Page 1: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

1ENTOC - All rights reserved, also regarding any disposal, exploitation, reproduction, editing, distribution, as well in the event of applications for industrial property rights

Atieh Hanna, Volvo Group Trucks Operations

Page 2: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

ENTOC Consortium

2

Page 3: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

Vision and objectives

From ambiguous natural language requirements and manual test generation …

… to formalized requirement documentation and automated test

generation

From component vendor and domain specific formats and delivery methods…

… to standardized mechatronic component models and

distribution systems

Instead of using engineering datafor designing and virtual commissioning only…

… using it continuously throughout the entire plant lifecycle for verification,

optimization and maintenance

From building company specific component simulation models …

… to simulation based on standardized mechatronic

component models

Increase efficiency, maturity and innovationin the engineering tool chain

by automated generation of virtual production systems

3

Page 4: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

Overview of work packages

4

Page 5: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

5

ENTOC Approach

5

Ass

iste

den

gine

erin

g

Future

Requirements EngineeringSpecification

Offer PreparationContract

Equipment DesignStatic 3D CAD Model

Virtual EngineeringDynamic Virtual Model

Virtual CommissioningTest Report for Control Logic

CommissioningStation ready to work

Final ApprovalAcceptance Certificate

Operation and MaintenanceMaintenance & Optimization Reports

Mai

nly

man

uale

ngin

eeri

ng

Today

Component & FMU store

Page 6: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

From ambiguous natural language requirements and manual test generation …

… to formalized requirement documentation and automated test

generation

From component vendor and domain specific formats and delivery methods…

… to standardized mechatronic component models and

distribution systems

From building company specific component simulation models …

… to simulation based on standardized mechatronic

component models

Instead of using engineering datafor designing and virtual commissioning only…

… using it continuously throughout the entire plant lifecycle for verification,

optimization and maintenance

ENTOC - Formalized requirements engineering

Page 7: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

ENTOC - Formalized requirements engineering

Page 8: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

From ambiguous natural language requirements and manual test generation …

… to formalized requirement documentation and automated test

generation

From component vendor and domain specific formats and delivery methods…

… to standardized mechatronic component models and

distribution systems

From building company specific component simulation models …

… to simulation based on standardized mechatronic

component models

Instead of using engineering datafor designing and virtual commissioning only…

… using it continuously throughout the entire plant lifecycle for verification,

optimization and maintenance

ENTOC - Creation and distribution of component models

Page 9: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

ENTOC - Creation and distribution of component models

Page 10: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

From ambiguous natural language requirements and manual test generation …

… to formalized requirement documentation and automated test

generation

From component vendor and domain specific formats and delivery methods…

… to standardized mechatronic component models and

distribution systems

From building company specific component simulation models …

… to simulation based on standardized mechatronic

component models

Instead of using engineering datafor designing and virtual commissioning only…

… using it continuously throughout the entire plant lifecycle for verification,

optimization and maintenance

ENTOC - Efficient processing of standard based mechatronic component models

Page 11: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

ENTOC - Efficient processing of standard based mechatronic component models

Page 12: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

From ambiguous natural language requirements and manual test generation …

… to formalized requirement documentation and automated test

generation

From component vendor and domain specific formats and delivery methods…

… to standardized mechatronic component models and

distribution systems

From building company specific component simulation models …

… to simulation based on standardized mechatronic

component models

Instead of using engineering datafor designing and virtual commissioning only…

… using it continuously throughout the entire plant lifecycle for verification,

optimization and maintenance

ENTOC - Optimization of models and Engineering Tool Chain

Page 13: Atieh Hanna, Volvo Group Trucks Operations€¦ · Atieh Hanna, Volvo Group Trucks Operations. ENTOC Consortium 2. ... Test Report for Control Logic. Commissioning. Station ready

ENTOC - Optimization of models and Engineering Tool Chain