shown the benefits of, and relied on, the use of the Pipetech TP-

1 transient pressure monitor. This technology is capable of recording transient events at high

frequency and background (steady state) pressures at a lower frequency; thereby not only minimizing

the size of the data set, but also inherently defining a single transient event through user initiated

recording parameters. As Chapter 5 has shown, the three (3) key parameters for defining a transient

event using the TP-1 transient pressure monitor (Pipetech, 2008) from an average background

pressure are as follows:

1. Start Record Standard Deviation (SSTART);

2. Start Record Absolute Pressure Change (∆PSTART); and

3. Stop Record Standard Deviation (SSTOP).

The above TP-1 parameters typically have to be adjusted to match specific pressures and the

operating philosophy of a particular system, but once in place these parameters do an excellent job

of delineating between a background pressure and a transient event. As a result, the traditional

event definition conundrum of any long-term statistical analysis is addressed in advance of the data

analysis stage. While this is beneficial for the ultimate end goal, the proper selection of the above

recording parameters is extremely important. The following TRI methodology directly assumes that

this critical step has been optimized.

While a TP-1 monitor can easily distinguish a transient event from a background pressure, it often

has trouble with:

1. Recording the entire transient event as a single event; and

Page 149: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

138

2. Recording the complete transient event.

The problem in both of these two cases is the issue of the pressure remaining relatively constant for

a short period of time during an actual transient event. From a physical point of view, one can

understand and accept that transient events can indeed contain plateau shaped crests (positive or

negative), or periods in which the relative constant pressure may actually resemble a new steady

state. Figure 7-2 presents a sample but generic pressure profile for a multiple transient event trace.

Figure 7-2: Multiple Transient Event Properties & Parameters

The blue data points represent low frequency recording during a relatively steady background

pressure period, while the red data points represent high frequency recording of transient pressures.

From a physical point of view, this sample pressure trace comprises two transient events: event no. 1

and event no. 2. Event no. 1 is a typical downsurge event that resembles a power failure. Following

this event, the system (background or steady state) pressure settles at a new equilibrium level. Event

no. 2 is an upsurge event that eventually raises the system background pressure. However, due to

the plateau in the low pressure crest of this second event, this event would likely be recorded as two

Page 150: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

139

separate events in the field. In other words, the TP-1 record parameters can mistake a short period

of constant pressure as new steady state equilibrium, thereby fragmenting a single transient event

into two (or more) events. This problem is unfortunately rooted back to the previously discussed

definition of a transient event, and more importantly requires a rigid definition that can delineate

between multiple transient pressure traces.

In their probabilistic analysis of the rainfall-runoff phenomenon, Adams and Papa (2000) applied

the concept of a statistical (and user defined) inter-event time in order to delineate between rainfall

events. Since such a user defined parameter can significantly impact any resulting statistical analysis,

the authors noted three (3) potential (but previously published) methods for determining a suitable

inter-event time for a data set. These methods include the following:

1. Autocorrelation Analysis – correlation of data in one point in time with another point

in time via a minimum lag time parameter.

2. Probability Density Analysis – correlation of inter-event times with a density

distribution such as the exponential, and a subsequent selection that yields a

coefficient of variation equal to unity.

3. Event Number Analysis – correlation between inter-event times and the resulting

number of events in a data set, and a subsequent selection based on minimal additional

impact on the number of events.

While an inter-event time definition is statistically powerful, and while the above inter-event time

selection methods can indeed be used, such a methodology is currently not necessarily required in

order to deal with the multiple event dilemma. In fact, due to the reliance on the recording

technology for the definition of a transient event, it is much simpler to account for multiple events

by a post data processing algorithm adjustment that is similar to the inter-event time definition.

Based on an analysis of multiple data sets (for different systems and different recording parameters),

the unintended fragmentation of a single transient event into multiple events can be eliminated by

introducing an inter-event time (TIE) that is correlated to a number of background recordings (see

Figure 7-2), such that:

TIE = m TIB

Page 151: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

140

where m is the number of background recordings during the perceived inter-event

time period and TIB is the preset time period between background recordings (i.e.,

inverse of the background record frequency)

In most of the data sets analyzed to date, a value of 2 or 3 for m is sufficient for ensuring that a post

data processing algorithm properly accounts for “fictitious” multiple transient events. In other

words, such a post data processing algorithm essentially prescribes a minimum number of

background recordings (and when combined with the frequency of recording – the overall duration)

prior to a transient event being classified as complete, thereby ensuring a more accurate

representation of any one transient event.

7.3 Methodology

With fine-tuned TP-1 (or equivalent) pressure recording parameters and rigid event parameters a

data processing algorithm can be used to extract all transient events from a continuous pressure

monitoring data set. Samples of such transient event summaries have previously been shown in

Chapter 5.5. These transient event summaries can then be used to calculate individual and

combined statistical event parameters, such as those previously outlined in Table 7-3. This is best

achieved through a simple database query of the transient event summary. The overall goal of this

type of analysis would be to associate a frequency to the event, and therefore establish a true metric

of risk. (To date, hydraulic transient “risk” assessments still lack the characterization of the

frequency component and are therefore mostly qualitative assessments of the expected

consequences).

With all of the definitions, assumptions and processed event data in place, a preliminary transient

risk assessment methodology such as the proposed Transient Risk Index (TRI) can finally be

compiled. Figure 7-3 presents a generic graphical representation of a possible TRI. The goal of a

TRI is to assess the cumulative risk of all transient events for a pressure monitoring period and to

then ideally extend this to the complete lifespan of a system. The basic notion here is that small

magnitude transient events (both positive and negative) occur frequently but with lower

consequence, and that large magnitude transient events (both positive and negative) occur

infrequently but with high consequence. Unlike in the case of a traditional risk analysis, it is NOT

only the rare and high consequence event that presents a risk to the system, but actually it is the

Page 152: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

141

combined effect of ALL events. While the TRI is likely not the only viable metric or approach,

system indices such as these are very simple to understand, benchmark, and compare, and are

therefore quite useful for understanding the transient performance (and therefore the risk) of a

system.

The TRI would be plotted on a both a positive and negative y-axis constituting an absolute or

normalized maximum and minimum transient pressure, and on an x-axis that constitutes an event

return period (TR). The negative pressure axis would ideally be limited to the full vacuum limit due

to inherent assumption that traditional water and wastewater systems likely cannot sustain such a

condition. (This statement does not imply that water is not capable of sustaining full vacuum

pressures.)

Figure 7-3: Transient Risk Index Schematic

Page 153: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

142

The event return period (or recurrence interval) for the x-axis can be calculated by initially compiling

a list, plot, or histogram of maximum and minimum transient pressures. The data processing

algorithm would produce an occurrence (i.e., event magnitude) count for a pre-selected pressure

gradation (e.g., 1 psi, 2 psi, 3 psi, etc. range), and this event magnitude count would then be ranked

for an m number of different pressure gradations. Several statistical analysis approaches can be

taken from this point on, but at this stage it is likely the simplest to define an event return period

such that:

where m is the rank of the pressure gradation count and n is the data

set recording or analysis period (in days)

The figure would essentially yield two curves that start from the origin: a positive transient pressure

risk limit curve and a negative transient pressure limit curve. The shape of the positive and negative

risk curves have yet to be officially determined, but should likely have a shape in which the transient

pressure magnitudes increase for a larger value of the return period. With a large enough sample

size (i.e., long enough duration of pressure monitoring), a specific function (e.g., exponential) could

eventually be mapped to the curves such that:

and

With the above two continuous functions in place, a TRI can then be calculated for the positive risk

index and for the negative risk index. The proposed notation for such indices is as follows:

TRI+= Positive Transient Risk Index

TRI- = Negative Transient Risk Index

TRI+ would simply be equal to the area under the positive risk curve and above the x-axis, and the

TRI- would be equal to the area above the negative risk curve and below the x-axis. The generic

equations for the two TRIs metrics would therefore be as follows:

0

( )

T

MAX RTRI P f T

+

+

= =∫

1R

nT

m

+=

( )MAX RP f T= ( )MIN RP f T=

Page 154: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

143

0

( )

T

MIN RTRI P f T

= =∫

The limits of integration for the risk indices would be that of the maximum return period from the

data set (denoted as T+ and T- in the above equations), and the units for the indices would be in the

form of pressure multiplied by the return period, such as psi-days or m(H20)-days. However, the

units would often be omitted in order to uphold the true sense of an index value.

The proposed TRI methodology is intended to provide a simple and easy method for determining

the degree of the overall transient pressure risk for water and wastewater systems. More

importantly, it is intended to provide a simple link and understanding between continuous transient

pressure monitoring and a risk assessment. Having said that, the concept, methodology and

definitions for the TRI are still in their preliminary stage, and the TRI may end up simply being used

as a stepping stone for more comprehensive (yet still quantitative in nature) hydraulic transient risk

assessments.

7.4 Sample Results

As noted earlier, the TRI concept is still in its early stage of development and therefore any sample

results must be considered as trial, and even as slightly premature. The short duration of less than a

year for a few of the system monitoring locations does not provide a large enough of a sample data

set. Furthermore, the data processing algorithm still requires additional flexibility and adjustments

for the gradation of the recorded transient events and pressure data. Nonetheless, Figure 7-4

presents two preliminary data sets for the previously discussed Lakeview Zone 1 and Zone 2 water

distribution systems in the Region of Peel.

Page 155: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

144

Figure 7-4: Sample Preliminary TRI Graph for the Lakeview Zone 1 and 2 Systems

The absolute positive transient pressure event magnitude is plotted against the return period, for a

pressure gradation of 2.5 psi. Due to the existing surge protection at the Lakeview WTP, the

transient pressure magnitudes are well controlled and therefore the sample data set is dominated by

absolute pressure in the 160 to 180 psi range. Furthermore, due to the current limitations of the

data processing algorithm, the y-axis only plots the absolute pressure value and not the transient

pressure range – a range which must be calculated based on the starting operating (i.e., steady state)

pressure. As of a result of both of these limitations, a risk curve and the calculation of the TRI (i.e.,

the area under the curve) are not provided at this time. Nonetheless, the sample figure re-establishes

the general TRI approach using actual field data.

7.5 Discussion

The previous chapters demonstrate the need for a field data based transient risk assessment and the

previous sections in this chapter provide the initial definitions and methodology for one sample

approach – the TRI. While general rules for the pressure recording and the definitions for a

Page 156: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

145

transient event (both single and multiple) are established, there still exist a lot of questions and

uncertainties as to what the best method to calculate such a risk assessment metric actually is. The

proposed TRI is simply one alternative; an alternative that frankly still needs to be completed before

it could gain widespread acceptance. There are many details that must be considered, and many

options and/or variances that can be used. This section provides a brief and itemized discussion of

several important considerations, and provides recommendations for the improvement and

implementation of this concept and methodology.

• Long-term data on the order of years should be acquired for a variety of systems, and the

data should be processed for the purpose of developing better TRI curves and values.

• A sensitivity analysis of the user defined TP-1 settings and parameters should be performed

in order to establish a rigorous approach for acquiring the transient pressure data.

• The TRI methodology should investigate the impacts of, and how to deal with, the

interference of actual multiple transient events. For example, how should the TRI metric

account for two transient events that superimpose across a certain period in time?

• More rigorous guidelines should be established for the pressure gradations (i.e., y-axis), and a

sensitivity analysis of the gradation parameter should be performed.

• A theoretical (i.e., non-recording logic driven) definition of a transient event should be

derived and compared to the results achieved from the data post-processing. In other

words, what actually constitutes a transient event? Are not all pressure recordings transient

depending on the scale being considered?

• Using long-term processed data, several TRI curves should be plotted and the sample values

calculated. The goal would be to determine the true nature and profile of the risk curves.

• The TRI curves and values should be compared across a range of different system types,

including but not limited to the differences between: water and wastewater, transmission and

distribution, high head and low head pumping, with and without surge protection, etc.

• TRI curves are likely to be fragmented (i.e., discretized) for most systems, and therefore the

continuous function approach may need to be reconsidered.

• The addition of another minimum pressure curve should be considered to account for the

fact that not all minimum pressures are negative. In other words, the methodology should

consider adjusting the x-axis to match an average operating pressure range rather than the

value of atmospheric pressure (i.e., 0 gauge).

Page 157: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

146

• The methodology should consider the potential benefits and differences of changing the

concept of both the x and y axes. More specifically, the value and/or usefulness of the

metric should be evaluated by changing the y-axis to either a normalized (i.e., ratio based)

version of transient pressure or a transient pressure range (rather than absolute value).

Similarly, the benefits of changing the x-axis from a traditional return period to a simpler

count (or histogram) should also be investigated.

• The proposed TRI methodology should consider and investigate the maximum limit of

integration. In other words, should it be limited to the maximum recorded pressure?

Maximum pipe or device pressure rating? Infinity? etc.

• Initial TRI system values should be used to set benchmarks and to compare not only the risk

between different systems but also the change in the risk across the life of one system.

• Once a rigid transient pressure recording and TRI methodology are established, the sample

TRI curves should be fitted with probability distribution curves. The type of curve would

likely depend on the properties of the system, but could be quite useful for not only

calculating the TRI values but also for establishing closed-form relationships between

transient pressure magnitudes and event occurrence.

• The resulting TRI curves should be correlated to system strength, such as pipe rating or

fatigue curves, in order to present a true transient load versus system strength analysis.

• The TRI methodology should be used to assess and adjust for different system components

(e.g., pipe, valve, pump, etc.) and failure types (intrusion, pipe rupture due to high pressure,

fatigue failure, etc.). Furthermore, the data and subsequent analysis should be used in

conjunction with specific (albeit still to be properly quantified in this context) risk measures

such as reliability, resilience and range of damages.

• The TRI methodology should be extended and applied to different transient event

parameters and not just pressure. Such parameters to consider include: event duration,

negative pressure duration, number of cycles, and transient wave decay.

• While the TRI should be accepted as an initial starting point, additional consideration and

investigation should be given to other (i.e., non TRI) approaches for making beneficial use

of long-term transient pressure data. Any such approach should be aimed at correlating the

frequency of a transient event to the overall risk to the system. Such options may include a

moving window analysis, transient scenario analysis using stochastic events, random event

analysis, choice-constraint analysis, analysis of frequency of loading, etc. For example, can

Page 158: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

147

the long-term transient pressure monitoring results be used within a Monte Carlo simulation

to determine a metric such as an annual expected damage? Similarly, can the long-term

transient pressure monitoring results be used to determine the frequency of loading (e.g.,

power failure events)?

• Academia and industry should begin to promote (as well to develop) frequency based risk

assessment methodologies in the realm of hydraulic transients. Decisions must eventually be

correlated to quantifiable metrics in order to truly understand the hydraulic transient

performance of the systems in question.

As demonstrated by the above long list of considerations and recommendations, the current state of

the proposed TRI (or any other quantitative transient risk assessment derived from long-term field

pressure data) is limited and uncertain, but also open for significant discussion. However, with the

proper definitions and additional (i.e., more comprehensive) field data, the answers for many of

these questions and concerns will slowly take form. In the end, the goal of any such analysis would

be to actually quantify the overall in-situ risk due to transients for a variety of traditional water and

wastewater systems.

7.6 Summary

The purpose of this chapter is to establish the need and methodology for a quantitative risk

assessment of transient events in water and wastewater systems. The chapter initially provides

background information on system failure types, and establishes the general idea that a transient risk

is not confined to a single rare event of high consequence, but to the combined impact of all events.

With that in mind, the chapter proposes a trial risk assessment methodology relying on an index-

based metric. Sample guidelines are provided for the recording of transient pressures and for the

definition of both single and multiple transient event parameters. Initial sample results are provided

under the knowledge that several externalities currently play a key role, and that many limitations

currently still exist. The chapter concludes with a discussion and recommendation of items that

should be considered in order to move this quantitative risk assessment approach forward.

Page 159: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

148

Chapter 8 Summary and Conclusions

Water and wastewater systems are an integral part of the overall infrastructure network and they play

a significant role in the welfare and progress of society. The analysis and design of such systems has

been at the forefront of Civil Engineering for centuries, and still continues to attract innovations and

intellectual thought in both academia and industry. The purpose of this thesis is to bring specific

attention to a small, often minimized, but quite important segment of water and wastewater system

design – the task of performing a hydraulic transient analysis. The overriding theme of this thesis is

the need to increase the use of field based hydraulic transient assessments as a means of

supplementing the now default standard of numerical modeling.

This thesis document provides the basic background for understanding what hydraulic transients

are, why they are important, and what should be done about them. More specifically, the thesis

discusses the nature of, and difference between, hydraulic transients in the context of three common

types of pressurized municipal systems: water transmission, water distribution and wastewater

forcemain. As a means of illustrating the risk and subsequent prevention/mitigation, a long list and

discussion of potential transient protection options and alternatives is presented.

The thesis document identifies the traditional and current methods for conducting a hydraulic

transient analysis, and proposes a hybrid alternative in which actual in-situ field assessment data can

be used in combination with numerical modeling and standard convention to yield the desired

output – a well designed and protected water and wastewater system. The thesis document also

provides a focused critical discussion of some of the shortcomings in the current approach; one in

which numerical models are typically used to assess the hydraulic transient risk. The discussion

includes consideration of steady state model assumptions, the non-deterministic nature of water

demand, and the traditional worst-case nature of transient loading design. Furthermore, this

discussion also identifies the key differences between water and wastewater transient analyses and

the re-emphasizes the overall need to improve the in-situ performance monitoring of real systems.

Following a brief aside on the field based quantification of the water quality risk from pathogen

intrusion via flooded air valve chambers during low pressure transient events, the thesis document

moves on to provide a comparison and assessment of modern transient pressure monitoring

Page 160: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

149

technology. The document provides a detailed and comprehensive comparison of six (6)

commercially available transient pressure monitors on the criteria of long-term field based transient

pressure recording. With this objective in mind, a single technology is shown to demonstrate the

greatest current potential, and the details of this technology, including actual case studies and

examples, are then presented in order to establish the capability of a field driven transient risk

assessment. The long-term transient pressure data is supplemented by data derived from transient

field tests in order to illustrate the difference between, and the need for, the proposed numerical and

field validation approach. This objective is also achieved through four (4) distinct case studies;

studies which cover a wide range of system types and transient based system variables.

The last section of the thesis provides an introduction to one option by which the long-term

transient pressure data for a system could be used to evaluate the overall risk due to hydraulic

transients. The approach is established as a means by which the shortcomings in the theoretical

assumptions could be overcome via a quantitative analysis in the form of a Transient Risk Index

(TRI). The proposed TRI methodology first establishes the required definitions for both the

recording logic and the general properties of a transient event. It then proceeds to illustrate how

such an index-based metric could actually be calculated and how this overall approach can be

beneficially implemented, used, and improved.

While a significant portion of the thesis document cannot be considered as completely innovative

from an academic point of view, it is the author’s strong belief that the nature and synthesis of the

information is indeed an indication of a significant shortcoming in the current (and the direction of

the future) industry practice with respect to hydraulic transient analysis. Even with that important

point in mind, the thesis document does provide several key and additional contributions to both

academia and industry, and these include the following:

1. The identification of current hydraulic transient analysis shortcomings and the need

for a revised hybrid approach that relies on field work such as transient pressure

monitoring to compliment and validate traditional numerical hydraulic transient

models.

Page 161: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

150

2. A comparison and identification of suitable technology for assessing the long-term

hydraulic transient performance of water and wastewater systems in the field, including

the detailed approach and sample recording logic for quick implementation.

3. The identification of the benefits and the establishment of the initial framework for

both short-term and long-term hydraulic transient pressure monitoring and risk

assessment. Inherent in this is the establishment of the need for a revised and

quantifiable form of a hydraulic transient assessment.

4. The establishment of the preliminary methodology for an index based hydraulic

transient risk assessment that relies on data derived from long-term continuous

transient pressure monitoring.

The last chapter of the thesis provides a discussion of the uncertainties and current limitations

of the proposed transient risk assessment approach. As part of the discussion, a list of future

work considerations is provided such that the TRI can be improved, tested, and implemented.

In the end, the goal of any such assessment methodology is to make good use of valuable in-

situ data for the purpose of ultimately improving the performance, efficiency, reliability and

safety of the system at hand. It is exactly this theme – the need to close the loop between

transient analysis and actual system performance – that is the overall purpose and focus of this

thesis document.

Page 162: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

151

References

Adams, B. J., and Papa, F. (2000). Urban Stormwater Management Planning with Analytical Probabilistic Models. John Wiley & Sons, Inc., New York, U.S.A. ANSI/AWWA. (1997). “C900 Standard: Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, 4 in. through 48 in. for Water Distribution,” American Water Works Association, Denver, Colorado, U.S.A. Axworthy D. H., and Chabot, N. (2004). “Pressure Transients in a Canadian Sewage Force Main.” Canadian Journal of Civil Engineering, 31:1039. Babayan, A. V., Kapelan, Z., Savic, D. A., and Walters, G. A. (2005). “Least Cost Design of Robust Water Distribution Networks Under Demand Uncertainty.” Journal of Water Resources Planning and Management, 131:5:375(8). Benjamin, J., and Cornell, C. A. (1970). Probability, Statistics, and Decisions for Civil Engineers. McGraw-Hill, New York, U.S.A. Bergant, A., Simpson, A. R., and Tijsseling A. S. (2006). “Water Hammer with Water Column Separation: A Historical Review.” Journal of Fluids and Structure, 22:135. Bergant, A., and Simpson A. R. (1999). “Pipeline Column Separation Flow Regimes.” Journal of Hydraulic Engineering, ASCE, 125:8:835. Besner, M. C. (2007). “Risk Evaluation of Drinking Water Distribution System Contamination Due to Operation and Maintenance Activities.” Ph.D. Dissertation, Ecole Polytechnique de Montreal, Montreal, Quebec, Canada. Bolous, P. F., Lansey, K. E., and Karney, B. W. (2006). Comprehensive Water Distribution Systems Analysis Handbook for Engineers and Planners, Second Edition. MWH Soft, Pasadena, California, U.S.A. Bolous, P. F., Karney, B. W., Wood, D. J., and Lingireddy S. (2005). "Hydraulic Transient Guidelines for Protecting Water Distribution Systems." Journal of AWWA, 97:5:111. Bowman, J. A. (1990). “The Fatigue Response of Polyvinyl Chloride and Polyethylene Pipe Systems”. In Buried Plastic Pipe Technology, Buczala and Cassady, eds., ASTM, Baltimore, Maryland, U.S.A. Chaudhry, H. M. (1987). Applied Hydraulic Transients. Van Nostrand Reinhold, New York, U.S.A. Elliot, R. C., and Axworthy D. H. (2009). “Special Considerations in Pressure Surge Analysis and Control for Wastewater Systems.” Proceedings of the 33rd IAHR Congress: Water Engineering for a Sustainable Environment, Vancouver, Canada; August 2009. Filion, Y. R. (2006). “Multi-Objective Stochastic Design of Water Distribution Systems.” Ph.D. Dissertation, University of Toronto, Toronto, Ontario, Canada.

Page 163: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

152

Fleming, K. K., Gullick, R. W., Dugandzic, J. P., and LeChevallier, M. W. (2006). Susceptibility of Potable Water Distribution Systems to Negative Pressure Transients. AWWARF, Denver, Colorado, U.S.A. Fraser, S. L., Lim, J., and Donskey, C. J. (2010). Enterococcal Infections. Emedicine Publication, January 7. Retrieved from: http://emedicine.medscape.com/article/216993-overview Giustolisi, O., Laucelli, D., and Colombo, A. (2009). “Deterministic Versus Stochastic Design of Water Distribution Networks.” Journal of Water Resources Planning and Management, 135:2:117(11). Gladwell, M. (1996). “Blowup.” The New Yorker, January 22, 1996; New York, U.S.A. Goulter, I. (1992). “Systems Analysis in Water-Distribution Network Design: From Theory to Practice.” Journal of Water Resources Planning and Management, 118:3:1238(11). Grayman, W. M. (2005). “Incorporating Uncertainty and Variability in Engineering Analysis.” Journal of Water Resources Planning and Management, ASCE, 131:3:158. Jeffrey, J. D., Moser, A. P., and Folkman, S. L. (2004). Long-Term Cyclic Testing of PVC Pipe. Utah State University, Logan, Utah, U.S.A. Jung, B. S., Bolous, P. F., and Wood, D. J. (2007). "Pitfalls of Water Distribution Model Skeletonization for Surge Analysis." Journal of AWWA, 99:2:87. Jung, B. S., Filion, Y. R, Adams, B. J., and Karney, B. W. (2010) “Multi-Objective Optimization with Analytical Probabilistic Assessment to Design Branched Pipeline Systems for Fire Flow Protection”, Under Preparation. Jung, B. S., and Karney, B. W. (2009). "Systematic Surge Protection for Worst-Case Transient Loadings in Water Distribution Systems." Journal of Hydraulic Engineering, ASCE, 135:3:218. Jung, B. S., and Karney, B. W. (2008). "Systematic Exploration of Pipeline Network Calibration Using Transients." Journal of Hydraulic Research, IAHR, 46:1:129. Jung, B. S., and Karney, B. W. (2005). “The Search for the Worst-case Transient Loadings in Water Distribution Systems.” Proceedings of IAHR Conference, Seoul, Korea; September 2005. Jung, B. S., Karney, B. W., Bolous, P. F., and Wood, D. J. (2007). "The Need for Comprehensive Transient Analysis of Distribution Systems." Journal of AWWA, 99:1:112. Karney, B. W., and McInnis, D. (1990). “Transient Analysis of Water Distribution Systems.” Journal of AWWA, 82:7:62. Karney, B. W., and Radulj, D. (2009). “Transient Field Monitoring as a Key Driver for Decision Making and Design.” Proceedings of the 33rd IAHR Congress: Water Engineering for a Sustainable Environment, Vancouver, British Columbia, Canada; August 2009.

Page 164: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

153

Karney, B. W., and Radulj, D. (2008). “Assessing the Performance of a Water Transmission System Using an Inverse Transient Method.” Ontario Water Works Association Joint Annual Conference, London, Ontario, Canada; April 2008. Kirby, P. C. (1980). “Surge and Fatigue in Unplasticised PVC Sewer Rising Mains, Plastics and Rubber.” In Plastics and Rubber Materials and Applications. Water Research Centre, 5:1:78(5), London, United Kingdom. Kirmeyer, G., Friedman, M., Martel, K., Howie, D., Lechevallier, M., Abbaszadegan, M., Karim, M., and Funk, J. (2001). “Pathogen Intrusion into the Distribution System.” AWWARF. Denver, Colorado, U.S.A. Lansey, K. E., Ning Duan Mays, L. W., and Yeou-Kung, T. (1989). “Water Distribution System Design Under Uncertainties.” Journal of Water Resources Planning and Management, 115:5:630(16). Lauchlan, C. S., Escarameia, M., May, R. W. P., Burrows, R., and Gahan, C. (2005). “Air in Pipelines: A Literature Review.” Report SR 649, Rev. 2, HR Wallingford Ltd., United Kingdom. Lee, J., Lohani V. K., Dietrich, M., and Loganathan, G. V. (2009). “Low Pressure Propagation at Service Lines”, World Environmental and Water Resources Congress, ASCE. Kansas City, Missouri, U.S.A.; May 2009. Lehr, J. H., and Keeley, J. (2005). Water Encyclopedia: 5 Volume Set. John Wiley & Sons, New York, U.S.A. Lingireddy, S., Wood, D. J., and Zloczower, N. (2004). “Pressure Surges in Pipeline Systems Resulting from Air Releases.” Journal of AWWA, 96:7:88. Marshall, G. P., Brogden, S., and Shepherd, M. A. (1998). Evaluation of Surge and Fatigue Resistance of Poly (Vinyl-Chloride) and Polyethylene Pipeline Materials for use in the UK Water Industry. Pipeline Developments Ltd., Salford, United Kingdom. McInnis, D. A., Karney, B. W., and Axworthy D. H. (2004). TransAM Reference Manual. HydraTek Solutions Inc., Ajax, Ontario, Canada. McKay, M. D., Conover, W. J., and Beckman, R. J. (1979). “A Comparison of Three Methods for Selecting Values of Input Variables in the Analysis of Output from a Computer Code.” Technometrics, 21:2:239(7). Ministry of the Environment (1985). Guidelines for the Design of Water Distribution Systems. Environmental Approvals and Project Engineering Branch, Province of Ontario, Toronto, Ontario. Ministry of the Environment (2008). Design Guidelines for Drinking Water Systems. Province of Ontario, Canada. Ministry of the Environment (2008). Design Guidelines for Sewage Works. Province of Ontario, Canada.

Page 165: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

154

Mielke, D. R. (2004). “A Guide for the Design of Water Transmission Pipelines.” ASCE, Proceedings of the Pipeline Division Specialty Congress, San Diego, California, August. Murray, S. L., Lecina, S., Thollet, J., and Clark, P. B. (2004). “Surge in Water Systems: Some Issues Facing the Designer.” Proceedings of the 9th International Conference on Pressure Surges, BHR Group, Chester, United Kingdom; March 2004. MWH (2005). Water Treatment: Principles and Design. 2nd Edition, John Wiley & Sons, Hoboken, New Jersey, U.S.A. National Research Council (2006). Drinking Water Distribution Systems: Assessing and Reducing Risks. The National Academic Press, Washington, D.C., U.S.A. National Research Council (2003). “Water Quality in Water Distribution Systems: A Best Practice by the National Guide to Sustainable Municipal Infrastructure.” Issue 10, Ottawa, Ontario, Canada. Opitz, E. M., Langowski, J. F., Dziegielewski, B., Hannah-Sommers, N. A., Willett, J. S., and Hauer, R. J. (1998). "Forecasting Urban Water Use: Models and Application." Urban Water Demand Management and Planning, Baumann D., Boland, J. and Hanemann, W. H., eds., McGraw Hill. New York, U.S.A. O’Rourke, C. E. (1940). General Engineering Handbook. 2nd Edition, McGraw-Hill Book Company, New York, U.S.A. Pipetech International (2008). Transient Pressure Monitoring System Manual. Phoenix, Arizona, U.S.A. Plastics Industry Pipe Association of Australia Limited (2002). Polyethylene Pressure Pipes Design for Dynamic Stresses. Industry Guideline Document Issue 5, Chatswood, NSW, Australia. Radulj, D. (2007). “The Role of Air Valves in Water Distribution Systems.” B.A.Sc. Thesis, University of Toronto, Toronto, Ontario, Canada. Rowe, W. D. (1979). Introduction to Risk Assessment. In Energy Risk Management, G.T. Goodman and W.D. Rowe, eds. Academic. Press, London, United Kingdom, p. 7-19. Trifunovic, N. (2006). Introduction to Urban Water Distribution. Taylor & Francis, Netherlands. Uni-Bell PVC Pipe Association (2001). Handbook of PVC Pipe Design & Construction. Fourth Edition, Dallas, Texas, U.S.A. Viessman, W., and Hammer, M. J. (2005). Water Supply and Pollution Control. 7th Edition, Pearson Prentice Hall, Upper Saddle River, New Jersey, U.S.A. Walski, T. M. (2006). “History of Water Distribution.” Journal of AWWA, 98:3:3. Walski, T. M. (2003). Advanced Water Distribution Modeling and Management. 1st Edition, Haestad Methods Inc., Connecticut, U.S.A.

Page 166: ASSESSING THE HYDRAULIC TRANSIENT PERFORMANCE OF WATER AND WASTEWATER SYSTEMS · PDF file · 2010-11-03ii Assessing the Hydraulic Transient Performance of Water and Wastewater Systems

155

Walski, T. M. (2001). “The Wrong Paradigm - Why Water Distribution Doesn’t Work?” Journal of Water Resources Planning and Management, 127:4:203(3). Walski, T.M., Chase, D. V., and Savic, D. (2001). Water Distribution Modeling. 1st Edition, Haestad Methods Inc., Connecticut, U.S.A. Wood, D. J., Lingireddy, S., Bolous, P. F., Karney, B. W., and McPherson, D.L. (2005). "Numerical Methods for Modeling Transient Flow in Distribution Systems." Journal of AWWA, 97:7:104. Wylie, B. E., and Streeter, V. L. (1993). Fluid Transients. FEB Books, Ann Arbor, Michigan, U.S.A. Ysusi, M. A. (2000). "System Design: An Overview." Water Distribution Systems Handbook, Mays, L. W., ed., McGraw-Hill, New York, U.S.A. Zarghamee, M. S., Eggers D. W., Ojdrovic, R. P., and Rose B. (2003). “Risk Analysis of Prestressed Concrete Cylinder Pipe with Broken Wires.” Proceedings of ASCE Specialty Conference Pipelines 2003, Baltimore, Maryland, U.S.A. Zarghamee, M. S., and Fok, K. (1990). “Analysis of Prestressed Concrete Pipe under Combined Loads.” Journal of Structural Engineering, 116:7:2022.